WO2016208974A1 - 전력 계통의 주파수 조정용 대용량 배터리 시스템 및 대용량 배터리 운영 방법 - Google Patents

전력 계통의 주파수 조정용 대용량 배터리 시스템 및 대용량 배터리 운영 방법 Download PDF

Info

Publication number
WO2016208974A1
WO2016208974A1 PCT/KR2016/006657 KR2016006657W WO2016208974A1 WO 2016208974 A1 WO2016208974 A1 WO 2016208974A1 KR 2016006657 W KR2016006657 W KR 2016006657W WO 2016208974 A1 WO2016208974 A1 WO 2016208974A1
Authority
WO
WIPO (PCT)
Prior art keywords
capacity
capacity battery
battery
large capacity
bidding
Prior art date
Application number
PCT/KR2016/006657
Other languages
English (en)
French (fr)
Inventor
안건호
최인선
김명회
원동준
최진영
양진선
Original Assignee
주식회사 효성
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 효성 filed Critical 주식회사 효성
Priority to US15/738,568 priority Critical patent/US10411470B2/en
Priority to EP16814687.6A priority patent/EP3316209A4/en
Publication of WO2016208974A1 publication Critical patent/WO2016208974A1/ko

Links

Images

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05FSYSTEMS FOR REGULATING ELECTRIC OR MAGNETIC VARIABLES
    • G05F1/00Automatic systems in which deviations of an electric quantity from one or more predetermined values are detected at the output of the system and fed back to a device within the system to restore the detected quantity to its predetermined value or values, i.e. retroactive systems
    • G05F1/66Regulating electric power
    • G05F1/67Regulating electric power to the maximum power available from a generator, e.g. from solar cell
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/36Arrangements for testing, measuring or monitoring the electrical condition of accumulators or electric batteries, e.g. capacity or state of charge [SoC]
    • G01R31/382Arrangements for monitoring battery or accumulator variables, e.g. SoC
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B13/00Adaptive control systems, i.e. systems automatically adjusting themselves to have a performance which is optimum according to some preassigned criterion
    • G05B13/02Adaptive control systems, i.e. systems automatically adjusting themselves to have a performance which is optimum according to some preassigned criterion electric
    • G05B13/04Adaptive control systems, i.e. systems automatically adjusting themselves to have a performance which is optimum according to some preassigned criterion electric involving the use of models or simulators
    • G05B13/048Adaptive control systems, i.e. systems automatically adjusting themselves to have a performance which is optimum according to some preassigned criterion electric involving the use of models or simulators using a predictor
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/06Buying, selling or leasing transactions
    • G06Q30/08Auctions
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01MPROCESSES OR MEANS, e.g. BATTERIES, FOR THE DIRECT CONVERSION OF CHEMICAL ENERGY INTO ELECTRICAL ENERGY
    • H01M10/00Secondary cells; Manufacture thereof
    • H01M10/42Methods or arrangements for servicing or maintenance of secondary cells or secondary half-cells
    • H01M10/44Methods for charging or discharging
    • H01M10/441Methods for charging or discharging for several batteries or cells simultaneously or sequentially
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J7/00Circuit arrangements for charging or depolarising batteries or for supplying loads from batteries
    • H02J7/0068Battery or charger load switching, e.g. concurrent charging and load supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02E60/10Energy storage using batteries

