WO2024074130A1 - Construction method for prefabricated hollow internally-rammed carrier pile - Google Patents

Construction method for prefabricated hollow internally-rammed carrier pile Download PDF

Info

Publication number
WO2024074130A1
WO2024074130A1 PCT/CN2023/123165 CN2023123165W WO2024074130A1 WO 2024074130 A1 WO2024074130 A1 WO 2024074130A1 CN 2023123165 W CN2023123165 W CN 2023123165W WO 2024074130 A1 WO2024074130 A1 WO 2024074130A1
Authority
WO
WIPO (PCT)
Prior art keywords
pile
slender
hollow pile
prefabricated hollow
piles
Prior art date
Application number
PCT/CN2023/123165
Other languages
French (fr)
Chinese (zh)
Inventor
王继忠
张力霆
张连喜
徐彤
张少雄
王光亮
杨启安
李湘明
Original Assignee
北京波森特岩土工程有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 北京波森特岩土工程有限公司 filed Critical 北京波森特岩土工程有限公司
Publication of WO2024074130A1 publication Critical patent/WO2024074130A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds

Definitions

  • the present application relates to the technical field of civil engineering foundation piles, and in particular to a construction method of prefabricated hollow internally rammed carrier piles.
  • precast piles are a type of pile often used in foundation treatment.
  • prestressed pipe piles are the most extensive, most mature and least expensive construction method in the field of precast piles, and they play a vital role in infrastructure construction.
  • a Chinese patent with publication number CN100375820C discloses a construction method of concrete piles. Specifically, it fills the bottom end of the pile pipe with bulk filler through the middle hole of the prestressed pipe pile, and then compacts the bulk filler with a rammer to compact and reinforce the foundation soil within a certain depth and range below the pile end until the optimal compacted soil that meets the required requirements is formed.
  • groundwater also drives the middle hole of the above-mentioned existing concrete piles to enter water during construction, making it impossible to continue to fill and tamp the piles, forming waste piles. This is not only a serious waste, but also seriously restricts the progress of the project and causes quality problems.
  • the present application provides a construction method for prefabricated hollow internal rammed carrier piles, which can meet the needs of high bearing capacity, can be applied to pipe piles in various geological soil layers, and has low cost.
  • a construction method for prefabricated hollow internal rammed carrier piles comprising the following construction steps:
  • Step S1 installing a bottom sealing steel plate at the lower end of the hollow pile body to perform bottom sealing treatment on the hollow pile body, the bottom sealing steel plate and the inner wall of the hollow pile body form a sealed isolation cavity, the upper side of the bottom sealing steel plate is also installed with a waterproof rubber pad that fits and seals the lower end of the hollow pile body, and the bottom sealed hollow pile body is placed in the area of the project site selection;
  • Step S2 slowly slide a slender weight along the pile mouth at the upper end of the hollow pile body into the inner cavity of the sealed isolation chamber, and leave fillers and air flow channels between the slender weight and the side wall of the sealed isolation chamber, feed a small amount of cement sand mixture into the sealed isolation chamber along the fillers and the air flow channels, and simultaneously use a steel wire rope to lift the slender weight, tamp the cement sand mixture with a relatively low tamping energy, drive the cement sand mixture downward to squeeze the bottom steel plate, and judge whether the bottom steel plate has been opened by observing the height of the position marked by the steel wire rope;
  • Step S3 repeating step S2 multiple times, and ensuring that the slender heavy hammer is continuously controlled with a relatively low tamping energy so as not to hit the bottom of the hollow pile body, until the forming height of the formed dense cement sand mixture or the filling amount of the cement sand mixture reaches a preset value;
  • Step S4 when the cement-sand mixture reaches a preset height in the sealed isolation chamber or the cement-sand mixture filling amount reaches a preset value, continue to fill the cement-sand mixture through the channel, appropriately increase the tamping energy, drive the cement-sand mixture and the soil within a certain depth and range under the pile end to be reinforced and compacted, and form a pile end carrier;
  • Step S5 after step S4, stop filling the cement-sand mixture, tamp the pile end carrier by dropping a slender heavy hammer three times in succession, measure the penetration of the three blows, stop tamping when the penetration measurement value meets the design value, and continue filling the cement-sand mixture and tamping operations in step S4 when the penetration measurement value does not meet the design value, until the penetration measurement value meets the design value.
  • step S1 when construction is carried out in a geological type with a low groundwater content at the construction site, in the above step S1, a waterproof rubber pad is installed on the upper side of the bottom steel plate, and in step S2, after the filler and the air flow channel are left between the slender weight and the side wall of the sealed isolation cavity, the slender weight is lifted to a certain height and then directly dropped to tamp the bottom steel plate, so as to knock the bottom steel plate away from the bottom end of the prefabricated hollow pile;
  • step S3 to step S5 a method of not considering low-energy tamping and a method of not considering whether the slender heavy hammer hits out of the bottom of the hollow pile body can be used for construction.
  • the method further comprises step S6, wherein a certain amount of bentonite or clay is wrapped with linen or cotton sack and placed into the hollow pile body through the upper opening of the hollow pile body;
  • the step S6 is located between step S1 and step S2. In addition, when water enters the hollow pile body during step S3 or step S4, this step can also be used to remove water and stop water.
  • the method further comprises the following steps:
  • Step S7 after step S5, continue to fill the cement sand mixture or concrete into the sealed isolation cavity, and use a slender heavy hammer to tamp it to form a dense body of a certain height in the sealed isolation cavity.
  • the method further comprises the following steps:
  • Step S8 pouring a certain amount of concrete into the center hole of the hollow pile body, or placing a steel cage in the center hole of the hollow pile body and then pouring a certain amount of concrete, after completion, processing the pile head of the hollow pile body to increase the pile body load.
  • the area of the bottom steel plate and the waterproof rubber pad is larger than the area of the central channel of the hollow pile body, and the bottom steel plate is fixed to the flange at the bottom end of the hollow pile body by bolts or welding.
  • the strength of the bolt or welding fixation is appropriately reduced to facilitate driving the bottom steel plate away from the bottom end of the hollow pile body in subsequent processes.
  • the size of the filler and the air flow channel in step S2 is 2 cm to 4 cm;
  • step S5 a certain amount of cement sand mixture is continuously added with a content greater than 0.1 m 3 .
  • step S2 to step S4 the amount of cement sand mixture or concrete filled in each time does not exceed 0.05 m 3 , and the number of tamping after each filling does not exceed 5 times.
  • the penetration refers to the sinking value of the slender hammer after it freely falls from the same height to hit the bottom filler, that is, the penetration of each tamping, and the penetration of the latter time is not greater than the penetration of the previous time;
  • the impact energy of the slender hammer should be close to 2100kN/ m2 (unit area).
  • the impact energy calculation formula is: the weight of the hammer multiplied by the drop distance divided by the bottom area of the hammer.
  • the buoyancy value of the hollow pile body is synchronously observed.
  • the prefabricated pipe pile is re-driven or re-pressed.
  • Re-driving or re-pressing means that the prefabricated hollow pile is sunk by hammering or static pressure.
  • the sinking value does not exceed the buoyancy value of the prefabricated hollow pile. If the prefabricated hollow pile does not float or the buoyancy is very small, there is no need to re-drive or re-press.
  • the present application includes at least one of the following beneficial technical effects:
  • Hollow piles are commonly used conventional pile types with mature construction technology. The advantages are simple process, fast speed, and no fear of groundwater, etc. However, since its bearing capacity mainly comes from The friction force on the pile side and the resistance value at the pile end are small, so the overall bearing capacity of the pile is limited and the quality is unstable. Based on the prefabricated hollow pile, this application cleverly uses the center hole of the prefabricated hollow pile to make the pile end carrier through reasonable and efficient technical means.
  • the prefabricated hollow pile is equivalent to a casing, which not only greatly improves the bearing capacity of ordinary prefabricated hollow piles, but also solves the difficulties of drilling and blocking groundwater during the construction of ordinary carrier piles, and avoids the common problems of pile body shrinkage in soft soil layers or soil layers rich in groundwater, achieving twice the result with half the effort.
  • the pile end carrier is composed of rammed cement sand mixture, compacted soil and impact soil.
  • the strength and modulus gradually decrease from the inside to the outside.
  • the pressure diffuses step by step during the load transfer process, which is equivalent to a multi-level extended foundation.
  • the bearing capacity of the pile end foundation soil is fully utilized, so that the stress borne by the pile body can be diffused, reduced and reduced layer by layer, thereby significantly improving the bearing capacity of the pile. Its ultimate bearing capacity can generally be increased by more than 2 times compared with conventional prefabricated hollow piles. The better the soil properties of the pile end bearing layer, the greater the increased bearing capacity of the pile end carrier and the higher the characteristic value of the single pile bearing capacity.
