WO2023065454A1 - 一种箱型桥弦杆的制作方法 - Google Patents
一种箱型桥弦杆的制作方法 Download PDFInfo
- Publication number
- WO2023065454A1 WO2023065454A1 PCT/CN2021/132147 CN2021132147W WO2023065454A1 WO 2023065454 A1 WO2023065454 A1 WO 2023065454A1 CN 2021132147 W CN2021132147 W CN 2021132147W WO 2023065454 A1 WO2023065454 A1 WO 2023065454A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- plate
- support
- box
- sided
- box girder
- Prior art date
Links
- 238000000034 method Methods 0.000 title claims abstract description 32
- 239000003351 stiffener Substances 0.000 claims abstract description 77
- 230000035515 penetration Effects 0.000 claims abstract description 74
- 238000003466 welding Methods 0.000 claims abstract description 72
- 238000004519 manufacturing process Methods 0.000 claims abstract description 41
- 238000005192 partition Methods 0.000 claims abstract description 35
- 238000010276 construction Methods 0.000 claims abstract description 15
- 238000009434 installation Methods 0.000 claims description 26
- 238000007789 sealing Methods 0.000 claims description 19
- 210000001503 joint Anatomy 0.000 claims description 16
- 238000004140 cleaning Methods 0.000 claims description 14
- 239000013256 coordination polymer Substances 0.000 claims description 9
- 230000002787 reinforcement Effects 0.000 claims 1
- 239000000919 ceramic Substances 0.000 description 11
- 229910000831 Steel Inorganic materials 0.000 description 2
- 238000005520 cutting process Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000003032 molecular docking Methods 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K31/00—Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups
- B23K31/02—Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups relating to soldering or welding
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K2103/00—Materials to be soldered, welded or cut
- B23K2103/02—Iron or ferrous alloys
- B23K2103/04—Steel or steel alloys
Definitions
- the invention belongs to the technical field of steel structure buildings, in particular to a method for manufacturing a box-shaped bridge chord.
- the chord refers to the upper and lower peripheral members of the truss.
- the upper member is called the upper chord
- the lower member is called the lower chord.
- it is not independently set in the bridge, and most of them need to be connected with other components, especially the lower chord, which not only needs to be vertically connected to the upper chord, but also needs to be connected to the bridge deck.
- the end beams are connected horizontally, the assembly between the various parts is relatively difficult, the existing chords do not have so many connection nodes, and when they are installed, many adapters are needed to realize the connection, which not only increases It not only reduces the construction cost, but also increases the difficulty of construction and prolongs the construction period.
- the purpose of the present invention is to provide a method for making box-shaped bridge chords.
- the box-shaped bridge chords can be reasonably manufactured and constructed. According to the different installation positions of different components Using different welding methods for assembly and welding can effectively improve the production quality of the entire box bridge chord, ensure the stability of its connection with the bridge deck and box end girder, and ensure its support, bearing capacity and safety in later use sex.
- the present invention provides a method for manufacturing box-shaped bridge chords, including the specific manufacturing method of box-shaped bridge chords as follows: 1): The box girder wall plate is first thickened and thinned on the horizontal tire frame.
- the butt joint of the panels, the gusset plate, the center line of the butt plate and the center line of the connecting web joint are pre-marked and positioned, and the stiffeners and stiffeners are assembled and welded with the box girder wall plate, and the correction after welding is qualified and hung on the tire frame Carry out positioning, that is: add 1 ⁇ welding shrinkage in the length direction of the box girder wall plate and make the gusset plate end upright, and add 10mm allowance at the other end; add 1 ⁇ welding shrinkage allowance cutting in the length direction of the longitudinal stiffener; box girder wall
- the center position of the plate corresponding to the stiffener is pressed against deformation at 179.5°; the stiffener and the box girder wall plate are welded by penetration;
- the root 2mm groove form, the reverse fillet weld is strengthened, and the stiffening aid is ground and tightened;
- the transverse stiffening partition and the box girder wall are vertically arranged.
- the three transverse diaphragms located in the node area of the first support and the top plate are single-sided Fillet welds, the other three sides are penetration welds, double-sided 40° root 2mm grooves are used with the box girder wall plate, and single-sided 40° root 2mm grooves are used between the bottom plate, and the diaphragms on both sides
- the direction of the side bevel of the bottom plate, the direction of the side bevel of the bottom plate of a diaphragm in the middle is towards the side of the manhole; if the drawing of the notch of the stiffener on the diaphragm is not enlarged, each side of the notch must be enlarged by 2mm for the stakeout; the position of the non-node area
- the three sides between the diaphragm and the wall and roof are in the form
- the bottom plate unit is hoisted onto the tire frame for assembly and positioning.
- the center line of the node and the position line and verticality of the port tongue and groove are determined.
- the specific welding method is: the length direction of the bottom plate Add 1 ⁇ of welding shrinkage and the end of the gusset plate is straight, and add 10mm margin at the other end; there is a penetration weld between the bottom plate and the box girder wall plate, and the position of the joint area adopts the form of a single-sided 40° root 2mm bevel, when the plate When the thickness is more than 40mm, the single-sided 30° root 2mm groove form is adopted; the bottom plate and the external diaphragm of the box are double-sided fillet welds, and the diaphragm and the bottom plate at the port need to adopt the form of single-sided fillet welds.
- the specific manufacturing method of the first support described in the present invention is as follows: 1): Weld the support top plate, make the support top plate in advance, and weld the U-shaped help and the first stiffening help on it, the U-shaped help and the first stiffening support. Both the stiffener and the top plate of the support are welded in the form of double-sided welds, the butt joints of the top plate of the support are welded in the form of internal welding and root cleaning grooves, and the first stiffener and the small stiffener and the frame are double-sided fillet welded seam
- the stiffening aid located at the node on the box girder wall plate and the deep penetration weld of the box girder wall plate adopt the form of double-sided 40° root 2mm groove, and there is no R hole in the middle of the stiffening aid;
- chord end beam assembly The specific manufacturing method of the chord end beam assembly described in the present invention is as follows:
- the box-shaped bridge chord in the present invention includes: a bottom plate, a set of box girder wall plates, a top plate, a chord end beam assembly, a first support and a set of second support, and the box girder wall plates are arranged oppositely. And set on the bottom plate, the top plate is set above the two box girder wall plates, the chord end beam assembly is set above the top plate, the first support is set under the bottom plate, and is connected with the chord end beam The components are arranged in reverse, and the second support is arranged on the top plate.
- the bottom plate includes a bottom plate body, and the two sides of the bottom plate body are symmetrically provided with lower corbel gusset plates, and a group of box outer transverse partitions are arranged between the lower corbel gusset plate and the outer edge plate of the top plate , and the two ends of the top plate are provided with patch panels.
- the box girder wall plate in the present invention includes a box girder wall plate body, a gusset plate for installing the chord end beam assembly is arranged above the box girder wall plate body, and the first support is arranged on the box girder wall plate
- a set of stiffening aids are provided on the inner wall of the box girder wall plate and the top plate, and a set of stiffening plates are provided on the stiffening aids, and a set of transverse stiffening partitions are arranged between the two box girder wall plates, and the The above-mentioned transverse stiffening partition is connected with the stiffeners on the inner wall of the box girder wall and roof at the same time;
- the diaphragm includes a diaphragm body, and a set of installation grooves for installing stiffeners is provided on the side of the diaphragm body.
- the chord end beam assembly in the present invention includes a set of butt webs and a set of sealing plates, the butt webs are arranged between two gusset plates, the sealing plates are arranged between two The webs are connected, and the sealing plate is arc-shaped.
- the first support includes a set of support top plates, a set of support gusset plates, a set of support inner partitions, a support bottom plate and a set of support inner transverse partitions.
- the support gusset plate is relatively arranged on the bottom plate, the inner partition of the support is arranged between the support gusset plates, the support bottom plate is arranged at the bottom of the support gusset plate, and the support
- the inner transverse partition is arranged vertically between the top plate of the support and the bottom plate of the support, and there are support wall plates on both sides of the inner transverse partition of the support;
- the inner and outer sides of the support wall plate are provided with long stiffening plates, and a small stiffening plate is also provided between the long stiffening plates on the outer side of the support wall plate;
- a U-shaped aid and a set of first stiffening aids are arranged on the top plate of the support.
- the three sides of the stiffening plate in the present invention are provided with installation grooves, and the installation grooves are herringbone grooves.
- the setting of the installation groove facilitates the installation of the stiffener, further optimizes the structure of the chord, and can improve the stability of the installation of the stiffener; the setting of the herringbone hole groove improves the stability of the installation of the stiffener by taking advantage of the particularity of its structure.
- the manufacturing method of a box-shaped bridge chord according to the present invention through a reasonable construction method, the box-shaped bridge chord is reasonably manufactured and constructed, and different welding methods are used according to the installation positions of different components. Welding can effectively improve the production quality of the entire box-shaped bridge chord, ensure the stability of its connection with the bridge deck and the box-shaped end beam, and ensure its support, load-bearing capacity and safety in later use.
- the box-shaped bridge chord described in the present invention has a simple structure, reasonable design, and is easy to manufacture. By setting the chord end beam assembly on the top plate, it is convenient to connect with other box-shaped chords.
- the first support The setting of the second support facilitates its connection with the box-shaped end beam, and the setting of the second support facilitates its connection with the bridge deck, realizes multi-directional connection, reduces the use of other adapters, and optimizes the structure of the chord. Shorten the construction period and make it better meet the needs of bridge construction.
- the bottom plate in the present invention includes a bottom plate body, and lower corbel gusset plates are arranged symmetrically on both sides of the bottom plate body, and a group of web plates are arranged between the lower corbel gusset plate and the outer edge plate of the top plate, and Both ends of the top plate are provided with patch panels.
- the setting of the web greatly improves the stability of the connection between the bottom plate, the top plate and the side wall plates, and at the same time, the two ends of the top plate are provided with patching plates, which further improves the stability of the entire chord structure.
- the chord end beam assembly described in the present invention includes a set of butt webs and a set of sealing plates.
- the arrangement of the butt webs and sealing plates can effectively improve the stability of the chord end beam structure and further improve The stability of its connection and the bearing capacity and safety of later use.
- the structural stability of the first support described in the present invention greatly improves the stability of its connection with the box-shaped end beam, and further improves the stability and safety of the entire structure.
- Fig. 1 is the structural representation of the manufacture method of box bridge chord among the present invention
- Fig. 2 is the installation schematic diagram of bearing top plate among the present invention
- Fig. 3 is the partial structural representation of box girder wall plate among the present invention.
- Fig. 4 is the installation schematic diagram of the first bearing among the present invention.
- Fig. 5 is the structural representation of diaphragm in the present invention.
- first and second are used for descriptive purposes only, and cannot be interpreted as indicating or implying relative importance or implicitly specifying the quantity of indicated technical features. Thus, a feature defined as “first” and “second” may explicitly or implicitly include one or more of these features.
- plural means two or more, unless otherwise clearly defined.
- a first feature being “on” or “under” a second feature may include direct contact between the first and second features, and may also include the first and second features Not in direct contact but through another characteristic contact between them.
- “above”, “above” and “above” the first feature on the second feature include that the first feature is directly above and obliquely above the second feature, or simply means that the first feature is horizontally higher than the second feature.
- “Below”, “beneath” and “under” the first feature to the second feature include that the first feature is directly below and obliquely below the second feature, or simply means that the first feature has a lower level than the second feature.
- the box girder wall plate 2 is firstly joined by thick and thin plates on the horizontal tire frame, the center line of the gusset plate, the center line of the butt plate and the center line of the connecting web node are pre-marked and positioned, and the stiffener 23 and the stiffener 24 Assembled and welded with the box girder wall plate 2, after welding, the correction is qualified and hung on the tire frame for positioning, that is: add 1 ⁇ welding shrinkage to the length direction of the box girder wall plate 2 and the gusset plate end is normal, and the other end is added 10mm margin ; Add 1 ⁇ welding shrinkage allowance blanking in the length direction of the longitudinal stiffener; the box girder wall plate 2 corresponds to the central position of the stiffener 23 and suppresses 179.5° anti-deformation; the joint between the stiffener 23 and the box girder wall plate 2 is a penetration weld; The stiffening plate 24 is welded with the 2 wall plates of the box girder by means of deep penetration we
- the direction of the side groove of the bottom plate of the diaphragm on both sides, and the direction of the side groove of the bottom plate of the middle diaphragm is towards the side of the manhole; if the drawing of the notch of the stiffener on the diaphragm is not enlarged, each side of the notch must be enlarged by 2mm for stakeout ; In the non-node area, the three sides between the diaphragm, the wall plate and the roof are in the form of double-sided fillet welds, and the gap between the diaphragm and the bottom plate is ground and tight. During the construction process, if the drawing of the stiffener notch on the diaphragm is not enlarged , the stakeout needs to enlarge each side of the notch by 2mm;
- the top plate 3 is hoisted, and the top plate 3 is assembled and welded with the stiffener 23 in advance, and the joint between the stiffener 23 and the top plate 3 is a penetration weld;
- the inter-node area is full penetration CP, which adopts the form of internal welding and external root cleaning groove; the rest of the position is penetration weld, and fillet weld is used outside the end diaphragm to strengthen. ;
- the specific welding method is: the bottom plate 1 Add 1 ⁇ welding shrinkage in the length direction and the gusset plate end is upright, and an additional 10mm allowance is placed at the other end; the penetration weld between the bottom plate 1 and the box girder wall plate 2, and the position of the joint area adopts a single-sided 40° root 2mm slope When the thickness of the plate is > 40mm, the single-sided 30° root 2mm groove form is adopted; the bottom plate 1 and the external diaphragm 13 of the box are double-sided fillet welds, and the gap between the transverse diaphragm and the bottom plate 1 at the port needs to be Single-sided fillet welds are used.
- the specific manufacturing method of the first support 5 described in the present embodiment is as follows: 1): Weld the support top plate 51, make the support top plate 51 in advance, and weld the U-shaped help 511 and the first stiffening help 512 on it, the described Both the U-shaped aid 511 and the first stiffening aid 512 are welded to the support top plate 51 in the form of double-sided welds. There are double-sided fillet welds between the stiffener and the frame;
- the stiffening aid located at the node on the box girder wall plate 2 and the deep penetration weld of the box girder wall plate 2 adopt the form of double-sided 40° root 2mm bevel, and there is no R hole in the middle of the stiffening aid;
- the inner transverse diaphragm 55 of the welded support, the penetration weld between the inner transverse diaphragm 55 of the support and the frame, and the top plate 51 of the support adopt the form of double-sided 40° root 2mm bevel;
- the 56 side support wall plates adopt the single-sided 40° root 2mm bevel form, and the bevel is facing outward;
- chord end beam assembly 4 The specific manufacturing method of the chord end beam assembly 4 described in this embodiment is as follows:
- the specific manufacturing method of the second support 6 described in the present embodiment is as follows:
- a method for making a box-shaped bridge chord includes: a bottom plate 1, a group of box girder wall plates 2, a top plate 3, a chord end beam assembly 4, and a first support 5 and a group of second bearings 6, the box girder wall plate 2 is arranged oppositely, and is set on the bottom plate 1, the top plate 3 is set above the two box girder wall plates 2, and the chord end beam assembly 4 It is arranged above the top plate 3 , the first support 5 is set under the bottom plate 1 and opposite to the chord end beam assembly 4 , and the second support 6 is set on the top plate 3 .
- the bottom plate 1 includes a bottom plate body 11, and the two sides of the bottom plate body 11 are symmetrically provided with a lower corbel gusset plate 12, and a gap is arranged between the lower corbel gusset plate 12 and the outer edge plate of the top plate 3.
- a set of horizontal partitions 13 on the outside of the box body, and the two ends of the top plate 3 are provided with patch panels 14 .
- the box girder wall plate 2 includes a box girder wall plate body 21, a gusset plate 22 for installing the chord end beam assembly 4 is arranged above the box girder wall plate body 21, and the first support 5 is arranged on the outer side of the box girder wall plate body 21, a set of stiffening aids 23 are provided on the inner walls of the box girder wall plate 2 and the top plate 3, and a stiffening plate 24 is provided on the stiffening aids 23, and the two box girder walls A group of transverse stiffening partitions 25 are arranged between the plates 2, and the transverse stiffening partitions 25 are simultaneously connected with the stiffeners 23 on the inner walls of the box girder wall 2 and the roof 3;
- the diaphragm 24 includes a diaphragm body, and a set of installation slots 251 for installing the stiffeners 23 are provided on the side of the diaphragm body.
- the chord end beam assembly 4 in this embodiment includes a set of butt webs 41 and a set of sealing plates 42, the butt webs 41 are arranged between two node plates 22, and the sealing plates 42 are arranged at two nodes between the plates 22 and connected with the butt web 41, and the sealing plate 42 is arc-shaped.
- the first support 5 in this embodiment includes a set of support top plates 51, a set of support gusset plates 52, a set of support inner partitions 53, a support bottom plate 54 and a set of support inner transverse partitions 55 ,
- the support top plate 51 is arranged on the outer side of the top plate 1
- the support gusset plate 52 is relatively arranged on the bottom plate 1
- the inner partition plate 53 of the support is arranged between the support gusset plates 52
- the support bottom plate 54 is located at the bottom of the support gusset plate 52
- the inner transverse partition 55 of the support is vertically arranged between the support top plate 51 and the support bottom plate 54, and the two sides of the support inner transverse diaphragm 55 are provided with support Seat wall 56;
- the inner and outer sides of the support wall plate 56 are provided with long stiffening plates 57, and a small stiffening plate is also provided between the long strip stiffening plates 57 outside the support wall plate 57;
- a U-shaped helper 511 and a set of first stiffeners 512 are arranged on the support top plate 51 .
- the three sides of the stiffening plate 24 are provided with installation grooves 241, and the installation grooves 241 are herringbone grooves.
- the manufacturing method of a kind of box-shaped bridge chord described in the present embodiment comprises the specific manufacturing method of box-shaped bridge chord as follows: 1): box girder wall plate 2 first carries out the jigsaw puzzle of thick and thin plates on the horizontal tire frame For butt jointing, the center line of the gusset plate, the center line of the butt plate and the center line of the connecting web member are pre-marked and positioned, and the stiffener 23 and stiffener 24 are assembled and welded with the box girder wall plate 2, and the post-welding correction is qualified and hung on the tire frame.
- Positioning that is: add 1 ⁇ welding shrinkage in the length direction of box girder wall plate 2 and make the gusset plate end upright, and add 10mm allowance at the other end; add 1 ⁇ welding shrinkage allowance cutting in the longitudinal direction of the stiffener;
- the plate 2 corresponds to the central position of the stiffener 23 and is pressed against deformation at 179.5°; the joint between the stiffener 23 and the two box girder wall plates is a penetration weld; the joint between the stiffener 24 and the two box beam wall plates is welded by a penetration weld. It adopts the form of groove with 40° on one side and 2mm root, and the fillet weld on the reverse side is strengthened, and it is ground and tightened with 23 stiffening aids;
- the direction of the side groove of the bottom plate of the diaphragm on both sides, and the direction of the side groove of the bottom plate of the middle diaphragm is towards the side of the manhole; if the drawing of the notch of the stiffener on the diaphragm is not enlarged, each side of the notch must be enlarged by 2mm for stakeout ; In the non-node area, the three sides between the diaphragm, the wall plate and the roof are in the form of double-sided fillet welds, and the gap between the diaphragm and the bottom plate is ground and tight. During the construction process, if the drawing of the stiffener notch on the diaphragm is not enlarged , the stakeout needs to enlarge each side of the notch by 2mm;
- the top plate 3 is hoisted, and the top plate 3 is assembled and welded with the stiffener 23 in advance, and the joint between the stiffener 23 and the top plate 3 is a penetration weld;
- the inter-node area is full penetration CP, which adopts the form of internal welding and external root cleaning groove; the rest of the position is penetration weld, and fillet weld is used outside the end diaphragm to strengthen. ;
- the specific welding method is: the bottom plate 1 Add 1 ⁇ welding shrinkage in the length direction and the gusset plate end is upright, and an additional 10mm allowance is placed at the other end; the penetration weld between the bottom plate 1 and the box girder wall plate 2, and the position of the joint area adopts a single-sided 40° root 2mm slope When the thickness of the plate is > 40mm, the single-sided 30° root 2mm groove form is adopted; the bottom plate 1 and the external diaphragm 13 of the box are double-sided fillet welds, and the gap between the transverse diaphragm and the bottom plate 1 at the port needs to be Single-sided fillet welds are used.
- the specific manufacturing method of the first support 5 described in the present embodiment is as follows: 1): Weld the support top plate 51, make the support top plate 51 in advance, and weld the U-shaped help 511 and the first stiffening help 512 on it, the described Both the U-shaped aid 511 and the first stiffening aid 512 are welded to the support top plate 51 in the form of double-sided welds. There are double-sided fillet welds between the stiffener and the frame;
- the stiffening aid located at the node on the box girder wall plate 2 and the deep penetration weld of the box girder wall plate 2 adopt the form of double-sided 40° root 2mm bevel, and there is no R hole in the middle of the stiffening aid;
- the inner transverse diaphragm 55 of the welded support, the penetration weld between the inner transverse diaphragm 55 of the support and the frame, and the top plate 51 of the support adopt the form of double-sided 40° root 2mm bevel;
