CN207553135U - A kind of pipe gallery - Google Patents

A kind of pipe gallery Download PDF

Info

Publication number
CN207553135U
CN207553135U CN201721105188.1U CN201721105188U CN207553135U CN 207553135 U CN207553135 U CN 207553135U CN 201721105188 U CN201721105188 U CN 201721105188U CN 207553135 U CN207553135 U CN 207553135U
Authority
CN
China
Prior art keywords
plate
pipe gallery
construction
bearing
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721105188.1U
Other languages
Chinese (zh)
Inventor
向辉兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhuyou Zhizao Technology Investment Co ltd
Original Assignee
China Mingsheng Drawin Technology Investment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Mingsheng Drawin Technology Investment Co Ltd filed Critical China Mingsheng Drawin Technology Investment Co Ltd
Priority to CN201721105188.1U priority Critical patent/CN207553135U/en
Application granted granted Critical
Publication of CN207553135U publication Critical patent/CN207553135U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

本实用新型属于市政建筑工程领域,公开了一种综合管廊,由多个管节拼接构成,所述管节包括顶板、底板和侧板,所述侧板的底端设有支承端头,所述底板设置在所述支承端头的上部。如此设置,在施工工程中,仅需将支承端头埋入地基中,作为临时支撑以及施工完成后的结构面,然后在相对设置的侧板之间铺设垫层,再将底板设置在支承端头的上部,如此,可减少管廊施工的作业面,施工中不需要放坡开挖基坑,减少了预制综合管廊侧壁外侧土方开挖、回填及压实的工作量,降低施工成本、提高了施工效率,大大减少了对于土地的临时占用和周围环境的扰动,同时,预制综合管廊侧壁能起到临时支撑的作用,降低了施工支撑费用的投入。

The utility model belongs to the field of municipal construction engineering, and discloses a comprehensive pipe gallery, which is formed by splicing a plurality of pipe joints. The pipe joints include a top plate, a bottom plate and a side plate, and the bottom end of the side plate is provided with a supporting end. The bottom plate is arranged on the upper part of the supporting end. In this way, in the construction project, it is only necessary to bury the support end in the foundation as a temporary support and a structural surface after construction, and then lay a cushion between the opposite side plates, and then set the bottom plate on the support end The upper part of the head, in this way, can reduce the working surface of the pipe gallery construction, and do not need to excavate the foundation pit during the construction, which reduces the workload of excavation, backfilling and compaction of the outer side of the side wall of the prefabricated comprehensive pipe gallery, and reduces the construction cost. , Improve the construction efficiency, greatly reduce the temporary occupation of the land and the disturbance of the surrounding environment. At the same time, the side wall of the prefabricated comprehensive pipe gallery can play the role of temporary support, reducing the investment in construction support costs.

Description

一种综合管廊A comprehensive corridor

技术领域technical field

本实用新型属于市政建筑工程领域,具体涉及一种综合管廊。The utility model belongs to the field of municipal construction engineering, in particular to a comprehensive pipe gallery.

背景技术Background technique

传统的地下管廊建设通常是如下两种方式:现场现浇或工厂预制;现场现浇式地下管廊的所有工作均在现场完成,所以侧墙及顶板均要配置模板,不仅造成大量模板的浪费,同时施工周期长,所有原材料均以散装形式运到现场,现场的制作对周边的生态环境也会照成破坏和污染,现场浇注的方式对人工振捣要求高,振捣不实,管廊后期出现微裂纹的可能性较大,会留下漏水隐患。预制管廊由多节预制管节在现场拼接而成,此种方式导致管廊的拼接缝较多,拼接缝处的防水要求高,难度大。The traditional underground pipe gallery construction is usually in the following two ways: cast-in-place or factory prefabrication; all the work of the cast-in-place underground pipe gallery is completed on site, so the side walls and roof must be equipped with formwork, which not only causes a large number of formwork waste, and at the same time the construction period is long, all raw materials are transported to the site in bulk, and the on-site production will also damage and pollute the surrounding ecological environment. The method of on-site pouring requires high manual vibration. Microcracks are more likely to appear in the late stage of the corridor, which will leave hidden dangers of water leakage. The prefabricated pipe gallery is spliced on site by multiple prefabricated pipe sections. This method leads to many joints in the pipe gallery, and the waterproof requirements at the joints are high and difficult.

