CN116816389A - Tunnel water-rich karst collapse cavity treatment method - Google Patents

Tunnel water-rich karst collapse cavity treatment method Download PDF

Info

Publication number
CN116816389A
CN116816389A CN202310863637.2A CN202310863637A CN116816389A CN 116816389 A CN116816389 A CN 116816389A CN 202310863637 A CN202310863637 A CN 202310863637A CN 116816389 A CN116816389 A CN 116816389A
Authority
CN
China
Prior art keywords
water
collapse
cavity
grouting
karst
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310863637.2A
Other languages
Chinese (zh)
Inventor
付弦
冉波
吴志勇
任光辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 19th Metallurgical Corp
Original Assignee
China 19th Metallurgical Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 19th Metallurgical Corp filed Critical China 19th Metallurgical Corp
Priority to CN202310863637.2A priority Critical patent/CN116816389A/en
Publication of CN116816389A publication Critical patent/CN116816389A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention relates to the field of tunnel construction methods, in particular to a tunnel water-rich karst collapse cavity treatment method which is simple to operate, fast in progress, low in cost and high in safety, and comprises the following treatment steps: a. rapidly spraying a plugging agent to seal the cavity collapse surface; b. advanced geological forecast; c. drainage water treatment; d. constructing a slurry stopping wall; e. grouting and water plugging of advanced curtain: according to the water inflow, water pressure and other conditions, comprehensively determining the arrangement of grouting holes, wherein the grouting mode adopts forward type sectional grouting; f. cavity collapse treatment in the hole; g. monitoring and measuring, namely after the collapse cavity treatment of karst is completed, monitoring and measuring and observing the karst cave section, analyzing the change condition of surrounding rock of the section of the karst cave section, and judging the effectiveness of karst cave treatment measures. The method for treating the water-rich karst collapse cavity is simple in operation, fast in progress, low in cost and high in safety, and is particularly suitable for treating the water-rich karst collapse cavity of the tunnel.

