Prior art keywords
rod
link
climbing frame
fixed
positioning holes
Prior art date
Application number
PCT/CN2020/132409
Other languages
French (fr)
Chinese (zh)
Inventor
魏群
张敏
王坤
柳良成
Original Assignee
江苏盛浩工程科技有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 江苏盛浩工程科技有限公司 filed Critical 江苏盛浩工程科技有限公司
Publication of WO2021135777A1 publication Critical patent/WO2021135777A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds

Definitions

  • the application relates to the technical field of building construction, and specifically is a connection structure of a climbing frame protection net frame and a vertical pole.
  • the climbing frame is also called the lifting frame. According to its power source, it can be divided into hydraulic type, electric type, and manual hand-pulled type. It is a new type of scaffolding system developed in recent years. It is mainly used in high-rise shear wall buildings. It can climb or descend along the building. This system completely changes the scaffolding technology: one is that there is no need to turn over the shelf; the other is that it eliminates the disassembly and assembly process of the scaffold, and is not limited by the height of the building, which greatly saves manpower and materials, and is also safe from the traditional perspective. The scaffolding has been greatly improved.
  • the protective screen frame of the climbing frame when installing the protective screen frame of the climbing frame, it is mainly connected by a pin.
  • the connection between the protective screen frame of the climbing frame and the pole is unstable, and the function of the scissor support cannot be realized, and the stability is low; at the same time, the pin is easy to fall off, which is easy to Causes the climbing frame protection net frame to fall off, increasing the safety hazard.
  • the purpose of the present application is to provide a connection structure between the climbing frame protection net frame and the vertical pole, so as to solve the problems raised in the background art.
  • this application provides the following technical solution: a connecting structure of a climbing frame protection net frame and a vertical pole, comprising a vertical pole and a plurality of climbing frame protection net frames on the left and right sides of the vertical pole, the climbing frame protection
  • Two connecting pieces are respectively fixed on both sides of the screen frame, the connecting piece is provided with a first positioning hole, and the vertical rod is provided with two U-shaped connecting seats corresponding to the two connecting pieces.
  • the left and right sides of the U-shaped connecting seat are respectively provided with third positioning holes.
  • the first positioning hole and the third positioning hole are provided with a fastening screw, and one end of the fastening screw is provided with a matching tightening hole. Fasten the nut.
  • a fixing block is installed inside the U-shaped connecting seat, and a second positioning hole is opened on the fixing block, the fastening screw also passes through the second positioning hole, and the upper and lower sides of the fixing block are respectively
  • a fixing plate is fixed, and symmetrically arranged left and right links are respectively fixed on the opposite sides of the two fixing plates, and the ends of the left and right links away from the fixing plate are respectively fixed with a limit stop
  • each of the limit sleeves is provided with a corresponding limit rod
  • the limit rod near the center of the left link is fixedly connected to the climbing frame on the left side of the vertical rod
  • the limit rod close to the center of the right link is fixedly connected to the climbing frame protective screen frame on the right side of the vertical rod.
  • the length of the left link and the right link are equal, the angle between the left link and the right link above the fixed block is 40-50 degrees, and the fixed block
  • the axes of the upper left link and the lower right link are collinear.
  • the end surface of the fixing block close to the U-shaped connecting seat is adapted to the installation groove opened on the U-shaped connecting seat, and the U-shaped connecting seat is placed in the installation groove.
  • the connecting piece includes an L-shaped plate, a triangular plate is fixed on both sides of the L-shaped plate, and the first positioning hole is provided on the L-shaped plate.
  • the beneficial effects achieved by this application are: in this application, connecting pieces are fixed on both sides of the climbing frame protective screen frame, and the U-shaped connection between the fastening screw and the fastening nut and the vertical rod is provided.
  • the base is connected, and the fastening screw is passed through the fixing block on the U-shaped connecting base.
  • the limit sleeves on the left link and the right link on the upper and lower sides of the fixing block are sleeved on the climbing frame protection net on both sides of the vertical pole.
  • the climbing frame protection screen frame is not embedded in the vertical pole, ensuring that the climbing frame protection screen frame realizes a horizontal connection and a vertical connection firmly, which promotes the climbing frame protection screen frame to be installed as a whole Frame-shear structure; at the same time, the fixed block and the left and right connecting rods on the upper and lower sides form an X structure to further improve the stability of the connection; and the installation operation is completed within the protection range of the climbing frame, and the installation and disassembly work is simple. Solved the problems of workers' installation risks and operation difficulties.
  • Figure 1 is a schematic diagram of the overall structure of the application
  • Figure 2 is a schematic diagram of the installation of the fixed block of the present application.
  • FIG. 3 is a schematic diagram of the structure of area A in FIG. 2 of the present application
  • FIG. 4 is a schematic view of the structure of the connecting piece of the present application
  • Figure 5 is a schematic diagram of the installation of the left link and the right link of the present application.
  • Fig. 6 is a schematic diagram of the connection between the climbing frame protection net frame and the vertical pole of the present application.
  • this application provides a technical solution: a connecting structure of a climbing frame protection net frame and a vertical pole, including a vertical pole 5 and multiple climbing frame protection screen frames 1 on the left and right sides of the vertical pole 5.
  • Two connecting pieces 7 are respectively fixed on both sides of the protective screen frame 1, the connecting piece 7 is provided with a first positioning hole 73, and the vertical rod 5 is provided with two U-shaped connecting seats 9 corresponding to the two connecting pieces 7 respectively.
  • the left and right sides of the U-shaped connecting seat 9 are respectively provided with third positioning holes 92, the first positioning hole 73 and the third positioning hole 92 are penetrated with a fastening screw 2, and one end of the fastening screw 2 is provided with a corresponding Matched fastening nut 6.
  • a fixing block 8 is installed inside the U-shaped connecting seat 9, and the fixing block 8 is provided with a second positioning hole 81,
  • the fastening screw 2 also passes through the second positioning hole 81.
  • the upper and lower sides of the fixing block 8 are respectively fixed with a fixing plate 4, and the opposite sides of the two fixing plates 4 are respectively fixed with a symmetrical left connecting rod 41 and a right connecting rod. 42.
  • One end of the left connecting rod 41 and the right connecting rod 42 away from the fixing plate 4 is respectively fixed with a limiting sleeve 3, and a matching limiting rod 11 is installed inside each limiting sleeve 3, which is close to the left connecting rod
  • the limit rod 11 in the center of 41 is fixed to the climbing frame protection screen frame 1 on the left side of the vertical rod 5, and the limit rod 11 near the center of the right connecting rod 42 is fixed to the climbing frame protection screen frame 1 on the right side of the vertical rod 5
  • the climbing frame protection screen frame 1 on the left and right sides of the vertical rod 5 is connected with the vertical rod 5 to improve the stability of the connection.
  • the left connecting rod 41 and the right connecting rod 42 are fixed to the fixed plate 4 by welding, which improves the stability of the connection between the fixed plate 4 and the fixed block 8, the left connecting rod 41 and the right connecting rod 42.
  • the length of the left link 41 and the right link 42 are equal, the angle between the left link 41 and the right link 42 above the fixed block 8 is 40-50 degrees, and the left link 41 above the fixed block 8 and below it
  • the axes of the right connecting rod 42 are collinear, so that the fixed block 8 and the left connecting rod 41 and the right connecting rod 42 on the upper and lower sides of the fixed block 8 form an X structure, which further improves the stability of the connection.
  • the end surface of the fixing block 8 close to the U-shaped connecting seat 9 is adapted to the installation groove 91 opened on the U-shaped connecting seat 9, and the U-shaped connecting seat 9 is placed in the installation groove 91 to facilitate the installation and limitation of the fixing block 8.
  • the connecting piece 7 includes an L-shaped plate 71. Triangular plates 72 are fixed on both sides of the L-shaped plate 71. The first positioning hole 73 is provided on the L-shaped plate 71. The two triangular plates 72 improve the stability of the connecting piece 7 to prevent L The template 71 is deformed.
  • the protective screen frame is an integral frame-shear structure when installed; at the same time, the fixed block 8 and the left link 41 and right link 42 on the upper and lower sides form an X-shaped structure to further improve the stability; and the installation operations are all in the protection of the climbing frame It is completed within the scope, the installation and disass

