WO2021088279A1 - Underground pipeline having two-in-one support pile and pipeline wall and construction method - Google Patents

Underground pipeline having two-in-one support pile and pipeline wall and construction method Download PDF

Info

Publication number
WO2021088279A1
WO2021088279A1 PCT/CN2020/077899 CN2020077899W WO2021088279A1 WO 2021088279 A1 WO2021088279 A1 WO 2021088279A1 CN 2020077899 W CN2020077899 W CN 2020077899W WO 2021088279 A1 WO2021088279 A1 WO 2021088279A1
Authority
WO
WIPO (PCT)
Prior art keywords
plate
combined
pipeline
top plate
bottom plate
Prior art date
Application number
PCT/CN2020/077899
Other languages
French (fr)
Chinese (zh)
Inventor
战福军
Original Assignee
南京联众工程技术有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from CN201911087642.9A external-priority patent/CN110792103A/en
Priority claimed from CN201921920525.1U external-priority patent/CN211773883U/en
Application filed by 南京联众工程技术有限公司 filed Critical 南京联众工程技术有限公司
Publication of WO2021088279A1 publication Critical patent/WO2021088279A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench

Definitions

  • the invention relates to an underground pipeline and a construction method, in particular to an underground pipeline in which a supporting pile and a pipeline wall are combined into one and a construction method.
  • the current underground large-diameter pipe gallery are mostly reinforced concrete structures.
  • the foundation pit is excavated first.
  • the foundation pit has a pile-supported foundation pit and a slope-excavated foundation pit without pile support.
  • the construction of the pipe gallery begins in the foundation pit, supporting the formwork, tying steel bars, pouring concrete, and so on.
  • the concrete strength reaches the standard, carry out the earth backfilling on both sides of the pipe gallery and the earth backfilling on the top of the pipe.
  • Most of the installation methods of underground pipe gallery have disadvantages such as longer construction period, higher construction cost, and greater impact on surrounding structures.
  • the present invention aims to provide an underground pipeline and a construction method that is convenient for construction, short construction period, and high-strength supporting piles and pipeline walls are combined into one.
  • An underground pipeline in which a supporting pile and a pipeline wall are combined into one comprising a pipe section composed of a top plate, a bottom plate and two side plates.
  • the adjacent pipe sections are spliced in the axial direction to form a pipe gallery.
  • the lower end of the slab extends downward and is inserted into the soil foundation, and at the same time acts as a supporting pile and a pipe wall.
  • the top plate, side plate and bottom plate are steel plates.
  • the top plate, side plate and bottom plate are flat steel plates or corrugated steel plates.
  • the adjacent side plates are connected in a sealed manner by flanges.
  • the two sides of the bottom plate and the top plate are respectively connected with flange pieces, and the flange pieces are respectively perpendicular to the bottom plate and the top plate; the bottom plate and the top plate are respectively connected to the side plates through the flange pieces.
  • the side plate is a corrugated steel plate
  • the flange piece is corrugated, and the corrugated arc of the flange is the same as the corrugated arc of the corrugated steel plate column.
  • the side plate is a combined steel plate, and an upper side plate and a lower side plate are arranged in the vertical direction, and the upper and lower side plates are connected in a detachable connection manner.
  • a splint and a bolt are used for connection.
  • the bottom plate and/or the top plate are arched outwards.
  • the upper part of the top plate is provided with a backfill layer.
  • the lower part of the bottom plate is provided with a concrete layer.
  • connection mode of adjacent side plates in the step B is flange connection.
  • the side plate is a combined steel plate, and an upper side plate and a lower side plate are arranged in the vertical direction, and the upper and lower side plates are externally connected by a detachable connection.
  • a splint and a bolt are used for connection.
  • step E the top plate is connected to the lower side plate; after step E is implemented, step F1 is implemented: remove the bolts on the splint, and pull out the upper side plate.
  • the utility model extends the side panels downwards and inserts them into the soil foundation to replace the traditional supporting structure. It not only plays a supporting role, but also serves as the side wall of the pipe gallery, which greatly saves the cost, greatly reduces the amount of construction, and makes the construction The construction period is shortened.
  • the bottom plate and top plate of the utility model are steel plates. Compared with the traditional concrete pipe gallery or the pipe gallery where the side plate is steel plate and the bottom plate is a concrete structure, the connection is more convenient, easier to seal, and the seal is stronger; the construction work surface is small , Reducing the impact on surrounding foundations and structures, and the construction process is more environmentally friendly.
  • the pipe gallery of the utility model is light in weight and convenient to transport, and each part of the structure can be transported over a long distance. Adopting this assembled structure facilitates standardized production.
  • Figure 1 is a schematic diagram of the process of step A of the present invention.
  • FIG. 2 is a schematic diagram of the process of step B of the present invention.
  • FIG. 3 is a schematic diagram of the process of step C of the present invention.
  • Figure 4 is a schematic diagram of the structure of the present invention.
  • Figure 5 is a schematic diagram of the combined steel plate structure of the present invention.
  • the inventor found that if it is a steel plate column support, the steel plate column must be pulled out, and if it is a pile that cannot be pulled out, the pile body will remain in the foundation.
  • the above-mentioned concrete pipe gallery has a long construction period, and there are many environmental protection problems such as dust and noise on the construction site, which have a greater impact on the traffic around the construction site, and there is a large demand for materials such as sand and gravel.