Definitions

  • the present invention relates to a large capacity battery system and a large capacity battery operating method for managing a large capacity battery used for frequency adjustment of a power system.
  • renewable energy system is a system for researching and developing new energy sources to solve problems such as energy shortage and environmental pollution, and converting existing fossil energy or using sunlight, water, geothermal energy, and bioorganisms. It is characterized by energy used to convert renewable energy and future energy source for sustainable energy supply system.
  • renewable energy systems include wind power generation systems and solar power generation systems.
  • Korean power system should maintain the frequency within 60 ⁇ 0.2Hz according to the notification of reliability.
  • the power system implements a frequency control assistant service for frequency control according to the reliability notification.
  • the frequency control assistant service is composed of a frequency response assistant service and a frequency adjustment assistant service, and each market exists. Accordingly, the development resources participate in the frequency response market or the frequency coordination market to provide frequency control assistance services.
  • Such a market consists of a full-day market and a real-time market
  • the full-day market refers to a market that is opened on the day before the operation
  • the real-time market refers to a market that is additionally opened due to the system status on the day of operation.
  • a technology for predicting a successful bid price of a power transaction market is disclosed. That is, in the related art, when the battery is charged and discharged, the reserve rate and the successful bid price history of the power transaction market are checked to predict a price that can be successful, and bidding is performed to increase the successful bid rate.
  • the optimum charging time is calculated according to the bidding result of the power generation bidding on the demand side.
  • SOC State of Charge
  • the present invention has been made to solve the above problems, the present invention by bidding the bidding capacity and the default value of the large capacity battery participating in the frequency adjustment market by the operation method planned the day before, to operate the large capacity battery economically,
  • the purpose is to manage the remaining capacity of the battery in a stable range.
  • the next day using the history information of the past frequency adjustment signal Calculating an expected frequency adjustment signal, calculating a bidding capacity and a default value of a large capacity battery that meets the expected frequency adjustment signal, determining an operation plan using the calculated bidding capacity and the default value, and in the day-to-day market of frequency adjustment Bidding the bidding capacity and the default value of the large capacity battery according to the operation plan, and if the bidding capacity and the default value of the large capacity battery are successful in the day-to-day market of frequency adjustment, receive and store the frequency adjustment signal in the real-time market of frequency adjustment, Large capacity double according to one frequency adjustment signal Operating the battery.
  • the remaining capacity (State Of Charge, SOC) of the large-capacity battery is within the range between the predetermined lower limit SOC and the upper limit SOC, the bid capacity and the default capacity of the large capacity battery calculated in the previous day's operation plan
  • SOC State Of Charge
  • the bidding capacity and the default value of the large capacity battery is recalculated in real time. Re-bid to the market.
  • the bidding capacity and default value for recharging the large-capacity battery can be re-bidted to the real-time market. have.
  • the bidding capacity and the default value are re-bidted until the remaining capacity of the large-capacity battery becomes a preset basic SOC to re-bid the real-time market to restore the remaining capacity of the large-capacity battery, and the remaining capacity of the large-capacity battery is If the basic SOC is exceeded, it will return to normal state, and the large-capacity battery can be operated with the bid capacity and default value of the large-capacity battery calculated in the previous day's operation plan.
  • the remaining capacity of the large capacity battery rises above the upper limit SOC, it is set to a discharge state for discharging the large capacity battery, and the bidding capacity and the default value for discharging the large capacity battery are recalculated to re-bid in the real time market. Can be.
  • the bidding capacity and the default value are recalculated until the remaining capacity of the large-capacity battery becomes the basic SOC and re-bid to the real-time market to restore the remaining capacity of the large-capacity battery, and the remaining capacity of the large-capacity battery is the basic SOC. If it is below SOC, it can return to normal state and operate the large capacity battery with the bid capacity and default value of the large capacity battery calculated in the previous day's operation plan.
  • the re-bidding prior notice time may be changed according to a rule set in each frequency adjustment market.
  • the bid capacity and the default value may be calculated using an optimization technique.
  • the battery pack has at least one large capacity battery (ESS, Energy Storage System), and output control for managing the output of the large capacity battery.
  • ESS Energy Storage System
  • Manage the device and at least one output control device receive the actual frequency adjustment signal from the frequency adjustment market and store the history, calculate the expected frequency adjustment signal for the next day using the historical information of the past frequency adjustment signal, and Calculate the bid capacity and default value of the large capacity battery according to the expected frequency adjustment signal, determine the operation plan using the calculated bid capacity and the default value, and bid capacity and default value of the large capacity battery according to the operation plan in the day before the frequency adjustment To the market, the day before the frequency adjustment If the bidding capacity and the default value of the large capacity battery is successful, the frequency adjustment signal is received and stored in the real-time market of frequency adjustment, and includes an integrated management device for operating the large capacity battery according to the received frequency adjustment signal.
  • ESS Energy Storage System
  • the integrated management device may operate a large capacity battery as a bidding capacity and a default value of the large capacity battery calculated in the previous day's operation plan when the remaining capacity (SOC) of the large capacity battery is within a range between a preset lower limit SOC and an upper limit SOC. Can be.
  • the integrated management device may re-bid the bidding capacity and the default value of the large capacity battery and re-bid the real time market. Can be.
  • the integrated management device sets the charging state for charging the large-capacity battery, recalculates the bidding capacity and the default value for charging the large-capacity battery in real time. Re-bid to the market.
  • the integrated management device recovers the remaining capacity of the large capacity battery by re-bidding the bidding capacity and the default value in the real time market until the remaining capacity of the large capacity battery becomes the preset basic SOC in the charged state.
  • the large capacity battery can be operated by the bid capacity and default value of the large capacity battery calculated in the previous day's operation plan.
  • the integrated management device sets a discharge state for discharging the large capacity battery, and recalculates a bidding capacity and a default value for discharging the large capacity battery. Re-bid to the real-time market.
  • the integrated management device re-bids the bidding capacity and the default value in the real time market until the remaining capacity of the large capacity battery becomes the basic SOC in the discharged state, thereby restoring the remaining capacity of the large capacity battery.
  • the remaining capacity is less than the basic SOC, it returns to the normal state, and the large capacity battery can be operated based on the bid capacity and the default value of the large capacity battery calculated in the previous day's operation plan.
  • the re-bidding prior notice time may be changed according to a rule set in each frequency adjustment market.
  • the integrated management device may calculate the bid capacity and the default value using an optimization technique.
  • the integrated management device may include a database for storing the frequency adjustment signal received in the real time market of the frequency adjustment.
  • the bidding capacity and the default value are determined in consideration of the remaining capacity of the large-capacity battery, so that the remaining capacity of the large-capacity battery can be stably operated within the preset remaining capacity range.
  • the operator since the bidding capacity and the default value are calculated and the operation plan is determined through the optimization method of the integrated management device including the remaining capacity, the operator can obtain the maximum profit. It has the advantage of being.
  • the present invention it is possible to stably manage the remaining capacity of the large capacity battery by preventing the remaining capacity from exceeding the limited range due to the error of the actual frequency adjustment signal and the expected frequency adjustment signal in the same day operation, It is effective to maintain the maximum profit of the operator by maintaining.
  • the present invention has the effect of increasing the accuracy of determining the expected frequency adjustment signal in the future by storing the actual frequency adjustment signal history in the integrated management device.
  • 1 is an exemplary diagram for describing frequency recovery by a frequency control assistance service.
  • FIG. 2 is a conceptual diagram illustrating a configuration of a large capacity battery system according to an embodiment of the present invention.
  • FIG. 3 is a flowchart illustrating a method of operating a large capacity battery system according to an embodiment of the present invention.
  • FIG. 4 is a view for explaining the default value and bid amount of a large capacity battery according to an embodiment of the present invention.
  • FIG 5 is an exemplary view of an operation plan determined by a large capacity battery system according to an embodiment of the present invention.
  • FIG. 6 is an exemplary view for explaining a charging / discharging method of a large capacity battery in a large capacity battery system according to an exemplary embodiment of the present invention.
  • FIG. 7 is a flowchart illustrating a charging / discharging method of a large capacity battery in a large capacity battery system according to an exemplary embodiment of the present invention.
  • 1 is an exemplary diagram for describing frequency recovery by a frequency control assistance service.
  • the power system is controlled by AGC control by frequency adjustment reserve power bidding on the frequency adjustment 104 market, and GFC control by frequency response reserve power bidding on the frequency response 103 market when leaving the floating zone. To control.
  • the frequency response (103) section is a control section based on the primary reserve power, and the sustaining time is relatively short at least 20 seconds, but is generated by a power source capable of quick response within 10 seconds, and the Pf of the governor Use droop control.
  • Frequency adjustment 104 section is a control section by the secondary reserve force, the response speed is somewhat slow, but is in charge of the power source that can maintain the output for a long time, and adjust the amount of generator of the generator operated below the rated power to recover the frequency do.
  • the power system When an accident such as generator dropout occurs in the normal 101 (102), the frequency is dropped rapidly, the power system performs the GFC control using the frequency response reserve by the frequency drop (103). Because GFC control uses P-f droop control, the frequency cannot be restored to the system frequency according to the reliability notice. Thus, after the GPC control, the power system adjusts the frequency by AGC control using the frequency adjustment reserve force (104). When the frequency is restored by the AGC control (105), the power system is operated in the normal state 101 again.
  • the present invention focuses on the market and operation of frequency adjustment corresponding to AGC control.
  • the large capacity battery system proposed by the present invention schedules bidding capacity and default value of a large capacity battery bidding to the frequency adjustment market the whole day to plan economic bidding, and stably maintains the remaining capacity. It is managed by real-time remaining capacity management method according to system situation on the day.
  • FIG. 2 is a conceptual diagram illustrating a configuration of a large capacity battery system according to an embodiment of the present invention.
  • the large capacity battery system of the present invention includes an output control device 200 and an integrated management device 100.
  • the output control device 200 has at least one large capacity battery (ESS, Energy Storage System) and manages the output of the large capacity battery.
  • ESS Energy Storage System
  • the integrated management device 100 manages at least one output control device 200, receives an actual frequency adjustment signal from the market, stores the history, and determines a full-day and real-time operation plan in consideration of the remaining capacity of the large-capacity battery.
  • the bid of the frequency adjustment market proposed by the present invention can be divided into the day before market and the real time market.
  • the market on the day before is a market that trades the frequency adjustment reserves to be used the next day.
  • the large-capacity battery system of the present invention participates in market bidding the day before using the bidding capacity and the default value.
  • the integrated management device 100 manages at least one output control device, receives the actual frequency adjustment signal from the frequency adjustment market, stores the history, and predicts the next day using the history information of the past frequency adjustment signal. Calculate the frequency adjustment signal.
  • the bidding capacity and the default value of the large capacity battery that meet the expected frequency adjustment signal are calculated, and the operation plan is determined using the calculated bid capacity and the default value.
  • the bidding capacity and the default value of the large capacity battery are bid in accordance with the operation plan in the market on the day before the frequency adjustment, and when the bidding capacity and the default value of the large capacity battery are successful in the day before the frequency adjustment, It receives and stores, and operates a large capacity battery according to the received frequency adjustment signal.
  • the integrated management device 100 of the large capacity battery Operate large capacity batteries with bid capacity and default.
  • the integrated management device 100 recalculates the bidding capacity and the default value of the large capacity battery if the remaining capacity (SOC) of the large capacity battery is not within a range between the preset SOC lower limit and the SOC upper limit . Re-bid.
  • the integrated management device 100 sets the charging state for charging the large capacity battery, recalculates the bidding capacity and the default value for charging the large capacity battery, thereby real-time market. Re-bid on
  • the integrated management device 100 recalculates the bidding capacity and the default value in the real-time market until the remaining capacity of the large capacity battery becomes the SOC base , which is a preset default SOC in the charged state, to recover the remaining capacity of the large capacity battery, If the remaining capacity of the large capacity battery exceeds the SOC base , it will return to normal state and operate the large capacity battery with the bidding capacity and default value of the large capacity battery calculated in the previous day's operation plan.
  • the integrated management device 100 has a remaining capacity of SOC upper When it rises beyond the limit , it is set to the discharge state for discharging the large capacity battery, and the bidding capacity and the default value for discharging the large capacity battery are recalculated to re-bid in the real time market.
  • the integrated management device 100 re-bids the bidding capacity and the default value to the real-time market until the remaining capacity of the large capacity battery becomes SOC base in the discharge state, thereby restoring the remaining capacity of the large capacity battery, and the remaining capacity of the large capacity battery When it is below SOC base , it returns to normal state and operates the large capacity battery with the bidding capacity and default value of the large capacity battery calculated in the previous day's operation plan.
  • the re-bidding prior notice time may be changed according to the rules set in each frequency adjustment market.
  • the integrated management device 100 may calculate a bidding capacity and a default value using an optimization technique.
  • the integrated management apparatus 100 may include a database for storing the frequency adjustment signal received in the real-time market of frequency adjustment.
  • FIG. 4 is a view for explaining the default value and bid amount of a large capacity battery according to an embodiment of the present invention.
  • the bidding capacity 402 refers to a capacity that a large capacity battery bids on the market the day before.
  • the large-capacity battery outputs the output corresponding to the power supply command from the integrated management device according to the bidding capacity.
  • the default value 401 indicates an output point at which the large capacity battery is constantly operating.
  • the initial default value is 0, which indicates no charging or discharging, and the large capacity battery outputs only the output corresponding to the power supply instruction based on the default value.
  • the large capacity battery outputs as much as the default value, and when the power supply instruction is issued based on the default value additionally outputs the power supply instruction.
  • the bid capacity 402 and the default value 401 are applied in the same manner in the real time market.
  • FIG. 3 is a flowchart illustrating a method of operating a large capacity battery system according to an embodiment of the present invention.
  • the integrated management device 100 calculates an expected frequency adjustment signal the next day using the past frequency adjustment signal history and weather information stored in a database in the integrated management device 100 (S301). S303).
  • the bidding capacity and the default value corresponding to the estimated frequency adjustment signal calculated using the optimization technique are calculated and the operation plan is set (S305).
  • the operation plan is that the large-capacity battery system is the SOC lower limit , which is the lower SOC that sets the remaining capacity of the battery (State Of Charge, SOC), and SOC upper , which is the upper SOC. It is controlled within the limit and refers to the operation plan to operate the large capacity battery system by bidding the bidding capacity and the default value to get the maximum profit.
  • the integrated management device 100 bids the bidding capacity and the default value according to the operation plan to the market the day before (S307).
  • the large-capacity battery system When the large-capacity battery system receives a successful bid in the market (S309), the large-capacity battery is operated by receiving the actual frequency adjustment signal in the same day operation (S311, S313), and stored as a database of the integrated management device 100, and the actual frequency adjustment According to the signal, the output is considered considering the bidding capacity and the default value.
  • the large capacity battery When SOC, the remaining capacity of the large capacity battery, is within the range of the SOC lower limit and the SOC upper limit , the large capacity battery is operated at the bidding capacity and the default value calculated in the previous day's operation plan (S317).
  • the bidding capacity and the default value are recalculated and re-bided (S319).
  • FIG 5 is an exemplary view of an operation plan determined by a large capacity battery system according to an embodiment of the present invention.
  • 501 is the time remaining capacity expected in the large-capacity battery system operation plan
  • 502 is the time zone default value.
  • the remaining capacity of the large-capacity battery is set when the remaining capacity (SOC) of the large-capacity battery is less than the SOC lower limit set or the SOC upper limit is exceeded.
  • the bidding capacity and the default value are recalculated and re-bid to the real-time market (S319).
  • the ratio of the output size and the charge / discharge signal is changed, and the remaining capacity of the large capacity battery can be charged or discharged, so that the remaining capacity of the large capacity battery is between the SOC lower limit and the SOC upper limit . You can manage from.
  • FIG. 6 is an exemplary view for explaining a charging and discharging method of a large capacity battery in a large capacity battery system according to an embodiment of the present invention
  • Figure 7 is a charging and discharging method of a large capacity battery in a large capacity battery system according to an embodiment of the present invention. Is a flow chart showing.
  • 6 and 7 show that the error between the estimated frequency adjustment signal calculated using the past frequency adjustment signal history and the actual frequency adjustment signal is increased in the same day operation of the large capacity battery system, so that the remaining capacity of the large capacity battery is less than the SOC lower limit .
  • This is an exemplary view for explaining the charging and discharging method for preventing the deviation of the remaining capacity in the real-time operation of a large capacity battery when the problem falls or exceeds the SOC upper limit .
  • the large capacity battery system bids to the market the day before without a separate control. Maintain the default value and maintain the default value.
  • the large capacity battery system is set to the state of charge, change the bidding capacity and the default value for charging to re-bid and operate in the real-time market (610).
  • the remaining capacity of a large-capacity battery is SOC upper If the limit is exceeded (622), the large-capacity battery system is set to a discharged state, and the bidding capacity and default value are changed for the discharge and re-bid and operated in the real-time market (630).
  • the re-bid prior notice time is changed according to the rules of each frequency adjustment market.
  • the large capacity battery system determines the state of the large capacity battery (S703).
  • step S715 SOC lower limit ⁇ SOC ⁇ SOC upper If it is out of the limit , the remaining capacity SOC ⁇ SOC lower limit is set to the state of charge (S723), the default value and bidding capacity is recalculated and re-bided (S725), and if the SOC upper limit ⁇ SOC is set to the discharged state ( S727), recalculates the default value and bidding capacity (S729).
  • step S703 If the current state of the large-capacity battery is a state of charge in step S703, if SOC ⁇ SOC base (S705), the default value and bidding capacity in the state of charge is recalculated and re-entered (S707, S711).
  • the SOC When the SOC is charged to the SOC base in step S705, it is set to the normal state (S709), and the large-capacity battery is operated with the default value and bidding capacity calculated in the previous day's operation plan (S713).
  • step S703 If the current state of the large-capacity battery is a discharge state in step S703, if SOC base ⁇ SOC (S731), the default value and bidding capacity in the discharge state are recalculated and re-entered (S733, S735).
  • the SOC When the SOC is discharged to the SOC base in step S731, it is set to a normal state (S737), and the large-capacity battery is operated at the default value and bidding capacity calculated in the previous day's operation plan (S739).
  • the present invention relates to a large capacity battery system and a large capacity battery operating method, which can be used in the large capacity battery field.