现有的预制综合管廊施工方法中,通常采用放坡开挖到设计标高后再浇筑垫层,吊装综合管廊完成后再回填,存在占用土地面积大、土方作业量大,需采取较多基坑排降水措施等问题。这种施工方法对于新区的建设还比较可行,但对于交通繁忙区市政管网的改造,工期、环境扰动方面就有比较明显的劣势。In the existing construction method of prefabricated integrated pipe gallery, the cushion layer is usually poured after grading and excavated to the design elevation, and the integrated pipe gallery is hoisted and then backfilled, which takes up a large area of land and a large amount of earthwork, and requires more Foundation pit drainage measures and other issues. This construction method is relatively feasible for the construction of new districts, but it has obvious disadvantages in terms of construction period and environmental disturbance for the reconstruction of municipal pipe networks in busy traffic areas.

综上所述,亟需开发一种成本节约、施工简便的综合管廊。To sum up, there is an urgent need to develop a cost-saving and easy-to-construct integrated pipe gallery.

实用新型内容Utility model content

本实用新型的目的是提供一种成本节约、施工简便优异的综合管廊。The purpose of the utility model is to provide a cost-saving, convenient and excellent comprehensive pipe gallery.

上述目的是通过如下技术方案实现:一种综合管廊,由多个管节拼接构成,所述管节包括顶板、底板和侧板,所述侧板的底端设有支承端头,所述底板设置在所述支承端头的上部。如此设置,在施工工程中,仅需将支承端头埋入地基中,作为临时支撑以及施工完成后的结构面,然后在相对设置的侧板之间铺设垫层,再将底板设置在支承端头的上部,如此,可减少管廊施工的作业面,施工中不需要放坡开挖基坑,减少了预制综合管廊侧壁外侧土方开挖、回填及压实的工作量,降低施工成本、提高了施工效率,大大减少了对于土地的临时占用和周围环境的扰动,同时,预制综合管廊侧壁能起到临时支撑的作用,降低了施工支撑费用的投入。优选,为保证支承端头支撑和承载作用,支承端头的应当厚度大于侧板主体的厚度。The above purpose is achieved through the following technical solutions: a comprehensive pipe gallery, which is composed of a plurality of pipe joints, the pipe joints include a top plate, a bottom plate and a side plate, and the bottom end of the side plate is provided with a supporting end. The bottom plate is arranged on the upper part of the supporting end. In this way, in the construction project, it is only necessary to bury the support end in the foundation as a temporary support and a structural surface after construction, and then lay a cushion between the opposite side plates, and then set the bottom plate on the support end The upper part of the head, in this way, can reduce the working surface of the pipe gallery construction, and do not need to excavate the foundation pit during construction, which reduces the workload of excavation, backfilling and compaction of the outer side of the side wall of the prefabricated comprehensive pipe gallery, and reduces the construction cost. 1. Improve the construction efficiency, greatly reduce the temporary occupation of land and the disturbance of the surrounding environment. At the same time, the side wall of the prefabricated comprehensive pipe gallery can play the role of temporary support, reducing the investment in construction support costs. Preferably, in order to ensure the supporting and bearing functions of the supporting end, the thickness of the supporting end should be greater than the thickness of the main body of the side plate.

进一步,所述侧板包括外页板和承重板,所述外页板与支承端头一体成型,所述承重板设置在所述外页板内侧并设置在所述支承端头的上部,所述承重板设有伸出钢筋,所述伸出钢筋沿所述承重板的周向伸出。Further, the side plate includes an outer page plate and a load-bearing plate, the outer page plate is integrally formed with the support end, the load-bearing plate is arranged inside the outer page plate and on the upper part of the support end, so The load-bearing plate is provided with protruding steel bars, and the protruding steel bars protrude along the circumferential direction of the load-bearing plate.

进一步,至少所述承重板的上端内侧设有支撑梁,所述顶板包括预制板和现浇层,所述预制板搭接在所述支撑梁上,所述现浇层浇筑在所述预制板上部。如此设置,采用预制和现浇相结合的方式进行拼装,结构整体性好、连接成本较低,防水质量明显提升,防水性能优异,另一方面,每个管节均有多个预制板拼装而成,构件的运输以及现场的吊装难度均降低,施工效率大大提高,施工周期短,相对于现浇模式,混凝土浇捣的量明显减少,减少现场施工的工作量。Further, at least the inner side of the upper end of the load-bearing plate is provided with a support beam, the roof includes a prefabricated slab and a cast-in-place layer, the prefabricated slab is lapped on the support beam, and the cast-in-place layer is cast on the prefabricated slab upper part. With such a setting, the combination of prefabrication and cast-in-place is used for assembly. The structural integrity is good, the connection cost is low, the waterproof quality is significantly improved, and the waterproof performance is excellent. On the other hand, each pipe section is assembled with multiple prefabricated panels. Compared with the cast-in-place mode, the amount of concrete pouring and tamping is significantly reduced, reducing the workload of on-site construction.

进一步,相邻设置的承重板之间形成第一拼接槽,所述现浇层延伸至所述第一拼接槽内,所述伸出钢筋锚固在所述现浇层内,相邻设置的承重板通过所述现浇层连接成整体。如此,相邻设置的承重板通过所述现浇层连接成整体,侧板在各个预制段内是连续的,即管廊的侧板通过现浇层构成整体,侧板之间的拼接缝也被现浇层封堵,防水效果好。Further, a first splicing groove is formed between adjacent bearing plates, the cast-in-place layer extends into the first splicing groove, the protruding steel bars are anchored in the cast-in-place layer, and the adjacent load-bearing plates The plates are connected as a whole through the cast-in-place layer. In this way, the adjacent load-bearing plates are connected into a whole through the cast-in-place layer, and the side plates are continuous in each prefabricated section, that is, the side plates of the pipe gallery are formed as a whole through the cast-in-place layer, and the joints between the side plates It is also blocked by the cast-in-place layer, and the waterproof effect is good.

进一步,所述承重板的中部内侧设有支撑梁。如此设置,可根据需要在承重板的中部的支撑梁上在设置预制板,如此,可构成多仓管廊,施工工艺简单,同时还可以起到传递管廊外页板由基坑传来的压力作用。Further, a support beam is provided on the inner side of the middle part of the bearing plate. In this way, prefabricated slabs can be set on the supporting beams in the middle of the load-bearing slab as required. In this way, a multi-storage pipe gallery can be formed, the construction process is simple, and at the same time, it can also play a role in transmitting the external pages of the pipe gallery from the foundation pit. pressure effect.

进一步,至少在所述承重板的中部的支撑梁设有穿筋孔,所述穿筋孔中穿设有预应力筋。如此设置,在顶板现浇层浇筑前,通过预应力钢筋的张拉和锚固,管节之间拼接更为紧密,拼接缝更小,提高预制管节的连接效果,顶板现浇层浇筑后整体性更好。Further, at least the support beam in the middle of the load-bearing plate is provided with a reinforcement hole, and prestressed tendons are pierced in the reinforcement hole. In this way, before the pouring of the roof cast-in-place layer, the pipe joints are more closely spliced and the joints are smaller through the tensioning and anchoring of the prestressed steel bars before the pouring of the roof cast-in-place layer, which improves the connection effect of the prefabricated pipe joints. Overall better.

进一步,所述底板为现浇底板。如此设置,管廊拼接后,现浇底板以及顶板现浇层的浇筑,将管节之间的拼接缝全部封堵,有效解决了管廊渗水问题。Further, the base plate is a cast-in-place base plate. In this way, after the pipe gallery is spliced, the pouring of the cast-in-place bottom plate and the cast-in-place roof layer will seal all the joints between the pipe joints, effectively solving the problem of water seepage in the pipe gallery.

进一步,所述支承端头呈倒锥形。如此,侧板的安装施工过程中,可先采用吊装机械使得侧板达到待安装位置,然后通过压桩机械固定侧板后在指定位置开始压桩,将支承端头压入地基中,将侧板压入到指定标高;优选,如果土质坚硬、可采用小型挖掘机开配合压桩机工作完成侧板的安装就位。Further, the supporting end is in an inverted tapered shape. In this way, during the installation and construction of the side panels, the hoisting machine can be used to make the side panels reach the position to be installed, and then the side panels can be fixed by the pile pressing machine, and then the piles can be pressed at the designated position to press the supporting end into the foundation, and then press the side panels into the foundation. The slab is pressed into the specified elevation; preferably, if the soil is hard, a small excavator can be used to cooperate with the pile driver to complete the installation of the side slab.

