CN206941656U - A kind of structure that injected hole is reserved using gas cell - Google Patents
A kind of structure that injected hole is reserved using gas cell Download PDFInfo
- Publication number
- CN206941656U CN206941656U CN201720821659.2U CN201720821659U CN206941656U CN 206941656 U CN206941656 U CN 206941656U CN 201720821659 U CN201720821659 U CN 201720821659U CN 206941656 U CN206941656 U CN 206941656U
- Authority
- CN
- China
- Prior art keywords
- air bag
- agent structure
- building enclosure
- reserved
- injected hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Abstract
The utility model discloses a kind of structure that injected hole is reserved using gas cell, is related to municipal Construction Technique of Underground Works field.Its air bag is fixed at the construction joint of agent structure on the groove of building enclosure;Anti-stick oxidant layer is coated on the gasbag outer surface close to agent structure side, strong adhesive layer is coated on the gasbag outer surface away from agent structure side, and the air bag away from agent structure side is fixed on by strong adhesive layer on the waterproof layer of building enclosure or building enclosure;Agent structure concreting is around air bag;Cavity is between agent structure concrete and air bag;Air bag diameter is equal with slip casting pipe diameter;Air bag is air bag with high intensity.Overcome the injected hole that prior art is reserved in Grouting Pipe easily to be blocked by concrete slurry in agent structure concreting, the shortcomings that being unable to reach plugging effect;With slip casting effect is preferable, lower-cost advantage.
Description
Technical field
Municipal Construction Technique of Underground Works field is the utility model is related to, more specifically it is a kind of pre- using gas cell
Stay the structure of injected hole.
Background technology
In order to solve the urban land contradiction in short supply between the Land Demand that expands day by day, urban construction is progressively from ground
Go underground.Construction of underground structure is constructed, inevitably in the presence of substantial amounts of construction joint, movement joint, the presence of these structural joints
Often turn into the main thoroughfare of underground water seepage, underground water seepage has had a strong impact on the utilization benefit and effect of the underground space;
By taking underground subway station as an example, on the one hand these percolating waters cause the wet stain in station ground or hinder station electrical equipment to use, shadow
The normal use of subway station is rung, brings bad social influence;Another aspect seepage easily causes structure erosion, influences station knot
Structure is safe to use.
Conventional way is when concreting at present, Grouting Pipe is reserved in construction joint or deformation joint, after
When phase finds seepage, the passive grouting for water plugging of Grouting Pipe is utilized;But there is larger defect in current this mode, be primarily due to reserve
Injected hole in Grouting Pipe is often just blocked in agent structure concreting by concrete slurry, and the later stage is noted by Grouting Pipe
The leak stopping slurries entered, which may not broken through, to be blocked, and leak stopping slurries can not enter concrete wall gap by hole in Grouting Pipe
In, often spend a large amount of funds to be but unable to reach expected plugging effect.
Existing Application No. 201210253475.2, patent name are《Deformation joint seepage mud jacking is stifled draw method for repairing and mending and its
Slip casting special equipment》Disclose and open up injected hole, inserting Grouting Pipe, the stifled mode repair distortion seam for drawing bar of installation, be a kind of quilt
Dynamic repairing method, applicable elements have more limitation;
Existing Application No. 201210312967.4, patent name are《The repairerment construction method of basement deformation joint seepage》
Disclose and set up water expandable waterstop, external labeling type waterstop and open up drainage groove, the method for diversion to plash carries out ground
The seepage treatment of lower room movement joint, sealing, somewhat expensive are realized by setting up measures of preventing water, and be not suitable for construction joint etc. its
His Leakage Position.
The content of the invention
The purpose of this utility model is to provide a kind of structure that injected hole is reserved using gas cell, and slip casting effect is preferable, uses
Air bag replaces Grouting Pipe, and cost is relatively low, simple to operate.
To achieve these goals, the technical solution of the utility model is:A kind of knot that injected hole is reserved using gas cell
Structure, it is characterised in that:Inflated airbag is fixed at the construction joint of agent structure on the groove of building enclosure;Anti-stick oxidant layer applies
The gasbag outer surface close to agent structure side is overlying on, strong adhesive layer is coated on the air bag appearance away from agent structure side
Face, the air bag away from agent structure side are fixed on the waterproof layer of building enclosure or building enclosure by strong adhesive layer
On;Agent structure concreting is around air bag;When gas is extracted and between air bag and agent structure concrete in air bag
Gap when having water injection, the air bag of coating anti-stick oxidant layer, which is separated with agent structure concrete and shunk, to be gathered in coating by force
The air bag side of adhesive layer, cavity is between agent structure concrete and air bag and in agent structure concrete;Gas
Capsule diameter is equal with slip casting pipe diameter;Air bag is air bag with high intensity, and intensity is more than or equal to 0.2MPa.
In the above-mentioned technical solutions, the groove of building enclosure determines according to that need to reserve slip casting cavity diameter or air bag diameter.
It is easy to fixation balloon.
In concreting, air pressure can support chutable concrete pressure and not produce moderate finite deformation in air bag;Air bag
For flexible air-bag, minimum volume can be contracted to a direction under external force.
Anti-stick oxidant layer is coated, using anti-stick measure, treats agent structure concrete setting, makes air bag easily and agent structure
Concrete departs from, and air bag shrinks to side, just forms slip casting cavity passage;Strong adhesive layer is coated, measure is bonded using strong,
It is easy to air bag to be shunk to the side, avoids air bag from blocking opposite side, enter agent structure coagulation soil cracking beneficial to follow-up leak stopping slurries
Gap.
The utility model has the following advantages that:
(1) air bag has higher-strength, in concreting, in air bag air pressure can support chutable concrete pressure,
And do not produce moderate finite deformation;
(2) air bag side coats strong adhesive layer and is coupled with outside building enclosure, and opposite side coating anti-stick oxidant layer is with mixing
Coagulate native non-binding, air in extracting air bag and outside air bag side hydraulic pressure effect under, air bag can to side shrink extruding, be easy to shape
It is preferable into the cavity that can inject leak stopping slurries, slip casting effect;The injected hole for effectively solving traditional built-in slip casting pipe is easily blocked, noted
Starch the problem of effect difference;
(3) be not provided with Grouting Pipe, but original built-in slip casting pipe it is local it is pre-buried with Grouting Pipe with the inflation of diameter
Air bag, when reserved injected hole is shorter, gas cell surrounding smears adhesive, and air bag is directly taken out;When reserved longer slip casting
During hole, after agent structure concrete setting, balloon occlusion mouth is opened, is extracted out airbag gas using air pump, while by water
Injected along gasbag ektexine, under water injection pressure and interior vacuum double action, air bag is provided with anti-stick oxidant layer side and concrete
Come off, and air bag is provided with strong binding agent side and extruded, form slip casting cavity passage, effectively solve to reserve longer slip casting hole
When, it is difficult to the technical barrier for taking out air bag;
(4) the utility model is also applied for movement joint or leak stopping at the structure of seepage easily occurs in other;
(5) Grouting Pipe is replaced with air bag, cost is relatively low, simple to operate, strong applicability, can bring preferable economic benefit
And social benefit.
Brief description of the drawings
Fig. 1 is the utility model agent structure, construction joint structure, building enclosure schematic diagram.
Fig. 2 is the utility model air bag pre-buried structure schematic diagram.
Fig. 3 is structural representation after the pumping of the utility model air bag.
Fig. 4 notes the structural representation in cavity for the utility model leak stopping slurries.
1- agent structures in figure, 2- construction joints, 3- building enclosures, 4- air bags, 5- agent structure concrete, 6- antitack agents
Layer, the strong adhesive layers of 7-, 8- cavitys, 9- leak stopping slurries, 10- cracks.
Embodiment
Describe performance of the present utility model in detail below in conjunction with the accompanying drawings, but they are not formed to of the present utility model
Limit, it is only for example.The advantages of making the utility model by explanation simultaneously, is more clear and is readily appreciated that.
Understood refering to accompanying drawing:A kind of structure that injected hole is reserved using gas cell, it is characterised in that:Inflated airbag 4 is solid
At the construction joint 2 of agent structure 1 on the groove of building enclosure 3 (as shown in Figure 1);Anti-stick oxidant layer 6 is coated on close to main
The outer surface of air bag 4 of the side of body structure 1, strong adhesive layer 7 is coated on the outer surface of air bag 4 away from the side of agent structure 1, remote
The air bag 4 of the side of agent structure 1 is fixed on the waterproof layer of building enclosure 3 or building enclosure 3 by strong adhesive layer 7;
Agent structure concrete 5 is poured around air bag 4;Cavity 8 is between agent structure concrete 5 and air bag 4 and is located at main body
In structural concrete 5 (as shown in Figure 2 and Figure 3);The diameter of air bag 4 is equal with slip casting pipe diameter;Air bag 4 is air bag with high intensity, intensity
More than or equal to 0.2MPa.The groove of building enclosure determines according to that need to reserve cavity diameter or air bag diameter.
A kind of grouting method of structure for using gas cell to reserve injected hole described in the utility model is in agent structure 1
Before pouring, the building enclosure 3 at main structure construction seam 2 is handled, little groove is formed, is fixed on after air bag 4 is inflated
In the little groove of building enclosure 3 (as shown in Figure 1 and Figure 2),
It is coated with the waterproof that the side of air bag 4 of strong adhesive layer is fixed in building enclosure 3 or be affixed in building enclosure 3
In material layer;Pour agent structure concrete 5;After the solidification of agent structure concrete 5, the gas in air bag 4 is extracted out, and to gas
Gap between capsule 4 and agent structure concrete 5 uses pressure water flooding method water filling, and water injection pressure is more than or equal to 0.1MPa;Gas
Including capsule 4, in the presence of external pressure, separated along air bag 4 coated with anti-stick oxidant layer side with agent structure concrete 5, and to
Coated with strong adhesive layer and the side of air bag 4 being fixed in building enclosure or be affixed on the waterproof layer in building enclosure
Shrink, form cavity 8 (as shown in Figure 3);Leak stopping slurries 9 are injected using slip casing by pressure normal direction cavity 8, leak stopping slurries 9 are being pressed
The crack 10 (as shown in Figure 4) in agent structure 1 is effectively entered under power effect, so as to reach the effect of effective leak-proof leak-stopping
Fruit.
Other unaccounted parts belong to prior art.
Claims (2)
- A kind of 1. structure that injected hole is reserved using gas cell, it is characterised in that:Inflated airbag (4) is fixed on agent structure (1) on the groove of construction joint (2) place's building enclosure (3);Anti-stick oxidant layer (6) is coated on close to agent structure (1) side Air bag (4) outer surface, strong adhesive layer (7) are coated on air bag (4) outer surface away from agent structure (1) side, away from main body The air bag (4) of structure (1) side is fixed on the waterproof material of building enclosure (3) or building enclosure (3) by strong adhesive layer (7) On layer;Agent structure concrete (5) is poured around air bag (4);Cavity (8) is located at agent structure concrete (5) and air bag (4) Between and in the agent structure concrete (5);Air bag (4) diameter is equal with slip casting pipe diameter;Air bag (4) is high intensity gas Capsule, intensity are more than or equal to 0.2MPa.
- A kind of 2. structure that injected hole is reserved using gas cell according to claim 1, it is characterised in that:Building enclosure (3) groove determines according to that need to reserve cavity (8) diameter or air bag (4) diameter.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720821659.2U CN206941656U (en) | 2017-07-08 | 2017-07-08 | A kind of structure that injected hole is reserved using gas cell |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720821659.2U CN206941656U (en) | 2017-07-08 | 2017-07-08 | A kind of structure that injected hole is reserved using gas cell |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206941656U true CN206941656U (en) | 2018-01-30 |
Family
ID=61369277
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720821659.2U Active CN206941656U (en) | 2017-07-08 | 2017-07-08 | A kind of structure that injected hole is reserved using gas cell |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206941656U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107165199A (en) * | 2017-07-08 | 2017-09-15 | 长江勘测规划设计研究有限责任公司 | A kind of use gas cell reserves the structure and its grouting method of injected hole |
-
2017
- 2017-07-08 CN CN201720821659.2U patent/CN206941656U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107165199A (en) * | 2017-07-08 | 2017-09-15 | 长江勘测规划设计研究有限责任公司 | A kind of use gas cell reserves the structure and its grouting method of injected hole |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103343543B (en) | Foundation pit dewatering well pressure-reduction-type plugging method | |
CN207739264U (en) | A kind of Grouting Pipe | |
CN107620312A (en) | High hydraulic pressure precipitation well construction and hydrostatic slip casting method for blocking in a kind of Metro station excavation | |
CN206016824U (en) | A kind of stopping means for preventing shield sky from pushing away Segment displacement | |
CN207727600U (en) | Plugging dewatering well device | |
CN209339169U (en) | A kind of precipitation well in foundation pit plugging device | |
CN101864778A (en) | Method for leaking stoppage of external wall of underground structure | |
CN207193996U (en) | A kind of precipitation pipe well well-sealing device | |
CN109915068B (en) | Automatic water-absorbing plugging and hole-sealing device and method for near-horizontal coal seam gas extraction drill hole | |
CN109139059A (en) | A kind of osmotic grouting suitable for shield tunnel integrates stick and construction method | |
CN102561314A (en) | Prefabricated waterproof pile (WSP pile) and inserting and pulling construction method thereof | |
CN106894820B (en) | A kind of waterproof well wall retractable device and its construction technology | |
CN105780792B (en) | A kind of foundation pit high water head Dewatering by pressure reduction well shut-in well method and structure of shunting in a well | |
CN103469792B (en) | Method for conducting grouting construction at back of pile bottom of cast-in-place pile | |
CN111926841A (en) | Dewatering well water-carrying plugging structure and construction method thereof | |
CN208235554U (en) | A kind of installation of pressure-bearing dewatering well and plugging device | |
CN203362181U (en) | Mud jacking film bag for water resistance and leaking stoppage in tunnel construction | |
CN207537993U (en) | A kind of diversion tunnel concrete plug | |
CN206941656U (en) | A kind of structure that injected hole is reserved using gas cell | |
CN107700440A (en) | A kind of diversion tunnel concrete plug and its construction method | |
CN201424658Y (en) | Water leakage detection of underground continuous wall groove seams and block repair device | |
CN105220700A (en) | Foundation pit waterproof curtain reinforcement | |
CN206971581U (en) | A kind of water-proofing treatment system of joint of plate perforating pipe position | |
CN107165199A (en) | A kind of use gas cell reserves the structure and its grouting method of injected hole | |