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Economics (AREA)
  • Health & Medical Sciences (AREA)
  • Theoretical Computer Science (AREA)
  • Strategic Management (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Accounting & Taxation (AREA)
  • Finance (AREA)
  • Power Engineering (AREA)
  • Automation & Control Theory (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Tourism & Hospitality (AREA)
  • Primary Health Care (AREA)
  • Human Resources & Organizations (AREA)
  • General Health & Medical Sciences (AREA)
  • Sustainable Development (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Electromagnetism (AREA)
  • Sustainable Energy (AREA)
  • Development Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Medical Informatics (AREA)
  • Evolutionary Computation (AREA)
  • Artificial Intelligence (AREA)
  • Software Systems (AREA)
  • Manufacturing & Machinery (AREA)
  • Computer Vision & Pattern Recognition (AREA)
  • Chemical & Material Sciences (AREA)
  • General Chemical & Material Sciences (AREA)
  • Electrochemistry (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Charge And Discharge Circuits For Batteries Or The Like (AREA)
  • Secondary Cells (AREA)

Abstract

본 발명은 전력 계통의 주파수 조정에 사용되는 대용량 배터리를 관리하는 대용량 배터리 시스템 및 대용량 배터리 운영 방법에 관한 것으로서, 본 발명의 전력 계통의 주파수 조정(Frequency Regulation)에 사용되는 대용량 배터리를 관리하는 대용량 배터리 시스템에서의 대용량 배터리 운영 방법에서, 과거 주파수 조정 신호의 이력 정보를 사용하여 다음날의 예상 주파수 조정 신호를 산출하는 단계, 상기 예상 주파수 조정 신호에 맞는 대용량 배터리의 입찰 용량과 기본값을 계산하는 단계, 계산된 입찰 용량과 기본값을 이용하여 운영 계획을 결정하는 단계, 주파수 조정의 전일 시장에서 상기 운영 계획에 따라 대용량 배터리의 입찰 용량과 기본값을 입찰하는 단계 및 주파수 조정의 전일 시장에서 대용량 배터리의 입찰 용량과 기본값이 낙찰되면, 주파수 조정의 실시간 시장에서 주파수 조정 신호를 수신하여 저장하고, 수신한 주파수 조정 신호에 따라 대용량 배터리를 운영하는 단계를 포함한다.

Description

전력 계통의 주파수 조정용 대용량 배터리 시스템 및 대용량 배터리 운영 방법
본 발명은 전력 계통의 주파수 조정에 사용되는 대용량 배터리를 관리하는 대용량 배터리 시스템 및 대용량 배터리 운영 방법에 관한 것이다.
환경 파괴, 자원 고갈 등이 문제되면서, 전력을 저장하고, 저장된 전력을 효율적으로 활용할 수 있는 시스템에 대한 관심이 높아지고 있다. 또한 태양광 발전 등 신재생 에너지의 중요성이 증대되고 있다. 특히 신재생 에너지는 태양광, 풍력, 조력 등 무한히 공급되는 천연 자원을 이용하고, 발전 과정에서 공해를 유발하지 않아, 그 활용 방안에 대한 연구가 활발히 진행 중이다.
일반적으로 신재생 에너지 시스템은, 에너지 부족과 환경 오염 등의 문제를 해결하고자 새로운 에너지원을 연구, 개발하는 시스템으로 기존 화석 에너지를 변환시켜 이용하거나, 햇빛, 물, 지열, 생물유기체 등을 포함하는 재생가능한 에너지를 변환시켜 이용하는 에너지, 지속 가능한 에너지 공급체계를 위한 미래에너지원을 그 특성으로 한다. 이러한 신재생 에너지 시스템에는 풍력 발전 시스템, 태양광 발전 시스템 등이 있다.
우리나라 전력계통은 신뢰도 고시에 따라 주파수를 60±0.2Hz 이내로 유지해야 한다. 이러한 전력계통은 신뢰도 고시에 따른 주파수 제어를 위해 주파수 제어 보조 서비스를 시행하고 있으며, 주파수 제어 보조 서비스는 주파수 응답 보조서비스와 주파수 조정 보조서비스로 구성되고, 각각의 시장이 존재한다. 이에 발전 자원들은 주파수응답 시장이나 주파수조정 시장에 참여하여 주파수 제어 보조 서비스를 제공하게 된다.
이러한 시장은 전일 시장과 실시간 시장으로 이루어지며, 전일 시장은 운영 하루 전일에 열리는 시장을 의미하고, 실시간 시장은 운영 당일 계통 상황 등의 이유로 추가적으로 열리는 시장을 의미한다. 주파수 조정 시장에 대용량 배터리가 입찰하여 주파수 조정을 수행하게 된다면 빠른 응답속도로 높은 신뢰도를 보장할 수 있고, 계통에 병입되어 증감발 운전하던 기존 발전기에 대한 고정 출력 및 최대 출력이 가능하게 된다. 하지만 대용량 배터리의 용량 제한으로 대용량 배터리의 주파수 조정 시장 참여에 제약이 따른다.
종래 배터리 충방전 기술에 있어서, 전력 거래 시장의 낙찰가를 예상하는 기술이 개시되어 있다. 즉, 종래에는 배터리 충방전시, 전력 거래 시장의 예비율이나 낙찰가 이력을 확인하여 낙찰 가능한 가격을 예측하고, 이를 이용하여 입찰을 시행함으로써, 낙찰률을 높일 수 있도록 하는 것이다.
그러나, 종래에는 낙찰가 이력에 따른 배터리의 낙찰에 관한 기술만 개시되어 있으며, 낙찰 후 배터리의 운영 방법에 대한 기술은 전무한 상태이며, 따라서 효율적이고 경제적인 배터리 운영이 어렵다고 하는 문제점이 있다.
또한, 배터리의 잔존 용량인 SOC(State of Charge) 관리에 있어서 수요측의 발전 입찰의 낙찰 결과에 따라 최적 충전 시간을 산출하기 때문에, 배터리를 실시간으로 신호가 변화하는 주파수 조정 예비력으로 사용 시, 배터리의 잔존 용량이 지속적으로 감소하거나 증가하여 배터리의 충방전 허용치를 초과하게 되는 문제점이 발생한다. 따라서 배터리를 주파수 조정 예비력으로 사용할 경우, 배터리를 보다 효율적이고 경제적으로 운영할 수 있고, 배터리의 잔존 용량을 안정적으로 관리할 수 있는 시스템이 필요하다.
본 발명은 상기와 같은 문제점을 해결하기 위하여 안출된 것으로서, 본 발명은 주파수 조정 시장에 참여하는 대용량 배터리의 입찰용량과 기본값을 전일 계획한 운영방법으로 입찰하여, 대용량 배터리를 경제적으로 운영하며, 대용량 배터리의 잔존 용량을 안정적인 범위에서 관리하는데 그 목적이 있다.
또한 당일 계통 상황에 따른 신호에 의해 대용량 배터리의 잔존 용량이 안정적인 범위에서 벗어날 경우, 입찰용량과 기본값을 재입찰하여 대용량 배터리의 잔존 용량을 회복시키는 것에 그 다른 목적이 있다.
본 발명의 목적은 이상에서 언급한 목적으로 제한되지 않으며, 언급되지 않은 또 다른 목적들은 아래의 기재로부터 당업자에게 명확하게 이해될 수 있을 것이다.
이와 같은 목적을 달성하기 위한 본 발명의 전력 계통의 주파수 조정(Frequency Regulation)에 사용되는 대용량 배터리를 관리하는 대용량 배터리 시스템에서의 대용량 배터리 운영 방법에서, 과거 주파수 조정 신호의 이력 정보를 사용하여 다음날의 예상 주파수 조정 신호를 산출하는 단계, 상기 예상 주파수 조정 신호에 맞는 대용량 배터리의 입찰 용량과 기본값을 계산하는 단계, 계산된 입찰 용량과 기본값을 이용하여 운영 계획을 결정하는 단계, 주파수 조정의 전일 시장에서 상기 운영 계획에 따라 대용량 배터리의 입찰 용량과 기본값을 입찰하는 단계 및 주파수 조정의 전일 시장에서 대용량 배터리의 입찰 용량과 기본값이 낙찰되면, 주파수 조정의 실시간 시장에서 주파수 조정 신호를 수신하여 저장하고, 수신한 주파수 조정 신호에 따라 대용량 배터리를 운영하는 단계를 포함한다.
상기 대용량 배터리를 운영하는 단계에서, 대용량 배터리의 잔존 용량(State Of Charge, SOC)이 미리 설정된 하한 SOC와 상한 SOC 사이의 범위 내에 있으면, 전일 운영 계획에서 산출된 대용량 배터리의 입찰 용량과 기본값으로 대용량 배터리를 운영할 수 있다.
상기 대용량 배터리를 운영하는 단계에서, 상기 대용량 배터리의 잔존 용량(State Of Charge, SOC)이 미리 설정된 하한 SOC와 상한 SOC 사이의 범위 내에 있지 않으면, 상기 대용량 배터리의 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰할 수 있다.
상기 대용량 배터리의 잔존 용량이 상기 하한 SOC 미만으로 하락하는 경우, 상기 대용량 배터리를 충전시키기 위한 충전 상태로 설정하고, 상기 대용량 배터리를 충전하기 위한 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰할 수 있다.
상기 충전 상태에서 상기 대용량 배터리의 잔존 용량이 미리 설정된 기본 SOC가 될 때까지 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰하여 상기 대용량 배터리의 잔존 용량을 회복시키고, 상기 대용량 배터리의 잔존 용량이 상기 기본 SOC를 초과하면 다시 정상 상태로 복귀하여, 전일 운영 계획에서 산출된 대용량 배터리의 입찰 용량과 기본값으로 대용량 배터리를 운영할 수 있다.
상기 대용량 배터리의 잔존 용량이 상기 상한 SOC 을 초과하여 상승하는 경우, 상기 대용량 배터리를 방전시키기 위한 방전 상태로 설정하고, 상기 대용량 배터리를 방전하기 위한 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰할 수 있다.
상기 방전 상태에서 상기 대용량 배터리의 잔존 용량이 상기 기본 SOC가 될 때까지 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰하여 상기 대용량 배터리의 잔존 용량을 회복시키고, 상기 대용량 배터리의 잔존 용량이 상기 기본 SOC 미만이 되면, 다시 정상 상태로 복귀하여, 전일 운영 계획에서 산출된 대용량 배터리의 입찰 용량과 기본값으로 대용량 배터리를 운영할 수 있다.
상기 대용량 배터리의 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰함에 있어서, 각 주파수 조정 시장에서 정해진 규칙에 따라 재입찰 사전 통보시간이 변경될 수 있다.
상기 예상 주파수 조정 신호에 맞는 대용량 배터리의 입찰 용량과 기본값을 계산하는 단계에서, 최적화 기법을 이용하여 상기 입찰 용량과 기본값을 계산할 수 있다.
본 발명의 전력 계통의 주파수 조정(Frequency Regulation)에 사용되는 대용량 배터리를 관리하는 대용량 배터리 시스템에서, 적어도 하나 이상의 대용량 배터리(ESS, Energy Storage System)를 가지며, 상기 대용량 배터리의 출력을 관리하는 출력 제어 장치 및 적어도 하나 이상의 출력 제어 장치를 관리하며, 주파수 조정 시장으로부터 실제 주파수 조정 신호를 수신하여 그 이력을 저장하고, 과거 주파수 조정 신호의 이력 정보를 사용하여 다음날의 예상 주파수 조정 신호를 산출하고, 상기 예상 주파수 조정 신호에 맞는 대용량 배터리의 입찰 용량과 기본값을 계산하고, 계산된 입찰 용량과 기본값을 이용하여 운영 계획을 결정하고, 주파수 조정의 전일 시장에서 상기 운영 계획에 따라 대용량 배터리의 입찰 용량과 기본값을 입찰하고, 주파수 조정의 전일 시장에서 대용량 배터리의 입찰 용량과 기본값이 낙찰되면, 주파수 조정의 실시간 시장에서 주파수 조정 신호를 수신하여 저장하고, 수신한 주파수 조정 신호에 따라 대용량 배터리를 운영하는 통합 관리 장치를 포함한다.
상기 통합 관리 장치는 대용량 배터리의 잔존 용량(State Of Charge, SOC)이 미리 설정된 하한 SOC와 상한 SOC 사이의 범위 내에 있으면, 전일 운영 계획에서 산출된 대용량 배터리의 입찰 용량과 기본값으로 대용량 배터리를 운영할 수 있다.
상기 통합 관리 장치는 상기 대용량 배터리의 잔존 용량(State Of Charge, SOC)이 미리 설정된 하한 SOC와 상한 SOC 사이의 범위 내에 있지 않으면, 상기 대용량 배터리의 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰할 수 있다.
상기 통합 관리 장치는 상기 대용량 배터리의 잔존 용량이 상기 하한 SOC 미만으로 하락하는 경우, 상기 대용량 배터리를 충전시키기 위한 충전 상태로 설정하고, 상기 대용량 배터리를 충전하기 위한 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰할 수 있다.
상기 통합 관리 장치는 상기 충전 상태에서 상기 대용량 배터리의 잔존 용량이 미리 설정된 기본 SOC가 될 때까지 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰하여 상기 대용량 배터리의 잔존 용량을 회복시키고, 상기 대용량 배터리의 잔존 용량이 상기 기본 SOC를 초과하면 다시 정상 상태로 복귀하여, 전일 운영 계획에서 산출된 대용량 배터리의 입찰 용량과 기본값으로 대용량 배터리를 운영할 수 있다.
