WO2021169391A1 - 空调的控制方法 - Google Patents

空调的控制方法 Download PDF

Info

Publication number
WO2021169391A1
WO2021169391A1 PCT/CN2020/126443 CN2020126443W WO2021169391A1 WO 2021169391 A1 WO2021169391 A1 WO 2021169391A1 CN 2020126443 W CN2020126443 W CN 2020126443W WO 2021169391 A1 WO2021169391 A1 WO 2021169391A1
Authority
WO
WIPO (PCT)
Prior art keywords
air conditioner
change
opening value
electronic expansion
expansion valve
Prior art date
Application number
PCT/CN2020/126443
Other languages
English (en)
French (fr)
Inventor
杨公增
王军
Original Assignee
青岛海尔空调电子有限公司
海尔智家股份有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 青岛海尔空调电子有限公司, 海尔智家股份有限公司 filed Critical 青岛海尔空调电子有限公司
Publication of WO2021169391A1 publication Critical patent/WO2021169391A1/zh

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/30Control or safety arrangements for purposes related to the operation of the system, e.g. for safety or monitoring
    • F24F11/49Control or safety arrangements for purposes related to the operation of the system, e.g. for safety or monitoring ensuring correct operation, e.g. by trial operation or configuration checks
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/50Control or safety arrangements characterised by user interfaces or communication
    • F24F11/52Indication arrangements, e.g. displays
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/50Control or safety arrangements characterised by user interfaces or communication
    • F24F11/61Control or safety arrangements characterised by user interfaces or communication using timers
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/62Control or safety arrangements characterised by the type of control or by internal processing, e.g. using fuzzy logic, adaptive control or estimation of values
    • F24F11/63Electronic processing
    • F24F11/64Electronic processing using pre-stored data
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/70Control systems characterised by their outputs; Constructional details thereof
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B30/00Energy efficient heating, ventilation or air conditioning [HVAC]
    • Y02B30/70Efficient control or regulation technologies, e.g. for control of refrigerant flow, motor or heating