Description

Tunnel water-rich karst collapse cavity treatment method
Technical Field
The invention relates to the field of tunnel construction methods, in particular to a tunnel water-rich karst collapse cavity treatment method.
Background
Karst areas have complex geological conditions, and long highway tunnel engineering is built in karst development areas, so that karst holes with different sizes and shapes can be met. If the construction process is improperly processed, engineering disasters such as collapse, mud bursting, water flushing, instability of the tunnel body and the like are extremely easy to cause threat to tunnel construction and operation safety. When a large-scale water-rich karst crushing belt is required to be treated in the tunnel excavation process, the adopted filler is mostly soft plastic soil, raw rock-containing weathered fragments are adopted, the filler is in a sliding outflow state after tunnel excavation, obvious water flow is sprayed or overflows, the possibility of breaking through karst disasters is high in construction, the conventional grouting is adopted for sealing karst cave treatment, the stability of a collapse cavity and a tunnel face is difficult to ensure, and the safety, quality and progress of tunnel construction are difficult to ensure.
Therefore, the existing construction process is not combined with the environmental characteristics of the water-rich karst collapse cavity of the tunnel, the adopted treatment method is long in treatment time, and the material waste is serious.
Disclosure of Invention
The technical problem to be solved by the invention is to provide the tunnel water-rich karst collapse cavity treatment method which is simple to operate, fast in progress, low in cost and high in safety.
The technical scheme adopted for solving the technical problems is as follows: the tunnel water-rich karst collapse cavity treatment method comprises the following treatment steps: a. quick injection of plugging agent seals the collapse surface: when a collapse cavity appears at the arch crown and the arch waist of the tunnel and the water yield is not large, rapidly closing the collapse cavity surface of the collapse cavity by adopting an overspeed setting plugging material; backfilling is completed by backfilling hole slag behind the tunnel face, a construction platform is arranged at the lower part of the collapse body, the height of the platform is flush with the back pressure hole slag of the impact section of the tunnel face, C30 concrete with the thickness of 20cm is sprayed after backfilling is completed, and the stability of the platform is ensured; b. advanced geological forecast: after the cavity surface of the collapse cavity is closed, adopting a geophysical prospecting method to find the shape, the range, the size, the filling materials, the groundwater and the like of the karst cave; c. drainage water treatment: a steel pipe scaffold is erected by utilizing a construction platform, a large-caliber steel pipe is installed, and the water discharged from the collapse cavity is subjected to preliminary flow returning, so that most of water burst is discharged along the flow guiding pipe; d. and (3) constructing a grout stopping wall: the slurry stopping wall is constructed on the tunnel face, so that the tunnel face is effectively sealed, and further surge condition of the tunnel face is prevented; e. grouting and water plugging of advanced curtain: according to the water inflow, water pressure and other conditions, comprehensively determining the arrangement of grouting holes, wherein the grouting mode adopts forward type sectional grouting; f. the cavity collapse treatment comprises the following steps: 1. drainage in the collapse cavity: after the collapse cavity is sealed and stable, a drain pipe is arranged, and the water outlet end of the drain pipe is provided with geotextile for preventing silt from blocking the pipe, so that water in the dissolution cavity is discharged through the annular drain pipe; 2. advanced support: setting up double rows of advanced grouting small pipes in the range of the collapse cavity, wherein the grouting small pipes adopt phi 42 seamless steel pipes, the external insertion angle of a lower row of short pipes is 10-15 degrees, and the external insertion angle of an upper row of long pipes is 20-35 degrees; 3. collapse affects the primary support reinforcement grouting of the section: erecting a steel arch on the primary support of the karst cave affected section; 4. and backfilling foam lightweight concrete in the cavity: pouring the mixed foam light concrete into the collapse cavity through a grouting small conduit, and stopping grouting by continuing lOmin when the grouting amount is gradually reduced and the grouting pressure tends to be stable, and adopting C30 concrete for hole sealing operation; 5. laying a waterproof layer: adopting a non-woven geotextile and a polymer self-adhesive waterproof coiled material composite waterproof layer to treat the outer layer of the collapse cavity; 6. and (3) performing secondary lining: the secondary lining of the collapse section of the collapse cavity adopts a reinforced concrete structure; g. monitoring and measuring, namely after the collapse cavity treatment of karst is completed, monitoring and measuring and observing the karst cave section, analyzing the change condition of surrounding rock of the section of the karst cave section, and judging the effectiveness of karst cave treatment measures.