상기 통합 관리 장치는 상기 대용량 배터리의 잔존 용량이 상기 상한 SOC 을 초과하여 상승하는 경우, 상기 대용량 배터리를 방전시키기 위한 방전 상태로 설정하고, 상기 대용량 배터리를 방전하기 위한 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰할 수 있다.
상기 통합 관리 장치는 상기 방전 상태에서 상기 대용량 배터리의 잔존 용량이 상기 기본 SOC가 될 때까지 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰하여 상기 대용량 배터리의 잔존 용량을 회복시키고, 상기 대용량 배터리의 잔존 용량이 상기 기본 SOC 미만이 되면, 다시 정상 상태로 복귀하여, 전일 운영 계획에서 산출된 대용량 배터리의 입찰 용량과 기본값으로 대용량 배터리를 운영할 수 있다.
상기 대용량 배터리의 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰함에 있어서, 각 주파수 조정 시장에서 정해진 규칙에 따라 재입찰 사전 통보시간이 변경될 수 있다.
상기 통합 관리 장치는 최적화 기법을 이용하여 상기 입찰 용량과 기본값을 계산할 수 있다.
상기 통합 관리 장치는 상기 주파수 조정의 실시간 시장에서 수신한 주파수 조정 신호를 저장하기 위한 데이터베이스를 포함할 수 있다.
본 발명에 의하면 대용량 배터리의 잔존 용량을 고려하여 입찰 용량과 기본값을 결정하여 전일 시장에 입찰하기 때문에 대용량 배터리의 잔존용량을 미리 설정한 잔존용량 범위 안에서 안정적으로 운영할 수 있다는 효과가 있다.
또한, 본 발명에 의하면 잔존 용량 고려를 포함하여 통합 관리 장치의 최적화 방법을 통해, 최대의 수익을 얻을 수 있는 입찰 용량과 기본값을 산출하고 운영 계획을 결정하기 때문에, 사업자는 최대 수익을 얻을 수 있게 되는 장점이 있다.
또한, 본 발명에 의하면 당일 운영에 있어서 실제 주파수조정 신호와 예상 주파수조정 신호의 오차에 의해 잔존 용량이 제한범위를 벗어나는 것을 방지하여 대용량 배터리의 잔존 용량을 안정적으로 관리할 수 있고, 전일 운영 계획을 유지하여 사업자의 최대 수익을 유지할 수 있는 효과가 있다.
또한, 본 발명에 의하면 통합 관리 장치에 실제 주파수 조정 신호 이력을 저장하여 향후 예상 주파수 조정 신호를 결정하는데 정확성을 높일 수 있다는 효과가 있다.
도 1은 주파수 제어 보조 서비스에 의한 주파수 회복을 설명하기 위한 예시도이다.
도 2는 본 발명의 일 실시예에 따른 대용량 배터리 시스템의 구성을 보여주는 개념도이다.
도 3은 본 발명의 일 실시예에 따른 대용량 배터리 시스템의 운영 방법을 보여주는 흐름도이다.
도 4는 본 발명의 일 실시예에 따른 대용량 배터리의 기본값과 입찰 요량을 설명하기 위한 도면이다.
도 5는 본 발명의 일 실시예에 따른 대용량 배터리 시스템에서 결정한 운영 계획의 예시도이다.
도 6은 본 발명의 일 실시예에 따른 대용량 배터리 시스템에서 대용량 배터리의 충방전 방법을 설명하기 위한 예시도이다.
도 7은 본 발명의 일 실시예에 따른 대용량 배터리 시스템에서 대용량 배터리의 충방전 방법을 보여주는 흐름도이다.
본 발명은 다양한 변경을 가할 수 있고 여러 가지 실시예를 가질 수 있는 바, 특정 실시예들을 도면에 예시하고 상세하게 설명하고자 한다. 그러나, 이는 본 발명을 특정한 실시 형태에 대해 한정하려는 것이 아니며, 본 발명의 사상 및 기술 범위에 포함되는 모든 변경, 균등물 내지 대체물을 포함하는 것으로 이해되어야 한다.
본 출원에서 사용한 용어는 단지 특정한 실시예를 설명하기 위해 사용된 것으로, 본 발명을 한정하려는 의도가 아니다. 단수의 표현은 문맥상 명백하게 다르게 뜻하지 않는 한, 복수의 표현을 포함한다. 본 출원에서, "포함하다" 또는 "가지다" 등의 용어는 명세서상에 기재된 특징, 숫자, 단계, 동작, 구성요소, 부품 또는 이들을 조합한 것이 존재함을 지정하려는 것이지, 하나 또는 그 이상의 다른 특징들이나 숫자, 단계, 동작, 구성요소, 부품 또는 이들을 조합한 것들의 존재 또는 부가 가능성을 미리 배제하지 않는 것으로 이해되어야 한다.
다르게 정의되지 않는 한, 기술적이거나 과학적인 용어를 포함해서 여기서 사용되는 모든 용어들은 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자에 의해 일반적으로 이해되는 것과 동일한 의미를 갖고 있다. 일반적으로 사용되는 사전에 정의되어 있는 것과 같은 용어들은 관련 기술의 문맥 상 갖는 의미와 일치하는 의미를 갖는 것으로 해석되어야 하며, 본 출원에서 명백하게 정의하지 않는 한, 이상적이거나 과도하게 형식적인 의미로 해석되지 않는다.
또한, 첨부 도면을 참조하여 설명함에 있어, 도면 부호에 관계없이 동일한 구성 요소는 동일한 참조부호를 부여하고 이에 대한 중복되는 설명은 생략하기로 한다. 본 발명을 설명함에 있어서 관련된 공지 기술에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우 그 상세한 설명을 생략한다.
도 1은 주파수 제어 보조 서비스에 의한 주파수 회복을 설명하기 위한 예시도이다.
도 1을 참조하면, 전력계통은 주파수 조정(104) 시장에 입찰한 주파수조정 예비력에 의한 AGC 제어와, 부동대를 벗어날 경우 주파수 응답(103) 시장에 입찰한 주파수응답 예비력에 의한 GFC 제어로 주파수를 제어한다.
주파수 응답(Frequency Response)(103) 구간은 1차 예비력에 의한 제어 구간으로서, 최소 20초 정도로 지속 가능 시간은 상대적으로 짧지만, 10초 이내의 빠른 응답이 가능한 발전원이 담당하고, 조속기의 P-f 드룹(Droop) 제어를 사용한다.
주파수 조정(104) 구간은 2차 예비력에 의한 제어 구간으로서, 응답 속도는 다소 느리지만 오랫동안 출력을 유지할 수 있는 발전원이 담당하고, 정격 출력 이하로 운전되는 발전기의 발전량을 조정하여 주파수를 회복하게 된다.
평상시(101)에 발전기 탈락 등의 사고가 발생(102)하게 되면, 주파수가 급격하게 하락하게 되고, 전력계통은 주파수 하락에 의해 주파수 응답 예비력을 사용한 GFC 제어를 수행한다(103). GFC 제어는 P-f 드룹(Droop) 제어를 사용하기 때문에 주파수를 신뢰도 고시에 따른 계통 주파수까지 회복시키지 못한다. 그래서 전력계통은 GPC 제어 후에, 주파수 조정 예비력을 사용한 AGC 제어로 주파수를 조정한다(104). AGC 제어에 의해 주파수가 회복되면(105), 전력계통은 다시 평상시(101) 상태로 동작하게 된다. 본 발명은 AGC 제어에 해당하는 주파수 조정의 시장과 운영에 대한 부분에 초점이 맞춰져 있다.
본 발명에서 제안하는 대용량 배터리 시스템은 주파수 조정 보조 서비스를 제공하기 위해, 주파수 조정 시장에 입찰하는 대용량 배터리의 입찰용량과 기본값을 전일 스케쥴링(scheduling)하여 경제적인 입찰을 계획하고, 안정적으로 잔존용량을 관리하며, 당일 계통 상황에 의한 실시간 잔존 용량 관리 방법으로 이루어져있다.
도 2는 본 발명의 일 실시예에 따른 대용량 배터리 시스템의 구성을 보여주는 개념도이다.
도 2를 참조하면, 본 발명의 대용량 배터리 시스템은 출력 제어 장치(200)과 통합 관리 장치(100)으로 이루어진다.
출력 제어 장치(200)은 적어도 하나 이상의 대용량 배터리(ESS, Energy Storage System)를 가지며 대용량 배터리의 출력을 관리한다.
통합 관리 장치(100)은 적어도 하나 이상의 출력 제어 장치(200)을 관리하며, 시장으로부터 실제 주파수 조정 신호를 받아 그 이력을 저장하고, 대용량 배터리의 잔존 용량을 고려한 전일 및 실시간 운영 계획을 결정한다.
본 발명에서 제안하는 주파수 조정 시장의 입찰은 전일 시장과 실시간 시장으로 나눌 수 있다. 전일 시장은 다음날 사용될 주파수조정 예비력을 시간대 별로 거래하는 시장을 말한다.
본 발명의 대용량 배터리 시스템은 입찰 용량과 기본값을 사용하여 전일 시장 입찰에 참여한다.
본 발명에서 통합 관리 장치(100)는 적어도 하나 이상의 출력 제어 장치를 관리하며, 주파수 조정 시장으로부터 실제 주파수 조정 신호를 수신하여 그 이력을 저장하고, 과거 주파수 조정 신호의 이력 정보를 사용하여 다음날의 예상 주파수 조정 신호를 산출한다. 그리고, 예상 주파수 조정 신호에 맞는 대용량 배터리의 입찰 용량과 기본값을 계산하고, 계산된 입찰 용량과 기본값을 이용하여 운영 계획을 결정한다. 그리고, 주파수 조정의 전일 시장에서 운영 계획에 따라 대용량 배터리의 입찰 용량과 기본값을 입찰하고, 주파수 조정의 전일 시장에서 대용량 배터리의 입찰 용량과 기본값이 낙찰되면, 주파수 조정의 실시간 시장에서 주파수 조정 신호를 수신하여 저장하고, 수신한 주파수 조정 신호에 따라 대용량 배터리를 운영한다.
통합 관리 장치(100)는 대용량 배터리의 잔존 용량(State Of Charge, SOC)이 미리 설정된 하한 SOC인 SOClower limit 와 상한 SOC인 SOCupper limit 사이의 범위 내에 있으면, 전일 운영 계획에서 산출된 대용량 배터리의 입찰 용량과 기본값으로 대용량 배터리를 운영한다.
통합 관리 장치(100)는 대용량 배터리의 잔존 용량(State Of Charge, SOC)이 미리 설정된 SOClower limit와 SOCupper limit 사이의 범위 내에 있지 않으면, 대용량 배터리의 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰한다.
통합 관리 장치(100)는 대용량 배터리의 잔존 용량이 SOClower limit 미만으로 하락하는 경우, 대용량 배터리를 충전시키기 위한 충전 상태로 설정하고, 대용량 배터리를 충전하기 위한 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰한다.
