WO2021000444A1 - 近接未封闭建筑物的重型设备吊装的地基加固结构及方法 - Google Patents
近接未封闭建筑物的重型设备吊装的地基加固结构及方法 Download PDFInfo
- Publication number
- WO2021000444A1 WO2021000444A1 PCT/CN2019/110664 CN2019110664W WO2021000444A1 WO 2021000444 A1 WO2021000444 A1 WO 2021000444A1 CN 2019110664 W CN2019110664 W CN 2019110664W WO 2021000444 A1 WO2021000444 A1 WO 2021000444A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- steel
- steel pipe
- lattice column
- steel sheet
- rows
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/04—Prefabricated parts, e.g. composite sheet piles made of steel
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/04—Prefabricated parts, e.g. composite sheet piles made of steel
- E02D5/08—Locking forms; Edge joints; Pile crossings; Branch pieces
Definitions
- the invention relates to the technical field of equipment hoisting, in particular to a foundation reinforcement structure and method for heavy equipment hoisting close to unclosed buildings.
- the heavy-duty equipment hoisting close to the main structure of the building is mostly carried out after the construction of the main structure of the building is completed.
- the main structure of the building is affected by various factors before the overall closed structure is formed, such as subway station construction.
- the shield machine has a large mass, and the equipment needs to be hoisted from the receiving end of the shield.
- the deep foundation pit excavated by the slope has not been backfilled, and the surrounding sides of the unclosed building are all deep foundations that have not been backfilled.
- the pit that is, there is no reinforced foundation around the main body of the building, and the lifting equipment is directly installed through the backfill.
- the lifting equipment is During the hoisting process, the backfilling of the soil will generate a certain amount of lateral pressure on the uncompleted building. The lateral pressure will adversely affect the unclosed building, may cause the building to crack, and even affect the uncompleted building body The service life of the structure will cause catastrophic consequences in severe cases.
- the present invention provides a foundation reinforcement structure for heavy equipment hoisting close to unclosed buildings.
- Temporary retaining walls can be set around the backfill soil to improve the stability of the backfill soil and pass steel pipe columns.
- a force-transmitting component is formed to transfer the stress of the crane on the backfilled soil to the underground rock layer to reduce the adverse effect of the lateral pressure of the formation caused by the hoisting load on the main structure of the unclosed station.
- the concrete plan of the foundation reinforcement structure for heavy equipment hoisting close to unenclosed buildings is as follows:
- the foundation reinforcement structure for heavy equipment hoisting close to unenclosed buildings including:
- the vertical steel sheet piles are divided into two rows, and the two rows of steel sheet piles are respectively set on the left and right sides of the side wall of the unclosed building in the foundation pit;
- the first connecting piece, the two rows of steel sheet piles are connected by the first connecting piece, and the first connecting piece is layered and provided with several layers;
- steel pipe lattice column structures are arranged between the two rows of steel sheet piles, and the steel pipe lattice column structures are also vertically arranged for vertical force transmission;
- the backfill soil is layered between two rows of steel sheet piles, and the height of the backfill soil is lower than the top of the steel pipe lattice column structure.
- the above-mentioned foundation reinforcement structure constitutes a reliable reinforced foundation as a whole.
- the first connecting piece is reliably connected, so that a temporary retaining wall is formed in the direction of the longitudinal foundation pit and the side wall of the building. , which effectively improves the stress stability of the backfilled soil.
- the steel lattice column can be used as a force transmission member to transfer the stress of the backfilled soil by the lifting equipment on the top of the backfill, such as a crane. To the rock layer below the foundation pit, thereby effectively avoiding the lateral pressure generated by the lifting equipment on the unclosed building structure during the hoisting process.
- the bottoms of the steel sheet piles in each row are inserted into the soil at the bottom of the foundation pit, which can effectively facilitate the installation of the first connector and at the same time help to improve the force stability of the steel sheet piles.
- the steel sheet pile includes a plurality of Lassen plates that are fastened with each other.
- the cross-section of the Larsen plates is U-shaped, and the fastened Lassen plates are beneficial to improve the bending rigidity of the steel sheet pile.
- the first connecting member is a steel wire rope
- the two ends of the steel wire rope are respectively connected with the first I-beam arranged outside the steel sheet pile, and the number of layers of the steel wire rope is the same as that of the first I-beam
- the Larsen plate is provided with openings for the wire rope to pass through.
- the first I-beam is arranged to facilitate the fixing of both ends of the wire rope and improve the stability of the Larsen plate.
- the board is vertical.
- each of the steel tube lattice column structure includes at least one steel tube, and the steel tube is filled with concrete to improve the strength of the steel tube lattice column.
- the bottom of the steel tube lattice column structure is provided with a first steel plate, and the first steel plate Supported by the bottom surface of the foundation pit, a second steel plate is arranged on the top of the steel pipe lattice column structure, and two adjacent steel pipes in each steel pipe lattice column structure are connected by a second connector.
- the second connecting piece is a second I-beam, and multiple rows of second connecting pieces are arranged between two adjacent steel pipes.
- the second I-beam is arranged horizontally and perpendicular to the installation direction of the steel pipe.
- the second steel plate is welded and connected to the steel pipe.
- the first steel plate is welded to the bottom end of the steel pipe, and the sizes of the first steel plate and the second steel plate are larger than the corresponding steel pipes.
- the size of the steel pipe in the lattice column structure, and the second steel plate is reserved for concrete pouring holes.
- the steel pipe lattice column structure at each location includes three steel pipes.
- the three steel pipes form three points of an equilateral triangle, which is beneficial to improve the stability of the steel pipe lattice column structure.
- the grouting pipe is a sleeve valve pipe whose length meets the requirements of grouting.
- the center position of the three steel pipes is consistent with the center position of the outrigger of a crane such as a car.
- the steel pipe lattice column structure includes at least four, and the four steel pipe lattice column structures form four rectangular points to be arranged, and the center positions of the four steel pipe lattice column structures are consistent with the center positions of the fully extended legs of the automobile crane , Can effectively transfer the stress of the car crane foot to the foundation downward, and distribute the lateral force generated by the lifting equipment to the rock layer at the bottom of the foundation pit.
- a concrete reinforcement layer is provided on the top of the backfilled soil body and the steel tube lattice column structure.
- the concrete reinforcement layer includes a steel mesh.
- the middle and lower steel mesh of the steel mesh is attached to the second steel plate to facilitate the arrangement of the concrete reinforcement layer and
- the steel pipe lattice column structure is connected as a whole, and a square box supporting the legs of the automobile crane is placed on the surface of the concrete reinforcement layer corresponding to the second steel plate.
- the present invention also provides a reinforcement method for a foundation reinforcement structure for heavy equipment hoisting close to an unenclosed building (partially closed at the top, partly closed at the top), including the following:
- the two rows of steel sheet piles are connected by arranging the first connecting pieces, and the first connecting pieces are arranged in layers. During the layered arrangement of the first connecting pieces, soil is gradually backfilled between the two rows of steel sheet piles;
- a second steel plate is installed on the top of the steel pipe, and the elevation after the soil is backfilled and rolled to the specified degree of compaction is the same as the second steel plate.
- the above-mentioned reinforcement method for the foundation reinforcement structure for heavy equipment hoisting close to the unenclosed building can set a stable foundation reinforcement structure, which not only ensures the safety of the unenclosed building, but also avoids the lifting equipment site area that may be caused by the foundation pit. Lifting safety risk caused by backfill quality.
- the present invention can fully improve the stability of the foundation reinforcement structure through the overall foundation reinforcement structure, effectively avoid the lifting safety risk that may be caused by the backfill quality of the foundation pit in the lifting equipment station area, and the force transmission of the foundation reinforcement structure
- the method can avoid the lateral pressure of the lifting load on the building and ensure the safety of the unclosed building.