  • the price of concrete is getting more and more expensive, and the cost of pipe gallery structures is getting higher and higher.
  • the foundation pit is a slope excavation foundation pit without pile support
  • the slope foundation pit has a large demand for the working surface of the site, and the amount of excavation and backfilling is large. If it is a bored pile or steel plate supporting foundation pit, The cost is higher, and the supporting structure has a great impact on the surrounding foundation and surrounding structures. In addition, the construction period is long and the personnel cost is relatively high.
  • two rows of parallel side plates 2 are driven into the target plot 1 with a pile driver.
  • the depth of the two rows of side plates is greater than the height of the pipe gallery, and the distance between the two rows of parallel side plates is equal to the design width of the pipe gallery .
  • the two rows of steel plates are composed of several steel plate unit pieces, and the sides of the steel plate are provided with flange faces and flange holes.
  • cross braces 3 should be arranged between the two rows of side plates, as shown in Figure 2.
  • the flange faces and flange holes on the adjacent side plates to seal the adjacent side plates with bolts.
  • the side plate can be a straight steel plate or a corrugated steel plate to improve the strength of the structure and the ability to resist lateral earth pressure.
  • a steel structure bottom plate 5 of the pipe gallery is set at the bottom of the foundation pit, flange plates 6 are welded on both sides of the bottom plate 5, and the flange plates are welded perpendicularly to the steel plate.
  • the flange sheet 6 is provided with flange holes, and the side plates are provided with reserved holes corresponding to the flange holes.
  • the bottom plate 5 is connected with the corrugated steel plate through bolts 7, as shown in FIG. 3.
  • the connecting surface between the flange sheet 6 and the side plate 2 can be provided with a rubber gasket to increase the sealing performance of the pipe gallery.
  • one-way construction bolts can be used. If ordinary bolts are used, nuts need to be welded to the holes on the back of the side plates in advance.
  • a top plate 8 is provided on the upper part of the side plate 2.
  • the top plate is connected in the same way as the bottom plate, and flange pieces 8 are welded on both sides of the top plate, and the top plate 8 is connected to the side plate 2 with bolts 10.
  • the connecting surface between the flange sheet 8 and the side plate 2 can be provided with a rubber gasket to increase the sealing performance of the pipe gallery.
  • the distance between the top plate and the bottom plate is equal to the design height of the pipe gallery.
  • the top plate 8 and the bottom plate 5 may be flat steel plates or corrugated steel plates.
  • the top plate 8 and the bottom plate 5 can also be arch plates that arch outward.
  • a flange connection is adopted, and a rubber sealing gasket is arranged between the flanges to increase the sealing performance of the pipe gallery.
  • the backfill layer 11 can be excavated soil or other backfill materials.
  • reinforcing ribs can be arranged between the flange piece and the top or bottom plate to increase the strength of the plate and prevent the plate from being deformed during the connection process.
  • the steel plate can also be a combined side plate 13, which is divided into two sections in the height direction, namely, an upper side plate 15 and a lower side plate 14, as shown in FIG. 5.
  • the upper side plate 15 and the lower side plate 14 are externally provided with a clamping plate 16 and bolts 17 to connect and fix the combined side plate 13.
  • the lower side plate 14 is connected with the top plate and the bottom plate to form pipe joints. After the top plate and steel plate are connected and installed, remove the bolts on the splint, backfill the upper part of the top plate to the ground, and pull out the upper side plate 15.
  • the combined side plate 13 can be used. The removal of the upper side plate can prevent the waste of steel and increase the strength of the side plate when it is driven into the soil foundation.
  • the combined side plate 13 may be a corrugated steel plate, and the corresponding splint 16 has a corrugated shape, and the corrugated shape is consistent with the corrugated steel plate shape.
  • the utility model replaces the traditional supporting structure with a steel plate knot, which not only plays a supporting role but also acts as a side wall of a pipe gallery, greatly saves the cost, greatly reduces the amount of construction, and shortens the construction period.
  • the bottom plate and the top plate of the utility model are made of steel plates. Compared with the traditional concrete pipe gallery or the pipe gallery where the side plate is a steel plate and the bottom plate is a concrete structure, the connection is more convenient, the seal is easier and the sealing performance is stronger.
  • the construction work surface is small, which reduces the impact on surrounding foundations and structures, and the construction process is more environmentally friendly.
  • the pipe gallery of the utility model has strong sealing performance, light weight and convenient transportation, and the structural parts of various parts can be transported in a long distance. Adopting this assembled structure facilitates standardized production.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Foundations (AREA)

Abstract

Disclosed is an underground pipeline having a two-in-one support pile and pipeline wall, comprising pipe joints which are composed of a top plate, a bottom plate and two side plates; adjacent pipe joints are spliced in the axial direction to form pipe racks; and lower ends of the two side plates extend downward and insert into a soil foundation, and simultaneously serve as a support pile and a pipeline wall. In the present invention, a traditional support structure is replaced with a steel plate structure, which not only has a supporting effect but also serves as a pipe rack side wall, thus greatly reducing fabrication costs, significantly reducing the construction volume, and shortening the construction period.