In the step d, a temporary water collecting ditch is arranged at the water inflow position to collect scattered water which does not flow out of the flow guide pipe, and a drainage steel pipe is arranged to guide the water out of the slurry stopping wall during the concrete pouring of the slurry stopping wall. The influence of scattered water on the grout stopping wall can be reduced by leading the water out of the grout stopping wall, and the smooth pouring of the grout stopping wall is ensured.
Further, in the step f, the drain pipe is a phi 30cm HDPE double-arm corrugated drain pipe.
Further, in the step f, the length of the short guide pipes of the lower row is 3m, and the interval between the short guide pipes of the lower row is 0.5m.
Further, in the step f, the upper long guide pipes are 5m long, and the interval between the upper long guide pipes is 0.5m.
In the step f, when the steel arch is erected on the primary support of the karst cave affected section, the steel arch adopts I20, the distance is 50cm, phi 8 steel bar meshes are hung, the grid distance is 20 multiplied by 20cm, phi 22 mortar anchor rods are radially arranged, the length is 4m, and the distance is 1.2 multiplied by 1.2m, and the steel arch is arranged in a quincuncial shape.
And in the step f, pouring the mixed foam light concrete into the collapse cavity through a grouting small conduit, wherein the pouring thickness is 2m.
The beneficial effects of the invention are as follows: 1. the double-row advanced small guide pipe grouting is adopted, the large locking feet are used for reinforcing the integral connection of the steel arch centering, the cavity collapse treatment requirement is met, and long-time treatment and material waste caused by reinforcing the long pipe shed are avoided; 2. the self-compaction material is high in durability, self-compaction, high in compressibility and ductility, and adjustable in density and strength; 3. the outer layer of the collapse cavity is treated by adopting the non-woven geotextile and the polymer self-adhesive waterproof coiled material composite waterproof layer, so that the secondary water seepage of the lining structure caused by breakage and non-adhesion during the laying of the waterproof board is effectively solved. The method for treating the water-rich karst collapse cavity is simple in operation, fast in progress, low in cost and high in safety, and is particularly suitable for treating the water-rich karst collapse cavity of the tunnel.
Drawings
FIG. 1 is a schematic view of karst collapse chamber and face closure.
FIG. 2 is a schematic elevation view of full-face curtain grouting pre-grouting.
FIG. 3 is a schematic cross-sectional view of a full-face curtain grouting pre-grouting section.
FIG. 4 is a schematic illustration of a karst collapse chamber support treatment.
Fig. 5 is a schematic view of a double row arrangement of small ducts.
Marked in the figure as: vault preliminary bracing 1, collapse cavity 2, grout stop wall 3, face 4, water stop rock 41, temporary catchment 5, backfill hole slag 6, C30 concrete 7, grouting holes 8, upper stage grouting holes 81, lower stage grouting holes 82, advanced grouting water shutoff zone 9, first grouting hole ring 91, second grouting hole ring 92, third grouting hole ring 93, I20 steel arch 10, lower row short conduit 101, upper row long conduit 102, preliminary bracing 11.
Detailed Description
The invention will be further described with reference to the drawings and examples.
The tunnel water-rich karst collapse cavity treatment method shown in fig. 1 to 5 has the advantages of simple operation, fast progress, low cost and high safety due to the adoption of a mode of fast sealing the collapse cavity surface and the tunnel face, grouting for dissolving cavity, emission reduction, drainage and depressurization, and comprehensive treatment measures such as foam lightweight concrete backfilling in the collapse cavity, double-row advanced small-conduit grouting, mortar anchor rod reinforcement and the like. When encountering a large-scale water-rich karst breaking belt in the tunnel excavation process, the following treatment mode is adopted: 1. and rapidly spraying the plugging agent to seal the cavity collapse surface. (1) When collapse cavity sections appear at the arch crown and the arch waist of the tunnel and the water yield is not large, the collapse cavity surfaces are sealed by adopting the overspeed setting plugging material rapidly. (2) Hole slag backfilling is adopted behind the tunnel face, a construction platform is arranged at the lower part of the collapse body, the platform height is flush with the tunnel slag in the impact section of the tunnel face, C30 concrete with the thickness of 20cm is sprayed after backfilling is finished, and the stability of the platform is ensured. 2. Advanced geological forecast. After the cavity collapse surface is closed, the conditions of the shape, the range, the size, the filling, the groundwater and the like of the karst cave are ascertained by adopting a geophysical prospecting method. 3. Drainage water treatment: and a steel pipe scaffold is erected by utilizing a construction platform, a large-caliber steel pipe is installed, and the yielding water in the collapse cavity is subjected to preliminary flow returning, so that most of the water burst is discharged along the flow guiding pipe. (1) In order not to change the flow rule of the underground water, the treatment of the water in the dissolving cavity adopts a mutual communication mode. Through multiple geological means, the development direction of the water in the dissolving tube around the tunnel is ascertained, the dissolving tube is communicated by adding an auxiliary channel at a proper position of the side wall, and a water channel is formed, so that the total flowing trend of underground water is not changed. (2) Because the water in the dissolving pipe generally contains a large amount of silt and can be influenced by atmospheric rainfall, the auxiliary pipeline should have a larger water cross section on one hand and a certain gradient on the other hand so as to prevent the silt from accumulating. 4. And (3) constructing a grout stopping wall: and a slurry stopping wall is arranged on the tunnel face, so that the tunnel face is effectively sealed, and further surge condition of the tunnel face is prevented. The grout stopping wall can be constructed in two sections: the first casting step plays a role in flow returning, and the second casting step plays a role in water shutoff; in order to facilitate construction, a temporary water collecting ditch can be arranged at a water gushing position to collect scattered water which does not flow out of the guide pipe, and a drainage steel pipe is arranged to guide the water out of the slurry stopping wall when the slurry stopping wall is concreted. 5. The advanced curtain grouting is used for plugging water, the grouting hole arrangement is comprehensively determined according to the water inflow, water pressure and other conditions, and the forward type sectional grouting is adopted in the grouting mode. The full-face (curtain) advanced pre-grouting construction technology comprises the following steps: (1) Before each cycle of advanced pre-grouting, a 100cm thick grout stopping wall is required to be arranged. (2) The hole forming grouting adopts forward type sectional grouting, after the sleeve is installed, grouting is started after each drill reaches 5-7 meters, and drilling grouting is started at the next stage after the grouting meets the design requirement. And a sleeve plunger mode is adopted during grouting, and meanwhile, a long grouting pipe is required to be inserted into a preset position especially for deep holes exceeding 20 meters, so that the grouting effect and the grouting efficiency at the bottom of the hole are improved. (3) The method adopts the measures of repeated injection, alternation of thin pulp and thick pulp, and combination of pressure control and injection pulp quantity control, and the grouting pressure is gradually increased from low to high. The initial grouting pressure is recommended to adopt 1.2 times of hydrostatic pressure, and the grouting time is flexibly adjusted according to the injection rate of the slurry. (4) After each cycle grouting is completed and the excavation construction is completed, about 6 meters is reserved to serve as a grouting and stopping section at the lower stage. 6. And (3) cavity collapse treatment in a hole: (1) collapse of the drainage in the cavity. After the cavity is closed and stable, a phi 30cm HDPE double-arm corrugated drain pipe (the water outlet end is provided with geotextile to prevent silt from blocking the pipe) is arranged, and water in the solution cavity is discharged through the annular drain pipe. (2) The method comprises the steps of advanced support, setting up double rows of advanced grouting small guide pipes in the cavity collapse range, wherein the grouting small guide pipes are phi 42 seamless steel pipes, the length of a lower row of short guide pipes is 3m, the external insertion angle is 10-15 degrees, the length of an upper row of long guide pipes is 5m, the external insertion angle is 20-35 degrees, and the circumferential spacing is 0.5m. (3) The method comprises the steps of reinforcing and grouting a collapse influence section primary support, and erecting steel arches on the karst cave influence section primary support, wherein the steel arches are I20, and the distance between the steel arches is 50cm. And phi 8 steel bar meshes are hung, the grid spacing is 20cm, phi 22 mortar anchor rods are radially arranged, the length is 4m, the spacing is 1.2 multiplied by 1.2m, and the quincuncial arrangement is realized. (4) And filling foam lightweight concrete in the cavity, and pouring the mixed foam lightweight concrete into the cavity through a grouting pipe, wherein the pouring thickness is 2m. And stopping grouting by continuously carrying out the lOmin when the grouting amount gradually decreases and the grouting pressure tends to be stable, and adopting C30 concrete to carry out hole sealing operation. (5) paving a waterproof layer: and processing the outer layer of the collapse cavity by adopting a composite waterproof layer of the non-woven geotextile and the high polymer self-adhesive waterproof coiled material. (6) performing secondary lining: the secondary lining of the collapse section adopts a reinforced concrete structure. 7. Monitoring and measuring, namely after karst collapse cavity treatment is completed, monitoring, measuring and observing the karst cave section, analyzing the change condition of surrounding rock of the cross section of the karst cave section, and judging the effectiveness of karst cave treatment measures.