Definitions

  • the present invention relates to the technical field of air conditioners, in particular to a control method of an air conditioner.
  • a liquid pipe shut-off valve is generally installed between the indoor heat exchanger and the outdoor heat exchanger, and a gas pipe shut-off valve is installed between the indoor heat exchanger and the compressor.
  • the indoor heat exchanger is controlled by the gas pipe shut-off valve and the liquid pipe shut-off valve.
  • the circulation and cut-off of the refrigerant between the heat exchanger and the outdoor heat exchanger are in an open state.
  • the present invention provides a control method of an air conditioner.
  • the air conditioner includes a compressor, an indoor heat exchanger, and an outdoor heat exchanger.
  • a refrigerant pipeline between the outdoor heat exchanger and the indoor heat exchanger is provided with a first A shut-off valve and an electronic expansion valve
  • the control method includes: obtaining the discharge pressure of the compressor and the opening value of the electronic expansion valve; calculating the amount of change in the discharge pressure per unit time after the air conditioner is turned on; The change in the exhaust pressure is compared with a preset exhaust pressure change threshold; the opening value of the electronic expansion valve is compared with the set opening value; based on the comparison result of the change in the exhaust pressure And the comparison result of the opening value of the electronic expansion valve to control the air conditioner.
  • control the air conditioner based on the comparison result of the change amount of the exhaust pressure and the comparison result of the opening value of the electronic expansion valve The step specifically includes: if the change in the exhaust pressure is greater than the exhaust pressure change threshold, and the opening value of the electronic expansion valve is less than the set opening value, then the electronic expansion valve The opening value is adjusted to be greater than or equal to the set opening value, and the air conditioner is continuously controlled based on the comparison result of the change amount of the exhaust pressure.
  • control the air conditioner based on the comparison result of the change amount of the exhaust pressure and the comparison result of the opening value of the electronic expansion valve The step specifically includes: if the change in the exhaust pressure is greater than the exhaust pressure change threshold, and the opening value of the electronic expansion valve is greater than or equal to the set opening value, acquiring the exhaust pressure The amount of change is greater than the duration of the exhaust pressure change threshold; if the duration is greater than the preset time threshold, the air conditioner is turned off.
  • the step of "controlling the air conditioner based on the comparison result of the change amount of the exhaust pressure” specifically includes: acquiring the change of the exhaust pressure The amount is greater than the duration of the exhaust pressure change threshold; if the duration is greater than the preset time threshold, the air conditioner is turned off.
  • control method further includes: when turning off the air conditioner, sending out a prompt that the first shut-off valve is not opened.
  • the present invention provides another air conditioner control method
  • the air conditioner includes a compressor, an indoor heat exchanger and an outdoor heat exchanger, and a refrigerant pipe between the outdoor heat exchanger and the indoor heat exchanger
  • An electronic expansion valve is provided on the road, and a second shut-off valve is provided on the refrigerant pipeline between the indoor heat exchanger and the compressor.
  • the control method includes: obtaining the suction pressure of the compressor and the electronic expansion valve Calculate the change in the suction pressure per unit time after the air conditioner is turned on; compare the change in the suction pressure with a preset suction pressure change threshold; compare the opening of the electronic expansion valve The degree value is compared with the set opening degree value; the air conditioner is controlled based on the comparison result of the change amount of the suction pressure and the comparison result of the opening degree value of the electronic expansion valve.
  • control the air conditioner based on the comparison result of the amount of change of the suction pressure and the comparison result of the opening value of the electronic expansion valve The step specifically includes: if the amount of change in the suction pressure is greater than a preset threshold value for the change in suction pressure, and the opening value of the electronic expansion valve is less than the set opening value, then opening the electronic expansion valve The degree value is adjusted to be greater than or equal to the set opening degree value, and the air conditioner is continuously controlled based on the comparison result of the change amount of the suction pressure.
  • control the air conditioner based on the comparison result of the amount of change of the suction pressure and the comparison result of the opening value of the electronic expansion valve The step specifically includes: if the change in the suction pressure is greater than the suction pressure change threshold, and the opening value of the electronic expansion valve is greater than or equal to the set opening value, acquiring the change in the suction pressure The amount is greater than the duration of the inhalation pressure change threshold; if the duration is greater than the preset time threshold, the air conditioner is turned off.
  • the step of "controlling the air conditioner based on the comparison result of the change of the suction pressure” specifically includes: obtaining the change of the suction pressure The amount is greater than the duration of the inhalation pressure change threshold; if the duration is greater than the preset time threshold, the air conditioner is turned off.
  • control method further includes: when turning off the air conditioner, sending out a prompt that the second shut-off valve is not opened.
  • the air conditioner control method provided by the present invention is based on the comparison result of the change in the compressor discharge pressure per unit time and the preset discharge pressure change threshold after the air conditioner is turned on, and the opening value and setting of the electronic expansion valve. Control the air conditioner based on the comparison result of the fixed opening value. Therefore, it can be judged whether the first shut-off valve provided on the refrigerant pipeline between the outdoor heat exchanger and the indoor heat exchanger is open, and when the first shut-off valve is not opened, the air conditioner is turned off to avoid the failure of the first shut-off valve. Under the circumstances, the air conditioner was turned on by mistake, which caused the air conditioner to be damaged or a safety accident occurred.
  • the air conditioner control method provided by the present invention is based on the comparison result of the change in the suction pressure of the compressor per unit time after the air conditioner is turned on and the preset suction pressure change threshold, and the opening degree of the electronic expansion valve.
  • the result of comparing the value and the set opening value the air conditioner is controlled. Therefore, it can be judged whether the second shut-off valve provided on the refrigerant pipeline between the indoor heat exchanger and the compressor is open, and when the second shut-off valve is not opened, the air conditioner is turned off to avoid the situation that the second shut-off valve is not opened.
  • the air conditioner is turned on by mistake, and the air conditioner is damaged or a safety accident occurs.
  • Figure 1 is a schematic structural diagram of an existing air conditioner
  • FIG. 2 is a schematic flowchart of a first embodiment of the air conditioner control method of this embodiment
  • FIG. 3 is a schematic flowchart of a second implementation manner of the air conditioner control method of this embodiment.
  • the existing air conditioner generally includes a compressor 1, an outdoor heat exchanger 2 and an indoor heat exchanger 6.
  • the refrigerant flows from the exhaust port of the compressor 1 to the outdoor.
  • the heat exchanger 2 the refrigerant flows out of the outdoor heat exchanger 2 and then passes through the indoor heat exchanger 6, and finally flows back to the compressor 1 from the suction port of the compressor 1.
  • a first shut-off valve 3 (or called a liquid pipe shut-off valve) and an electronic expansion valve 5 are provided on the pipeline between the indoor heat exchanger 6 and the outdoor heat exchanger 2, and the indoor heat exchanger 6 and the compressor
  • the pipeline between 1 is provided with a second shut-off valve 7 (or called tracheal shut-off valve).
  • a second shut-off valve 7 (or called tracheal shut-off valve).
  • suction port of the compressor 1 is also provided with a suction pressure sensor 12, and the discharge port of the compressor 1 is also provided with a discharge pressure sensor 11, which is used to monitor the suction pressure and discharge pressure of the compressor 1 respectively. , To provide data for air conditioning control.
  • the above-mentioned air conditioner in this embodiment is a refrigeration air conditioner, in which the outdoor heat exchanger 2 is used as a condenser, and the indoor heat exchanger 6 is used as an evaporator.
  • a condensation temperature sensor 21 for measuring the condensation temperature can be installed on the outdoor heat exchanger 2
  • an evaporation temperature sensor 61 for measuring the evaporation temperature can be installed on the indoor heat exchanger 6 to monitor the condensation effect of the outdoor heat exchanger 2 and indoor heat exchange The evaporation effect of the device 6.
  • This embodiment provides a control method of an air conditioner, wherein, as shown in FIG. 1, the air conditioner includes a compressor 1, an indoor heat exchanger 6 and an outdoor heat exchanger 2.
  • the outdoor heat exchanger 2 and the indoor heat exchanger 6 A first shut-off valve 3 and an electronic expansion valve 5 are provided on the refrigerant pipeline in between, as shown in Fig. 2, the control method includes:
  • the exhaust pressure sensor 11 can be used to monitor and obtain the exhaust pressure of the compressor 1, and the opening degree of the electronic expansion valve 5 can also be obtained with a special monitoring instrument.
  • the amount of change in exhaust pressure per unit time can be 3s, 5s, etc. as the amount of change per unit time, or the amount of change in exhaust pressure within a period of time after the air conditioner is turned on.
  • the time setting is based on the refrigerant pipeline in the air conditioner.
  • the safe time for the pressure to rise to a safe value is used as a reference, and should not exceed the safe time. For example, one tenth of the time can be taken as the unit time.
  • the exhaust pressure change threshold may refer to the normal change value of the compressor 1 during normal operation, and this value may be different for different air conditioners.
  • the opening degree value of the electronic expansion valve 5 is compared with the set opening degree value, so that the factor that the opening degree of the electronic expansion valve 5 is too small and causing an abnormal influence on the variation of the exhaust pressure per unit time can be excluded.
  • step S12 is performed first and then step S13 is performed
  • step S14 can also be performed between steps S11 and S12, or step S14 can also be performed between steps S12 and S13.
  • step S11 when obtaining the discharge pressure of the compressor 1 and the opening value of the electronic expansion valve 5 in step S11, they can be performed simultaneously or sequentially, and there is no special requirement on the sequence.
  • the air conditioner control method provided in this embodiment is based on the comparison result of the change in the discharge pressure of the compressor 1 per unit time and the preset discharge pressure change threshold after the air conditioner is turned on, and the opening degree of the electronic expansion valve 5 The result of comparing the value and the set opening value, the air conditioner is controlled. Therefore, it can be judged whether the first shut-off valve 3 provided on the refrigerant pipeline between the outdoor heat exchanger 2 and the indoor heat exchanger 6 is opened, and when the first shut-off valve 3 is not opened, the air conditioner is turned off to avoid the first shut-off. If the valve 3 is not opened, the air conditioner is turned on by mistake, resulting in damage to the air conditioner or a safety accident.
  • the step of "controlling the air conditioner based on the comparison result of the amount of change in exhaust pressure and the comparison result of the opening value of the electronic expansion valve 5" specifically includes : If the exhaust pressure change is greater than the exhaust pressure change threshold, and the opening value of the electronic expansion valve 5 is less than the set opening value, the opening value of the electronic expansion valve 5 is adjusted to be greater than or equal to the set opening value Value, and continue to control the air conditioner based on the comparison result of the change in exhaust pressure.
  • the opening of the electronic expansion valve 5 when the opening of the electronic expansion valve 5 is small, it will also affect the amount of change in the exhaust pressure. Therefore, when it is monitored that the opening of the electronic expansion valve 5 is less than the set value, the electronic expansion valve 5 needs to be opened. Adjust the degree value to be greater than or equal to the set opening value, and continue to monitor and compare the discharge pressure of compressor 1, and then control the air conditioner based on the comparison result of the change in discharge pressure to eliminate electronic expansion
  • the opening degree of the valve 5 has an abnormal effect on the amount of change in the exhaust pressure per unit time.
  • the step of "controlling the air conditioner based on the comparison result of the change in exhaust pressure” specifically includes: obtaining the exhaust pressure The amount of change is greater than the duration of the exhaust pressure change threshold; if the duration is greater than the preset time threshold, the air conditioner is turned off.
  • the step of "controlling the air conditioner based on the comparison result of the amount of change in exhaust pressure and the comparison result of the opening value of the electronic expansion valve 5" specifically includes : If the exhaust pressure change is greater than the exhaust pressure change threshold, and the opening value of the electronic expansion valve 5 is greater than or equal to the set opening value, the duration of the exhaust pressure change greater than the exhaust pressure change threshold is acquired ; If the duration is greater than the preset time threshold, turn off the air conditioner.
  • obtaining the duration of the exhaust pressure change greater than the exhaust pressure change threshold can more reliably determine whether the first shut-off valve 3 is open. If the duration is greater than the preset time threshold, it means that the first shut-off valve 3 is indeed not opened. At this time, the air conditioner is turned off to avoid damage or danger to the air conditioner.
  • control method further includes: while turning off the air conditioner, sending out a prompt that the first shutoff valve 3 is not opened.
  • the air conditioner emits an alarm sound, and the display on the air conditioner also displays an error message to remind the air conditioner installer to pay attention.
  • the above-mentioned embodiments show specific implementations of the air conditioner control method required to avoid damage to the air conditioner or safety accidents due to the failure of the first shut-off valve 3 (liquid pipe shut-off valve).
  • the first shut-off valve 3 liquid pipe shut-off valve
  • the second shut-off valve 7 trace shut-off valve
  • the two are the same in principle, and both are based on whether the air pressure change on the refrigerant pipeline is normal or not to control the air conditioner.
  • this embodiment provides another air conditioner control method.
  • the air conditioner includes a compressor 1, an indoor heat exchanger 6 and an outdoor heat exchanger 2, and a refrigerant pipe between the outdoor heat exchanger 2 and the indoor heat exchanger 6
  • An electronic expansion valve 5 is provided on the road, and a second stop valve 7 is provided on the refrigerant pipeline between the indoor heat exchanger 6 and the compressor 1, as shown in Fig. 3,
  • the control method includes:
  • the suction pressure sensor 12 can be used to monitor and obtain the discharge pressure of the compressor 1, and the opening degree of the electronic expansion valve 5 can also be obtained with a special monitoring instrument.
  • the amount of change in the suction pressure per unit time can be 3s, 5s, etc. as the amount of change per unit time, or the amount of change in the suction pressure within a period of time after the air conditioner is turned on.
  • the time setting is based on the refrigerant pipeline in the air conditioner.
  • the safe time for the pressure to rise to a safe value is used as a reference, and should not exceed the safe time. For example, one tenth of the time can be taken as the unit time.
  • the suction pressure change threshold may refer to the normal change value of the compressor 1 during normal operation, and this value may be different for different air conditioners.
  • the opening degree value of the electronic expansion valve 5 is compared with the set opening degree value, so that the factor that the opening degree of the electronic expansion valve 5 is too small and causing abnormal influence on the change of the suction pressure per unit time can be eliminated.
  • step S22 is performed first and then step S23 is performed
  • step S24 can also be performed between steps S21 and S22, or step S24 can also be performed between steps S22 and S23.
  • step S24 can also be performed between steps S22 and S23.
  • the control method of the air conditioner provided in this embodiment is based on the comparison result of the change in the suction pressure of the compressor 1 per unit time after the air conditioner is turned on and the preset suction pressure change threshold, and the opening degree of the electronic expansion valve 5
  • the result of comparing the value and the set opening value the air conditioner is controlled. Therefore, it can be judged whether the second shut-off valve 7 provided on the refrigerant pipeline between the indoor heat exchanger 6 and the compressor 1 is open, and when the second shut-off valve 7 is not open, the air conditioner is turned off to avoid the second shut-off valve 7 If the air conditioner is turned on by mistake when it is not turned on, the air conditioner may be damaged or a safety accident may occur.
  • the step of "controlling the air conditioner based on the comparison result of the change of the suction pressure and the comparison result of the opening value of the electronic expansion valve 5" specifically includes : If the change in suction pressure is greater than the preset suction pressure change threshold, and the opening value of the electronic expansion valve 5 is less than the set opening value, the opening value of the electronic expansion valve 5 is adjusted to be greater than or equal to the set opening value. Set the opening value, and continue to control the air conditioner based on the comparison result of the amount of change in the suction pressure.
  • the opening degree of the electronic expansion valve 5 when the opening degree of the electronic expansion valve 5 is small, it will also affect the amount of change in the suction pressure. Therefore, when it is monitored that the opening degree of the electronic expansion valve 5 is less than the set value, the electronic expansion valve 5 needs to be opened. Adjust the degree value to be greater than or equal to the set opening value, and continue to monitor and compare the suction pressure of compressor 1, and then control the air conditioner based on the comparison result of the change in suction pressure to eliminate electronic expansion The opening degree of the valve 5 has an abnormal effect on the amount of change in the suction pressure per unit time.
  • the step of "controlling the air conditioner based on the comparison result of the change in the suction pressure” specifically includes: obtaining the suction pressure The amount of change is greater than the duration of the inspiratory pressure change threshold; if the duration is greater than the preset time threshold, the air conditioner is turned off.
  • the step of "controlling the air conditioner based on the comparison result of the change of the suction pressure and the comparison result of the opening value of the electronic expansion valve 5" specifically includes : If the change in suction pressure is greater than the suction pressure change threshold, and the opening value of the electronic expansion valve 5 is greater than or equal to the set opening value, obtain the duration of the change in suction pressure greater than the suction pressure change threshold; If the duration is greater than the preset time threshold, the air conditioner is turned off.
  • obtaining the duration of the change of the suction pressure greater than the suction pressure change threshold can more reliably determine whether the second shut-off valve 7 is open. If the duration is greater than the preset time threshold, it means that the second shut-off valve 7 is indeed not opened. At this time, the air conditioner is turned off to avoid damage or danger to the air conditioner.
  • control method further includes: while turning off the air conditioner, sending out a prompt that the second shut-off valve 7 is not opened.
  • the air conditioner emits an alarm sound, and the display on the air conditioner also displays an error message to remind the air conditioner installer to pay attention.
  • step S11 can be combined with step S21, that is, in the first step, the suction pressure and discharge pressure of the compressor 1 and the opening value of the electronic expansion valve 5 can be obtained.
  • step S21 that is, in the first step, the suction pressure and discharge pressure of the compressor 1 and the opening value of the electronic expansion valve 5 can be obtained.
  • the subsequent steps are combined to simultaneously determine whether the first shut-off valve 3 and the second shut-off valve 7 are in an open state, and to control the air conditioner.
  • the air conditioner pair control method provided in this embodiment can be stored as a program in a computer readable storage medium.
  • the storage medium includes a number of instructions for causing a computer device (which may be a personal computer, a server, or a network device, etc.) or a processor to execute some steps of the methods in the various embodiments of the present invention.
  • the aforementioned storage media include: U disk, mobile hard disk, read-only memory (Read-Only Memory, ROM), random access memory (Random Access Memory, RAM), magnetic disk or optical disk and other media that can store program code .

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Human Computer Interaction (AREA)
  • Signal Processing (AREA)
  • Physics & Mathematics (AREA)
  • Fuzzy Systems (AREA)
  • Mathematical Physics (AREA)
  • Air Conditioning Control Device (AREA)

Abstract

一种空调的控制方法,通过基于空调开启后压缩机(1)的排气压力在单位时间内的变化量与预设的排气压力变化阈值的比较结果,以及电子膨胀阀(5)的开度值与设定开度值的比较结果,对空调进行控制。

Description

空调的控制方法 技术领域
本发明涉及空调技术领域,具体涉及一种空调的控制方法。
背景技术
空调中一般在室内换热器和室外换热器之间安装有液管截止阀,在室内换热器与压缩机之间安装有气管截止阀,通过气管截止阀和液管截止阀来控制室内换热器和室外换热器之间冷媒的流通与截止。在空调正常运行时,需要气管截止阀和液管截止阀均处于打开状态。
但是,在空调安装时,由于人们很容易忽视提示标签或其他原因,在未打开气管截止阀或液管截止阀的情况下误开空调,而导致空调损坏或者发生安全事故的问题。
相应地,本领域需要一种新的空调的控制方法来解决上述问题。
发明内容
为了解决现有技术中的上述问题,即为了解决在空调安装时,由于人们很容易忽视提示标签或其他原因,在未打开气管截止阀或液管截止阀的情况下误开空调,而导致空调损坏或者发生安全事故的问题。
本发明提供了一种空调的控制方法,所述空调包括压缩机、室内换热器和室外换热器,所述室外换热器与所述室内换热器之间的冷媒管路上设置有第一截止阀和电子膨胀阀,所述控制方法包括:获取压缩机的排气压力以及所述电子膨胀阀的开度值;计算空调开启后单位时间内所述排气压力的变化量;将所述排气压力的变化量与预设的排气压力变化阈值进行比较;将所述电子膨胀阀的开度值与设定开度值进行比较;基于所述排气压力的变化量的比较结果以及所述电子膨胀阀的开度值的比较结果,对所述空调进行控制。
作为本发明提供的上述控制方法的一种优选的技术方案,“基于所述排气压力的变化量的比较结果以及所述电子膨胀阀的开度值 的比较结果,对所述空调进行控制”的步骤具体包括:若所述排气压力的变化量大于所述排气压力变化阈值,同时所述电子膨胀阀的开度值小于所述设定开度值,则将所述电子膨胀阀的开度值调节至大于或等于所述设定开度值,并继续基于所述排气压力的变化量的比较结果,对所述空调进行控制。
作为本发明提供的上述控制方法的一种优选的技术方案,“基于所述排气压力的变化量的比较结果以及所述电子膨胀阀的开度值的比较结果,对所述空调进行控制”的步骤具体包括:若所述排气压力的变化量大于所述排气压力变化阈值,同时所述电子膨胀阀的开度值大于或等于设定开度值,则获取所述排气压力的变化量大于所述排气压力变化阈值的持续时间;若所述持续时间大于预设的时间阈值,关闭所述空调。
作为本发明提供的上述控制方法的一种优选的技术方案,“基于所述排气压力的变化量的比较结果,对所述空调进行控制”的步骤具体包括:获取所述排气压力的变化量大于所述排气压力变化阈值的持续时间;若所述持续时间大于预设的时间阈值,则关闭所述空调。
作为本发明提供的上述控制方法的一种优选的技术方案,所述控制方法还包括:在关闭所述空调的同时,发出所述第一截止阀未打开的提示。
此外,本发明提供的另一种空调的控制方法,所述空调包括压缩机、室内换热器和室外换热器,且所述室外换热器与所述室内换热器之间的冷媒管路上设置有电子膨胀阀,所述室内换热器与所述压缩机之间的冷媒管路上设置有第二截止阀,所述控制方法包括:获取压缩机的吸气压力以及所述电子膨胀阀的开度值;计算空调开启后单位时间内所述吸气压力的变化量;将所述吸气压力的变化量与预设的吸气压力变化阈值进行比较;将所述电子膨胀阀的开度值与设定开度值进行比较;基于所述吸气压力的变化量的比较结果以及所述电子膨胀阀的开度值的比较结果,对所述空调进行控制。
作为本发明提供的上述控制方法的一种优选的技术方案,“基于所述吸气压力的变化量的比较结果以及所述电子膨胀阀的开度值的比较结果,对所述空调进行控制”的步骤具体包括:若所述吸气压力 的变化量大于预设的吸气压力变化阈值,同时所述电子膨胀阀的开度值小于设定开度值,则将所述电子膨胀阀的开度值调节至大于或等于设定开度值,并继续基于所述吸气压力的变化量的比较结果,对所述空调进行控制。
作为本发明提供的上述控制方法的一种优选的技术方案,“基于所述吸气压力的变化量的比较结果以及所述电子膨胀阀的开度值的比较结果,对所述空调进行控制”的步骤具体包括:若所述吸气压力的变化量大于所述吸气压力变化阈值,同时所述电子膨胀阀的开度值大于或等于设定开度值,获取所述吸气压力的变化量大于所述吸气压力变化阈值的持续时间;若所述持续时间大于预设的时间阈值,则关闭所述空调。
作为本发明提供的上述控制方法的一种优选的技术方案,“基于所述吸气压力的变化量的比较结果,对所述空调进行控制”的步骤具体包括:获取所述吸气压力的变化量大于所述吸气压力变化阈值的持续时间;若所述持续时间大于预设的时间阈值,则关闭所述空调。
作为本发明提供的上述控制方法的一种优选的技术方案,所述控制方法还包括:在关闭所述空调的同时,发出所述第二截止阀未打开的提示。
本发明提供的空调的控制方法,通过基于空调开启后压缩机的排气压力在单位时间内的变化量与预设的排气压力变化阈值的比较结果,以及电子膨胀阀的开度值与设定开度值的比较结果,对空调进行控制。从而可以判断室外换热器与室内换热器之间的冷媒管路上设置的第一截止阀是否开启,并当第一截止阀未开启时,关闭空调,以避免在第一截止阀未打开的情况下误开空调,而导致空调损坏或者发生安全事故的问题。
此外,本发明提供的空调的控制方法,还通过基于空调开启后压缩机的吸气压力在单位时间内的变化量与预设的吸气压力变化阈值的比较结果,以及电子膨胀阀的开度值与设定开度值的比较结果,对空调进行控制。从而可以判断室内换热器与压缩机之间的冷媒管路上设置的第二截止阀是否开启,并当第二截止阀未开启时,关闭空调,以避免 在第二截止阀未打开的情况下误开空调,而导致空调损坏或者发生安全事故的问题。
附图说明
下面参照附图并结合空调的基本结构来描述本发明的空调的控制方法。附图中:
图1为现有的空调的结构示意图;
图2为本实施例的空调的控制方法的第一个实施方式的流程示意图;
图3为本实施例的空调的控制方法的第二个实施方式的流程示意图。
附图标记列表
1-压缩机;11-排气压力传感器;12-吸气压力传感器;2-室外换热器;21-冷凝温度传感器;3-第一截止阀;4-过滤器;5-电子膨胀阀;6-室内换热器;61-蒸发温度传感器;7-第二截止阀。
具体实施方式
下面参照附图来描述本发明的优选实施方式。本领域技术人员应当理解的是,这些实施方式仅仅用于解释本发明的技术原理,并非旨在限制本发明的保护范围。例如,虽然本实施例中的空调的控制方法是针对一种具体的空调的结构进行介绍的,但是这并非旨在于限制本发明的保护范围,而空调的结构并非一成不变的,在不偏离本发明原理的条件下,本领域技术人员可以将本发明应用于结构调整或改变后的空调。例如,设置有气液分离器、储液罐的空调等。
在对本发明提供的空调的控制方法进行说明之前,先对现有的空调的基本结构作简单的说明。如图1所示,以制冷空调为例,现有的空调一般包括压缩机1、室外换热器2和室内换热器6,空调运行时,冷媒由压缩机1的排气口流向室外换热器2,冷媒流出室外换热器2后经过室内换热器6,最终由压缩机1的吸气口流回压缩机1。其中,在室内换热器6与室外换热器2之间的管路上设置有第一截止阀3(或称为液管截止阀)和电子膨胀阀5,在室内换热器6与压缩机1之间的管路上设置 有第二截止阀7(或称为气管截止阀)。通过第一截止阀3和第二截止阀7来控制室内换热器6和室外换热器2之间冷媒的流通与截止。在空调正常运行时,需要第一截止阀3和第二截止阀7均处于打开状态。
进一步的,压缩机1的吸气口上还设置有吸气压力传感器12,压缩机1的排气口上还设置有排气压力传感器11,分别用来监测压缩机1的吸气压力和排气压力,以为空调的控制提供数据。
本实施例中的上述空调为制冷空调,其中室外换热器2作冷凝器使用,室内换热器6作蒸发器使用。可以在室外换热器2上设置测量冷凝温度的冷凝温度传感器21,以及在室内换热器6上设置测量蒸发温度的蒸发温度传感器61,以监测室外换热器2的冷凝效果和室内换热器6的蒸发效果。
压缩机1运行时的粉末磨屑、冷媒管道中产生的氧化皮之类的污物等会使冷媒中会含有一些杂质,影响空调的正常工作,所以一般还可以在第一截止阀3与电子膨胀阀5之间设置过滤器4。
上述说明的是现有空调的一般结构,但是,本领域技术人员应当理解的是,在不偏离本发明原理的条件下,本申请的空调的控制方法还可以适用于其他结构或类型的空调,例如,既有制冷功能,又有制热功能的空调等。因此,上述说明的空调的基本结构不应看作是对本发明的空调的控制方法的保护范围的限制。
本实施例提供了一种空调的控制方法,其中,如图1所示,该空调包括压缩机1、室内换热器6和室外换热器2,室外换热器2与室内换热器6之间的冷媒管路上设置有第一截止阀3和电子膨胀阀5,如图2所示,该控制方法包括:
S11、获取压缩机1的排气压力以及电子膨胀阀5的开度值;
S12、计算空调开启后单位时间内排气压力的变化量;
S13、将排气压力的变化量与预设的排气压力变化阈值进行比较;
S14、将电子膨胀阀5的开度值与设定开度值进行比较;
S15、基于排气压力的变化量的比较结果以及电子膨胀阀5的开度值的比较结果,对空调进行控制。
示例性地,如图1中的空调,排气压力传感器11可以用来监测并获取压缩机1的排气压力,电子膨胀阀5的开度也可以用专门的监测仪器来获取。
单位时间内排气压力的变化量可以为3s、5s等一段时间作为单位时间内的变化量,或者空调开启后的一段时间内排气压力的变化量,该时间的设置以空调中冷媒管路上的压力上升到安全值所用的安全时间作为参考,不应超过该安全时间,例如,可以取该时间的十分之一作为单位时间。
排气压力变化阈值可以参考压缩机1正常工作时的正常变化值,针对不同的空调该值可能存在差别。此外,将电子膨胀阀5的开度值与设定开度值进行比较,从而可以排除电子膨胀阀5的开度太小而对单位时间内排气压力的变化量造成不正常影响的因素。
需要说明的是,尽管上文详细描述了本发明方法的详细步骤,但是,在不偏离本发明的基本原理的前提下,本领域技术人员可以对上述步骤进行组合、拆分及调换顺序,如此修改后的技术方案并没有改变本发明的基本构思,因此也落入本发明的保护范围之内。例如,在先进行步骤S12再进行步骤S13的前提下,步骤S14还可以在步骤S11和S12之间进行,或者步骤S14还可以在步骤S12和S13之间进行。再如,步骤S11中在获取压缩机1的排气压力以及电子膨胀阀5的开度值时,可以同时进行,也可以按顺序先后进行,且顺序上没有特殊要求。
本实施例提供的空调的控制方法,通过基于空调开启后压缩机1的排气压力在单位时间内的变化量与预设的排气压力变化阈值的比较结果,以及电子膨胀阀5的开度值与设定开度值的比较结果,对空调进行控制。从而可以判断室外换热器2与室内换热器6之间的冷媒管路上设置的第一截止阀3是否开启,并当第一截止阀3未开启时,关闭空调,以避免在第一截止阀3未打开的情况下误开空调,而导致空调损坏或者发生安全事故的问题。
作为本实施例提供的上述控制方法的一种优选的实施方式,“基于排气压力的变化量的比较结果以及电子膨胀阀5的开度值的比较结果,对空调进行控制”的步骤具体包括:若排气压力的变化量大于排气压力变化阈值,同时电子膨胀阀5的开度值小于设定开度值,则将电子 膨胀阀5的开度值调节至大于或等于设定开度值,并继续基于排气压力的变化量的比较结果,对空调进行控制。
示例性地,由于电子膨胀阀5的开度较小时,也会影响排气压力的变化量,所以当监测到电子膨胀阀5的开度小于设定值时,需要将电子膨胀阀5的开度值调节至大于或等于设定开度值,并继续对压缩机1的排气压力进行监测、比较,然后再基于排气压力的变化量的比较结果,对空调进行控制,以排除电子膨胀阀5的开度对单位时间内排气压力的变化量的不正常影响。
然后,再将电子膨胀阀5的开度值调节至大于或等于设定开度值之后,“基于排气压力的变化量的比较结果,对空调进行控制”的步骤具体包括:获取排气压力的变化量大于排气压力变化阈值的持续时间;若持续时间大于预设的时间阈值,则关闭空调。
作为本实施例提供的上述控制方法的一种优选的实施方式,“基于排气压力的变化量的比较结果以及电子膨胀阀5的开度值的比较结果,对空调进行控制”的步骤具体包括:若排气压力的变化量大于排气压力变化阈值,同时电子膨胀阀5的开度值大于或等于设定开度值,则获取排气压力的变化量大于排气压力变化阈值的持续时间;若持续时间大于预设的时间阈值,关闭空调。
其中,获取排气压力的变化量大于排气压力变化阈值的持续时间,可以更可靠的确定第一截止阀3是否打开。若其持续时间大于预设的时间阈值,则说明第一截止阀3确实未打开,此时则关闭空调,避免对空调造成损坏或发生危险。
作为本实施例提供的上述控制方法的一种优选的实施方式,控制方法还包括:在关闭空调的同时,发出第一截止阀3未打开的提示。例如,空调发出警报音,且空调上的显示器也显示报错信息,以提醒空调安装人员注意。
上述实施例示出了为避免由于第一截止阀3(液管截止阀)未打开,而导致空调损坏或发生安全事故,所需的空调的控制方法的具体实施方式。下面则对为避免由于第二截止阀7(气管截止阀)未打开,而导致空调损坏或发生安全事故,所需的空调的控制方法的具体实施方 式进行说明。二者在原理上是相同的,均是基于冷媒管路上的气压变化是否正常对空调进行控制的。
此外,本实施例提供的另一种空调的控制方法,空调包括压缩机1、室内换热器6和室外换热器2,且室外换热器2与室内换热器6之间的冷媒管路上设置有电子膨胀阀5,室内换热器6与压缩机1之间的冷媒管路上设置有第二截止阀7,如图3所示,该控制方法包括:
S21、获取压缩机1的吸气压力以及电子膨胀阀5的开度值;
S22、计算空调开启后单位时间内吸气压力的变化量;
S23、将吸气压力的变化量与预设的吸气压力变化阈值进行比较;
S24、将电子膨胀阀5的开度值与设定开度值进行比较;
S25、基于吸气压力的变化量的比较结果以及电子膨胀阀5的开度值的比较结果,对空调进行控制。
示例性地,如图1中的空调,吸气压力传感器12可以用来监测并获取压缩机1的排气压力,电子膨胀阀5的开度也可以用专门的监测仪器来获取。
单位时间内吸气压力的变化量可以为3s、5s等一段时间作为单位时间内的变化量,或者空调开启后的一段时间内吸气压力的变化量,该时间的设置以空调中冷媒管路上的压力上升到安全值所用的安全时间作为参考,不应超过该安全时间,例如,可以取该时间的十分之一作为单位时间。
吸气压力变化阈值可以参考压缩机1正常工作时的正常变化值,针对不同的空调该值可能存在差别。此外,将电子膨胀阀5的开度值与设定开度值进行比较,从而可以排除电子膨胀阀5的开度太小而对单位时间内吸气压力的变化量造成不正常影响的因素。
需要说明的是,尽管上文详细描述了本发明方法的详细步骤,但是,在不偏离本发明的基本原理的前提下,本领域技术人员可以对上述步骤进行组合、拆分及调换顺序,如此修改后的技术方案并没有改变本发明的基本构思,因此也落入本发明的保护范围之内。例如,在先进行步骤S22再进行步骤S23的前提下,步骤S24还可以在步骤S21和S22之间进行,或者步骤S24还可以在步骤S22和S23之间进行。再如,步 骤S21中在获取压缩机1的吸气压力以及电子膨胀阀5的开度值时,可以同时进行,也可以按顺序先后进行,且顺序上没有特殊要求。
本实施例提供的空调的控制方法,通过基于空调开启后压缩机1的吸气压力在单位时间内的变化量与预设的吸气压力变化阈值的比较结果,以及电子膨胀阀5的开度值与设定开度值的比较结果,对空调进行控制。从而可以判断室内换热器6与压缩机1之间的冷媒管路上设置的第二截止阀7是否开启,并当第二截止阀7未开启时,关闭空调,以避免在第二截止阀7未打开的情况下误开空调,而导致空调损坏或者发生安全事故的问题。
作为本实施例提供的上述控制方法的一种优选的实施方式,“基于吸气压力的变化量的比较结果以及电子膨胀阀5的开度值的比较结果,对空调进行控制”的步骤具体包括:若吸气压力的变化量大于预设的吸气压力变化阈值,同时电子膨胀阀5的开度值小于设定开度值,则将电子膨胀阀5的开度值调节至大于或等于设定开度值,并继续基于吸气压力的变化量的比较结果,对空调进行控制。
示例性地,由于电子膨胀阀5的开度较小时,也会影响吸气压力的变化量,所以当监测到电子膨胀阀5的开度小于设定值时,需要将电子膨胀阀5的开度值调节至大于或等于设定开度值,并继续对压缩机1的吸气压力进行监测、比较,然后再基于吸气压力的变化量的比较结果,对空调进行控制,以排除电子膨胀阀5的开度对单位时间内吸气压力的变化量的不正常影响。
然后,再将电子膨胀阀5的开度值调节至大于或等于设定开度值之后,“基于吸气压力的变化量的比较结果,对空调进行控制”的步骤具体包括:获取吸气压力的变化量大于吸气压力变化阈值的持续时间;若持续时间大于预设的时间阈值,则关闭空调。
作为本实施例提供的上述控制方法的一种优选的实施方式,“基于吸气压力的变化量的比较结果以及电子膨胀阀5的开度值的比较结果,对空调进行控制”的步骤具体包括:若吸气压力的变化量大于吸气压力变化阈值,同时电子膨胀阀5的开度值大于或等于设定开度值,获取吸气压力的变化量大于吸气压力变化阈值的持续时间;若持续时间大于预设的时间阈值,则关闭空调。
其中,获取吸气压力的变化量大于吸气压力变化阈值的持续时间,可以更可靠的确定第二截止阀7是否打开。若其持续时间大于预设的时间阈值,则说明第二截止阀7确实未打开,此时则关闭空调,避免对空调造成损坏或发生危险。
作为本实施例提供的上述控制方法的一种优选的实施方式,控制方法还包括:在关闭空调的同时,发出第二截止阀7未打开的提示。例如,空调发出警报音,且空调上的显示器也显示报错信息,以提醒空调安装人员注意。
当然,上述可以替换的实施方式之间、以及可以替换的实施方式和优选的实施方式之间还可以交叉配合使用,从而组合出新的实施方式以适用于更加具体的应用场景。例如,可以将步骤S11与步骤S21进行组合,即在第一个步骤中可以获取压缩机1的吸气压力、排气压力以及电子膨胀阀5的开度值,相应的对两个实施方式的之后的步骤进行组合,以同时对第一截止阀3和第二截止阀7是否处于打开状态进行判断,并对空调进行控制。
本领域的技术人员应当理解的是,可以将本实施例提供的空调对控制方法作为程序存储在一个计算机可读取存储介质中。该存储介质中包括若干指令用以使得一台计算机设备(可以是个人计算机,服务器,或者网络设备等)或处理器(processor)执行本发明各个实施例方法的部分步骤。而前述的存储介质包括:U盘、移动硬盘、只读存储器(Read-Only Memory,ROM)、随机存取存储器(Random Access Memory,RAM)、磁碟或者光盘等各种可以存储程序代码的介质。
此外,本领域的技术人员能够理解,尽管在此所述的一些实施例包括其它实施例中所包括的某些特征而不是其它特征,但是不同实施例的特征的组合意味着处于本发明的保护范围之内并且形成不同的实施例。例如,在本发明的权利要求书中,所要求保护的实施例的任意之一都可以以任意的组合方式来使用。
至此,已经结合附图所示的优选实施方式描述了本发明的技术方案,但是,本领域技术人员容易理解的是,本发明的保护范围显然不局限于这些具体实施方式。在不偏离本发明的原理的前提下,本领域 技术人员可以对相关技术特征作出等同的更改或替换,这些更改或替换之后的技术方案都将落入本发明的保护范围之内。

Claims (10)

  1. 一种空调的控制方法,所述空调包括压缩机、室内换热器和室外换热器,所述室外换热器与所述室内换热器之间的冷媒管路上设置有第一截止阀和电子膨胀阀,其特征在于,所述控制方法包括:
    获取压缩机的排气压力以及所述电子膨胀阀的开度值;
    计算空调开启后单位时间内所述排气压力的变化量;
    将所述排气压力的变化量与预设的排气压力变化阈值进行比较;
    将所述电子膨胀阀的开度值与设定开度值进行比较;
    基于所述排气压力的变化量的比较结果以及所述电子膨胀阀的开度值的比较结果,对所述空调进行控制。
  2. 根据权利要求1所述的控制方法,其特征在于,“基于所述排气压力的变化量的比较结果以及所述电子膨胀阀的开度值的比较结果,对所述空调进行控制”的步骤具体包括:
    若所述排气压力的变化量大于所述排气压力变化阈值,同时所述电子膨胀阀的开度值小于所述设定开度值,则将所述电子膨胀阀的开度值调节至大于或等于所述设定开度值,并继续基于所述排气压力的变化量的比较结果,对所述空调进行控制。
  3. 根据权利要求1所述的控制方法,其特征在于,“基于所述排气压力的变化量的比较结果以及所述电子膨胀阀的开度值的比较结果,对所述空调进行控制”的步骤具体包括:
    若所述排气压力的变化量大于所述排气压力变化阈值,同时所述电子膨胀阀的开度值大于或等于设定开度值,则获取所述排气压力的变化量大于所述排气压力变化阈值的持续时间;
    若所述持续时间大于预设的时间阈值,关闭所述空调。
  4. 根据权利要求2所述的控制方法,其特征在于,“基于所述排气压力的变化量的比较结果,对所述空调进行控制”的步骤具体包括:
    获取所述排气压力的变化量大于所述排气压力变化阈值的持续时间;
    若所述持续时间大于预设的时间阈值,则关闭所述空调。
  5. 根据权利要求3或4所述的控制方法,其特征在于,所述控制方法还包括:
    在关闭所述空调的同时,发出所述第一截止阀未打开的提示。
  6. 一种空调的控制方法,所述空调包括压缩机、室内换热器和室外换热器,且所述室外换热器与所述室内换热器之间的冷媒管路上设置有电子膨胀阀,所述室内换热器与所述压缩机之间的冷媒管路上设置有第二截止阀,其特征在于,所述控制方法包括:
    获取压缩机的吸气压力以及所述电子膨胀阀的开度值;
    计算空调开启后单位时间内所述吸气压力的变化量;
    将所述吸气压力的变化量与预设的吸气压力变化阈值进行比较;
    将所述电子膨胀阀的开度值与设定开度值进行比较;
    基于所述吸气压力的变化量的比较结果以及所述电子膨胀阀的开度值的比较结果,对所述空调进行控制。
  7. 根据权利要求6所述的控制方法,其特征在于,“基于所述吸气压力的变化量的比较结果以及所述电子膨胀阀的开度值的比较结果,对所述空调进行控制”的步骤具体包括:
    若所述吸气压力的变化量大于预设的吸气压力变化阈值,同时所述电子膨胀阀的开度值小于设定开度值,则将所述电子膨胀阀的开度值调节至大于或等于设定开度值,并继续基于所述吸气压力的变化量的比较结果,对所述空调进行控制。
  8. 根据权利要求6所述的控制方法,其特征在于,“基于所述吸气压力的变化量的比较结果以及所述电子膨胀阀的开度值的比较结果,对所述空调进行控制”的步骤具体包括:
    若所述吸气压力的变化量大于所述吸气压力变化阈值,同时所述电子膨胀阀的开度值大于或等于设定开度值,获取所述吸气压力的变化量大于所述吸气压力变化阈值的持续时间;
    若所述持续时间大于预设的时间阈值,则关闭所述空调。
  9. 根据权利要求7所述的控制方法,其特征在于,“基于所述吸气压力的变化量的比较结果,对所述空调进行控制”的步骤具体包括:
    获取所述吸气压力的变化量大于所述吸气压力变化阈值的持续时间;
    若所述持续时间大于预设的时间阈值,则关闭所述空调。
  10. 根据权利要求8或9所述的控制方法,其特征在于,所述控制方法还包括:
    在关闭所述空调的同时,发出所述第二截止阀未打开的提示。
PCT/CN2020/126443 2020-02-26 2020-11-04 空调的控制方法 WO2021169391A1 (zh)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202010120478.3 2020-02-26
CN202010120478.3A CN111425996B (zh) 2020-02-26 2020-02-26 空调的控制方法

Publications (1)

Publication Number Publication Date
WO2021169391A1 true WO2021169391A1 (zh) 2021-09-02

Family

ID=71547996

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2020/126443 WO2021169391A1 (zh) 2020-02-26 2020-11-04 空调的控制方法

Country Status (2)

Country Link
CN (1) CN111425996B (zh)
WO (1) WO2021169391A1 (zh)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111425996B (zh) * 2020-02-26 2022-11-22 青岛海尔空调电子有限公司 空调的控制方法

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2265229B (en) * 1992-03-16 1995-04-26 Toshiba Kk Air-conditioning apparatus having heat source unit and plural indoor units connected to the heat source unit
JP2001174112A (ja) * 1999-12-21 2001-06-29 Toshiba Kyaria Kk 空気調和機
CN1766445A (zh) * 2004-10-26 2006-05-03 Lg电子株式会社 检测热泵型复式空调的管道的阻塞状态的系统及方法
CN102401447A (zh) * 2011-05-24 2012-04-04 宁波奥克斯电气有限公司 Vrv空调室内侧管路部分堵塞导致故障停机的处理方法
CN104896785A (zh) * 2015-05-15 2015-09-09 广东美的暖通设备有限公司 一种喷气增焓多联机空调系统及其控制方法
CN107091517A (zh) * 2017-06-30 2017-08-25 珠海格力电器股份有限公司 空调机组的保护控制方法、装置以及空调机组
CN107763889A (zh) * 2017-11-21 2018-03-06 宁波奥克斯电气股份有限公司 一种多联机空调系统及其控制方法
CN110173810A (zh) * 2019-05-27 2019-08-27 广东美的制冷设备有限公司 空调器及其控制方法和装置
US20190360731A1 (en) * 2018-05-23 2019-11-28 Carrier Corporation Refrigerant transfer control in multi mode air conditioner with hot water generator
CN111425996A (zh) * 2020-02-26 2020-07-17 青岛海尔空调电子有限公司 空调的控制方法

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101089494B (zh) * 2006-06-16 2011-07-06 乐金电子(天津)电器有限公司 空调电子膨胀阀控制方法
CN101832621A (zh) * 2010-04-30 2010-09-15 中国科学院广州能源研究所 一种多联机空调系统自保护控制方法以及自保护控制装置
CN102434915B (zh) * 2011-09-20 2013-10-30 海信(山东)空调有限公司 空调器及空调器的控制方法
CN104197572B (zh) * 2014-09-01 2016-04-13 广东志高暖通设备股份有限公司 一种三管制热回收多联机系统
CN108375170B (zh) * 2018-02-12 2020-05-15 海信(山东)空调有限公司 一种电子膨胀阀的控制方法、装置及空调器
CN108758975B (zh) * 2018-06-12 2020-11-13 广东美的暖通设备有限公司 空调系统的控制方法、系统及空调

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2265229B (en) * 1992-03-16 1995-04-26 Toshiba Kk Air-conditioning apparatus having heat source unit and plural indoor units connected to the heat source unit
JP2001174112A (ja) * 1999-12-21 2001-06-29 Toshiba Kyaria Kk 空気調和機
CN1766445A (zh) * 2004-10-26 2006-05-03 Lg电子株式会社 检测热泵型复式空调的管道的阻塞状态的系统及方法
CN102401447A (zh) * 2011-05-24 2012-04-04 宁波奥克斯电气有限公司 Vrv空调室内侧管路部分堵塞导致故障停机的处理方法
CN104896785A (zh) * 2015-05-15 2015-09-09 广东美的暖通设备有限公司 一种喷气增焓多联机空调系统及其控制方法
CN107091517A (zh) * 2017-06-30 2017-08-25 珠海格力电器股份有限公司 空调机组的保护控制方法、装置以及空调机组
CN107763889A (zh) * 2017-11-21 2018-03-06 宁波奥克斯电气股份有限公司 一种多联机空调系统及其控制方法
US20190360731A1 (en) * 2018-05-23 2019-11-28 Carrier Corporation Refrigerant transfer control in multi mode air conditioner with hot water generator
CN110173810A (zh) * 2019-05-27 2019-08-27 广东美的制冷设备有限公司 空调器及其控制方法和装置
CN111425996A (zh) * 2020-02-26 2020-07-17 青岛海尔空调电子有限公司 空调的控制方法

Also Published As

Publication number Publication date
CN111425996A (zh) 2020-07-17
CN111425996B (zh) 2022-11-22

Similar Documents

Publication Publication Date Title
US10767882B2 (en) Refrigerant pump down for an HVAC system
CN103134142B (zh) 空调系统全堵的检测方法
CN108317662B (zh) 故障检测方法、装置、空调器和计算机可读存储介质
WO2020024695A1 (zh) 空调器的控制方法、控制装置及空调器
WO2022237912A1 (zh) 多联机中内机电子膨胀阀的控制方法
CN109357443B (zh) 一种电子膨胀阀开度控制方法、装置及多联机系统
WO2022183986A1 (zh) 多联机空调系统的控制方法
WO2021169391A1 (zh) 空调的控制方法
CN108278715A (zh) 一种空调机缺氟保护方法及具有缺氟保护功能的空调机
WO2020177284A1 (zh) 防止空调器的压缩机液击的控制方法及控制系统
CN110173816B (zh) 一种空调制冷剂泄漏的检测方法及检测装置
JP3491449B2 (ja) 故障診断付き空気調和装置
WO2023274228A1 (zh) 空调器的起火检测控制方法
JP3915819B2 (ja) 空気調和装置
WO2022194218A1 (zh) 一拖多空调器的压缩机频率的控制方法及一拖多空调器
WO2022041623A1 (zh) 感温包安装状态检测方法、装置、风管机空调器及介质
WO2021174915A1 (zh) 提高循环冷媒量的控制方法、装置及空调
WO2023197711A1 (zh) 多联机空调系统、故障定位方法及故障诊断模型训练方法
CN114659547B (zh) 用于定位异常传感器的方法、设备和介质
CN112212462B (zh) 一种空调器及其控制方法
JP7361935B2 (ja) 空気調和機診断装置
CN107355951B (zh) 空调制冷模式控制方法、装置以及空调
CN110398035B (zh) 空调器室内风机故障检测方法、装置及可读存储介质
WO2017098577A1 (ja) 圧縮機劣化診断装置および圧縮機劣化診断方法
CN111271819B (zh) 一种多联机系统可靠性的控制方法

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 20921964

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 20921964

Country of ref document: EP

Kind code of ref document: A1