통합 관리 장치(100)는 충전 상태에서 대용량 배터리의 잔존 용량이 미리 설정된 기본 SOC인 SOCbase가 될 때까지 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰하여 상기 대용량 배터리의 잔존 용량을 회복시키고, 대용량 배터리의 잔존 용량이 SOCbase를 초과하면 다시 정상 상태로 복귀하여, 전일 운영 계획에서 산출된 대용량 배터리의 입찰 용량과 기본값으로 대용량 배터리를 운영한다.
통합 관리 장치(100)는 대용량 배터리의 잔존 용량이 SOCupper limit 을 초과하여 상승하는 경우, 대용량 배터리를 방전시키기 위한 방전 상태로 설정하고, 대용량 배터리를 방전하기 위한 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰한다.
통합 관리 장치(100)는 방전 상태에서 대용량 배터리의 잔존 용량이 SOCbase가 될 때까지 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰하여 대용량 배터리의 잔존 용량을 회복시키고, 대용량 배터리의 잔존 용량이 SOCbase 미만이 되면, 다시 정상 상태로 복귀하여, 전일 운영 계획에서 산출된 대용량 배터리의 입찰 용량과 기본값으로 대용량 배터리를 운영한다.
대용량 배터리의 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰함에 있어서, 각 주파수 조정 시장에서 정해진 규칙에 따라 재입찰 사전 통보시간이 변경될 수 있다.
통합 관리 장치(100)는 최적화 기법을 이용하여 입찰 용량과 기본값을 계산할 수 있다.
통합 관리 장치(100)는 주파수 조정의 실시간 시장에서 수신한 주파수 조정 신호를 저장하기 위한 데이터베이스를 포함하여 이루어질 수 있다.
도 4는 본 발명의 일 실시예에 따른 대용량 배터리의 기본값과 입찰 요량을 설명하기 위한 도면이다.
도 4에서 입찰 용량(402)이란 대용량 배터리가 전일 시장에 입찰하는 용량을 말한다. 입찰한 용량이 낙찰되었을 경우, 대용량 배터리는 입찰 용량에 따라 통합 관리 장치에서 내려오는 급전 명령에 맞는 출력을 내게 된다.
또한, 기본값(401)은 대용량 배터리가 상시 운전하고 있는 출력 지점을 나타낸다. 기본적으로 초기 기본값은 0 을 기준으로 하고, 이는 충전이나 방전을 하고 있지 않은 상태를 나타내며, 대용량 배터리는 기본값을 기준으로 하여 급전 지시에 맞는 출력만을 내게 된다.
또한 기본값(401)을 변경하여 운전하게 되면 대용량 배터리는 상시 기본값만큼의 출력을 내고, 급전 지시가 내려올 경우 기본값을 기준으로 하여 추가로 급전 지시만큼의 출력을 내게 된다.
입찰 용량(402)과 기본값(401)은 실시간 시장에서도 같은 방식으로 적용된다.
도 3은 본 발명의 일 실시예에 따른 대용량 배터리 시스템의 운영 방법을 보여주는 흐름도이다.
도 3을 참조하면, 통합 관리 장치(100)은 통합 관리 장치(100) 내에 있는 데이터베이스에 저장되어 있는(S301), 과거 주파수 조정 신호 이력과 날씨정보를 사용하여 다음날 예상 주파수 조정 신호를 산출한다(S303).
그리고, 최적화 기법을 사용하여 산출한 예상 주파수 조정 신호에 맞는 입찰용량과 기본값을 계산하고 운영 계획을 설정한다(S305). 여기서 운영계획은 대용량 배터리 시스템은 배터리의 잔존 용량(State Of Charge, SOC)을 설정한 하한 SOC인 SOClower limit과 상한 SOC인 SOCupper limit의 범위 내에서 제어하며, 최대의 수익을 얻을 수 있는 입찰 용량과 기본값을 입찰하여 대용량 배터리 시스템을 운영하는 운영계획을 말한다.
다음, 통합 관리 장치(100)은 운영 계획에 따른 입찰 용량과 기본값을 전일 시장에 입찰한다(S307).
대용량 배터리 시스템은 전일 시장에서 낙찰받게 되면(S309), 당일 운영에서 실제 주파수조정 신호를 수신하여 대용량 배터리를 운영하게 되는데(S311, S313), 통합 관리 장치(100)의 데이터베이스로 저장하고, 실제 주파수 조정 신호에 따라서 입찰용량과 기본값을 고려한 출력을 낸다.
대용량 배터리의 잔존 용량인 SOC가 SOClower limit과 SOCupper limit의 범위 안에 있으면, 전일 운영계획에서 산출된 입찰 용량과 기본값으로 대용량 배터리를 운영한다(S317).
그러나, SOC가 SOClower limit과 SOCupper limit의 범위 안에 있지 않으면, 입찰 용량과 기본값을 재산출하고 재입찰한다(S319).
도 5는 본 발명의 일 실시예에 따른 대용량 배터리 시스템에서 결정한 운영 계획의 예시도이다.
도 5를 참조하면, 501은 대용량 배터리 시스템 운영계획에서 예상하는 시간대별 잔존 용량이며, 502는 시간대별 기본값을 나타낸다.
대용량 배터리 시스템은 당일 운영에 있어 대용량 배터리의 잔존 용량 관리를 위하여 대용량 배터리의 잔존용량(SOC)이 설정한 SOClower limit 미만이거나, 상기 SOCupper limit을 초과하게 되면, 대용량 배터리의 잔존 용량을 설정한 SOClower limit 와 SOCupper limit 사이로 회복시키기 위해, 입찰용량과 기본값을 재산출하고, 실시간 시장에 재입찰하게 된다(S319).
입찰용량과 기본값을 변경하게 되면, 출력의 크기와 충방전 신호의 비율이 바뀌게 되고, 대용량 배터리의 잔존 용량을 충전시키거나 방전시킬 수 있어서, 대용량 배터리의 잔존 용량을 SOClower limit 와 SOCupper limit 사이에서 관리할 수 있게 된다.
도 6은 본 발명의 일 실시예에 따른 대용량 배터리 시스템에서 대용량 배터리의 충방전 방법을 설명하기 위한 예시도이고, 도 7은 본 발명의 일 실시예에 따른 대용량 배터리 시스템에서 대용량 배터리의 충방전 방법을 보여주는 흐름도이다.
도 6과 도 7은 대용량 배터리 시스템의 당일 운영에 있어, 과거 주파수 조정 신호 이력을 사용하여 산출한 예상 주파수 조정 신호와, 실제 주파수 조정 신호와의 오차가 커져 대용량 배터리의 잔존 용량이 SOClower limit 미만으로 하락하거나, SOCupper limit 을 초과하는 문제가 발생할 시, 대용량 배터리의 실시간 운영에서 잔존용량의 제한범위 이탈을 방지하기 위한 충방전 방법을 설명하기 위한 예시도이다.
도 6을 참조하면, 대용량 배터리의 실시간 운영에서 배터리의 잔존용량이 미리 설정한 SOClower limit 와 SOCupper limit 내에서 운영 시(620), 대용량 배터리 시스템은 별도의 제어 없이 전일 시장에 입찰한 입찰용량과 기본값을 유지하여 정상 상태로 운영한다.
이때, 대용량 배터리의 잔존용량이 SOClower limit 미만으로 하락할 경우(621), 대용량 배터리 시스템은 충전 상태로 설정하여, 충전을 위해 입찰용량과 기본값을 변경하여 실시간 시장에 재입찰하고 운영하게 된다(610).
그리고, 변경된 입찰용량과 기본값에 따라 대용량 배터리의 잔존용량이 대용량 배터리 시스템에서 설정한 SOCbase까지 충전이 되면(611), 다시 정상 상태로 설정하여, 전일 운영계획에서 결정한 입찰용량과 기본값으로 입찰하고 운영한다(620).
또한, 대용량 배터리의 잔존용량이 SOCupper limit 를 초과할 경우(622), 대용량 배터리 시스템은 방전 상태로 설정하여, 방전을 위해 입찰용량과 기본값을 변경하여 실시간 시장에 재입찰하고 운영하게 된다(630).
그리고, 변경된 입찰용량과 기본값에 따라 대용량 배터리의 잔존용량이 대용량 배터리 시스템에서 설정한 SOCbase까지 방전이 되면(631), 다시 정상 상태로 설정하여, 전일 운영계획에서 결정한 입찰용량과 기본값으로 입찰하고 운영한다(620).
여기서, 기본값 재입찰에 있어 재입찰 사전 통보 시간은 각각의 주파수 조정 시장에 규칙에 따라 변경한다.
도 7을 참조하면, 대용량 배터리 시스템은 대용량 배터리를 운영함에 있어서(S701), 대용량 배터리의 상태를 판단한다(S703).
대용량 배터리의 현재 상태가 정상 상태이면 SOClower limit < SOC < SOCupper limit 를 유지하는 동안에는(S715), 정상 상태를 유지하여(S719), 전일 운영계획에서 산출된 기본값 및 입찰용량으로 대용량 배터리를 운영한다(S721).
그러나, S715 단계에서 SOClower limit < SOC < SOCupper limit 의 범위를 벗어나는 경우, 잔존용량 SOC < SOClower limit 이면 충전 상태로 설정하여(S723), 기본값 및 입찰용량을 재산출하여 재입찰하고(S725), SOCupper limit < SOC 이면 방전 상태로 설정하여(S727), 기본값 및 입찰용량을 재산출하여 재입찰한다(S729).
S703 단계에서 대용량 배터리의 현재 상태가 충전 상태인 경우, SOC < SOCbase 이면(S705), 충전 상태에서의 기본값 및 입찰용량을 재산출하고 재입출한다(S707, S711).
S705 단계에서 SOC가 SOCbase 까지 충전이 되면, 정상 상태로 설정하여(S709), 전일 운영계획에서 산출된 기본값 및 입찰용량으로 대용량 배터리를 운영한다(S713).
S703 단계에서 대용량 배터리의 현재 상태가 방전 상태인 경우, SOCbase < SOC이면(S731), 방전 상태에서의 기본값 및 입찰용량을 재산출하고 재입출한다(S733, S735).
S731 단계에서 SOC가 SOCbase 까지 방전이 되면, 정상 상태로 설정하여(S737), 전일 운영계획에서 산출된 기본값 및 입찰용량으로 대용량 배터리를 운영한다(S739).
이상 본 발명을 몇 가지 바람직한 실시예를 사용하여 설명하였으나, 이들 실시예는 예시적인 것이며 한정적인 것이 아니다. 본 발명이 속하는 기술분야에서 통상의 지식을 지닌 자라면 본 발명의 사상과 첨부된 특허청구범위에 제시된 권리범위에서 벗어나지 않으면서 다양한 변화와 수정을 가할 수 있음을 이해할 것이다.
[부호의 설명]
100 통합 관리 장치
200 출력 제어 장치
본 발명은 대용량 배터리 시스템 및 대용량 배터리 운영 방법에 관한 것으로서, 대용량 배터리 분야에 이용 가능하다.

