CN209243731U - Facet foundation pit is inverse to make rapid construction device - Google Patents
Facet foundation pit is inverse to make rapid construction device Download PDFInfo
- Publication number
- CN209243731U CN209243731U CN201821682317.8U CN201821682317U CN209243731U CN 209243731 U CN209243731 U CN 209243731U CN 201821682317 U CN201821682317 U CN 201821682317U CN 209243731 U CN209243731 U CN 209243731U
- Authority
- CN
- China
- Prior art keywords
- section
- bucket
- steel
- shield bucket
- steel shield
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Make rapid construction device the utility model discloses a kind of facet foundation pit is inverse, device includes first segment steel shield bucket the second section steel shield bucket, third section steel protects bucket, section four, steel shield bucket and Section of five steel protect bucket, first segment steel shield bucket the second section steel protects bucket, third section steel protects bucket, section four, steel shield bucket and the successively linear arrangement from top to bottom of Section of five steel shield bucket, the second section steel shield bucket is tightly attached to the inner wall of first segment steel shield bucket, the third section steel shield bucket is tightly attached to the inner wall of the second section steel shield bucket, section four, the steel shield bucket is tightly attached to the inner wall of third section steel shield bucket, section five, the steel shield bucket is tightly attached to the inner wall of Section of four steel shield bucket, notch is provided on the steel shield bucket, receiver section and common section are provided on described Section four and Section of five steel shield bucket.The utility model construction area is small, on surrounding enviroment influence it is small, water-stagnating effect is good, meet underground obstacle easy to clean, easy construction, quickly.
Description
Technical field
Make rapid construction device the utility model relates to facet technical field of construction more particularly to facet foundation pit are inverse.
Background technique
By taking the construction method of the existing facet foundation pit in Yangtze River Delta Area as an example, foundation pit enclosure form is broadly divided into Larsen
Steel sheet pile+inner support is gone along with sb. to guard him, the SMW engineering method of fashioned iron cement mixing method is gone along with sb. to guard him and cast-in-situ bored pile+inner support is gone along with sb. to guard him.Wherein
SMW engineering method and the form of going along with sb. to guard him of drilled pile are also widely used in push pipe working pit and push pipe reception hole.
Existing form of going along with sb. to guard him has obtained sufficiently reliable verifying on deep pit monitor, and has become for the type foundation pit
More conventional building enclosure form.But there is also some of itself to lack for these foundation pit enclosure forms in some special operation conditions
Point, such as be difficult to squeeze into when Larsen steel sheet pile chance cobble, sandy gravel stratum or erratic boulder underground obstacle, steel sheet pile squeezes into rear catch sealing
It is ineffective, the disadvantages of being affected to periphery when steel sheet pile is extracted.
It is that required construction site is larger that the SMW engineering method of fashioned iron cement mixing method, which goes along with sb. to guard him the problem through being commonly encountered, and equipment is flat
Face size just has 7m × 10m or so, Gao Yueyou 20m, and also needs certain equipment rotation and mobile space, although this method
After the completion of construction by fashioned iron carried out extract recycle, but the soil body itself mixed and stirred through cement slurry received it is a degree of
Soil pollution, and the soil strength after stirring is higher, causes certain difficulty to the construction of the following region Other Engineering.
The SMW engineering method of fashioned iron cement mixing method go along with sb. to guard him also be commonly encountered lower part soil layer be rubble, erratic boulder or when rock without
The problems such as method is constructed.
Operating space needed for cast-in-situ bored pile+inner support building enclosure form compares SMW engineering method is relatively small, but drills
Stake building enclosure because can not sealing, be often used cooperatively together with rotary churning pile, the shared area of plane is larger, it is unilateral at least 0.6m
Drilled pile+0.8m single or double rotary churning pile, width is up to 1.4m to 1.9m or so, and drilled pile will after Practical Completion
As permanent barrier, larger obstacle is caused for day rear line and other engineerings.
Top-down construction method in foundation pit construction also through frequently with, but it is most of for set diaphram wall or pile foundation it
The inverse form of construction work for making liner afterwards;The steel reinforced concrete dado form of artificial digging pile, the inverse inverse work for making to be steel reinforced concrete dado, is excavated
The building enclosure form of the retaining wall of the after-pouring of the 1m range.
Those skilled in the art are dedicated to solving above-mentioned technological deficiency.
Utility model content
In view of the above drawbacks of the prior art, the technical purpose of the utility model is to solve in above-mentioned background technique
Existing defect.