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mutual Connection Of Rods And Tubes (AREA)
  • Fencing (AREA)

Abstract

A connecting structure for climbing scaffolding protective reticulated panels and an upright pole, comprising an upright pole (5) and multiple climbing scaffolding protective reticulated panels (1) on the left and right side of the upright pole (5). Two connecting pieces (7) respectively are fixed at either side edge of the climbing scaffolding protective reticulated panels (1). First positioning holes (73) are provided on the connecting pieces (7). Two U-shaped connecting bases (9) corresponding respectively to the two connecting pieces (7) are provided on the upright pole (5). Third positioning holes (92) respectively are provided on the left and right side of the U-shaped connecting bases (9). Fastening screws (2) are provided running through the first positioning holes (73) and the third positioning holes (92). The fastening screws (2) are provided at one end with a fastening nut (6) mated therewith. Fixing blocks (8) are mounted within the U-shaped connecting base (9). Second positioning holes (81) are provided on the fixing blocks (8). The fastening screws (2) also run through the second positioning holes (81). Fixing plates (4) respectively are fixed on the upper and lower sides of the fixing blocks (8). The connecting structure is characterized by strong stability and convenient mounting and solves the problem of mounting risks for workers and great operating difficulty.

Description

一种爬架防护网框和立杆的连接结构Connecting structure of climbing frame protection net frame and vertical pole 技术领域Technical field
本申请涉及建筑施工技术领域,具体为一种爬架防护网框和立杆的连接结构。The application relates to the technical field of building construction, and specifically is a connection structure of a climbing frame protection net frame and a vertical pole.
背景技术Background technique
爬架又叫提升架,依照其动力来源可分为液压式、电动式、人力手拉式等主要几类。它是近年来开发的新型脚手架体系,主要应用于高层剪力墙式楼盘,它能沿着建筑物进行攀升或下降。这种体系使脚手架技术完全改观:一是不必翻架子;二是免除了脚手架的拆装工序,且不受建筑物高度的限制,极大的节省了人力和材料,并且在安全角度也对于传统的脚手架有较大的改观。The climbing frame is also called the lifting frame. According to its power source, it can be divided into hydraulic type, electric type, and manual hand-pulled type. It is a new type of scaffolding system developed in recent years. It is mainly used in high-rise shear wall buildings. It can climb or descend along the building. This system completely changes the scaffolding technology: one is that there is no need to turn over the shelf; the other is that it eliminates the disassembly and assembly process of the scaffold, and is not limited by the height of the building, which greatly saves manpower and materials, and is also safe from the traditional perspective. The scaffolding has been greatly improved.
而目前对爬架防护网框安装时,主要是使用销轴连接,爬架防护网框与立杆的连接不稳定,不能实现剪刀撑的作用,稳固性低;同时销轴易脱落,从而易造成爬架防护网框的脱落,增加了安全隐患。At present, when installing the protective screen frame of the climbing frame, it is mainly connected by a pin. The connection between the protective screen frame of the climbing frame and the pole is unstable, and the function of the scissor support cannot be realized, and the stability is low; at the same time, the pin is easy to fall off, which is easy to Causes the climbing frame protection net frame to fall off, increasing the safety hazard.
发明内容Summary of the invention
本申请的目的在于提供一种爬架防护网框和立杆的连接结构,以解决上述背景技术中提出的问题。The purpose of the present application is to provide a connection structure between the climbing frame protection net frame and the vertical pole, so as to solve the problems raised in the background art.
为了解决上述技术问题,本申请提供如下技术方案:一种爬架防护网框和立杆的连接结构,包括立杆和立杆左右两侧的多个爬架防护网框,所述爬架防护网框的两侧边缘分别固定有两连接片,所述连接片上开设有第一定位孔,所述立杆上设有两个分别与两所述连接片相对应的U型连接座,所述U型连接座的左右两侧分别开设有第三定位孔,所述第一定位孔和第三定位孔内穿设有一紧固螺钉,所述紧固螺钉的一端设有与其相适配的紧固螺母。In order to solve the above technical problems, this application provides the following technical solution: a connecting structure of a climbing frame protection net frame and a vertical pole, comprising a vertical pole and a plurality of climbing frame protection net frames on the left and right sides of the vertical pole, the climbing frame protection Two connecting pieces are respectively fixed on both sides of the screen frame, the connecting piece is provided with a first positioning hole, and the vertical rod is provided with two U-shaped connecting seats corresponding to the two connecting pieces. The left and right sides of the U-shaped connecting seat are respectively provided with third positioning holes. The first positioning hole and the third positioning hole are provided with a fastening screw, and one end of the fastening screw is provided with a matching tightening hole. Fasten the nut.