- the 56 side support wall plates adopt the single-sided 40° root 2mm bevel form, and the bevel is facing outward;
- chord end beam assembly 4 The specific manufacturing method of the chord end beam assembly 4 described in this embodiment is as follows:
- the specific manufacturing method of the second support 6 described in the present embodiment is as follows:
- the butt joint between the top plate of the bridge deck and the top plate of the lower chord is ceramic backing plate welding, the groove is 40°, leaving 2 gaps of 6mm (evenly divided on both sides), and the groove faces upward;
- the butt joint between the lower panel of the transverse T rib of the bridge deck and the lower chord corbel gusset plate is welded with a ceramic backing plate.
- the groove is 40° leaving 2 gaps of 6mm (evenly divided on both sides), and the groove faces upward.
- the butt joint method between the box-shaped end girder and the lower chord end truss in the processed box-shaped bridge chord is as follows:
- the butt joint between the box-shaped corbel web of the lower chord end beam and the box-shaped end beam web is ceramic backing plate welding, the groove is 40°, leaving 2 gaps of 6mm (evenly divided on both sides), and the groove faces the outside;
- the butt joint between the box-shaped corbel top plate and the support top plate 51 in the box-shaped end beam is ceramic backing plate welding, the groove is 40°, leaving 2 gaps of 6mm (evenly divided on both sides), and the groove faces upward.
- the butt joint of the web is ceramic backing plate welding, the groove is 40°, leaving 2 gaps of 6mm (evenly divided on both sides), and the groove is facing the outside of the box;
- the butt joint of the bottom plate is ceramic backing plate welding, the groove is 40°, leaving 2 gaps of 6mm (evenly divided on both sides), and the groove faces the inside of the box;
- the butt joint of the top plate is ceramic backing plate welding, the groove is 40°, leaving 2 gaps of 6mm (evenly divided on both sides), and the groove faces upward;
- the surrounding part of the hole is welded with ceramic backing plate, the groove is 40°, leaving 2 gaps of 6mm (evenly divided on both sides), and the groove faces upward;
- the stiffener inserts on the web are welded with ceramic backing plates, the groove is 40°, leaving 2 gaps of 6mm (evenly divided on both sides), and the groove faces upward.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
一种箱型桥弦杆的制作方法,包括箱梁壁板(2)先在水平胎架上进行厚薄板的拼板对接,节点板、对接板中心线及连接腹杆节点中心线预先划线定位,并将加劲肋(23)和加劲板(24)与箱梁壁板(2)间进行组装焊接;安装箱体内部的横向加劲隔板(25);安装另一块箱梁壁板(2);吊装顶板(3),顶板(3)预先与加劲肋(23)进行组装焊接,加劲肋(23)与顶板(3)间为熔深焊缝;将箱梁壁板(2)外侧箱体外侧横隔板(13)依次吊上胎架;将底板(1)单元吊上胎架进行组装定位;然后装焊第一支座(5)和一组第二支座(6);通过合理的施工方法,根据不同部件安装位置的不同采用不同的焊接方式进行装焊,能够有效的提高整个箱型桥弦杆的制作质量,保证其与桥面和箱型端梁连接的稳定性,保证其支撑性、承载性和后期使用的安全性。
Description
本发明属于钢结构建筑技术领域,特别涉及一种箱型桥弦杆的制作方法。
传统的桥梁大多是钢筋水泥制成,其施工周期较长,且容易受到环境的影响,影响其整个工期,而钢结构建筑,受到施工环境的影响较小,且其施工周期较短,因而近年来受到广泛的应用。
弦杆是指桁架上、下外围的杆件,上边的杆件称为上弦杆,下边的杆件称为下弦杆。无论是上弦杆还是下弦杆,其在桥梁中都不是独立设置的,大多都是需要与其他部件进行连接的,尤其是下弦杆,其不仅需要与上弦杆进行竖向连接,还需要与桥面以及端梁进行横向连接,各个部件之间的组装难度较大,现有的弦杆不具备这么多的连接节点,其在安装时,就需要采用诸多的转接件才能够实现连接,不仅增加了施工成本,同时还会增加施工的难度,延长施工的周期。
发明内容
发明目的:为了克服以上不足,本发明的目的是提供一种箱型桥弦杆的制作方法,通过合理的施工方法,对箱型桥弦杆进行合理的制作施工,根据不同部件安装位置的不同采用不同的焊接方式进行装焊,能够有效的提高整个箱型桥弦杆的制作质量,保证其与桥面和箱型端梁连接的稳定性,保证其支撑性、承载性和后期使用的安全性。
技术方案:为了实现上述目的,本发明提供了一种箱型桥弦杆的制作方法,包括箱型桥弦杆的具体制作方法如下:1):箱梁壁板先在水平胎架上进行厚薄板的拼板对接,节点板、对接板中心线及连接腹杆节点中心线预先划线定位,并将加劲助和加劲板与箱梁壁板间进行组装焊接,焊后矫正合格吊上胎架进行定位,即:箱梁壁板长度方向加放1‰焊接收缩且节点板端正作,另一端加放10mm余量;纵向加劲肋长度方向加放1‰焊接收缩余量下料;箱梁壁板对应加劲助中心位置压制179.5°反变形;加劲助与箱梁壁板间为熔深焊缝;加劲板与箱梁壁板间采用熔深焊缝的方式进行焊接,采用单面40°留根2mm坡口形式,反面角焊缝加强,与加劲助间磨平顶紧;
2):安装箱体内部的横向加劲隔板,定位安装时横向加劲隔板与箱梁壁板的垂直设置,其中位于第一支座节点区域位置的3块横隔板与顶板间为单面角焊缝,其余三面为熔深焊缝,与箱梁壁板间采用双面40°留根2mm坡口形式,与底板间采用单面40°留根2mm坡口形 式,两侧横隔板底板侧坡口方向,中间一块横隔板底板侧坡口方向朝向开人孔侧;如横隔板上加劲肋槽口图纸未放大时,放样需将槽口每边放大2mm;非节点区域位置横隔板与壁板及顶板间3面为双面角焊缝形式,与底板间为磨平顶紧,施工过程中,若横隔板上加劲肋槽口图纸未放大时,放样需将槽口每边放大2mm;
3):安装另一块箱梁壁板,定位时定对节点中心线和端口企口位置线及垂直度,;
4):待上一步骤中箱梁壁板定位合格后,吊装顶板,顶板预先与加劲肋进行组装焊接,加劲肋与顶板间为熔深焊缝;顶板与壁板间节点区域为全熔透,采用内焊外清根坡口形式;其余位置为熔深焊缝,端隔板以外采用角焊缝加强。;
5):待顶板装焊合格后,将箱梁壁板外侧箱体外侧横隔板依次吊上胎架,定位安装时箱体外侧横隔板与箱梁壁板需要垂直设置,且制作过程中非节点区域箱体外侧横隔板与箱梁壁板间为熔深焊缝,非节点区域箱体外侧横隔板与顶板间为双面角焊缝;箱体外部横隔板上槽口每边加放2mm下料;
6):待箱体外侧横隔板定位合格后,将底板单元吊上胎架进行组装定位,定位时定对节点中心线和端口企口位置线及垂直度,具体焊接方式为:底板长度方向加放1‰焊接收缩且节点板端正作,另一端加放10mm余量;底板与箱梁壁板间为熔深焊缝,节点区域位置采用单面40°留根2mm坡口形式,当板厚>40mm时,采用单面30°留根2mm坡口形式;底板与箱体外部横隔板为双面角焊缝,且端口处横隔板与底板间需采用单面角焊缝形式。
7):然后装焊第一支座和一组第二支座。
本发明中所述第一支座具体制作方法如下:1):焊接支座顶板,预先制作支座顶板,并在其上焊接U型助和第一加劲助,所述U型助和第一加劲助与支座顶板间均采用双面焊缝形式焊接,支座顶板对接缝采用内焊外清根焊坡口形式,第一加劲助及小劲板与构架间均为双面角焊缝;
2):箱梁壁板上位于节点处的加劲助与箱梁壁板熔深焊缝,采用双面40°留根2mm坡口形式,且该加劲助中间无R孔;
3):装焊支座节点板,先预先装焊中间一块支座节点板,与构架间采用容身焊缝形式焊接,并采用四面双面40°留根2mm坡口形式;
4):装焊支座内横隔板,支座内横隔板与构架间均为熔深焊缝,与支座顶板间采用双面40°留根2mm坡口形式;与两侧支座壁板间采用单面40°留根2mm坡口形式,坡口朝向外侧;
5):装焊支座底板,支座底板与本体节点板间为全熔透焊接,并采用内焊外清根坡口形式,且箱梁壁板上位于节点处的加劲助与支座底板间为双面角焊缝形,支座内横隔板与支座底板间采用双面40°留根2mm坡口形式;
6):装焊剩余的支座节点板,剩余支座节点板采用退装法装焊,与构架间为熔深焊缝,采用四面单面40°留根2mm坡口形式;
7):装焊支座壁板,支座壁板与构架间均为熔深焊缝方式焊接,并采用单面30°留根2mm坡口形式,且坡口朝向外侧,支座内横隔板以外内侧采用角焊缝加强;支座壁板上槽口放大4mm下料,且U肋及长条加劲肋与支座壁板间为双面角焊缝;
8):装焊长条加劲板和小块加劲板,支座壁板外侧的长条加劲板和小块加劲板均采用熔深焊缝的形式与支座壁板焊接,采用双面40°留根2mm坡口形式,外侧小块加劲板为熔深焊缝,采用单面40°留根2mm坡口形式;支座壁板内侧的长条加劲板为熔深焊缝,采用单面40°留根2mm坡口形式,并采用退装法进行安装。
本发明中所述弦杆端梁组件具体制作方法如下:
1):装焊对接腹板,对接腹杆的加劲板根部200mm范围需全熔透,采用内焊外清根坡口形式,其余位置为熔深焊缝,当板厚≤20mm时,采用单面40°留根2mm坡口形式;当板厚>20mm时,采用双面40°留根2mm坡口形式;
2):装焊封板,封板与两节点板之间采用单面40°留2的坡口形式进行焊接,吊耳与构架间为全熔透,采用清根焊坡口形式。
本发明中所述第二支座的具体制作方法如下:
1):先对第二支座进行H型合拢,且H型合拢采用双面角焊缝焊接;
2):装焊第二支座盖板,第二支座盖板与H型合拢为熔深焊缝,采用单面40°留根2mm坡口形式焊接;
3):第二支座自身合拢完成后,第二支座与构架间均为熔深焊缝,采用单面40°留根2mm坡口形式,坡口朝向外侧;
4):对应第二支座中的小加劲板与本体及加劲肋间均为双面角焊缝。
本发明中所述箱型桥弦杆包括:底板、一组箱梁壁板、顶板、弦杆端梁组件、第一支座和一组第二支座,所述箱梁壁板相对设置,并设于底板上,所述顶板设于两箱梁壁板的上方,所述弦杆端梁组件设于顶板的上方,所述第一支座设于底板的下方,并与弦杆端梁组件反向设置,所述第二支座设于顶板上。
本发明中所述底板包括底板本体,所述底板本体的两侧对称设有下牛腿节点板,所述 下牛腿节点板与顶板的外缘板之间设有一组箱体外侧横隔板,且所述顶板的两端设有嵌补板。
本发明中所述箱梁壁板包括箱梁壁板本体,所述箱梁壁板本体的上方设有用于安装弦杆端梁组件的节点板,所述第一支座设于箱梁壁板本体的外侧,所述箱梁壁板和顶板的内壁上均设有一组加劲助,所述加劲助上设有加劲板,且两箱梁壁板之间设有一组横向加劲隔板,且所述横向加劲隔板同时与箱梁壁板和顶板的内壁上的加劲助连接;
所述横隔板包括横隔板本体,所述横隔板本体的侧边设有一组用于安装加劲助的安装槽。
本发明中所述弦杆端梁组件包括一组对接腹板和一组封板,所述对接腹板设于两节点板之间,所述封板设于两节点板之间,并与对接腹板连接,且所述封板呈圆弧状。
本发明中所述第一支座包括一组支座顶板、一组支座节点板、一组支座内隔板、支座底板和一组支座内横隔板,所述支撑顶板设于顶板的外侧,所述支座节点板相对设于底板上,所述支座内隔板设于支座节点板之间,所述支座底板设于支座节点板的底部,所述支座内横隔板垂直设于支座顶板和支座底板之间,且位于支座内横隔板的两侧设有支座壁板;
所述支座壁板的内外两侧均设有长条加劲板,且位于支座壁板外侧的长条加劲板之间还设有小块加劲板;
所述支座顶板上设有U型助和一组第一加劲助。
本发明中所述加劲板的三条边上设有安装槽,所述安装槽为人字孔槽。安装槽的设置,便于加劲助的安装,进一步优化了弦杆的结构,能够提高加劲助安装的稳定性;人字孔槽的设置,利用其结构的特殊性,提高加劲助安装的稳定性。
上述技术方案可以看出,本发明具有如下有益效果:
1、本发明所述的一种箱型桥弦杆的制作方法,通过合理的施工方法,对箱型桥弦杆进行合理的制作施工,根据不同部件安装位置的不同采用不同的焊接方式进行装焊,能够有效的提高整个箱型桥弦杆的制作质量,保证其与桥面和箱型端梁连接的稳定性,保证其支撑性、承载性和后期使用的安全性。
2、本发明中所述的箱型桥弦杆,其结构简单,设计合理,易于制作,通过在顶板上设置弦杆端梁组件,便于其与其他箱型弦杆连接,第一支座的设置,便于其与箱型端梁连接,所述第二支座的设置,便于其与桥面进行连接,实现多方向的连接,减少了其他转接件的使用,优化了弦杆的结构,缩短施工周期,让其更好的满足桥梁施工的需要。
3、本发明中所述底板包括底板本体,所述底板本体的两侧对称设有下牛腿节点板,所述下牛腿节点板与顶板的外缘板之间设有一组腹板,且所述顶板的两端设有嵌补板。所述 腹板的设置,大大的提高了底板与顶板以及侧壁板连接的稳定性,同时,还在顶板的两端设置了嵌补板,进一步提高了整个弦杆结构的稳定性。
4、本发明中所述弦杆端梁组件包括一组对接腹板和一组封板,所述对接腹板和封板的设置,能够有效的提高弦杆端梁结构的稳定性,进一步提高其连接的稳定性和后期使用的承载性和安全性。
5、本发明中所述第一支座结构稳定性,大大的提高了其与箱型端梁连接的稳定性,进一步提高整个结构的稳定性和安全性。
图1为本发明中箱型桥弦杆的制作方法的结构示意图;
图2为本发明中支座顶板的安装示意图;
图3为本发明中箱梁壁板的局部结构示意图;
图4为本发明中第一支座的安装示意图;
图5为本发明中横隔板的结构示意图;
[根据细则91更正 21.02.2022]
[根据细则91更正 21.02.2022]
[根据细则91更正 21.02.2022]
下面结合附图和具体实施例,进一步阐明本发明。
实施例
下面详细描述本发明的实施例,所述实施例的示例在附图中示出,其中自始至终相同或类似的标号表示相同或类似的元件或具有相同或类似功能的元件。下面通过参考附图描述的实施例是示例性的,旨在用于解释本发明,而不能理解为对本发明的限制。
在本发明的描述中,需要理解的是,术语“中心”、“纵向”、“横向”、“长度”、“宽度”、“厚度”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”“内”、“顺时针”、“逆时针”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。
此外,术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”的特征可以明示或者隐含地包括一个或者更多个该特征。在本发明的描述中,除非另有说明,“多个”的含 义是两个或两个以上,除非另有明确的限定。
在本发明中,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”、“固定”等术语应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本发明中的具体含义。
在本发明中,除非另有明确的规定和限定,第一特征在第二特征之“上”或之“下”可以包括第一和第二特征直接接触,也可以包括第一和第二特征不是直接接触而是通过它们之间的另外的特征接触。而且,第一特征在第二特征“之上”、“上方”和“上面”包括第一特征在第二特征正上方和斜上方,或仅仅表示第一特征水平高度高于第二特征。第一特征在第二特征“之下”、“下方”和“下面”包括第一特征在第二特征正下方和斜下方,或仅仅表示第一特征水平高度小于第二特征。
实施例1
本实施例中所述的一种箱型桥弦杆的制作方法,包括箱型桥弦杆的具体制作方法如下:
1):箱梁壁板2先在水平胎架上进行厚薄板的拼板对接,节点板、对接板中心线及连接腹杆节点中心线预先划线定位,并将加劲助23和加劲板24与箱梁壁板2间进行组装焊接,焊后矫正合格吊上胎架进行定位,即:箱梁壁板2长度方向加放1‰焊接收缩且节点板端正作,另一端加放10mm余量;纵向加劲肋长度方向加放1‰焊接收缩余量下料;箱梁壁板2对应加劲助23中心位置压制179.5°反变形;加劲助23与箱梁壁板2间为熔深焊缝;加劲板24与箱梁壁板2间采用熔深焊缝的方式进行焊接,采用单面40°留根2mm坡口形式,反面角焊缝加强,与加劲助23间磨平顶紧;
2):安装箱体内部的横向加劲隔板25,定位安装时横向加劲隔板25与箱梁壁板2的垂直设置,其中位于第一支座5节点区域位置的3块横隔板与顶板间为单面角焊缝,其余三面为熔深焊缝,与箱梁壁板2间采用双面40°留根2mm坡口形式,与底板间采用单面40°留根2mm坡口形式,两侧横隔板底板侧坡口方向,中间一块横隔板底板侧坡口方向朝向开人孔侧;如横隔板上加劲肋槽口图纸未放大时,放样需将槽口每边放大2mm;非节点区域位置横隔板与壁板及顶板间3面为双面角焊缝形式,与底板间为磨平顶紧,施工过程中,若横隔板上加劲肋槽口图纸未放大时,放样需将槽口每边放大2mm;
3):安装另一块箱梁壁板2,定位时定对节点中心线和端口企口位置线及垂直度;
4):待上一步骤中箱梁壁板2定位合格后,吊装顶板3,顶板3预先与加劲肋23进行组装 焊接,加劲肋23与顶板3间为熔深焊缝;顶板3与壁板间节点区域为全熔透CP,采用内焊外清根坡口形式;其余位置为熔深焊缝,端隔板以外采用角焊缝加强。;
5):待顶板3装焊合格后,将箱梁壁板2外侧箱体外侧横隔板13依次吊上胎架,定位安装时箱体外侧横隔板13与箱梁壁板2需要垂直设置,且制作过程中非节点区域箱体外部横隔板13与箱梁壁板2间为熔深焊缝,非节点区域箱体外部横隔板13与顶板3间为双面角焊缝;箱体外部横隔板上槽口每边加放2mm下料;
6):待箱体外侧横隔板13定位合格后,将底板1单元吊上胎架进行组装定位,定位时定对节点中心线和端口企口位置线及垂直度,具体焊接方式为:底板1长度方向加放1‰焊接收缩且节点板端正作,另一端加放10mm余量;底板1与箱梁壁板2间为熔深焊缝,节点区域位置采用单面40°留根2mm坡口形式,当板厚>40mm时,采用单面30°留根2mm坡口形式;底板1与箱体外部横隔板13为双面角焊缝,且端口处横隔板与底板1间需采用单面角焊缝形式。
7):然后装焊第一支座5和一组第二支座6。
本实施例中所述第一支座5具体制作方法如下:1):焊接支座顶板51,预先制作支座顶板51,并在其上焊接U型助511和第一加劲助512,所述U型助511和第一加劲助512与支座顶板51间均采用双面焊缝形式焊接,支座顶板51对接缝采用内焊外清根焊坡口形式,第一加劲助512及小劲板与构架间均为双面角焊缝;
2):箱梁壁板2上位于节点处的加劲助与箱梁壁板2熔深焊缝,采用双面40°留根2mm坡口形式,且该加劲助中间无R孔;
3):装焊支座节点板52,先预先装焊中间一块支座节点板52,与构架间采用容身焊缝形式焊接,并采用四面双面40°留根2mm坡口形式;
4):装焊支座内横隔板55,支座内横隔板55与构架间均为熔深焊缝,与支座顶板51间采用双面40°留根2mm坡口形式;与两侧支座壁板56间采用单面40°留根2mm坡口形式,坡口朝向外侧;
5):装焊支座底板54,支座底板54与本体节点板间为全熔透焊接,并采用内焊外清根坡口形式,且箱梁壁板2上位于节点处的加劲助与支座底板54间为双面角焊缝形,支座内横隔板55与支座底板54间采用双面40°留根2mm坡口形式;
6):装焊剩余的支座节点板52,剩余支座节点板52采用退装法装焊,与构架间为熔深焊缝,采用四面单面40°留根2mm坡口形式;
7):装焊支座壁板56,支座壁板56与构架间均为熔深焊缝方式焊接,并采用单面30°留根 2mm坡口形式,且坡口朝向外侧,支座内横隔板55以外内侧采用角焊缝加强;支座壁板56上槽口放大4mm下料,且U肋及长条加劲肋与支座壁板56间为双面角焊缝;
8):装焊长条加劲板57和小块加劲板,支座壁板56外侧的长条加劲板57和小块加劲板均采用熔深焊缝的形式与支座壁板56焊接,采用双面40°留根2mm坡口形式,外侧小块加劲板为熔深焊缝,采用单面40°留根2mm坡口形式;支座壁板56内侧的长条加劲板57为熔深焊缝,采用单面40°留根2mm坡口形式,并采用退装法进行安装。
本实施例中所述弦杆端梁组件4具体制作方法如下:
1):装焊对接腹板41,对接腹杆的加劲板根部200mm范围需全熔透CP,采用内焊外清根坡口形式,其余位置为熔深焊缝,当板厚≤20mm时,采用单面40°留根2mm坡口形式;当板厚>20mm时,采用双面40°留根2mm坡口形式;
2):装焊封板42,封板42与两节点板22之间采用单面40°留2的坡口形式进行焊接,吊耳与构架间为全熔透CP,采用清根焊坡口形式。
本实施例中所述第二支座6的具体制作方法如下:
1):先对第二支座6进行H型合拢,且H型合拢采用双面角焊缝焊接;
2):装焊第二支座盖板,第二支座盖板与H型合拢为熔深焊缝,采用单面40°留根2mm坡口形式焊接;
3):第二支座6自身合拢完成后,第二支座6与构架间均为熔深焊缝,采用单面40°留根2mm坡口形式,坡口朝向外侧;
4):对应第二支座6中的小加劲板与本体及加劲肋间均为双面角焊缝。
实施例2
如图所示的一种箱型桥弦杆的制作方法,所述箱型桥弦杆包括:底板1、一组箱梁壁板2、顶板3、弦杆端梁组件4、第一支座5和一组第二支座6,所述箱梁壁板2相对设置,并设于底板1上,所述顶板3设于两箱梁壁板2的上方,所述弦杆端梁组件4设于顶板3的上方,所述第一支座5设于底板1的下方,并与弦杆端梁组件4反向设置,所述第二支座6设于顶板3上。
本实施例中所述底板1包括底板本体11,所述底板本体11的两侧对称设有下牛腿节点板12,所述下牛腿节点板12与顶板3的外缘板之间设有一组箱体外侧横隔板13,且所述顶板3的两端设有嵌补板14。
本实施例中所述箱梁壁板2包括箱梁壁板本体21,所述箱梁壁板本体21的上方设有用于安装弦杆端梁组件4的节点板22,所述第一支座5设于箱梁壁板本体21的外侧,所述 箱梁壁板2和顶板3的内壁上均设有一组加劲助23,所述加劲助23上设有加劲板24,且两箱梁壁板2之间设有一组横向加劲隔板25,且所述横向加劲隔板25同时与箱梁壁板2和顶板3的内壁上的加劲助23连接;
所述横隔板24包括横隔板本体,所述横隔板本体的侧边设有一组用于安装加劲助23的安装槽251。
本实施例中所述弦杆端梁组件4包括一组对接腹板41和一组封板42,所述对接腹板41设于两节点板22之间,所述封板42设于两节点板22之间,并与对接腹板41连接,且所述封板42呈圆弧状。
本实施例中所述第一支座5包括一组支座顶板51、一组支座节点板52、一组支座内隔板53、支座底板54和一组支座内横隔板55,所述支撑顶板51设于顶板1的外侧,所述支座节点板52相对设于底板1上,所述支座内隔板53设于支座节点板52之间,所述支座底板54设于支座节点板52的底部,所述支座内横隔板55垂直设于支座顶板51和支座底板54之间,且位于支座内横隔板55的两侧设有支座壁板56;
所述支座壁板56的内外两侧均设有长条加劲板57,且位于支座壁板57外侧的长条加劲板57之间还设有小块加劲板;
所述支座顶板51上设有U型助511和一组第一加劲助512。
本实施例中所述加劲板24的三条边上设有安装槽241,所述安装槽241为人字孔槽。
本实施例中所述的一种箱型桥弦杆的制作方法,包括箱型桥弦杆的具体制作方法如下:1):箱梁壁板2先在水平胎架上进行厚薄板的拼板对接,节点板、对接板中心线及连接腹杆节点中心线预先划线定位,并将加劲助23和加劲板24与箱梁壁板2间进行组装焊接,焊后矫正合格吊上胎架进行定位,即:箱梁壁板2长度方向加放1‰焊接收缩且节点板端正作,另一端加放10mm余量;纵向加劲肋长度方向加放1‰焊接收缩余量下料;箱梁壁板2对应加劲助23中心位置压制179.5°反变形;加劲助23与箱梁壁板2间为熔深焊缝;加劲板24与箱梁壁板2间采用熔深焊缝的方式进行焊接,采用单面40°留根2mm坡口形式,反面角焊缝加强,与加劲助23间磨平顶紧;
2):安装箱体内部的横向加劲隔板25,定位安装时横向加劲隔板25与箱梁壁板2的垂直设置,其中位于第一支座5节点区域位置的3块横隔板与顶板间为单面角焊缝,其余三面为熔深焊缝,与箱梁壁板2间采用双面40°留根2mm坡口形式,与底板间采用单面40°留根2mm坡口形式,两侧横隔板底板侧坡口方向,中间一块横隔板底板侧坡口方向朝向开人孔 侧;如横隔板上加劲肋槽口图纸未放大时,放样需将槽口每边放大2mm;非节点区域位置横隔板与壁板及顶板间3面为双面角焊缝形式,与底板间为磨平顶紧,施工过程中,若横隔板上加劲肋槽口图纸未放大时,放样需将槽口每边放大2mm;
3):安装另一块箱梁壁板2,定位时定对节点中心线和端口企口位置线及垂直度;
4):待上一步骤中箱梁壁板2定位合格后,吊装顶板3,顶板3预先与加劲肋23进行组装焊接,加劲肋23与顶板3间为熔深焊缝;顶板3与壁板间节点区域为全熔透CP,采用内焊外清根坡口形式;其余位置为熔深焊缝,端隔板以外采用角焊缝加强。;
5):待顶板3装焊合格后,将箱梁壁板2外侧箱体外侧横隔板13依次吊上胎架,定位安装时箱体外侧横隔板13与箱梁壁板2需要垂直设置,且制作过程中非节点区域箱体外部横隔板13与箱梁壁板2间为熔深焊缝,非节点区域箱体外部横隔板13与顶板3间为双面角焊缝;箱体外部横隔板上槽口每边加放2mm下料;
6):待箱体外侧横隔板13定位合格后,将底板1单元吊上胎架进行组装定位,定位时定对节点中心线和端口企口位置线及垂直度,具体焊接方式为:底板1长度方向加放1‰焊接收缩且节点板端正作,另一端加放10mm余量;底板1与箱梁壁板2间为熔深焊缝,节点区域位置采用单面40°留根2mm坡口形式,当板厚>40mm时,采用单面30°留根2mm坡口形式;底板1与箱体外部横隔板13为双面角焊缝,且端口处横隔板与底板1间需采用单面角焊缝形式。
7):然后装焊第一支座5和一组第二支座6。
本实施例中所述第一支座5具体制作方法如下:1):焊接支座顶板51,预先制作支座顶板51,并在其上焊接U型助511和第一加劲助512,所述U型助511和第一加劲助512与支座顶板51间均采用双面焊缝形式焊接,支座顶板51对接缝采用内焊外清根焊坡口形式,第一加劲助512及小劲板与构架间均为双面角焊缝;
2):箱梁壁板2上位于节点处的加劲助与箱梁壁板2熔深焊缝,采用双面40°留根2mm坡口形式,且该加劲助中间无R孔;
3):装焊支座节点板52,先预先装焊中间一块支座节点板52,与构架间采用容身焊缝形式焊接,并采用四面双面40°留根2mm坡口形式;
4):装焊支座内横隔板55,支座内横隔板55与构架间均为熔深焊缝,与支座顶板51间采用双面40°留根2mm坡口形式;与两侧支座壁板56间采用单面40°留根2mm坡口形式,坡口朝向外侧;
5):装焊支座底板54,支座底板54与本体节点板间为全熔透焊接,并采用内焊外清根坡口 形式,且箱梁壁板2上位于节点处的加劲助与支座底板54间为双面角焊缝形,支座内横隔板55与支座底板54间采用双面40°留根2mm坡口形式;
6):装焊剩余的支座节点板52,剩余支座节点板52采用退装法装焊,与构架间为熔深焊缝,采用四面单面40°留根2mm坡口形式;
7):装焊支座壁板56,支座壁板56与构架间均为熔深焊缝方式焊接,并采用单面30°留根2mm坡口形式,且坡口朝向外侧,支座内横隔板55以外内侧采用角焊缝加强;支座壁板56上槽口放大4mm下料,且U肋及长条加劲肋与支座壁板56间为双面角焊缝;
8):装焊长条加劲板57和小块加劲板,支座壁板56外侧的长条加劲板57和小块加劲板均采用熔深焊缝的形式与支座壁板56焊接,采用双面40°留根2mm坡口形式,外侧小块加劲板为熔深焊缝,采用单面40°留根2mm坡口形式;支座壁板56内侧的长条加劲板57为熔深焊缝,采用单面40°留根2mm坡口形式,并采用退装法进行安装。
本实施例中所述弦杆端梁组件4具体制作方法如下:
1):装焊对接腹板41,对接腹杆的加劲板根部200mm范围需全熔透CP,采用内焊外清根坡口形式,其余位置为熔深焊缝,当板厚≤20mm时,采用单面40°留根2mm坡口形式;当板厚>20mm时,采用双面40°留根2mm坡口形式;
2):装焊封板42,封板42与两节点板22之间采用单面40°留2的坡口形式进行焊接,吊耳与构架间为全熔透CP,采用清根焊坡口形式。
本实施例中所述第二支座6的具体制作方法如下:
1):先对第二支座6进行H型合拢,且H型合拢采用双面角焊缝焊接;
2):装焊第二支座盖板,第二支座盖板与H型合拢为熔深焊缝,采用单面40°留根2mm坡口形式焊接;
3):第二支座6自身合拢完成后,第二支座6与构架间均为熔深焊缝,采用单面40°留根2mm坡口形式,坡口朝向外侧;
4):对应第二支座6中的小加劲板与本体及加劲肋间均为双面角焊缝。
本实施例中所述的一种箱型桥弦杆的制作方法,其加工后的箱型桥弦杆与桥面间对接方式如下:
A、桥面顶板与下弦杆顶板间对接为陶瓷垫板焊,坡口为40°留2间隙6mm(两侧均分),坡口朝向上;
B、桥面横向T肋腹板与箱体外侧横隔板13间对接为陶瓷垫板焊,坡口为40°留2间隙6mm(两侧均分),坡口朝向桥梁长度方向中心;
C、桥面横向T肋下面板与下弦牛腿节点板间对接为陶瓷垫板焊,坡口为40°留2间隙6mm(两侧均分),坡口朝向上。
本实施例中所述的一种箱型桥弦杆的制作方法,其加工后的箱型桥弦杆中的箱形端梁与下弦端桁架间对接方式如下:
A、下弦端梁箱形牛腿腹板与箱形端梁腹板间对接为陶瓷垫板焊,坡口为40°留2间隙6mm(两侧均分),坡口朝向外侧;
B、箱形牛腿底板与箱形端梁中的支座底板54间对接为陶瓷垫板焊,坡口为40°留2间隙6mm(两侧均分),坡口朝向箱体内部;
C、箱形牛腿顶板与箱形端梁中的支座顶板51间对接为陶瓷垫板焊,坡口为40°留2间隙6mm(两侧均分),坡口朝向上。
本实施例中箱型桥弦杆间对接方式如下:
A、腹板对接为陶瓷垫板焊,坡口为40°留2间隙6mm(两侧均分),坡口朝向箱体外侧;
B、底板对接为陶瓷垫板焊,坡口为40°留2间隙6mm(两侧均分),坡口朝向箱体内部;
C、顶板对接为陶瓷垫板焊,坡口为40°留2间隙6mm(两侧均分),坡口朝向上;
D、洞口嵌补段四周均为陶瓷垫板焊,坡口为40°留2间隙6mm(两侧均分),坡口朝向上;
E、腹板上加劲肋嵌补段均为陶瓷垫板焊,坡口为40°留2间隙6mm(两侧均分),坡口朝向上。
以上所述仅是本发明的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以做出若干改进,这些改进也应视为本发明的保护范围。
Claims (10)
- 一种箱型桥弦杆的制作方法,其特征在于:包括箱型桥弦杆的具体制作方法如下:1):箱梁壁板(2)先在水平胎架上进行厚薄板的拼板对接,节点板、对接板中心线及连接腹杆节点中心线预先划线定位,并将加劲助(23)和加劲板(24)与箱梁壁板(2)间进行组装焊接,焊后矫正合格吊上胎架进行定位,即:箱梁壁板(2)长度方向加放1‰焊接收缩且节点板端正作,另一端加放10mm余量;纵向加劲肋长度方向加放1‰焊接收缩余量下料;箱梁壁板(2)对应加劲助(23)中心位置压制179.5°反变形;加劲助(23)与箱梁壁板(2)间为熔深焊缝;加劲板(24)与箱梁壁板(2)间采用熔深焊缝的方式进行焊接,采用单面40°留根2mm坡口形式,反面角焊缝加强,与加劲助(23)间磨平顶紧;2):安装箱体内部的横向加劲隔板(25),定位安装时横向加劲隔板(25)与箱梁壁板(2)的垂直设置,其中位于第一支座(5)节点区域位置的3块横隔板与顶板间为单面角焊缝,其余三面为熔深焊缝,与箱梁壁板(2)间采用双面40°留根2mm坡口形式,与底板间采用单面40°留根2mm坡口形式,两侧横隔板底板侧坡口方向,中间一块横隔板底板侧坡口方向朝向开人孔侧;如横隔板上加劲肋槽口图纸未放大时,放样需将槽口每边放大2mm;非节点区域位置横隔板与壁板及顶板间3面为双面角焊缝形式,与底板间为磨平顶紧,施工过程中,若横隔板上加劲肋槽口图纸未放大时,放样需将槽口每边放大2mm;3):安装另一块箱梁壁板(2),定位时定对节点中心线和端口企口位置线及垂直度,;4):待上一步骤中箱梁壁板(2)定位合格后,吊装顶板(3),顶板(3)预先与加劲肋(23)进行组装焊接,加劲肋(23)与顶板(3)间为熔深焊缝;顶板(3)与壁板间节点区域为全熔透(CP),采用内焊外清根坡口形式;其余位置为熔深焊缝,端隔板以外采用角焊缝加强;5):待顶板(3)装焊合格后,将箱梁壁板(2)外侧箱体外侧横隔板(13)依次吊上胎架,定位安装时箱体外侧横隔板(13)与箱梁壁板(2)需要垂直设置,且制作过程中非节点区域箱体外侧横隔板与箱梁壁板(2)间为熔深焊缝,非节点区域箱体外侧横隔板与顶板(3)间为双面角焊缝;箱体外部横隔板上槽口每边加放2mm下料;6):待箱体外侧横隔板(13)定位合格后,将底板(1)单元吊上胎架进行组装定位,定位时定对节点中心线和端口企口位置线及垂直度,具体焊接方式为:底板(1)长度方向加放1‰焊接收缩且节点板端正作,另一端加放10mm余量;底板(1)与箱梁壁板(2)间为熔深焊缝,节点区域位置采用单面40°留根2mm坡口形式,当板厚>40mm时,采用单面30°留根2mm坡口形式;底板(1)与箱体外部横隔板(13)为双面角焊缝,且端口处横隔板与底板(1)间需采用单面角焊缝形式;7):然后装焊第一支座(5)和一组第二支座(6)。
- 根据权利要求1所述的箱型桥弦杆的制作方法,其特征在于:所述第一支座(5)具体制作方法如下:1):焊接支座顶板(51),预先制作支座顶板(51),并在其上焊接U型助(511)和第一加劲助(512),所述U型助(511)和第一加劲助(512)与支座顶板(51)间均采用双面焊缝形式焊接,支座顶板(51)对接缝采用内焊外清根焊坡口形式,第一加劲助(512)及小劲板与构架间均为双面角焊缝;2):箱梁壁板(2)上位于节点处的加劲助与箱梁壁板(2)熔深焊缝,采用双面40°留根2mm坡口形式,且该加劲助中间无R孔;3):装焊支座节点板(52),先预先装焊中间一块支座节点板(52),与构架间采用容身焊缝形式焊接,并采用四面双面40°留根2mm坡口形式;4):装焊支座内横隔板(55),支座内横隔板(55)与构架间均为熔深焊缝,与支座顶板(51)间采用双面40°留根2mm坡口形式;与两侧支座壁板(56)间采用单面40°留根2mm坡口形式,坡口朝向外侧;5):装焊支座底板(54),支座底板(54)与本体节点板间为全熔透焊接,并采用内焊外清根坡口形式,且箱梁壁板(2)上位于节点处的加劲助与支座底板(54)间为双面角焊缝形,支座内横隔板(55)与支座底板(54)间采用双面40°留根2mm坡口形式;6):装焊剩余的支座节点板(52),剩余支座节点板(52)采用退装法装焊,与构架间为熔深焊缝,采用四面单面40°留根2mm坡口形式;7):装焊支座壁板(56),支座壁板(56)与构架间均为熔深焊缝方式焊接,并采用单面30°留根2mm坡口形式,且坡口朝向外侧,支座内横隔板(55)以外内侧采用角焊缝加强;支座壁板(56)上槽口放大4mm下料,且U肋及长条加劲肋与支座壁板(56)间为双面角焊缝;8):装焊长条加劲板(57)和小块加劲板,支座壁板(56)外侧的长条加劲板(57)和小块加劲板均采用熔深焊缝的形式与支座壁板(56)焊接,采用双面40°留根2mm坡口形式,外侧小块加劲板为熔深焊缝,采用单面40°留根2mm坡口形式;支座壁板(56)内侧的长条加劲板(57)为熔深焊缝,采用单面40°留根2mm坡口形式,并采用退装法进行安装。
- 根据权利要求1所述的箱型桥弦杆的制作方法,其特征在于:所述弦杆端梁组件(4)具体制作方法如下:1):装焊对接腹板(41),对接腹杆的加劲板根部200mm范围需全熔透(CP),采用内焊外清根坡口形式,其余位置为熔深焊缝,当板厚≤20mm时,采用单面40°留根2mm坡口形 式;当板厚>20mm时,采用双面40°留根2mm坡口形式;2):装焊封板(42),封板(42)与两节点板(22)之间采用单面40°留2的坡口形式进行焊接,吊耳与构架间为全熔透(CP),采用清根焊坡口形式。
- 根据权利要求1所述的箱型桥弦杆的制作方法,其特征在于:所述第二支座(6)的具体制作方法如下:1):先对第二支座(6)进行H型合拢,且H型合拢采用双面角焊缝焊接;2):装焊第二支座盖板,第二支座盖板与H型合拢为熔深焊缝,采用单面40°留根2mm坡口形式焊接;3):第二支座(6)自身合拢完成后,第二支座(6)与构架间均为熔深焊缝,采用单面40°留根2mm坡口形式,坡口朝向外侧;4):对应第二支座(6)中的小加劲板与本体及加劲肋间均为双面角焊缝。
- 根据权利要求1所述的箱型桥弦杆的制作方法,其特征在于:所述箱型桥弦杆包括:底板(1)、一组箱梁壁板(2)、顶板(3)、弦杆端梁组件(4)、第一支座(5)和一组第二支座(6),所述箱梁壁板(2)相对设置,并设于底板(1)上,所述顶板(3)设于两箱梁壁板(2)的上方,所述弦杆端梁组件(4)设于顶板(3)的上方,所述第一支座(5)设于底板(1)的下方,并与弦杆端梁组件(4)反向设置,所述第二支座(6)设于顶板(3)上。
- 根据权利要求5所述的箱型桥弦杆的制作方法,其特征在于:所述底板(1)包括底板本体(11),所述底板本体(11)的两侧对称设有下牛腿节点板(12),所述下牛腿节点板(12)与顶板(3)的外缘板之间设有一组箱体外侧横隔板(13),且所述顶板(3)的两端设有嵌补板(14)。
- 根据权利要求5所述的箱型桥弦杆的制作方法,其特征在于:所述箱梁壁板(2)包括箱梁壁板本体(21),所述箱梁壁板本体(21)的上方设有用于安装弦杆端梁组件(4)的节点板(22),所述第一支座(5)设于箱梁壁板本体(21)的外侧,所述箱梁壁板(2)和顶板(3)的内壁上均设有一组加劲助(23),所述加劲助(23)上设有加劲板(24),且两箱梁壁板(2)之间设有一组横向加劲隔板(25),且所述横向加劲隔板(25)同时与箱梁壁板(2)和顶板(3)的内壁上的加劲助(23)连接;所述横隔板(24)包括横隔板本体,所述横隔板本体的侧边设有一组用于安装加劲助(23)的安装槽(251)。
- 根据权利要求5所述的箱型桥弦杆的制作方法,其特征在于:所述弦杆端梁组件(4)包括一组对接腹板(41)和一组封板(42),所述对接腹板(41)设于两节点板(22)之间, 所述封板(42)设于两节点板(22)之间,并与对接腹板(41)连接,且所述封板(42)呈圆弧状。
- 根据权利要求5所述的箱型桥弦杆的制作方法,其特征在于:所述第一支座(5)包括一组支座顶板(51)、一组支座节点板(52)、一组支座内隔板(53)、支座底板(54)和一组支座内横隔板(55),所述支撑顶板(51)设于顶板(1)的外侧,所述支座节点板(52)相对设于底板(1)上,所述支座内隔板(53)设于支座节点板(52)之间,所述支座底板(54)设于支座节点板(52)的底部,所述支座内横隔板(55)垂直设于支座顶板(51)和支座底板(54)之间,且位于支座内横隔板(55)的两侧设有支座壁板(56);所述支座壁板(56)的内外两侧均设有长条加劲板(57),且位于支座壁板(57)外侧的长条加劲板(57)之间还设有小块加劲板;所述支座顶板(51)上设有U型助(511)和一组第一加劲助(512)。
- 根据权利要求8所述的箱型桥弦杆的制作方法,其特征在于:所述加劲板(24)的三条边上设有安装槽(241),所述安装槽(241)为人字孔槽。
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111210251.9 | 2021-10-18 | ||
CN202111210251.9A CN114131227A (zh) | 2021-10-18 | 2021-10-18 | 一种箱型桥弦杆的制作方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2023065454A1 true WO2023065454A1 (zh) | 2023-04-27 |
Family
ID=80394304
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/CN2021/132147 WO2023065454A1 (zh) | 2021-10-18 | 2021-11-22 | 一种箱型桥弦杆的制作方法 |
Country Status (2)
Country | Link |
---|---|
CN (1) | CN114131227A (zh) |
WO (1) | WO2023065454A1 (zh) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102966033A (zh) * | 2012-12-12 | 2013-03-13 | 中铁山桥集团有限公司 | 全焊铁路连续钢桁梁多节点弦杆及制造方法 |
CN105729063A (zh) * | 2016-02-26 | 2016-07-06 | 江苏中铁山桥重工有限公司 | 一种双锚箱式体外节点弦杆制作方法 |
CN109208486A (zh) * | 2018-10-19 | 2019-01-15 | 江苏京沪重工有限公司 | 一种钢桥梁顶板之间嵌补分段制造工艺 |
CN111136424A (zh) * | 2019-12-24 | 2020-05-12 | 江苏中铁山桥重工有限公司 | 一种大型多封闭结构支座弦杆的制造方法 |
JP2021004475A (ja) * | 2019-06-26 | 2021-01-14 | 株式会社三井E&S鉄構エンジニアリング | 溶接方法、およびトラス橋の支点補強方法 |
CN112605620A (zh) * | 2020-12-31 | 2021-04-06 | 江苏京沪重工有限公司 | 一种带竖杆的华伦形桁架上弦杆加工方法 |
-
2021
- 2021-10-18 CN CN202111210251.9A patent/CN114131227A/zh active Pending
- 2021-11-22 WO PCT/CN2021/132147 patent/WO2023065454A1/zh active Application Filing
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102966033A (zh) * | 2012-12-12 | 2013-03-13 | 中铁山桥集团有限公司 | 全焊铁路连续钢桁梁多节点弦杆及制造方法 |
CN105729063A (zh) * | 2016-02-26 | 2016-07-06 | 江苏中铁山桥重工有限公司 | 一种双锚箱式体外节点弦杆制作方法 |
CN109208486A (zh) * | 2018-10-19 | 2019-01-15 | 江苏京沪重工有限公司 | 一种钢桥梁顶板之间嵌补分段制造工艺 |
JP2021004475A (ja) * | 2019-06-26 | 2021-01-14 | 株式会社三井E&S鉄構エンジニアリング | 溶接方法、およびトラス橋の支点補強方法 |
CN111136424A (zh) * | 2019-12-24 | 2020-05-12 | 江苏中铁山桥重工有限公司 | 一种大型多封闭结构支座弦杆的制造方法 |
CN112605620A (zh) * | 2020-12-31 | 2021-04-06 | 江苏京沪重工有限公司 | 一种带竖杆的华伦形桁架上弦杆加工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN114131227A (zh) | 2022-03-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2022142764A1 (zh) | 一种十字箱型转圆管内十字支撑节点及其制作方法 | |
WO2023024281A1 (zh) | 一种内部多道加劲圆管转接目字结构支撑节点及制作工艺 | |
CN112692508A (zh) | 一种十字转圆管型钢柱及其工作方法 | |
CN111877402B (zh) | 一种沉管隧道管节的建造方法 | |
CN114150770B (zh) | 一种内嵌十字型圆管吊柱节点构件及其制作方法 | |
WO2023024282A1 (zh) | 一种弧型墙板型支撑节点及其制作工艺 | |
WO2023065454A1 (zh) | 一种箱型桥弦杆的制作方法 | |
CN113565259B (zh) | 一种圆弧悬挑观景平台钢箱梁悬挑段加工工艺 | |
CN113789909A (zh) | 一种超大跨鱼腹式屋盖桁架的施工工艺 | |
CN111136424B (zh) | 一种大型多封闭结构支座弦杆的制造方法 | |
WO2023019781A1 (zh) | 一种基于复杂墩梁的稳定式桥塔墩及其制作工艺 | |
WO2023035412A1 (zh) | 一种异形双层塔桥结构及制作方法 | |
WO2023093115A1 (zh) | 一种用于逆作法一桩一柱的连接结构及其施工方法 | |
CN114396121A (zh) | 一种超厚板异形箱型组合拉索节点及其制作方法 | |
CN212670855U (zh) | 一种装配式建筑节点连接结构 | |
CN112605620B (zh) | 一种带竖杆的华伦形桁架上弦杆加工方法 | |
CN114182811A (zh) | 一种复杂箱形与十字形柱组合结构及其制作方法 | |
CN114250908B (zh) | 一种超大截面箱体内部纵横向隔板及其制作方法 | |
CN217027470U (zh) | 一种异形箱型组合拉索节点 | |
CN216156373U (zh) | 一种大跨度超重钢箱梁定位安装结构 | |
CN220978555U (zh) | 一种箱形截面钢构件 | |
CN220686837U (zh) | 一种既有空间桁架结构平面外新增悬挑平台的连接结构 | |
CN115559556B (zh) | 超高层建筑改造时a字柱与新增斜外框柱的对接施工方法 | |
CN216427966U (zh) | 一种装配式钢结构栈桥 | |
CN217557845U (zh) | 一种装配式水池用预制壁板及其拼缝结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 21961193 Country of ref document: EP Kind code of ref document: A1 |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 21961193 Country of ref document: EP Kind code of ref document: A1 |