To realize the above-mentioned technical purpose, the utility model provides a kind of inverse work of facet foundation pit of the utility model quickly
Constructing device, including first segment steel shield bucket, the second section steel shield bucket, third section steel shield bucket, Section of four steel shield bucket and Section of five steel shield
Bucket, first segment steel protect bucket, the second section steel shield bucket, third section steel shield bucket, Section of four steel shield bucket and Section of five steel shield bucket from top to bottom
Successively linear arrangement, the second section steel shield bucket are tightly attached to the inner wall of first segment steel shield bucket, and the third section steel shield bucket is tightly attached to the
Two section steel protect the inner wall of bucket, and Section of four steel shield bucket is tightly attached to the inner wall of third section steel shield bucket, and Section of five steel shield bucket is tight
It is affixed on the inner wall of Section of four steel shield bucket, notch is provided on each steel shield bucket, Section of four steel shield bucket and Section of five steel protect equal on bucket
It is provided with receiver section and common section, the multi-disc that the receiver section respectively includes heading into position positioned at push pipe with common section is mutually spliced
Receiver section section of jurisdiction and remaining position at common section section of jurisdiction, the reception area of Section of four steel shield bucket, which includes that two pieces of left and right is independent, to be held
Plate above plate and pluggable board.
Further, the top of steel shield bucket is peripherally uniformly arranged that there are four suspension centres;Slot on any steel shield bucket
The quantity of mouth is eight, and the bucket that is located at of the notch is pushed up to more than bucket bottom 20 centimeters.
Further, the outer diameter of the first segment steel shield bucket is 5.575 meters, and internal diameter is 5.525 meters, barrel wall thickness 0.25
Rice, the height of shield bucket are 2 meters;Second section steel protect bucket outer diameter be 5.52 meters, internal diameter be 5.47 meters, 0.25 meter of barrel wall thickness,
It is 2 meters that it, which protects bucket height,;The outer diameter of the third section steel shield bucket is 5.465 meters, and internal diameter is 5.415 meters, and barrel wall thickness is 0.25
Rice, shield bucket height is 2 meters;Section four, the outer diameter of the steel shield bucket is 5.41 meters, and internal diameter is 5.34 meters, and barrel wall thickness is 0.35
Rice, shield bucket height is 3 meters;Section five, the outer diameter of the steel shield bucket is 5.205 meters, and internal diameter is 5.155 meters, and a barrel wall thickness is
0.25 meter, shield bucket height is 2.04 meters.
Further, the inner wall upper and lower ends of Section of four steel shield bucket and Section of five steel shield bucket are provided with prestress steel
Rope fixed point, the prestressed cable fixed point are connected with prestressed cable.
The utility model has the beneficial effects that
The device of the utility model, construction area is small, small on surrounding enviroment influence, and water-stagnating effect is good, meets underground obstacle
Easy to clean, easy construction, quickly.
Detailed description of the invention
Fig. 1 is that the utility model CDR method goes along with sb. to guard him plan view;
Fig. 2 is that the utility model CDR method goes along with sb. to guard him sectional view;
Fig. 3 is the utility model receiver section steel plate socket joint detail drawing;
Fig. 4 is that the utility model steel protects bucket bucket wall construction schematic diagram.
In figure: 1 first steel protects bucket, 2 second steel shield bucket, 3 third steel shield bucket, 4 the 4th steel shield bucket, 5 the 5th steel and protects bucket, 6 slots
Mouth, 7 push pipes, 8 suspension centres, 9 prestressed cable fixed points, 10 boards, 11 plates, 12 prestressed cables.
Specific embodiment
Make furtherly below with reference to technical effect of the attached drawing to the design of the utility model, specific structure and generation
It is bright, to be fully understood from the purpose of this utility model, feature and effect.
Embodiment:
- Fig. 4 referring to Fig.1, a kind of facet foundation pit of the utility model is inverse to make rapid construction device, including first segment steel shield
Bucket 1 second section steel shield bucket 2, third section steel shield bucket 3, Section of four steel shield bucket 4 and Section of five steel protect bucket 5, and the first segment steel protects bucket
1, the second section steel shield bucket 2, third section steel shield bucket 3, Section of four steel shield bucket 4 and Section of five steel shield bucket 5 are successively linear from top to bottom
Arrangement, the second section steel shield bucket 2 are tightly attached to the inner wall of first segment steel shield bucket 1, and the third section steel shield bucket 3 is tightly attached to the second section
Steel protects the inner wall of bucket 2, and Section of four steel shield bucket 4 is tightly attached to the inner wall of third section steel shield bucket 3, and Section of five steel shield bucket 5 is tight
It is affixed on the inner wall of Section of four steel shield bucket 4, notch 6, Section of four steel shield bucket 4 and Section of five steel are provided on each steel shield bucket
Receiver section and common section are provided on shield bucket 5, the receiver section and common section respectively include heading into the more of position positioned at push pipe 7
The reception area of the common section section of jurisdiction at receiver section section of jurisdiction and remaining position that piece mutually splices, Section of four steel shield bucket 4 includes left and right
The plate 11 of 10 top of two pieces of independent boards 10 and pluggable board.
Further, the top of steel shield bucket is peripherally uniformly arranged that there are four suspension centres 8;
Further, the quantity of notch 6 is eight on any steel shield bucket, and the notch 6 be located at bucket push up to
More than bucket bottom 20 centimeters;
Further, the outer diameter of the first segment steel shield bucket 1 is 5.575 meters, and internal diameter is 5.525 meters, barrel wall thickness 0.25
Rice, the height of shield bucket are 2 meters;
Further, the outer diameter of the second section steel shield bucket 2 is 5.52 meters, and internal diameter is 5.47 meters, 0.25 meter of barrel wall thickness,
It is 2 meters that it, which protects bucket height,;
Further, the outer diameter of the third section steel shield bucket 3 is 5.465 meters, and internal diameter is 5.415 meters, and a barrel wall thickness is
0.25 meter, shield bucket height is 2 meters;
Further, the outer diameter of Section of four steel shield bucket 4 is 5.41 meters, and internal diameter is 5.34 meters, and barrel wall thickness is 0.35
Rice, shield bucket height is 3 meters;
Further, the outer diameter of Section of five steel shield bucket 5 is 5.205 meters, and internal diameter is 5.155 meters, and a barrel wall thickness is
0.25 meter, shield bucket height is 2.04 meters;
Further, the inner wall upper and lower ends of Section of four steel shield bucket 4 and Section of five steel shield bucket 5 are provided with prestressing force
Cable wire fixed point 9, the prestressed cable fixed point 9 are connected with prestressed cable 12.
The facet foundation pit of the utility model is inverse to make rapid constructing method, the specific steps are as follows:
The first step flattens live soil, excavates and changes back-up sand bed course;
Second step, the installation first segment steel protect bucket 1, draw the soil body dug in first segment steel shield bucket 1, and by the first segment
Steel shield bucket 1 is sunk down at the absolute altitude of setting;
Third step, when the first segment steel shield bucket 1 sink down into setting absolute altitude at after, lifting the second section steel protect bucket 2, by slot
Mouth 6 positions the second section steel of corresponding installation protects bucket 2, equally excavates to the soil body in the second section steel shield bucket 2, and
It sinks down into it at absolute altitude of setting, the third section steel then is installed using same method and protects bucket 3;
4th step, when installing Section of four steel shield bucket 4, need the first receiver section of assembled Section of four steel shield bucket 4 and general
Arc-shaped plate (plate thickness 15mm) is inserted into two pieces of boards by logical section, receiver section, and in anchor cable fixed point, (anchor cable is fixed after assembly
Point: it because steel shield bucket 4 and steel shield bucket 5 are spliced by two or more sections of jurisdiction, needs as the bucket one by wood board splicing
Outside sample plus one encloses iron wire and applies prestressing force, prestressing force of this engineering without the same steel wire of application outside of image of Buddha wooden buckt, because
This just welds the handle of the semi-circular shape of a diagram every the space of 300mm or ear mouth exists in the place of casing 4 and casing 5
On steel drum, so that steel strand wires can pass through in the handle or ear mouth in casing and then form one for steel shield bucket fixed bit entirety
One circle) circular hole in insertion prestressed cable and apply prestressing force, then according to the installation side of first segment steel shield bucket 1
Method is installed;
5th step, the receiver section of the assembled Section of five steel shield bucket 5 and common section, will be inserted into the circular hole of anchor cable fixed point
Prestress wire simultaneously applies prestressing force, lifts by crane Section of five steel and protects bucket 5, and Section of five steel shield bucket 5 is pressed receiver hole
It (because the top of steel shield bucket 5 is that have push pipe so steel shield bucket 5 is spliced by receiver section section of jurisdiction and common section section of jurisdiction, installs
Need to be determined when positioning received push pipe steel shield bucket 5 reception area section of jurisdiction within the scope of) position install, excavate the soil body simultaneously sink;
6th step, push pipe 7 extract Section four of plate before accessing, recycle after-pouring in push pipe head or build internal check
Well backfills below the soil body to prestressed cable after it forms setting intensity, continues to be backfilled to after cutting off prestressed cable 12
Next 12 face of prestressed cable cuts off the prestressed cable 12 at backfill face place, is backfilled at the top of every section steel shield bucket to backfill
Afterwards, it extracts steel and protects bucket, backfill after extraction to extracting the gap that steel shield bucket generates, recycle Section of four steel shield bucket 4 and the
When five section steel protect bucket 5, the shield bucket of common section is first lifted by crane, after the completion of the recycling of the shield bucket of common section, on one side by the shield bucket of receiver section
It is extracted upwards on one side to lateral movement;
7th step continues to backfill and extract every section steel shield bucket to ground according to above-mentioned steps.