进一步,所述支承端头的底部设有桩尖。如此,有利于压桩机械将支承端头压入地基中,减少操作难度。Further, the bottom of the supporting end is provided with a pile point. In this way, it is beneficial for the pile pressing machine to press the supporting end into the foundation, reducing the difficulty of operation.

进一步,所述预制板设有伸出钢筋,所述预制板与所述外页板形成第二拼接槽,所述伸出钢筋至少伸入至所述第二拼接槽中,所述预制板的伸出钢筋与承重板部的伸出钢筋错位设置,所述现浇层延伸至所述第二拼接槽中。在预制板的吊运落位过程中,保证预制板的伸出钢筋与承重板部的伸出钢筋交错设置,待现浇层浇筑后,不仅有效的封堵的拼接槽,杜绝漏水渗水的可能,同时顶板与侧板的整体性更好。Further, the prefabricated panel is provided with protruding steel bars, and the prefabricated panel and the outer panel form a second splicing groove, and the protruding steel bars at least extend into the second splicing groove, and the prefabricated panels The protruding steel bars and the protruding steel bars of the load-bearing plate are misplaced, and the cast-in-place layer extends into the second splicing groove. During the hoisting and landing process of the prefabricated slab, ensure that the protruding steel bars of the prefabricated slab and the protruding steel bars of the load-bearing slab are arranged alternately. After the cast-in-place layer is poured, not only the splicing groove is effectively blocked, but also the possibility of water leakage and water seepage is eliminated. , At the same time, the integrity of the top plate and the side plate is better.

附图说明Description of drawings

构成本实用新型的一部分的附图用来提供对本实用新型的进一步理解,本实用新型的示意性实施例及其说明用于解释本实用新型,并不构成对本实用新型的不当限定。The accompanying drawings constituting a part of the utility model are used to provide a further understanding of the utility model, and the schematic embodiments of the utility model and their descriptions are used to explain the utility model, and do not constitute improper limitations to the utility model.

图1为本实用新型一种实施方式所涉及的综合管廊未浇筑顶板现浇层时的结构示意图;Fig. 1 is a schematic structural view of the comprehensive pipe gallery involved in an embodiment of the present invention when the roof cast-in-place layer is not poured;

图2分别为本实用新型一种实施方式所涉及的侧板的结构示意图;FIG. 2 is a schematic structural view of side plates involved in an embodiment of the present invention;

图3为本实用新型一种实施方式所涉及的综合管廊施工状态的示意图。Fig. 3 is a schematic diagram of the construction status of the comprehensive utility gallery involved in an embodiment of the present invention.

图中:In the picture:

1底板 2侧板 3预制板 4支承端头1 Bottom plate 2 Side plate 3 Prefabricated plate 4 Support end

5地基 6垫层 7外页板 8承重板5 Foundation 6 Cushion 7 Outer panels 8 Bearing panels

9伸出钢筋 10第一拼接槽 11支撑梁 12穿筋孔9 protruding steel bar 10 first splicing groove 11 supporting beam 12 piercing hole

13预应力筋 14第二拼接槽13 Prestressed tendon 14 Second splicing groove

具体实施方式Detailed ways

下面结合附图对本实用新型进行详细描述,本部分的描述仅是示范性和解释性,不应对本实用新型的保护范围有任何的限制作用。此外,本领域技术人员根据本文件的描述,可以对本文件中实施例中以及不同实施例中的特征进行相应组合。The utility model will be described in detail below in conjunction with the accompanying drawings. The description in this part is only exemplary and explanatory, and should not have any limiting effect on the protection scope of the utility model. In addition, those skilled in the art can make corresponding combinations of features in the embodiments in this document and in different embodiments according to the descriptions in this document.

本实用新型实施例如下,参照图1和图3,一种综合管廊,由多个管节拼接构成,所述管节包括顶板、底板1和侧板2,所述侧板2的底端设有支承端头4,所述底板1设置在所述支承端头4的上部。如此设置,在施工工程中,仅需将支承端头4埋入地基5中,作为临时支撑以及施工完成后的结构面,然后在相对设置的侧板2之间铺设垫层6,再将底板1设置在支承端头4的上部,如此,可减少管廊施工的作业面,施工中不需要放坡开挖基坑,减少了预制综合管廊侧壁外侧土方开挖、回填及压实的工作量,降低施工成本、提高了施工效率,大大减少了对于土地的临时占用和周围环境的扰动,同时,预制综合管廊侧壁能起到临时支撑的作用,降低了施工支撑费用的投入。优选,为保证支承端头4支撑和承载作用,支承端头4的应当厚度大于侧板2主体的厚度。Examples of the utility model are as follows, referring to Fig. 1 and Fig. 3, a comprehensive pipe gallery is composed of a plurality of pipe joints spliced together, the pipe joints include a top plate, a bottom plate 1 and a side plate 2, and the bottom end of the side plate 2 A supporting end 4 is provided, and the bottom plate 1 is arranged on the upper part of the supporting end 4 . In this way, in the construction project, it is only necessary to embed the support end 4 in the foundation 5 as a temporary support and a structural surface after construction, and then lay a cushion 6 between the oppositely arranged side plates 2, and then place the bottom plate 1 is set on the upper part of the supporting end 4, so that the working surface of the pipe gallery construction can be reduced, and the foundation pit does not need to be sloped and excavated during the construction, which reduces the excavation, backfilling and compaction of the outer side wall of the prefabricated comprehensive pipe gallery. The workload reduces the construction cost, improves the construction efficiency, and greatly reduces the temporary occupation of the land and the disturbance of the surrounding environment. At the same time, the side wall of the prefabricated comprehensive pipe gallery can play the role of temporary support, reducing the investment in construction support costs. Preferably, in order to ensure the supporting and bearing functions of the supporting end 4 , the thickness of the supporting end 4 should be greater than the thickness of the main body of the side plate 2 .

上述实施例的基础上,本实用新型另一实施例中,如图2,所述侧板2包括外页板7和承重板8,所述外页板7与支承端头4一体成型,所述承重板8设置在所述外页板7内侧并设置在所述支承端头4的上部,所述承重板8设有伸出钢筋9,所述伸出钢筋9沿所述承重板8的周向伸出。On the basis of the above embodiments, in another embodiment of the present invention, as shown in Figure 2, the side plate 2 includes an outer leaf plate 7 and a bearing plate 8, and the outer leaf plate 7 and the supporting end 4 are integrally formed, so that The load-bearing plate 8 is arranged on the inner side of the outer leaf plate 7 and is arranged on the upper part of the support end 4, and the load-bearing plate 8 is provided with protruding steel bars 9, and the protruding steel bars 9 are arranged along the edge of the load-bearing plate 8. Protrude circumferentially.

上述实施例的基础上,本实用新型另一实施例中,如图1和图3,至少所述承重板8的上端内侧设有支撑梁11,所述顶板包括预制板3和现浇层,所述预制板3搭接在所述支撑梁11上,所述现浇层浇筑在所述预制板3上部。如此设置,采用预制和现浇相结合的方式进行拼装,结构整体性好、连接成本较低,防水质量明显提升,防水性能优异,另一方面,每个管节均有多个预制板3拼装而成,构件的运输以及现场的吊装难度均降低,施工效率大大提高,施工周期短,相对于现浇模式,混凝土浇捣的量明显减少,减少现场施工的工作量。On the basis of the above-mentioned embodiments, in another embodiment of the utility model, as shown in Fig. 1 and Fig. 3, at least the inner side of the upper end of the bearing plate 8 is provided with a support beam 11, and the top plate includes a prefabricated plate 3 and a cast-in-place layer, The prefabricated slab 3 is lapped on the support beam 11 , and the cast-in-place layer is poured on the upper part of the prefabricated slab 3 . With such a setting, the combination of prefabrication and cast-in-place is used for assembly, the structural integrity is good, the connection cost is low, the waterproof quality is significantly improved, and the waterproof performance is excellent. On the other hand, each pipe section has multiple prefabricated panels 3 assembled As a result, the difficulty of component transportation and on-site hoisting is reduced, the construction efficiency is greatly improved, and the construction period is short. Compared with the cast-in-place mode, the amount of concrete pouring and tamping is significantly reduced, reducing the workload of on-site construction.

上述实施例的基础上,本实用新型另一实施例中,如图1,相邻设置的承重板8之间形成第一拼接槽10,所述现浇层延伸至所述第一拼接槽10内,所述伸出钢筋9锚固在所述现浇层内,相邻设置的承重板8通过所述现浇层连接成整体。如此,相邻设置的承重板8通过所述现浇层连接成整体,侧板2在各个预制段内是连续的,即管廊的侧板2通过现浇层构成整体,侧板2之间的拼接缝也被现浇层封堵,防水效果好。On the basis of the above-mentioned embodiments, in another embodiment of the present invention, as shown in Figure 1, a first splicing groove 10 is formed between adjacent bearing plates 8, and the cast-in-place layer extends to the first splicing groove 10 Inside, the protruding steel bars 9 are anchored in the cast-in-place layer, and the adjacent bearing plates 8 are connected as a whole through the cast-in-place layer. In this way, the adjacent load-bearing plates 8 are connected into a whole through the cast-in-place layer, and the side plates 2 are continuous in each prefabricated section, that is, the side plates 2 of the pipe gallery are formed as a whole through the cast-in-place layer, and the side plates 2 The splicing seams are also blocked by the cast-in-place layer, and the waterproof effect is good.

上述实施例的基础上,本实用新型另一实施例中,如图1和图2,所述承重板8的中部内侧设有支撑梁11。如此设置,可根据需要在承重板8的中部的支撑梁11上在设置预制板3,如此,可构成多仓管廊,施工工艺简单,同时还可以起到传递管廊外页板7由基坑传来的压力作用。On the basis of the above-mentioned embodiments, in another embodiment of the present invention, as shown in Fig. 1 and Fig. 2 , a supporting beam 11 is provided on the inner side of the middle part of the bearing plate 8 . In this way, the prefabricated slab 3 can be set on the support beam 11 in the middle of the load-bearing slab 8 according to the needs. In this way, a multi-storey pipe gallery can be formed, the construction process is simple, and at the same time, it can also play the role of transferring the outer slab 7 of the pipe gallery from the foundation. The pressure effect from the pit.

上述实施例的基础上,本实用新型另一实施例中,如图1~3,至少在所述承重板8的中部的支撑梁11设有穿筋孔12,所述穿筋孔12中穿设有预应力筋13。如此设置,在顶板现浇层浇筑前,通过预应力钢筋的张拉和锚固,管节之间拼接更为紧密,拼接缝更小,提高预制管节的连接效果,顶板现浇层浇筑后整体性更好。On the basis of the above embodiments, in another embodiment of the present invention, as shown in Figures 1 to 3, at least the support beam 11 in the middle of the bearing plate 8 is provided with a rib hole 12, and the rib hole 12 is pierced Prestressed ribs 13 are provided. In this way, before the pouring of the roof cast-in-place layer, through the tensioning and anchoring of the prestressed steel bars, the joints between the pipe joints will be tighter and the splicing joints will be smaller, which will improve the connection effect of the prefabricated pipe joints. After the roof cast-in-place layer is poured Overall better.

上述实施例的基础上,本实用新型另一实施例中,如图1,所述底板1为现浇底板1。如此设置,管廊拼接后,现浇底板1以及顶板现浇层的浇筑,将管节之间的拼接缝全部封堵,有效解决了管廊渗水问题。On the basis of the above-mentioned embodiments, in another embodiment of the present invention, as shown in FIG. 1 , the bottom plate 1 is a cast-in-place bottom plate 1 . In this way, after the pipe gallery is spliced, the pouring of the cast-in-place bottom plate 1 and the top plate cast-in-place layer will seal all the joints between the pipe joints, effectively solving the problem of water seepage in the pipe gallery.

上述实施例的基础上,本实用新型另一实施例中,如图1,所述支承端头4呈倒锥形。如此,侧板2的安装施工过程中,可先采用吊装机械使得侧板2达到待安装位置,然后通过压桩机械固定侧板2后在指定位置开始压桩,将支承端头4压入地基5中,将侧板2压入到指定标高;优选,如果土质坚硬、可采用小型挖掘机开配合压桩机工作完成侧板2的安装就位。On the basis of the above-mentioned embodiments, in another embodiment of the present invention, as shown in FIG. 1 , the support end 4 is in the shape of an inverted cone. In this way, during the installation and construction process of the side plate 2, a hoisting machine can be used to make the side plate 2 reach the position to be installed, and then the side plate 2 is fixed by the pile pressing machine, and then the piles are started at the designated position to press the supporting end 4 into the foundation In step 5, the side plate 2 is pressed into the specified elevation; preferably, if the soil is hard, a small excavator can be used to cooperate with a pile driver to complete the installation of the side plate 2 in place.

上述实施例的基础上,本实用新型另一实施例中,所述支承端头4的底部设有桩尖。如此,有利于压桩机械将支承端头4压入地基5中,减少操作难度。On the basis of the above embodiments, in another embodiment of the present utility model, the bottom of the supporting end 4 is provided with a pile tip. In this way, it is beneficial for the pile pressing machine to press the support end 4 into the foundation 5, reducing the difficulty of operation.

上述实施例的基础上,本实用新型另一实施例中,如图1,所述预制板3设有伸出钢筋9,所述预制板3与所述外页板7形成第二拼接槽14,所述伸出钢筋9至少伸入至所述第二拼接槽14中,所述预制板3的伸出钢筋9与承重板8部的伸出钢筋9错位设置,所述现浇层延伸至所述第二拼接槽14中。在预制板3的吊运落位过程中,保证预制板3的伸出钢筋9与承重板8部的伸出钢筋9交错设置,待现浇层浇筑后,不仅有效的封堵的拼接槽,杜绝漏水渗水的可能,同时顶板与侧板2的整体性更好。On the basis of the above embodiments, in another embodiment of the present invention, as shown in Figure 1, the prefabricated panel 3 is provided with protruding steel bars 9, and the prefabricated panel 3 and the outer leaf panel 7 form a second splicing groove 14 , the protruding steel bars 9 at least extend into the second splicing groove 14, the protruding steel bars 9 of the prefabricated slab 3 and the protruding steel bars 9 of the bearing plate 8 are misplaced, and the cast-in-place layer extends to In the second splicing groove 14 . During the hoisting and placing process of the prefabricated slab 3, it is ensured that the protruding steel bars 9 of the prefabricated slab 3 and the protruding steel bars 9 of the bearing plate 8 are arranged alternately. After the cast-in-place layer is poured, not only the splicing grooves are effectively blocked, The possibility of water leakage and water seepage is eliminated, and the integrity of the top plate and the side plate 2 is better.

以上所述仅是本实用新型的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本实用新型原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也应视为本实用新型的保护范围。The above is only a preferred embodiment of the utility model, it should be pointed out that for those of ordinary skill in the art, without departing from the principle of the utility model, some improvements and modifications can also be made, these improvements and Retouching should also be regarded as the scope of protection of the present utility model.

Claims (10)

1. a kind of pipe gallery is spliced to form by multiple tube couplings, the tube coupling includes top plate, bottom plate and side plate, which is characterized in that The bottom end of the side plate is equipped with bearing end, and the bottom plate is arranged on the top of the bearing end.
2. pipe gallery according to claim 1, which is characterized in that the side plate includes outer page board and bearing plate, described Outer page board is first body formed with supported end, and the bearing plate is arranged on the inside of the outer page board and is arranged on the bearing end Top, the bearing plate, which is equipped with, stretches out reinforcing bar, and the reinforcing bar that stretches out is stretched out along the circumferential direction of the bearing plate.
3. pipe gallery according to claim 2, which is characterized in that support is equipped on the inside of the upper end of at least described bearing plate Beam, the top plate include prefabricated board and in-situ layer, and the prefabricated board is overlapped in the supporting beam, and the in-situ layer is cast in institute State prefabricated board top.
4. pipe gallery according to claim 3, which is characterized in that the first splicing is formed between the bearing plate being disposed adjacent Slot, the in-situ layer are extended in the first splicing slot, and the stretching Bar Anchorage is disposed adjacent in the in-situ layer Bearing plate is connected integral by the in-situ layer.
5. according to the pipe gallery described in claim 2~4 any one, which is characterized in that the inside middle portion of the bearing plate Equipped with supporting beam.
6. pipe gallery according to claim 5, which is characterized in that the supporting beam at least at the middle part of the bearing plate is set Muscle hole is worn, described wear in muscle hole is equipped with presstressed reinforcing steel.
7. pipe gallery according to claim 3 or 4, which is characterized in that the bottom plate is cast-in-place bottom plate.
8. pipe gallery according to claim 7, which is characterized in that the bearing end is in back taper.
9. pipe gallery according to claim 7, which is characterized in that the bottom of the bearing end is equipped with pile top.
10. pipe gallery according to claim 8, which is characterized in that the prefabricated board, which is equipped with, stretches out reinforcing bar, described prefabricated Plate forms the second splicing slot with the outer page board, and the stretching reinforcing bar is at least stretched in the second splicing slot, described prefabricated The stretching reinforcing bar and the stretching reinforcing bar of load-bearing plate portion of plate shift to install, and the in-situ layer is extended in the second splicing slot.
CN201721105188.1U 2017-08-30 2017-08-30 A kind of pipe gallery Expired - Fee Related CN207553135U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721105188.1U CN207553135U (en) 2017-08-30 2017-08-30 A kind of pipe gallery

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721105188.1U CN207553135U (en) 2017-08-30 2017-08-30 A kind of pipe gallery

Publications (1)

Publication Number Publication Date
CN207553135U true CN207553135U (en) 2018-06-29

Family

ID=62675850

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721105188.1U Expired - Fee Related CN207553135U (en) 2017-08-30 2017-08-30 A kind of pipe gallery

Country Status (1)

Country Link
CN (1) CN207553135U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021088279A1 (en) * 2019-11-08 2021-05-14 南京联众工程技术有限公司 Underground pipeline having two-in-one support pile and pipeline wall and construction method
CN113026471A (en) * 2021-03-26 2021-06-25 广州市第二市政工程有限公司 Construction method of assembled prestressed supporting system
CN113373975A (en) * 2021-07-13 2021-09-10 荣华(青岛)建设科技有限公司 Assembled rectangle utility tunnel of underground construction and piping lane prefab
CN115652938A (en) * 2022-11-11 2023-01-31 广西建工集团冶金建设有限公司 Construction method of drainage pipe and assembled drainage pipe joint thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021088279A1 (en) * 2019-11-08 2021-05-14 南京联众工程技术有限公司 Underground pipeline having two-in-one support pile and pipeline wall and construction method
CN113026471A (en) * 2021-03-26 2021-06-25 广州市第二市政工程有限公司 Construction method of assembled prestressed supporting system
CN113373975A (en) * 2021-07-13 2021-09-10 荣华(青岛)建设科技有限公司 Assembled rectangle utility tunnel of underground construction and piping lane prefab
CN115652938A (en) * 2022-11-11 2023-01-31 广西建工集团冶金建设有限公司 Construction method of drainage pipe and assembled drainage pipe joint thereof

Similar Documents

Publication Publication Date Title
CN101914925B (en) Basement by using optimized composite prefabricated arch wall as external wall
CN102434717B (en) Construction method of joist steel pipe-jacking work pit
CN101418569B (en) Optimized composite arch wall with combination of prefabricated arch, support and main structure
CN206189455U (en) a corridor
CN104805866A (en) Prefabricated comprehensive pipe gallery and construction method
CN110004991B (en) Anti-floating system and construction method of underground structure based on convex wing foot plate
CN207553135U (en) A kind of pipe gallery
CN103912000A (en) Reusable composite-material soil nailing wall supporting face plate and construction method thereof
CN108396778A (en) A kind of construction method in precast assembly tunnel
CN105672450A (en) Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure
CN212452715U (en) Burst prefabricated construction of dark heavy open caisson
CN204753627U (en) Prefabricated comprehensive piping lane
CN104988915A (en) Prefabrication and installation method of detachable steel protection tube device and underwater connection beam
CN113502835A (en) Wet cellular assembled gridwork roof beam slope protection structure of connecting
CN102286982A (en) Deep foundation pit precast building enclosure for constructing in low environment
CN209873873U (en) Prefabricated assembled power pipeline working well
CN106978814A (en) A kind of Fabricated Structure for Support of Excavation
CN206189454U (en) Piping lane
CN109972657B (en) Pile culvert integrally assembled steel-reinforced concrete integrated pipeline corridor
CN113308954B (en) Construction method of anchor rod foam concrete widening roadbed
CN109137984A (en) Assembled integral mixes prefabricated pipe gallery
CN114482070B (en) Construction tool and construction method for temporary high-speed railway line deep foundation pit occluding pile
CN201883453U (en) Combined pipe jacking working well
CN114960675B (en) A combined support system for pipe gallery foundation pit support
CN206189458U (en) Multi -deck formula piping lane

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 5 / F, office building 2, Zhongmin zhuyou Co., Ltd., No. 10, Zhongshi Road, shaping street, Kaifu District, Changsha City, Hunan Province, 410000

Patentee after: Zhuyou Zhizao Technology Investment Co.,Ltd.

Address before: 410205 room 3005, complex building, Changsha Jin Xia bonded logistics center, 30 Xingang Road, Kaifu District, Changsha, Hunan.

Patentee before: Zhongmin Zhuyou Technology Investment Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180629