进一步的,所述U型连接座的内部安装有固定块,所述固定块上开设有第二定位孔,所述紧固螺钉还穿过第二定位孔,所述固定块的上下两侧分别固定有一固定板,两所述固定板相背的一侧分别固定有对称设置的左连杆和右连杆, 所述左连杆和右连杆远离所述固定板的一端分别固定有一限位套筒,各所述限位套筒的内部安装有与其相适配的限位杆,靠近所述左连杆中心的所述限位杆固接于所述立杆左侧的所述爬架防护网框上,靠近所述右连杆中心的所述限位杆固接于所述立杆右侧的所述爬架防护网框上。Further, a fixing block is installed inside the U-shaped connecting seat, and a second positioning hole is opened on the fixing block, the fastening screw also passes through the second positioning hole, and the upper and lower sides of the fixing block are respectively A fixing plate is fixed, and symmetrically arranged left and right links are respectively fixed on the opposite sides of the two fixing plates, and the ends of the left and right links away from the fixing plate are respectively fixed with a limit stop A sleeve, each of the limit sleeves is provided with a corresponding limit rod, and the limit rod near the center of the left link is fixedly connected to the climbing frame on the left side of the vertical rod On the protective screen frame, the limit rod close to the center of the right link is fixedly connected to the climbing frame protective screen frame on the right side of the vertical rod.
进一步的,所述左连杆和所述右连杆的长度相等,所述固定块上方的所述左连杆和所述右连杆之间的夹角为40-50度,所述固定块上方的所述左连杆和其下方的所述右连杆的轴线共线。Further, the length of the left link and the right link are equal, the angle between the left link and the right link above the fixed block is 40-50 degrees, and the fixed block The axes of the upper left link and the lower right link are collinear.
进一步的,所述固定块靠近所述U型连接座的端面与所述U型连接座上开设的安装槽相适配,且所述U型连接座置于所述安装槽内。Further, the end surface of the fixing block close to the U-shaped connecting seat is adapted to the installation groove opened on the U-shaped connecting seat, and the U-shaped connecting seat is placed in the installation groove.
进一步的,所述连接片包括L型板,所述L型板的两侧固定有三角形板,所述第一定位孔设于L型板上。Further, the connecting piece includes an L-shaped plate, a triangular plate is fixed on both sides of the L-shaped plate, and the first positioning hole is provided on the L-shaped plate.
与现有技术相比,本申请所达到的有益效果是:本申请,通过设置有爬架防护网框两侧边缘固定有连接片,通过紧固螺钉和紧固螺母与立杆的U型连接座相连接,同时使紧固螺钉穿过U型连接座上的固定块,固定块上下两侧的左连杆和右连杆上的限位套筒套设于立杆两侧爬架防护网框上的限位杆外部,爬架防护网框不嵌入立杆中,保证各爬架防护网框之间实现了横向连接和竖向的稳固连接,促使爬架防护网框安装时为一个整体框剪结构;同时固定块及其上下两侧的左连杆和右连杆形成X结构,进一步提高连接的稳固性;并且安装操作都是在爬架的防护范围内完成,安装拆卸工作简便,解决的工人的安装风险和操作难度大问题。Compared with the prior art, the beneficial effects achieved by this application are: in this application, connecting pieces are fixed on both sides of the climbing frame protective screen frame, and the U-shaped connection between the fastening screw and the fastening nut and the vertical rod is provided. The base is connected, and the fastening screw is passed through the fixing block on the U-shaped connecting base. The limit sleeves on the left link and the right link on the upper and lower sides of the fixing block are sleeved on the climbing frame protection net on both sides of the vertical pole. Outside the limit bar on the frame, the climbing frame protection screen frame is not embedded in the vertical pole, ensuring that the climbing frame protection screen frame realizes a horizontal connection and a vertical connection firmly, which promotes the climbing frame protection screen frame to be installed as a whole Frame-shear structure; at the same time, the fixed block and the left and right connecting rods on the upper and lower sides form an X structure to further improve the stability of the connection; and the installation operation is completed within the protection range of the climbing frame, and the installation and disassembly work is simple. Solved the problems of workers' installation risks and operation difficulties.
附图说明Description of the drawings
附图用来提供对本申请的进一步理解,并且构成说明书的一部分,与本申请的实施例一起用于解释本申请,并不构成对本申请的限制。在附图中:The accompanying drawings are used to provide a further understanding of the application, and constitute a part of the specification. Together with the embodiments of the application, they are used to explain the application, and do not constitute a limitation to the application. In the attached picture:
图1是本申请的整体结构示意图;Figure 1 is a schematic diagram of the overall structure of the application;
图2是本申请的固定块安装示意图;Figure 2 is a schematic diagram of the installation of the fixed block of the present application;
图3是本申请的图2中A区域结构示意图;图4是本申请的连接片结构示意图;FIG. 3 is a schematic diagram of the structure of area A in FIG. 2 of the present application; FIG. 4 is a schematic view of the structure of the connecting piece of the present application;
图5是本申请的左连杆、右连杆安装示意图;Figure 5 is a schematic diagram of the installation of the left link and the right link of the present application;
图6是本申请的爬架防护网框和立杆连接示意图;Fig. 6 is a schematic diagram of the connection between the climbing frame protection net frame and the vertical pole of the present application;
图中:1、爬架防护网框;11、限位杆;2、紧固螺钉;3、限位套筒;4、固定板;41、左连杆;42、右连杆;5、立杆;6、紧固螺母;7、连接片;71、L型板;72、三角形板;73、第一定位孔;8、固定块;81、第二定位孔;9、U型连接座;91、安装槽;92、第三定位孔。In the picture: 1. Climbing frame protective net frame; 11. Limit rod; 2. Fastening screw; 3. Limit sleeve; 4. Fixed plate; 41. Left connecting rod; 42, Right connecting rod; 5. Standing Rod; 6, fastening nut; 7, connecting piece; 71, L-shaped plate; 72, triangular plate; 73, first positioning hole; 8, fixing block; 81, second positioning hole; 9, U-shaped connecting seat; 91. Mounting groove; 92. The third positioning hole.
具体实施方式Detailed ways
下面将结合本申请实施例中的附图,对本申请实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本申请一部分实施例,而不是全部的实施例。基于本申请中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本申请保护的范围。The technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present application. Obviously, the described embodiments are only a part of the embodiments of the present application, rather than all the embodiments. Based on the embodiments in this application, all other embodiments obtained by those of ordinary skill in the art without creative work shall fall within the protection scope of this application.
请参阅图1-6,本申请提供技术方案:一种爬架防护网框和立杆的连接结构,包括立杆5和立杆5左右两侧的多个爬架防护网框1,爬架防护网框1的两侧边缘分别固定有两连接片7,连接片7上开设有第一定位孔73,立杆5上设有两个分别与两连接片7相对应的U型连接座9,U型连接座9的左右两侧分别开设有第三定位孔92,第一定位孔73和第三定位孔92内穿设有一紧固螺钉2,紧固螺钉2的一端设有与其相适配的紧固螺母6。Please refer to Figure 1-6, this application provides a technical solution: a connecting structure of a climbing frame protection net frame and a vertical pole, including a vertical pole 5 and multiple climbing frame protection screen frames 1 on the left and right sides of the vertical pole 5. Two connecting pieces 7 are respectively fixed on both sides of the protective screen frame 1, the connecting piece 7 is provided with a first positioning hole 73, and the vertical rod 5 is provided with two U-shaped connecting seats 9 corresponding to the two connecting pieces 7 respectively. , The left and right sides of the U-shaped connecting seat 9 are respectively provided with third positioning holes 92, the first positioning hole 73 and the third positioning hole 92 are penetrated with a fastening screw 2, and one end of the fastening screw 2 is provided with a corresponding Matched fastening nut 6.
U型连接座9的内部安装有固定块8,固定块8上开设有第二定位孔81,A fixing block 8 is installed inside the U-shaped connecting seat 9, and the fixing block 8 is provided with a second positioning hole 81,
紧固螺钉2还穿过第二定位孔81,固定块8的上下两侧分别固定有一固定板4,两固定板4相背的一侧分别固定有对称设置的左连杆41和右连杆42,左连杆41和右连杆42远离固定板4的一端分别固定有一限位套筒3,各限位套筒3的内部安装有与其相适配的限位杆11,靠近左连杆41中心的限位杆11固接于立杆5左侧的爬架防护网框1上,靠近右连杆42中心的限位杆11固接于立杆5右侧的爬架防护网框1上,通过限位套筒3与限位杆11的配合连接,将立杆5左右两侧的爬架防护网框1与立杆5连接,提高连接的稳固性。左连杆41和右 连杆42与固定板4之间均通过焊接固定,提高固定板4与固定块8、左连杆41及右连杆42连接的稳定性。The fastening screw 2 also passes through the second positioning hole 81. The upper and lower sides of the fixing block 8 are respectively fixed with a fixing plate 4, and the opposite sides of the two fixing plates 4 are respectively fixed with a symmetrical left connecting rod 41 and a right connecting rod. 42. One end of the left connecting rod 41 and the right connecting rod 42 away from the fixing plate 4 is respectively fixed with a limiting sleeve 3, and a matching limiting rod 11 is installed inside each limiting sleeve 3, which is close to the left connecting rod The limit rod 11 in the center of 41 is fixed to the climbing frame protection screen frame 1 on the left side of the vertical rod 5, and the limit rod 11 near the center of the right connecting rod 42 is fixed to the climbing frame protection screen frame 1 on the right side of the vertical rod 5 On the upper side, through the matching connection of the limit sleeve 3 and the limit rod 11, the climbing frame protection screen frame 1 on the left and right sides of the vertical rod 5 is connected with the vertical rod 5 to improve the stability of the connection. The left connecting rod 41 and the right connecting rod 42 are fixed to the fixed plate 4 by welding, which improves the stability of the connection between the fixed plate 4 and the fixed block 8, the left connecting rod 41 and the right connecting rod 42.
左连杆41和右连杆42的长度相等,固定块8上方的左连杆41和右连杆42之间的夹角为40-50度,固定块8上方的左连杆41和其下方的右连杆42的轴线共线,便于固定块8及其上下两侧的左连杆41和右连杆42形成X结构,进一步提高连接的稳固性。The length of the left link 41 and the right link 42 are equal, the angle between the left link 41 and the right link 42 above the fixed block 8 is 40-50 degrees, and the left link 41 above the fixed block 8 and below it The axes of the right connecting rod 42 are collinear, so that the fixed block 8 and the left connecting rod 41 and the right connecting rod 42 on the upper and lower sides of the fixed block 8 form an X structure, which further improves the stability of the connection.
固定块8靠近U型连接座9的端面与U型连接座9上开设的安装槽91相适配,且U型连接座9置于安装槽91内,方便对固定块8的安装限位。The end surface of the fixing block 8 close to the U-shaped connecting seat 9 is adapted to the installation groove 91 opened on the U-shaped connecting seat 9, and the U-shaped connecting seat 9 is placed in the installation groove 91 to facilitate the installation and limitation of the fixing block 8.
连接片7包括L型板71,L型板71的两侧固定有三角形板72,第一定位孔73设于L型板71上,通过两三角形板72提高连接片7的稳固性,防止L型板71发生形变。The connecting piece 7 includes an L-shaped plate 71. Triangular plates 72 are fixed on both sides of the L-shaped plate 71. The first positioning hole 73 is provided on the L-shaped plate 71. The two triangular plates 72 improve the stability of the connecting piece 7 to prevent L The template 71 is deformed.
进行安装工作时,将爬架防护网框1贴近立杆5的左侧或右侧,使连接片7上的第一定位孔73与U型连接座9上的第三定位孔92对应,同时将固定块8置于安装槽91内,使各限位套筒3套接有于各限位杆11外部,之后通过紧固螺钉2穿过连接片7内部第一定位孔73、U型连接座9上的第三定位孔92及固定块8内部的第二定位孔81,并通过紧固螺母6固定,实现各爬架防护网框1之间横向连接和竖向的稳固连接,使得外防护网框安装时为一个整体框剪结构;同时固定块8与其上下两侧的左连杆41和右连杆42形成X型结构,进一步提高稳固性;并且安装操作都是在爬架的防护范围内完成,安装拆卸工作简便,解决的工人的安装风险和操作难度大问题。During installation, place the climbing frame protective screen frame 1 close to the left or right side of the pole 5, so that the first positioning hole 73 on the connecting piece 7 corresponds to the third positioning hole 92 on the U-shaped connecting seat 9, and at the same time Place the fixing block 8 in the mounting groove 91, so that each limit sleeve 3 is sleeved on the outside of each limit rod 11, and then the fastening screw 2 is passed through the first positioning hole 73 inside the connecting piece 7 and U-shaped connection The third locating hole 92 on the seat 9 and the second locating hole 81 inside the fixing block 8 are fixed by the fastening nut 6 to realize the horizontal and vertical connection between the climbing frame protective net frames 1 and make the outer The protective screen frame is an integral frame-shear structure when installed; at the same time, the fixed block 8 and the left link 41 and right link 42 on the upper and lower sides form an X-shaped structure to further improve the stability; and the installation operations are all in the protection of the climbing frame It is completed within the scope, the installation and disassembly work is simple, and the installation risks and operation difficulties of workers are solved.
需要说明的是,在本文中,诸如第一和第二等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。It should be noted that in this article, relational terms such as first and second are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply one of these entities or operations. There is any such actual relationship or order between. Moreover, the terms "include", "include" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements not only includes those elements, but also includes those that are not explicitly listed Other elements of, or also include elements inherent to this process, method, article or equipment.
最后应说明的是:以上所述仅为本申请的优选实施例而已,并不用于限制本申请,尽管参照前述实施例对本申请进行了详细的说明,对于本领域的技术人员来说,其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换。凡在本申请的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本申请的保护范围之内。Finally, it should be noted that the above descriptions are only preferred embodiments of the application, and are not intended to limit the application. Although the application has been described in detail with reference to the foregoing embodiments, for those skilled in the art, it is still The technical solutions described in the foregoing embodiments may be modified, or some of the technical features may be equivalently replaced. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of this application shall be included in the protection scope of this application.

Claims (2)

  1. 一种爬架防护网框和立杆的连接结构,包括立杆(5)和立杆(5)左右两侧的多个爬架防护网框(1),其特征在于:所述爬架防护网框(1)的两侧边缘分别固定有两连接片(7),所述连接片(7)上开设有第一定位孔(73),所述立杆(5)上设有两个分别与两所述连接片(7)相对应的U型连接座(9),所述U型连接座(9)的左右两侧分别开设有第三定位孔(92),所述第一定位孔(73)和第三定位孔(92)内穿设有一紧固螺钉(2),所述紧固螺钉(2)的一端设有与其相适配的紧固螺母(6),所述U型连接座(9)的内部安装有固定块(8),所述固定块(8)上开设有第二定位孔(81),所述紧固螺钉(2)还穿过第二定位孔(81),所述固定块(8)的上下两侧分别固定有一固定板(4),两所述固定板(4)相背的一侧分别固定有对称设置的左连杆(41)和右连杆(42),所述左连杆(41)和右连杆(42)远离所述固定板(4)的一端分别固定有一限位套筒(3),各所述限位套筒(3)的内部安装有与其相适配的限位杆(11),靠近所述左连杆(41)中心的所述限位杆(11)固接于所述立杆(5)左侧的所述爬架防护网框(1)上,靠近所述右连杆(42)中心的所述限位杆(11)固接于所述立杆(5)右侧的所述爬架防护网框(1)上。A connecting structure of a climbing frame protection net frame and a vertical pole, comprising a vertical rod (5) and a plurality of climbing frame protection net frames (1) on the left and right sides of the vertical rod (5), characterized in that: the climbing frame protection Two connecting pieces (7) are respectively fixed on both sides of the screen frame (1), the connecting piece (7) is provided with a first positioning hole (73), and the vertical rod (5) is provided with two connecting pieces (7). The U-shaped connecting seat (9) corresponding to the two connecting pieces (7), the left and right sides of the U-shaped connecting seat (9) are respectively provided with third positioning holes (92), the first positioning holes (73) and the third positioning hole (92) are bored with a fastening screw (2), one end of the fastening screw (2) is provided with a fastening nut (6) adapted to it, the U-shaped A fixing block (8) is installed inside the connecting seat (9). The fixing block (8) is provided with a second positioning hole (81), and the fastening screw (2) also passes through the second positioning hole (81). ), the upper and lower sides of the fixing block (8) are respectively fixed with a fixing plate (4), and the opposite sides of the two fixing plates (4) are respectively fixed with a symmetrical left connecting rod (41) and a right connecting rod (41). Rod (42), one end of the left connecting rod (41) and the right connecting rod (42) away from the fixing plate (4) is respectively fixed with a limiting sleeve (3), each of the limiting sleeves (3) ) Is fitted with a matching limit rod (11), and the limit rod (11) close to the center of the left link (41) is fixed to the left side of the vertical rod (5). On the climbing frame protection net frame (1), the limit rod (11) near the center of the right link (42) is fixedly connected to the climbing frame protection net frame on the right side of the vertical rod (5) (1) On.
  2. 根据权利要求1所述的爬架防护网框和立杆的连接结构,其特征在于:述左连杆(41)和所述右连杆(42)的长度相等,所述固定块(8)上方的所述左连杆(41)和所述右连杆(42)之间的夹角为40-50度,所述固定块(8)上方的所述左连杆(41)和其下方的所述右连杆(42)的轴线共线。The connecting structure of the climbing frame protection net frame and the vertical pole according to claim 1, wherein the length of the left link (41) and the right link (42) are equal, and the fixed block (8) The angle between the upper left link (41) and the right link (42) is 40-50 degrees, and the left link (41) above the fixed block (8) and the bottom The axes of the right link (42) are collinear.
PCT/CN2020/132409 2020-01-03 2020-11-27 Connecting structure for climbing scaffolding protective reticulated panels and upright pole WO2021135777A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202020011458 2020-01-03
CN202020011458.8 2020-01-03

Publications (1)

Publication Number Publication Date
WO2021135777A1 true WO2021135777A1 (en) 2021-07-08

Family

ID=76687062

Family Applications (3)

Application Number Title Priority Date Filing Date
PCT/CN2020/132406 WO2021135776A1 (en) 2020-01-03 2020-11-27 Connection structure for scaffold protection screen frame and vertical post
PCT/CN2020/132396 WO2021135775A1 (en) 2020-01-03 2020-11-27 Connecting structure for upright pole and climbing frame protective net frames
PCT/CN2020/132409 WO2021135777A1 (en) 2020-01-03 2020-11-27 Connecting structure for climbing scaffolding protective reticulated panels and upright pole

Family Applications Before (2)

Application Number Title Priority Date Filing Date
PCT/CN2020/132406 WO2021135776A1 (en) 2020-01-03 2020-11-27 Connection structure for scaffold protection screen frame and vertical post
PCT/CN2020/132396 WO2021135775A1 (en) 2020-01-03 2020-11-27 Connecting structure for upright pole and climbing frame protective net frames

Country Status (1)

Country Link
WO (3) WO2021135776A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114319833A (en) * 2022-01-13 2022-04-12 中铁十六局集团城市建设发展有限公司 Adjustable integrated connecting device for fixing net piece of climbing frame

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114848900A (en) * 2022-04-02 2022-08-05 深圳大学总医院 Artificial bone material and preparation method thereof
CN114622712A (en) * 2022-04-07 2022-06-14 中建四局第三建设有限公司 Attached protective net for scaffold

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100907796B1 (en) * 2008-12-18 2009-07-15 한동엽 Fall prevention device
CN203257084U (en) * 2013-04-01 2013-10-30 罗永木 Building outer frame pull rod
CN208777673U (en) * 2018-07-24 2019-04-23 南京淮港建筑工程有限公司 The fixation device of the one plug-in safety net of discharge plate buckle type scaffold
CN209353662U (en) * 2018-11-20 2019-09-06 中国建筑第八工程局有限公司 Climbing frame protective net frame and upright bar connection structure
CN209457352U (en) * 2018-12-27 2019-10-01 郑州大禾机电科技有限公司 Portable stable type scaffold
CN209686915U (en) * 2018-12-23 2019-11-26 田宝 A kind of attachment device for building structure strengthening

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101843068B1 (en) * 2016-06-29 2018-03-28 임채성 Supporting apparatus for hight placework safety apparatus
CN206667795U (en) * 2017-04-22 2017-11-24 延安大学西安创新学院 A kind of construction engineering protective net
KR101899118B1 (en) * 2018-05-09 2018-09-14 동양건설(주) a falling rock prevention pance with open type
CN209429512U (en) * 2018-12-27 2019-09-24 厦门安科科技有限公司 A kind of scaffold mesh sheet Fast Installation fastener and mesh sheet mounting structure
CN209874528U (en) * 2019-05-10 2019-12-31 聂晓璐 Safety protection net is used in highway construction
CN211080975U (en) * 2019-08-28 2020-07-24 江苏盛浩工程科技有限公司 Connecting structure of climbing frame protective net frame

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100907796B1 (en) * 2008-12-18 2009-07-15 한동엽 Fall prevention device
CN203257084U (en) * 2013-04-01 2013-10-30 罗永木 Building outer frame pull rod
CN208777673U (en) * 2018-07-24 2019-04-23 南京淮港建筑工程有限公司 The fixation device of the one plug-in safety net of discharge plate buckle type scaffold
CN209353662U (en) * 2018-11-20 2019-09-06 中国建筑第八工程局有限公司 Climbing frame protective net frame and upright bar connection structure
CN209686915U (en) * 2018-12-23 2019-11-26 田宝 A kind of attachment device for building structure strengthening
CN209457352U (en) * 2018-12-27 2019-10-01 郑州大禾机电科技有限公司 Portable stable type scaffold

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114319833A (en) * 2022-01-13 2022-04-12 中铁十六局集团城市建设发展有限公司 Adjustable integrated connecting device for fixing net piece of climbing frame

Also Published As

Publication number Publication date
WO2021135776A1 (en) 2021-07-08
WO2021135775A1 (en) 2021-07-08

Similar Documents

Publication Publication Date Title
WO2021135777A1 (en) Connecting structure for climbing scaffolding protective reticulated panels and upright pole
WO2021237635A1 (en) Temporary work shed for building construction
CN204590556U (en) With the steel pipe lifting scaffold of steel sash net safeguard structure
CN204754271U (en) Take protection frame of prefabricated outer wall hanging plate construction usefulness of window of wafing
CN111350337A (en) Bearing frame for building construction
CN212836622U (en) Connecting structure for climbing frame protective screen frame and vertical rod
CN215212255U (en) Suspension type frame combined high-altitude operation platform
CN205602977U (en) Elevator integrated form car ceiling
CN211080975U (en) Connecting structure of climbing frame protective net frame
KR20190142913A (en) Workbench support device
CN209430099U (en) A kind of moveable safety escalator
CN220203377U (en) Novel connecting piece for climbing frame
CN215331339U (en) Net frame external suspension construction platform
CN211949503U (en) Novel movable door type scaffold
CN107780644B (en) Operation platform for elevator shaft construction and use method thereof
CN216893597U (en) Elevartor shaft instrument formula protection frame convenient to dismouting
CN210067401U (en) Positioning and adjusting device for climbing scaffold
CN214942222U (en) Climbing frame equipment convenient to install
CN212562404U (en) Overhanging scaffold
CN219528315U (en) Suspended ceiling mounting platform for fresh air handling unit of air conditioner
CN219711967U (en) Connecting piece for mounting climbing frame
CN216196493U (en) Climbing frame and vertical rod connecting device for same
CN212271346U (en) Building curtain wall base
CN216949440U (en) Building climbing frame for building
CN220845069U (en) Dedicated balance gallows of prefabricated component

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 20909582

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 20909582

Country of ref document: EP

Kind code of ref document: A1