  • the pile end carrier provides a high bearing capacity and the pile end carrier can be set in the shallow soil layer in the foundation, the length and diameter of the prefabricated hollow pile can be effectively shortened under the condition of providing the same bearing capacity, so that the overall cost of the foundation project can be reduced by more than 30%. At the same time, it is more suitable for buildings or structures with larger upper loads.
  • waterproof technical measures such as the bottom sealing of the pile body, the provision of waterproof rubber pads, the slender heavy hammer never hitting the bottom of the prefabricated hollow pile, the use of cement sand filler to seal the central channel of the prefabricated hollow pile, and the gradual increase of the tamping energy of the slender heavy hammer after the cement sand mixture filled in reaches a certain amount, etc.
  • waterproof technical measures can ensure the engineering quality of the pile foundation and the pile completion rate of the construction.
  • FIG1 is a construction process diagram of embodiment 1 a-f of the present application.
  • FIG2 is a construction process diagram of Example 1 g-i of the present application.
  • FIG3 is a construction process diagram of a-f of Example 2 of the present application.
  • FIG4 is a construction process diagram of g-h of Example 2 of the present application.
  • 1 hollow pile body
  • 2 bottom steel plate
  • 3 sealed isolation cavity
  • 4 waterproof rubber pad
  • 5 slender weight
  • 6 filler and air flow channel
  • 7 cement sand mixture
  • 8 pile end carrier
  • 11 dense body
  • 12 steel cage
  • 13 flange
  • 14 concrete
  • 15 compacted soil
  • 16 affected soil.
  • the embodiment of the present application discloses a construction method of a prefabricated hollow internal ramming carrier pile, which is mainly used in the engineering pile foundation construction of the related technology, and overcomes the technical defects of the engineering foundation piles in the related technology that the construction is difficult and the construction quality is low in areas with high groundwater levels, and has the effects of convenient construction, good molding quality, and high bearing weight.
  • Embodiment 1 is a diagrammatic representation of Embodiment 1:
  • a construction method of a prefabricated hollow internal ramming carrier pile is disclosed, which is mainly used in areas with a high groundwater level; specifically, in the actual construction process, first, in order to prevent the groundwater from affecting the construction of the hollow pile body 1, a bottom sealing steel plate 2 is installed at the lower end of the hollow pile body 1 to perform bottom sealing treatment on the hollow pile body 1, and the bottom sealing steel plate 2 and the inner wall of the hollow pile body 1 form a sealed isolation cavity 3;
  • the hollow pile body 1 is an existing prestressed pipe pile, a prefabricated hollow bamboo pile, a prefabricated hollow square pile, etc.
  • the bottom sealing steel plate 2 is fixed to the flange 13 at the bottom end of the hollow pile body 1 by bolts or spot welding, and the strength of the bolts or welding fixation is appropriately reduced to facilitate the bottom sealing steel plate 2 to be driven away from the bottom end of the hollow pile body 1 in the subsequent process.
  • a waterproof rubber pad 4 is installed on the upper side of the bottom sealing steel plate 2 to fit and seal with the lower end of the hollow pile body 1.
  • the area of the bottom sealing steel plate 2 and the waterproof rubber pad 4 is larger than the area of the central channel of the hollow pile body 1. The waterproof rubber pad 4 is used to further waterproof and improve the actual sealing effect.
  • the bottom sealed prefabricated hollow pile body 1 is sunk into the soil to a set depth by one of the methods such as hammering, vibration, and static pressure, so as to complete the installation of the hollow pile body 1 in the area with a high groundwater content.
  • the slender weight 5 is lifted by a steel wire rope and slowly slid into the inner cavity of the sealed isolation chamber 3 along the pile mouth at the upper end of the hollow pile body 1, and a filler and an air flow channel 6 are left between the slender weight 5 and the side wall of the sealed isolation chamber 3, and a small amount of cement sand mixture 7 is fed into the sealed isolation chamber 3 along the filler and the air flow channel 6.
  • the size of the filler and the air flow channel 6 is 2 cm to 4 cm, and the height of the position of the slender weight 5 to the bottom steel plate 2 is marked on the steel wire rope for suspending the slender weight 5.
  • the slender heavy hammer 5 is lifted to tamp the cement-sand mixture 7 with a drop distance not exceeding 2 m, driving the cement-sand mixture 7 to squeeze the bottom steel plate 2 downward.
  • the slender heavy hammer 5 is lifted to tamp the cement-sand mixture 7 with a drop distance not exceeding 2 m, driving the cement-sand mixture 7 to squeeze the bottom steel plate 2 downward.
  • the slender heavy hammer 5 may not be knocked out from the lower end of the hollow pile body 1 during the tamping process, or it may be knocked out from the lower end of the hollow pile body 1, depending on the actual situation.
  • the amount of cement sand mixture 7 filled in each time does not exceed 0.05m3 , and the number of tamping times after each filling does not exceed 5 times.
  • the impact energy of the slender weight 5 should be close to 2100kN/m 2 (unit area), and the impact energy calculation formula is: the weight of the hammer multiplied by the drop distance divided by the bottom area of the hammer.
  • a small amount of cement-sand mixture 7 is then filled into the central channel of the hollow pile body 1, and a slender heavy hammer 5 is used to tamp with a relatively low tamping energy to form a dense body 11 of cement-sand mixture 7 with a height of 2m in the central channel.
  • a steel cage 12 is sunk into the central hole of the hollow pile body 1, and then concrete 14 is poured to the top of the precast hollow pile, or concrete 14 is directly poured to the top. After completion, the pile head of the hollow pile body 1 is processed to increase the pile body load.
  • the buoyancy value of the hollow pile body 1 is observed synchronously during the above-mentioned construction steps.
  • the prefabricated pipe pile is re-driven or re-pressed.
  • Re-driving or re-pressing means that the prefabricated hollow pile is sunk by hammering or static pressure.
  • the sinking value does not exceed the buoyancy value of the prefabricated hollow pile. If the prefabricated hollow pile does not float or the floating amount is very small, there is no need to re-drive or re-press.
  • Embodiment 2 is a diagrammatic representation of Embodiment 1:
  • this embodiment discloses the construction and installation of the foundation in an area with less groundwater content, as follows:
  • the bottom of the hollow pile body 1 is also installed with a bottom sealing steel plate 2 by welding or bolting, etc., as in Example 1, but there is no need to additionally install a waterproof rubber pad 4, and after the hollow pile body 1 passing through the bottom sealing is placed under the soil, a slender weight 5 is placed and a filler and an air flow channel 6 are left. After the slender weight 5 is lifted to a certain height, it is directly dropped to tamp the bottom sealing steel plate 2, so as to knock the bottom sealing steel plate 2 away from the bottom end of the prefabricated hollow pile.
  • the construction can be carried out without considering the low-energy tamping method, or without considering whether the slender heavy hammer 5 hits out of the bottom of the hollow pile body 1, so as to complete the construction quickly.
  • a steel cage 12 is sunk into the central hole of the hollow pile body 1, and then concrete 14 is poured to the top of the prefabricated hollow pile, or concrete 14 is directly poured to the top. After completion, the pile head of the hollow pile body 1 is processed to increase the pile body load.
  • a certain amount of bentonite or clay can be wrapped with linen or cotton sack 1, and then put into the hollow pile body 1 through the upper end opening of the hollow pile body 1, and then the extruded material after the bentonite is wrapped with linen is squeezed by a slender heavy hammer 5, so that the water inside the hollow pile body 1 is squeezed out, and Linen and bentonite also have a certain water absorption effect, thereby improving the actual water removal and water stopping effect.
  • this step can also be used to remove water and stop water, thereby improving the qualification rate of actual construction piles and reducing the generation of waste piles.
  • pile foundation construction operations can be performed when there is more groundwater, less groundwater, or when water overflows from the pile body or during the construction process, without being affected by groundwater.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present application relates to the technical field of civil engineering foundation piles, in particular to a construction method for a prefabricated hollow internally-rammed carrier pile, the method comprising the following steps: mounting a bottom sealing steel plate at a lower end of a hollow pile body to seal the bottom of the hollow pile body; and slowly humping a slender heavy hammer into an inner cavity of a sealed isolation cavity through a pile opening at an upper end of the hollow pile body, wherein a filler and airflow channel is provided between the slender heavy hammer and a side wall of the sealed isolation cavity, such that cement sand mixture is tamped with low tamping energy, and whether the bottom sealing steel plate is opened or not is determined. When the cement sand mixture reaches a preset height in the sealed isolation cavity or the filled amount of the cement sand mixture reaches a preset value, the cement sand mixture is continuously filled through the channel, the tamping energy is properly increased, the cement sand mixture and the soil body below the pile end within a certain depth and range are driven to be reinforced and compacted to form a pile end carrier. According to the present application, the influences of underground water on engineering foundation pile construction can be overcome, and the yield in an actual foundation pile construction process is improved.

Description

一种预制空心内夯载体桩的施工方法A construction method for prefabricated hollow internal rammed carrier piles
相关申请的交叉引用CROSS-REFERENCE TO RELATED APPLICATIONS
本申请主张在2022年10月08日在中国提交的中国专利申请No.202211229263.0的优先权,其全部内容通过引用包含于此。This application claims priority to Chinese Patent Application No. 202211229263.0 filed in China on October 8, 2022, the entire contents of which are incorporated herein by reference.
技术领域Technical Field
本申请涉及土建基桩的技术领域,特别是涉及一种预制空心内夯载体桩的施工方法。The present application relates to the technical field of civil engineering foundation piles, and in particular to a construction method of prefabricated hollow internally rammed carrier piles.
背景技术Background technique
随着基础建设的快速发展、基础基建的广泛展开,建筑施工技术、建筑工程的施工要求也在同步的大幅度提高,特别是大型施工工程如超级体量的桥梁、建筑等在近些年被建设出来。从另一方面,也促使施工技术在基建建设、超高难度的建筑施工生产方面大幅度进步。With the rapid development of infrastructure and the widespread deployment of basic infrastructure, the construction technology and construction requirements of construction projects have also been greatly improved, especially large-scale construction projects such as super-large bridges and buildings have been built in recent years. On the other hand, it has also prompted construction technology to make great progress in infrastructure construction and super-difficult construction production.
而在施工工程建设施工过程中,建筑工程地基的基础建设,往往是最基础也是最至关重要的一步;在现阶段的建筑工程地基基础处理领域中,预制桩是地基处理中经常采用的一种桩型。就现阶段而言,预应力管桩是预制桩领域最为广泛、施工技术最成熟以及施工成本较低的一种施工方式,其在基础建设中占有举足轻重的作用。In the process of construction engineering, the foundation construction of the construction engineering is often the most basic and most crucial step; in the current field of construction engineering foundation treatment, precast piles are a type of pile often used in foundation treatment. At this stage, prestressed pipe piles are the most extensive, most mature and least expensive construction method in the field of precast piles, and they play a vital role in infrastructure construction.
然而,在施工基建建设的体量和重量越来越大、施工环境越来越复杂的前提下,原有的预应力管桩也逐步的暴露了其自身不可避免的缺陷。在经过大量实验实践总结之后发现,预应力管桩在承受大重量的承载基体时,其桩身本体已受损。而预应力管桩采用的是柴油锤锤击法进行大压力安装,桩身应力波传递过程中产生的拉应力常常将桩身混凝土拉裂,而遇到硬塑粘土、夹层粉土、粉砂及卵石土层时,预应力管桩本身就入桩难度就大,再加以须达到预定的入桩进量,就势必要通过加大桩机配重或者加大锤重,以驱使预应力基桩入桩量达到施工要求。当采用的压力和动能的能量超出桩身能够承受的强度时,会造成桩头的破碎和桩身产生裂纹,这种受损的预制桩在有地下水或腐蚀矿物质的情况下,必将造成预应力筋的锈蚀和混凝土的强度受损,给施工建设带来较大的隐患。除此之外,预制管桩的承载能力大部分来源于桩侧摩擦力,其桩端阻力值相对较低,在施工建筑体量、重量越来越大的施工背景之下,预应力基桩的基础承载力也会凸显出一定的承载风险。However, under the premise that the volume and weight of infrastructure construction are getting bigger and bigger and the construction environment is getting more and more complex, the original prestressed pipe piles have gradually exposed their inevitable defects. After a large number of experimental practices, it was found that the pile body of the prestressed pipe pile was damaged when it was subjected to a heavy load-bearing matrix. The prestressed pipe piles are installed under high pressure by the diesel hammer hammering method. The tensile stress generated during the transmission of the pile body stress wave often cracks the pile body concrete. When encountering hard plastic clay, interlayer silt, silt sand and pebble soil layers, the prestressed pipe pile itself is difficult to enter the pile. In addition, it is necessary to increase the pile driver counterweight or hammer weight to drive the prestressed foundation pile to reach the construction requirements. When the pressure and kinetic energy used exceed the strength that the pile body can withstand, it will cause the pile head to break and the pile body to crack. In the presence of groundwater or corrosive minerals, such damaged prefabricated piles will inevitably cause the corrosion of the prestressed tendons and the strength of the concrete to be damaged, which will bring great hidden dangers to construction. In addition, the bearing capacity of precast pipe piles is mostly derived from the friction on the pile side, and the pile end resistance value is relatively low. Under the construction background of increasing volume and weight of construction buildings, the foundation bearing capacity of prestressed piles will also highlight certain bearing risks.
基于此,在相关技术中的预应力管桩的基础上,为了克服上述预应力管桩凸显的技术缺陷,公开号为CN100375820C的中国专利,其公开了一种混凝土桩的施工方法,具体,其通过预应力管桩的中孔,向桩管底端填入散体填充料后通过夯锤对散体填充料进行夯实,对桩端下方的一定深度和范围的地基土体进行密实加固,直至形成满足所需要求的最优的挤密土体。Based on this, on the basis of the prestressed pipe piles in the relevant technology, in order to overcome the technical defects highlighted by the above-mentioned prestressed pipe piles, a Chinese patent with publication number CN100375820C discloses a construction method of concrete piles. Specifically, it fills the bottom end of the pile pipe with bulk filler through the middle hole of the prestressed pipe pile, and then compacts the bulk filler with a rammer to compact and reinforce the foundation soil within a certain depth and range below the pile end until the optimal compacted soil that meets the required requirements is formed.
但是在上述混凝土桩施工的基础之上,依然存在相应的技术缺陷: However, based on the above concrete pile construction, there are still corresponding technical defects:
(1)、预制管桩生产技术相对落后,所出厂的管桩中孔内壁不规则、不圆滑,残留混凝土较多,夯锤夯击过程中极易出现,很难实现夯锤的夯击动作;(1) The production technology of prefabricated pipe piles is relatively backward. The inner wall of the hole in the pipe piles shipped from the factory is irregular and not smooth, and there is a lot of residual concrete. It is very easy to cause problems during the tamping process, and it is difficult to achieve the tamping action of the tamping hammer;
(2)、采用如碎砖烂瓦、干硬性混凝土等散体填充料,而预制管桩的中孔又比较细小,因此必须将夯锤完全提出预制管桩的上口后方能填料,施工工效低;(2) Using bulk filling materials such as broken bricks and tiles, dry and hard concrete, and the central hole of the precast pipe pile is relatively small, so the rammer must be completely lifted out of the upper mouth of the precast pipe pile before filling, which leads to low construction efficiency;
(3)、散体填充料极易堵塞预制管桩的中孔(特别是中孔底部),在测量完贯入度后还要再填入一定量的干硬性混凝土,因此经常将预制管桩底端打裂、打爆,造成废桩;(3) Bulk fillers are very likely to clog the middle hole (especially the bottom of the middle hole) of the precast pipe pile. After measuring the penetration, a certain amount of dry hard concrete must be added. As a result, the bottom of the precast pipe pile is often cracked or exploded, resulting in waste piles.
最后还有的是,在相关领域中,基建建设的大幅度扩展、如沿海地区、山区等地区,其地下水的含量较为丰富,土质较软,一方面预应力管桩难以得到最佳的应力耐受度,其次,地下水也给上述现有的混凝土桩的施工时驱使管桩的中孔内进水后无法继续填料夯击,形成废桩,不仅浪费严重,还严重制约工程进度、造成质量问题。Finally, in related fields, infrastructure construction has expanded substantially, such as in coastal areas, mountainous areas, etc., where the groundwater content is relatively rich and the soil is relatively soft. On the one hand, it is difficult for prestressed pipe piles to obtain the best stress tolerance. Secondly, groundwater also drives the middle hole of the above-mentioned existing concrete piles to enter water during construction, making it impossible to continue to fill and tamp the piles, forming waste piles. This is not only a serious waste, but also seriously restricts the progress of the project and causes quality problems.
综上,在相关技术中的管桩施工前提之下,为满足高承载力需要和适用于各种地质土层、以及成本控制,相关技术中的管桩以及管桩的施工工艺还有改进的空间。In summary, under the premise of pipe pile construction in the relevant technology, in order to meet the needs of high bearing capacity and be applicable to various geological soil layers, as well as cost control, there is still room for improvement in the pipe piles and the construction technology of the pipe piles in the relevant technology.
发明内容Summary of the invention
本申请提供一种预制空心内夯载体桩的施工方法,能够满足高承载力需要,能够适用于各种地质土层的管桩,成本较低。The present application provides a construction method for prefabricated hollow internal rammed carrier piles, which can meet the needs of high bearing capacity, can be applied to pipe piles in various geological soil layers, and has low cost.
一种预制空心内夯载体桩的施工方法,包括以下施工步骤:A construction method for prefabricated hollow internal rammed carrier piles, comprising the following construction steps:
步骤S1,在空心桩体下端安装封底钢板以对空心桩体进行封底处理,封底钢板与空心桩体内侧壁形成密封隔绝腔,所述封底钢板上侧还安装有和空心桩体下端贴合密封的防水胶垫,并将经封底的空心桩体置入工程选址地的区域;Step S1, installing a bottom sealing steel plate at the lower end of the hollow pile body to perform bottom sealing treatment on the hollow pile body, the bottom sealing steel plate and the inner wall of the hollow pile body form a sealed isolation cavity, the upper side of the bottom sealing steel plate is also installed with a waterproof rubber pad that fits and seals the lower end of the hollow pile body, and the bottom sealed hollow pile body is placed in the area of the project site selection;
步骤S2,将细长重锤沿空心桩体上端桩口处缓慢溜放至密封隔绝腔内腔中,且所述细长重锤与密封隔绝腔侧壁留有填料与气流通道,沿填料与气流通道向密封隔绝腔中送入少量的水泥砂拌合物,同步利用钢丝绳提升细长重锤,以较低夯击能量对水泥砂拌合物进行夯击,驱使水泥砂拌合物向下挤压封底钢板,通过观察上述钢丝绳标记位置高度,判断是否已打开封底钢板;Step S2, slowly slide a slender weight along the pile mouth at the upper end of the hollow pile body into the inner cavity of the sealed isolation chamber, and leave fillers and air flow channels between the slender weight and the side wall of the sealed isolation chamber, feed a small amount of cement sand mixture into the sealed isolation chamber along the fillers and the air flow channels, and simultaneously use a steel wire rope to lift the slender weight, tamp the cement sand mixture with a relatively low tamping energy, drive the cement sand mixture downward to squeeze the bottom steel plate, and judge whether the bottom steel plate has been opened by observing the height of the position marked by the steel wire rope;
