WO2019101158A1 - Intensive flood irrigation channel - Google Patents

Intensive flood irrigation channel Download PDF

Info

Publication number
WO2019101158A1
WO2019101158A1 PCT/CN2018/117127 CN2018117127W WO2019101158A1 WO 2019101158 A1 WO2019101158 A1 WO 2019101158A1 CN 2018117127 W CN2018117127 W CN 2018117127W WO 2019101158 A1 WO2019101158 A1 WO 2019101158A1
Authority
WO
WIPO (PCT)
Prior art keywords
channel
dam wall
water
water supply
outer dam
Prior art date
Application number
PCT/CN2018/117127
Other languages
French (fr)
Chinese (zh)
Inventor
党海愚
Original Assignee
党海愚
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 党海愚 filed Critical 党海愚
Publication of WO2019101158A1 publication Critical patent/WO2019101158A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B13/00Irrigation ditches, i.e. gravity flow, open channel water distribution systems
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B5/00Artificial water canals, e.g. irrigation canals
    • E02B5/08Details, e.g. gates, screens

Definitions

  • the invention belongs to the field of farmland water conservancy technology, in particular to an intensive flood irrigation channel.
  • the invention provides an intensive flood irrigation channel in order to solve the problem that the traditional slurry rolling dam is high in cost and cannot be taken locally and is not allowed to be densely constructed in the river.
  • an intensive flood irrigation channel including an inner limited dam wall and an outer dam wall, the inner limited dam wall and the outer dam wall are arranged in parallel, and the inner limit dam wall and the outer dam wall are channels, channels
  • the elevation is lower than the lowest water level of the riverbed in this section, and the downstream end of the outer dam wall is provided with a water-retaining pier of the outer dam wall.
  • the water-retaining pier of the outer dam wall is provided with a sediment discharge port, and the outer dam wall is limited to the outer side of the water-side pier.
  • a channel gate is provided at the downstream of the sediment discharge channel, and the channel is downstream of the channel.
  • the water outlet is provided with left and right pull gates.
  • top elevation of the swim end of the outer dam wall is higher than the top elevation of the downstream end.
  • the width of the outlet channel is smaller than the width of the channel.
  • the elevation of the inner dam wall of the channel is higher than the elevation of the side of the outer dam wall.
  • the width of the sediment discharge channel is the same as the width of the channel, and the elevation of the sediment discharge channel (4) is lower than the elevation of the bottom of the channel.
  • a filter sheet is provided on the water supply channel.
  • the intensive flood irrigation channel technology of the present invention is directed to the various defects existing in the vertical channel water intake port and the river channel slurry-blocking dam, and is changed to the vertical channel to directly take water, thereby omitting the fixed roll.
  • the dam does not affect the safe flooding of the river.
  • the channel uses eight functions of priority water intake, automatic overflow conditioning, automatic sand washing, sediment discharge, filtration and drainage of floating debris and grass seeds, self-flowing water supply, free handling and safe flood control.
  • Engineering materials can replace and locally extract materials and add a protective layer that resists light and sand.
  • the channel can also increase the amount of water supplied, and it can be used in the flood control of small and medium-flow water in the flood control project.
  • Floods in the main and tributary channels can also be accessed simultaneously or separately from the tributary channels. It can also be used in conjunction with the dry land in the Hirakawa area to solve the problem of flood irrigation and water supply. Therefore, it is possible to convert floods, ice and snow, and constant water in the river into agricultural water, and do not need electromechanical power equipment and computer room pumping stations equipped with water lifting, all of which are self-flowing, clean and low-cost flooding.
  • Figure 1 is a schematic structural view of the present invention
  • an intensive flood irrigation channel includes an inner dam wall 1 and an outer dam wall 3, and the inner dam wall 1 and the outer dam wall 3 are arranged in parallel, and the inner dam wall 1 and the outer dam wall 3 are
  • the channel is channel 12, the channel 12 elevation is lower than the lowest water level of the river bed, the outer dam wall 3 is provided with the outer dam wall water-retaining pier 2, and the outer dam wall water-retaining pier 2 is provided with the sedimentation port.
  • Road 4 the outer dam wall is limited to the outer side of the water-retaining pier 2, and there is an overflow adjustment section, the abundance 13 is provided.
  • the outer side of the sedimentation and discharge channel 4 is provided with a sedimentation and drainage channel gravity protection 8 and a sediment discharge channel.
  • the water supply channel 5 is provided with a water supply port pulling type amu 10 and a water supply channel.
  • the downstream side is provided with a water outlet channel 6, and the water outlet channel 6 is provided with a left and right pulling gate 7.
  • the top elevation of the upstream end of the outer dam wall 3 is higher than the top elevation of the downstream end. That is, the top elevation of the upstream end of the outer dam wall 3 is 40 cm higher than the bottom of the channel, and the top elevation of the downstream end of the outer dam wall 3 is 30 cm higher than the bottom of the channel.
  • the width of the outlet 6 is less than the width of the channel 12. Some of the garbage in the flood does not enter the water supply channel 5 and is discharged from the water outlet channel 6.
  • the inner elevation of the inner dam wall 1 of the channel 12 is higher than the elevation of the side of the outer dam wall 3.
  • the slope is 1:0.1, forcing the coarse sand stones entering the channel to advance along the channel on one side of the outer dam wall and being pushed into the sediment discharge channel by subsequent floods.
  • the width of the sediment discharge channel 4 is the same as the width of the channel 12, and the elevation of the sedimentation channel 4 is lower than the elevation of the bottom of the channel 12.
  • a filter plate is provided on the water supply passage 5. Filters the floating debris and grass seeds in the flood.
  • the invention is constructed close to the mantle and the dam wall on one side of the river channel, and the water supply port is placed at the commanding height of the irrigated farmland, and is extended upward according to the reference, and the numerical value of the longitudinal slope of the river channel is used as a reference for comparison.
  • the vertical slope at the bottom of the channel reaches 100:1, and the address of the water intake should be found.
  • the channel intake is lower than the lowest point of the channel or the minimum water level of the normal water is 30 cm.
  • the dam wall in the channel is a limited dam wall, the top is not flooded by the maximum flood of the river channel, the slope is smaller than the slope at the bottom of the channel, and the outer dam wall is an overflow regulating dam wall, and the channel width is generally 1 meter.
  • the bottom of the channel water intake is lower than the lowest point of the river bed or the minimum water level of the normal water is 30 cm, so that the river water flow preferentially enters the channel.
  • the top of the outer dam wall end of the channel water intake is 40 cm higher than the bottom of the channel. Based on this, it extends downwards along the horizontal line to form an overflow drainage section, and the overflow section is cut off.
  • the dam crest of a small section of the outer dam wall of the square is level with the dam crest of the inner dam wall as the water-retaining pier of the overflow section.
  • the river bed on the overflow part of the overflow discharge section is constructed with a gravity-like sheet and a series of automatic settlement aprons, which are more than 2 meters wide, both as a water-falling aquarium and a channel flood control.
  • the top of the overflow dam wall of the outer dam wall will be submerged. Due to the limitation of the channel width, excessive floods entering the channel will be evenly discharged into the channel from the entire section.
  • the lateral slope is the slope of the inner high and the low, and the slope is 1:0.1 of the channel width, so that the coarse sand entering the channel
  • the stone runs along the bottom of the side of the outer dam wall, and is smoothly pushed into the sediment discharge channel by subsequent floods.
  • Sediment discharge that is, the sediment discharge port on the wall of the water-restricted pier with a distance of 2 meters from the cut-off point of the overflow dam section of the outer dam wall, the width is equal to the width of the channel, and the channel is The inner angle of the outer wall of the upper side is 45°, and the bottom is 20 cm lower than the bottom of the channel. It is also a vertical and horizontal two-way slope, which causes the heavy sand in the channel to fall into the channel and is pushed into the river by the subsequent flood. The flakes and the strings are automatically settled in the face and the river. Vertical gullies are formed on the dam walls on both sides of the mouth for replacement of the same ram. When no flood is used, the water flowing into the channel from the daily channel is discharged into the channel from the channel.
  • Self-flowing water supply that is, a water supply channel is provided on the inner dam wall 2 meters away from the sedimentation discharge channel, and the width is equal to the width of the channel, so that the water flow enters the farmland from the mouthway, and the channel can also be used.
  • a water supply port is added to the inner dam wall at 2 meters downstream to meet the water supply needs.
  • Filtration and drainage with flooding debris and grass seeds that is, the filter plate is fixedly installed on the inner side of the dam wall outside the channel water supply port.
  • the mesh of the filtering eyes can filter the grass seeds, and does not enter the farmland, the filter sheets can be freely disassembled and preserved. use.
  • the width of the outlet at the end of the channel shrinks to 30 cm and leads to the channel.
  • the outside is provided with a manually operated brake pad that can be pulled left and right and has mechanical properties, so that the residual sediment and floating debris in the channel are from the mouth.
  • the road is randomly discharged into the river and can restrict the discharge of water.
  • the channels are generally made of stone slurry.
  • the construction area without stone, washed sand and water source allows the manufacturer to use plastics to make container parts with the shape of bricks, sand and sand instead of stone, each piece is glued with waterproof glue, and the bottom of the channel is welded with plastic steel plate.
  • the channel can use the micro-flood, ice-cold water and constant-flow water in the river channel, and can be adjusted by large-section overflow to adapt to the largest flood utilization in the river.
  • the channel is applied to the water supply and drainage of the sloping flood and silt and farmland soil improvement thickening and flooding project: the water supply port of the dam wall in the channel is enlarged, and after the land is silted, the dam wall can be rebuilt. Increase the channel width.

Abstract

An intensive flood irrigation channel, comprising an inner water-limiting dam wall (1) and an outer dam wall (3). The inner water-limiting dam wall (1) and the outer dam wall (3) are arranged in parallel. A channel (12) is found between the inner water-limiting dam wall (1) and the outer dam wall (3). The elevation of the channel (12) is lower than the minimum water level of a present section of riverbed. An outer dam wall water-limiting counterfort (2) is provided at a downstream extremity of the outer dam wall (3). A settled sand and flood discharging drain (4) is provided on the outer dam wall water-limiting counterfort (2). An overflow volume-adjustment sectional apron (13) is provided on the outside of the outer dam wall water-limiting counterfort (2). A settled sand and flood discharging drain gravitational apron (8) is provided on the outside of the settled sand and flood discharging drain (4). A channel gate (11) is provided downstream to the settled sand and flood discharging drain (4). A water supply inlet (5) is provided on the inner water-limiting dam wall (1) downstream to the channel gate (11). A water supply inlet pull-type apron (10) is provided on the inside of the water supply inlet (5). A water outlet (6) is provided downstream to the water supply inlet (5). A left-right pulling gate (7) is provided at the water outlet (6).

Description

集约式洪灌渠道Intensive flood irrigation channel 技术领域Technical field
本发明属于农田水利技术领域,具体是一种集约式洪灌渠道。The invention belongs to the field of farmland water conservancy technology, in particular to an intensive flood irrigation channel.
背景技术Background technique
自从水泥发明后,推动河道滚水坝枢纽工程建设有了一次发展,解决了洪水淤地及农田灌溉的可稳定性配套取水问题。但是由于受山丘区河道拐弯和支流汇合等影响,河道两侧可利用土地的单位面积都被切割成小片,而要把河道两侧的每片土地都能够达到淤灌供水目的,就需要在河道中近距离或密集型建造横向滚水坝,不仅建设财力无法承受,而且遇到特大洪水,势必全线涌入河槽水位,危及河道安全通洪和人民群众的生命财产安全。因此,严重制约着山丘区淤滩坝地工程建设的正常选址,成为洪水难以就地农用的一个重要原因。Since the invention of cement, the development of the river rolling dam hub project has been developed once, which solves the problem of stable and stable water intake for flood silt and farmland irrigation. However, due to the influence of river bends and tributaries in the hilly area, the unit area of the land available for use on both sides of the river channel is cut into small pieces, and each piece of land on both sides of the river can be used for silt irrigation purposes. Close-up or intensive construction of horizontal rolling dams in river courses not only fails to bear the financial resources of construction, but also encounters a large flood, which is bound to flood the river channel water level, endangering the safe flooding of rivers and the lives and property of the people. Therefore, it seriously restricts the normal site selection of the construction of the silt dam in the hilly area, which has become an important reason for the flood to be difficult to use on the spot.
发明内容Summary of the invention
本发明为了解决传统浆砌滚水坝费用高,不能就地取材和不允许在河道中密集型建造的问题,提供一种集约式洪灌渠道。The invention provides an intensive flood irrigation channel in order to solve the problem that the traditional slurry rolling dam is high in cost and cannot be taken locally and is not allowed to be densely constructed in the river.
本发明采取以下技术方案:一种集约式洪灌渠道,包括内限水坝墙和外坝墙,内限水坝墙与外坝墙平行设置,内限水坝墙与外坝墙之间为渠道,渠道高程低于本段河床最低水位,外坝墙下游端部设有外坝墙限水边墩,外坝墙限水边墩上设有沉沙排洪口道,外坝墙限水边墩外侧设有溢流调容断面护坦,沉沙排洪口道外侧设有沉沙排洪口道重力护坦,沉沙排洪口道下游处设有渠道闸片,渠道闸片下游方的内限水坝墙上设有供水口道,供水口道内侧设有供水口 道牵拉式护坦,供水口道下游方设有出水口道,出水口道处设有左右拉动闸板。The invention adopts the following technical solutions: an intensive flood irrigation channel, including an inner limited dam wall and an outer dam wall, the inner limited dam wall and the outer dam wall are arranged in parallel, and the inner limit dam wall and the outer dam wall are channels, channels The elevation is lower than the lowest water level of the riverbed in this section, and the downstream end of the outer dam wall is provided with a water-retaining pier of the outer dam wall. The water-retaining pier of the outer dam wall is provided with a sediment discharge port, and the outer dam wall is limited to the outer side of the water-side pier. There is an overflow and volume adjustment section, and there is a gravitational protection channel on the outside of the sediment discharge channel. A channel gate is provided at the downstream of the sediment discharge channel, and the channel is downstream of the channel. There is a water supply channel on the wall of the limited dam. There is a water supply port on the inner side of the water supply channel, and a water outlet is provided on the downstream of the water supply channel. The water outlet is provided with left and right pull gates.
进一步的,外坝墙上游端的顶部高程高于下游端的顶部高程。Further, the top elevation of the swim end of the outer dam wall is higher than the top elevation of the downstream end.
进一步的,出水口道的宽度小于渠道的宽度。Further, the width of the outlet channel is smaller than the width of the channel.
进一步的,渠道的内限水坝墙一侧高程高于外坝墙一侧高程。Further, the elevation of the inner dam wall of the channel is higher than the elevation of the side of the outer dam wall.
进一步的,沉沙排洪口道的宽度与渠道的宽度相同,沉沙排洪口道(4)的高程低于渠道底部高程。Further, the width of the sediment discharge channel is the same as the width of the channel, and the elevation of the sediment discharge channel (4) is lower than the elevation of the bottom of the channel.
进一步的,供水口道上设有过滤片。Further, a filter sheet is provided on the water supply channel.
与现有技术相比,本发明的集约式洪灌渠道技术针对纵向渠道取水口需与河道中浆砌拦洪滚水坝配套所存在的种种缺陷,改变为纵向渠道直接取水,从而省略了固定滚水坝,以不影响河道安全通洪。该渠道把优先取水、自动溢流调容、水流自动冲沙、沉沙排洪、过滤排泄浮游杂物和草籽、自流供水、吞吐自如和安全防洪等八项功能集渠道用于一身。工程材料能够替代和就地取材及加设抗光蚀和抗水沙冲刷摩擦的防护层。该渠道亦可加大供水量,配套应用于洪淤工程的中小流量取水用洪。也可横跨支流河道,同步取用或单独取用主干河道及支流河道中的洪水。也可与平川地区的旱地想配套,解决洪灌供水问题。所以,能把河道中的洪水、冰雪水和常流水都转变成农业用水,并且不需要配备提水的机电动力设备和机房泵站,一律自流、清洁和低成本用洪水。Compared with the prior art, the intensive flood irrigation channel technology of the present invention is directed to the various defects existing in the vertical channel water intake port and the river channel slurry-blocking dam, and is changed to the vertical channel to directly take water, thereby omitting the fixed roll. The dam does not affect the safe flooding of the river. The channel uses eight functions of priority water intake, automatic overflow conditioning, automatic sand washing, sediment discharge, filtration and drainage of floating debris and grass seeds, self-flowing water supply, free handling and safe flood control. Engineering materials can replace and locally extract materials and add a protective layer that resists light and sand. The channel can also increase the amount of water supplied, and it can be used in the flood control of small and medium-flow water in the flood control project. Floods in the main and tributary channels can also be accessed simultaneously or separately from the tributary channels. It can also be used in conjunction with the dry land in the Hirakawa area to solve the problem of flood irrigation and water supply. Therefore, it is possible to convert floods, ice and snow, and constant water in the river into agricultural water, and do not need electromechanical power equipment and computer room pumping stations equipped with water lifting, all of which are self-flowing, clean and low-cost flooding.
附图说明DRAWINGS
图1为本发明结构示意图;Figure 1 is a schematic structural view of the present invention;
图中1-内限水坝墙,2-外坝墙限水边墩,3-外坝墙,4-沉沙排洪口道,5-供水口道,6-出水口道,7-左右拉动闸板,8-沉沙排洪口道重力护坦,9-出水口道 重力护坦,10-供水口道牵拉式护坦,11-渠道闸片,12-渠道,13-溢流调容断面护坦。In the figure, 1 - inner limit dam wall, 2 - outer dam wall water limit pier, 3 - outer dam wall, 4 - sediment discharge port, 5 - water supply channel, 6 - outlet channel, 7 - pull Gate, 8-sand flood discharge channel gravity protector, 9-outlet channel gravity protector, 10-water supply channel pull-type protector, 11-channel brake, 12-channel, 13-overflow The volume of the section is protected.
具体实施方式Detailed ways
如图1所示,一种集约式洪灌渠道,包括内限水坝墙1和外坝墙3,内限水坝墙1与外坝墙3平行设置,内限水坝墙1与外坝墙3之间为渠道12,渠道12高程低于本段河床最低水位,外坝墙3下游端部设有外坝墙限水边墩2,外坝墙限水边墩2上设有沉沙排洪口道4,外坝墙限水边墩2外侧设有溢流调容断面护坦13,沉沙排洪口道4外侧设有沉沙排洪口道重力护坦8,沉沙排洪口道4下游处设有渠道闸片11,渠道闸片11下游方的内限水坝墙1上设有供水口道5,供水口道5内侧设有供水口道牵拉式护坦10,供水口道5下游方设有出水口道6,出水口道6处设有左右拉动闸板7。As shown in Fig. 1, an intensive flood irrigation channel includes an inner dam wall 1 and an outer dam wall 3, and the inner dam wall 1 and the outer dam wall 3 are arranged in parallel, and the inner dam wall 1 and the outer dam wall 3 are The channel is channel 12, the channel 12 elevation is lower than the lowest water level of the river bed, the outer dam wall 3 is provided with the outer dam wall water-retaining pier 2, and the outer dam wall water-retaining pier 2 is provided with the sedimentation port. Road 4, the outer dam wall is limited to the outer side of the water-retaining pier 2, and there is an overflow adjustment section, the abundance 13 is provided. The outer side of the sedimentation and discharge channel 4 is provided with a sedimentation and drainage channel gravity protection 8 and a sediment discharge channel. 4 There is a channel gate 11 at the downstream, and a water supply channel 5 is provided on the inner dam wall 1 of the downstream of the channel gate 11. The water supply channel 5 is provided with a water supply port pulling type amu 10 and a water supply channel. 5 The downstream side is provided with a water outlet channel 6, and the water outlet channel 6 is provided with a left and right pulling gate 7.
外坝墙3上游端的顶部高程高于下游端的顶部高程。即外坝墙3上游端的顶部高程高于渠道底部40厘米,而外坝墙3下游端的顶部高程高于渠道底部30厘米。The top elevation of the upstream end of the outer dam wall 3 is higher than the top elevation of the downstream end. That is, the top elevation of the upstream end of the outer dam wall 3 is 40 cm higher than the bottom of the channel, and the top elevation of the downstream end of the outer dam wall 3 is 30 cm higher than the bottom of the channel.
出水口道6的宽度小于渠道12的宽度。一些洪水中的垃圾不会进入供水口道5而从出水口道6排出。The width of the outlet 6 is less than the width of the channel 12. Some of the garbage in the flood does not enter the water supply channel 5 and is discharged from the water outlet channel 6.
渠道12的内限水坝墙1一侧高程高于外坝墙3一侧高程。坡度为1:0.1,迫使进入渠道中的粗沙石头优先沿着外坝墙一侧的渠道前进,被后续洪水推入沉沙排洪口道中。The inner elevation of the inner dam wall 1 of the channel 12 is higher than the elevation of the side of the outer dam wall 3. The slope is 1:0.1, forcing the coarse sand stones entering the channel to advance along the channel on one side of the outer dam wall and being pushed into the sediment discharge channel by subsequent floods.
沉沙排洪口道4的宽度与渠道12的宽度相同,沉沙排洪口道4的高程低于渠道12底部高程。供水口道5上设有过滤片。过滤排泄洪水中的浮游杂物和草籽。The width of the sediment discharge channel 4 is the same as the width of the channel 12, and the elevation of the sedimentation channel 4 is lower than the elevation of the bottom of the channel 12. A filter plate is provided on the water supply passage 5. Filters the floating debris and grass seeds in the flood.
本发明紧靠河槽一侧地塄和坝墙构建,供水口置于所灌溉农田的制高点,以此为基准,向上方延伸,并以本段河道的纵坡比降数值为参考对比依据,使渠道底部的纵坡达100:1,找到取水口的应建地址,再加上渠道取水口低于本段河道最低点或常流水最低水位线30厘米。即渠道内坝墙为限水坝墙,顶部不被河槽最大洪水淹没,其坡度小于渠道底部的坡度,外坝墙为溢流调容坝墙,渠道宽度一般为1米。The invention is constructed close to the mantle and the dam wall on one side of the river channel, and the water supply port is placed at the commanding height of the irrigated farmland, and is extended upward according to the reference, and the numerical value of the longitudinal slope of the river channel is used as a reference for comparison. The vertical slope at the bottom of the channel reaches 100:1, and the address of the water intake should be found. The channel intake is lower than the lowest point of the channel or the minimum water level of the normal water is 30 cm. That is, the dam wall in the channel is a limited dam wall, the top is not flooded by the maximum flood of the river channel, the slope is smaller than the slope at the bottom of the channel, and the outer dam wall is an overflow regulating dam wall, and the channel width is generally 1 meter.
1.优选取水:即渠道取水口底部低于本段河床最低点或常流水最低水位线30厘米,使河道水流优先进入该渠道中。1. It is preferred to take water: the bottom of the channel water intake is lower than the lowest point of the river bed or the minimum water level of the normal water is 30 cm, so that the river water flow preferentially enters the channel.
2.自动溢流调容:即渠道取水口外坝墙端头的顶部高于渠道底部40厘米,以此为基准,并以水平线向下方延伸,构成溢流泄水断面,溢流断面截止点下行方一小段外坝墙的坝顶与内坝墙坝顶持平,作为溢流断面的限水边墩。溢流泄水断面跌水部位的河床上构建重力式片状并串自动沉降护坦,宽为2米以上,既作为跌水护坦,又兼顾渠道防洪护坦。当河道中遇到特大洪水通行时,将相继淹没外坝墙溢流断面墙顶,受渠道宽度的限制,进入渠道的过量洪水将从该断面全线均匀排入河道中。2. Automatic overflow capacity adjustment: the top of the outer dam wall end of the channel water intake is 40 cm higher than the bottom of the channel. Based on this, it extends downwards along the horizontal line to form an overflow drainage section, and the overflow section is cut off. The dam crest of a small section of the outer dam wall of the square is level with the dam crest of the inner dam wall as the water-retaining pier of the overflow section. The river bed on the overflow part of the overflow discharge section is constructed with a gravity-like sheet and a series of automatic settlement aprons, which are more than 2 meters wide, both as a water-falling aquarium and a channel flood control. When a large flood is encountered in the river, the top of the overflow dam wall of the outer dam wall will be submerged. Due to the limitation of the channel width, excessive floods entering the channel will be evenly discharged into the channel from the entire section.
3.水流自动冲沙清渠:即渠道底部用混凝土打底,为纵横双向坡度,其横向坡度为内高外低的直线坡度,坡度为渠道宽度的1:0.1,使进入渠道中的粗沙石头优先沿着外坝墙一侧的渠底运行,被后续洪水顺利推入沉沙排洪口道中。3. The water flow automatically flushes the clear channel: the bottom of the channel is made of concrete, which is the vertical and horizontal two-way slope. The lateral slope is the slope of the inner high and the low, and the slope is 1:0.1 of the channel width, so that the coarse sand entering the channel The stone runs along the bottom of the side of the outer dam wall, and is smoothly pushed into the sediment discharge channel by subsequent floods.
4.沉沙排洪:即在距离外坝墙溢流泄水断面截止点错下2米处的限水边墩坝墙上留沉沙排洪口道,宽度与渠道宽度相等,口道与其上行方外墙的内夹角呈45°,底部低于渠道底部20厘米,亦为纵横双向坡度,使渠道中的随洪石头粗沙跌落其中,被后续洪水推入河道中所建造的重力式片状并串自动沉降护坦 面部及河道中。口道两侧的坝墙上开有垂向槽口,供同一块闸板置换使用。不予用洪水时,使日常进入渠道中的水流从该口道排入河道中。4. Sediment discharge: that is, the sediment discharge port on the wall of the water-restricted pier with a distance of 2 meters from the cut-off point of the overflow dam section of the outer dam wall, the width is equal to the width of the channel, and the channel is The inner angle of the outer wall of the upper side is 45°, and the bottom is 20 cm lower than the bottom of the channel. It is also a vertical and horizontal two-way slope, which causes the heavy sand in the channel to fall into the channel and is pushed into the river by the subsequent flood. The flakes and the strings are automatically settled in the face and the river. Vertical gullies are formed on the dam walls on both sides of the mouth for replacement of the same ram. When no flood is used, the water flowing into the channel from the daily channel is discharged into the channel from the channel.
5.自流供水:即在距离沉沙排洪口道下行方2米处的内坝墙上设供水口道,宽度与渠道宽度相等,使水流从该口道进入农田,也可在该口道下行方2米处的内坝墙上再增加一个供水口,以满足供水需要。5. Self-flowing water supply: that is, a water supply channel is provided on the inner dam wall 2 meters away from the sedimentation discharge channel, and the width is equal to the width of the channel, so that the water flow enters the farmland from the mouthway, and the channel can also be used. A water supply port is added to the inner dam wall at 2 meters downstream to meet the water supply needs.
6.过滤排泄随洪浮游杂物和草籽:即在渠道供水口外坝墙的内侧固定安装过滤片,过滤眼的目数能够滤住草籽,不进入农田,过滤片可自由拆卸和保存待用。渠道末端出水口的宽度收缩为30厘米,并通向河槽中,其外侧设有一个能够左右拉动的和具有机械性能的人工操作闸片,使渠道中的残留沉沙和浮游杂物从该口道中随机排入河道中,并能限制水流排泄。6. Filtration and drainage with flooding debris and grass seeds: that is, the filter plate is fixedly installed on the inner side of the dam wall outside the channel water supply port. The mesh of the filtering eyes can filter the grass seeds, and does not enter the farmland, the filter sheets can be freely disassembled and preserved. use. The width of the outlet at the end of the channel shrinks to 30 cm and leads to the channel. The outside is provided with a manually operated brake pad that can be pulled left and right and has mechanical properties, so that the residual sediment and floating debris in the channel are from the mouth. The road is randomly discharged into the river and can restrict the discharge of water.
7.工程材料:渠道一般采用石料浆砌。无石料、水洗砂和水源的施工区域,可让厂家用塑料特制成外形如砖头状的容器构件,内装沙土而替代石料,各块用防水胶粘合,渠道底部用塑钢板材焊接起来。7. Engineering materials: The channels are generally made of stone slurry. The construction area without stone, washed sand and water source allows the manufacturer to use plastics to make container parts with the shape of bricks, sand and sand instead of stone, each piece is glued with waterproof glue, and the bottom of the channel is welded with plastic steel plate.
8.吞吐自如:即该渠道既可取用河道中的微量洪水、冰雪水和常流水,又可通过大断面溢流调容,与河道中最大的洪水利用相适应。8. Freezing and swallowing: that is, the channel can use the micro-flood, ice-cold water and constant-flow water in the river channel, and can be adjusted by large-section overflow to adapt to the largest flood utilization in the river.
9.渠道配套应用于格堰洪淤和农田土壤改良加厚洪淤工程的取洪供水:即把渠道内坝墙的供水口扩大,待土地淤成后,再补建坝墙,也可适当加大渠道宽度。9. The channel is applied to the water supply and drainage of the sloping flood and silt and farmland soil improvement thickening and flooding project: the water supply port of the dam wall in the channel is enlarged, and after the land is silted, the dam wall can be rebuilt. Increase the channel width.
10.渠道横跨支流河道而同步取用主干河道和支流河道供水的应用:即把渠道溢流调容断面的一段坝墙延长,使延长的这段内外坝墙的顶部与支流河道的河床持平,内坝墙两侧加限水边墩,使支流河道洪水从边墩之间的墙顶通过。上行方边墩错上位置的外坝墙上加设一个沉沙排洪口道和闸槽闸板,使进入渠 道的主干河道的洪水能够从该口道单独排入河道中。10. The application of the channel across the tributary channel and the simultaneous use of the main river channel and the tributary channel water supply: the extension of a section of the dam wall of the channel overflow diversion section, so that the top of the extended inner and outer dam wall is level with the river bed of the tributary channel Water-side piers are added to both sides of the inner dam wall to allow the tributary channel flood to pass from the top of the wall between the piers. A silt discharge channel and a gate sluice are added to the outer dam wall of the upper side of the upper side pier so that the flood of the main channel entering the channel can be separately discharged into the channel from the channel.

Claims (6)

  1. 一种集约式洪灌渠道,其特征在于:包括内限水坝墙(1)和外坝墙(3),内限水坝墙(1)与外坝墙(3)平行设置,内限水坝墙(1)与外坝墙(3)之间为渠道(12),渠道(12)高程低于本段河床最低水位,外坝墙(3)下游端部设有外坝墙限水边墩(2),外坝墙限水边墩(2)上设有沉沙排洪口道(4),外坝墙限水边墩(2)外侧设有溢流调容断面护坦(13),沉沙排洪口道(4)外侧设有沉沙排洪口道重力护坦(8),沉沙排洪口道(4)下游处设有渠道闸片(11),渠道闸片(11)下游方的内限水坝墙(1)上设有供水口道(5),供水口道(5)内侧设有供水口道牵拉式护坦(10),供水口道(5)下游方设有出水口道(6),出水口道(6)处设有左右拉动闸板(7)。An intensive flood irrigation channel characterized by comprising an inner dam wall (1) and an outer dam wall (3), an inner dam wall (1) and an outer dam wall (3) being arranged in parallel, and an inner dam wall ( 1) The channel (12) is between the outer dam wall (3), the channel (12) elevation is lower than the lowest water level of the riverbed, and the outer dam wall (3) is provided with the outer dam wall water-limiting pier (2). ), the water-retaining pier (2) of the outer dam wall is provided with a sediment discharge channel (4), and the outer side of the water-retaining pier (2) of the outer dam wall is provided with an overflow adjustment section (13), Shen On the outer side of the sand discharge Hongkou Road (4), there is a gravity protection channel (8) for the sediment discharge channel, and a channel gate (11) for the downstream of the sediment discharge channel (4), the channel gate (11) The downstream dam wall (1) is provided with a water supply channel (5), and the water supply channel (5) is provided with a water supply port pulling type apron (10), and the water supply channel (5) is downstream. There is a water outlet (6), and the water outlet (6) is provided with a left and right pull gate (7).
  2. 根据权利要求1所述的集约式洪灌渠道,其特征在于:所述的外坝墙(3)上游端的顶部高程高于下游端的顶部高程。The intensive flood irrigation channel according to claim 1, characterized in that the top elevation of the upstream end of the outer dam wall (3) is higher than the top elevation of the downstream end.
  3. 根据权利要求1或2所述的集约式洪灌渠道,其特征在于:所述的出水口道(6)的宽度小于渠道(12)的宽度。The intensive flood irrigation channel according to claim 1 or 2, characterized in that the width of the water outlet channel (6) is smaller than the width of the channel (12).
  4. 根据权利要求3所述的集约式洪灌渠道,其特征在于:所述的渠道(12)的内限水坝墙(1)一侧高程高于外坝墙(3)一侧高程。The intensive flood irrigation channel according to claim 3, characterized in that: the inner dam wall (1) of the channel (12) has an elevation higher than that of the outer dam wall (3).
  5. 根据权利要求4所述的集约式洪灌渠道,其特征在于:所述的沉沙排洪口道(4)的宽度与渠道(12)的宽度相同,沉沙排洪口道(4)的高程低于渠道(12)底部高程。The intensive flood irrigation channel according to claim 4, characterized in that: the width of the sediment discharge channel (4) is the same as the width of the channel (12), and the sedimentation channel (4) of the sedimentation The elevation is lower than the bottom elevation of the channel (12).
  6. 根据权利要求5所述的集约式洪灌渠道,其特征在于:所述的供水口道(5)上设有过滤片。The intensive flood irrigation channel according to claim 5, characterized in that the water supply channel (5) is provided with a filter.
PCT/CN2018/117127 2017-11-25 2018-11-23 Intensive flood irrigation channel WO2019101158A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201711196514.9A CN108086264B (en) 2017-11-25 2017-11-25 Intensive flooded channel
CN201711196514.9 2017-11-25

Publications (1)

Publication Number Publication Date
WO2019101158A1 true WO2019101158A1 (en) 2019-05-31

Family

ID=62172986

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2018/117127 WO2019101158A1 (en) 2017-11-25 2018-11-23 Intensive flood irrigation channel

Country Status (2)

Country Link
CN (1) CN108086264B (en)
WO (1) WO2019101158A1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108086264B (en) * 2017-11-25 2019-09-06 党海愚 Intensive flooded channel

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009209545A (en) * 2008-03-03 2009-09-17 Tohoku Sekizai Block Kk Partially-porous product facilitating habitat environment of freshwater fishery product
KR101676378B1 (en) * 2015-08-25 2016-11-29 김종국 Water flow system
CN206052667U (en) * 2016-08-10 2017-03-29 云南农业大学 A kind of environmental trapezoidal metal channel of straight wall
CN107366270A (en) * 2017-06-26 2017-11-21 安徽盛美金属科技有限公司 Water channel engineering for field irrigation
CN108086264A (en) * 2017-11-25 2018-05-29 党海愚 Intensive flooded channel

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005282327A (en) * 2004-03-26 2005-10-13 Tsutomu Yamada Retaining-wall u-shaped ditch
CN100570069C (en) * 2008-04-28 2009-12-16 钮本良 Rocky broad-river reach, trench, beach and reservoir exploitation improvement method
CN204898614U (en) * 2015-07-02 2015-12-23 中国电建集团成都勘测设计研究院有限公司 A flow blocking dam for protection of mud -rock flow river course
CN205276231U (en) * 2015-12-11 2016-06-01 攀枝花晶能太阳能科技有限公司 Be applied to rivers lifting irrigation's husky water intake device of row

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009209545A (en) * 2008-03-03 2009-09-17 Tohoku Sekizai Block Kk Partially-porous product facilitating habitat environment of freshwater fishery product
KR101676378B1 (en) * 2015-08-25 2016-11-29 김종국 Water flow system
CN206052667U (en) * 2016-08-10 2017-03-29 云南农业大学 A kind of environmental trapezoidal metal channel of straight wall
CN107366270A (en) * 2017-06-26 2017-11-21 安徽盛美金属科技有限公司 Water channel engineering for field irrigation
CN108086264A (en) * 2017-11-25 2018-05-29 党海愚 Intensive flooded channel

Also Published As

Publication number Publication date
CN108086264A (en) 2018-05-29
CN108086264B (en) 2019-09-06

Similar Documents

Publication Publication Date Title
CN101260661B (en) Automatic irrigation and drainage method and system for agricultural land
CN108029517B (en) Direct-drainage drip irrigation system for channel of yellow-drainage irrigation area and operation method
CN210684607U (en) Protective structure of hydraulic and hydroelectric engineering side slope
WO2022217749A1 (en) Rainwater filtering garden
CN104963322A (en) Hydraulic junction facility
CN106836439B (en) Emergency self-opening device
CN102926362B (en) Pollution control and emission reduction method for farmland drainage
CN207003629U (en) A kind of sewage treatment shunting well
CN108625453A (en) Skyscraper sponge City complex system
WO2019101158A1 (en) Intensive flood irrigation channel
CN106049348A (en) Retaining wall structure for sponge city construction
CN112081063A (en) Go into sea mouth and fall siphon system
CN214460826U (en) Bottom grid barrier and upstream surface seepage flow perforated pipe water collecting gallery water taking system
CN212026122U (en) Water conservancy bank protection
CN211571912U (en) Urban rainwater collection water level control system
CN210122703U (en) Constructed in wetland facility is strained to essence of river course riverbed
CN207453073U (en) One kind automatically controls drainage pumping stations
CN214832349U (en) Water quantity control device for mountain pond
CN205024819U (en) Novel confluence channel vatch basin
CN110565781A (en) Gutter inlet transformation method
CN209874009U (en) Grass planting ditch system based on sponge city
CN212689073U (en) Green energy-saving building rainwater collecting and processing system
CN206034601U (en) A rainwater collection system for strand area
CN110714436A (en) Retaining system of check dam
CN217458994U (en) Unpowered riverbed type wetland purification facility

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 18881314

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 18881314

Country of ref document: EP

Kind code of ref document: A1