Description

支护桩与管道墙体合二为一的地下管道及施工方法Underground pipeline with supporting pile and pipeline wall combined into one and construction method 技术领域Technical field
本发明涉及一种地下管道及施工方法,尤其涉及一种支护桩与管道墙体合二为一的地下管道及施工方法。The invention relates to an underground pipeline and a construction method, in particular to an underground pipeline in which a supporting pile and a pipeline wall are combined into one and a construction method.
背景技术Background technique
现在的地下大口径管廊,特别是矩形管廊,大部分是钢筋混凝土结构。一般首先进行基坑开挖,基坑有桩支护基坑和无桩支护的放坡开挖基坑。基坑施工完毕后,在基坑内开始管廊的建筑施工,支模板御扎钢筋、浇筑混凝土等等。混凝土强度达标后,进行管廊两侧的土方回填及管顶的土方回填。大部分地下管廊的安装方法存在施工工期较长、施工成本较高、对周围结构影响较大等缺点。The current underground large-diameter pipe gallery, especially the rectangular pipe gallery, are mostly reinforced concrete structures. Generally, the foundation pit is excavated first. The foundation pit has a pile-supported foundation pit and a slope-excavated foundation pit without pile support. After the construction of the foundation pit is completed, the construction of the pipe gallery begins in the foundation pit, supporting the formwork, tying steel bars, pouring concrete, and so on. After the concrete strength reaches the standard, carry out the earth backfilling on both sides of the pipe gallery and the earth backfilling on the top of the pipe. Most of the installation methods of underground pipe gallery have disadvantages such as longer construction period, higher construction cost, and greater impact on surrounding structures.
发明内容Summary of the invention
发明目的:本发明旨在提供一种施工方便、施工周期短、强度高的支护桩与管道墙体合二为一的地下管道及施工方法。Purpose of the invention: The present invention aims to provide an underground pipeline and a construction method that is convenient for construction, short construction period, and high-strength supporting piles and pipeline walls are combined into one.
技术方案:一种支护桩与管道墙体合二为一的地下管道,包括由顶板、底板和两侧板组成的管节,相邻管节沿轴向拼接成管廊,所述两侧板下端向下延伸插入土基中,同时充当支护桩与管道墙体。所述顶板、侧板和底板为钢板。Technical solution: An underground pipeline in which a supporting pile and a pipeline wall are combined into one, comprising a pipe section composed of a top plate, a bottom plate and two side plates. The adjacent pipe sections are spliced in the axial direction to form a pipe gallery. The lower end of the slab extends downward and is inserted into the soil foundation, and at the same time acts as a supporting pile and a pipe wall. The top plate, side plate and bottom plate are steel plates.
所述顶板、侧板和底板为平直钢板或波纹钢板。The top plate, side plate and bottom plate are flat steel plates or corrugated steel plates.
所述相邻侧板通过法兰密封连接。The adjacent side plates are connected in a sealed manner by flanges.
所述底板和顶板两侧边分别连接有法兰片,该法兰片分别与底板、顶板垂直;所述底板和顶板分别通过法兰片连接至侧板。The two sides of the bottom plate and the top plate are respectively connected with flange pieces, and the flange pieces are respectively perpendicular to the bottom plate and the top plate; the bottom plate and the top plate are respectively connected to the side plates through the flange pieces.
当侧板为波纹钢板时,所述法兰片为波纹形,该法兰波纹弧度与波纹钢板柱波纹弧度相同。When the side plate is a corrugated steel plate, the flange piece is corrugated, and the corrugated arc of the flange is the same as the corrugated arc of the corrugated steel plate column.
所述侧板为组合式钢板,在竖直方向设有上段侧板和下段侧板,上、下段侧板之间采用可拆卸连接方式连接。优选的,采用夹板与螺栓进行连接。The side plate is a combined steel plate, and an upper side plate and a lower side plate are arranged in the vertical direction, and the upper and lower side plates are connected in a detachable connection manner. Preferably, a splint and a bolt are used for connection.
所述底板和/或顶板向外起拱。The bottom plate and/or the top plate are arched outwards.
所述顶板上部设有回填层。The upper part of the top plate is provided with a backfill layer.
所述底板下部设有混凝土层。The lower part of the bottom plate is provided with a concrete layer.
本发明的一种支护桩与管道墙体合二为一的地下管道施工方法,其特征在于,包括以下步骤:An underground pipeline construction method in which a supporting pile and a pipeline wall are combined into one according to the present invention is characterized in that it comprises the following steps:
A、根据管廊设计宽度,将至少两排侧板平行打入目标地块;A. According to the design width of the pipe gallery, drive at least two rows of side panels into the target plot in parallel;
B、将每排钢板之间的土基挖除至管廊设计深度,密封连接相邻的侧板(2), 并在平行钢板之间设置横撑;B. Excavate the soil foundation between each row of steel plates to the design depth of the pipe gallery, seal and connect the adjacent side plates (2), and install transverse bracing between the parallel steel plates;
C、在基坑底部设置底板,将底板与侧板密封连接;C. Set a bottom plate at the bottom of the foundation pit, and seal the bottom plate with the side plate;
D、向基坑底与底板之间的空隙内填充混凝土;D. Fill the space between the bottom of the foundation pit and the floor with concrete;
E、在每片侧板上部设置顶板,顶板安装高度等于管廊设计高度,顶板与侧板密封连接;E. Set a top plate on the upper part of each side plate, the installation height of the top plate is equal to the design height of the pipe gallery, and the top plate and the side plate are connected in a sealed manner;
F、向管廊顶板上部填充回填材料与地面平齐。F. Fill the upper part of the pipe gallery with backfill material to be flush with the ground.
所述步骤B中的相邻侧板连接方式为法兰连接。The connection mode of adjacent side plates in the step B is flange connection.
所述侧板为组合式钢板,在竖直方向设有上段侧板和下段侧板,上、下段侧板外部采用可拆卸连接方式连接。优选的,采用夹板与螺栓连接。The side plate is a combined steel plate, and an upper side plate and a lower side plate are arranged in the vertical direction, and the upper and lower side plates are externally connected by a detachable connection. Preferably, a splint and a bolt are used for connection.
在步骤E中,所述顶板连接下段侧板;在实施步骤E后,实施步骤F1:拆除夹板上的螺栓,拔出上段侧板。In step E, the top plate is connected to the lower side plate; after step E is implemented, step F1 is implemented: remove the bolts on the splint, and pull out the upper side plate.
有益效果:与现有技术相比,本发明具有如下显著优点:Beneficial effects: Compared with the prior art, the present invention has the following significant advantages:
(1)本实用新型将侧板向下延伸插入土基中,替代传统支护结构,既起到支护作用,又充当管廊侧壁,大大节省造价,极大地减少了施工量,使施工工期缩短。(1) The utility model extends the side panels downwards and inserts them into the soil foundation to replace the traditional supporting structure. It not only plays a supporting role, but also serves as the side wall of the pipe gallery, which greatly saves the cost, greatly reduces the amount of construction, and makes the construction The construction period is shortened.
(2)本实用新型的底板与顶板为钢板,与传统混凝土管廊或侧板为钢板底板为混凝土结构的管廊相比,连接更加方便,更容易密封且密封性更强;施工工作面小,减少了对周围地基及构造物的影响,施工过程更加环保。(2) The bottom plate and top plate of the utility model are steel plates. Compared with the traditional concrete pipe gallery or the pipe gallery where the side plate is steel plate and the bottom plate is a concrete structure, the connection is more convenient, easier to seal, and the seal is stronger; the construction work surface is small , Reducing the impact on surrounding foundations and structures, and the construction process is more environmentally friendly.
(3)本实用新型的管廊的重量轻,运输方便,各部分结构件可远距离运输。采用该装配式结构,便于进行标准化生产。(3) The pipe gallery of the utility model is light in weight and convenient to transport, and each part of the structure can be transported over a long distance. Adopting this assembled structure facilitates standardized production.
附图说明Description of the drawings
图1为本发明步骤A的过程示意图;Figure 1 is a schematic diagram of the process of step A of the present invention;
图2为本发明步骤B的过程示意图;Figure 2 is a schematic diagram of the process of step B of the present invention;
图3为本发明步骤C的过程示意图;Figure 3 is a schematic diagram of the process of step C of the present invention;
图4为本发明的结构示意图;Figure 4 is a schematic diagram of the structure of the present invention;
图5为本发明的组合式钢板结构示意图。Figure 5 is a schematic diagram of the combined steel plate structure of the present invention.
具体实施方式Detailed ways
下面结合附图对本发明的技术方案作进一步说明。The technical scheme of the present invention will be further described below in conjunction with the accompanying drawings.
发明人经过研究不同的支护方式发现,如果是钢板柱支护,则要拔出钢板柱,如果是不能拔出的桩,则桩体会留在地基内。上述混凝土管廊工期长,工地施工的灰尘、噪音等环保问题多,对工地周围通行影响较大,对砂石等材料需求大。除此之外,因环保问题混凝土的价格越来越贵,管廊结构体造价越来越高。After studying different support methods, the inventor found that if it is a steel plate column support, the steel plate column must be pulled out, and if it is a pile that cannot be pulled out, the pile body will remain in the foundation. The above-mentioned concrete pipe gallery has a long construction period, and there are many environmental protection problems such as dust and noise on the construction site, which have a greater impact on the traffic around the construction site, and there is a large demand for materials such as sand and gravel. In addition, due to environmental issues, the price of concrete is getting more and more expensive, and the cost of pipe gallery structures is getting higher and higher.
如果基坑为无桩支护的放坡开挖基坑,在施工方面,放坡基坑对场地工作面需求大,开挖量和回填量大,若是钻孔桩或钢板支护基坑,则造价较高,支护结构体对周边地基及周边结构物影响大。另外,施工周期长,人员成本较大。If the foundation pit is a slope excavation foundation pit without pile support, in terms of construction, the slope foundation pit has a large demand for the working surface of the site, and the amount of excavation and backfilling is large. If it is a bored pile or steel plate supporting foundation pit, The cost is higher, and the supporting structure has a great impact on the surrounding foundation and surrounding structures. In addition, the construction period is long and the personnel cost is relatively high.
如图1所示,将两排平行侧板2用打桩机打入目标地块1,两排侧板打入深度大于管廊的高度,两排平行侧板之间的距离等于管廊设计宽度。两排钢板由若干片钢板单元片组成,钢板侧边设有法兰面与法兰孔。As shown in Figure 1, two rows of parallel side plates 2 are driven into the target plot 1 with a pile driver. The depth of the two rows of side plates is greater than the height of the pipe gallery, and the distance between the two rows of parallel side plates is equal to the design width of the pipe gallery . The two rows of steel plates are composed of several steel plate unit pieces, and the sides of the steel plate are provided with flange faces and flange holes.
将两排钢板中间的土基挖除,土基坑底部4达到一定深度时,两排侧板之间要设置横撑3,如图2所示。开挖过程中或开挖完成后,利用相邻的侧板上的法兰面及法兰孔,用螺栓将相邻的侧板密封连接。Excavate the soil foundation between the two rows of steel plates, and when the bottom 4 of the soil foundation pit reaches a certain depth, cross braces 3 should be arranged between the two rows of side plates, as shown in Figure 2. During the excavation process or after the excavation is completed, use the flange faces and flange holes on the adjacent side plates to seal the adjacent side plates with bolts.
侧板可为平直钢板,也可以为波纹钢板,提高结构的强度和抗侧土压力能力。The side plate can be a straight steel plate or a corrugated steel plate to improve the strength of the structure and the ability to resist lateral earth pressure.
基坑达到该管廊所需深度后,在基坑底部设置管廊的钢结构底板5,底板5的两侧焊接有法兰片6,法兰片与钢板垂直焊接。法兰片6上设有法兰孔,侧板上设有预留孔对应法兰孔,通过螺栓7将底板5与波纹钢板连接,如图3所示。法兰片6与侧板2之间的连接面可设置橡胶垫,增加管廊的密封性。上述连接的螺栓,可采用单向施工的螺栓,若采用普通螺栓,则需在侧板背面的孔上预先焊接螺母。After the foundation pit reaches the required depth of the pipe gallery, a steel structure bottom plate 5 of the pipe gallery is set at the bottom of the foundation pit, flange plates 6 are welded on both sides of the bottom plate 5, and the flange plates are welded perpendicularly to the steel plate. The flange sheet 6 is provided with flange holes, and the side plates are provided with reserved holes corresponding to the flange holes. The bottom plate 5 is connected with the corrugated steel plate through bolts 7, as shown in FIG. 3. The connecting surface between the flange sheet 6 and the side plate 2 can be provided with a rubber gasket to increase the sealing performance of the pipe gallery. For the above-mentioned connecting bolts, one-way construction bolts can be used. If ordinary bolts are used, nuts need to be welded to the holes on the back of the side plates in advance.
安装多片底板后,用管道向该底板5与基底之间的空隙填充混凝土12,该混凝土为泡沫混凝土。After installing multiple bottom plates, pipes are used to fill the gap between the bottom plate 5 and the base with concrete 12, which is foamed concrete.
在侧板2的上部设置顶板8,顶板连接方式与底板相同,也采用在顶板两侧焊接法兰片8的方式,用螺栓10将顶板8连接至侧板2。法兰片8与侧板2之间的连接面可设置橡胶垫,增加管廊的密封性。顶板与底板之间的距离等于管廊的设计高度。A top plate 8 is provided on the upper part of the side plate 2. The top plate is connected in the same way as the bottom plate, and flange pieces 8 are welded on both sides of the top plate, and the top plate 8 is connected to the side plate 2 with bolts 10. The connecting surface between the flange sheet 8 and the side plate 2 can be provided with a rubber gasket to increase the sealing performance of the pipe gallery. The distance between the top plate and the bottom plate is equal to the design height of the pipe gallery.
顶板8与底板5可以为平直钢板,也可以为波纹钢板。顶板8与底板5还可以为向外起拱的拱板。顶板8与底板5在沿轴向方向连接时采用用法兰连接,法兰之间设有橡胶密封的垫片,增加管廊密封性。The top plate 8 and the bottom plate 5 may be flat steel plates or corrugated steel plates. The top plate 8 and the bottom plate 5 can also be arch plates that arch outward. When the top plate 8 and the bottom plate 5 are connected in the axial direction, a flange connection is adopted, and a rubber sealing gasket is arranged between the flanges to increase the sealing performance of the pipe gallery.
安装完顶板后,回填管廊顶板上部基坑至地面,即完成所需埋地管廊工程。回填层11可以为挖除的土料,也可以为其它回填材料。After installing the roof, backfill the upper foundation pit of the pipe gallery roof to the ground to complete the required buried pipe gallery project. The backfill layer 11 can be excavated soil or other backfill materials.
在具体实施中,法兰片与顶板或底板之间可设加强筋,增加板片强度,防止连接过程中板片变形。In specific implementation, reinforcing ribs can be arranged between the flange piece and the top or bottom plate to increase the strength of the plate and prevent the plate from being deformed during the connection process.
钢板还可以是组合式侧板13,在高度方向分为两段,即上段侧板15和下段侧板14,如图5所示。上段侧板15和下段侧板14的外部设置夹板16及螺栓17连接固定该组合式侧板13。上述组合式波纹侧板13,在施工过程中,下段侧板 14与顶板、底板连接形成管节。在顶板与钢板连接安装完成后,拆除夹板上的螺栓,回填顶板上部至地面,拔出上段侧板15。当管廊预埋深度较深时,可采用组合式侧板13,拆除上段侧板可防止对钢材的浪费,同时增加了侧板打入土基时候的强度。The steel plate can also be a combined side plate 13, which is divided into two sections in the height direction, namely, an upper side plate 15 and a lower side plate 14, as shown in FIG. 5. The upper side plate 15 and the lower side plate 14 are externally provided with a clamping plate 16 and bolts 17 to connect and fix the combined side plate 13. In the above-mentioned combined corrugated side plate 13, during the construction process, the lower side plate 14 is connected with the top plate and the bottom plate to form pipe joints. After the top plate and steel plate are connected and installed, remove the bolts on the splint, backfill the upper part of the top plate to the ground, and pull out the upper side plate 15. When the pre-buried depth of the pipe gallery is deep, the combined side plate 13 can be used. The removal of the upper side plate can prevent the waste of steel and increase the strength of the side plate when it is driven into the soil foundation.
该组合式侧板13可以为波纹钢板,相应夹板16为波纹形,波纹形状与波纹钢板形状一致。The combined side plate 13 may be a corrugated steel plate, and the corresponding splint 16 has a corrugated shape, and the corrugated shape is consistent with the corrugated steel plate shape.
本实用新型将钢板结替代传统支护结构,既起到支护作用,又充当管廊侧壁,大大节省造价,极大地减少了施工量,使施工工期缩短。本实用新型的底板与顶板为钢板,与传统混凝土管廊或侧板为钢板底板为混凝土结构的管廊相比,连接更加方便,更容易密封且密封性更强。施工工作面小,减少了对周围地基及构造物的影响,施工过程更加环保。本实用新型的管廊的密封性强,重量轻,运输方便,各部分结构件可远距离运输。采用该装配式结构,便于进行标准化生产。The utility model replaces the traditional supporting structure with a steel plate knot, which not only plays a supporting role but also acts as a side wall of a pipe gallery, greatly saves the cost, greatly reduces the amount of construction, and shortens the construction period. The bottom plate and the top plate of the utility model are made of steel plates. Compared with the traditional concrete pipe gallery or the pipe gallery where the side plate is a steel plate and the bottom plate is a concrete structure, the connection is more convenient, the seal is easier and the sealing performance is stronger. The construction work surface is small, which reduces the impact on surrounding foundations and structures, and the construction process is more environmentally friendly. The pipe gallery of the utility model has strong sealing performance, light weight and convenient transportation, and the structural parts of various parts can be transported in a long distance. Adopting this assembled structure facilitates standardized production.

Claims (12)

  1. 一种支护桩与管道墙体合二为一的地下管道,包括由顶板(8)、底板(6)和两侧板(2)组成的管节,相邻管节沿轴向拼接成管廊,其特征在于,所述两侧板(2)下端向下延伸插入土基中,同时充当支护桩与管道墙体;所述顶板(8)、侧板(2)和底板(9)为钢板。An underground pipeline in which a supporting pile and a pipeline wall are combined into one, comprising a pipe section composed of a top plate (8), a bottom plate (6) and two side plates (2), and adjacent pipe sections are spliced along the axial direction to form a pipe Corridor, characterized in that the lower ends of the two side panels (2) extend downward and are inserted into the soil foundation, and at the same time serve as supporting piles and pipe walls; the top panel (8), the side panels (2) and the bottom panel (9) For steel plate.
  2. 根据权利要求1所述的支护桩与管道墙体合二为一的地下管道,其特征在于,所述侧板为组合式侧板(13),在竖直方向设有上段侧板(15)和下段侧板(14),上、下段侧板之间采用可拆卸连接方式连接;所述顶板(8)连接下段侧板(14)。The underground pipeline in which the supporting pile and the pipeline wall are combined into one according to claim 1, wherein the side plate is a combined side plate (13), and an upper side plate (15) is provided in the vertical direction. ) And the lower section side plate (14), and the upper and lower section side plates are connected in a detachable connection mode; the top plate (8) is connected to the lower section side plate (14).
  3. 根据权利要求1所述的支护桩与管道墙体合二为一的地下管道,其特征在于,所述底板(6)和/或顶板(8)向外起拱。The underground pipeline in which the supporting pile and the pipeline wall are combined into one according to claim 1, characterized in that the bottom plate (6) and/or the top plate (8) arch outwards.
  4. 根据权利要求1所述的支护桩与管道墙体合二为一的地下管道,其特征在于,所述顶板(8)、底板(6)和两侧板(2)为平直钢板。The underground pipeline in which the supporting pile and the pipeline wall are combined into one according to claim 1, wherein the top plate (8), the bottom plate (6) and the two side plates (2) are flat steel plates.
  5. 根据权利要求1所述的支护桩与管道墙体合二为一的地下管道,其特征在于,所述顶板(8)、底板(6)和两侧板(2)为波纹钢板。The underground pipeline in which the supporting pile and the pipeline wall are combined into one according to claim 1, wherein the top plate (8), the bottom plate (6) and the two side plates (2) are corrugated steel plates.
  6. 根据权利要求1所述的支护桩与管道墙体合二为一的地下管道,其特征在于,所述底板(6)和顶板(8)两侧边分别连接有法兰片,该法兰片分别与底板、顶板垂直;所述底板(6)和顶板(8)分别通过法兰连接至侧板(2)。The underground pipeline in which the supporting pile and the pipeline wall are combined into one according to claim 1, wherein the two sides of the bottom plate (6) and the top plate (8) are respectively connected with flange pieces, and the flange The sheets are respectively perpendicular to the bottom plate and the top plate; the bottom plate (6) and the top plate (8) are respectively connected to the side plates (2) through flanges.
  7. 根据权利要求5或6所述的支护桩与管道墙体合二为一的地下管道,其特征在于,所述法兰片为波纹形,该法兰波纹弧度与波纹钢板柱波纹弧度相同。The underground pipeline in which the supporting pile and the pipeline wall are combined into one according to claim 5 or 6, characterized in that the flange piece is corrugated, and the corrugated arc of the flange is the same as the corrugated arc of the corrugated steel plate column.
  8. 根据权利要求1所述的支护桩与管道墙体合二为一的地下管道,其特征在于,所述底板下部设有混凝土层。The underground pipeline in which the supporting pile and the pipeline wall are combined into one according to claim 1, wherein the lower part of the bottom plate is provided with a concrete layer.
  9. 根据权利要求1所述的支护桩与管道墙体合二为一的地下管道,其特征在于,所述顶边上部设有回填层。The underground pipeline in which the supporting pile and the pipeline wall are combined into one according to claim 1, wherein the upper part of the top edge is provided with a backfill layer.
  10. 一种支护桩与管道墙体合二为一的地下管道施工方法,其特征在于,包括以下步骤:An underground pipeline construction method in which a supporting pile and a pipeline wall are combined into one is characterized in that it comprises the following steps:
    A、根据管廊设计宽度,将两排侧板(2)平行打入目标地块(1);A. According to the design width of the pipe gallery, drive the two rows of side panels (2) into the target plot (1) in parallel;
    B、将每排钢板之间的土基挖除至管廊设计深度,密封连接相邻的侧板(2),并在平行钢板之间设置横撑;B. Excavate the soil foundation between each row of steel plates to the design depth of the pipe gallery, seal and connect the adjacent side plates (2), and set up cross braces between the parallel steel plates;
    C、在基坑底部设置底板(5),将底板与侧板(2)密封连接;C. Set a bottom plate (5) at the bottom of the foundation pit, and seal the bottom plate and side plates (2);
    D、向基坑底(4)与底板(5)之间的空隙内填充混凝土(12);D. Fill the space between the bottom of the foundation pit (4) and the bottom plate (5) with concrete (12);
    E、在每片侧板上部设置顶板(8),顶板(8)安装高度等于管廊设计高度,顶板与侧板密封连接;E. Set a top plate (8) on the upper part of each side plate, the installation height of the top plate (8) is equal to the design height of the pipe gallery, and the top plate and the side plate are connected in a sealed manner;
    F、向管廊顶板上部填充回填材料(11)与地面平齐。F. Fill the upper part of the pipe gallery with backfill material (11) flush with the ground.
  11. 根据权利要求10所述的支护桩与管道墙体合二为一的地下管道施工方法,其特征在于,所述侧板为组合式侧板(13),在竖直方向设有上段侧板(15)和下段侧板(14),上、下段侧板外部采用可拆卸连接方式连接。The method for constructing an underground pipeline in which the supporting pile and the pipeline wall are combined into one according to claim 10, wherein the side plate is a combined side plate (13), and an upper side plate is provided in the vertical direction. (15) and the lower section side plate (14), the outer side of the upper and lower section side plates are connected by detachable connection.
  12. 根据权利要求11所述的支护桩与管道墙体合二为一的地下管道施工方法,其特征在于,在步骤E中,所述顶板(8)连接下段侧板(14);在实施步骤E后,实施步骤F1:拆除所述可拆卸连接装置,拔出上段侧板(15)。The underground pipeline construction method in which the supporting pile and the pipeline wall are combined into one according to claim 11, characterized in that, in step E, the top plate (8) is connected to the lower side plate (14); in the implementation step After E, perform step F1: dismantle the detachable connecting device, and pull out the upper side panel (15).
PCT/CN2020/077899 2019-11-08 2020-03-05 Underground pipeline having two-in-one support pile and pipeline wall and construction method WO2021088279A1 (en)

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
CN201911087642.9A CN110792103A (en) 2019-11-08 2019-11-08 Underground pipeline with integrated supporting piles and pipeline wall and construction method
CN201911087642.9 2019-11-08
CN201921920525.1 2019-11-08
CN201921920525.1U CN211773883U (en) 2019-11-08 2019-11-08 Underground pipeline with integrated supporting piles and pipeline wall

Publications (1)

Publication Number Publication Date
WO2021088279A1 true WO2021088279A1 (en) 2021-05-14

Family

ID=75849356

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2020/077899 WO2021088279A1 (en) 2019-11-08 2020-03-05 Underground pipeline having two-in-one support pile and pipeline wall and construction method

Country Status (1)

Country Link
WO (1) WO2021088279A1 (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003193494A (en) * 2001-12-25 2003-07-09 Nihon Samicon Co Ltd Underground hollow structure constructing method and the underground hollow structure
KR20130142045A (en) * 2012-06-18 2013-12-27 윤진숙 Underground structure construction method with unit wall block
CN106049530A (en) * 2016-05-27 2016-10-26 俞晓东 Urban comprehensive pipe gallery and construction method
CN106759462A (en) * 2016-12-09 2017-05-31 广州市市政工程设计研究总院 A kind of prefabricated piping lane and its construction method suitable for narrow construction site
CN107190772A (en) * 2017-06-27 2017-09-22 南京联众建设工程技术有限公司 A kind of underground pipe gallery base configuration and its construction method
CN207331746U (en) * 2017-09-18 2018-05-08 南京叭叭智能科技有限公司 A kind of underground pipe gallery
CN207553135U (en) * 2017-08-30 2018-06-29 中民筑友科技投资有限公司 A kind of pipe gallery
CN110792103A (en) * 2019-11-08 2020-02-14 南京联众工程技术有限公司 Underground pipeline with integrated supporting piles and pipeline wall and construction method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003193494A (en) * 2001-12-25 2003-07-09 Nihon Samicon Co Ltd Underground hollow structure constructing method and the underground hollow structure
KR20130142045A (en) * 2012-06-18 2013-12-27 윤진숙 Underground structure construction method with unit wall block
CN106049530A (en) * 2016-05-27 2016-10-26 俞晓东 Urban comprehensive pipe gallery and construction method
CN106759462A (en) * 2016-12-09 2017-05-31 广州市市政工程设计研究总院 A kind of prefabricated piping lane and its construction method suitable for narrow construction site
CN107190772A (en) * 2017-06-27 2017-09-22 南京联众建设工程技术有限公司 A kind of underground pipe gallery base configuration and its construction method
CN207553135U (en) * 2017-08-30 2018-06-29 中民筑友科技投资有限公司 A kind of pipe gallery
CN207331746U (en) * 2017-09-18 2018-05-08 南京叭叭智能科技有限公司 A kind of underground pipe gallery
CN110792103A (en) * 2019-11-08 2020-02-14 南京联众工程技术有限公司 Underground pipeline with integrated supporting piles and pipeline wall and construction method

Similar Documents

Publication Publication Date Title
CN101736749B (en) Method for constructing soft soil foundation continuous caisson
KR100722665B1 (en) Steel guide wall for construction of underground diaphragm wall and construction method of underground diaphragm wall using the same
CN108612110B (en) Combined type supporting construction method for deep foundation pit of subway station
KR100698878B1 (en) Y Type Connecting Structure of Steel Pipe Struts
KR100968048B1 (en) A retaining panel structure and construction method
KR100531385B1 (en) Construction method of underground structure that enables continuous retaining wall using steel wale and diaphragm effect of concrete slab
CN102286980A (en) Steel truss foundation pit supporting structure
KR101221970B1 (en) Construction Method for Basement Structure without Temporary Structure
KR101171040B1 (en) Pre-fabricated earth retaining wall structure constructing method using prestressed tendon
KR20090114863A (en) Parallelly connected iron tube and construction method for underground structure using the same
KR20090029993A (en) Underground structure and its construction method with retaining wall supported by rigid diaphragm
CN110670603B (en) Assembled type long-strip foundation pit supporting device and method
CN211312570U (en) Can have enough to meet need formula steel open caisson supporting device
KR101862208B1 (en) Earth retaining wall structure and constructuon mothod thereof
KR101054696B1 (en) Top-down construction method for underground structure with slurry wall retained by slab diaphragm effect
KR102490872B1 (en) Reinforced earth retaining wall and construction method using tensile force of steel rod piles
WO2021088279A1 (en) Underground pipeline having two-in-one support pile and pipeline wall and construction method
CN211773883U (en) Underground pipeline with integrated supporting piles and pipeline wall
KR200492883Y1 (en) Braced wall
KR100641355B1 (en) Construction method of corrugated steel pipe structure
JP2018009336A (en) Underground space construction method
KR20100118482A (en) To use reclamation steel perimeter beam and slab diaphragm effect in order for one side of the basement outer wall continuous construct was possible ,which the basement infrastructure construction method
CN110792103A (en) Underground pipeline with integrated supporting piles and pipeline wall and construction method
KR100935317B1 (en) Assembly retaining wall system with ground reinforcement and its construction method
CN211547738U (en) Be used for subway station light weight assembled excavation supporting system that excels in

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 20885886

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 20885886

Country of ref document: EP

Kind code of ref document: A1