WO2023016034A1 - Pile end bottom grouting apparatus, cast-in-place pile and construction method therefor - Google Patents
Pile end bottom grouting apparatus, cast-in-place pile and construction method therefor Download PDFInfo
- Publication number
- WO2023016034A1 WO2023016034A1 PCT/CN2022/094671 CN2022094671W WO2023016034A1 WO 2023016034 A1 WO2023016034 A1 WO 2023016034A1 CN 2022094671 W CN2022094671 W CN 2022094671W WO 2023016034 A1 WO2023016034 A1 WO 2023016034A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- grout
- storage bag
- pile
- grouting
- pipe
- Prior art date
Links
- 238000010276 construction Methods 0.000 title claims abstract description 21
- 238000003860 storage Methods 0.000 claims abstract description 127
- 239000011440 grout Substances 0.000 claims abstract description 111
- 239000002002 slurry Substances 0.000 claims description 104
- 239000002390 adhesive tape Substances 0.000 claims description 14
- 239000002689 soil Substances 0.000 claims description 14
- 230000002787 reinforcement Effects 0.000 claims description 11
- 238000007789 sealing Methods 0.000 claims description 11
- 238000004891 communication Methods 0.000 claims description 10
- 238000001514 detection method Methods 0.000 claims description 8
- 239000013049 sediment Substances 0.000 claims description 8
- 239000000126 substance Substances 0.000 claims description 6
- 239000002985 plastic film Substances 0.000 claims description 4
- 229920006255 plastic film Polymers 0.000 claims description 4
- 230000001681 protective effect Effects 0.000 claims description 4
- 229920002994 synthetic fiber Polymers 0.000 claims description 4
- 239000012209 synthetic fiber Substances 0.000 claims description 4
- 230000000903 blocking effect Effects 0.000 claims description 3
- 239000004744 fabric Substances 0.000 claims description 3
- 238000004140 cleaning Methods 0.000 claims description 2
- 230000007547 defect Effects 0.000 abstract description 2
- 230000000694 effects Effects 0.000 description 21
- 239000002775 capsule Substances 0.000 description 10
- 239000000243 solution Substances 0.000 description 9
- 238000000034 method Methods 0.000 description 7
- 230000006872 improvement Effects 0.000 description 6
- 239000004033 plastic Substances 0.000 description 6
- 229920003023 plastic Polymers 0.000 description 6
- VYPSYNLAJGMNEJ-UHFFFAOYSA-N Silicium dioxide Chemical compound O=[Si]=O VYPSYNLAJGMNEJ-UHFFFAOYSA-N 0.000 description 5
- 238000011065 in-situ storage Methods 0.000 description 5
- 239000000463 material Substances 0.000 description 5
- 239000000741 silica gel Substances 0.000 description 5
- 229910002027 silica gel Inorganic materials 0.000 description 5
- 238000010586 diagram Methods 0.000 description 4
- 229910052751 metal Inorganic materials 0.000 description 4
- 239000002184 metal Substances 0.000 description 4
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 4
- 239000010410 layer Substances 0.000 description 3
- 238000009958 sewing Methods 0.000 description 3
- 238000010146 3D printing Methods 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 2
- 230000009471 action Effects 0.000 description 2
- 239000013013 elastic material Substances 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000003292 glue Substances 0.000 description 2
- -1 polyethylene Polymers 0.000 description 2
- 230000008569 process Effects 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 238000009941 weaving Methods 0.000 description 2
- 229920002972 Acrylic fiber Polymers 0.000 description 1
- 239000004677 Nylon Substances 0.000 description 1
- 239000004698 Polyethylene Substances 0.000 description 1
- 239000004743 Polypropylene Substances 0.000 description 1
- 239000000853 adhesive Substances 0.000 description 1
- 230000001070 adhesive effect Effects 0.000 description 1
- 229910052782 aluminium Inorganic materials 0.000 description 1
- XAGFODPZIPBFFR-UHFFFAOYSA-N aluminium Chemical compound [Al] XAGFODPZIPBFFR-UHFFFAOYSA-N 0.000 description 1
- 230000004888 barrier function Effects 0.000 description 1
- 238000007664 blowing Methods 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 230000008602 contraction Effects 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 239000011888 foil Substances 0.000 description 1
- 238000001746 injection moulding Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000003754 machining Methods 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 229920001778 nylon Polymers 0.000 description 1
- 229920000728 polyester Polymers 0.000 description 1
- 229920000573 polyethylene Polymers 0.000 description 1
- 229920001155 polypropylene Polymers 0.000 description 1
- 229920000915 polyvinyl chloride Polymers 0.000 description 1
- 239000004800 polyvinyl chloride Substances 0.000 description 1
- 238000004537 pulping Methods 0.000 description 1
- 238000009991 scouring Methods 0.000 description 1
- 238000005204 segregation Methods 0.000 description 1
- 239000002356 single layer Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/62—Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
- E02D15/04—Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
Claims (16)
- 一种桩端底部注浆装置,包括:A pile end bottom grouting device, comprising:固定板(1);fixed plate (1);其特征在于,还包括:It is characterized in that it also includes:储浆袋(2),固定在所述固定板(1)上,所述储浆袋(2)形成适于容置浆液的容置腔或所述储浆袋(2)与所述固定板(1)围成适于容置浆液的容置腔,所述储浆袋(2)具有内部填充浆液以承载桩体的充盈状态和内部中空的收拢状态,所述储浆袋(2)预设固定的极限承压强度值且在充盈状态下容积固定。A slurry storage bag (2), fixed on the fixed plate (1), the slurry storage bag (2) forms an accommodating cavity suitable for accommodating slurry or the slurry storage bag (2) and the fixed plate (1) Enclosing an accommodating cavity suitable for accommodating grout, the grout storage bag (2) has a filling state in which the grout is filled inside to carry the pile body and a collapsed state in which the inside is hollow, and the grout storage bag (2) is prefabricated A fixed ultimate compressive strength value is set and the volume is fixed in the filling state.
- 根据权利要求1所述的桩端底部注浆装置,其特征在于,所述储浆袋(2)由化学合成纤维布料或塑料薄膜制成。The pile end bottom grouting device according to claim 1, characterized in that, the grout storage bag (2) is made of chemical synthetic fiber cloth or plastic film.
- 根据权利要求1或2所述的桩端底部注浆装置,其特征在于,所述储浆袋(2)上设有薄弱区域,所述薄弱区域的承压强度小于所述储浆袋(2)其他部位的承压强度以在受压时形成出浆区域。The pile end bottom grouting device according to claim 1 or 2, characterized in that, the slurry storage bag (2) is provided with a weak area, and the pressure bearing strength of the weak area is smaller than that of the slurry storage bag (2). ) the bearing strength of other parts to form a slurry area when under pressure.
- 根据权利要求1所述的桩端底部注浆装置,其特征在于,还包括:The pile end bottom grouting device according to claim 1, further comprising:注浆管(3),与所述储浆袋(2)的内腔相连通,适于向所述储浆袋(2)内注浆;The grouting pipe (3) communicates with the inner cavity of the grout storage bag (2), and is suitable for grouting into the grout storage bag (2);第一单向阀(4),设于所述注浆管(3)与所述储浆袋(2)的连通位置,适于阻挡所述储浆袋(2)内的堵塞物进入所述注浆管(3)。The first one-way valve (4) is located at the communication position between the grouting pipe (3) and the grout storage bag (2), and is suitable for blocking the blockage in the grout storage bag (2) from entering the Grouting pipe (3).
- 根据权利要求4所述的桩端底部注浆装置,其特征在于,所述注浆管(3)的管壁上开设有第一出浆孔(311),所述第一单向阀(4)包括:The pile end bottom grouting device according to claim 4, characterized in that, a first grout hole (311) is opened on the pipe wall of the grouting pipe (3), and the first one-way valve (4 )include:第一止水胶带(41),缠绕于所述注浆管(3)开设有第一出浆孔(311)的 部位;The first water-stop adhesive tape (41), wound around the position where the grouting pipe (3) is provided with the first grouting hole (311);第一胶套(42),直接或间接套于所述第一止水胶带(41)外侧;The first rubber sleeve (42) is directly or indirectly placed on the outside of the first waterproof tape (41);所述第一止水胶带(41)和所述第一胶套(42)具有向靠近所述注浆管(3)方向收紧的密封状态,以及受所述注浆管(3)内压力作用与所述注浆管(3)形成间隙的打开状态;The first water-stop tape (41) and the first rubber sleeve (42) have a tight sealing state towards the grouting pipe (3), and are subject to the internal pressure of the grouting pipe (3). Acting in an open state forming a gap with the grouting pipe (3);第一硬质片(43),夹于所述第一止水胶带(41)与所述第一胶套(42)之间,且对应所述第一出浆孔(311)设置。The first hard sheet (43) is sandwiched between the first waterproof adhesive tape (41) and the first rubber sleeve (42), and is arranged corresponding to the first pulp outlet hole (311).
- 根据权利要求4或5所述的桩端底部注浆装置,其特征在于,所述注浆管(3)包括:The pile end bottom grouting device according to claim 4 or 5, wherein the grouting pipe (3) comprises:第一出浆部(31),位于所述储浆袋(2)内腔中;The first pulp outlet (31) is located in the inner cavity of the pulp storage bag (2);接口(32),穿过所述固定板(1)且与所述第一出浆部(31)连通;An interface (32), which passes through the fixed plate (1) and communicates with the first slurry outlet (31);进浆管(33),与所述接口(32)密封连通。The slurry feeding pipe (33) is in sealing communication with the interface (32).
- 根据权利要求1所述的桩端底部注浆装置,其特征在于,所述固定板(1)为环形板,所述储浆袋(2)为与所述环形板适配的环形结构。The pile end bottom grouting device according to claim 1, characterized in that, the fixing plate (1) is an annular plate, and the slurry storage bag (2) is an annular structure adapted to the annular plate.
- 根据权利要求7所述的桩端底部注浆装置,其特征在于,所述固定板(1)的内环边缘设有延伸至所述储浆袋(2)内环的环形挡件(5)。The pile end bottom grouting device according to claim 7, characterized in that, the inner ring edge of the fixing plate (1) is provided with an annular stopper (5) extending to the inner ring of the slurry storage bag (2) .
- 根据权利要求8所述的桩端底部注浆装置,其特征在于,还包括:The pile end bottom grouting device according to claim 8, further comprising:补浆管(6),与所述环形挡件(5)内部区域相连通,适于向桩孔内注浆;The grout filling pipe (6) communicates with the inner area of the annular stopper (5), and is suitable for grouting into the pile hole;第二单向阀(7),设于所述补浆管(6)与所述环形挡件(5)内部区域的连通位置,适于阻挡所述桩孔内的堵塞物进入所述补浆管(6)。The second one-way valve (7) is located at the communication position between the grout replenishing pipe (6) and the inner area of the annular stopper (5), and is suitable for blocking the blockage in the pile hole from entering the grout replenishment Tube (6).
- 根据权利要求9所述的桩端底部注浆装置,其特征在于,所述补浆管(6)的管壁上开设有第二出浆孔(611),所述第二单向阀(7)包括:The pile end bottom grouting device according to claim 9, characterized in that, a second grout hole (611) is opened on the pipe wall of the grout filling pipe (6), and the second one-way valve (7 )include:第二止水胶带(71),缠绕于所述补浆管(6)开设有第二出浆孔(611)的部位;The second water-stop adhesive tape (71) is wound around the position where the second grout hole (611) is opened in the grout filling pipe (6);第二胶套(72),直接或间接套于所述第二止水胶带(71)外侧;The second rubber sleeve (72) is directly or indirectly placed on the outside of the second waterproof tape (71);所述第二止水胶带(71)和第二胶套(72)皆具有向靠近所述补浆管(6)方向收紧的密封状态,以及受所述补浆管(6)内压力作用与所述补浆管(6)形成间隙的打开状态;Both the second water-stop tape (71) and the second rubber sleeve (72) have a sealing state that is tightened toward the direction of the grout replenishing pipe (6), and are affected by the internal pressure of the grout replenishing pipe (6). An open state that forms a gap with the grout filling pipe (6);第二硬质片(73),夹于所述第二止水胶带(71)与所述第二胶套(72)之间,且对应所述第二出浆孔(611)设置。The second hard sheet (73) is sandwiched between the second waterproof adhesive tape (71) and the second rubber sleeve (72), and is arranged corresponding to the second slurry outlet hole (611).
- 根据权利要求9或10所述的桩端底部注浆装置,其特征在于,所述补浆管(6)具有延伸至所述环形挡件(5)内部区域的第二出浆部(61),所述第二出浆部(61)为沿所述环形挡件(5)内壁延伸的环形管路。The pile end bottom grouting device according to claim 9 or 10, characterized in that, the grout filling pipe (6) has a second grout outlet (61) extending to the inner area of the annular stopper (5) , the second slurry outlet (61) is an annular pipeline extending along the inner wall of the annular stopper (5).
- 根据权利要求1所述的桩端底部注浆装置,其特征在于,所述固定板(1)上设有检测口(21),所述检测口(21)适于向所述储浆袋(2)内充入介质。The pile end bottom grouting device according to claim 1, characterized in that, the fixed plate (1) is provided with a detection port (21), and the detection port (21) is suitable for feeding to the slurry storage bag ( 2) filled with medium.
- 根据权利要求1所述的桩端底部注浆装置,其特征在于,还包括:The pile end bottom grouting device according to claim 1, further comprising:保护罩,与所述固定板(1)可拆卸连接,且适于在施工前罩设在所述储浆袋(2)的外侧。The protective cover is detachably connected with the fixing plate (1), and is suitable for covering the outside of the slurry storage bag (2) before construction.
- 一种灌注桩,其特征在于,包括:A cast-in-place pile, characterized in that it comprises:权利要求1至13中任一项所述的桩端底部注浆装置;The pile end bottom grouting device according to any one of claims 1 to 13;钢筋笼(8),与所述桩端底部注浆装置的固定板(1)相连。The reinforcement cage (8) is connected with the fixed plate (1) of the grouting device at the bottom of the pile end.
- 一种权利要求14所述的灌注桩的施工方法,其特征在于,依次包括如下步骤:A construction method for cast-in-place piles according to claim 14, characterized in that, comprising the steps in turn:S1.形成桩孔,对所述桩孔内的沉渣进行清理;S1. forming a pile hole, and cleaning the sediment in the pile hole;S2.将下端安装有所述桩端底部注浆装置的钢筋笼(8)下沉至所述桩孔的底部;S2. sinking the reinforcement cage (8) with the grouting device at the bottom of the pile end installed at the lower end to the bottom of the pile hole;S3.向所述桩孔内灌注混凝土,以形成灌注桩;S3. Pouring concrete into the pile hole to form a cast-in-place pile;S4.向所述储浆袋(2)内注浆,形成桩底扩大头。S4. Injecting grout into the grout storage bag (2) to form a pile bottom expansion head.
- 根据权利要求15所述的施工方法,其特征在于,在步骤S4中,根据形成桩孔的土壤性质进行控制:若为砂性土,控制实际注浆量和注浆压力皆大于所述储浆袋(2)的预设值,以使储浆袋(2)破裂;若为黏性土,控制实际注浆量和注浆压力小于所述储浆袋(2)的预设值,避免储浆袋(2)破裂。The construction method according to claim 15, characterized in that, in step S4, control is performed according to the properties of the soil forming the pile hole: if it is sandy soil, control the actual grouting amount and grouting pressure to be greater than the stored grout The preset value of the bag (2), so that the grout storage bag (2) ruptures; if it is clayey soil, control the actual grouting amount and grouting pressure to be less than the preset value of the grout storage bag (2) to avoid storage The slurry bag (2) is broken.
Applications Claiming Priority (4)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110906032.8 | 2021-08-09 | ||
CN202110906032 | 2021-08-09 | ||
CN202111162217.9 | 2021-09-30 | ||
CN202111162217.9A CN113737786A (en) | 2021-08-09 | 2021-09-30 | Pile end bottom grouting device, cast-in-place pile and construction method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2023016034A1 true WO2023016034A1 (en) | 2023-02-16 |
Family
ID=78725907
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/CN2022/094671 WO2023016034A1 (en) | 2021-08-09 | 2022-05-24 | Pile end bottom grouting apparatus, cast-in-place pile and construction method therefor |
Country Status (2)
Country | Link |
---|---|
CN (2) | CN113737786A (en) |
WO (1) | WO2023016034A1 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113737786A (en) * | 2021-08-09 | 2021-12-03 | 高永光 | Pile end bottom grouting device, cast-in-place pile and construction method thereof |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001214438A (en) * | 2000-02-02 | 2001-08-07 | East Japan Railway Co | Method for construction cast-in-place concrete pile, and preload device onto ground under bottom of cast-in- place concrete pile. |
JP2005194766A (en) * | 2004-01-07 | 2005-07-21 | East Japan Railway Co | Construction method of tip-reinforced cast-in-place concrete pile, injection bag, and steel frame |
JP2006138100A (en) * | 2004-11-11 | 2006-06-01 | East Japan Railway Co | Constructing method for tip-reinforcing cast-in-place pile |
CN103469792A (en) * | 2013-09-09 | 2013-12-25 | 广东省第二建筑工程公司 | Method for conducting grouting construction at back of pile bottom of cast-in-place pile |
CN203514303U (en) * | 2013-10-30 | 2014-04-02 | 南京工业大学 | Post-grouting enlarged-toe uplift micropile |
CN106759277A (en) * | 2016-11-16 | 2017-05-31 | 上海市建工设计研究院有限公司 | Grouting device, bottom-enlarging prefabricated pile tube, bottom-enlarging filling pile and its construction method |
CN107780308A (en) * | 2017-09-27 | 2018-03-09 | 中铁十局集团第三建设有限公司 | A kind of application process of Bag Grouting Pile in Soft Railway |
CN108411920A (en) * | 2018-01-25 | 2018-08-17 | 天津大学 | A kind of the multiple spot bellows grouting device and its method of control soil deformation |
CN110896646A (en) * | 2018-12-25 | 2020-03-20 | 高永光 | Pile bottom grouting cavity and using method thereof, cast-in-place pile body and construction method thereof |
CN113737786A (en) * | 2021-08-09 | 2021-12-03 | 高永光 | Pile end bottom grouting device, cast-in-place pile and construction method thereof |
-
2021
- 2021-09-30 CN CN202111162217.9A patent/CN113737786A/en active Pending
- 2021-09-30 CN CN202122409067.9U patent/CN218990144U/en active Active
-
2022
- 2022-05-24 WO PCT/CN2022/094671 patent/WO2023016034A1/en active Application Filing
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001214438A (en) * | 2000-02-02 | 2001-08-07 | East Japan Railway Co | Method for construction cast-in-place concrete pile, and preload device onto ground under bottom of cast-in- place concrete pile. |
JP2005194766A (en) * | 2004-01-07 | 2005-07-21 | East Japan Railway Co | Construction method of tip-reinforced cast-in-place concrete pile, injection bag, and steel frame |
JP2006138100A (en) * | 2004-11-11 | 2006-06-01 | East Japan Railway Co | Constructing method for tip-reinforcing cast-in-place pile |
CN103469792A (en) * | 2013-09-09 | 2013-12-25 | 广东省第二建筑工程公司 | Method for conducting grouting construction at back of pile bottom of cast-in-place pile |
CN203514303U (en) * | 2013-10-30 | 2014-04-02 | 南京工业大学 | Post-grouting enlarged-toe uplift micropile |
CN106759277A (en) * | 2016-11-16 | 2017-05-31 | 上海市建工设计研究院有限公司 | Grouting device, bottom-enlarging prefabricated pile tube, bottom-enlarging filling pile and its construction method |
CN107780308A (en) * | 2017-09-27 | 2018-03-09 | 中铁十局集团第三建设有限公司 | A kind of application process of Bag Grouting Pile in Soft Railway |
CN108411920A (en) * | 2018-01-25 | 2018-08-17 | 天津大学 | A kind of the multiple spot bellows grouting device and its method of control soil deformation |
CN110896646A (en) * | 2018-12-25 | 2020-03-20 | 高永光 | Pile bottom grouting cavity and using method thereof, cast-in-place pile body and construction method thereof |
CN113737786A (en) * | 2021-08-09 | 2021-12-03 | 高永光 | Pile end bottom grouting device, cast-in-place pile and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN113737786A (en) | 2021-12-03 |
CN218990144U (en) | 2023-05-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2020133992A1 (en) | Pile-bottom grouting cavity and method for using same, and cast-in-place pile body and method for constructing same | |
WO2023016034A1 (en) | Pile end bottom grouting apparatus, cast-in-place pile and construction method therefor | |
WO2020024740A1 (en) | Pile bottom grouting cavity and use method, and poured pile body and construction method of poured pile body | |
CN207739264U (en) | A kind of Grouting Pipe | |
CN107761753A (en) | A kind of foundation ditch water burst rapid rescue slip casting method for blocking | |
CN112832279B (en) | Waterproof structure and method for dewatering well of underground foundation pit | |
CN107513995A (en) | A kind of bridge struction pile post grouting construction method | |
CN109139059A (en) | A kind of osmotic grouting suitable for shield tunnel integrates stick and construction method | |
CN114457790B (en) | Pile forming device and pile forming method for cast-in-place piles in karst areas | |
CN110896646B (en) | Pile bottom grouting device and using method thereof, cast-in-place pile body and construction method thereof | |
CN210395360U (en) | Pile bottom grouting cavity and cast-in-place pile body | |
CN111188350A (en) | Confined water dewatering well structure and dewatering method | |
CN107816041B (en) | Non-dumping hole-forming prestressed anchor rod, anchor hole leakage-proof structure and construction method thereof | |
JPH0734521A (en) | Remade basin and sanitary sewage pipeline | |
CN109555140A (en) | Foundation pit and Tunnel Base spring pump drainage method for blocking and device | |
CN214272102U (en) | Waterproof construction of underground foundation ditch precipitation well | |
CN212896306U (en) | Collapsible foundation membrane bag grouting control system | |
JP2004285801A (en) | Water cut off joining method and structure between members | |
CN107419721B (en) | Improve the method for the pre-buried sound detecting pipe survival rate of bored concrete pile and the Sound Surveillance System of bored concrete pile | |
KR960005718Y1 (en) | Anchoring-bolt structure with provisions for grouting | |
CN206941656U (en) | A kind of structure that injected hole is reserved using gas cell | |
CN209243728U (en) | A kind of OPT interlocking pile slip casting around pile pipe device | |
CN207111115U (en) | A kind of slip casting orifice tube for the slip casting of roadway surrounding rock dead zone | |
CN219621838U (en) | Plugging device | |
JPH073863A (en) | Remade pit and sewage pipeline |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 22855020 Country of ref document: EP Kind code of ref document: A1 |
|
WWE | Wipo information: entry into national phase |
Ref document number: 2024/0117.1 Country of ref document: KZ Ref document number: 2401000790 Country of ref document: TH |
|
REG | Reference to national code |
Ref country code: BR Ref legal event code: B01A Ref document number: 112024002640 Country of ref document: BR |
|
NENP | Non-entry into the national phase |
Ref country code: DE |