WO2021088349A1 - Method for excavating tunnel shaft - Google Patents

Method for excavating tunnel shaft Download PDF

Info

Publication number
WO2021088349A1
WO2021088349A1 PCT/CN2020/090406 CN2020090406W WO2021088349A1 WO 2021088349 A1 WO2021088349 A1 WO 2021088349A1 CN 2020090406 W CN2020090406 W CN 2020090406W WO 2021088349 A1 WO2021088349 A1 WO 2021088349A1
Authority
WO
WIPO (PCT)
Prior art keywords
shaft
hole
excavation
holes
drill
Prior art date
Application number
PCT/CN2020/090406
Other languages
French (fr)
Chinese (zh)
Inventor
徐强
何开伟
李强
Original Assignee
中铁二局集团有限公司
中铁二局第四工程有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中铁二局集团有限公司, 中铁二局第四工程有限公司 filed Critical 中铁二局集团有限公司
Publication of WO2021088349A1 publication Critical patent/WO2021088349A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • E21D1/03Sinking shafts mechanically, e.g. by loading shovels or loading buckets, scraping devices, conveying screws
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • E21D1/08Sinking shafts while moving the lining downwards

Definitions

  • the invention relates to the technical field of tunnels and underground engineering, in particular to a method for excavating a tunnel shaft.
  • the main shaft method is mainly suitable for construction under the condition that there is no passage at the bottom of the shaft, that is, the flat hole at the bottom of the shaft has not been formed, and the shaft needs to be formed first.
  • the main construction method is to use the umbrella drill to drill first, artificial charging, smooth blasting, and then use The rock grabbing machine loads the blasting slag into the bucket and the winch lifts it to the ground.
  • the raise-drilling construction method is mainly suitable for the formation of the shaft bottom
  • the main construction method is to use raise drilling rigs (or directional drilling rigs) to carry out pilot hole (generally 270mm diameter) construction from top to bottom. After the pilot hole is opened, install the drill reaming bit at the bottom of the shaft, and then down Reaming upwards to form a pilot well (generally 1400mm in diameter).
  • the pilot well After the pilot well is penetrated, it is manually expanded from bottom to top to form a slag chute, and the slag excavated by the reaming is directly slipped from the slag chute to the flat hole at the bottom of the well. Inside, the slag truck transports the slag directly in the Pingdong.
  • the purpose of the present invention is to overcome the prior art in the urban tunnel construction, it is not suitable to use the blasting method to excavate, if there is no channel at the bottom, the non-blasting method of excavating the construction efficiency is low, and the excavation process is deep for a long time. Under the pit operation, the safety risk period is long, the safety risk is high and the above-mentioned shortcomings, provide a tunnel shaft excavation method.
  • a method for excavating a tunnel shaft includes the following steps:
  • the number and distribution of the first hole are determined according to the diameter of the first drill bit and the diameter of the shaft.
  • the first drill bit is used to drill the first hole, and the diameter of the first hole is smaller than the diameter of the shaft.
  • the diameter of the hole 1 depends on the diameter of the drill bit 1.
  • determine the number and distribution of the first hole excavate from the periphery to the middle, and excavate the hole during the excavation, that is, the next hole one is excavated and the previous one At least one hole one is spaced between one hole one, and each hole one is backfilled as soon as the excavation is completed. After all the hole one is backfilled, the excavation range of the shaft is opened for a second time.
  • one hole one is spaced between the next hole one to be excavated and the previous hole one.
  • step c the specific steps are as follows:
  • the mass of the mixed cement is 5%-8% of the mass of the drill slag.
  • the interval between two adjacent holes is 10-20 cm.
  • the first hole is drilled by the rotary drill.
  • Adopting a tunnel shaft excavation method of the present invention using a rotary drill to drill a hole instead of a conventional water mill drill core plus splitting excavation method, creating a large-area empty surface, convenient for construction, and for hard Rock formations are particularly suitable.
  • the use of the tunnel shaft excavation method of the present invention greatly reduces the idle time of the drill bit for excavating hole one, ensures the effective use of the drill bit, and relatively lowers the drilling cost.
  • Fig. 1 is a flow chart of a method for excavating a tunnel shaft according to the present invention
  • Figure 2 is a schematic diagram of step a according to the present invention.
  • Figure 3 is a schematic diagram of step b according to the present invention.
  • Figure 4 is the second schematic diagram of step b according to the present invention.
  • Figure 5 is the third schematic diagram of step b according to the present invention.
  • Figure 6 is a fourth schematic diagram of step b according to the present invention.
  • Figure 7 is a schematic diagram five of step b according to the present invention.
  • Fig. 8 is a schematic diagram of step c according to the present invention.
  • the method for excavating a tunnel shaft includes the following steps:
  • the number and distribution of the hole-2 are determined according to the diameter of the drill bit one and the diameter of the shaft 1.
  • the drill bit one is used to drill the hole-2, and the diameter of the hole-2 is smaller than the diameter of the shaft 1.
  • Fig. 2 first set out and locate, mark the excavation range of the shaft 1, and construct the lock and the ground beam at the head of the well.
  • a rotary drill is used to excavate a number of holes-2.
  • the diameter of the hole-2 depends on the diameter of the drill bit one. According to the diameter of the hole-2 and the diameter of the shaft 1, Determine the number and distribution of the holes-2, and the interval between two adjacent holes-2 is 10-20cm, as in the example of this embodiment, the diameter of the shaft 1 is 6.88m, and the rotary digging
  • the drill bit one has a diameter of 1.5m, that is, the diameter of the hole-2 is 1.5m.
  • the arrangement of all the holes-2 is shown in Figure 3.
  • the excavation sequence is 1#-3#-5#-7#-9#-2#-4#-6#-8#-10#- #- #- #- #, you can also start with any serial number of hole-2, such as from 3#, 7#, then you can also excavate in a counterclockwise direction, or you can excavate with multiple holes-2, such as 1#-4 #-6#-8#, after the construction of all the holes 1-2 of the outer ring is completed, the construction of the holes 1-2 of the inner ring can be carried out.
  • the inner ring can also be excavated from any hole 1-2, and then continue to separate. Hole excavation of the next hole-2, each hole-2 will be backfilled after the excavation is completed, that is, the next hole-2 will be excavated after the backfilling is completed, and the backfill will be mixed with 5%- 8% cement is backfilled.
  • the excavation range of the shaft 1 is excavated twice, and the excavation is carried out in layers during excavation, and the excavation is carried out while supporting until the shaft 1 is completed.
  • Excavation specifically, first excavate the area on one side of the shaft 1, such as park the excavator on the left area of the shaft 1 in Fig. 7, excavate the right area of the shaft 1 in Fig. 7, and open
  • When digging firstly start excavation from the part of the hole-2 in the corresponding area, and at the same time break the wall in the corresponding range, that is, the space between the two holes-2 and the hole-2
  • the distance between the excavation depth and the edge of the shaft 1 is 50-60 cm.
  • the excavator After opening the corresponding elevation, the excavator moves to the right area of the shaft 1 in Fig. 7 and excavates the left side of the shaft 1 in Fig. 7 In the side area, when the left area is also dug to the corresponding elevation, the excavator is used to remove the slag. After the removal is completed, the excavator is lifted out of the shaft 1, and the shaft wall of the corresponding depth of the shaft 1 is carried out. Supporting, after completing the corresponding supporting work, hoist the excavator into the shaft 1 to excavate the next layer, repeat the steps of excavating the excavator, and then excavate 50-60cm and support, Until the final completion of the excavation work of the tunnel shaft 1.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Earth Drilling (AREA)

Abstract

A method for excavating a tunnel shaft (1), by drilling a number of holes I (2) with smaller diameters, it is possible to predict groundwater and bad geology etc. in advance, which is convenient for confirming the degree of coincidence of the geological survey data, so as to provide guidance for subsequent construction and reduce construction risks and difficulties, at the same time, the excavation from top to bottom does not require the restriction of the formation of a positive hole at the bottom of the shaft (1), it can also be constructed in a non-blasting manner, which has high safety and can loosen the rock and soil in advance, improves the construction efficiency of excavation, and shortens the construction period.

Description

一种隧道竖井的开挖方法Method for excavating tunnel shaft 技术领域Technical field
本发明涉及隧道与地下工程技术领域,特别涉及一种隧道竖井的开挖方法。The invention relates to the technical field of tunnels and underground engineering, in particular to a method for excavating a tunnel shaft.
背景技术Background technique
目前国内外地下工程中,比如水利水电工程、煤矿工程、石油工程、公路和铁路长大隧道交通工程、地铁工程等,竖井施工十分普遍,根据其施工条件不同,其施工方法也有所区别,主要有正井法、反井钻机法开挖,根据地质情况和地下水情况可预先采取围护结构和止水措施后再开挖。At present, in underground engineering at home and abroad, such as water conservancy and hydropower engineering, coal engineering, petroleum engineering, highway and railway long tunnel traffic engineering, subway engineering, etc., shaft construction is very common. According to the different construction conditions, the construction methods are also different. Excavation can be carried out by the upwell method and the upwell drilling rig method. According to the geological conditions and groundwater conditions, the excavation can be carried out after the enclosure structure and water stop measures are taken in advance.
正井法主要适用于竖井底部无通道,即竖井底平洞还未形成、竖井需优先形成的条件下施工,其主要施工方法为先利用伞钻钻孔,人工装药,光面爆破,再利用抓岩机将爆破石渣装吊桶,绞车提升至地面,但由于采用爆破技术不宜适于市区、学校等周边环境复杂的施工场地;反井钻施工法主要适用于竖井底部正洞已形成的条件下施工,其主要施工方法为采用反井钻机(或定向钻机)从上往下进行导向孔(一般孔径为270mm)施工,导向孔打通后,在竖井底部安装钻机扩孔钻头,再由下向上扩孔成导井(一般孔径为1400mm),导井贯通后,在采用人工自下而上扩挖成溜渣井,扩孔开挖的石渣直接从溜渣井溜至井底平洞内,运渣车直接在平洞内将渣土外运。The main shaft method is mainly suitable for construction under the condition that there is no passage at the bottom of the shaft, that is, the flat hole at the bottom of the shaft has not been formed, and the shaft needs to be formed first. The main construction method is to use the umbrella drill to drill first, artificial charging, smooth blasting, and then use The rock grabbing machine loads the blasting slag into the bucket and the winch lifts it to the ground. However, due to the use of blasting technology, it is not suitable for construction sites with complex surrounding environments such as urban areas and schools; the raise-drilling construction method is mainly suitable for the formation of the shaft bottom Under the conditions of construction, the main construction method is to use raise drilling rigs (or directional drilling rigs) to carry out pilot hole (generally 270mm diameter) construction from top to bottom. After the pilot hole is opened, install the drill reaming bit at the bottom of the shaft, and then down Reaming upwards to form a pilot well (generally 1400mm in diameter). After the pilot well is penetrated, it is manually expanded from bottom to top to form a slag chute, and the slag excavated by the reaming is directly slipped from the slag chute to the flat hole at the bottom of the well. Inside, the slag truck transports the slag directly in the Pingdong.
目前当竖井底部无通道时,各类竖井施工大部分均采用机械加爆破的正井开挖技术,非爆破开挖施工技术应用较少。At present, when there is no passage at the bottom of the shaft, most of the various shaft constructions adopt the main shaft excavation technology of mechanical and blasting, and the application of non-blasting excavation construction technology is less.
发明内容Summary of the invention
本发明的目的在于克服现有技术中在市区隧道的竖井施工,不宜采用爆破方法开挖,若底部无通道,采用非爆破的正井法开挖施工效率低,开挖过程中长时间深基坑下作业,安全风险期长,安全风险大等上述不足,提供一种隧道竖井的开挖方法。The purpose of the present invention is to overcome the prior art in the urban tunnel construction, it is not suitable to use the blasting method to excavate, if there is no channel at the bottom, the non-blasting method of excavating the construction efficiency is low, and the excavation process is deep for a long time. Under the pit operation, the safety risk period is long, the safety risk is high and the above-mentioned shortcomings, provide a tunnel shaft excavation method.
为了实现上述目的,本发明提供了以下技术方案:In order to achieve the above objectives, the present invention provides the following technical solutions:
一种隧道竖井的开挖方法,包含如下步骤:A method for excavating a tunnel shaft includes the following steps:
a、放样定位竖井的中心位置,根据定位中心点标示出所述竖井的开挖范围,然后在所述竖井井口施工钢筋混凝土锁口和地梁;a. Stake out the center position of the positioning shaft, mark the excavation range of the shaft according to the positioning center point, and then construct reinforced concrete locks and ground beams at the head of the shaft;
b、在所述竖井的待开挖范围内标示出若干个孔一的待开挖范围,相邻两个所述孔一之间具有间隔,然后采用先周边后中心的顺序依次开挖所有所述孔一,开挖所有所述孔一时进行隔孔开挖,每个所述孔一开挖至底后,将钻渣掺拌水泥回填回对应的所述孔一内,然后再开挖 下一个所述孔一;b. Mark a number of holes to be excavated in the range of the shaft to be excavated, and there is a gap between two adjacent holes, and then excavate all the holes in the order of the periphery first and then the center. In the first hole, excavate all the holes at the same time and excavate the partition holes. After each hole is excavated to the bottom, the drilling slag mixed with cement is backfilled into the corresponding hole one, and then the next hole is excavated. One of said holes;
c、最后一个所述孔一回填完毕后,在所述竖井的开挖范围内进行二次开挖并破除相邻两个所述孔一之间以及所述孔一与竖井壁之间的墙体,边开挖边进行支护,完成全部支护工作后即完成所述竖井的开挖;c. After the last hole one is backfilled, perform a secondary excavation within the excavation range of the shaft and break the walls between two adjacent holes one and between the hole one and the shaft wall The shaft is supported while digging, and the excavation of the shaft is completed after all the supporting work is completed;
其中,所述孔一的数量和分布情况根据钻头一的直径和所述竖井的直径确定,所述钻头一用于钻孔所述孔一,所述孔一的直径小于所述竖井的直径。Wherein, the number and distribution of the first hole are determined according to the diameter of the first drill bit and the diameter of the shaft. The first drill bit is used to drill the first hole, and the diameter of the first hole is smaller than the diameter of the shaft.
首先放样定位,标示出竖井的开挖范围,并在井口施工锁口和地梁,然后在竖井的待开挖范围内开挖若干个孔一,所述孔一的直径取决于钻头一的直径,根据所述孔一的直径和竖井的直径,确定所述孔一的数量和分布,从周边往中间开挖,开挖时隔孔开挖,即开挖的下一个所述孔一与前一个所述孔一之间间隔至少一个所述孔一,每个所述孔一开挖完毕后即进行回填,所有所述孔一回填完毕后,对所述竖井的开挖范围进行二次开挖,开挖时分层进行开挖,边开挖边进行支护,直到完成所述竖井的开挖,采用本方法通过现在钻取若干直径更小的孔,能够提前预判地下水及不良地质等情况,便于印证地勘资料的吻合程度,以便为后续施工提供指导,降低施工风险和难度,同时,采用从上向下开挖,无需竖井底部形成正洞的限制,还能采用非爆破的形式施工,安全性高,并且能够提前钻松岩土,提高了开挖的施工效率,缩短了工期,特别是缩短了人工深基坑作业时间,有效降低安全风险,节省施工成本,具有广泛的推广意义。First set out and locate, mark the excavation range of the shaft, and construct the lock and ground beam at the wellhead, and then dig a number of holes in the range to be excavated in the shaft. The diameter of the hole 1 depends on the diameter of the drill bit 1. According to the diameter of the first hole and the diameter of the shaft, determine the number and distribution of the first hole, excavate from the periphery to the middle, and excavate the hole during the excavation, that is, the next hole one is excavated and the previous one At least one hole one is spaced between one hole one, and each hole one is backfilled as soon as the excavation is completed. After all the hole one is backfilled, the excavation range of the shaft is opened for a second time. During excavation, excavation is carried out in layers, and the excavation is carried out while supporting until the excavation of the shaft is completed. By using this method to drill several holes with smaller diameters, the groundwater and bad geological conditions can be predicted in advance It is convenient to verify the degree of coincidence of the geological survey data, so as to provide guidance for subsequent construction and reduce construction risks and difficulties. At the same time, excavation from top to bottom is used, without the restriction of forming a positive hole at the bottom of the shaft, and non-blasting can also be used. Formal construction, high safety, and can drill loose rock and soil in advance, improve the construction efficiency of excavation, shorten the construction period, especially shorten the operation time of artificial deep foundation pit, effectively reduce safety risks, save construction costs, and have a wide range of promotion significance.
优选的,在所述步骤b中,开挖的下一个所述孔一与前一个所述孔一之间间隔一个所述孔一。Preferably, in the step b, one hole one is spaced between the next hole one to be excavated and the previous hole one.
优选的,在所述步骤c中,具体步骤如下:Preferably, in the step c, the specific steps are as follows:
c1、先开挖所述竖井的一侧区域并破除对应范围内的所述墙体,开挖深度为50-60cm;c1. First excavate one side area of the shaft and break the wall in the corresponding range, and the excavation depth is 50-60cm;
c2、然后开挖所述竖井的另一侧区域并破除对应范围内的所述墙体,开挖深度与步骤c1中的开挖深度相同;c2. Then excavate the other side area of the shaft and destroy the wall in the corresponding range, and the excavation depth is the same as the excavation depth in step c1;
c3、清理对应深度内的渣土;c3. Clean up the muck within the corresponding depth;
c4、对所述竖井对应深度的井壁进行支护;c4. Support the shaft wall at the corresponding depth of the shaft;
c5、重复步骤c1-c4,直至完成所述竖井的支护。c5. Repeat steps c1-c4 until the support of the shaft is completed.
采用回填后再二次开挖并支护方法,大大降低了开挖孔一的钻头的闲置时间,保证了钻头的有效利用,相对较低了钻孔费用。Using the method of re-excavating and supporting after backfilling greatly reduces the idle time of the drill bit for excavating hole one, ensures the effective use of the drill bit, and relatively lowers the drilling cost.
优选的,在所述步骤b中,掺拌的所述水泥的质量为钻渣质量的5%-8%。Preferably, in the step b, the mass of the mixed cement is 5%-8% of the mass of the drill slag.
优选的,相邻两个所述孔一之间的间隔为10-20cm。Preferably, the interval between two adjacent holes is 10-20 cm.
优选的,所述孔一通过所述旋挖钻进行钻孔。Preferably, the first hole is drilled by the rotary drill.
综上所述,与现有技术相比,本发明的有益效果是:In summary, compared with the prior art, the beneficial effects of the present invention are:
1、采用本发明所述的一种隧道竖井的开挖方法,通过现在钻取若干直径更小的孔,能够提前预判地下水及不良地质等情况,便于印证地勘资料的吻合程度,以便为后续施工提供指导,降低施工风险和难度,同时,采用从上向下开挖,无需竖井底部形成正洞的限制,还能采用非爆破的形式施工,安全性高,并且能够提前钻松岩土,提高了开挖的施工效率,缩短了工期,特别是缩短了人工深基坑作业时间,有效降低安全风险,节省施工成本,具有广泛的推广意义。1. Using the tunnel shaft excavation method of the present invention, by now drilling several holes with smaller diameters, it is possible to predict the conditions of groundwater and bad geology in advance, and it is convenient to confirm the degree of coincidence of the geological prospecting data, so as to Subsequent construction provides guidance to reduce construction risks and difficulties. At the same time, it uses top-down excavation without the restriction of forming a hole at the bottom of the shaft. It can also be constructed in a non-blasting manner, which is safe and can be drilled in advance to loosen the rock and soil. The construction efficiency of the excavation is improved, the construction period is shortened, especially the operation time of the artificial deep foundation pit is shortened, the safety risk is effectively reduced, and the construction cost is saved, which has a wide range of promotion significance.
2、采用本发明所述的一种隧道竖井的开挖方法,使用旋挖钻钻孔一代替常规水磨钻钻芯加劈裂开挖方法,创造了大面积临空面,方便施工,对于坚硬岩层特别适用。2. Adopting a tunnel shaft excavation method of the present invention, using a rotary drill to drill a hole instead of a conventional water mill drill core plus splitting excavation method, creating a large-area empty surface, convenient for construction, and for hard Rock formations are particularly suitable.
3、采用本发明所述的一种隧道竖井的开挖方法,大大降低了开挖孔一的钻头的闲置时间,保证了钻头的有效利用,相对较低了钻孔费用。3. The use of the tunnel shaft excavation method of the present invention greatly reduces the idle time of the drill bit for excavating hole one, ensures the effective use of the drill bit, and relatively lowers the drilling cost.
附图说明:Description of the drawings:
图1为本发明所述的一种隧道竖井的开挖方法的流程图;Fig. 1 is a flow chart of a method for excavating a tunnel shaft according to the present invention;
图2为本发明所述的步骤a的示意图;Figure 2 is a schematic diagram of step a according to the present invention;
图3为本发明所述的步骤b的示意图一;Figure 3 is a schematic diagram of step b according to the present invention;
图4为本发明所述的步骤b的示意图二;Figure 4 is the second schematic diagram of step b according to the present invention;
图5为本发明所述的步骤b的示意图三;Figure 5 is the third schematic diagram of step b according to the present invention;
图6为本发明所述的步骤b的示意图四;Figure 6 is a fourth schematic diagram of step b according to the present invention;
图7为本发明所述的步骤b的示意图五;Figure 7 is a schematic diagram five of step b according to the present invention;
图8为本发明所述的步骤c的示意图。Fig. 8 is a schematic diagram of step c according to the present invention.
图中标记:1-竖井,2-孔一。Mark in the picture: 1-shaft, 2-hole one.
具体实施方式Detailed ways
下面结合附图及具体实施例对本发明作进一步的详细描述。但不应将此理解为本发明上述主题的范围仅限于以下的实施例,凡基于本发明内容所实现的技术均属于本发明的范围。The present invention will be further described in detail below in conjunction with the drawings and specific embodiments. However, it should not be understood that the scope of the above-mentioned subject of the present invention is limited to the following embodiments, and all technologies implemented based on the content of the present invention belong to the scope of the present invention.
实施例1Example 1
如图1所示,本发明所述的一种隧道竖井的开挖方法,包含如下步骤:As shown in Figure 1, the method for excavating a tunnel shaft according to the present invention includes the following steps:
a、放样定位竖井1的中心位置,根据定位中心点标示出所述竖井1的开挖范围,然后在所述竖井1井口施工钢筋混凝土锁口和地梁;a. Loft the center position of the positioning shaft 1, mark the excavation range of the shaft 1 according to the positioning center point, and then construct reinforced concrete locks and ground beams at the head of the shaft 1;
b、在所述竖井1的待开挖范围内标示出若干个孔一2的待开挖范围,相邻两个所述孔一2之间具有间隔,所述间隔为10-20cm,然后采用先周边后中心的顺序依次开挖所有所述孔一2,开挖所有所述孔一2时进行隔孔开挖,每个所述孔一2开挖至底后,将钻渣掺拌水泥回填回对应的所述孔一2内,然后再开挖下一个所述孔一2;b. Mark the range to be excavated for a number of holes-2 in the range of the shaft 1 to be excavated, and there is an interval between the two adjacent holes-2, and the interval is 10-20cm, and then use Excavate all the holes 1 and 2 in the order of the periphery first and then the center. When all the holes 1 and 2 are excavated, excavate the partition holes. After each hole 2 is excavated to the bottom, mix the drilling slag with cement Backfill the corresponding hole-2, and then excavate the next hole-2;
c、最后一个所述孔一2回填完毕后,在所述竖井1的开挖范围内进行二次开挖并破除相邻两个所述孔一2之间以及所述孔一2与竖井1壁之间的墙体,边开挖边进行支护,完成全部支护工作后即完成所述竖井1的开挖;c. After the last hole-2 is backfilled, a secondary excavation is carried out within the excavation range of the shaft 1 and the space between the two adjacent holes-2, the hole-2 and the shaft 1 is broken. The wall between the walls is supported while digging, and the excavation of the shaft 1 is completed after all the supporting work is completed;
其中,所述孔一2的数量和分布情况根据钻头一的直径和所述竖井1的直径确定,所述钻头一用于钻孔所述孔一2,所述孔一2的直径小于所述竖井1的直径。Wherein, the number and distribution of the hole-2 are determined according to the diameter of the drill bit one and the diameter of the shaft 1. The drill bit one is used to drill the hole-2, and the diameter of the hole-2 is smaller than the diameter of the shaft 1. The diameter of shaft 1.
具体的,如图2所示,首先放样定位,标示出竖井1的开挖范围,并在井口施工锁口和地梁。Specifically, as shown in Fig. 2, first set out and locate, mark the excavation range of the shaft 1, and construct the lock and the ground beam at the head of the well.
然后在竖井1的待开挖范围内采用旋挖钻开挖若干个孔一2,所述孔一2的直径取决于钻头一的直径,根据所述孔一2的直径和竖井1的直径,确定所述孔一2的数量和分布,并且相邻两个所述孔一2之间的间隔为10-20cm,如本实施例示例,所述竖井1的直径为6.88m,所述旋挖钻的钻头一直径为1.5m,即所述孔一2的直径为1.5m,所有所述孔一2的布置情况如图3所示,为便于表述,对图3中的所有所述孔一2进行了编号,共有14个所述孔一2,呈两圈分布,①#-⑩#孔一2位于外圈,
Figure PCTCN2020090406-appb-000001
#-
Figure PCTCN2020090406-appb-000002
#孔一2位于内圈,开挖时隔孔开挖,从周边往中间开挖,开挖的下一个所述孔一2与前一个所述孔一2之间间隔至少一个所述孔一2,如图4-7所示,开挖顺序为①#-③#-⑤#-⑦#-⑨#-②#-④#-⑥#-⑧#-⑩#-
Figure PCTCN2020090406-appb-000003
#-
Figure PCTCN2020090406-appb-000004
#-
Figure PCTCN2020090406-appb-000005
#-
Figure PCTCN2020090406-appb-000006
#,也可以任意一个序号的孔一2开始,如从③#、⑦#,然后也可以沿逆时针方向隔孔开挖,也可以间隔多个孔一2进行开挖,如①#-④#-⑥#-⑧#,外圈的所有所述孔一2施工完毕后再进行内圈的所述孔一2的施工,内圈也可以从任意一个孔一2开始开挖,然后继续隔孔开挖下一个所述孔一2,每个所述孔一2开挖完毕后即进行回填,即回填完毕后再开挖下一个所述孔一2,回填采用钻渣掺拌5%-8%水泥进行回填。
Then, within the range of shaft 1 to be excavated, a rotary drill is used to excavate a number of holes-2. The diameter of the hole-2 depends on the diameter of the drill bit one. According to the diameter of the hole-2 and the diameter of the shaft 1, Determine the number and distribution of the holes-2, and the interval between two adjacent holes-2 is 10-20cm, as in the example of this embodiment, the diameter of the shaft 1 is 6.88m, and the rotary digging The drill bit one has a diameter of 1.5m, that is, the diameter of the hole-2 is 1.5m. The arrangement of all the holes-2 is shown in Figure 3. For ease of description, all the holes in Figure 3 2 is numbered, there are 14 holes-2 in total, distributed in two circles, ①#-⑩#hole-2 is located in the outer ring,
Figure PCTCN2020090406-appb-000001
#-
Figure PCTCN2020090406-appb-000002
#孔一2 is located in the inner circle. During excavation, the excavation is separated from the periphery to the middle. There is at least one hole one between the next hole-2 and the previous hole-2. 2. As shown in Figure 4-7, the excavation sequence is ①#-③#-⑤#-⑦#-⑨#-②#-④#-⑥#-⑧#-⑩#-
Figure PCTCN2020090406-appb-000003
#-
Figure PCTCN2020090406-appb-000004
#-
Figure PCTCN2020090406-appb-000005
#-
Figure PCTCN2020090406-appb-000006
#, you can also start with any serial number of hole-2, such as from ③#, ⑦#, then you can also excavate in a counterclockwise direction, or you can excavate with multiple holes-2, such as ①#-④ #-⑥#-⑧#, after the construction of all the holes 1-2 of the outer ring is completed, the construction of the holes 1-2 of the inner ring can be carried out. The inner ring can also be excavated from any hole 1-2, and then continue to separate. Hole excavation of the next hole-2, each hole-2 will be backfilled after the excavation is completed, that is, the next hole-2 will be excavated after the backfilling is completed, and the backfill will be mixed with 5%- 8% cement is backfilled.
所有所述孔一2回填完毕后,对所述竖井1的开挖范围进行二次开挖,开挖时分层进行开挖,边开挖边进行支护,直到完成所述竖井1的开挖,具体的,先开挖所述竖井1的一侧区域,如将挖机停放在图7中所述竖井1的左侧区域,开挖图7中所述竖井1的右侧区域,开挖时,先从对应区域内的所述孔一2的部分开始开挖,同时破除对应范围内的所述墙体,即两个所述孔一2之间的间隔,以及所述孔一2与竖井1边缘的间隔,开挖深度为50-60cm,开外置对应标高后,所述挖机行至图7中所述竖井1的右侧区域,开挖图7中所述 竖井1的左侧区域,当左侧区域也挖至对应标高后,采用挖机进行清渣工作,清渣完成后,将所述挖机吊出所述竖井1,对所述竖井1对应深度的井壁进行支护,完成对应的支护工作后,再将挖机吊入所述竖井1中,进行下一层的开挖,重复前述挖机开挖的步骤,再开挖50-60cm并支护,直至最终完成隧道竖井1的开挖工作。After all the holes 1 and 2 are backfilled, the excavation range of the shaft 1 is excavated twice, and the excavation is carried out in layers during excavation, and the excavation is carried out while supporting until the shaft 1 is completed. Excavation, specifically, first excavate the area on one side of the shaft 1, such as park the excavator on the left area of the shaft 1 in Fig. 7, excavate the right area of the shaft 1 in Fig. 7, and open When digging, firstly start excavation from the part of the hole-2 in the corresponding area, and at the same time break the wall in the corresponding range, that is, the space between the two holes-2 and the hole-2 The distance between the excavation depth and the edge of the shaft 1 is 50-60 cm. After opening the corresponding elevation, the excavator moves to the right area of the shaft 1 in Fig. 7 and excavates the left side of the shaft 1 in Fig. 7 In the side area, when the left area is also dug to the corresponding elevation, the excavator is used to remove the slag. After the removal is completed, the excavator is lifted out of the shaft 1, and the shaft wall of the corresponding depth of the shaft 1 is carried out. Supporting, after completing the corresponding supporting work, hoist the excavator into the shaft 1 to excavate the next layer, repeat the steps of excavating the excavator, and then excavate 50-60cm and support, Until the final completion of the excavation work of the tunnel shaft 1.
采用本方法通过现在钻取若干直径更小的孔,能够提前预判地下水及不良地质等情况,便于印证地勘资料的吻合程度,以便为后续施工提供指导,降低施工风险和难度,同时,采用从上向下开挖,无需竖井底部形成正洞的限制,还能采用非爆破的形式施工,安全性高,并且能够提前钻松岩土,提高了开挖的施工效率,缩短了工期,特别是缩短了人工深基坑作业时间,有效降低安全风险,节省施工成本,具有广泛的推广意义。By using this method to drill several holes with smaller diameters, it can predict groundwater and bad geology in advance, and it is convenient to confirm the degree of coincidence of the geological survey data, so as to provide guidance for subsequent construction and reduce construction risks and difficulties. At the same time, use Excavation from the top to the bottom, without the restriction of the formation of the main hole at the bottom of the shaft, it can also be constructed in the form of non-blasting, which has high safety and can be drilled in advance to loosen the rock and soil, which improves the construction efficiency of excavation and shortens the construction period, especially It shortens the operation time of artificial deep foundation pits, effectively reduces safety risks, saves construction costs, and has extensive promotion significance.
以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。The above descriptions are only the preferred embodiments of the present invention and are not intended to limit the present invention. Any modification, equivalent replacement and improvement made within the spirit and principle of the present invention shall be included in the protection of the present invention. Within range.

Claims (6)

  1. 一种隧道竖井的开挖方法,其特征在于,包含如下步骤:A method for excavating a tunnel shaft is characterized in that it comprises the following steps:
    a、放样定位竖井(1)的中心位置,根据定位中心点标示出所述竖井(1)的开挖范围,然后在所述竖井(1)井口施工钢筋混凝土锁口和地梁;a. Stake out the center position of the positioning shaft (1), mark the excavation range of the shaft (1) according to the positioning center point, and then construct reinforced concrete locks and ground beams at the head of the shaft (1);
    b、在所述竖井(1)的待开挖范围内标示出若干个孔一(2)的待开挖范围,相邻两个所述孔一(2)之间具有间隔,然后采用先周边后中心的顺序依次开挖所有所述孔一(2),开挖所有所述孔一(2)时进行隔孔开挖,每个所述孔一(2)开挖至底后,将钻渣掺拌水泥回填回对应的所述孔一(2)内,然后再开挖下一个所述孔一(2);b. Mark a number of holes one (2) to be excavated in the range of the shaft (1) to be excavated, and there is a gap between two adjacent holes (2), and then use the first periphery Excavate all the holes one (2) in sequence in the rear center, and excavate all the holes one (2) when excavating all the holes one (2), and after excavating to the bottom of each hole one (2), drill The slag mixed cement is backfilled back into the corresponding hole one (2), and then the next hole one (2) is excavated;
    c、最后一个所述孔一(2)回填完毕后,在所述竖井(1)的开挖范围内进行二次开挖并破除相邻两个所述孔一(2)之间以及所述孔一(2)与竖井(1)壁之间的墙体,边开挖边进行支护,完成全部支护工作后即完成所述竖井(1)的开挖;c. After the last hole (2) is backfilled, perform a secondary excavation within the excavation range of the shaft (1) and break the gap between two adjacent holes (2) and the The wall between the hole one (2) and the wall of the shaft (1) is supported while digging, and the excavation of the shaft (1) is completed after all the supporting work is completed;
    其中,所述孔一(2)的数量和分布情况根据钻头一的直径和所述竖井(1)的直径确定,所述钻头一用于钻孔所述孔一(2),所述孔一(2)的直径小于所述竖井(1)的直径。Wherein, the number and distribution of the first hole (2) are determined according to the diameter of the first drill bit and the diameter of the shaft (1). The first drill bit is used to drill the first hole (2), and the first hole is used to drill the first hole (2). The diameter of (2) is smaller than the diameter of the shaft (1).
  2. 根据权利要求1所述的方法,其特征在于,在所述步骤b中,开挖的下一个所述孔一(2)与前一个所述孔一(2)之间间隔一个所述孔一(2)。The method according to claim 1, characterized in that, in the step b, the next hole one (2) to be excavated and the previous hole one (2) are separated by one hole one. (2).
  3. 根据权利要求1所述的方法,其特征在于,在所述步骤c中,具体步骤如下:The method according to claim 1, wherein in the step c, the specific steps are as follows:
    c1、先开挖所述竖井(1)的一侧区域并破除对应范围内的所述墙体,开挖深度为50-60cm;c1. First excavate one side area of the shaft (1) and destroy the wall in the corresponding range, and the excavation depth is 50-60cm;
    c2、然后开挖所述竖井(1)的另一侧区域并破除对应范围内的所述墙体,开挖深度与步骤c1中的开挖深度相同;c2. Then excavate the other side area of the shaft (1) and destroy the wall in the corresponding range, and the excavation depth is the same as the excavation depth in step c1;
    c3、清理对应深度内的渣土;c3. Clean up the muck within the corresponding depth;
    c4、对所述竖井(1)对应深度的井壁进行支护;c4. Support the shaft wall at the corresponding depth of the shaft (1);
    c5、重复步骤c1-c4,直至完成所述竖井(1)的支护。c5. Repeat steps c1-c4 until the support of the shaft (1) is completed.
  4. 根据权利要求1-3任一所述的方法,其特征在于,在所述步骤b中,掺拌的所述水泥的质量为钻渣质量的5%-8%。The method according to any one of claims 1 to 3, characterized in that, in the step b, the mass of the cement mixed is 5%-8% of the mass of the drill slag.
  5. 根据权利要求1-3任一所述的方法,其特征在于,相邻两个所述孔一(2)之间的间隔为10-20cm。The method according to any one of claims 1-3, wherein the interval between two adjacent holes (2) is 10-20 cm.
  6. 根据权利要求1-3任一所述的方法,其特征在于,所述孔一(2)通过所述旋挖钻进行钻孔。The method according to any one of claims 1 to 3, wherein the hole one (2) is drilled by the rotary drill.
PCT/CN2020/090406 2019-11-08 2020-05-15 Method for excavating tunnel shaft WO2021088349A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201911090117.2 2019-11-08
CN201911090117.2A CN110821497A (en) 2019-11-08 2019-11-08 Excavation method of tunnel vertical shaft

Publications (1)

Publication Number Publication Date
WO2021088349A1 true WO2021088349A1 (en) 2021-05-14

Family

ID=69554006

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2020/090406 WO2021088349A1 (en) 2019-11-08 2020-05-15 Method for excavating tunnel shaft

Country Status (2)

Country Link
CN (1) CN110821497A (en)
WO (1) WO2021088349A1 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110821497A (en) * 2019-11-08 2020-02-21 中铁二局集团有限公司 Excavation method of tunnel vertical shaft
CN111794249B (en) * 2020-07-20 2022-03-15 中国铁建重工集团股份有限公司 Construction method of shaft locking structure and shaft locking structure
CN113404496B (en) * 2021-06-30 2023-03-21 中建八局第二建设有限公司 Construction method of limited space ultra-deep shaft
CN113389552B (en) * 2021-07-09 2023-11-10 中铁二局第四工程有限公司 Construction method for dead angle area of small-section ultra-deep vertical shaft of hard plastic rock stratum
CN114790894A (en) * 2022-04-28 2022-07-26 中交第一公路勘察设计研究院有限公司 Large-section hard rock shaft drilling spalling excavation method
CN114961734A (en) * 2022-07-14 2022-08-30 山东黄金矿业科技有限公司深井开采实验室分公司 Drilling pressure relief method suitable for ultra-deep vertical shaft

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060071200A (en) * 2004-12-21 2006-06-26 (주)동양엠티 Method for a rock blasting
CN105201513A (en) * 2015-09-11 2015-12-30 重庆工程职业技术学院 Shaft construction method for rail transit
CN106194193A (en) * 2016-07-25 2016-12-07 长江三峡勘测研究院有限公司(武汉) The auxiliary excavation method of a kind of group hole, big cross section vertical shaft non-explosion large aperture
CN207131404U (en) * 2017-07-24 2018-03-23 中铁二院工程集团有限责任公司 Railway tunnel ultra-deep shaft construction freezing method structural system
CN109681223A (en) * 2018-12-20 2019-04-26 中铁二局集团有限公司 A kind of hard rock stratum tunnel non-explosive excavation construction method
CN110821497A (en) * 2019-11-08 2020-02-21 中铁二局集团有限公司 Excavation method of tunnel vertical shaft

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105401946A (en) * 2015-10-27 2016-03-16 中国水利水电第三工程局有限公司 Reverse blasting excavation method of shaft and pilot shaft

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060071200A (en) * 2004-12-21 2006-06-26 (주)동양엠티 Method for a rock blasting
CN105201513A (en) * 2015-09-11 2015-12-30 重庆工程职业技术学院 Shaft construction method for rail transit
CN106194193A (en) * 2016-07-25 2016-12-07 长江三峡勘测研究院有限公司(武汉) The auxiliary excavation method of a kind of group hole, big cross section vertical shaft non-explosion large aperture
CN207131404U (en) * 2017-07-24 2018-03-23 中铁二院工程集团有限责任公司 Railway tunnel ultra-deep shaft construction freezing method structural system
CN109681223A (en) * 2018-12-20 2019-04-26 中铁二局集团有限公司 A kind of hard rock stratum tunnel non-explosive excavation construction method
CN110821497A (en) * 2019-11-08 2020-02-21 中铁二局集团有限公司 Excavation method of tunnel vertical shaft

Also Published As

Publication number Publication date
CN110821497A (en) 2020-02-21

Similar Documents

Publication Publication Date Title
WO2021088349A1 (en) Method for excavating tunnel shaft
CN105298507B (en) A kind of underground pipe gallery construction method of top open cut bottom tunneler construction
CN110219654B (en) Advanced construction method for side pilot tunnel of mud-rock arch tunnel
CN109371974A (en) A kind of PHC tubular pole implantation construction method suitable for hard geology
CN106150508B (en) A kind of tunnel drilling operation method in karst strata
CN106088099B (en) A kind of subway foundation pit anchor cable processing method
CN104947690A (en) Grooving construction method for embedding underground continuous wall into rock
CN103775110A (en) Underground excavation construction method for multilayer underground space of soft soil area
CN108797618A (en) One kind being used for Urban Underground pipe gallery drainage of foundation pit structure and its construction method
CN110656947A (en) Method for tunneling raised section of seabed bedrock
CN105909262B (en) A kind of bored tunnel driving method
CN108071110A (en) Rotary drilling rig Pile method under complex geological condition
CN104315251B (en) Artificial pipe jacking construction method under soil stone combination geological conditions
CN115478552A (en) Sinking and underground sinking construction method for hard rock geological condition
Davis et al. Groundwater control and stability in an excavation in Magnesian Limestone near Sunderland, NE England
CN109555158A (en) A kind of piping lane construction method
CN110144903B (en) Construction method for foundation pit support in air defense cavity
CN210857242U (en) Side slope anti-skidding supporting construction
CN108019211B (en) Water-intercepting curtain in pilot tunnel of water-rich sandy pebble stratum and construction method thereof
CN209243731U (en) Facet foundation pit is inverse to make rapid construction device
CN112942399A (en) Open caisson mechanical construction device and method for penetrating rock stratum
CN207469263U (en) A kind of rotary digging stake and the compound Extra-Deep Foundation Pit system of high-pressure slip-casting pile pile
CN112031738A (en) Construction method of vertical shaft slag sliding well raise boring machine with diameter of 4-6 m
CN113482630B (en) Advanced pilot pit construction method applied to small-clear-distance double-hole tunnel
CN111648773A (en) Construction method of connection channel communicated with existing underground structure of central urban area

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 20883889

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 20883889

Country of ref document: EP

Kind code of ref document: A1