Claims (7)

1. The tunnel water-rich karst collapse cavity treatment method is characterized by comprising the following treatment steps:
a. quick injection of plugging agent seals the collapse surface: when a collapse cavity (2) appears at the arch top and the arch waist of the tunnel and the water yield is not large, rapidly closing the collapse cavity surface of the collapse cavity (2) by adopting an overspeed setting plugging material; backfilling is completed by adopting backfill hole slag (6) behind the tunnel face (4), a construction platform is arranged at the lower part of the collapse body, the platform height is flush with the back pressure hole slag of the impact section of the tunnel face (4), and C30 concrete (7) with the thickness of 20cm is sprayed after backfill is completed, so that the stability of the platform is ensured;
b. advanced geological forecast: after the cavity surface of the collapse cavity (2) is closed, adopting a geophysical prospecting method to ascertain the shape, range, size, filling, groundwater and the like of the karst cave;
c. drainage water treatment: a steel pipe scaffold is erected by utilizing a construction platform, a large-caliber steel pipe is installed, and the water discharged from the collapse cavity is subjected to preliminary flow returning, so that most of water burst is discharged along the flow guiding pipe;
d. and (3) constructing a grout stopping wall: the slurry stopping wall (3) is constructed on the tunnel face (4), the tunnel face (4) is effectively sealed, and further surge conditions of the tunnel face (4) are prevented;
e. grouting and water plugging of advanced curtain: according to the water inflow, water pressure and other conditions, comprehensively determining the arrangement of grouting holes, wherein the grouting mode adopts forward type sectional grouting;
f. the cavity collapse treatment comprises the following steps:
1. drainage in the collapse cavity: after the collapse cavity is sealed and stable, a drain pipe is arranged, and the water outlet end of the drain pipe is provided with geotextile for preventing silt from blocking the pipe, so that water in the dissolution cavity is discharged through the annular drain pipe;
2. advanced support: setting up double rows of advanced grouting small pipes in the range of the collapse cavity (2), wherein the grouting small pipes adopt phi 42 seamless steel pipes, the external insertion angle of a lower row of short pipes (101) is 10-15 degrees, and the external insertion angle of an upper row of long pipes (102) is 20-35 degrees;
3. collapse affects the primary support reinforcement grouting of the section: erecting a steel arch on an initial support (11) of a karst cave influence section;
4. and backfilling foam lightweight concrete in the cavity: pouring the mixed foam light concrete into the collapse cavity (2) through a grouting small conduit, and stopping grouting by continuing lOmin when the grouting amount is gradually reduced and the grouting pressure tends to be stable, and adopting C30 concrete for hole sealing operation;
5. laying a waterproof layer: adopting a non-woven geotextile and a polymer self-adhesive waterproof coiled material composite waterproof layer to treat the outer layer of the collapse cavity (2);
6. and (3) performing secondary lining: the secondary lining of the collapse section of the collapse cavity (2) adopts a reinforced concrete structure;
g. monitoring and measuring, namely after the karst collapse cavity (2) is processed, monitoring and measuring and observing the karst cave section, analyzing the change condition of the surrounding rock of the karst cave section, and judging the effectiveness of karst cave treatment measures.
2. The method for treating the water-rich karst collapse of the tunnel according to claim 1, wherein the method comprises the following steps: in the step d, a temporary water collecting ditch (5) is arranged at a water gushing position to collect scattered water which does not flow out of the flow guide pipe, and a flow guide steel pipe is arranged to guide the water out of the slurry stopping wall (3) while the concrete of the slurry stopping wall (3) is poured.
3. The tunnel water-rich karst collapse cavity processing method according to claim 1 or 2, characterized in that: in step f, the drain pipe is a phi 30cm HDPE double-arm corrugated drain pipe.
4. The tunnel water-rich karst collapse cavity processing method according to claim 1 or 2, characterized in that: in step f, the lower short guide pipes (101) are 3m long, and the interval between the lower short guide pipes (101) is 0.5m.
5. The tunnel water-rich karst collapse cavity processing method according to claim 1 or 2, characterized in that: in step f, the upper long guide pipes (102) are 5m long, and the interval between the upper long guide pipes (102) is 0.5m.
6. The tunnel water-rich karst collapse cavity processing method according to claim 1 or 2, characterized in that: in the step f, when a steel arch is erected on the primary support (11) of the karst cave affected section, the steel arch adopts I20, the distance is 50cm, phi 8 steel bar meshes are hung, the grid distance is 20 multiplied by 20cm, phi 22 mortar anchor rods are radially arranged, the length is 4m, and the distance is 1.2 multiplied by 1.2m, and the steel arch is arranged in a quincuncial shape.
7. The tunnel water-rich karst collapse cavity processing method according to claim 1 or 2, characterized in that: and f, pouring the mixed foam light concrete into the collapse cavity (2) through a grouting small conduit, wherein the pouring thickness is 2m.
CN202310863637.2A 2023-07-14 2023-07-14 Tunnel water-rich karst collapse cavity treatment method Pending CN116816389A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310863637.2A CN116816389A (en) 2023-07-14 2023-07-14 Tunnel water-rich karst collapse cavity treatment method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310863637.2A CN116816389A (en) 2023-07-14 2023-07-14 Tunnel water-rich karst collapse cavity treatment method

Publications (1)

Publication Number Publication Date
CN116816389A true CN116816389A (en) 2023-09-29

Family

ID=88112672

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310863637.2A Pending CN116816389A (en) 2023-07-14 2023-07-14 Tunnel water-rich karst collapse cavity treatment method

Country Status (1)

Country Link
CN (1) CN116816389A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117780392A (en) * 2024-02-26 2024-03-29 中国建筑第六工程局有限公司 Airbag grouting treatment method for collapse of underground tunneling hole

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117780392A (en) * 2024-02-26 2024-03-29 中国建筑第六工程局有限公司 Airbag grouting treatment method for collapse of underground tunneling hole
CN117780392B (en) * 2024-02-26 2024-05-17 中国建筑第六工程局有限公司 Airbag grouting treatment method for collapse of underground tunneling hole

Similar Documents

Publication Publication Date Title
CN107642360B (en) Full-section advanced pre-grouting construction method
CN108678777B (en) Support method for tunnel fault fracture zone section
CN104453913B (en) A kind of Shaft Stopes front pre-grouting method
KR101500667B1 (en) steel pipe grouting device and tunnel reinforcement andbarrier grouting method using this
CN110735653A (en) deep-hole retreating type grouting water plugging construction method for igneous rock water-rich fault
CN111119940B (en) Grouting construction treatment method
CN103334770A (en) Construction method of superhigh water pressure water-affluent crushed zones of long-large counter-slope tunnels
CN108952732A (en) A kind of excavation construction method suitable for rich water fault belt large cross-section tunnel
CN110924976A (en) Surrounding rock outer ring grouting reinforcement method
CN112412496A (en) Full-section advanced curtain grouting construction method for water-rich broken geological zone tunnel
CN101793154A (en) Method for grouting for stopping up water by using geological parameters of tunnel surrounding rocks and setting relief holes
CN111271064A (en) Excavation construction method for water-rich stratum tunnel stabilization tunnel face
CN109371980B (en) Deep foundation pit enclosure construction method combining spray anchor reverse construction and punched pile
CN102296621A (en) Construction method of ground sectional water-stop curtain
CN116816389A (en) Tunnel water-rich karst collapse cavity treatment method
CN114109442B (en) Tunnel karst crushing belt sliding collapse half-section curtain progressive grouting reinforcement treatment method
CN103572764A (en) Watertight structure for retaining wall of ultra-deep manually excavated pile and construction method thereof
CN111287794A (en) Karst tunnel underground water open type drainage structure and method
CN111287769A (en) Tunnel surrounding rock advanced grouting reinforcement structure and construction method thereof
CN111424695B (en) Seepage-proofing and leakage-stopping method for deep-buried karst pipeline
CN113404517B (en) Construction method for tunnel mud bursting and water flushing
CN115012993A (en) Rapid and safe disposal method for tunnel water-rich karst surge body
CN115787693A (en) Water stopping method for water gushing in deep foundation pit under riverside slow-dip interbed
CN112177634B (en) Treatment method for reinforcing primary support of tunnel
CN111441775B (en) Rapid grouting arching reinforcement method before excavation of tunnel in stratum with poor groutability and difficult self-stabilization

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination