WO2020132407A1 - Building foundation system - Google Patents
Building foundation system Download PDFInfo
- Publication number
- WO2020132407A1 WO2020132407A1 PCT/US2019/067776 US2019067776W WO2020132407A1 WO 2020132407 A1 WO2020132407 A1 WO 2020132407A1 US 2019067776 W US2019067776 W US 2019067776W WO 2020132407 A1 WO2020132407 A1 WO 2020132407A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- matrix material
- waterproof layer
- fibers
- gradient
- lagging
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/30—Foundations made with permanent use of sheet pile bulkheads, walls of planks, or sheet piling boxes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
- E02D31/04—Watertight packings for use under hydraulic pressure
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/20—Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0001—Rubbers
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0006—Plastics
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0006—Plastics
- E02D2300/0007—PVC
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0006—Plastics
- E02D2300/0014—PU
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0051—Including fibers
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0051—Including fibers
- E02D2300/0053—Including fibers made from glass
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0051—Including fibers
- E02D2300/0054—Including fibers made from plastic
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0051—Including fibers
- E02D2300/0064—Including fibers made from metal
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0079—Granulates
Definitions
- the general inventive concepts relate to building foundations and, more particularly, to a blindside waterproofed building foundation system and method of forming the same.
- Blindside waterproofing is considerably more complex than traditional below-grade waterproofing because the construction process is reversed, and waterproofing is installed before the foundation is poured or applied. Structures are increasingly being built on less desirable or hard to access land. Typically, blindside waterproofing projects are required in high-density areas where property lines, nearby structures, and terrain limit excavation, access, and otherwise result in congested areas.
- Conventional blindside waterproofing systems and methods typically utilize multiple sheets of waterproofing membrane material that are adhered or fastened to a lagging wall. Because conventional blindside waterproofing systems and methods use multiple sheets of waterproofing membrane material, each joint, seam, or lap between adjacent membranes or other openings ( e.g ., openings to accommodate tieback anchors) must also be sealed to ensure complete waterproofing. Such conventional systems and methods are highly labor intensive and tedious, which increases the overall time and costs associated with constructing a waterproofed foundation in this manner.
- Another problem associated with conventional blindside waterproofing systems involves the deterioration over time of the lagging wall, which typically includes wooden planks or timbers. Intimate contact with soil and moisture may cause the wooden planks or timbers to deteriorate or decompose, or the lagging wall may move or shift, and the waterproofing membrane material may remain adhered or fastened to the wooden planks or timbers instead of the foundation, which could expose the foundation surface to soil and moisture.
- the general inventive concepts relate to a blindside waterproofed building foundation system and method of forming the same. To illustrate various aspects of the general inventive concepts, several exemplary embodiments of the system and method are disclosed.
- a blindside waterproofed building foundation system includes a lagging wall, a monolithic waterproof layer adjacent to the lagging wall, and a foundation layer adjacent to the monolithic waterproof layer.
- a method of forming a blindside waterproofed building foundation includes forming a lagging wall, applying a monolithic waterproof layer onto the lagging wall, and applying a foundation layer onto the monolithic waterproof layer.
- FIG. 1 is a cross-sectional elevation view, partially broken away, showing an embodiment of a blindside waterproofed building foundation system of the present disclosure
- FIG. 2 is a top plan view illustrating an embodiment of a lagging wall of a blindside waterproofed building foundation system of the present disclosure.
- the present application discloses exemplary embodiments of a blindside waterproofed building foundation system and methods of forming blindside waterproofed building foundations.
- the inventive system and method is much less labor intensive than conventional blindside waterproofing systems and methods, which reduces the overall time and costs associated with forming a blindside waterproofed building foundation.
- the inventive system and method provides a monolithic waterproof layer that remains adhered to a foundation surface even if the materials used to form a lagging wall deteriorate or decompose over time, or if the lagging wall moves or shifts due to reasons such as soil erosion, seismic shifts, or building settling.
- the term“monolithic” as used herein refers to a unitary structure that does not have any joints, seams, or laps.
- the system 100 includes a lagging wall 10, a monolithic waterproof layer 20 adjacent to the lagging wall 10, and a foundation layer 30 adjacent to the monolithic waterproof layer 20.
- the lagging wall 10 is installed vertically next to soil 5.
- the lagging wall 10 generally includes a plurality of piles and a plurality of lagging planks placed between and spanning adjacent piles. Generally, there are gaps between the lagging planks of the lagging wall 10, which gaps may be 1/64 inch to 2 inches, but more typically are 0.25 inch to 0.75 inch.
- FIG. 2 illustrates a typical lagging wall 10 arrangement that includes a pile 12 (only one pile is shown) and lagging planks 14 that abut a flange of the pile 12.
- the piles 12 may have an“I-beam” or“H-beam” configuration.
- the piles 12 may be formed of steel or concrete (pre-cast or cast-in-place), or other structural materials known in the art. Steel piles or pre-cast concrete piles can either be installed in pre-drilled pilot holes in an excavation site and backfilled with concrete or can be installed by driving the piles directly into an excavation site. Cast-in-place concrete piles can be constructed in pre-drilled holes in an excavation site. It should be understood that any conventional pile may be used in accordance with the present disclosure to form the lagging wall 10.
- a plurality of lagging planks 14 are placed horizontally between and span adjacent piles 12 to form the lagging wall 10.
- the lagging planks 14 may be formed from a variety of materials. Exemplary materials include, but are not limited to, wood or timber, polymeric lumber, concrete, and steel. Preferably, the lagging planks 14 are formed of wood or timber. As seen in FIG. 2, the lagging planks 14 may be placed within the flanges of the pile 12 and span horizontally to the next adjacent pile 12. Alternatively, the lagging planks 14 may be secured to the pile 12 in front of the flanges or secured to the pile 12 behind the flanges and span horizontally to the next adjacent pile 12.
- gaps between the lagging planks there are typically gaps between the lagging planks, which gaps may be 1/64 inch to 2 inches, but more typically are 0.25 inch to 0.75 inch. Although these gaps are conventional in lagging walls, such gaps permit ingress of water.
- the placement of lagging planks 14 may continue until a desired height of the lagging wall 10 is achieved.
- the lagging wall 10 may also include tieback anchors (not shown) to provide lateral support.
- the blindside waterproofed building foundation system 100 includes a monolithic waterproof layer 20 adjacent to the lagging wall 10.
- the monolithic waterproof layer 20 is a unitary structure that has no joints, no seams, and no laps.
- the monolithic waterproof layer 20 includes a matrix material and a filler material. A variety of materials may be used as a matrix material to form the monolithic waterproof layer 20.
- Exemplary matrix materials suitable for use in forming the monolithic waterproof layer 20 of the present disclosure include, but are not limited to, polyolefins (e.g ., polyethylene, polypropylene), polyvinyl chloride (PVC), polyvinylidene chloride, polyesters, polystyrenes, polyamides, ethylene vinyl acetate (EVA), polyurethanes, polyureas, polyepoxides, silicone, silicone hybrids, fluoropolymers, polyacrylonitriles, rubber materials, polyacrylics, asphaltic materials, latexes, and the like.
- polyolefins e.g ., polyethylene, polypropylene
- PVC polyvinyl chloride
- EVA ethylene vinyl acetate
- polyurethanes polyureas
- polyepoxides silicone
- silicone hybrids fluoropolymers
- fluoropolymers polyacrylonitriles, rubber materials, polyacrylics, asphaltic materials, latex
- the matrix material may comprise mixtures, blends, interpenetrating polymer networks, and/or copolymers of the aforementioned matrix materials.
- the matrix material may be a hot-applied material.
- the matrix material may also include additives such as plasticizers, colorants, stabilizers, coupling agents, and the like. Such additives may also include chemicals that promote chemical bonding with the cementitious material of the foundation layer 30 via techniques including, but not limited to, acid-base interactions, covalent bonding, and ionic bonding.
- the additives may comprise up to about 90% by weight of the matrix material, including from 0.1% to 90% by weight, from 0.1% to 75% by weight, from 0.1% to 50% by weight, from 0.1% to 25% by weight, from 0.1% to 10% by weight, from 0.1% to 5% by weight, and also including from 0.1% to 3% by weight of the matrix material.
- the monolithic waterproof layer 20 may block the passage of both liquid water and water vapor or a brownfield gas (e.g., methane, radon) and, thus, may also serve as a vapor barrier, vapor retarder, and/or gas barrier.
- a brownfield gas e.g., methane, radon
- the monolithic waterproof layer 20 of the present disclosure also includes a filler material.
- a filler material Any filler material known in the art that is capable of imparting a texturized surface may be used in accordance with the present disclosure. By imparting a texturized surface, the filler material may improve the adherence of the foundation layer 30 to the monolithic waterproof layer 20.
- a variety of materials may be used as the filler material to form the monolithic waterproof layer 20.
- the filler material may have various shapes or forms including, but not limited to, fibers, flakes, beads, and the like.
- Exemplary filler materials suitable for use in forming the monolithic waterproof layer 20 of the present disclosure include, but are not limited to, glass fibers, polymer fibers, carbon fibers, ceramic fibers, metal fibers, natural fibers (e.g, jute, hemp, cotton), glass flakes, corn-cob shell, walnut shell, sand, silica, calcium carbonate particles, limestone particles, limestone fines, ground reprocessed concrete, ground rubber, polymeric particles, Portland cement, pozzolanic materials, expanded glass spheres, and the like.
- the filler material comprises chopped glass fibers.
- the glass fibers comprise alkali resistant chopped glass fibers.
- the filler material of the monolithic waterproof layer 20 is also capable of bridging the gaps between the lagging planks of the lagging wall 10.
- the filler material may comprise alkali resistant chopped glass fibers having a minimum length of 0.125 inch, which when combined with the matrix material is capable of bridging gaps between lagging planks that range from 0.25 inch to 2 inches.
- the filler material essentially provides structure onto which the matrix material can adhere so as to bridge or close the gaps between the lagging planks to provide an effective barrier to water ingress.
- the monolithic waterproof layer 20 comprising the matrix material and the filler material is capable of withstanding compressive forces applied during application of the foundation layer 30.
- the unsupported portions of the monolithic waterproof layer 20 z.e., the portions located in the gaps between the lagging planks
- the compressive forces e.g ., impingement forces
- the monolithic waterproof layer 20 comprises 5% to 95% by weight matrix material and from 5% to 95% by weight filler material. In embodiments of the present disclosure, the monolithic waterproof layer 20 comprises 10% to 90% by weight matrix material and from 10% to 90% by weight filler material. In embodiments of the present disclosure, the monolithic waterproof layer 20 comprises 20% to 80% by weight matrix material and from 20% to 80% by weight filler material. In embodiments of the present disclosure, the monolithic waterproof layer 20 comprises 30% to 70% by weight matrix material and from 30% to 70% by weight filler material. In embodiments of the present disclosure, the monolithic waterproof layer 20 comprises 40% to 70% by weight matrix material and from 30% to 60% by weight filler material.
- the monolithic waterproof layer 20 comprises 50% to 65% by weight matrix material and from 35% to 50% by weight filler material. Any one or more of the previously mentioned matrix materials and filler materials may be used in the foregoing embodiments.
- the monolithic waterproof layer 20 of the present disclosure may have a thickness of 0.060 inch to 6 inches. In embodiments of the present disclosure, the monolithic waterproof layer 20 may have a thickness of 0.25 inch to 4 inches. In embodiments of the present disclosure, the monolithic waterproof layer 20 may have a thickness of 0.5 inch to 3 inches. In embodiments of the present disclosure, the monolithic waterproof layer 20 may have a thickness of 0.75 inch to 2 inches.
- the monolithic waterproof layer 20 comprises a single matrix material and a single filler distributed throughout the matrix material. It is also contemplated that the monolithic waterproof layer 20 may comprise gradients of materials. The gradients of materials may comprise one or more of the previously described matrix materials, one or more of the previously described filler materials, or one or more of the previously described matrix materials in combination with one or more of the previously described filler materials.
- the monolithic waterproof layer 20 comprises a first gradient of material comprising a first matrix material and a first filler material, and a second gradient of material comprising a second matrix material and optionally a second filler material.
- the first matrix material and the second matrix material may be the same or different.
- the first filler material and the optional second filler material may be the same or different. Any of the previously described matrix materials and filler materials may be used for the first and second matrix materials and the first and second filler materials.
- the monolithic waterproof layer 20 may include additional gradient(s) of material (e.g ., a third gradient of material, a fourth gradient of material, a fifth gradient of material, and so forth).
- the additional gradient(s) of material may comprise a matrix material that is the same or different from the first and/or second matrix materials.
- the additional gradient(s) of material may optionally comprise a filler material that is the same or different from the first filler material and/or optional second filler material.
- the gradients of material can transition to a final gradient of material that consists of one or more filler materials.
- the final gradient of material includes only filler material and no matrix material.
- the filler material of the final gradient of material creates a texturized surface to promote better adherence of the foundation layer 30 to the monolithic waterproof layer 20. Any one or more of the previously described filler materials may be used in the final gradient of material.
- the first gradient of material comprises a polymer modified asphalt emulsion and chopped glass fibers
- the second gradient of material comprises a polymer modified asphalt emulsion.
- a commercially available polymer modified asphalt emulsion is TREMproof® 260 asphalt emulsion from Tremco, Inc. (Beachwood, Ohio).
- the first gradient of material comprises a styrene butadiene rubber (SBR) latex and chopped glass fibers
- the second gradient of material comprises a polymer modified asphalt emulsion.
- SBR styrene butadiene rubber
- the monolithic waterproof layer 20 is applied to the lagging wall 10.
- the monolithic waterproof layer 20 is applied directly to the lagging wall 10 and bridges the gaps between the lagging planks of the lagging wall 20.
- an optional intermediate layer of material such as a drainage mat, may be applied directly to the lagging wall 10 and the monolithic waterproof layer 20 may be directly applied to the intermediate layer of material and, thus, indirectly applied to the lagging wall 10.
- the monolithic waterproof layer 20 may be applied to the lagging wall 10 in a variety of ways.
- the monolithic waterproof layer 20 may be applied to the lagging wall 10 by techniques including, but not limited to, spraying, painting, brushing, rolling, and the like. In embodiments of the present disclosure, the monolithic waterproof layer 20 is applied to the lagging wall 10 by one or more of spraying, painting, brushing, and rolling. Preferably, the monolithic waterproof layer 20 is spray-applied onto the lagging wall 10. In embodiments of the present disclosure, at least a portion of the monolithic waterproof layer 20 may be spray-applied onto the lagging wall 10 using a resin spray chopper gun, such as the chopper guns used in spray-up molding for fiberglass applications.
- a resin spray chopper gun such as the chopper guns used in spray-up molding for fiberglass applications.
- a first gradient of material comprising a first matrix material and a first filler material is spray-applied onto the lagging wall 10 and the second gradient of material comprising a second matrix material and optionally a second filler material is spray-applied onto the first gradient of material to form the monolithic waterproof layer 20.
- the first matrix material and the second matrix material may be the same or different.
- the first filler material and the optional second filler material may be the same or different. Any of the previously described matrix materials and filler materials may be used for the first and second matrix materials and the first and second filler materials. It is contemplated that additional gradients of material may be used to form the monolithic waterproof layer 20.
- each gradient of material may be applied using the same application technique or different application techniques. For example, the first gradient of material may be applied by spraying and the second gradient of material may be applied by rolling.
- Spray application of the monolithic waterproof layer 20 onto the lagging wall 10 is much less labor intensive than conventional methods that require the application of multiple sheets of waterproofing membranes and ensuring that all joints, seams, and/or laps between adjacent membranes or other openings (e.g ., openings to accommodate tieback anchors) are adequately sealed. Furthermore, spray application of the monolithic waterproof layer 20 onto the lagging wall 10 creates a monolithic waterproofing layer that is free from joints, seams, laps, and other openings, thus providing improved waterproofing capabilities over conventional blindside waterproofing techniques.
- the blindside waterproofed building foundation system 100 includes a foundation layer 30 adjacent to the monolithic waterproof layer 20.
- the foundation layer 30 comprises a cementitious material that is applied in a wet state and allowed to harden or cure over time. Any conventional cementitious material that is used in constructing building foundations may be used in accordance with the present disclosure.
- the foundation layer 30 is applied to the monolithic waterproof layer 20.
- the foundation layer 30 is applied directly to the monolithic waterproof layer 20.
- the monolithic waterproof layer 20 may have a texturized surface to increase the surface area onto which the foundation layer is applied 30.
- a texturized surface can promote better adherence of the foundation layer 30 to the monolithic waterproof layer 20 by providing projecting filler materials, uneven surfaces, and undercuts that bond or lock the foundation layer 30 to the monolithic waterproof layer 20. This bonding or locking is advantageous in that upon deterioration or decomposition of the lagging wall 10, the monolithic waterproof layer 20 remains adhered to the foundation layer 30 and waterproofing capabilities are not compromised.
- the monolithic waterproof layer 20 preferentially adheres to the foundation layer 30 rather than to the lagging wall 10. This preferential adherence ensures that the monolithic waterproof layer 20 remains adhered to the foundation layer 30 to provide waterproofing capabilities upon deterioration, decomposition, and/or movement of the lagging wall 10.
- an adhesive value between the monolithic waterproof layer 20 and the foundation layer 30 is greater than an adhesive value between the monolithic waterproof layer 20 and the lagging wall 10.
- the adhesive values can be determined using conventional peel tests known in the art, such as ASTM C794.
- the monolithic waterproof layer 20 may adhere to the foundation layer 30 with an adhesive value that is greater than 5 pounds of force per linear inch, including from 5 pounds per linear inch to 100 pounds per linear inch, as determined by a conventional peel test such as ASTM C794.
- ASTM C794 a conventional peel test
- the adhesive value between the monolithic waterproof layer 20 and the lagging wall 10 is less than 5 pounds per linear inch to less than 100 pounds per linear inch as long as the adhesive value between the waterproof layer 20 and the lagging wall 10 is less than the adhesive value between the monolithic waterproof layer 20 and the foundation layer 30.
- the foundation layer 30 may be reinforced with rebar or other suitable reinforcements.
- a grid of rebar reinforcements may be installed adjacent to the monolithic waterproof layer 20, and the foundation layer 30 may be applied to the monolithic waterproof layer 20 and encase the grid of rebar reinforcements.
- the foundation layer 30 may be applied to the monolithic waterproof layer 20 in a variety of ways.
- the foundation layer 30 may be applied to the monolithic waterproof layer 20 by techniques including, but not limited to, spraying, pouring, and the like.
- the foundation layer 30 is spray-applied onto the monolithic waterproof layer 20.
- the foundation layer 30 comprises shotcrete, which is a Portland cement material that is spray-applied onto the monolithic waterproof layer 20.
- the foundation layer 30 comprises concrete that is poured-in-place.
- the foundation layer 30 comprises a combination of shotcrete that is spray-applied and concrete that is poured-in-place.
- the foundation layer 30 of the present disclosure may have a thickness that is appropriate in view of the structure to be erected. In embodiments of the present disclosure, the foundation layer 30 may have a thickness of 4 inches to 72 inches. In embodiments of the present disclosure, the foundation layer 30 may have a thickness of 12 inches to 60 inches.
- the blindside waterproofed building foundation system and method of the present disclosure provides a number of advances over conventional blindside waterproofing systems and methods.
- the blindside waterproofed building foundation system and method of the present disclosure ensures that the gaps between lagging planks in the lagging wall are bridged or closed to provide an effective barrier to water ingress.
- the blindside waterproofed building foundation system and method of the present disclosure also provides a monolithic waterproofing layer that does not include any joints, seams, laps, holes, or other openings that would potentially allow water ingress.
- the preferential adherence of the monolithic waterproof layer to the foundation layer rather than the lagging wall ensures that the monolithic waterproof layer remains adhered to the foundation layer to provide waterproofing capabilities upon deterioration or decomposition of the lagging wall.
- Example 1 In this example, qualitative tests were conducted to evaluate the adhesive values of several matrix materials (with and without a filler) to a wood material and to a simulated shotcrete material. The qualitative testing was conducted as follows. Approximately 60 mils (about 1.5 mm) of matrix material (with or without a filler) was applied to a 12 inch by 12 inch piece of oriented strand board (OSB) and allowed to cure. Next, a wet mix of Eucoshot 105 50 shotcrete (available from Euclid Chemical Co., Cleveland, Ohio) was applied to the cured matrix material and compressed with 2 psi of force to simulate real world shotcrete impingement forces.
- OSB oriented strand board
- the adhesion values observed for Samples 2, 3, and 4 indicate that the matrix materials for those samples preferentially adhere to the shotcrete material rather than to the wood material.
- the adhesion values observed for Sample 5 indicate that the matrix material used for that sample preferentially adheres to the wood material rather than the shotcrete material.
- adhesion to the shotcrete was successfully maintained or increased by the addition of the filler material (i.e., 5% by weight 1/4” chopped glass fibers) to the matrix material.
- Example 2 In this example, quantitative tests were conducted to evaluate the adhesive values of several matrix materials to a wood material. The quantitative testing was conducted as follows. Approximately 60 mils (about 1.5 mm) of matrix material (with or without a filler) was applied to a 3 inch by 6 inch piece of oriented strand board (OSB). A 1 inch wide strip of steel mesh was applied to the wet matrix material before applying another gradient of matrix material and allowing to cure for 2 weeks at 77°F and 50% relative humidity. After cure, the resulting assembly was subjected to a peel test in accordance with ASTM C794. The results of the peel test (in pounds per linear inch (pli)) are shown in Table 3. TABLE 3 - Quantitative Testing Results
- Sample A was also tested to evaluate the adhesive value of the matrix material to a simulated shotcrete material.
- the sample was prepared as described above and further included applying a wet mix of Eucoshot 105 50 shotcrete (available from Euclid Chemical Co., Cleveland, Ohio) to the cured matrix material and then compressing the shotcrete with 2 psi of force to simulate real world shotcrete impingement forces. After the shotcrete material cured, a peel test was performed on the sample.
- the adhesive value of the matrix material to the simulated shotcrete material for Sample A was 8.9 pli (cohesive), which indicates that the matrix material of Sample A preferentially adheres to the shotcrete material rather than to the wood material (5.4 pli (cohesive)).
- system and method of the present disclosure can comprise, consist of, or consist essentially of the essential elements and limitations of the disclosure as described herein, as well as any additional or optional ingredients, components, or limitations described herein or otherwise useful in blindside waterproofing applications.
- compositions and materials associated with the system and method of the present disclosure may also be substantially free of any optional or selected essential ingredient or feature described herein, provided that the remaining composition still contains all of the required ingredients or features as described herein.
- the term“substantially free” means that the selected composition contains less than a functional amount of the optional ingredient, typically less than 0.1% by weight, and also including zero percent by weight of such optional or selected essential ingredient.
- the terms“include,”“includes,” or“including” are used in the specification or the claims, they are intended to be inclusive in a manner similar to the term “comprising” as that term is interpreted when employed as a transitional word in a claim.
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Hydrology & Water Resources (AREA)
- Environmental & Geological Engineering (AREA)
- Building Environments (AREA)
- Finishing Walls (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Priority Applications (6)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201980092117.8A CN113423893B (zh) | 2018-12-21 | 2019-12-20 | 建筑物地基系统 |
| EP19842690.0A EP3899148A1 (en) | 2018-12-21 | 2019-12-20 | Building foundation system |
| JP2021536051A JP2022515205A (ja) | 2018-12-21 | 2019-12-20 | 建物基礎システム |
| PH1/2021/551403A PH12021551403A1 (en) | 2018-12-21 | 2019-12-20 | Building foundation system |
| AU2019404344A AU2019404344A1 (en) | 2018-12-21 | 2019-12-20 | Building foundation system |
| KR1020217023073A KR20210110324A (ko) | 2018-12-21 | 2019-12-20 | 건물 기초 시스템 |
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| US201862783435P | 2018-12-21 | 2018-12-21 | |
| US62/783,435 | 2018-12-21 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2020132407A1 true WO2020132407A1 (en) | 2020-06-25 |
Family
ID=69191259
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/US2019/067776 Ceased WO2020132407A1 (en) | 2018-12-21 | 2019-12-20 | Building foundation system |
Country Status (9)
| Country | Link |
|---|---|
| US (1) | US10907319B2 (https=) |
| EP (1) | EP3899148A1 (https=) |
| JP (1) | JP2022515205A (https=) |
| KR (1) | KR20210110324A (https=) |
| CN (1) | CN113423893B (https=) |
| AU (1) | AU2019404344A1 (https=) |
| CA (1) | CA3065723C (https=) |
| PH (1) | PH12021551403A1 (https=) |
| WO (1) | WO2020132407A1 (https=) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2023008898A (ja) * | 2021-06-30 | 2023-01-19 | 関西ペイント株式会社 | 防水塗料、防水膜、及び防水積層膜 |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR102830003B1 (ko) * | 2024-01-23 | 2025-07-04 | 주식회사 리폼이엔지 | 시공이 간단하고 거동 대응성이 우수하며 양면 점착이 가능한 합벽구간 역방수 시공 방법 |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CA1202190A (en) * | 1982-08-18 | 1986-03-25 | Joseph Sartor | Wall drainage system |
| WO1997038174A1 (en) * | 1996-04-06 | 1997-10-16 | Arc Limited | Lining for a landfill site |
| EP2177349A1 (de) * | 2008-10-15 | 2010-04-21 | Sika Technology AG | Wasserdichte Membran |
| EP2907832A1 (de) * | 2014-02-17 | 2015-08-19 | FRANKEN-Systems GmbH | Verfahren zur druckwasserfesten Abdichtung von Bauwerken |
| KR101881577B1 (ko) * | 2017-07-26 | 2018-08-24 | 우경기술주식회사 | 강재와 콘크리트로 보강된 중공형 말뚝을 활용한 옹벽 및 그 시공방법 |
| US20180313055A1 (en) * | 2017-04-28 | 2018-11-01 | R&B Leasing | Landfill liner system |
Family Cites Families (37)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US3243963A (en) | 1962-11-16 | 1966-04-05 | Jr Harry Schnabel | Method of reinforcing deep excavations |
| GB1518263A (en) | 1974-06-20 | 1978-07-19 | Butyl Products Ltd | Method of lining a waterway or reservoir and a laminate suitable for such purpose |
| US4561804A (en) | 1980-10-01 | 1985-12-31 | Schnabel Foundation Company | Earth retaining method |
| US5002438B1 (en) | 1990-01-03 | 1995-05-30 | Strong Systems Inc | Method of rehabilitating manholes by custom lining/relining. |
| US5389166A (en) | 1990-12-17 | 1995-02-14 | American Colloid Company | Water barrier formed from a clay-fiber mat |
| US5496615A (en) | 1991-03-01 | 1996-03-05 | W. R. Grace & Co.-Conn. | Waterproofing membrane |
| JP3175069B2 (ja) | 1993-09-29 | 2001-06-11 | 株式会社大林組 | ゴムアスファルト系防水組成物 |
| US5671889A (en) | 1995-02-17 | 1997-09-30 | Petty; Ralph S. | Waterproofing spray apparatus |
| EP0725185A1 (de) | 1996-01-08 | 1996-08-07 | Roland F. Wolfseher | Tunnelauskleidung und Verfahren zu deren Anbringung |
| GB9625163D0 (en) | 1996-12-04 | 1997-01-22 | Sandoz Ltd | Organic compounds |
| GB9815685D0 (en) | 1998-07-20 | 1998-09-16 | Mbt Holding Ag | Waterproofer |
| US6225393B1 (en) | 1999-05-14 | 2001-05-01 | Spraytex, Inc. | Hardenable exterior texture material in aerosol form |
| US6793441B2 (en) | 2000-06-12 | 2004-09-21 | W. R. Grace & Co.-Conn. | Tunnel waterproofing method |
| US6767164B2 (en) | 2000-06-12 | 2004-07-27 | W. R. Grace & Co.-Conn. | Tunnel waterproofing construction method |
| US6648962B2 (en) | 2001-09-06 | 2003-11-18 | W. R. Grace & Co.-Conn. | Micro-granulose particulates |
| US20030092848A1 (en) | 2001-09-11 | 2003-05-15 | Ashok Sengupta | Sprayable liner for supporting the rock surface of a mine |
| JP4076126B2 (ja) * | 2002-03-29 | 2008-04-16 | 秀雄 藤田 | 土中コンクリート壁の防湿工法及び防湿体 |
| US6852813B2 (en) | 2002-09-25 | 2005-02-08 | Amcol International Corporation | Polymer-filled sheet material |
| CN1607301A (zh) * | 2003-10-13 | 2005-04-20 | 侯彩虹 | 一种冷自粘防水卷材的施工方法 |
| US8524822B2 (en) | 2005-01-11 | 2013-09-03 | W. R. Grace & Co.—Conn. | Vapor permeable liquid-applied membrane |
| US7565779B2 (en) | 2005-02-25 | 2009-07-28 | W. R. Grace & Co.-Conn. | Device for in-situ barrier |
| US7662221B2 (en) | 2006-06-23 | 2010-02-16 | Johns Manville | Spray applied building wrap coating material, spray applied building wrap, and building construction assembly |
| US20080178769A1 (en) | 2007-01-30 | 2008-07-31 | Construction Research & Technology Gmbh | Kit and method for preparing a hardenable cementitious composition |
| US7722293B2 (en) | 2008-01-28 | 2010-05-25 | Darin R. Kruse | Methods for constructing underground structures |
| JP5133731B2 (ja) * | 2008-02-19 | 2013-01-30 | ミサワホーム株式会社 | ユニット式建物の基礎構造およびユニット式建物の施工方法 |
| US20110203218A1 (en) | 2010-02-23 | 2011-08-25 | Solov Jerry | Spray on barrier systems and methods of making same |
| JP2014503715A (ja) | 2010-11-08 | 2014-02-13 | アンコル インターナショナル コーポレイション | 誘導溶接防水 |
| US8635833B2 (en) | 2010-12-23 | 2014-01-28 | Richard Roy ANDERSON | Top-down method for constructing below-grade structures |
| US20120198787A1 (en) | 2011-02-08 | 2012-08-09 | Yu-Cheng Mo | Pre-pave Waterproof Construction Method |
| CA2830280C (en) | 2011-03-18 | 2019-01-15 | Peter Mervyn NEIL | Composite wall panel, wall system and components thereof, and a method of construction thereof |
| FR2976003B1 (fr) | 2011-06-01 | 2021-01-29 | Soletanche Freyssinet | Procede de fabrication d'une paroi de soutenement a partir d'une paroi brute en soil-mixing |
| CN104169379A (zh) | 2011-12-30 | 2014-11-26 | 乔舒亚·V·布赖恩 | 用于建筑产品的低碳足印(footprint)涂布材料 |
| US8650830B2 (en) | 2013-03-08 | 2014-02-18 | John Cogburn | Method of basement construction |
| US20150197909A1 (en) | 2014-01-14 | 2015-07-16 | John Huh | Waterproofing and vapor barrier system |
| CN203977446U (zh) * | 2014-06-21 | 2014-12-03 | 济南中建建筑设计院有限公司 | 一种组合式钢筋混凝土地下室外墙 |
| US20160097278A1 (en) | 2014-10-07 | 2016-04-07 | John Huh | Waterproofing system for exposed rock surfaces |
| US9909313B1 (en) | 2017-01-19 | 2018-03-06 | Austin M. Grubbs | Composite materials, methods of making composite materials, and enclosures constructed from composite materials |
-
2019
- 2019-12-20 PH PH1/2021/551403A patent/PH12021551403A1/en unknown
- 2019-12-20 KR KR1020217023073A patent/KR20210110324A/ko not_active Ceased
- 2019-12-20 WO PCT/US2019/067776 patent/WO2020132407A1/en not_active Ceased
- 2019-12-20 EP EP19842690.0A patent/EP3899148A1/en not_active Withdrawn
- 2019-12-20 US US16/722,312 patent/US10907319B2/en active Active
- 2019-12-20 AU AU2019404344A patent/AU2019404344A1/en not_active Abandoned
- 2019-12-20 CA CA3065723A patent/CA3065723C/en active Active
- 2019-12-20 JP JP2021536051A patent/JP2022515205A/ja active Pending
- 2019-12-20 CN CN201980092117.8A patent/CN113423893B/zh not_active Expired - Fee Related
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CA1202190A (en) * | 1982-08-18 | 1986-03-25 | Joseph Sartor | Wall drainage system |
| WO1997038174A1 (en) * | 1996-04-06 | 1997-10-16 | Arc Limited | Lining for a landfill site |
| EP2177349A1 (de) * | 2008-10-15 | 2010-04-21 | Sika Technology AG | Wasserdichte Membran |
| EP2907832A1 (de) * | 2014-02-17 | 2015-08-19 | FRANKEN-Systems GmbH | Verfahren zur druckwasserfesten Abdichtung von Bauwerken |
| US20180313055A1 (en) * | 2017-04-28 | 2018-11-01 | R&B Leasing | Landfill liner system |
| KR101881577B1 (ko) * | 2017-07-26 | 2018-08-24 | 우경기술주식회사 | 강재와 콘크리트로 보강된 중공형 말뚝을 활용한 옹벽 및 그 시공방법 |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2023008898A (ja) * | 2021-06-30 | 2023-01-19 | 関西ペイント株式会社 | 防水塗料、防水膜、及び防水積層膜 |
| JP7839700B2 (ja) | 2021-06-30 | 2026-04-02 | 関西ペイント株式会社 | 防水塗料、防水膜、及び防水積層膜 |
Also Published As
| Publication number | Publication date |
|---|---|
| EP3899148A1 (en) | 2021-10-27 |
| CA3065723C (en) | 2021-11-23 |
| AU2019404344A1 (en) | 2021-07-01 |
| CN113423893B (zh) | 2023-03-14 |
| CN113423893A (zh) | 2021-09-21 |
| KR20210110324A (ko) | 2021-09-07 |
| US20200199840A1 (en) | 2020-06-25 |
| CA3065723A1 (en) | 2020-06-21 |
| PH12021551403A1 (en) | 2022-05-11 |
| JP2022515205A (ja) | 2022-02-17 |
| US10907319B2 (en) | 2021-02-02 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| Buchanan et al. | Performance of houses during the Christchurch earthquake of 22 February 2011 | |
| US20120198787A1 (en) | Pre-pave Waterproof Construction Method | |
| US5736197A (en) | Method of waterproofing rigid structural materials | |
| JP2018523770A5 (https=) | ||
| MX2012011043A (es) | Sistema para reforzar estructura usando materiales adaptados en el sitio. | |
| CA3065723C (en) | A blindside waterproofed building foundation system and method of forming same | |
| KR20240148712A (ko) | 합벽, cip벽, 지하벽, h파일벽, 흙막이벽, 지하주차장, 지하구조물의 방수, 방근, 조경, 건설, 공사, 방근방수 공법 | |
| CN112144581A (zh) | 大型整体式地下空间防水施工结构及其施工方法 | |
| Park et al. | & Wright, E | |
| County | INSULATED PRECAST CONCRETE WALL PANELS | |
| Morgan et al. | Seismic retrofit of a concrete immersed tube tunnel with reinforced shotcrete | |
| George | City of St. Charles School District R-VI | |
| Terman | Building the Earth Sheltered House | |
| Eustis | TRADOC–ARMY COMBAT FITNESS TESTING (ACFT) DESIGN | |
| Drawings | 1.1 RELATED DOCUMENTS | |
| Schools et al. | Allen Bowden Activity Center | |
| Submittals et al. | SECTION 02222 EXCAVATION AND BACKFILL FOR UTILITIES | |
| JP2022001708A (ja) | 土系材料から成る構造物の構築方法 | |
| PARK | CONCESSIONS, STORAGE, AND RESTROOM BUILDING | |
| SP et al. | 1.5 REGULATORY REQUIREMENTS | |
| Liebing | Review of Sample Details | |
| SHARFUDDIN | REPAIR AND REHABILITATION OF STRUCTURES | |
| Garrett | Hastings boys' high school administration buildings, Hastings, Hawke's Bay, New Zealand: Case studies: earthquake risk buildings | |
| Warner | Ventura City Hall Restoration | |
| MORSY | Repair and Strengthening of Reinforced Concrete Structures |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 19842690 Country of ref document: EP Kind code of ref document: A1 |
|
| ENP | Entry into the national phase |
Ref document number: 2021536051 Country of ref document: JP Kind code of ref document: A |
|
| NENP | Non-entry into the national phase |
Ref country code: DE |
|
| ENP | Entry into the national phase |
Ref document number: 2019404344 Country of ref document: AU Date of ref document: 20191220 Kind code of ref document: A |
|
| ENP | Entry into the national phase |
Ref document number: 20217023073 Country of ref document: KR Kind code of ref document: A |
|
| ENP | Entry into the national phase |
Ref document number: 2019842690 Country of ref document: EP Effective date: 20210721 |