In the present embodiment, in second step, if first segment steel shield bucket 1 because the resistance of lateral wall is excessively high when can not sink,
The artificial method for pushing and hammering is taken to help heavy.
In the present embodiment, in the 4th step, receiver section is inserted into ear mouth after plate is smeared vaseline.
In the present embodiment, in the 6th step, backfill should be layered progress, and guarantee to be not less than 0.90 compactness.
In the present embodiment, in the 6th step, backfilled after backfill is backfilled at the top of every section steel shield bucket using loop wheel machine extraction
The steel at place protects bucket, smears the method drag reduction of lubricant before every section steel shield bucket backfill using inner wall.
In the present embodiment, in the 6th step, gap is backfilled with medium coarse sand or tracking grouting after extraction.
The utility model construction area is small, small on surrounding enviroment influence, and water-stagnating effect is good, meets underground obstacle easy to clean,
Easy construction, quickly.
The preferred embodiments of the present invention have been described in detail above.It should be appreciated that the ordinary skill people of this field
Member according to the present utility model can conceive without creative work makes many modifications and variations.Therefore, all this technology necks
Technical staff passes through logic analysis, reasoning or limited reality according to the design of the utility model on the basis of existing technology in domain
Available technical solution is tested, it all should be within the scope of protection determined by the claims.
Claims (4)
1. a kind of facet foundation pit is inverse to make rapid construction device, which is characterized in that protect bucket (1), the second section steel including first segment steel
It protects bucket (2), third section steel shield bucket (3), Section of four steel shield bucket (4) and Section of five steel and protects bucket (5), first segment steel shield bucket (1),
Second section steel protects bucket (2), third section steel shield bucket (3), Section of four steel shield bucket (4) and Section of five steel and protects bucket (5) from top to bottom successively
Linear arrangement, the second section steel shield bucket (2) are tightly attached to the inner wall of first segment steel shield bucket (1), and the third section steel protects bucket (3)
It is tightly attached to the inner wall of the second section steel shield bucket (2), Section of four steel shield bucket (4) is tightly attached to the inner wall of third section steel shield bucket (3), institute
The inner wall that Section of five steel shield bucket (5) is tightly attached to Section of four steel shield bucket (4) is stated, is provided with notch (6) on each steel shield bucket, described the
Receiver section and common section are provided in four section steel shield bucket (4) and Section of five steel shield bucket (5), the receiver section and common section are distinguished
The common section section of jurisdiction at the receiver section section of jurisdiction and remaining position that the multi-disc of position is mutually spliced is headed into including being located at push pipe (7), the
The reception area that four section steel protect bucket (4) includes the plate (11) above the two pieces of independent boards (10) in left and right and pluggable board.
2. a kind of facet foundation pit is inverse according to claim 1 makees rapid construction device, it is characterised in that: the top of steel shield bucket
It is peripherally uniformly arranged there are four suspension centre (8), the quantity that steel protects notch (6) on bucket is eight, and the notch (6) are located at
Bucket is pushed up to more than bucket bottom 20 centimeters.
3. a kind of facet foundation pit is inverse according to claim 1 makees rapid construction device, it is characterised in that: the first segment steel
The outer diameter for protecting bucket (1) is 5.575 meters, and internal diameter is 5.525 meters, and 0.25 meter of barrel wall thickness, the height of shield bucket is 2 meters;Described
The outer diameter that two section steel protect bucket (2) is 5.52 meters, and internal diameter is 5.47 meters, and 0.25 meter of barrel wall thickness, shield bucket height is 2 meters;It is described
The outer diameter that third section steel protects bucket (3) is 5.465 meters, and internal diameter is 5.415 meters, and barrel wall thickness is 0.25 meter, and shield bucket height is 2
Rice;Section four, the outer diameter of steel shield bucket (4) is 5.41 meters, and internal diameter is 5.34 meters, and barrel wall thickness is 0.35 meter, protects bucket height
It is 3 meters;Section five, the outer diameter of steel shield bucket (5) is 5.205 meters, and internal diameter is 5.155 meters, and barrel wall thickness is 0.25 meter, shield
Bucket height is 2.04 meters.
4. a kind of facet foundation pit is inverse according to claim 1 makees rapid construction device, it is characterised in that: Section of four steel
Shield bucket (4) and the inner wall upper and lower ends of Section of five steel shield bucket (5) are provided with prestressed cable fixed point (9), the prestressing force
Cable wire fixed point (9) is connected with prestressed cable (12).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821682317.8U CN209243731U (en) | 2018-10-17 | 2018-10-17 | Facet foundation pit is inverse to make rapid construction device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821682317.8U CN209243731U (en) | 2018-10-17 | 2018-10-17 | Facet foundation pit is inverse to make rapid construction device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209243731U true CN209243731U (en) | 2019-08-13 |
Family
ID=67525118
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821682317.8U Active CN209243731U (en) | 2018-10-17 | 2018-10-17 | Facet foundation pit is inverse to make rapid construction device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209243731U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109208608A (en) * | 2018-10-17 | 2019-01-15 | 上海市城市建设设计研究总院(集团)有限公司 | Facet foundation pit is inverse to make rapid construction devices and methods therefor |
-
2018
- 2018-10-17 CN CN201821682317.8U patent/CN209243731U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109208608A (en) * | 2018-10-17 | 2019-01-15 | 上海市城市建设设计研究总院(集团)有限公司 | Facet foundation pit is inverse to make rapid construction devices and methods therefor |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106988302B (en) | A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method | |
WO2021088349A1 (en) | Method for excavating tunnel shaft | |
Allenby et al. | Examples of open caisson sinking in Scotland | |
CN205822220U (en) | A kind of assembled open caisson | |
CN209243731U (en) | Facet foundation pit is inverse to make rapid construction device | |
CN104533289B (en) | Overhead transmission line grounded screen non-excavating construction method | |
CN103806444A (en) | Soft soil layer rotary excavating pile construction method | |
CN110512594A (en) | The simple and easy method of churning driven opportunity cavity pore-forming | |
CN103161469A (en) | Method for excavating vertical shaft to underground repair pipe-jacking tool pipe | |
CN112943256B (en) | Construction method of prefabricated pipe-jacking working well | |
CN109208608A (en) | Facet foundation pit is inverse to make rapid construction devices and methods therefor | |
CN113653052A (en) | Obstacle clearing construction method for large-diameter underground steel-concrete composite structure | |
Boon et al. | Protection of buildings and structures within the influence of tunnelling works | |
Mok et al. | Trenchless construction of Phase IIIA district cooling system (DCS) by TBM pipejacking and hand-dug tunnelling on Kai Tak Development: part I–design and construction considerations | |
Sze et al. | Application of shaft grouting technique in deep foundations-Hong Kong experience | |
CN110306533A (en) | The construction method of steel reinforced concrete column type connector and the joint continuous concrete wall | |
Quigg | Battersea cable tunnel: powering regeneration in central London, UK. | |
Chu et al. | Integrate approach for deep excavation along soft ground (MTRC) tunnels | |
Linde-Arias et al. | Depressurisation for the excavation of Stepney Green cavern | |
Morrison et al. | Design and construction of a deep shaft for Crossrail | |
CN215252906U (en) | A special-shaped double row pile supporting construction for karst cave development stratum | |
US10954645B2 (en) | System and apparatus for driving piles | |
Kumar et al. | Emerging Trends in Foundation Engineering in India: Case Study | |
CN109403336B (en) | Dangerous house protection structure near foundation pit and construction method thereof | |
CN106436737A (en) | Communication steel pipe pile foundation pile pressing type greenbelt communication tower and installation method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |