WO2017075742A1 - Device and process for receiving slurry-balanced pipe jacking machine in high-water-pressure condition - Google Patents

Device and process for receiving slurry-balanced pipe jacking machine in high-water-pressure condition Download PDF

Info

Publication number
WO2017075742A1
WO2017075742A1 PCT/CN2015/000884 CN2015000884W WO2017075742A1 WO 2017075742 A1 WO2017075742 A1 WO 2017075742A1 CN 2015000884 W CN2015000884 W CN 2015000884W WO 2017075742 A1 WO2017075742 A1 WO 2017075742A1
Authority
WO
WIPO (PCT)
Prior art keywords
pipe
water
grouting
receiving
compartment
Prior art date
Application number
PCT/CN2015/000884
Other languages
French (fr)
Chinese (zh)
Inventor
彭仕国
韩利民
潘建立
张斌梁
高海东
黄欣
刘应亮
马胜利
罗兴虎
宫大辉
Original Assignee
中铁十八局集团有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中铁十八局集团有限公司 filed Critical 中铁十八局集团有限公司
Priority to JP2016573991A priority Critical patent/JP6397940B2/en
Publication of WO2017075742A1 publication Critical patent/WO2017075742A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries

Abstract

A device and a process for receiving a slurry-balanced pipe jacking machine in a high-water-pressure condition. As to the device and the process, a steel brush is used as a first water-stopping curtain of a pressurized receiving cabin, to make it have a sufficient pressure-bearing capacity to bear the water and earth pressure on an outer wall of a pipe joint, preventing the soil erosion; rubber is used for a second water-stopping curtain (23) to stop water; and then inject Marithan between the two water-stopping curtains to close the water-system communication between the pipe jacking machine and the formation, and inject cement paste between the outer wall of the pipe joint and an orifice-pipe to achieve clogging. Accordingly, there is no water leakage when the cabin is opened, and the operation of receiving the pipe jacking machine is successfully completed. Said device and process can effectively prevent water-permeating and water-leakage accidents during the operation of the slurry-balanced pipe jacking machine, improving the security of the process implementation.

Description

高水条件下泥水平衡顶管机接收装置及工艺Mud water balance pipe jacking device receiving device and process under high water condition 技术领域Technical field
本发明涉及高水条件下泥水平衡顶管机接收装置及工艺,属于泥水平衡顶管技术领域。The invention relates to a mud water balance pipe jack receiving device and a process under high water conditions, and belongs to the technical field of mud water balance pipe jacking.
背景技术Background technique
泥水平衡顶管机出洞接收是顶管施工中重大风险点之一,尤其在地下水丰富,土质软弱,水压大的复杂地质地层。顶管机进入有压接收舱后,需要开舱处理机头,拆除管线。在开舱过程中,由于地下水丰富且压力大,管节外壁土体易被冲刷出,出现涌水、涌泥,使得地层中水土流失,影响顶管曲线线型以及管幕施工,水土流失量过大进而可能造成地表塌陷或裂缝等安全隐患。The acceptance of the mud-water balance pipe jacking machine is one of the major risk points in the pipe jacking construction, especially in complex geological strata with abundant groundwater, weak soil and large water pressure. After the pipe jacking machine enters the pressurized receiving compartment, it is necessary to open the handling head and remove the pipeline. During the process of opening the cabin, due to the rich groundwater and high pressure, the soil outside the pipe section is easily washed out, and there is water and mud, which causes water and soil loss in the stratum, affecting the curve of the pipe jacking and the construction of the pipe curtain. Large and further may cause safety hazards such as surface collapse or cracks.
发明内容Summary of the invention
此项发明是采用钢刷作为有压接收舱的第一道止水帘幕,使其有足够的承压能力承受管节外壁的水土压力,防止水土流失;第二道采用橡胶止水帘幕止水;然后在两道止水帘幕间注马丽散封闭顶管机与地层的水系联通,管节外壁与孔口管间注水泥浆封堵,从而达到开舱无漏水,顺利完成顶管机接收工作。The invention adopts a steel brush as the first water stop curtain of the pressurized receiving compartment, so that it has sufficient pressure bearing capacity to withstand the water and earth pressure of the outer wall of the pipe joint to prevent soil erosion; the second adopts a rubber water curtain Stop the water; then, in the two water curtain curtains, the Ma Lisan closed pipe jacking machine is connected with the water system of the stratum, and the cement pipe is sealed between the outer wall of the pipe joint and the orifice pipe, so that no water leakage is achieved in the opening, and the pipe jacking is successfully completed. The machine receives the work.
为实现上述目的,本发明采用的技术方案为高水条件下泥水平衡顶管机接收装置,该装置包括顶管机机头4、接收孔口管6、前舱7、中舱8、尾舱9、泄压管10、泄压管阀门11、接收舱基座12、顶管机接收平台13、泥浆池14、观察窗15、井字形肋板16、螺栓孔17、排浆孔18、前舱加强肋板19、中舱加强肋板20、预留注浆管21、钢刷止水帘幕22、橡胶止水帘幕23;In order to achieve the above object, the technical solution adopted by the present invention is a mud-water balance pipe jacking machine receiving device under high water conditions, which comprises a pipe jacking machine head 4, a receiving orifice pipe 6, a front tank 7, a middle tank 8, and a tail tank. 9. Pressure relief pipe 10, pressure relief pipe valve 11, receiving compartment base 12, pipe jacking machine receiving platform 13, mud pool 14, observation window 15, well-shaped rib 16, bolt hole 17, slurry hole 18, front Compartment reinforcing rib 19, middle cabin reinforcing rib 20, reserved grouting pipe 21, steel brush curtain 22, rubber water curtain 23;
前舱7、中舱8、尾舱9依次连接组成舱体部分,舱体部分安装在接收舱基座12上;顶管机机头4设置在舱体部分前端且与管幕管节5接触;The front compartment 7, the middle compartment 8, and the tail compartment 9 are sequentially connected to form a cabin portion, and the cabin portion is mounted on the receiving compartment base 12; the pipe jacking machine head 4 is disposed at the front end of the cabin portion and is in contact with the tube curtain section 5 ;
接收舱基座12安装在顶管机接收平台13上;前舱7与接收孔口管6通过 螺栓连接固定;顶管机接收平台13设在管幕施工工作井1侧壁与钢筋混凝土地下连续墙2之间;泄压管10一端与尾舱9连接,且泄压管10上设置有泄压管阀门11,泄压管10另一端与泥浆池14连接;尾舱9的端面上设有井字形肋板16,尾舱9的端面顶部设有观察窗15,尾舱9的端面底部设有排浆孔18;尾舱9的端面上均匀对称设有螺栓孔17;前舱7的外围焊接有前舱加强肋板19;中舱8的外围焊接有中舱加强肋板20;接收孔口管6与前舱7之间的舱体部分上设有钢刷止水帘幕22;前舱7与中舱8之间的舱体部分上设有橡胶止水帘幕23;预留注浆管21设置在接收孔口管6与钢刷止水帘幕22之间的舱体部分以及钢刷止水帘幕22与橡胶止水帘幕23之间的舱体部分上。The receiving compartment base 12 is mounted on the jacking machine receiving platform 13; the front compartment 7 and the receiving orifice tube 6 are passed The bolting connection is fixed; the pipe jacking machine receiving platform 13 is disposed between the side wall of the pipe curtain working working well 1 and the reinforced concrete underground continuous wall 2; one end of the pressure releasing pipe 10 is connected with the tail tank 9, and the pressure releasing pipe 10 is provided with a drain The pressure tube valve 11 and the other end of the pressure relief tube 10 are connected to the mud pool 14; the end surface of the tail chamber 9 is provided with a well-shaped rib 16 , and the end surface of the tail chamber 9 is provided with an observation window 15 , and the end surface of the tail chamber 9 is provided at the bottom end. There is a discharge hole 18; a bolt hole 17 is uniformly symmetrically arranged on the end surface of the tail chamber 9; a front compartment reinforcement rib 19 is welded to the periphery of the front compartment 7; a middle compartment reinforcement rib 20 is welded to the periphery of the middle compartment 8; A steel brush curtain 22 is disposed on the cabin portion between the mouth tube 6 and the front cabin 7; a rubber water curtain 22 is disposed on the cabin portion between the front cabin 7 and the middle cabin 8; The slurry tube 21 is disposed on a cabin portion between the receiving orifice tube 6 and the steel brush curtain 22 and a portion of the body between the steel brush curtain 22 and the rubber water curtain 22.
高水条件下泥水平衡顶管机接收工艺,该工艺流程如下,The process of receiving the mud-water balance pipe jacking machine under high water conditions, the process flow is as follows,
S1在顶管机接收平台13上按前舱7、中舱8、尾舱9顺利拼装完成后与接收孔口管6通过螺栓连接,如图1所示。S1 is connected to the receiving orifice tube 6 by bolting on the pipe jacking machine receiving platform 13 according to the front tank 7, the middle tank 8, and the tail tank 9, as shown in Fig. 1.
S2从泄压管10向接收舱注满清水,检查接收舱密闭性,渗漏水处及时加紧螺栓、更换接合橡胶垫等措施进行修补,合格后排空接收舱,打开泄压管阀门11,注满泥水平衡泥浆。S2 fills the receiving tank from the pressure relief pipe 10 to the receiving compartment, checks the tightness of the receiving compartment, tightens the bolts in time, tightens the bolts in time, replaces the rubber pad, and so on. After the qualified, the receiving compartment is emptied, and the pressure relief pipe valve 11 is opened. Fill the mud with water to balance the mud.
S3顶管机4接收前根据测量结果调整机头姿态,使顶管机4能以良好的姿态到达接收舱。Before the S3 pipe jacking machine 4 receives the head posture according to the measurement result, the pipe jacking machine 4 can reach the receiving cabin in a good posture.
S4顶管机4钻进速度控制在1cm/min以内,减速破除洞门素混凝土墙3开始进入接收舱,关闭泄压管阀门11。The drilling speed of the S4 pipe jacking machine 4 is controlled within 1cm/min, and the concrete wall 3 is decelerated to break into the concrete door, and the pressure relief pipe valve 11 is closed.
S5顶管机4整体进入接收舱到达指定位置,抽出舱内泥浆,冲洗泥浆管路,顶管机4停止操作。The S5 pipe jacking machine 4 enters the receiving compartment as a whole and reaches the designated position, extracts the mud in the tank, flushes the mud pipeline, and stops the pipe jacking machine 4.
S6从预留注浆管21往两道帘幕间注马丽散止水(预留注浆管布置在前舱正上、左下及右下三个位置,呈120度环向布置);注浆采用的是小型气动注浆机, 先注下侧预留注浆管,再注上部预留注浆管,注浆时注浆速度不宜过快,避免浆液流失,使马丽散与钢刷能充分结合形成整体,防止地层中的水土流失,封闭前舱7与中舱8的水系联通,如图3所示。S6 from the reserved grouting pipe 21 to the two curtains, Ma Li San stopped water (reserved grouting pipe is arranged in the front, the lower left and the lower right three positions, arranged in a circular direction of 120 degrees); The slurry is a small pneumatic grouting machine. Firstly, the lower side is reserved for the grouting pipe, and the upper part is reserved for the grouting pipe. When grouting, the grouting speed should not be too fast, avoiding the loss of the slurry, so that the Ma Li San and the steel brush can be fully combined to form a whole, preventing the formation. Soil erosion, the closed front compartment 7 is connected to the water system of the middle compartment 8, as shown in Figure 3.
S7待马丽散基本凝固后,检验止水效果。打开预留注浆管,用钢筋疏通注浆导管至舱内,无渗水即可开始进行接收孔口管注浆;若有渗水,对渗水部位补注马丽散。After the S7 is finally solidified, the water stop effect is checked. Open the reserved grouting pipe, use the steel bar to dredge the grouting pipe into the cabin, and start the grouting of the receiving orifice pipe without seepage; if there is water seepage, fill the water seepage part with Ma Lisan.
S8从接收孔口管6上的预留注浆管注水泥浆(预留注浆管布置在接收孔口管正上、左下及右下三个位置,呈120度环向布置);注浆时,采用的是液压注浆机,先注一侧预留注浆管,打开另一侧预留注浆管,待另一侧预留注浆管有浆液流出时关闭该注浆管,然后打开上部预留注浆管,待有浆液流出时关闭该预留注浆管;若注浆压力过大,换其他预留注浆管注浆,使浆液充满管节外壁与接收孔口管间的空隙,封闭前舱7、孔口管6与地层中水的联通。S8 grouts the cement slurry from the reserved grouting pipe on the receiving orifice pipe 6 (the reserved grouting pipe is arranged at the top, bottom left and bottom right positions of the receiving orifice pipe, and is arranged in a circular direction of 120 degrees); The hydraulic grouting machine is used. The grouting pipe is reserved on one side, and the grouting pipe is opened on the other side. When the grouting pipe on the other side is reserved, the grouting pipe is closed and then opened. The grouting pipe is reserved in the upper part, and the reserved grouting pipe is closed when the slurry flows out; if the grouting pressure is too large, the other grouting pipe is grouted, so that the slurry is filled between the outer wall of the pipe joint and the receiving orifice pipe. The gap, the closed front compartment 7, the orifice tube 6 and the water in the formation.
S9待水泥浆基本凝固后,检验注浆效果。打开预留注浆管,疏通注浆管至接收孔口管内,若无渗水即可进行开仓接收工作;若有渗水,对渗水部位进行补注水泥浆。After the S9 is substantially solidified, the grouting effect is checked. Open the reserved grouting pipe, unblock the grouting pipe into the receiving orifice pipe, if there is no water seepage, you can open the warehouse to receive the work; if there is water seepage, refill the seepage part with cement slurry.
S10注浆效果检验合格后,打开排浆孔18排除舱内的的泥浆,打开后盖直接查看舱内是否有漏水或渗水现象,无漏水时拆除中舱8及尾舱9的上半圆部分,清除舱内的泥浆、砂石,吊出顶管机4,随即拆除其下部半圆部分。After the S10 grouting effect is passed, the slurry hole 18 is opened to remove the mud in the tank, and the back cover is opened to directly check whether there is water leakage or water seepage in the tank. When there is no water leakage, the upper half of the middle tank 8 and the tail tank 9 are removed. Remove the mud and sand in the cabin, lift the pipe jacking machine 4, and then remove the lower semicircular portion.
S11在顶管机4后第一、二节管节5内的预留导丝管位置注双液浆止水,完全阻断接收孔口管6与地层中水的联通;注浆完成后即可开始管内管线的拆除工作。S11 in the first and second tube sections 5 after the pipe jacking machine 4, the position of the reserved guide wire tube is injected into the double liquid slurry to stop the water, completely blocking the communication between the receiving orifice tube 6 and the water in the formation; The removal of the pipeline inside the pipe can be started.
S12待双液浆凝固后,打开导丝管检查止水效果,有渗水部位进行补注;注浆效果满足要求时后,拆除前舱及过渡环,立即用钢板封堵管节5与接收孔口 管6之间的间隙,如图4所示。After the S12 is solidified, the guide wire tube is opened to check the water stop effect, and the water seepage part is filled; when the grouting effect meets the requirements, the front tank and the transition ring are removed, and the pipe joint 5 and the receiving hole are immediately blocked by the steel plate. mouth The gap between the tubes 6 is as shown in FIG.
S13管内管线全部拆除后,进行泥浆置换注浆,接收工作完成。After the S13 pipe is completely removed, the mud replacement grouting is carried out, and the receiving work is completed.
与现有技术相比,本发明可有效阻止泥水平衡顶管机工作过程的透水、漏水事故,大大提高了工艺实施的安全性。Compared with the prior art, the invention can effectively prevent the water leakage and water leakage accidents of the mud water balance pipe jacking machine working process, and greatly improve the safety of the process implementation.
附图说明DRAWINGS
图1是泥水平衡顶管机有压接收舱作业示意图。Figure 1 is a schematic view of the operation of the pressurized receiving compartment of the muddy water balance pipe jacking machine.
图2是泥水平衡顶管机有压接收舱尾舱后舱盖构造示意图。Figure 2 is a schematic view showing the structure of the rear hatch of the pressurized receiving compartment of the mud-water balance pipe jacking machine.
图3是泥水平衡顶管机有压接收舱前舱止水帘幕构造示意图。Fig. 3 is a schematic view showing the structure of the water curtain of the front compartment of the pressurized receiving tank of the mud-water balance pipe jacking machine.
图4是管壁与孔口管封堵钢板示意图。Figure 4 is a schematic view of the sealing plate of the pipe wall and the orifice pipe.
图中:1-管幕施工工作井,2-钢筋混凝土地下连续墙,3-素混凝土地下连续墙,4-顶管机机头,5-管幕管节,6-接收孔口管,7-前舱,8-中舱,9-尾舱,10-泄压管,11-泄压管阀门,12-接收舱基座,13-顶管机接收平台,14-泥浆池,15-观察窗,16-井字形肋板,17-螺栓孔,18-排浆孔,19-前舱加强肋板,20-中舱加强肋板,21-预留注浆管,22-钢刷止水帘幕,23-橡胶止水帘幕,24-封堵钢板。In the picture: 1-tube curtain construction working well, 2-reinforced concrete underground continuous wall, 3-primed concrete underground continuous wall, 4-pipe tube head, 5-tube curtain tube section, 6-receiving orifice tube, 7 - front compartment, 8-mid compartment, 9-tail compartment, 10-pressure relief pipe, 11-relief pipe valve, 12-receiving tank base, 13-pipe jacking platform, 14-mud pool, 15-observation Window, 16-well-shaped ribbed, 17-bolt hole, 18-slurry hole, 19-front compartment reinforced rib, 20-middle compartment reinforced rib, 21- reserved grouting tube, 22-steel brush Curtain, 23-rubber water curtain, 24-block steel plate.
具体实施方式detailed description
如图1-4所示,高水条件下泥水平衡顶管机接收装置,该装置包括顶管机机头4、接收孔口管6、前舱7、中舱8、尾舱9、泄压管10、泄压管阀门11、接收舱基座12、顶管机接收平台13、泥浆池14、观察窗15、井字形肋板16、螺栓孔17、排浆孔18、前舱加强肋板19、中舱加强肋板20、预留注浆管21、钢刷止水帘幕22、橡胶止水帘幕23;As shown in Figure 1-4, the mud-water balance pipe jacking machine receiving device under high water conditions includes a pipe jacking machine head 4, a receiving orifice pipe 6, a front tank 7, a middle tank 8, a tail tank 9, and a pressure relief. Tube 10, pressure relief pipe valve 11, receiving compartment base 12, pipe jacking machine receiving platform 13, mud pool 14, observation window 15, well-shaped rib 16, bolt hole 17, slurry hole 18, front compartment reinforcing rib 19. The mid-cabin reinforced rib 20, the reserved grouting pipe 21, the steel brush water curtain 22, the rubber water curtain 22;
前舱7、中舱8、尾舱9依次连接组成舱体部分,舱体部分安装在接收舱基座12上;顶管机机头4设置在舱体部分前端且与管幕管节5接触;The front compartment 7, the middle compartment 8, and the tail compartment 9 are sequentially connected to form a cabin portion, and the cabin portion is mounted on the receiving compartment base 12; the pipe jacking machine head 4 is disposed at the front end of the cabin portion and is in contact with the tube curtain section 5 ;
接收舱基座12安装在顶管机接收平台13上;前舱7与接收孔口管6通过 螺栓连接固定;顶管机接收平台13设在管幕施工工作井1侧壁与钢筋混凝土地下连续墙2之间;泄压管10一端与尾舱9连接,且泄压管10上设置有泄压管阀门11,泄压管10另一端与泥浆池14连接;尾舱9的端面上设有井字形肋板16,尾舱9的端面顶部设有观察窗15,尾舱9的端面底部设有排浆孔18;尾舱9的端面上均匀对称设有螺栓孔17;前舱7的外围焊接有前舱加强肋板19;中舱8的外围焊接有中舱加强肋板20;接收孔口管6与前舱7之间的舱体部分上设有钢刷止水帘幕22;前舱7与中舱8之间的舱体部分上设有橡胶止水帘幕23;预留注浆管21设置在接收孔口管6与钢刷止水帘幕22之间的舱体部分以及钢刷止水帘幕22与橡胶止水帘幕23之间的舱体部分上。The receiving compartment base 12 is mounted on the jacking machine receiving platform 13; the front compartment 7 and the receiving orifice tube 6 are passed The bolting connection is fixed; the pipe jacking machine receiving platform 13 is disposed between the side wall of the pipe curtain working working well 1 and the reinforced concrete underground continuous wall 2; one end of the pressure releasing pipe 10 is connected with the tail tank 9, and the pressure releasing pipe 10 is provided with a drain The pressure tube valve 11 and the other end of the pressure relief tube 10 are connected to the mud pool 14; the end surface of the tail chamber 9 is provided with a well-shaped rib 16 , and the end surface of the tail chamber 9 is provided with an observation window 15 , and the end surface of the tail chamber 9 is provided at the bottom end. There is a discharge hole 18; a bolt hole 17 is uniformly symmetrically arranged on the end surface of the tail chamber 9; a front compartment reinforcement rib 19 is welded to the periphery of the front compartment 7; a middle compartment reinforcement rib 20 is welded to the periphery of the middle compartment 8; A steel brush curtain 22 is disposed on the cabin portion between the mouth tube 6 and the front cabin 7; a rubber water curtain 22 is disposed on the cabin portion between the front cabin 7 and the middle cabin 8; The slurry tube 21 is disposed on a cabin portion between the receiving orifice tube 6 and the steel brush curtain 22 and a portion of the body between the steel brush curtain 22 and the rubber water curtain 22.
高水条件下泥水平衡顶管机接收工艺,该工艺流程如下,The process of receiving the mud-water balance pipe jacking machine under high water conditions, the process flow is as follows,
S1在顶管机接收平台13上按前舱7、中舱8、尾舱9顺利拼装完成后与接收孔口管6通过螺栓连接,如图1所示。S1 is connected to the receiving orifice tube 6 by bolting on the pipe jacking machine receiving platform 13 according to the front tank 7, the middle tank 8, and the tail tank 9, as shown in Fig. 1.
S2从泄压管10向接收舱注满清水,检查接收舱密闭性,渗漏水处及时加紧螺栓、更换接合橡胶垫等措施进行修补,合格后排空接收舱,打开泄压管阀门11,注满泥水平衡泥浆。S2 fills the receiving tank from the pressure relief pipe 10 to the receiving compartment, checks the tightness of the receiving compartment, tightens the bolts in time, tightens the bolts in time, replaces the rubber pad, and so on. After the qualified, the receiving compartment is emptied, and the pressure relief pipe valve 11 is opened. Fill the mud with water to balance the mud.
S3顶管机4接收前根据测量结果调整机头姿态,使顶管机4能以良好的姿态到达接收舱。Before the S3 pipe jacking machine 4 receives the head posture according to the measurement result, the pipe jacking machine 4 can reach the receiving cabin in a good posture.
S4顶管机4钻进速度控制在1cm/min以内,减速破除洞门素混凝土墙3开始进入接收舱,关闭泄压管阀门11。The drilling speed of the S4 pipe jacking machine 4 is controlled within 1cm/min, and the concrete wall 3 is decelerated to break into the concrete door, and the pressure relief pipe valve 11 is closed.
S5顶管机4整体进入接收舱到达指定位置,抽出舱内泥浆,冲洗泥浆管路,顶管机4停止操作。The S5 pipe jacking machine 4 enters the receiving compartment as a whole and reaches the designated position, extracts the mud in the tank, flushes the mud pipeline, and stops the pipe jacking machine 4.
S6从预留注浆管21往两道帘幕间注马丽散止水(预留注浆管布置在前舱正上、左下及右下三个位置,呈120度环向布置);注浆采用的是小型气动注浆机, 先注下侧预留注浆管,再注上部预留注浆管,注浆时注浆速度不宜过快,避免浆液流失,使马丽散与钢刷能充分结合形成整体,防止地层中的水土流失,封闭前舱7与中舱8的水系联通,如图3所示。S6 from the reserved grouting pipe 21 to the two curtains, Ma Li San stopped water (reserved grouting pipe is arranged in the front, the lower left and the lower right three positions, arranged in a circular direction of 120 degrees); The slurry is a small pneumatic grouting machine. Firstly, the lower side is reserved for the grouting pipe, and the upper part is reserved for the grouting pipe. When grouting, the grouting speed should not be too fast, avoiding the loss of the slurry, so that the Ma Li San and the steel brush can be fully combined to form a whole, preventing the formation. Soil erosion, the closed front compartment 7 is connected to the water system of the middle compartment 8, as shown in Figure 3.
S7待马丽散基本凝固后,检验止水效果。打开预留注浆管,用钢筋疏通注浆导管至舱内,无渗水即可开始进行接收孔口管注浆;若有渗水,对渗水部位补注马丽散。After the S7 is finally solidified, the water stop effect is checked. Open the reserved grouting pipe, use the steel bar to dredge the grouting pipe into the cabin, and start the grouting of the receiving orifice pipe without seepage; if there is water seepage, fill the water seepage part with Ma Lisan.
S8从接收孔口管6上的预留注浆管注水泥浆(预留注浆管布置在接收孔口管正上、左下及右下三个位置,呈120度环向布置);注浆时,采用的是液压注浆机,先注一侧预留注浆管,打开另一侧预留注浆管,待另一侧预留注浆管有浆液流出时关闭该注浆管,然后打开上部预留注浆管,待有浆液流出时关闭该预留注浆管;若注浆压力过大,换其他预留注浆管注浆,使浆液充满管节外壁与接收孔口管间的空隙,封闭前舱7、孔口管6与地层中水的联通。S8 grouts the cement slurry from the reserved grouting pipe on the receiving orifice pipe 6 (the reserved grouting pipe is arranged at the top, bottom left and bottom right positions of the receiving orifice pipe, and is arranged in a circular direction of 120 degrees); The hydraulic grouting machine is used. The grouting pipe is reserved on one side, and the grouting pipe is opened on the other side. When the grouting pipe on the other side is reserved, the grouting pipe is closed and then opened. The grouting pipe is reserved in the upper part, and the reserved grouting pipe is closed when the slurry flows out; if the grouting pressure is too large, the other grouting pipe is grouted, so that the slurry is filled between the outer wall of the pipe joint and the receiving orifice pipe. The gap, the closed front compartment 7, the orifice tube 6 and the water in the formation.
S9待水泥浆基本凝固后,检验注浆效果。打开预留注浆管,疏通注浆管至接收孔口管内,若无渗水即可进行开仓接收工作;若有渗水,对渗水部位进行补注水泥浆。After the S9 is substantially solidified, the grouting effect is checked. Open the reserved grouting pipe, unblock the grouting pipe into the receiving orifice pipe, if there is no water seepage, you can open the warehouse to receive the work; if there is water seepage, refill the seepage part with cement slurry.
S10注浆效果检验合格后,打开排浆孔18排除舱内的的泥浆,打开后盖直接查看舱内是否有漏水或渗水现象,无漏水时拆除中舱8及尾舱9的上半圆部分,清除舱内的泥浆、砂石,吊出顶管机4,随即拆除其下部半圆部分。After the S10 grouting effect is passed, the slurry hole 18 is opened to remove the mud in the tank, and the back cover is opened to directly check whether there is water leakage or water seepage in the tank. When there is no water leakage, the upper half of the middle tank 8 and the tail tank 9 are removed. Remove the mud and sand in the cabin, lift the pipe jacking machine 4, and then remove the lower semicircular portion.
S11在顶管机4后第一、二节管节5内的预留导丝管位置注双液浆止水,完全阻断接收孔口管6与地层中水的联通;注浆完成后即可开始管内管线的拆除工作。S11 in the first and second tube sections 5 after the pipe jacking machine 4, the position of the reserved guide wire tube is injected into the double liquid slurry to stop the water, completely blocking the communication between the receiving orifice tube 6 and the water in the formation; The removal of the pipeline inside the pipe can be started.
S12待双液浆凝固后,打开导丝管检查止水效果,有渗水部位进行补注;注浆效果满足要求时后,拆除前舱及过渡环,立即用钢板封堵管节5与接收孔口 管6之间的间隙,如图4所示。After the S12 is solidified, the guide wire tube is opened to check the water stop effect, and the water seepage part is filled; when the grouting effect meets the requirements, the front tank and the transition ring are removed, and the pipe joint 5 and the receiving hole are immediately blocked by the steel plate. mouth The gap between the tubes 6 is as shown in FIG.
S13管内管线全部拆除后,进行泥浆置换注浆,接收工作完成。 After the S13 pipe is completely removed, the mud replacement grouting is carried out, and the receiving work is completed.

Claims (2)

  1. 高水条件下泥水平衡顶管机接收装置,其特征在于:该装置包括顶管机机头(4)、接收孔口管(6)、前舱(7)、中舱(8)、尾舱(9)、泄压管(10)、泄压管阀门(11)、接收舱基座(12)、顶管机接收平台(13)、泥浆池(14)、观察窗(15)、井字形肋板(16)、螺栓孔(17)、排浆孔(18)、前舱加强肋板(19)、中舱加强肋板(20)、预留注浆管(21)、钢刷止水帘幕(22)、橡胶止水帘幕(23);A mud-water balance pipe jacking machine receiving device under high water conditions, characterized in that the device comprises a pipe jacking machine head (4), a receiving orifice pipe (6), a front tank (7), a middle tank (8), a tail tank (9), pressure relief pipe (10), pressure relief pipe valve (11), receiving compartment base (12), pipe jacking machine receiving platform (13), mud pool (14), observation window (15), well shape Rib (16), bolt hole (17), slurry hole (18), front tank reinforcement rib (19), middle tank reinforcement rib (20), reserved grouting pipe (21), steel brush water stop Curtain (22), rubber water curtain (23);
    前舱(7)、中舱(8)、尾舱(9)依次连接组成舱体部分,舱体部分安装在接收舱基座(12)上;顶管机机头(4)设置在舱体部分前端且与管幕管节(5)接触;The front compartment (7), the middle compartment (8) and the tail compartment (9) are sequentially connected to form a cabin part, the cabin part is mounted on the receiving compartment base (12); the pipe jacking head (4) is arranged in the cabin Part of the front end and in contact with the tube tube section (5);
    接收舱基座(12)安装在顶管机接收平台(13)上;前舱(7)与接收孔口管(6)通过螺栓连接固定;顶管机接收平台(13)设在管幕施工工作井(1)侧壁与钢筋混凝土地下连续墙(2)之间;泄压管(10)一端与尾舱9连接,且泄压管(10)上设置有泄压管阀门(11),泄压管(10)另一端与泥浆池(14)连接;尾舱(9)的端面上设有井字形肋板(16),尾舱(9)的端面顶部设有观察窗(15),尾舱(9)的端面底部设有排浆孔(18);尾舱(9)的端面上均匀对称设有螺栓孔(17);前舱(7)的外围焊接有前舱加强肋板(19);中舱(8)的外围焊接有中舱加强肋板(20);接收孔口管(6)与前舱(7)之间的舱体部分上设有钢刷止水帘幕(22);前舱(7)与中舱(8)之间的舱体部分上设有橡胶止水帘幕(23);预留注浆管(21)设置在接收孔口管(6)与钢刷止水帘幕(22)之间以及钢刷止水帘幕(22)与橡胶止水帘幕(23)之间的舱体部分上。 The receiving compartment base (12) is mounted on the pipe jacking machine receiving platform (13); the front compartment (7) and the receiving orifice pipe (6) are fixed by bolts; the pipe jacking machine receiving platform (13) is arranged in the pipe curtain construction Between the side wall of the working well (1) and the reinforced concrete underground continuous wall (2); one end of the pressure relief pipe (10) is connected with the tail tank 9, and the pressure relief pipe (10) is provided with a pressure relief pipe valve (11), The other end of the pressure relief pipe (10) is connected with the mud pool (14); the end of the tail tank (9) is provided with a ribbed rib (16), and the end of the end of the tail (9) is provided with an observation window (15). The bottom end of the tail chamber (9) is provided with a slurry discharge hole (18); the end surface of the tail chamber (9) is uniformly symmetrically provided with a bolt hole (17); and the front chamber (7) is welded with a front chamber reinforcement rib ( 19); the middle compartment (8) is welded with a middle cabin reinforcing rib (20); a cabin brush body between the receiving orifice tube (6) and the front compartment (7) is provided with a steel brush curtain ( 22); a rubber water curtain (23) is arranged on the cabin portion between the front cabin (7) and the middle cabin (8); the reserved grouting pipe (21) is arranged at the receiving orifice pipe (6) and Between the steel brush curtains (22) and between the steel curtain curtain (22) and the rubber water curtain (23).
  2. 高水条件下泥水平衡顶管机接收工艺,其特征在于:该工艺流程如下,The process of receiving the mud-water balance pipe jacking machine under high water conditions is characterized in that the process flow is as follows.
    S1在顶管机接收平台(13)上按前舱(7)、中舱(8)、尾舱(9)顺利拼装完成后与接收孔口管(6)通过螺栓连接;S1 is connected to the receiving orifice tube (6) by bolts on the pipe jacking machine receiving platform (13) according to the front compartment (7), the middle compartment (8) and the tail compartment (9);
    S2从泄压管(10)向接收舱注满清水,检查接收舱密闭性,渗漏水处及时加紧螺栓、更换接合橡胶垫等措施进行修补,合格后排空接收舱,打开泄压管阀门(11),注满泥水平衡泥浆;S2 fills the receiving tank from the pressure relief pipe (10) with clean water, checks the tightness of the receiving compartment, tightens the bolts in time, tightens the bolts, replaces the rubber pad, and other measures to repair. After passing the air, the receiving compartment is evacuated and the pressure relief valve is opened. (11), filled with muddy water balance mud;
    S3顶管机(4)接收前根据测量结果调整机头姿态,使顶管机(4)能以良好的姿态到达接收舱;The S3 pipe jacking machine (4) adjusts the attitude of the nose according to the measurement result before receiving, so that the pipe jacking machine (4) can reach the receiving cabin in a good posture;
    S4顶管机(4)钻进速度控制在1cm/min以内,减速破除洞门素混凝土墙(3)开始进入接收舱,关闭泄压管阀门(11);S4 pipe jacking machine (4) drilling speed is controlled within 1cm / min, deceleration to break the hole door concrete wall (3) began to enter the receiving compartment, close the pressure relief pipe valve (11);
    S5顶管机(4)整体进入接收舱到达指定位置,抽出舱内泥浆,冲洗泥浆管路,顶管机(4)停止操作;The S5 pipe jacking machine (4) enters the receiving compartment as a whole and reaches the designated position, extracts the mud in the tank, flushes the mud pipeline, and stops the pipe jacking machine (4);
    S6从预留注浆管(21)往两道帘幕间注马丽散止水,预留注浆管布置在前舱正上、左下及右下三个位置,呈120度环向布置;注浆采用的是小型气动注浆机,先注下侧预留注浆管,再注上部预留注浆管,注浆时注浆速度不宜过快,避免浆液流失,使马丽散与钢刷能充分结合形成整体,防止地层中的水土流失,封闭前舱(7)与中舱(8)的水系联通;S6 from the reserved grouting pipe (21) to the two curtains, Ma Li San stopped water, reserved grouting pipe is arranged in the front compartment, the lower left and the lower right three positions, arranged in a circular direction of 120 degrees; The grouting adopts a small pneumatic grouting machine. The grouting pipe is reserved on the lower side, and the grouting pipe is reserved in the upper part. The grouting speed should not be too fast when grouting, avoiding the loss of slurry, and making the powder and steel The brush can be fully combined to form a whole body to prevent water and soil loss in the formation, and the closed front compartment (7) is connected with the water system of the middle compartment (8);
    S7待马丽散基本凝固后,检验止水效果;打开预留注浆管,用钢筋疏通注浆导管至舱内,无渗水即可开始进行接收孔口管注浆;若有渗水,对渗水部位补注马丽散; After the S7 is finally solidified, the water-stopping effect is checked; the reserved grouting pipe is opened, and the grouting pipe is dredged into the tank by the steel bar, and the receiving orifice pipe can be started without water seepage; if there is water seepage, the water seepage Part replenishment Ma Lisan;
    S8从接收孔口管(6)上的预留注浆管注水泥浆,预留注浆管布置在接收孔口管正上、左下及右下三个位置,呈120度环向布置;注浆时,采用的是液压注浆机,先注一侧预留注浆管,打开另一侧预留注浆管,待另一侧预留注浆管有浆液流出时关闭该注浆管,然后打开上部预留注浆管,待有浆液流出时关闭该预留注浆管;若注浆压力过大,换其他预留注浆管注浆,使浆液充满管节外壁与接收孔口管间的空隙,封闭前舱(7)、孔口管(6)与地层中水的联通;S8 grouts the cement slurry from the reserved grouting pipe on the receiving orifice pipe (6), and the reserved grouting pipe is arranged at the top, bottom left and bottom right positions of the receiving orifice pipe, and is arranged in a circular direction of 120 degrees; grouting At the time, the hydraulic grouting machine is used, the grouting pipe is reserved on one side, and the grouting pipe is opened on the other side. When the grouting pipe on the other side is reserved, the grouting pipe is closed, and then the grouting pipe is closed. Open the upper reserved grouting pipe, close the reserved grouting pipe when the slurry flows out; if the grouting pressure is too large, change the other grouting pipe to grout, so that the slurry fills the outer wall of the pipe joint and the receiving orifice pipe a gap, closing the front compartment (7), the orifice tube (6) and the water in the formation;
    S9待水泥浆基本凝固后,检验注浆效果;打开预留注浆管,疏通注浆管至接收孔口管内,若无渗水即可进行开仓接收工作;若有渗水,对渗水部位进行补注水泥浆;S9 After the cement slurry is basically solidified, check the grouting effect; open the reserved grouting pipe, dredge the grouting pipe to the receiving orifice pipe, and if there is no water seepage, open the binning work; if there is water seepage, fill the seepage site Grouting slurry
    S10注浆效果检验合格后,打开排浆孔(18)排除舱内的的泥浆,打开后盖直接查看舱内是否有漏水或渗水现象,无漏水时拆除中舱(8)及尾舱(9)的上半圆部分,清除舱内的泥浆、砂石,吊出顶管机(4),随即拆除其下部半圆部分;After the S10 grouting effect is passed, open the slurry drain hole (18) to remove the mud in the cabin, open the back cover and directly check whether there is water leakage or water seepage in the cabin. When there is no water leakage, remove the middle cabin (8) and the tail tank (9) ) in the upper semicircle, remove the mud and sand in the cabin, lift the pipe jacking machine (4), and then remove the lower semicircle;
    S11在顶管机(4)后第一、二节管节(5)内的预留导丝管位置注双液浆止水,完全阻断接收孔口管(6)与地层中水的联通;注浆完成后即可开始管内管线的拆除工作;S11 in the first and second tube sections (5) after the pipe jacking machine (4), the position of the reserved guide wire tube is injected into the double liquid slurry to stop the water, completely blocking the communication between the receiving orifice tube (6) and the water in the formation. After the grouting is completed, the demolition work of the pipeline can be started;
    S12待双液浆凝固后,打开导丝管检查止水效果,有渗水部位进行补注;注浆效果满足要求时后,拆除前舱及过渡环,立即用钢板封堵管节(5)与接收孔口管(6)之间的间隙;After S12 is solidified, the guide wire tube is opened to check the water stop effect, and the water seepage part is refilled; after the grouting effect meets the requirements, the front tank and the transition ring are removed, and the pipe joint is immediately blocked with a steel plate (5) Receiving a gap between the orifice tubes (6);
    S13管内管线全部拆除后,进行泥浆置换注浆,接收工作完成。 After the S13 pipe is completely removed, the mud replacement grouting is carried out, and the receiving work is completed.
PCT/CN2015/000884 2015-11-04 2015-12-10 Device and process for receiving slurry-balanced pipe jacking machine in high-water-pressure condition WO2017075742A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016573991A JP6397940B2 (en) 2015-11-04 2015-12-10 High water pressure compatible mud balance pipe propulsion device and construction method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201510752859.2A CN105257299B (en) 2015-11-04 2015-11-04 Slurry-balanced pipe jacking machine receiving device and technology under high water condition
CN201510752859.2 2015-11-04

Publications (1)

Publication Number Publication Date
WO2017075742A1 true WO2017075742A1 (en) 2017-05-11

Family

ID=55097189

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2015/000884 WO2017075742A1 (en) 2015-11-04 2015-12-10 Device and process for receiving slurry-balanced pipe jacking machine in high-water-pressure condition

Country Status (3)

Country Link
JP (1) JP6397940B2 (en)
CN (1) CN105257299B (en)
WO (1) WO2017075742A1 (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107956482A (en) * 2017-12-23 2018-04-24 哈尔滨工业大学 Seasonal frost region tunnel surrounding crack deicing slip casting crack arrest system and method
CN108221952A (en) * 2018-03-16 2018-06-29 沈阳建筑大学 A kind of pressure-adjustable orientation grouting sleeve valve pipe and grouting method
CN109026151A (en) * 2018-10-17 2018-12-18 中铁隧道局集团有限公司 Big cross section rectangular top pipe tunnel portal sealing device and its installation method
CN109991158A (en) * 2019-03-22 2019-07-09 湖南城市学院 The push pipe of push pipe experimental box
CN110500122A (en) * 2019-08-22 2019-11-26 郑州市市政工程总公司 Jacking construction hole waterproofing reinforcement structure and jacking construction hole water proofing and reinforcing method
CN111156032A (en) * 2020-01-20 2020-05-15 杭州临安中民筑友智造科技有限公司 Structure and method for reinforcing existing subway tunnel through inserting section steel into grouting pipe and grouting
CN112664221A (en) * 2020-12-29 2021-04-16 中交第三航务工程局有限公司 Pipe jacking construction method for complex geological formation
CN112963178A (en) * 2021-04-25 2021-06-15 中化学交通建设集团市政工程有限公司 Slurry-based silty clay stratum pipe jacking construction grouting process
CN113137239A (en) * 2021-05-15 2021-07-20 中铁十一局武汉重型装备有限公司 Shield cutter head face reinforcing method and grouting reinforcing device used for method
CN113338983A (en) * 2021-07-30 2021-09-03 中国建筑第七工程局有限公司 Large-diameter mud-water balance pipe jacking construction method suitable for high-water-level rock geology
CN114542799A (en) * 2022-02-08 2022-05-27 中交水利水电建设有限公司 Vertical jacking construction method for underground finite space
CN116718523A (en) * 2023-08-09 2023-09-08 长江三峡集团实业发展(北京)有限公司 Push pipe Zhou Nijiang distribution test device and test method
CN117685416A (en) * 2024-01-25 2024-03-12 安徽水安建设集团股份有限公司 Water blocking structure and water blocking method suitable for rectangular pipe jacking membrane bag

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108104828B (en) * 2017-11-02 2020-04-10 上海市政建设有限公司 Hole entering and exiting method for directly grinding hole door by pipe jacking machine
CN107989638A (en) * 2017-12-28 2018-05-04 中铁二局集团有限公司 A kind of push pipe receives water-stopping method
CN108952745A (en) * 2018-08-21 2018-12-07 上海交通大学 A kind of double gas storehouses are rectified a deviation by force air pressure balance jacking pipe machine
CN109184729A (en) * 2018-11-01 2019-01-11 中铁十八局集团有限公司 A kind of accurate received control method of realization push-bench
CN112943259A (en) * 2019-12-10 2021-06-11 湖北电工联盟建设管理有限公司 Pipe jacking machine tunneling construction process for electric power engineering
CN112159165B (en) * 2020-10-23 2021-12-17 中铁二十五局集团有限公司 Shield freezing and opening material and preparation method thereof
CN113153396B (en) * 2021-04-19 2023-03-31 华北科技学院 Hole sealing, grouting and water plugging reinforcing method for anchor cable holes in roadway water spraying area
CN114542091B (en) * 2022-04-26 2022-08-12 中国铁路设计集团有限公司 Advanced pre-support construction method and structure for small-caliber pipe curtain of underground excavation close-connection project

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4052859A (en) * 1976-02-12 1977-10-11 Tekken Construction Co. Ltd. Method and apparatus of completing slurry shield tunneling at vertical shaft
US4569616A (en) * 1982-12-03 1986-02-11 Mitsui Kensetsu Kabushiki Kaisha Driving process of enlarged tunnel
CN104455724A (en) * 2014-09-30 2015-03-25 中铁十八局集团有限公司 Tube push bench receiving device and method under high-water-pressure condition
CN104763436A (en) * 2015-03-09 2015-07-08 中国地质大学(武汉) Method and device for receiving pipe jacking machine under condition of high water pressure complicated geological conditions
CN205349342U (en) * 2015-11-04 2016-06-29 中铁十八局集团有限公司 Balanced pipe pushing jack receiving arrangement of muddy water under high water condition

Family Cites Families (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2533906B2 (en) * 1988-03-22 1996-09-11 日本電信電話株式会社 Propulsion method
JP2987501B2 (en) * 1998-04-16 1999-12-06 有限会社タム・テック Tunnel entrance sealing device
JP2005344360A (en) * 2004-06-02 2005-12-15 Taisei Corp Arrival portal cut-off method in shield tunneling method and jacking method
JP2007315030A (en) * 2006-05-25 2007-12-06 Kidoh Tech Co Ltd Asbestos pipe removing method
CN101749028B (en) * 2008-12-16 2013-05-29 上海广联建设发展有限公司 Cross-pulling construction method for soft soil zone with high ground water level
CN101532387B (en) * 2009-04-09 2011-11-09 上海建工(集团)总公司 Water sealing device applied in process of entering receiving well in push pipe and tunnel construction and method thereof
JP2014015747A (en) * 2012-07-09 2014-01-30 Watashin Tekko:Kk Pit mouth cut-off device of casing shaft
JP6365970B2 (en) * 2014-03-19 2018-08-01 三和機材株式会社 Horizontal drain hole installation method
CN104265321B (en) * 2014-08-06 2016-04-13 上海隧道工程有限公司 Ultra-large type tunneling boring rectangular top pipe tunneling construction method
CN204153317U (en) * 2014-08-20 2015-02-11 中铁十八局集团第一工程有限公司 A kind of mud water balance push bench has crimping to receive cabin
CN204511467U (en) * 2014-12-24 2015-07-29 浙江大学城市学院 A kind of hole water-stopping structure
CN204533813U (en) * 2015-03-31 2015-08-05 苏州群业建筑工程有限公司 A kind of slurry-water balance type push pipe system
CN204533812U (en) * 2015-03-31 2015-08-05 苏州群业建筑工程有限公司 A kind of slurry-water balance type jacking construction system
CN104790964A (en) * 2015-04-29 2015-07-22 中铁十八局集团轨道交通工程有限公司 Construction method for shield tunneling machine moving-out on condition of tunnel portal deviation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4052859A (en) * 1976-02-12 1977-10-11 Tekken Construction Co. Ltd. Method and apparatus of completing slurry shield tunneling at vertical shaft
US4569616A (en) * 1982-12-03 1986-02-11 Mitsui Kensetsu Kabushiki Kaisha Driving process of enlarged tunnel
CN104455724A (en) * 2014-09-30 2015-03-25 中铁十八局集团有限公司 Tube push bench receiving device and method under high-water-pressure condition
CN104763436A (en) * 2015-03-09 2015-07-08 中国地质大学(武汉) Method and device for receiving pipe jacking machine under condition of high water pressure complicated geological conditions
CN205349342U (en) * 2015-11-04 2016-06-29 中铁十八局集团有限公司 Balanced pipe pushing jack receiving arrangement of muddy water under high water condition

Cited By (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107956482B (en) * 2017-12-23 2024-03-01 哈尔滨工业大学 Deicing, grouting and crack-stopping system and method for tunnel surrounding rock cracks in quaternary frozen area
CN107956482A (en) * 2017-12-23 2018-04-24 哈尔滨工业大学 Seasonal frost region tunnel surrounding crack deicing slip casting crack arrest system and method
CN108221952A (en) * 2018-03-16 2018-06-29 沈阳建筑大学 A kind of pressure-adjustable orientation grouting sleeve valve pipe and grouting method
CN109026151A (en) * 2018-10-17 2018-12-18 中铁隧道局集团有限公司 Big cross section rectangular top pipe tunnel portal sealing device and its installation method
CN109991158A (en) * 2019-03-22 2019-07-09 湖南城市学院 The push pipe of push pipe experimental box
CN110500122B (en) * 2019-08-22 2024-04-12 郑州市市政工程总公司 Waterproof reinforcing structure and waterproof reinforcing method for pipe-jacking construction hole
CN110500122A (en) * 2019-08-22 2019-11-26 郑州市市政工程总公司 Jacking construction hole waterproofing reinforcement structure and jacking construction hole water proofing and reinforcing method
CN111156032A (en) * 2020-01-20 2020-05-15 杭州临安中民筑友智造科技有限公司 Structure and method for reinforcing existing subway tunnel through inserting section steel into grouting pipe and grouting
CN111156032B (en) * 2020-01-20 2024-04-02 杭州临安中民筑友智造科技有限公司 Grouting pipe inserted section steel grouting reinforcement existing subway tunnel structure and method
CN112664221A (en) * 2020-12-29 2021-04-16 中交第三航务工程局有限公司 Pipe jacking construction method for complex geological formation
CN112664221B (en) * 2020-12-29 2023-08-25 中交第三航务工程局有限公司 Pipe jacking construction method for complex geological layer
CN112963178B (en) * 2021-04-25 2023-07-07 中化学交通建设集团市政工程有限公司 Mud powder clay stratum pipe jacking construction grouting process
CN112963178A (en) * 2021-04-25 2021-06-15 中化学交通建设集团市政工程有限公司 Slurry-based silty clay stratum pipe jacking construction grouting process
CN113137239B (en) * 2021-05-15 2023-08-22 中铁十一局武汉重型装备有限公司 Method for reinforcing tunnel face of shield cutter head and grouting reinforcing device for method
CN113137239A (en) * 2021-05-15 2021-07-20 中铁十一局武汉重型装备有限公司 Shield cutter head face reinforcing method and grouting reinforcing device used for method
CN113338983A (en) * 2021-07-30 2021-09-03 中国建筑第七工程局有限公司 Large-diameter mud-water balance pipe jacking construction method suitable for high-water-level rock geology
CN113338983B (en) * 2021-07-30 2024-03-12 中国建筑第七工程局有限公司 Large-pipe-diameter mud-water balance jacking pipe construction method suitable for high-water-level rock geology
CN114542799A (en) * 2022-02-08 2022-05-27 中交水利水电建设有限公司 Vertical jacking construction method for underground finite space
CN114542799B (en) * 2022-02-08 2023-06-20 中交水利水电建设有限公司 Underground limited space vertical jacking construction method
CN116718523B (en) * 2023-08-09 2024-01-05 长江三峡集团实业发展(北京)有限公司 Distribution test method for push pipe Zhou Nijiang
CN116718523A (en) * 2023-08-09 2023-09-08 长江三峡集团实业发展(北京)有限公司 Push pipe Zhou Nijiang distribution test device and test method
CN117685416A (en) * 2024-01-25 2024-03-12 安徽水安建设集团股份有限公司 Water blocking structure and water blocking method suitable for rectangular pipe jacking membrane bag
CN117685416B (en) * 2024-01-25 2024-04-23 安徽水安建设集团股份有限公司 Water blocking structure and water blocking method suitable for rectangular pipe jacking membrane bag

Also Published As

Publication number Publication date
JP2017536490A (en) 2017-12-07
CN105257299B (en) 2017-05-17
JP6397940B2 (en) 2018-09-26
CN105257299A (en) 2016-01-20

Similar Documents

Publication Publication Date Title
WO2017075742A1 (en) Device and process for receiving slurry-balanced pipe jacking machine in high-water-pressure condition
CN206053969U (en) A kind of shield tunnel and open cut main body portal ring beam hermetic water-proof structure
CN106014201B (en) A kind of outer release hole safe construction technique of tunnel grouting curtain
CN101251017B (en) Subsection retrusive slip-casting method for porthole slurry-stop jackrod
CN100510274C (en) Construction method of enclosing level rotary-jet pile hole-mouth using double-liquid slip jection method
CN107762532A (en) Tunnel vault band mould grouting construction method
CN111734420B (en) Water-rich stratum shield underwater receiving method provided with tunnel portal mortar retaining wall
CN111396067B (en) Comprehensive shield steel sleeve receiving construction method in complex environment
CN107761753A (en) A kind of foundation ditch water burst rapid rescue slip casting method for blocking
CN109184750A (en) A kind of tunnel radial grouting device and method
CN201129184Y (en) Tubule external valve one-way type subsection back grouting apparatus
CN105781586B (en) A kind of solid pipe method for blocking of gushing water borehole wall filter stream pressure relief vent inner sleeve
CN203702071U (en) Water inrush preventing drill ejecting device for water exploration and grouting construction of vertical shaft
CN207062938U (en) Tubaeform mud jacking head and squeezing unit
CN103174135B (en) Repair method of unqualified post-grouting bored concrete pile
CN104674817B (en) The method of the sealing of falling pressure type slip casting closure reserving hole
CN105220700A (en) Foundation pit waterproof curtain reinforcement
CN104343123A (en) Double-layer film bag device applied to injection pipe sealing in water bursting sand layer and method therefor
CN204252139U (en) Be applied to the two-layer equation film bagging apparatus of Grouting Pipe sealing in water burst sandy soils
CN209603062U (en) Change the concentrative seepage plugging structure that dynamic water is hydrostatic in gallery
CN116816389A (en) Tunnel water-rich karst collapse cavity treatment method
CN206844136U (en) Closure high speed, big flow move the flow control system of water karst
CN212079318U (en) Shield starting water stopping system under water-rich sand layer geological condition
CN209083292U (en) A kind of tunnel radial grouting device
CN209508995U (en) One kind closing water valve device and its shut-in well structure

Legal Events

Date Code Title Description
ENP Entry into the national phase

Ref document number: 2016573991

Country of ref document: JP

Kind code of ref document: A

121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 15907584

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 15907584

Country of ref document: EP

Kind code of ref document: A1