步骤S3,重复多次步骤S2,并保证持续的以较低夯击能量控制细长重锤始终不击出空心桩体最底部,直至形成的密实水泥砂拌合物的成型高度或者水泥砂拌合物的填入量达到预设值;Step S3, repeating step S2 multiple times, and ensuring that the slender heavy hammer is continuously controlled with a relatively low tamping energy so as not to hit the bottom of the hollow pile body, until the forming height of the formed dense cement sand mixture or the filling amount of the cement sand mixture reaches a preset value;
步骤S4,当水泥砂拌合物在密封隔绝腔中达到预设高度或者水泥砂拌合物填入量达到预设值之后,继续利用通道填入水泥砂拌合物,适度加大夯击能量,驱使水泥砂拌合物和桩端下一定深度和范围内的土体被加固密实,形成桩端载体;Step S4, when the cement-sand mixture reaches a preset height in the sealed isolation chamber or the cement-sand mixture filling amount reaches a preset value, continue to fill the cement-sand mixture through the channel, appropriately increase the tamping energy, drive the cement-sand mixture and the soil within a certain depth and range under the pile end to be reinforced and compacted, and form a pile end carrier;
步骤S5,在经过步骤S4之后,停止填入水泥砂拌合物,通过细长重锤连续三次下落对桩端载体进行夯击,测量三次击打的贯入度,贯入度测量值满足设计值时停止夯击,贯入度测量值不满足设计值时,继续进行步骤S4的填入水泥砂拌合物和夯击操作,直至贯入度测量值满足设计值。 Step S5, after step S4, stop filling the cement-sand mixture, tamp the pile end carrier by dropping a slender heavy hammer three times in succession, measure the penetration of the three blows, stop tamping when the penetration measurement value meets the design value, and continue filling the cement-sand mixture and tamping operations in step S4 when the penetration measurement value does not meet the design value, until the penetration measurement value meets the design value.
可选地,当在施工场地地下水含量较低的地质类型进行施工时,上述步骤S1中,于所述封底钢板上侧安装防水胶垫,且在步骤S2中,于所述细长重锤与密封隔绝腔侧壁留有填料与气流通道之后,提升细长重锤一定高度后直接下落夯击封底钢板,将封底钢板击离预制空心桩的底端;Optionally, when construction is carried out in a geological type with a low groundwater content at the construction site, in the above step S1, a waterproof rubber pad is installed on the upper side of the bottom steel plate, and in step S2, after the filler and the air flow channel are left between the slender weight and the side wall of the sealed isolation cavity, the slender weight is lifted to a certain height and then directly dropped to tamp the bottom steel plate, so as to knock the bottom steel plate away from the bottom end of the prefabricated hollow pile;
然后重复步骤S3-步骤S5,且在进行步骤S3-步骤S5的过程中,可以采用不考虑低能量夯击的方式,以及可以采用不考虑细长重锤是否击出空心桩体底部的方式进行施工的方式。Then repeat step S3 to step S5, and in the process of performing step S3 to step S5, a method of not considering low-energy tamping and a method of not considering whether the slender heavy hammer hits out of the bottom of the hollow pile body can be used for construction.
可选地,还包括步骤S6,通过麻布或者棉麻袋包覆以一定量的膨润土或者黏土,并通过空心桩体的上端开口投放至空心桩体中;Optionally, the method further comprises step S6, wherein a certain amount of bentonite or clay is wrapped with linen or cotton sack and placed into the hollow pile body through the upper opening of the hollow pile body;
所述步骤S6位于步骤S1与步骤S2之间,除此之外,在进行步骤S3或者步骤S4过程中发生空心桩体内进水的情况时,也可采用此步骤进行去水止水处理。The step S6 is located between step S1 and step S2. In addition, when water enters the hollow pile body during step S3 or step S4, this step can also be used to remove water and stop water.
可选地,还包括以下步骤:Optionally, the method further comprises the following steps:
步骤S7,在经过步骤S5之后,通过继续填入水泥砂拌合物或者填入混凝土至密封隔绝腔中,并利用细长重锤进行夯击以在密封隔绝腔中形成一定高度的密实体。Step S7, after step S5, continue to fill the cement sand mixture or concrete into the sealed isolation cavity, and use a slender heavy hammer to tamp it to form a dense body of a certain height in the sealed isolation cavity.
可选地,还包括以下步骤:Optionally, the method further comprises the following steps:
步骤S8,于空心桩体中心孔内灌注一定数量的混凝土,或者在空心桩体中心孔内放置钢筋笼之后再灌注一定数量的混凝土,完成之后对空心桩体桩头进行处理,以提高桩身载荷。Step S8, pouring a certain amount of concrete into the center hole of the hollow pile body, or placing a steel cage in the center hole of the hollow pile body and then pouring a certain amount of concrete, after completion, processing the pile head of the hollow pile body to increase the pile body load.
可选地,所述封底钢板和防水胶垫的面积大于空心桩体中心孔道的面积,封底钢板以螺栓或者焊接方式与空心桩体底端的法兰盘固定,螺栓或者焊接固定的强度适当降低,以利于后续工序中将封底钢板击离空心桩体的底端。Optionally, the area of the bottom steel plate and the waterproof rubber pad is larger than the area of the central channel of the hollow pile body, and the bottom steel plate is fixed to the flange at the bottom end of the hollow pile body by bolts or welding. The strength of the bolt or welding fixation is appropriately reduced to facilitate driving the bottom steel plate away from the bottom end of the hollow pile body in subsequent processes.
可选地,步骤S2中的填料与气流通道大小为2cm至4cm;Optionally, the size of the filler and the air flow channel in step S2 is 2 cm to 4 cm;
步骤S5中持续填入一定数量的水泥砂拌合物的含量大于0.1m3In step S5, a certain amount of cement sand mixture is continuously added with a content greater than 0.1 m 3 .
步骤S2-步骤S4中,每次填入的水泥砂拌合物或者混凝土的数量不超过0.05m3,并且每次填料后的夯击次数不超过5次。In step S2 to step S4, the amount of cement sand mixture or concrete filled in each time does not exceed 0.05 m 3 , and the number of tamping after each filling does not exceed 5 times.
可选地,在步骤S5中,贯入度是指细长重锤以相同的高度自由下落击打底端填料后的当次下沉数值,即为每一次夯击的贯入度,并且后一次的贯入度不大于前一次的贯入度;Optionally, in step S5, the penetration refers to the sinking value of the slender hammer after it freely falls from the same height to hit the bottom filler, that is, the penetration of each tamping, and the penetration of the latter time is not greater than the penetration of the previous time;
在测量细长重锤贯入度时,细长重锤的冲击能量应接近2100kN/m2(单位面积),冲击能量计算公式为:锤的重量乘以落距除以锤底面积。When measuring the penetration of a slender hammer, the impact energy of the slender hammer should be close to 2100kN/ m2 (unit area). The impact energy calculation formula is: the weight of the hammer multiplied by the drop distance divided by the bottom area of the hammer.
可选地,在进行步骤S2至S5时,同步观测空心桩体的上浮数值,当空心桩体上升时,对预制管桩进行复打或者复压,复打或者复压是指通过锤击或者静压的方式使预制空心桩下沉,下沉值不超过预制空心桩的上浮值,如预制空心桩没有上浮或者上浮量很小则无需复打或者复压。Optionally, when performing steps S2 to S5, the buoyancy value of the hollow pile body is synchronously observed. When the hollow pile body rises, the prefabricated pipe pile is re-driven or re-pressed. Re-driving or re-pressing means that the prefabricated hollow pile is sunk by hammering or static pressure. The sinking value does not exceed the buoyancy value of the prefabricated hollow pile. If the prefabricated hollow pile does not float or the buoyancy is very small, there is no need to re-drive or re-press.
综上所述,本申请包括以下至少一种有益技术效果:In summary, the present application includes at least one of the following beneficial technical effects:
1.充分结合空心桩体与桩端载体的各自优势:空心桩体是普遍使用的常规桩型,施工技术成熟,优势是工艺简单、速度快,不惧怕地下水等,但是由于其承载能力主要来源于 桩侧摩擦力,桩端阻力值较小,因此桩的整体承载能力受限并且质量不稳定。本申请在预制空心桩的基础上,通过合理高效的技术手段巧妙利用预制空心桩的中心孔制作桩端载体,这样预制空心桩就相当于护筒,不仅使普通预制空心桩的承载力大幅提升,同时解决了普通载体桩施工时成孔及封堵地下水等困难,避免了载体桩在较软土层或地下水丰富土层易出现桩身缩径等通病,起到事半功倍的效果。1. Fully combine the respective advantages of hollow piles and pile end carriers: Hollow piles are commonly used conventional pile types with mature construction technology. The advantages are simple process, fast speed, and no fear of groundwater, etc. However, since its bearing capacity mainly comes from The friction force on the pile side and the resistance value at the pile end are small, so the overall bearing capacity of the pile is limited and the quality is unstable. Based on the prefabricated hollow pile, this application cleverly uses the center hole of the prefabricated hollow pile to make the pile end carrier through reasonable and efficient technical means. In this way, the prefabricated hollow pile is equivalent to a casing, which not only greatly improves the bearing capacity of ordinary prefabricated hollow piles, but also solves the difficulties of drilling and blocking groundwater during the construction of ordinary carrier piles, and avoids the common problems of pile body shrinkage in soft soil layers or soil layers rich in groundwater, achieving twice the result with half the effort.
2.桩端载体是由夯击水泥砂拌合物、挤密土体和影响土体组成,从内到外强度和模量逐渐降低,受力时荷载在传递过程中压力逐级扩散,相当于多级的扩展基础,充分发挥桩端地基土体的承载力,使桩身承受的应力逐层扩散、消减和降低,从而显著提高桩的承载能力,其极限承载力一般可比常规预制空心桩提高2倍以上,桩端持力层的土性越好,桩端载体增加的承载能力越大,单桩承载力特征值越高。2. The pile end carrier is composed of rammed cement sand mixture, compacted soil and impact soil. The strength and modulus gradually decrease from the inside to the outside. When subjected to force, the pressure diffuses step by step during the load transfer process, which is equivalent to a multi-level extended foundation. The bearing capacity of the pile end foundation soil is fully utilized, so that the stress borne by the pile body can be diffused, reduced and reduced layer by layer, thereby significantly improving the bearing capacity of the pile. Its ultimate bearing capacity can generally be increased by more than 2 times compared with conventional prefabricated hollow piles. The better the soil properties of the pile end bearing layer, the greater the increased bearing capacity of the pile end carrier and the higher the characteristic value of the single pile bearing capacity.
3.因桩端载体提供的承载能力高,同时桩端载体可以设在地基中的浅部土层,在提供相同承载能力的条件下可有效缩短预制空心桩的长度和直径,使得基础工程的整体造价能够降低30%以上,同时更加适用于上部荷载较大的建筑物或者构筑物。3. Because the pile end carrier provides a high bearing capacity and the pile end carrier can be set in the shallow soil layer in the foundation, the length and diameter of the prefabricated hollow pile can be effectively shortened under the condition of providing the same bearing capacity, so that the overall cost of the foundation project can be reduced by more than 30%. At the same time, it is more suitable for buildings or structures with larger upper loads.
4.针对不同的地质条件特别是根据地基土体中含水量的多寡,设计了有针对性的施工工艺。地基土体中含水量的不同,直接影响施工的成败与效率,以及桩基的工程质量,在含水量较高的土层中尤其要注意。本申请由于要在预制空心桩的底端增加载体,所以更要防止水进入到中心孔道中,因此在整个技术方案中基本上每个步骤都有防水的技术措施,比如桩身封底、设防水胶垫、细长重锤始终不击出预制空心桩的底端、利用水泥砂填料封堵预制空心桩中心孔道、等到填入的水泥砂拌合物达到一定数量之后再逐渐加大细长重锤的夯击能量,等等。这些防水的技术措施能够确保桩基的工程质量和施工的成桩率。4. According to different geological conditions, especially according to the amount of water content in the foundation soil, targeted construction technology is designed. The different water content in the foundation soil directly affects the success and efficiency of the construction, as well as the engineering quality of the pile foundation, and it is especially important to pay attention to the soil layer with higher water content. Since the present application needs to add a carrier at the bottom of the prefabricated hollow pile, it is even more necessary to prevent water from entering the central channel. Therefore, in the entire technical solution, basically every step has waterproof technical measures, such as the bottom sealing of the pile body, the provision of waterproof rubber pads, the slender heavy hammer never hitting the bottom of the prefabricated hollow pile, the use of cement sand filler to seal the central channel of the prefabricated hollow pile, and the gradual increase of the tamping energy of the slender heavy hammer after the cement sand mixture filled in reaches a certain amount, etc. These waterproof technical measures can ensure the engineering quality of the pile foundation and the pile completion rate of the construction.
附图说明BRIEF DESCRIPTION OF THE DRAWINGS
图1是本申请实施例一a-f施工工序图;FIG1 is a construction process diagram of embodiment 1 a-f of the present application;
图2是本申请实施例一g-i施工工序图;FIG2 is a construction process diagram of Example 1 g-i of the present application;
图3是本申请实施例二a-f施工工序图;FIG3 is a construction process diagram of a-f of Example 2 of the present application;
图4是本申请实施例二g-h施工工序图;FIG4 is a construction process diagram of g-h of Example 2 of the present application;
附图标记说明:1:空心桩体;2:封底钢板;3:密封隔绝腔;4:防水胶垫;5:细长重锤;6:填料与气流通道;7:水泥砂拌合物;8:桩端载体;11:密实体;12:钢筋笼;13:法兰盘;14:混凝土;15:被挤密的土体;16:影响土体。Explanation of the reference numerals: 1: hollow pile body; 2: bottom steel plate; 3: sealed isolation cavity; 4: waterproof rubber pad; 5: slender weight; 6: filler and air flow channel; 7: cement sand mixture; 8: pile end carrier; 11: dense body; 12: steel cage; 13: flange; 14: concrete; 15: compacted soil; 16: affected soil.
具体实施方式Detailed ways
以下结合附图1-4对本申请作进一步详细说明。The present application is further described in detail below in conjunction with Figures 1-4.
本申请实施例公开一种预制空心内夯载体桩的施工方法,其主要应用于相关技术的工程桩基施工中,并且克服了相关技术中工程基桩在地下水位较多的地区施工难度大、施工质量低的技术缺陷,具有方便施工、成型质量好、承载重量高等的效果。 The embodiment of the present application discloses a construction method of a prefabricated hollow internal ramming carrier pile, which is mainly used in the engineering pile foundation construction of the related technology, and overcomes the technical defects of the engineering foundation piles in the related technology that the construction is difficult and the construction quality is low in areas with high groundwater levels, and has the effects of convenient construction, good molding quality, and high bearing weight.
实施例一:Embodiment 1:
本实施例中,参阅图1中a所示,公开了一种预制空心内夯载体桩的施工方法,其主要使用在地下水位较多的地区;具体在实际施工的过程中,首先,为了防止地下水对空心桩体1的施工带来影响,在空心桩体1下端安装封底钢板2以对空心桩体1进行封底处理,封底钢板2与空心桩体1内侧壁形成密封隔绝腔3;需要说明的是,空心桩体1为现有的预应力管桩、预制空心竹节桩、预制空心方桩等,且封底钢板2以螺栓或者焊接点焊方式与空心桩体1底端的法兰盘13固定,螺栓或者焊接固定的强度适当降低,以利于后续工序中将封底钢板2击离空心桩体1的底端。In this embodiment, referring to FIG. 1 a, a construction method of a prefabricated hollow internal ramming carrier pile is disclosed, which is mainly used in areas with a high groundwater level; specifically, in the actual construction process, first, in order to prevent the groundwater from affecting the construction of the hollow pile body 1, a bottom sealing steel plate 2 is installed at the lower end of the hollow pile body 1 to perform bottom sealing treatment on the hollow pile body 1, and the bottom sealing steel plate 2 and the inner wall of the hollow pile body 1 form a sealed isolation cavity 3; it should be noted that the hollow pile body 1 is an existing prestressed pipe pile, a prefabricated hollow bamboo pile, a prefabricated hollow square pile, etc., and the bottom sealing steel plate 2 is fixed to the flange 13 at the bottom end of the hollow pile body 1 by bolts or spot welding, and the strength of the bolts or welding fixation is appropriately reduced to facilitate the bottom sealing steel plate 2 to be driven away from the bottom end of the hollow pile body 1 in the subsequent process.
通过分封底钢板2的设置,能够保证空心桩体1在下沉至土体中时,位于土体中的地下水不会对空心桩体1带来影响。除此之外,为进一步提高实际防水效果,封底钢板2上侧还安装有和空心桩体1下端贴合密封的防水胶垫4,封底钢板2和防水胶垫4的面积大于空心桩体1中心孔道的面积,利用防水胶垫4进一步防水以提高实际的密封效果。By setting the bottom sealing steel plate 2, it can be ensured that when the hollow pile body 1 sinks into the soil, the groundwater in the soil will not affect the hollow pile body 1. In addition, in order to further improve the actual waterproof effect, a waterproof rubber pad 4 is installed on the upper side of the bottom sealing steel plate 2 to fit and seal with the lower end of the hollow pile body 1. The area of the bottom sealing steel plate 2 and the waterproof rubber pad 4 is larger than the area of the central channel of the hollow pile body 1. The waterproof rubber pad 4 is used to further waterproof and improve the actual sealing effect.
参照图1中b所示,在对空心桩体1进行封底与密封操作之后,利用锤击、振动、静压的等方式之一将已封底的预制空心桩体1在土体中沉入至设定深度,以完成空心桩体1于地下水含量较多的地区进行安装。Referring to FIG. 1 b , after the bottom sealing and sealing operation is performed on the hollow pile body 1, the bottom sealed prefabricated hollow pile body 1 is sunk into the soil to a set depth by one of the methods such as hammering, vibration, and static pressure, so as to complete the installation of the hollow pile body 1 in the area with a high groundwater content.
参照图1中c和图1中d所示,当空心桩体1安装完成之后,利用钢丝绳提升细长重锤5将细长重锤5沿空心桩体1上端桩口处缓慢溜放至密封隔绝腔3内腔中,且细长重锤5与密封隔绝腔3侧壁留有填料与气流通道6,沿填料与气流通道6向密封隔绝腔3中送入少量的水泥砂拌合物7。本实施例中,填料与气流通道6大小为2cm至4cm,在悬吊细长重锤5的钢丝绳上标记细长重锤5至封底钢板2时的位置高度。Referring to FIG. 1 c and FIG. 1 d, after the installation of the hollow pile body 1 is completed, the slender weight 5 is lifted by a steel wire rope and slowly slid into the inner cavity of the sealed isolation chamber 3 along the pile mouth at the upper end of the hollow pile body 1, and a filler and an air flow channel 6 are left between the slender weight 5 and the side wall of the sealed isolation chamber 3, and a small amount of cement sand mixture 7 is fed into the sealed isolation chamber 3 along the filler and the air flow channel 6. In this embodiment, the size of the filler and the air flow channel 6 is 2 cm to 4 cm, and the height of the position of the slender weight 5 to the bottom steel plate 2 is marked on the steel wire rope for suspending the slender weight 5.
继续的,水泥砂拌合物从填料与气流通道6落入到防水胶垫4上之后,提升细长重锤5以不超过2m的落距对水泥砂拌合物7进行夯击,驱使水泥砂拌合物7向下挤压封底钢板2通过观察上述钢丝绳标记位置高度,判断是否已打开封底钢板2,如果未打开可适当增加夯击次数或者少幅增加锤的落距,直至打开封底钢板2。Continuing, after the cement-sand mixture falls from the filler and the air flow channel 6 onto the waterproof rubber pad 4, the slender heavy hammer 5 is lifted to tamp the cement-sand mixture 7 with a drop distance not exceeding 2 m, driving the cement-sand mixture 7 to squeeze the bottom steel plate 2 downward. By observing the height of the position marked with the above-mentioned wire rope, it is determined whether the bottom steel plate 2 has been opened. If not, the number of tamping times can be appropriately increased or the drop distance of the hammer can be slightly increased until the bottom steel plate 2 is opened.
参照图1中e所示,继续填入少量的水泥砂拌合物7并利用细长重锤5对水泥砂拌合物7进行夯击,在此过程中以较低夯击能量控制细长重锤5始终不击出中心孔道的底端,保证始终有水泥砂拌合物7对中心孔道予以封堵,防止空心桩体1中水的进入。Referring to e in Figure 1, continue to fill in a small amount of cement-sand mixture 7 and use the slender heavy hammer 5 to tamp the cement-sand mixture 7. During this process, the slender heavy hammer 5 is controlled with a lower tamping energy to never hit the bottom of the central channel, ensuring that the central channel is always blocked by the cement-sand mixture 7 to prevent water from entering the hollow pile body 1.
参照图1中f所示,当水泥砂拌合物7在密封隔绝腔3中达到预设高度或者水泥砂拌合物7填入量达到预设值之后,本实施例中填入的水泥砂拌合物7超过0.1m3之后,在空心桩体1的底端形成了一定挤密范围的防水层,适度加大夯击能量,驱使水泥砂拌合物和桩端下一定深度和范围内的土体被加固密实,形成桩端载体8。在形成桩端载体8的过程中,根据实际施工情况,为确保桩端载体8的保质形成,此时细长重锤5在夯击的过程中可能不会从空心桩体1下端击出,也可能将会击出空心桩体1下端,根据实际情况而定。并且,在形成桩端载体8过程中,每次填入的水泥砂拌合物7的数量不超过0.05m3,每次填料后的夯击次数不超过5次。 As shown in FIG. 1 f, when the cement sand mixture 7 reaches a preset height in the sealed isolation chamber 3 or the amount of cement sand mixture 7 filled reaches a preset value, after the cement sand mixture 7 filled in this embodiment exceeds 0.1m3 , a waterproof layer with a certain compaction range is formed at the bottom of the hollow pile body 1, and the tamping energy is appropriately increased to drive the cement sand mixture and the soil within a certain depth and range under the pile end to be reinforced and compacted to form a pile end carrier 8. In the process of forming the pile end carrier 8, according to the actual construction situation, in order to ensure the quality of the pile end carrier 8, the slender heavy hammer 5 may not be knocked out from the lower end of the hollow pile body 1 during the tamping process, or it may be knocked out from the lower end of the hollow pile body 1, depending on the actual situation. In addition, in the process of forming the pile end carrier 8, the amount of cement sand mixture 7 filled in each time does not exceed 0.05m3 , and the number of tamping times after each filling does not exceed 5 times.
参照图2中g所示,在不填料时,即停止填入水泥砂拌合物,通过细长重锤5连续三次下落对桩端载体8进行夯击,测量三次击打的贯入度,贯入度测量值满足设计值时停止夯击,贯入度测量值不满足设计值时,继续进行填入水泥砂拌合物7和夯击操作,直至贯入度测量值满足设计值。在空心桩体1的底端,自内向外形成由填入的水泥砂拌合物7、被挤密的、影响土体16组成的载体。于测量细长重锤5贯入度时,细长重锤5的冲击能量应接近2100kN/m2(单位面积),冲击能量计算公式为:锤的重量乘以落距除以锤底面积。Referring to g in FIG. 2 , when there is no filling material, that is, the cement sand mixture is stopped, and the pile end carrier 8 is rammed by dropping the slender weight 5 three times in a row, and the penetration of the three hits is measured. When the penetration measurement value meets the design value, the ramming is stopped. When the penetration measurement value does not meet the design value, the cement sand mixture 7 and the ramming operation are continued until the penetration measurement value meets the design value. At the bottom end of the hollow pile body 1, a carrier composed of the filled cement sand mixture 7 and the compacted, impact soil 16 is formed from the inside to the outside. When measuring the penetration of the slender weight 5, the impact energy of the slender weight 5 should be close to 2100kN/m 2 (unit area), and the impact energy calculation formula is: the weight of the hammer multiplied by the drop distance divided by the bottom area of the hammer.
参照图2中h所示,再继续在空心桩体1的中心孔道中填入少量水泥砂拌合物7,并利用细长重锤5以较低的夯击能量进行夯击,在中心孔道内形成2m高度的水泥砂拌合物7密实体11。2h, a small amount of cement-sand mixture 7 is then filled into the central channel of the hollow pile body 1, and a slender heavy hammer 5 is used to tamp with a relatively low tamping energy to form a dense body 11 of cement-sand mixture 7 with a height of 2m in the central channel.
最后的,参照图2中i所示,在空心桩体1的中心孔道中沉入钢筋笼12,再灌注混凝土14至预制空心桩顶端,或者直接灌注混凝土14至顶端,完成之后对空心桩体1桩头进行处理,以提高桩身载荷。Finally, as shown in Fig. 2 i, a steel cage 12 is sunk into the central hole of the hollow pile body 1, and then concrete 14 is poured to the top of the precast hollow pile, or concrete 14 is directly poured to the top. After completion, the pile head of the hollow pile body 1 is processed to increase the pile body load.
另外需要进行说明的有,在空心桩体1置入工程施工土地下之后,进行上述施工步骤的过程中,同步观测空心桩体1的上浮数值,当空心桩体1上升时,对预制管桩进行复打或者复压,复打或者复压是指通过锤击或者静压的方式使预制空心桩下沉,下沉值不超过预制空心桩的上浮值,如预制空心桩没有上浮或者上浮量很小则无需复打或者复压。In addition, it needs to be explained that after the hollow pile body 1 is placed underground in the construction site, the buoyancy value of the hollow pile body 1 is observed synchronously during the above-mentioned construction steps. When the hollow pile body 1 rises, the prefabricated pipe pile is re-driven or re-pressed. Re-driving or re-pressing means that the prefabricated hollow pile is sunk by hammering or static pressure. The sinking value does not exceed the buoyancy value of the prefabricated hollow pile. If the prefabricated hollow pile does not float or the floating amount is very small, there is no need to re-drive or re-press.
实施例二:Embodiment 2:
在实施例一的基础上,本实施例中公开了在地下水含量较少的地区中施行地基的施工安装,具体如下:Based on the first embodiment, this embodiment discloses the construction and installation of the foundation in an area with less groundwater content, as follows:
参照图3中的a、b、c、d、e、f,以及图4中的g和h所示,当地下水含量较低时,与实施例一相同的,空心桩体1底部同样通过焊接或者螺栓等方式安装封底钢板2进行封底操作,但是不需要额外安装防水胶垫4,并且,在将通过封底的空心桩体1置入土体下之后,置入细长重锤5并留有填料与气流通道6,提升细长重锤5一定高度后直接下落夯击封底钢板2,将封底钢板2击离预制空心桩的底端。Referring to a, b, c, d, e, f in Figure 3, and g and h in Figure 4, when the groundwater content is low, the bottom of the hollow pile body 1 is also installed with a bottom sealing steel plate 2 by welding or bolting, etc., as in Example 1, but there is no need to additionally install a waterproof rubber pad 4, and after the hollow pile body 1 passing through the bottom sealing is placed under the soil, a slender weight 5 is placed and a filler and an air flow channel 6 are left. After the slender weight 5 is lifted to a certain height, it is directly dropped to tamp the bottom sealing steel plate 2, so as to knock the bottom sealing steel plate 2 away from the bottom end of the prefabricated hollow pile.
而且,在形成桩端载体8的过程中,可以采用不考虑低能量夯击的方式,也可以采用不考虑细长重锤5是否击出空心桩体1底部的方式进行施工,以快速的完成施工的。Moreover, in the process of forming the pile end carrier 8, the construction can be carried out without considering the low-energy tamping method, or without considering whether the slender heavy hammer 5 hits out of the bottom of the hollow pile body 1, so as to complete the construction quickly.
同样,最终的,在空心桩体1的中心孔道中沉入钢筋笼12,再灌注混凝土14至预制空心桩顶端,或者直接灌注混凝土14至顶端,完成之后对空心桩体1桩头进行处理,以提高桩身载荷。Similarly, finally, a steel cage 12 is sunk into the central hole of the hollow pile body 1, and then concrete 14 is poured to the top of the prefabricated hollow pile, or concrete 14 is directly poured to the top. After completion, the pile head of the hollow pile body 1 is processed to increase the pile body load.
实施例三:Embodiment three:
由于在实际施工过程中,可能会出现空心桩体1的漏水,在本实施例中,为了克服这种情况带来的施工问题,在进行施工基桩的施工过程中,可以通过麻布或者棉麻袋1包覆以一定量的膨润土或者黏土,并通过空心桩体1的上端开口投放至空心桩体1中,然后通过细长重锤5挤压麻布包裹膨润土之后的挤压物,驱使空心桩体1内部的水被挤出,而且 麻布以及膨润土也具有一定的吸水效果,从而提高实际去水止水的效果。Since water leakage may occur in the hollow pile body 1 during the actual construction process, in order to overcome the construction problems caused by this situation, in the present embodiment, during the construction of the foundation pile, a certain amount of bentonite or clay can be wrapped with linen or cotton sack 1, and then put into the hollow pile body 1 through the upper end opening of the hollow pile body 1, and then the extruded material after the bentonite is wrapped with linen is squeezed by a slender heavy hammer 5, so that the water inside the hollow pile body 1 is squeezed out, and Linen and bentonite also have a certain water absorption effect, thereby improving the actual water removal and water stopping effect.
而且的,在形成密实体11和形成桩端载体8的过程中如果出现溢水情况,同样可以使用此步骤进行去水止水,提高实际施工桩的合格率减少废桩的产生。Moreover, if water overflow occurs during the process of forming the dense body 11 and the pile end carrier 8, this step can also be used to remove water and stop water, thereby improving the qualification rate of actual construction piles and reducing the generation of waste piles.
因而,基于上述实施方式,使得能够在地下水较多、地下水较少时,以及桩体出现溢水和施工过程中出现溢水时的桩基施工操作,达到不受地下水影响施工进行的效果。Therefore, based on the above-mentioned implementation mode, pile foundation construction operations can be performed when there is more groundwater, less groundwater, or when water overflows from the pile body or during the construction process, without being affected by groundwater.
以上实施例中,其描述的是整体基桩的施工工艺步骤,是以实施例一、实施例二以及实施例三整体作为基础进行阐述,因而根据本领域技术人员的常规手段,如何进行在地下水充足或者地下水较少时以及桩体出现溢水时的施工工艺选择,其均应涵盖于本申请的保护范围中。In the above embodiments, the construction process steps of the integral foundation piles are described, which are explained based on the first embodiment, the second embodiment and the third embodiment as a whole. Therefore, according to the conventional means of those skilled in the art, how to select the construction process when there is sufficient or less groundwater and when the pile body overflows, it should be covered in the protection scope of this application.
本具体实施方式的实施例均为本申请的可选实施例,并非依此限制本申请的保护范围,故:凡依本申请的结构、形状、原理所做的等效变化,均应涵盖于本申请的保护范围之内。 The embodiments of this specific implementation method are all optional embodiments of the present application, and are not intended to limit the protection scope of the present application. Therefore, all equivalent changes made based on the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims (13)

  1. 一种预制空心桩内夯载体桩的施工方法,所述方法适用于地下水含量较高的地质类型,其步骤包括:A construction method for a prefabricated hollow pile inner rammed carrier pile, the method being applicable to geological types with a high groundwater content, and comprising the following steps:
    1)在预制空心桩的底端,采用封底钢板或者封底钢板加防水胶垫对预制空心桩的中心孔道进行封堵处理;1) At the bottom of the prefabricated hollow pile, a bottom steel plate or a bottom steel plate plus a waterproof rubber pad is used to seal the central channel of the prefabricated hollow pile;
    2)在桩位处,通过锤击、振动、静压的方式之一将上述已封底的预制空心桩在土体中沉入至设定深度;或者通过重锤冲击、螺旋钻引孔、旋挖成孔的方式之一在土体中预先形成桩孔,然后在桩孔中置入上述已封底的预制空心桩;2) At the pile position, the prefabricated hollow pile with the sealed bottom is sunk into the soil to a set depth by hammering, vibration, or static pressure; or a pile hole is pre-formed in the soil by hammering, auger drilling, or rotary drilling, and then the prefabricated hollow pile with the sealed bottom is placed in the pile hole;
    3)在预制空心桩的中心孔道中,将细长重锤缓慢溜放到桩底,细长重锤的外壁与中心孔道的内壁留有一定间隙以形成填料通道和气流通道,在悬吊细长重锤的钢丝绳上标记细长重锤的锤底抵至封底钢板时的位置高度,在预制空心桩的中心孔道中填入少量水泥砂拌合物,提升细长重锤以较低夯击能量对水泥砂拌合物进行夯击以向下挤压封底钢板,通过观察上述钢丝绳标记位置高度,判断是否已打开封底钢板;3) In the central hole of the precast hollow pile, slowly slide a slender weight to the bottom of the pile, leaving a certain gap between the outer wall of the slender weight and the inner wall of the central hole to form a filling channel and an air flow channel, mark the height of the position when the bottom of the slender weight hits the bottom steel plate on the steel wire rope for suspending the slender weight, fill a small amount of cement sand mixture in the central hole of the precast hollow pile, lift the slender weight to tamp the cement sand mixture with a low tamping energy to press the bottom steel plate downward, and judge whether the bottom steel plate has been opened by observing the height of the position marked on the steel wire rope;
    4)继续进行上述填入一定数量的水泥砂拌合物和利用细长重锤对水泥砂拌合物进行夯击的操作,在此过程中以较低夯击能量控制细长重锤始终不击出预制空心桩的底端:4) Continue the above operation of filling a certain amount of cement-sand mixture and tamping the cement-sand mixture with a slender heavy hammer. During this process, the slender heavy hammer is controlled with a relatively low tamping energy so as not to hit the bottom end of the prefabricated hollow pile.
    5)当填入的水泥砂拌合物达到一定数量之后,逐渐加大细长重锤的夯击能量,继续进行上述填入一定数量的水泥砂拌合物和利用细长重锤对水泥砂拌合物进行夯击的操作,在此过程中细长重锤可以击出预制空心桩的底端,使桩端下一定深度和范围内的土体被加固密实,逐渐形成桩端载体;5) When the cement-sand mixture filled in reaches a certain amount, gradually increase the tamping energy of the slender weight, continue to fill in a certain amount of cement-sand mixture and tamping the cement-sand mixture with the slender weight, during which the slender weight can knock out the bottom of the prefabricated hollow pile, so that the soil within a certain depth and range under the pile end is reinforced and compacted, and gradually form a pile end carrier;
    6)在不填料状态下,测量细长重锤连续三次下落击打的贯入度,贯入度测量值满足设计值时停止夯击,贯入度测量值不满足设计值时,继续进行上述步骤5)的填入水泥砂拌合物和夯击操作,直至贯入度测量值满足设计值;6) Under the unfilled state, measure the penetration of the slender hammer after three consecutive drops. When the penetration value meets the design value, stop tamping. When the penetration value does not meet the design value, continue to fill the cement sand mixture and tamping operation in step 5) above until the penetration value meets the design value;
    7)继续进行上述填入水泥砂拌合物和细长重锤的夯击操作,在预制空心桩中心孔道内形成一定高度的水泥砂拌合物密实体,或者在预制空心桩中心孔道内灌注一定数量的混凝土;7) Continue the above-mentioned filling of cement-sand mixture and tamping operation with the slender heavy hammer to form a cement-sand mixture compact body of a certain height in the central hole of the precast hollow pile, or pour a certain amount of concrete in the central hole of the precast hollow pile;
    8)根据地质条件和荷载要求进行桩身处理,包括在预制空心桩的中心孔道中灌注混凝土或者水泥砂浆,或者在预制空心桩的中心孔道中置入钢筋笼之后再灌注混凝土或者水泥砂浆,还包括对预制空心桩桩头的处理。8) Carry out pile body treatment according to geological conditions and load requirements, including pouring concrete or cement mortar into the central hole of the precast hollow pile, or placing a steel cage in the central hole of the precast hollow pile and then pouring concrete or cement mortar, and also including the treatment of the pile head of the precast hollow pile.
  2. 一种预制空心桩内夯载体桩的施工方法,所述方法适用于地下水含量较低的地质类型,其步骤包括:A construction method for a prefabricated hollow pile inner rammed carrier pile, the method being applicable to geological types with low groundwater content, and comprising the following steps:
    1)在预制空心桩的底端,采用封底钢板对预制空心桩的中心孔道进行封堵处理;1) At the bottom of the prefabricated hollow pile, a bottom steel plate is used to seal the central channel of the prefabricated hollow pile;
    2)在桩位处,通过锤击、振动、静压的方式之一将上述已封底的预制空心桩在土体中沉入至设定深度;或者通过重锤冲击、螺旋钻引孔、旋挖成孔的方式之一在土体中预先形成桩孔,然后在桩孔中置入上述已封底的预制空心桩; 2) At the pile position, the prefabricated hollow pile with the sealed bottom is sunk into the soil to a set depth by hammering, vibration, or static pressure; or a pile hole is pre-formed in the soil by hammering, auger drilling, or rotary drilling, and then the prefabricated hollow pile with the sealed bottom is placed in the pile hole;
    3)在预制空心桩的中心孔道中,置入细长重锤,细长重锤的外壁与中心孔道的内壁留有一定间隙以形成填料通道和气流通道,提升细长重锤一定高度后下落夯击封底钢板,将封底钢板击离预制空心桩的底端;3) A slender weight is placed in the central hole of the prefabricated hollow pile, with a certain gap between the outer wall of the slender weight and the inner wall of the central hole to form a filler channel and an air flow channel. The slender weight is lifted to a certain height and then dropped to tamp the bottom steel plate, thereby knocking the bottom steel plate away from the bottom end of the prefabricated hollow pile;
    4)在预制空心桩的中心孔道中填入一定数量的水泥砂拌合物,提升细长重锤一定高度后下落对水泥砂拌合物进行夯击;4) Fill a certain amount of cement-sand mixture into the central hole of the prefabricated hollow pile, lift a slender heavy hammer to a certain height and then drop it to tamp the cement-sand mixture;
    5)重复进行步骤4)的操作,使桩端下一定深度和范围内的土体被加固密实,逐渐形成桩端载体;5) Repeat the operation of step 4) to reinforce and compact the soil within a certain depth and range under the pile end, and gradually form a pile end carrier;
    6)在不填料状态下,测量细长重锤连续三次下落击打的贯入度,贯入度测量值满足设计值时停止夯击,贯入度测量值不满足设计值时,继续进行上述步骤5)的填入水泥砂拌合物和夯击操作,直至贯入度测量值满足设计值;6) Under the unfilled state, measure the penetration of the slender hammer after three consecutive drops. When the penetration value meets the design value, stop tamping. When the penetration value does not meet the design value, continue to fill the cement sand mixture and tamping operation in step 5) above until the penetration value meets the design value;
    7)继续进行上述填入水泥砂拌合物和细长重锤的夯击操作,在预制空心桩中心孔道内形成一定高度的水泥砂拌合物密实体,或者在预制空心桩中心孔道内灌注一定数量的混凝土;7) Continue the above-mentioned filling of cement-sand mixture and tamping operation with the slender heavy hammer to form a cement-sand mixture compact body of a certain height in the central hole of the precast hollow pile, or pour a certain amount of concrete in the central hole of the precast hollow pile;
    8)根据地质条件和荷载要求进行桩身处理,包括在预制空心桩的中心孔道中灌注混凝土或者水泥砂浆,或者在预制空心桩的中心孔道中置入钢筋笼之后再灌注混凝土或者水泥砂浆,还包括对预制空心桩桩头的处理。8) Carry out pile body treatment according to geological conditions and load requirements, including pouring concrete or cement mortar into the central hole of the precast hollow pile, or placing a steel cage in the central hole of the precast hollow pile and then pouring concrete or cement mortar, and also including the treatment of the pile head of the precast hollow pile.
  3. 根据权利要求1或者权利要求2所述的预制空心桩内夯载体桩的施工方法,其中,预制空心桩包括预应力管桩、预制空心竹节桩、预制空心方桩。According to the construction method of prefabricated hollow pile internal ramming carrier piles according to claim 1 or claim 2, the prefabricated hollow piles include prestressed pipe piles, prefabricated hollow bamboo piles, and prefabricated hollow square piles.
  4. 根据权利要求1或者权利要求2所述的预制空心桩内夯载体桩的施工方法,其中,封底钢板的面积大于预制空心桩中心孔道的面积,封底钢板以螺栓或者焊接方式与预制空心桩底端的法兰盘固定,螺栓或者焊接固定的强度适当降低,以利于后续工序中将封底钢板击离预制空心桩的底端。According to the construction method of ramming carrier piles in prefabricated hollow piles as described in claim 1 or claim 2, the area of the bottom steel plate is larger than the area of the central channel of the prefabricated hollow pile, the bottom steel plate is fixed to the flange at the bottom end of the prefabricated hollow pile by bolts or welding, and the strength of the bolt or welding fixation is appropriately reduced to facilitate the bottom steel plate to be driven away from the bottom end of the prefabricated hollow pile in the subsequent process.
  5. 根据权利要求2所述的预制空心桩内夯载体桩的施工方法,其中,在某些情况如先在土体中预先形成桩孔然后在桩孔中置入预制空心桩时,则不需要对预制空心桩进行封底处理。According to the construction method of prefabricated hollow pile internal rammed carrier piles as described in claim 2, in some cases, such as when a pile hole is pre-formed in the soil and then a prefabricated hollow pile is placed in the pile hole, it is not necessary to perform bottom sealing treatment on the prefabricated hollow pile.
  6. 根据权利要求1或者权利要求2所述的预制空心桩内夯载体桩的施工方法,其中,细长重锤的外壁与中心孔道的内壁留有的间隙为2cm至4cm。According to the construction method of prefabricated hollow pile internal ramming carrier piles according to claim 1 or claim 2, the gap left between the outer wall of the slender weight and the inner wall of the central channel is 2 cm to 4 cm.
  7. 根据权利要求1所述的预制空心桩内夯载体桩的施工方法,其中,以较低夯击能量是指减小细长重锤的落距或者锤的重量,反之在步骤5)中逐渐加大细长重锤的夯击能量是指增加细长重锤的落距或者锤的重量。According to the construction method of ramming carrier piles in prefabricated hollow piles as described in claim 1, using lower ramming energy means reducing the drop distance of the slender heavy hammer or the weight of the hammer, whereas gradually increasing the ramming energy of the slender heavy hammer in step 5) means increasing the drop distance of the slender heavy hammer or the weight of the hammer.
  8. 根据权利要求1或者权利要求2所述的预制空心桩内夯载体桩的施工方法,其中,所述的水泥砂拌合物的材料包括水泥、砂子,还包括水、小粒径碎石、矿渣、钢渣。According to the construction method of prefabricated hollow pile internal ramming carrier piles according to claim 1 or claim 2, the materials of the cement sand mixture include cement, sand, water, small-size crushed stone, slag, and steel slag.
  9. 根据权利要求1所述的预制空心桩内夯载体桩的施工方法,其中,所述的水泥砂拌合物达到一定数量是大于0.1m3。According to the construction method of prefabricated hollow pile internal ramming carrier piles as described in claim 1, wherein the cement sand mixture reaches a certain amount greater than 0.1m3.
  10. 根据权利要求1或者权利要求2所述的预制空心桩内夯载体桩的施工方法,其中, 每次填入水泥砂拌合物的数量不超过0.05m3,并且每次填料后的夯击次数不超过5次。The construction method of prefabricated hollow pile internal ramming carrier pile according to claim 1 or claim 2, wherein: The amount of cement-sand mixture filled in each time shall not exceed 0.05m3, and the number of tamping times after each filling shall not exceed 5 times.
  11. 根据权利要求1或者权利要求2所述的预制空心桩内夯载体桩的施工方法,其中,贯入度是指细长重锤以相同的高度自由下落击打底端填料后的当次下沉数值,即为1击的贯入度,并且后一次的贯入度不大于前一次的贯入度;在测量细长重锤贯入度时,参考规范要求,细长重锤的冲击能量应接近2100kN/m2(单位面积),冲击能量计算公式为:锤的重量乘以落距除以锤底面积。According to the construction method of rammed carrier piles in prefabricated hollow piles as described in claim 1 or claim 2, the penetration refers to the sinking value of a slender heavy hammer after it freely falls from the same height to hit the bottom filler, that is, the penetration of one hit, and the penetration of the latter is not greater than the penetration of the previous one; when measuring the penetration of the slender heavy hammer, referring to the requirements of the specifications, the impact energy of the slender heavy hammer should be close to 2100kN/m2 (unit area), and the impact energy calculation formula is: the weight of the hammer multiplied by the drop distance divided by the bottom area of the hammer.
  12. 根据权利要求1或者权利要求2所述的预制空心桩内夯载体桩的施工方法,其中,观测预制空心桩是否存在上浮,并根据预制管桩的上浮数值,对预制管桩进行复打或者复压,复打或者复压是指通过锤击或者静压的方式使预制空心桩下沉,下沉值不超过预制空心桩的上浮值,如预制空心桩没有上浮或者上浮量很小则无需复打或者复压。According to the construction method of prefabricated hollow pile internal ramming carrier piles as described in claim 1 or claim 2, it is observed whether the prefabricated hollow piles are floating, and the prefabricated pipe piles are re-driven or re-pressed according to the floating value of the prefabricated pipe piles. The re-driving or re-pressing means that the prefabricated hollow piles are sunk by hammering or static pressure, and the sinking value does not exceed the floating value of the prefabricated hollow piles. If the prefabricated hollow piles do not float or the floating amount is very small, there is no need to re-drive or re-press.
  13. 根据权利要求1或者权利要求2所述的预制空心桩内夯载体桩的施工方法,其中,在预制空心桩中心孔道内形成一定高度的水泥砂拌合物密实体或者在灌注一定数量的混凝土,目的是将预制空心桩底部封闭并增加桩底与载体的接触面积,同时防止桩底土体在四周压力下在中心孔道内向上反涌。 According to the construction method of rammed carrier piles in precast hollow piles as described in claim 1 or claim 2, a cement-sand mixture compact of a certain height is formed in the central channel of the precast hollow pile or a certain amount of concrete is poured, the purpose of which is to seal the bottom of the precast hollow pile and increase the contact area between the pile bottom and the carrier, while preventing the soil at the bottom of the pile from surging upward in the central channel under the surrounding pressure.
PCT/CN2023/123165 2022-10-08 2023-10-07 Construction method for prefabricated hollow internally-rammed carrier pile WO2024074130A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202211229263.0A CN115288131B (en) 2022-10-08 2022-10-08 Construction method of prefabricated hollow internally-rammed carrier pile
CN202211229263.0 2022-10-08

Publications (1)

Publication Number Publication Date
WO2024074130A1 true WO2024074130A1 (en) 2024-04-11

Family

ID=83819230

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2023/123165 WO2024074130A1 (en) 2022-10-08 2023-10-07 Construction method for prefabricated hollow internally-rammed carrier pile

Country Status (2)

Country Link
CN (1) CN115288131B (en)
WO (1) WO2024074130A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118313095A (en) * 2024-06-06 2024-07-09 江西省交通工程集团有限公司 Digital quality control method and system for hydraulic tamper

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115288131B (en) * 2022-10-08 2023-01-13 石家庄铁道大学 Construction method of prefabricated hollow internally-rammed carrier pile
CN115852932B (en) * 2023-02-13 2024-02-23 北京波森特岩土工程有限公司 Construction method of carrier pile

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0369714A (en) * 1989-08-08 1991-03-26 Kaiyo Kogyo Kk Method of building crushed stone column by dropping weight and method of estimating ground bearing power
CN1563604A (en) * 2004-04-02 2005-01-12 王继忠 Construction method for concrete pile
US20060147274A1 (en) * 2004-11-12 2006-07-06 Jinliang Ding Construction process for composite pile foundation
CN105821836A (en) * 2016-02-18 2016-08-03 王继忠 Construction method for carrier pile
CN113653032A (en) * 2021-08-27 2021-11-16 北京波森特岩土工程有限公司 Construction method of uplift carrier pile
CN114517472A (en) * 2021-07-08 2022-05-20 北京波森特岩土工程有限公司 Construction method of carrier pile
CN115288131A (en) * 2022-10-08 2022-11-04 石家庄铁道大学 Construction method of prefabricated hollow internal ramming carrier pile

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103821139B (en) * 2014-02-11 2015-08-19 浙江交通职业技术学院 A kind of rammer expands carrier strength core multiple elements design stake and reinforced soft soil ground construction method
CN111794216A (en) * 2020-07-21 2020-10-20 王继忠 Construction method of uplift carrier pile
CN215888202U (en) * 2021-07-08 2022-02-22 北京波森特岩土工程有限公司 Bottom sealing device of precast tubular pile

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0369714A (en) * 1989-08-08 1991-03-26 Kaiyo Kogyo Kk Method of building crushed stone column by dropping weight and method of estimating ground bearing power
CN1563604A (en) * 2004-04-02 2005-01-12 王继忠 Construction method for concrete pile
US20060147274A1 (en) * 2004-11-12 2006-07-06 Jinliang Ding Construction process for composite pile foundation
CN105821836A (en) * 2016-02-18 2016-08-03 王继忠 Construction method for carrier pile
CN114517472A (en) * 2021-07-08 2022-05-20 北京波森特岩土工程有限公司 Construction method of carrier pile
CN113653032A (en) * 2021-08-27 2021-11-16 北京波森特岩土工程有限公司 Construction method of uplift carrier pile
CN115288131A (en) * 2022-10-08 2022-11-04 石家庄铁道大学 Construction method of prefabricated hollow internal ramming carrier pile

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118313095A (en) * 2024-06-06 2024-07-09 江西省交通工程集团有限公司 Digital quality control method and system for hydraulic tamper

Also Published As

Publication number Publication date
CN115288131B (en) 2023-01-13
CN115288131A (en) 2022-11-04

Similar Documents

Publication Publication Date Title
WO2024074130A1 (en) Construction method for prefabricated hollow internally-rammed carrier pile
US7201540B2 (en) Construction process for composite pile foundation
CN110318394B (en) Construction method of composite pile
CN114517472B (en) Construction method of carrier pile
CN102733378B (en) Construction method of concrete pile
CN108894214B (en) Karst cave geological environment cast-in-place pile and pile-forming construction method thereof
CN203213136U (en) Caisson and pile combined foundation of consolidated subsoil
CN112663694B (en) Construction method for lifting and rectifying building on silt geology
CN113653032A (en) Construction method of uplift carrier pile
CN102808407B (en) Construction method of soft-foundation reinforced concrete cast-in-place pile
CN112064623A (en) Construction method of carrier pile
CN105064332A (en) Construction method for bearing base piles of square pile bodies
CN205776209U (en) The construction equipment of concrete-pile
CN212506308U (en) Combined supporting structure of inclined tubular pile and vertical wedge-shaped pile
CN212506305U (en) Combined supporting structure of inclined wedge-shaped pile and vertical wedge-shaped pile
CN112144522A (en) Construction method of prestressed pipe pile and special prestressed pipe pile thereof
CN201512782U (en) Softening prevention pile
CN112144516A (en) Construction method of concrete pile
CN111075471A (en) Large karst cavity top filling type tunnel rockfall prevention structure and construction method
CN115852932B (en) Construction method of carrier pile
CN206428692U (en) A kind of multitube grouting device of two-tube compound club-footed pile machine
CN206768890U (en) A kind of reinforcement operation platform of the building foundation of river bank
CN215669468U (en) Expand end concrete PHC strength nature stake
CN219260990U (en) Pile end rear grouting reinforcement structure of overlying gap stratum foundation pile
CN117926814A (en) Construction forming method of carrier pile

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 23874322

Country of ref document: EP

Kind code of ref document: A1