- the present invention not only constitutes the lateral retaining wall of the backfilled soil, but also improves the strength and stability of the backfilled soil in the transverse direction.
- the present invention can transmit the lifting load to the supporting rock layer at the bottom of the foundation pit as a vertical force transmission structure, thereby avoiding the lateral pressure of the lifting load on the building and improving the foundation structure Vertical stability.
- Fig. 1 is a schematic cross-sectional view of the current status of the station and foundation pit in the embodiment of the present invention
- Figure 2 is a schematic cross-sectional schematic diagram of foundation treatment of a crane in an embodiment of the present invention
- Fig. 3 is a schematic diagram of the horizontal plane of foundation treatment of the crane in the embodiment of the present invention.
- Figure 4 is a schematic cross-sectional view of a retaining wall in an embodiment of the present invention.
- Figure 5 is a horizontal schematic diagram of the retaining wall in the embodiment of the present invention.
- Figure 6 is a schematic plan view of the steel pipe lattice column structure in the embodiment of the present invention.
- Figure 7 is a schematic side view of the steel pipe lattice column structure in the embodiment of the present invention.
- Figure 8 is a top view of the hoist in the embodiment of the present invention.
- the present invention proposes a foundation reinforcement structure for lifting heavy equipment close to an unenclosed building.
- the following is a further development of the present invention with reference to the drawings. Elaboration.
- the maximum mass of a shield machine for a rail transit project is 130t for the front shield and 120t for the middle shield, which needs to be hoisted.
- the main structure of the receiving end of the shield receiving station is only It is about 30m completed without forming a closed overall structure.
- the depth of the foundation pit is 20m.
- the station foundation pit is a three-level grading excavation.
- the second-level grading platform is 1m higher than the top of the second floor of the station, and the height of the first floor of the station is 8.5m.
- the design cover thickness of the station roof is 4m, and the surrounding side of the station is a foundation pit. It is impossible to hoist the shield machine components according to the conventional hoisting method.
- a 350t crawler crane 5 is installed on the top of the station.
- the crawler crane 5 hoists the shield equipment to the temporary storage platform 4 on the side of the crawler crane, and then is installed on the side of the station.
- a crane such as a 500t truck crane 3 is used for hoisting.
- the truck crane station requires a certain level of space, otherwise the truck cannot get in and out and hoist operations in the foundation pit. Therefore, this embodiment proposes foundation reinforcement for heavy equipment hoisting close to unenclosed buildings Structure:
- the structure includes vertical steel sheet piles 7, which are divided into two rows.
- the two rows of steel sheet piles 7 are respectively arranged on the left and right sides of the side walls of the unclosed station end in the foundation pit; the first connecting piece, two rows of steel sheet piles 7 They are connected by a first connecting piece, and the first connecting piece is layered and provided with several layers; a number of steel pipe lattice column structures arranged between two rows of steel sheet piles 7 are also vertically arranged to Perform vertical force transmission; backfill soil 2 is layered between two rows of steel sheet piles 7, and the height of backfill soil 2 is lower than the top of the steel pipe lattice column structure.
- each row of steel sheet piles 7 is inserted into the soil at the bottom of the foundation pit, and sand bags are placed at a position not less than 2m near the side wall of the main structure of the station 6 to avoid the disadvantages of the steel sheet pile installation on the station structure Influence, the earthwork is backfilled between the steel sheet pile and the side wall of the main structure of the station.
- the side wall of the main body of the station where the earthwork is backfilled shall be waterproofed according to the requirements of the station structure, and the earthwork shall be backfilled after laying foam bricks 11;
- the steel sheet pile 7 includes a number of interlocking Larsen
- the Larsen plate has a U-shaped cross-section, and the interlocking Larsen plates are beneficial to improve the bending rigidity of the steel sheet pile 7.
- the first connecting member is divided into multiple layers and multiple rows to connect the Larsen plates on both sides.
- the counter-pressure earthwork 12 is arranged on one side or the outer side of the steel sheet pile on both sides, which is beneficial to improve the stability of the steel sheet pile.
- the first connecting member is a steel wire rope 10. As shown in Figs. 4 and 5, both ends of the steel wire rope 10 are respectively connected to the first I-beam 13 arranged on the outside of the steel sheet pile 7. The number of layers of the steel 13 is the same.
- the Larsen plate is provided with openings for the wire rope to pass through.
- the arrangement of the first I-beam 13 facilitates the fixing of both ends of the steel wire 10.
- the first I-beam is arranged horizontally and perpendicularly to the wire rope. For the forest board, both ends of the steel wire rope 10 are fixed by rope clamps.
- one end of the steel wire rope 10 and the first I-beam 13 are connected and fixed by a rope clamp, and the other end of the steel wire rope is passed around the first I-beam 13 and then tightened with a rope tensioner. Then fix it with a rope clamp.
- the steel pipe lattice column structure at each location includes at least one steel pipe 8, and the steel pipe 8 is filled with concrete to improve the strength of the steel pipe lattice column.
- the steel pipe lattice column structure is provided with a first steel plate 16 at the bottom.
- the first steel plate 16 is supported by the bottom surface of the foundation pit, a second steel plate 17 is arranged on the top of the steel pipe lattice column structure, and two adjacent steel pipes 8 in each steel pipe lattice column structure are connected by a second connector.
- the second connecting piece is a second I-beam 15, and multiple rows of second connecting pieces are arranged between two adjacent steel pipes.
- the second I-beam 15 is arranged horizontally and perpendicular to the installation direction of the steel pipe 8.
- a concrete reinforcement layer 1 is provided on the top of the steel tubular lattice column structure and the backfilled soil.
- the concrete reinforcement layer 1 forms an organic unity with the second steel plate 17 and the steel tubular lattice column structure. It further improves the strength of the foundation reinforcement structure, and plays the role of transferring the lifting load to the bottom of the foundation pit.
- the first steel plate 16 is a 1000 ⁇ 1000 ⁇ 20mm thick steel plate
- the second steel plate 17 is a 1000 ⁇ 1000 ⁇ 20mm thick steel plate
- the second steel plate 17 has a ⁇ 200mm concrete pouring hole reserved in the center
- the height of the steel pipe is consistent with the height of the backfilled soil.
- the upper part of the reinforcement layer is provided with a square box 18 at the corresponding position of the lattice steel pipe column to facilitate the even transmission of the lifting load.
- 3 steel pipes 8 are reliably welded with 20 I-beam to form a steel pipe lattice column; there are no less than 4 ⁇ 50 sleeve valve grouting pipes embedded in the 8 steel pipes, and the concrete reinforcement layer is poured into the steel pipe 8 through the pouring hole After the strength of the concrete and the concrete reinforcement layer reaches 50% or more, the sleeve valve pipe static pressure grouting is carried out to further improve the compactness of the soil between the steel pipes.
- each steel pipe lattice column structure includes three steel pipes 8. As shown in Figures 6 and 7, the three steel pipes 8 form three points of an equilateral triangle. The three steel pipes 8 are arranged in an equilateral triangle. 1.5m.
- the steel pipe lattice column structure includes at least four places, and the four steel pipe lattice column structures form four rectangular points to be arranged, so as to be consistent with the center position of the four outriggers of lifting equipment such as car cranes, which can effectively lift the car
- the supporting feet transfer the stress of the foundation downwards, and transfer the lifting load generated by the lifting equipment downwards to the bearing layer at the bottom of the foundation pit.
- the above-mentioned foundation reinforcement structure constitutes a reinforced foundation as a whole with stable strength.
- the first connecting piece Through the installation of two rows of steel sheet piles, they are reliably connected by the first connecting piece, so that two temporary retaining walls are installed in the longitudinal direction of the foundation pit.
- the retaining wall, the side wall of the building, and the slope of the foundation pit constitute a closed space.
- the soil is backfilled in this space, which effectively improves the stability of the backfilled soil.
- the arrangement of the steel pipe lattice column can be used as a force transmission member to
- the stress of the lifting equipment on the top of the backfill, such as a crane, on the backfill is transmitted to the rock layer under the foundation pit through the steel pipe lattice column, thus effectively avoiding the lateral pressure of the lifting equipment on the building structure during the hoisting process .
- the present invention also provides a reinforcement method for a foundation reinforcement structure for heavy equipment hoisting close to an unenclosed building, including the following contents:
- the anti-pressure earthwork 12 shall be properly backfilled outside the steel sheet pile to improve the stability of the soil outside the steel sheet pile.
- the "back pressure earthwork 12" area which is the north side area of the steel sheet pile construction site, is backfilled with part of the soil to further increase the force of the steel sheet pile stability.
- the inner side of the steel pipe lattice column is backfilled in layers, compacted and tested according to the design requirements. After the first layer of backfilled soil meets the requirements, the steel sheet piles are placed outside according to the design requirements.
- the first I-beam and the first I-beam on both sides are connected with a ⁇ 20 steel wire rope. Use a buckle to fix the first I-beam on one end to the steel wire rope. After the other end of the steel wire rope is worn, use a rope tightener to tighten the wire rope before using the card. Buckle fixed.
- step 8 the soil is backfilled, rolled, and the steel wire rope 10 is placed according to the design elevation.
- the height of the backfilled soil body 2 can be 4m, and the compaction degree of the soil body shall be checked again after the backfilling is completed.
- soil compaction it is necessary to prevent the steel pipe lattice column from being hit, and at the same time monitor the displacement of the sandbags at 6 locations close to the main structure of the station.
- each steel pipe 8 of the steel pipe lattice column is welded with a second steel plate of 1000 ⁇ 1000 ⁇ 20mm, and a ⁇ 200mm concrete pouring hole is reserved in the center of the steel plate.
- the second steel plate is the same height as the backfilled soil;
- the area of the station is to tie the steel bars above the backfilled soil.
- the steel bar on the upper part of the steel tubular lattice column is located on the upper part of the second steel plate.
- the reserved sleeve valve pipe should be protected from damage during the steel bar binding; the concrete reinforcement layer 1 shall be constructed after the steel bars are tied outside. At the same time, pour concrete into the steel tube 8 and ensure good vibrating.
- the concrete reinforcement layer 1 and the steel tube lattice column form an integral force transmission structure, so that the lifting load of the 500t truck crane passes through the crane legs, square boxes and concrete reinforcement layer , The steel pipe lattice column is transmitted to the mudstone bearing layer under the foundation pit.
- the shield equipment hoisting construction begins.
- the 500t truck crane enters the site, installs counterweights, inspects spreaders and locks according to the site requirements, completes the acceptance work, and hoists the corresponding equipment through the truck crane.
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Civil Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Composite Materials (AREA)
- Soil Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- Agronomy & Crop Science (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
Claims (10)
- 近接未封闭建筑物的重型设备吊装的地基加固结构,其特征在于,包括:竖向设置的钢板桩,分为两排,两排钢板桩分别设于基坑内未封闭建筑物的左右两侧;第一连接件,两排钢板桩之间通过第一连接件进行连接,且第一连接件分层并设有若干层;设于两排钢板桩之间的若干钢管格构柱结构,钢管格构柱结构同样竖向设置以进行竖向传力;回填土体,分层填设于两排钢板桩之间,回填土体的高度低于钢管格构柱结构的顶部设置。
- 根据权利要求1所述的近接未封闭建筑物的重型设备吊装的地基加固结构,其特征在于,每一排的所述钢板桩底部插入基坑底部土体内。
- 根据权利要求1所述的近接未封闭建筑物的重型设备吊装的地基加固结构,其特征在于,所述钢板桩包括若干相互扣合的拉森板,拉森板断面为U型。
- 根据权利要求1所述的近接未封闭建筑物的重型设备吊装的地基加固结构,其特征在于,所述第一连接件为钢丝绳,钢丝绳的两端分别与设于所述钢板桩外侧的第一工字钢进行连接。
- 根据权利要求1所述的近接未封闭建筑物的重型设备吊装的地基加固结构,其特征在于,每一处的所述钢管格构柱结构均包括至少一根钢管,钢管内填充有混凝土,钢管格构柱结构底部设置第一钢板,钢管格构柱结构顶部设置第二钢板,且每一处钢管格构柱结构中相邻的两根钢管通过第二连接件连接。
- 根据权利要求5所述的近接未封闭建筑物的重型设备吊装的地基加固结构,其特征在于,第二连接件为第二工字钢,相邻的两根钢管之间设有多排第二连接件;所述第二钢板与钢管焊接连接,且第二钢板预留有混凝土浇筑孔。
- 根据权利要求1所述的近接未封闭建筑物的重型设备吊装的地基加固结构,其特征在于,在所述回填土体与所述钢管格构柱结构的顶部设置混凝土加固层。
- 根据权利要求5所述的近接未封闭建筑物的重型设备吊装的地基加固结构,其特征在于,每一处的所述钢管格构柱结构均包括三根钢管,三根钢管构成等边三角形的三个点进行设置,钢管间设有注浆管。
- 根据权利要求5所述的近接未封闭建筑物的重型设备吊装的地基加固结构,其特征在于,所述钢管格构柱结构包括至少四处,四处钢管格构柱结构构成矩形的四个点进行设置,四处钢管格构柱结构的中心位置与吊机支腿全伸出的中心位置一致。
- 根据权利要求1-9中任一项所述的近接未封闭建筑物的重型设备吊装的地基加固结构的加固方法,其特征在于,包括如下内容:在基坑底面设置第一钢板,并竖向设置钢管格构柱结构的钢管,相邻的钢管格构柱结构间隔按设定距离设置;在基坑内未封闭建筑物侧壁的两侧各设置一排钢板桩;两排钢板桩之间通过设置第一连接件进行连接,第一连接件分层设置,在第一连接件分层设置的过程中,逐渐在两排钢板桩之间回填土体;土体回填至钢管顶部时,在钢管顶部设置第二钢板,在回填土体上部与第二钢板顶部布设钢筋浇筑混凝土板,同时向钢管内浇筑混凝土。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
AU2019452705A AU2019452705B2 (en) | 2019-07-01 | 2019-10-11 | Foundation reinforcement structure and method for hoisting heavy equipment close to unclosed building |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910584848.6 | 2019-07-01 | ||
CN201910584848.6A CN110306524B (zh) | 2019-07-01 | 2019-07-01 | 近接未封闭建筑物的重型设备吊装的地基加固结构及方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2021000444A1 true WO2021000444A1 (zh) | 2021-01-07 |
Family
ID=68078663
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/CN2019/110664 WO2021000444A1 (zh) | 2019-07-01 | 2019-10-11 | 近接未封闭建筑物的重型设备吊装的地基加固结构及方法 |
Country Status (3)
Country | Link |
---|---|
CN (1) | CN110306524B (zh) |
AU (1) | AU2019452705B2 (zh) |
WO (1) | WO2021000444A1 (zh) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113202107A (zh) * | 2021-05-18 | 2021-08-03 | 青海送变电工程有限公司 | 一种全地形深基坑开挖智能装置 |
CN113882348A (zh) * | 2021-09-01 | 2022-01-04 | 武汉市政工程设计研究院有限责任公司 | 一种深厚软土深基坑软弱土体预加固方法 |
CN113931228A (zh) * | 2021-10-21 | 2022-01-14 | 中天建设集团有限公司 | 一种用于地下室施工的材料平台施工方法 |
CN113982035A (zh) * | 2021-10-25 | 2022-01-28 | 中国建筑一局(集团)有限公司 | 一种逆作法施工中梁柱转换结构及其施工方法 |
CN115217114A (zh) * | 2022-06-24 | 2022-10-21 | 深圳市工勘岩土集团有限公司 | 基坑抢险反压平台施工方法 |
CN115262584A (zh) * | 2022-09-07 | 2022-11-01 | 中国建筑第八工程局有限公司 | 一种用于地铁深基坑分仓提前围闭的施工方法 |
CN115749346A (zh) * | 2022-11-04 | 2023-03-07 | 中建八局第二建设有限公司 | 车库顶板荷载分散施工方法 |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110306524B (zh) * | 2019-07-01 | 2020-12-18 | 济南轨道交通集团有限公司 | 近接未封闭建筑物的重型设备吊装的地基加固结构及方法 |
CN115324077A (zh) * | 2022-10-13 | 2022-11-11 | 山东飞鸿建设集团有限公司 | 一种带有格构柱支撑的基坑防护结构 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106168031A (zh) * | 2016-08-26 | 2016-11-30 | 上海市政工程设计研究总院(集团)有限公司 | 一种多功能钢板桩围堰 |
EP2393993B1 (de) * | 2009-02-06 | 2017-03-15 | Soiltec GmbH | Unterbau für bauwerke |
CN107083774A (zh) * | 2017-04-17 | 2017-08-22 | 浙江中成建工集团有限公司 | 多层水平连接双排钢板桩基坑支护结构及其施工方法 |
CN109723062A (zh) * | 2019-01-18 | 2019-05-07 | 济南轨道交通集团有限公司 | 基于近接深基坑施工环境的重载设备吊装装置及吊装方法 |
CN110306524A (zh) * | 2019-07-01 | 2019-10-08 | 济南轨道交通集团有限公司 | 近接未封闭建筑物的重型设备吊装的地基加固结构及方法 |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN206110140U (zh) * | 2016-10-26 | 2017-04-19 | 杭州市电力设计院有限公司 | 一种用于软土基坑大放坡开挖的竖向加固体 |
-
2019
- 2019-07-01 CN CN201910584848.6A patent/CN110306524B/zh active Active
- 2019-10-11 AU AU2019452705A patent/AU2019452705B2/en active Active
- 2019-10-11 WO PCT/CN2019/110664 patent/WO2021000444A1/zh active Application Filing
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2393993B1 (de) * | 2009-02-06 | 2017-03-15 | Soiltec GmbH | Unterbau für bauwerke |
CN106168031A (zh) * | 2016-08-26 | 2016-11-30 | 上海市政工程设计研究总院(集团)有限公司 | 一种多功能钢板桩围堰 |
CN107083774A (zh) * | 2017-04-17 | 2017-08-22 | 浙江中成建工集团有限公司 | 多层水平连接双排钢板桩基坑支护结构及其施工方法 |
CN109723062A (zh) * | 2019-01-18 | 2019-05-07 | 济南轨道交通集团有限公司 | 基于近接深基坑施工环境的重载设备吊装装置及吊装方法 |
CN110306524A (zh) * | 2019-07-01 | 2019-10-08 | 济南轨道交通集团有限公司 | 近接未封闭建筑物的重型设备吊装的地基加固结构及方法 |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113202107A (zh) * | 2021-05-18 | 2021-08-03 | 青海送变电工程有限公司 | 一种全地形深基坑开挖智能装置 |
CN113882348A (zh) * | 2021-09-01 | 2022-01-04 | 武汉市政工程设计研究院有限责任公司 | 一种深厚软土深基坑软弱土体预加固方法 |
CN113882348B (zh) * | 2021-09-01 | 2023-02-14 | 武汉市政工程设计研究院有限责任公司 | 一种深厚软土深基坑软弱土体预加固方法 |
CN113931228A (zh) * | 2021-10-21 | 2022-01-14 | 中天建设集团有限公司 | 一种用于地下室施工的材料平台施工方法 |
CN113931228B (zh) * | 2021-10-21 | 2023-01-10 | 中天建设集团有限公司 | 一种用于地下室施工的材料平台施工方法 |
CN113982035A (zh) * | 2021-10-25 | 2022-01-28 | 中国建筑一局(集团)有限公司 | 一种逆作法施工中梁柱转换结构及其施工方法 |
CN115217114A (zh) * | 2022-06-24 | 2022-10-21 | 深圳市工勘岩土集团有限公司 | 基坑抢险反压平台施工方法 |
CN115217114B (zh) * | 2022-06-24 | 2024-01-16 | 深圳市工勘岩土集团有限公司 | 基坑抢险反压平台施工方法 |
CN115262584A (zh) * | 2022-09-07 | 2022-11-01 | 中国建筑第八工程局有限公司 | 一种用于地铁深基坑分仓提前围闭的施工方法 |
CN115749346A (zh) * | 2022-11-04 | 2023-03-07 | 中建八局第二建设有限公司 | 车库顶板荷载分散施工方法 |
Also Published As
Publication number | Publication date |
---|---|
AU2019452705A1 (en) | 2021-10-07 |
CN110306524B (zh) | 2020-12-18 |
CN110306524A (zh) | 2019-10-08 |
AU2019452705B2 (en) | 2023-04-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2021000444A1 (zh) | 近接未封闭建筑物的重型设备吊装的地基加固结构及方法 | |
CN108842819B (zh) | 一种城市轨道交通电缆线路隧道施工方法 | |
CN110485429A (zh) | 一种预应力型钢装配式组合内支撑施工方法 | |
CN106958256A (zh) | 一种分层浇筑、多次下沉的沉井施工工艺 | |
CN102926400B (zh) | 一种组合挡土墙结构及其施工方法 | |
CN111456019A (zh) | 一种基坑开挖安全施工方法 | |
CN111119198A (zh) | 一种用于smw工法桩支护体系的加固结构 | |
CN104894926B (zh) | 既有铁路高路堤上支挡结构及其施工方法 | |
CN104264682A (zh) | 一种锚拉护壁桩首层加混凝土梁支撑技术 | |
CN108118689B (zh) | 一种可部分循环使用预制地下连续墙、吊具以及施工方法 | |
CN206800370U (zh) | 一种无肥槽开挖地下连续侧墙支挡防护构造 | |
CN108330963A (zh) | 一种用于土体内部既有桩基接桩的施工装置 | |
CN110241863B (zh) | 软土基坑开挖过程管廊变形控制装置及其控制方法 | |
CN111997043A (zh) | 一种分节钢筋笼及低净空高压线下的连续墙施工方法 | |
CN111218938A (zh) | 既有隧道上方的基坑开挖施工方法 | |
CN212452684U (zh) | 一种基坑支护结构灌注桩之间的土体防护结构 | |
CN114837088A (zh) | 一种公路上承台的施工方法 | |
CN204940310U (zh) | 一种组合支挡结构 | |
CN104805876B (zh) | 一种倾斜独立排架柱竖向顶推校正的方法 | |
CN106836325A (zh) | 一种室外施工电梯基础加固装置 | |
AU2019453220B2 (en) | Hosting method for heavy apparatus close to unsealed building | |
CN210561510U (zh) | 铁路线路防护装置 | |
CN209555962U (zh) | 一种适用于钻孔灌注桩ⅲ类桩与承台连接结构 | |
CN112031018A (zh) | 一种装配式轻型支挡结构及施工方法 | |
CN110656576A (zh) | 一种桥墩结构及其施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 19935932 Country of ref document: EP Kind code of ref document: A1 |
|
ENP | Entry into the national phase |
Ref document number: 2019452705 Country of ref document: AU Date of ref document: 20191011 Kind code of ref document: A |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 19935932 Country of ref document: EP Kind code of ref document: A1 |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 19935932 Country of ref document: EP Kind code of ref document: A1 |
|
32PN | Ep: public notification in the ep bulletin as address of the adressee cannot be established |
Free format text: NOTING OF LOSS OF RIGHTS PURSUANT TO RULE 112(1) EPC (EPO FORM 1205 DATED 11.10.2022) |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 19935932 Country of ref document: EP Kind code of ref document: A1 |