Claims (19)

  1. 전력 계통의 주파수 조정(Frequency Regulation)에 사용되는 대용량 배터리를 관리하는 대용량 배터리 시스템에서의 대용량 배터리 운영 방법에서,
    과거 주파수 조정 신호의 이력 정보를 사용하여 다음날의 예상 주파수 조정 신호를 산출하는 단계;
    상기 예상 주파수 조정 신호에 맞는 대용량 배터리의 입찰 용량과 기본값을 계산하는 단계;
    계산된 입찰 용량과 기본값을 이용하여 운영 계획을 결정하는 단계;
    주파수 조정의 전일 시장에서 상기 운영 계획에 따라 대용량 배터리의 입찰 용량과 기본값을 입찰하는 단계; 및
    주파수 조정의 전일 시장에서 대용량 배터리의 입찰 용량과 기본값이 낙찰되면, 주파수 조정의 실시간 시장에서 주파수 조정 신호를 수신하여 저장하고, 수신한 주파수 조정 신호에 따라 대용량 배터리를 운영하는 단계를 포함하는 대용량 배터리 운영 방법.
  2. 청구항 1에 있어서,
    상기 대용량 배터리를 운영하는 단계에서,
    대용량 배터리의 잔존 용량(State Of Charge, SOC)이 미리 설정된 하한 SOC와 상한 SOC 사이의 범위 내에 있으면, 전일 운영 계획에서 산출된 대용량 배터리의 입찰 용량과 기본값으로 대용량 배터리를 운영하는 것을 특징으로 하는 대용량 배터리 운영 방법.
  3. 청구항 2에 있어서,
    상기 대용량 배터리를 운영하는 단계에서,
    상기 대용량 배터리의 잔존 용량(State Of Charge, SOC)이 미리 설정된 하한 SOC와 상한 SOC 사이의 범위 내에 있지 않으면, 상기 대용량 배터리의 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰하는 것을 특징으로 하는 대용량 배터리 운영 방법.
  4. 청구항 3에 있어서,
    상기 대용량 배터리의 잔존 용량이 상기 하한 SOC 미만으로 하락하는 경우, 상기 대용량 배터리를 충전시키기 위한 충전 상태로 설정하고, 상기 대용량 배터리를 충전하기 위한 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰하는 것을 특징으로 하는 대용량 배터리 운영 방법.
  5. 청구항 4에 있어서,
    상기 충전 상태에서 상기 대용량 배터리의 잔존 용량이 미리 설정된 기본 SOC가 될 때까지 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰하여 상기 대용량 배터리의 잔존 용량을 회복시키고,
    상기 대용량 배터리의 잔존 용량이 상기 기본 SOC를 초과하면 다시 정상 상태로 복귀하여, 전일 운영 계획에서 산출된 대용량 배터리의 입찰 용량과 기본값으로 대용량 배터리를 운영하는 것을 특징으로 하는 대용량 배터리 운영 방법.
  6. 청구항 5에 있어서,
    상기 대용량 배터리의 잔존 용량이 상기 상한 SOC 을 초과하여 상승하는 경우, 상기 대용량 배터리를 방전시키기 위한 방전 상태로 설정하고, 상기 대용량 배터리를 방전하기 위한 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰하는 것을 특징으로 하는 대용량 배터리 운영 방법.
  7. 청구항 6에 있어서,
    상기 방전 상태에서 상기 대용량 배터리의 잔존 용량이 상기 기본 SOC가 될 때까지 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰하여 상기 대용량 배터리의 잔존 용량을 회복시키고,
    상기 대용량 배터리의 잔존 용량이 상기 기본 SOC 미만이 되면, 다시 정상 상태로 복귀하여, 전일 운영 계획에서 산출된 대용량 배터리의 입찰 용량과 기본값으로 대용량 배터리를 운영하는 것을 특징으로 하는 대용량 배터리 운영 방법.
  8. 청구항 3에 있어서,
    상기 대용량 배터리의 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰함에 있어서, 각 주파수 조정 시장에서 정해진 규칙에 따라 재입찰 사전 통보시간이 변경되는 것을 특징으로 하는 대용량 배터리 운영 방법.
  9. 청구항 1에 있어서,
    상기 예상 주파수 조정 신호에 맞는 대용량 배터리의 입찰 용량과 기본값을 계산하는 단계에서, 최적화 기법을 이용하여 상기 입찰 용량과 기본값을 계산하는 것을 특징으로 하는 대용량 배터리 운영 방법.
  10. 전력 계통의 주파수 조정(Frequency Regulation)에 사용되는 대용량 배터리를 관리하는 대용량 배터리 시스템에서,
    적어도 하나 이상의 대용량 배터리(ESS, Energy Storage System)를 가지며, 상기 대용량 배터리의 출력을 관리하는 출력 제어 장치; 및
    적어도 하나 이상의 출력 제어 장치를 관리하며, 주파수 조정 시장으로부터 실제 주파수 조정 신호를 수신하여 그 이력을 저장하고, 과거 주파수 조정 신호의 이력 정보를 사용하여 다음날의 예상 주파수 조정 신호를 산출하고, 상기 예상 주파수 조정 신호에 맞는 대용량 배터리의 입찰 용량과 기본값을 계산하고, 계산된 입찰 용량과 기본값을 이용하여 운영 계획을 결정하고, 주파수 조정의 전일 시장에서 상기 운영 계획에 따라 대용량 배터리의 입찰 용량과 기본값을 입찰하고, 주파수 조정의 전일 시장에서 대용량 배터리의 입찰 용량과 기본값이 낙찰되면, 주파수 조정의 실시간 시장에서 주파수 조정 신호를 수신하여 저장하고, 수신한 주파수 조정 신호에 따라 대용량 배터리를 운영하는 통합 관리 장치를 포함하는 대용량 배터리 시스템.
  11. 청구항 10에 있어서,
    상기 통합 관리 장치는 대용량 배터리의 잔존 용량(State Of Charge, SOC)이 미리 설정된 하한 SOC와 상한 SOC 사이의 범위 내에 있으면, 전일 운영 계획에서 산출된 대용량 배터리의 입찰 용량과 기본값으로 대용량 배터리를 운영하는 것을 특징으로 하는 대용량 배터리 운영 시스템.
  12. 청구항 11에 있어서,
    상기 통합 관리 장치는 상기 대용량 배터리의 잔존 용량(State Of Charge, SOC)이 미리 설정된 하한 SOC와 상한 SOC 사이의 범위 내에 있지 않으면, 상기 대용량 배터리의 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰하는 것을 특징으로 하는 대용량 배터리 운영 시스템.
  13. 청구항 12에 있어서,
    상기 통합 관리 장치는 상기 대용량 배터리의 잔존 용량이 상기 하한 SOC 미만으로 하락하는 경우, 상기 대용량 배터리를 충전시키기 위한 충전 상태로 설정하고, 상기 대용량 배터리를 충전하기 위한 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰하는 것을 특징으로 하는 대용량 배터리 운영 시스템.
  14. 청구항 13에 있어서,
    상기 통합 관리 장치는 상기 충전 상태에서 상기 대용량 배터리의 잔존 용량이 미리 설정된 기본 SOC가 될 때까지 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰하여 상기 대용량 배터리의 잔존 용량을 회복시키고,
    상기 대용량 배터리의 잔존 용량이 상기 기본 SOC를 초과하면 다시 정상 상태로 복귀하여, 전일 운영 계획에서 산출된 대용량 배터리의 입찰 용량과 기본값으로 대용량 배터리를 운영하는 것을 특징으로 하는 대용량 배터리 운영 시스템.
  15. 청구항 14에 있어서,
    상기 통합 관리 장치는 상기 대용량 배터리의 잔존 용량이 상기 상한 SOC 을 초과하여 상승하는 경우, 상기 대용량 배터리를 방전시키기 위한 방전 상태로 설정하고, 상기 대용량 배터리를 방전하기 위한 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰하는 것을 특징으로 하는 대용량 배터리 운영 시스템.
  16. 청구항 15에 있어서,
    상기 통합 관리 장치는 상기 방전 상태에서 상기 대용량 배터리의 잔존 용량이 상기 기본 SOC가 될 때까지 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰하여 상기 대용량 배터리의 잔존 용량을 회복시키고,
    상기 대용량 배터리의 잔존 용량이 상기 기본 SOC 미만이 되면, 다시 정상 상태로 복귀하여, 전일 운영 계획에서 산출된 대용량 배터리의 입찰 용량과 기본값으로 대용량 배터리를 운영하는 것을 특징으로 하는 대용량 배터리 운영 시스템.
  17. 청구항 10에 있어서,
    상기 대용량 배터리의 입찰 용량과 기본값을 재산출하여 실시간 시장에 재입찰함에 있어서, 각 주파수 조정 시장에서 정해진 규칙에 따라 재입찰 사전 통보시간이 변경되는 것을 특징으로 하는 대용량 배터리 운영 시스템.
  18. 청구항 10에 있어서,
    상기 통합 관리 장치는 최적화 기법을 이용하여 상기 입찰 용량과 기본값을 계산하는 것을 특징으로 하는 대용량 배터리 운영 시스템.
  19. 청구항 10에 있어서,
    상기 통합 관리 장치는 상기 주파수 조정의 실시간 시장에서 수신한 주파수 조정 신호를 저장하기 위한 데이터베이스를 포함하는 것을 특징으로 하는 대용량 배터리 운영 시스템.
PCT/KR2016/006657 2015-06-23 2016-06-23 전력 계통의 주파수 조정용 대용량 배터리 시스템 및 대용량 배터리 운영 방법 WO2016208974A1 (ko)

Priority Applications (2)

Application Number Priority Date Filing Date Title
US15/738,568 US10411470B2 (en) 2015-06-23 2016-06-23 Large capacity battery system for power system frequency regulation and large capacity battery operation method
EP16814687.6A EP3316209A4 (en) 2015-06-23 2016-06-23 LARGE CAPACITY BATTERY SYSTEM FOR POWER SYSTEM FREQUENCY REGULATION AND OPERATING PROCEDURES FOR LARGE CAPACITY BATTERY

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR1020150089236A KR101716259B1 (ko) 2015-06-23 2015-06-23 전력 계통의 주파수 조정용 대용량 배터리 시스템 및 대용량 배터리 운영 방법
KR10-2015-0089236 2015-06-23

Publications (1)

Publication Number Publication Date
WO2016208974A1 true WO2016208974A1 (ko) 2016-12-29

Family

ID=57585815

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/KR2016/006657 WO2016208974A1 (ko) 2015-06-23 2016-06-23 전력 계통의 주파수 조정용 대용량 배터리 시스템 및 대용량 배터리 운영 방법

Country Status (4)

Country Link
US (1) US10411470B2 (ko)
EP (1) EP3316209A4 (ko)
KR (1) KR101716259B1 (ko)
WO (1) WO2016208974A1 (ko)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10867360B1 (en) * 2016-10-28 2020-12-15 Chicago Mercantile Exchange Inc. Electric battery recharging unit controlled by a seasonality detection unit of a futures margin modeling system
KR102067830B1 (ko) 2017-09-25 2020-01-17 효성중공업 주식회사 Ess 출력 제어 방법
JP7285053B2 (ja) * 2018-09-05 2023-06-01 株式会社日立製作所 電力需給制御装置、電力需給制御システムおよび電力需給制御方法
CN110266026B (zh) * 2019-06-26 2022-10-18 中国能源建设集团广东省电力设计研究院有限公司 一种电厂储能辅助调频的储能定容方法
US11036250B2 (en) * 2019-07-02 2021-06-15 Microsoft Technology Licensing, Llc Datacenter stabilization of regional power grids
US11334036B2 (en) 2019-07-02 2022-05-17 Microsoft Technology Licensing, Llc Power grid aware machine learning device
CN111725819B (zh) * 2020-05-18 2022-10-18 中国电力科学研究院有限公司 一种电池储能参与频率恢复控制的方法及系统

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20130035758A (ko) * 2011-09-30 2013-04-09 한국전력공사 전력저장장치 운영장치 및 방법
KR101477648B1 (ko) * 2013-06-28 2014-12-30 재단법인대구경북과학기술원 계통 주파수 변화에 따라 에너지 저장장치를 운용하는 시스템 및 방법
KR101493785B1 (ko) * 2013-09-30 2015-02-17 한국전력공사 실시간 전력계통 상황에 기반한 에너지저장장치의 운영 시스템 및 방법
KR101529294B1 (ko) * 2014-12-15 2015-06-19 주식회사 파워이십일 에너지 저장 장치를 제어하는 전력 관리 시스템
KR20150067860A (ko) * 2013-12-10 2015-06-19 현대중공업 주식회사 에너지 저장장치의 전력관리장치 및 전력관리방법

Family Cites Families (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7839027B2 (en) * 2008-10-09 2010-11-23 The Aes Corporation Frequency responsive charge sustaining control of electricity storage systems for ancillary services on an electrical power grid
WO2011146780A2 (en) * 2010-05-20 2011-11-24 Energy Cache, Inc. Apparatuses and methods for energy storage
US9514428B2 (en) * 2011-10-28 2016-12-06 Viridity Energy, Inc. Managing energy assets associated with transport operations
JP2013168010A (ja) * 2012-02-15 2013-08-29 Sanyo Electric Co Ltd 電力制御システム
JP5738212B2 (ja) 2012-02-20 2015-06-17 三菱重工業株式会社 電力貯蔵型の発電システム
US9509176B2 (en) * 2012-04-04 2016-11-29 Ihi Inc. Energy storage modeling and control
US9634508B2 (en) * 2012-09-13 2017-04-25 Stem, Inc. Method for balancing frequency instability on an electric grid using networked distributed energy storage systems
JP5907497B2 (ja) * 2012-11-13 2016-04-26 パナソニックIpマネジメント株式会社 蓄電池制御装置、蓄電池制御方法、および蓄電池システム
US9880576B2 (en) * 2012-12-07 2018-01-30 Battelle Memorial Institute Direct load control frequency regulation support system
US9846886B2 (en) * 2013-11-07 2017-12-19 Palo Alto Research Center Incorporated Strategic modeling for economic optimization of grid-tied energy assets
JP6183727B2 (ja) * 2013-11-19 2017-08-23 パナソニックIpマネジメント株式会社 周波数制御方法、周波数制御装置、及び、蓄電池システム
US9965802B2 (en) * 2014-02-27 2018-05-08 The Trustees Of Princeton University Method for bidding battery storage into hour-ahead energy markets
JP6281817B2 (ja) * 2014-03-14 2018-02-21 パナソニックIpマネジメント株式会社 需給制御方法、および、需給制御装置
CN103927590B (zh) * 2014-03-20 2017-01-25 清华大学 信息不对称情况下的电力系统优化控制及费用计算方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20130035758A (ko) * 2011-09-30 2013-04-09 한국전력공사 전력저장장치 운영장치 및 방법
KR101477648B1 (ko) * 2013-06-28 2014-12-30 재단법인대구경북과학기술원 계통 주파수 변화에 따라 에너지 저장장치를 운용하는 시스템 및 방법
KR101493785B1 (ko) * 2013-09-30 2015-02-17 한국전력공사 실시간 전력계통 상황에 기반한 에너지저장장치의 운영 시스템 및 방법
KR20150067860A (ko) * 2013-12-10 2015-06-19 현대중공업 주식회사 에너지 저장장치의 전력관리장치 및 전력관리방법
KR101529294B1 (ko) * 2014-12-15 2015-06-19 주식회사 파워이십일 에너지 저장 장치를 제어하는 전력 관리 시스템

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See also references of EP3316209A4 *

Also Published As

Publication number Publication date
KR101716259B1 (ko) 2017-03-14
US10411470B2 (en) 2019-09-10
EP3316209A1 (en) 2018-05-02
EP3316209A4 (en) 2019-01-16
KR20170000238A (ko) 2017-01-02
US20180191161A1 (en) 2018-07-05

Similar Documents

Publication Publication Date Title
WO2016208974A1 (ko) 전력 계통의 주파수 조정용 대용량 배터리 시스템 및 대용량 배터리 운영 방법
US10795428B2 (en) Cryptocurrency processing center solar power distribution architecture
WO2017142241A1 (ko) 신재생 에너지 연계형 ess의 전력 관리 방법
CN105846418B (zh) 一种孤岛型微电网实时调度能量管理系统
EP2605359B1 (en) Battery system and its control method
WO2015102396A1 (ko) 에너지 저장 시스템에서 전력 분배 방법 및 장치
US11289914B2 (en) Cryptocurrency mining data center with a solar power distribution and management system
CN109842139B (zh) 一种含移动储能的微电网扩展规划方法
CN102460886B (zh) 控制提供信息技术服务的网络计算集群的方法
WO2013122372A1 (ko) 분산 발전 시스템 및 그 제어 방법
WO2018199395A1 (ko) 과도안정도 상태에 따른 ess 제어 장치 및 그 방법
Jahic et al. Preemptive vs. non-preemptive charging schedule for large-scale electric bus depots
CN109193725B (zh) 一种基于微电网恢复负荷的方法
Amamra et al. Day-ahead primary power reserve planning and day-D primary frequency control of a Li-ion battery
WO2019221361A1 (ko) 전력 관리 시스템
Khalid et al. Impact of energy management of electric vehicles on transient voltage stability of microgrid
EP3460944A1 (en) Current/voltage control system
WO2016063351A1 (ja) 充放電管理装置
JP2021051574A (ja) 託送システム及び託送方法
WO2017204497A1 (ko) 스마트 그리드용 bess의 제어 시스템 및 방법
JP7084296B2 (ja) 電力管理装置、電力管理システム及び電力管理方法
Jiang Multi-objective optimal scheduling method for regional photovoltaic-storage-charging integrated system participating in demand response
CN111490555A (zh) 一种双向变流器控制方法及装置
WO2021132759A1 (ko) 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법 및 장치
CN105978129A (zh) 一种分布式风光储充一体化充电方法

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 16814687

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

WWE Wipo information: entry into national phase

Ref document number: 2016814687

Country of ref document: EP