Prior art keywords
power source
energy storage
output amount
storage device
output
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/KR2019/018455
Other languages
English (en)
French (fr)
Inventor
장용호
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nuri Telecom Co Ltd
Original Assignee
Nuri Telecom Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nuri Telecom Co Ltd filed Critical Nuri Telecom Co Ltd
Publication of WO2021132759A1 publication Critical patent/WO2021132759A1/ko
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for AC mains or AC distribution networks
    • H02J3/38Arrangements for feeding a single network from two or more generators or sources in parallel; Arrangements for feeding already energised networks from additional generators or sources in parallel
    • H02J3/381Dispersed generators
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for AC mains or AC distribution networks
    • H02J3/28Arrangements for balancing of the load in networks by storage of energy
    • H02J3/32Arrangements for balancing of the load in networks by storage of energy using batteries or super capacitors with converting means
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for AC mains or AC distribution networks
    • H02J3/38Arrangements for feeding a single network from two or more generators or sources in parallel; Arrangements for feeding already energised networks from additional generators or sources in parallel
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J7/00Circuit arrangements for charging or discharging batteries or for supplying loads from batteries
    • H02J7/34Parallel operation in networks using both storage and other DC sources, e.g. providing buffering
    • H02J7/35Parallel operation in networks using both storage and other DC sources, e.g. providing buffering with light sensitive cells
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02SGENERATION OF ELECTRIC POWER BY CONVERSION OF INFRARED RADIATION, VISIBLE LIGHT OR ULTRAVIOLET LIGHT, e.g. USING PHOTOVOLTAIC [PV] MODULES
    • H02S10/00PV power plants; Combinations of PV energy systems with other systems for the generation of electric power
    • H02S10/20Systems characterised by their energy storage means
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2101/00Supply or distribution of decentralised, dispersed or local electric power generation
    • H02J2101/20Dispersed power generation using renewable energy sources
    • H02J2101/22Solar energy
    • H02J2101/24Photovoltaics
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy
    • Y02E10/56Power conversion systems, e.g. maximum power point trackers
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E70/00Other energy conversion or management systems reducing GHG emissions
    • Y02E70/30Systems combining energy storage with energy generation of non-fossil origin
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/12Monitoring or controlling equipment for energy generation units, e.g. distributed energy generation [DER] or load-side generation
    • Y04S10/123Monitoring or controlling equipment for energy generation units, e.g. distributed energy generation [DER] or load-side generation the energy generation units being or involving renewable energy sources
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/14Energy storage units

Definitions

  • the present invention relates to a method and apparatus for intelligent operation of an energy storage device associated with a heterogeneous distributed resource.
  • renewable energy refers to energy that can be obtained from nature and energy that can be obtained by recycling existing energy. It refers to energy used by converting existing fossil fuels or converting it into renewable energy including sunlight, water, precipitation, and biological organisms. Renewable energy includes solar power, solar heat, bio, wind, and hydro power, and new energy includes fuel cells and hydrogen energy.
  • An energy storage system for example, connects a renewable energy generation system represented by solar power and a power storage system, and stores renewable energy or surplus power of the power system in a battery that can be charged and discharged. It is a system that supplies power to the load when necessary.
  • an energy storage device associated with a distributed resource charges the energy storage device with energy generated from the distributed resource or system power, and supplies power to the load through the energy storage device when power supply is required to the load.
  • the solar power source maintains an output value close to the rated output in the dry season.
  • the solar power source shows a phenomenon in which the output decreases compared to the dry season.
  • the output of the hydroelectric power plant maintains a constant monthly average output value, and an output value close to the rated output is maintained during the rainy season.
  • the output of the hydroelectric power source has a low output value during the dry season, and the output value may change within a short period of time due to the influence of sudden weather.
  • each power generation source since the output of the solar power source and the hydro power source varies greatly according to the dry season or the wet season, by selecting a distributed resource having a constant output among heterogeneous distributed resources and charging the energy storage device, each power generation source
  • An object of the present invention is to provide a method and apparatus for intelligent operation of an energy storage device linked to a heterogeneous distributed resource, which can reduce changes in charging caused by changes in the output value of .
  • Embodiments of the present invention provide an intelligent driving method of an energy storage device linked to a heterogeneous distributed resource, in which the output value of a power source that is a charging target of the energy storage device is constantly changed to predict the daily charging value for the energy storage device and devices.
  • Embodiments of the present invention can determine a constant charging value for the energy storage device, so that it is possible to determine a suitable charging value that affects the state of health (SOH).
  • An object of the present invention is to provide an intelligent driving method and device.
  • Embodiments of the present invention set the discharge output value of the energy storage device according to the rainy season and the dry season, and determine the output load value of the energy storage device according to the set variable value.
  • An object of the present invention is to provide an intelligent driving method and device.
  • an intelligent driving method of an energy storage device linked to a heterogeneous distributed resource may be provided.
  • the step of setting the primary charging target includes an output value obtained by dividing the output amount of the photovoltaic power source for a preset first time by the rated output amount of the photovoltaic power source, and the hydroelectric power source for a preset first time.
  • the primary charging target of the energy storage device may be set by comparing the output value obtained by dividing the output amount by the rated output amount of the hydroelectric power source.
  • the determining of the dry season or the wet season includes an output value obtained by dividing an output amount of the photovoltaic power generation source accumulated for a second preset time by the rated output amount of the photovoltaic power source, and an accumulated calculation during the second preset time.
  • a dry season or a rainy season may be determined by comparing an output value obtained by dividing the output amount of the hydroelectric power source by the rated output amount of the hydroelectric power source.
  • the method may further include monitoring the output amount of the distributed resource set as the set secondary charging target, and maintaining or resetting the set secondary charging target according to the presence or absence of an increase pattern of the output amount of the monitored distributed resource. have.
  • the step of maintaining or resetting the set secondary charging target may include maintaining the set secondary charging target when the output amount of the monitored distributed resource approaches the rated output while having an increasing pattern, and the monitored output amount of the distributed resource If it has this increasing pattern but has a decreasing pattern, the set secondary charging target may be reset.
  • the primary charging target of the energy storage device may be set by comparing the output amount of the solar power source and the output amount of the hydroelectric power generation source for each preset date or preset period.
  • the method may further include selectively discharging the energy storage device based on a pattern of a load connected to the energy storage device and the determined dry season or wet season.
  • an energy storage device associated with a heterogeneous distributed resource of a solar power source and a hydroelectric power source; a communication module for communicating with heterogeneous distributed resources of the solar power source and the hydroelectric power source; a memory storing one or more programs; and a processor executing the stored one or more programs, wherein the processor compares the output amount of the solar power source collected through the communication module and the output amount of the hydro power source to set the primary charging target of the energy storage device and calculating the output amount of the solar power source and the output amount of the hydro power source, and comparing the accumulated output amount of the solar power generation source with the output amount of the hydro power source to determine the dry season or the wet season, and the The output of the distributed resource corresponding to the determined season result may be set as the secondary charging target.
  • the processor the output value obtained by dividing the output amount of the solar power source for the first preset time by the rated output amount of the photovoltaic power source, and the output amount of the hydro power source for the first preset time of the hydroelectric power source
  • the primary charging target of the energy storage device can be set by comparing the output value divided by the rated output.
  • the processor calculates an output value obtained by dividing the accumulated output amount of the solar power generation source by the rated output amount of the solar power generation source for a second preset time, and the output amount of the hydroelectric power source accumulated for a second preset time. It can be determined as a dry season or a rainy season by comparing the output value divided by the rated output of the hydroelectric power plant.
  • the processor may monitor the output amount of the distributed resource set as the set secondary charging target, and maintain or reset the set secondary charging target according to the presence or absence of an increase pattern of the monitored output amount of the distributed resource.
  • the processor maintains the set secondary charging target when the output amount of the monitored distributed resource has an increasing pattern and approaches the rated output, and has a decreased pattern while the output amount of the monitored distributed resource has an increase pattern
  • the set secondary charging target may be reset.
  • the processor may set the primary charging target of the energy storage device by comparing the output amount of the solar power generation source and the output amount of the hydroelectric power generation source for each predetermined date or predetermined period.
  • the processor may selectively discharge the energy storage device based on a pattern of a load connected to the energy storage device and the determined dry season or wet season.
  • the disclosed technology may have the following effects. However, this does not mean that a specific embodiment should include all of the following effects or only the following effects, so the scope of the disclosed technology should not be understood as being limited thereby.
  • each power generation source since the output of the solar power source and the hydro power source varies greatly according to the dry season or the wet season, by selecting a distributed resource having a constant output among heterogeneous distributed resources and charging the energy storage device, each power generation source It is possible to reduce the change in charge caused by the change in the output value of .
  • the output value of a power source which is a target for charging the energy storage device, is constantly changed, so that the daily charging value for the energy storage device may be estimated.
  • Embodiments of the present invention may determine a constant charge value for the energy storage device, so that an appropriate charge value affecting a state of health (SOH) may be determined.
  • SOH state of health
  • Embodiments of the present disclosure may set the discharge output value of the energy storage device according to the rainy season and the dry season, and determine the output load value of the energy storage device according to the set variable value.
  • FIG. 1 is a block diagram showing the configuration of an intelligent driving system of an energy storage device linked to a heterogeneous distributed resource according to an embodiment of the present invention.
  • FIG. 2 is a flowchart of an intelligent driving method of an energy storage device associated with a heterogeneous distributed resource according to an embodiment of the present invention.
  • FIG. 3 is a detailed flowchart of an operation for setting a charging target and an operation for determining a season in an intelligent driving method of an energy storage device according to an embodiment of the present invention.
  • FIG. 4 is a flowchart of a charging target verification and maintenance operation according to an embodiment of the present invention.
  • FIG. 5 is a block diagram showing the configuration of an intelligent driving device of an energy storage device linked to a heterogeneous distributed resource according to an embodiment of the present invention.
  • FIG. 1 is a block diagram showing the configuration of an intelligent driving system of an energy storage device linked to a heterogeneous distributed resource according to an embodiment of the present invention.
  • the intelligent driving system 100 of the energy storage device 130 includes a heterogeneous distributed resource 110 , an intelligent driving device 120 , and an energy storage device 130 . ) is included. However, not all illustrated components are essential components.
  • the intelligent driving system 100 of the energy storage device 130 may be implemented with more components than the illustrated components, and the intelligent driving system 100 of the energy storage device 130 may be implemented with fewer components. can be
  • the heterogeneous distributed resource 110 represents a power generation facility that generates power using heterogeneous distributed resources such as solar power, hydropower, wind power, and tidal power.
  • the heterogeneous distributed resource 110 may include a power source capable of generating different types of distributed resources.
  • the heterogeneous distributed resource 110 may include a configuration capable of converting natural energy into electrical energy or thermal energy.
  • the solar power generation source 111 and the hydroelectric power generation source 112 are designated as examples of the heterogeneous distributed resource 110 .
  • the heterogeneous distributed resource 110 includes a solar power source 111 and a hydroelectric power source 112 .
  • the load 140 represents a consumer who consumes power, and represents a facility that consumes power, such as a home, a building, or a factory.
  • Household or industrial equipment may be the main consumer of electricity, and specific requirements such as required amount of electricity and voltage may vary depending on the type and time of each consumer.
  • the energy storage device 130 stores energy by charging the power generated from the heterogeneous distributed resource 110 in a battery.
  • the energy storage device 130 may discharge the battery under the control of the intelligent driving device 120 to supply the stored power to the load 140 or the power grid.
  • the energy storage device 130 may include a battery, a power conditioning system (PCS), and a battery management system (BMS).
  • PCS power conditioning system
  • BMS battery management system
  • the intelligent driving device 120 operates an energy storage device based on the output amount of the heterogeneous distributed resource 110 in the operation of a heterogeneous power source combining heterogeneous distributed resources (eg, solar and hydraulic power).
  • a heterogeneous power source combining heterogeneous distributed resources (eg, solar and hydraulic power).
  • the energy storage device 130 may be charged through a charging target that does not have a change in charging according to a change in an output value.
  • the intelligent driving device 120 changes the amount of discharge in the energy storage device 130 for each season. can be operated by
  • the intelligent driving device 120 may predict the daily charging amount (Wh) and charging value (Power) of the energy storage device 130 when driving by dividing the charging algorithm according to the season. .
  • the intelligent driving device 120 performs an intelligent driving algorithm in order to effectively operate the energy storage device 130 on a heterogeneous distributed resource 110 linked to hydropower and solar power, and changes for each season. It is possible to effectively operate the energy storage device 130 by determining the amount of generation of the heterogeneous distributed resource 110 and the pattern of the load 140 .
  • the intelligent driving device 120 sets the output of the solar power and the hydro power source 112 in the structure of the energy storage device 130 in which the solar power source 111 and the hydro power source 112 are linked. value can be obtained.
  • the rated output of the solar power source 111 is as follows.
  • the output amount P[nx] of the solar power generation source 111 represents a value obtained by dividing the sum of the hydroelectric power generation sources 112 output for n hours for n hours.
  • the daily output amount P[dx] of the photovoltaic power generation source 111 represents a value obtained by adding the total of the photovoltaic power generation sources 111 output for 24 hours a day.
  • the output H[sx] of the solar power source 111 means the rated output of the solar power output.
  • the rated output of the hydro power source 112 is as follows.
  • the output amount H[nx] of the hydro power source 112 represents a value obtained by dividing the sum of the hydro power sources 112 output for n hours for n hours.
  • the daily output amount H[dx] of the hydroelectric power source 112 represents a value obtained by adding the sum of the output amounts of the hydroelectric power source 112 output for 24 hours a day.
  • the hydraulic power output H[sx] means the rated power of the hydraulic power output.
  • the intelligent driving device 120 sets the primary charging target of the energy storage device 130 by comparing the output amount of the solar power generation source 111 and the output amount of the hydroelectric power generation source 112 . And the intelligent driving device 120 cumulatively calculates the output amount of the photovoltaic power source 111 and the output amount of the hydroelectric power generation source 112 , and the accumulated calculated output amount of the solar power generation source 111 and the hydroelectric power generation source 112 . ) and judged as dry season or rainy season. Next, the intelligent driving device 120 sets the output of the distributed resource corresponding to the determined season result as the secondary charging target.
  • the intelligent driving device 120 divides the output amount of the photovoltaic power source 111 for a preset first time (eg, one day, 24 hours, 11 hours, etc.) by the rated output amount of the photovoltaic power source 111 .
  • the primary charging target of the energy storage device 130 is set by comparing the output value and the output value obtained by dividing the output amount of the hydro power source 112 for the first preset time by the rated output amount of the hydro power source 112 can
  • the intelligent driving device 120 sets the output amount of the photovoltaic power source 111 accumulated for the second preset time (eg, 7 days, 168 hours, 77 hours, etc.) into the rated output amount of the photovoltaic power source 111 .
  • a dry season or a wet season may be determined by comparing the divided output value with an output value obtained by dividing the output amount of the hydroelectric power generation source 112 accumulated for the second preset time by the rated output amount of the hydroelectric power generation source 112 .
  • the intelligent driving device 120 may perform a driving algorithm of the energy storage device 130 according to a schedule driving.
  • the schedule algorithm is an algorithm having a drive by designating a specific date and defining a target corresponding to the date in advance.
  • the intelligent driving device 120 does not apply the schedule algorithm to a specific date, but rather the hydroelectric power source 112 on a corresponding date (eg, the 1st of every month, a periodically designated date of each month, etc.) By comparing the output amount and the rated output amount of the solar power generation source 111 and selecting a value having a comparative advantage, it is possible to determine a charging target for charging the energy storage device 130 .
  • the intelligent driving device 120 may perform an automatic selection discharge algorithm of the energy storage device 130 scheduled in the dry season and the rainy season.
  • the intelligent driving device 120 may selectively perform a discharging operation in consideration of characteristics or patterns of the load 140 connected to the energy storage device 130 .
  • a discharge operation may be performed based on a load pattern corresponding to the commercial building and a discharge plan scheduled for dry season and rainy season.
  • a discharge operation may be performed based on a load pattern corresponding to the home building and a discharge plan scheduled for the dry season and the rainy season.
  • FIG. 2 is a flowchart of an intelligent driving method of an energy storage device associated with a heterogeneous distributed resource according to an embodiment of the present invention.
  • step S101 the intelligent driving device 120 waits for an operating state.
  • step S102 the intelligent driving device 120 sets the primary charging target by comparing the output amount of the heterogeneous distributed resource 110 .
  • step S103 the intelligent driving device 120 cumulatively calculates the output amount of the heterogeneous distributed resource 110 .
  • step S104 the intelligent driving device 120 compares the cumulatively calculated output amounts of the heterogeneous distributed resources 110 to determine the dry season or the wet season.
  • step S105 the intelligent driving device 120 sets the output of the distributed resource corresponding to the season determination result as the secondary charging target.
  • step S106 the intelligent driving device 120 maintains the secondary charging target.
  • FIG. 3 is a detailed flowchart of an operation for setting a charging target and an operation for determining a season in an intelligent driving method of an energy storage device according to an embodiment of the present invention.
  • step S201 the intelligent driving device 120 waits for an operating state.
  • step S202 the intelligent driving device 120 checks whether the output value of the solar power source 111 exceeds the output value of the hydro power source 112 (P[X] > H[X]).
  • step S203 when the output value of the solar power source 111 exceeds the output value of the hydro power source 112 , the intelligent driving device 120 sets the output of the solar power source 111 as the primary charging target.
  • the output value P[X] of the photovoltaic power source 111 is the output amount P[nx] of the photovoltaic power source 111 for n hours as the rated output amount P[sx] of the photovoltaic power source 111 It is expressed as the divided output value (P[nx]/P[sx]).
  • the output value H [X] of the hydro power source 112 is the output value H [nx] of the hydro power source 112 for n hours divided by the rated output H [sx] of the hydro power source 112 (H [nx]/H[sx]).
  • the intelligent driving device 120 uses the accumulated output value over a time unit to which the change in the output value is not applied. target can be determined.
  • step S204 the intelligent driving device 120 accumulates the output value of the solar power source 111 .
  • step S205 the intelligent driving device 120 determines whether the daily output value of the solar power source 111 for one day exceeds the daily output value of the hydro power source 112 (P[dX] > H[dX]) check cognition
  • step S206 if the daily output value of the solar power source 111 for one day exceeds the daily output value of the hydroelectric power source 112, the intelligent driving device 120 sets the solar power source 111 for 7 days. ) exceeds the output value of the hydroelectric power source 112 (P[7dX] > H[7dX]). On the other hand, if the daily output value of the solar power source 111 for one day does not exceed the daily output value of the hydro power source 112, the intelligent driving device 120 performs again from step S202 to compare the output values. . This indicates that the output value of the power source fluctuates during the day, and the output value has to be compared again.
  • step S207 if the output value of the solar power source 111 for 7 days exceeds the output value of the hydro power source 112 , the intelligent driving device 120 determines that it is a dry season.
  • the intelligent driving device 120 may determine the season based on the accumulated calculated output value data of the week or more for a preset time or longer, rather than the predetermined time or daily output value data.
  • the intelligent driving device 120 checks whether the output value of the solar power source 111 for 7 days exceeds the output value of the hydro power source 112 (P[7dX] > H[7dX]) and , it is possible to calculate the output value of the photovoltaic power source 111 for 7 days by weighting the daily output value for the most recent period rather than the daily output value for the early period among 7 days. For example, set a higher weight to the daily output value for the last 4 days than the daily output value for the first 3 days out of 7 days, and calculate the output value of the solar power source 111 for 7 days based on the set weight. can This is to accurately judge the current season by giving a higher weight to the daily output value of the most recent period close to the present than the past period among 7 days.
  • step S208 the intelligent driving device 120 sets the output of the solar power source 111 corresponding to the dry season as the secondary charging target.
  • the intelligent driving device 120 maintains the charging target determined as the primary charging target because the output values of the hydroelectric power source 112 and the solar power generation source 111 may change rapidly to maintain the energy storage device 130 . ) is charged.
  • the intelligent driving device 120 continuously compares the value of the time unit, and when it is maintained for more than 77 hours (when viewed as 11 hours a day based on the solar sunrise to sunset time), the power source with the superior output value is selected as 2 Decide on the car charging target.
  • the intelligent driving device 120 is an output value of 77 hours, which is 1 week (11 hours ⁇ 7 days), based on the time period in which sunlight is generated (eg, 7 am to 18 pm: total 11 hours). It is possible to determine the vehicle charging target.
  • step S209 if the output value of the solar power source 111 does not exceed the output value of the hydro power source 112 , the intelligent driving device 120 first charges the output of the hydro power source 112 . set as target
  • step S210 the intelligent driving device 120 cumulatively calculates the output value of the hydroelectric power source 112 .
  • step S211 the intelligent driving device 120 determines whether the daily output value of the hydro power source 112 for one day exceeds the daily output value of the solar power source 111 (H[dX] > P[dX]) Confirmation is made, and step S206 is performed.
  • step S206 if the daily output value of the hydro power source 112 for one day exceeds the daily output value of the solar power source 111 , the intelligent driving device 120 sets the solar power source 111 for 7 days ) exceeds the output value of the hydroelectric power source 112 (P[7dX] > H[7dX]). On the other hand, if the daily output value of the hydro power source 112 for one day does not exceed the daily output value of the solar power source 111, the intelligent driving device 120 performs again from step S202 to compare the output values. . This indicates that the output value of the power source fluctuates during the day, and the output value has to be compared again.
  • step S212 if the output value of the solar power source 111 for 7 days does not exceed the output value of the hydro power source 112 , the intelligent driving device 120 determines that it is a rainy season.
  • step S214 the intelligent driving device 120 sets the output of the hydroelectric power source 112 corresponding to the rainy season as the secondary charging target.
  • FIG. 4 is a flowchart of a charging target verification and maintenance operation according to an embodiment of the present invention.
  • step S301 the intelligent driving device 120 charges the energy storage device 130 according to the set secondary charging target.
  • step S302 the intelligent driving device 120 monitors the output value of the set secondary charging target.
  • step S303 the intelligent driving device 120 checks whether there is an increase pattern of the output value.
  • step S304 if there is an increase pattern of the output value, the intelligent driving device 120 maintains the secondary charging target.
  • step S305 if there is no increase pattern in the output value, the intelligent driving device 120 resets the secondary charging target and performs step S303 again to confirm the increase pattern in the output value.
  • the intelligent driving device 120 may verify the rainy season or the dry season.
  • the intelligent driving device 120 may determine the dry season season when an increase pattern is observed by checking the daily output value of the solar power generation source 111 . Conversely, the intelligent driving device 120 may determine the rainy season when an increase pattern is observed by checking the daily output value of the hydroelectric power source 112 .
  • the intelligent driving device 120 cumulatively compares the daily output value P[dx] of sunlight and the daily output value P[dx] of the hydroelectric power source 112 . And the intelligent driving device 120 increases the daily output value of any one power source to the value of the rated output (P[sx] or H[sx]), and continues to maintain an output value close to the rated output for a preset time If you do, you can judge it as the appropriate season.
  • the output values of solar and hydraulic power show an increase pattern for a certain period of time, but may not show an increase pattern when approaching the rated output.
  • FIG. 5 is a block diagram showing the configuration of an intelligent driving device of an energy storage device linked to a heterogeneous distributed resource according to an embodiment of the present invention.
  • the intelligent driving device 120 includes a communication module 210 , a memory 220 , and a processor 230 .
  • a communication module 210 the intelligent driving apparatus 120 may be implemented by more components than the illustrated components, or the intelligent driving apparatus 120 may be implemented by fewer components.
  • the energy storage device 130 is associated with a heterogeneous distributed resource 110 of the solar power generation source 111 and the hydroelectric power generation source 112 .
  • the communication module 210 communicates with the heterogeneous distributed resource 110 of the solar power source 111 and the hydro power source 112 .
  • the communication module 210 receives each output amount corresponding to the heterogeneous distributed resource 110 .
  • the communication module 210 may receive various information related to the heterogeneous distributed resource 110 or communicate with the energy storage device 130 or an external server (eg, a power server, a weather server, etc.).
  • the memory 220 stores one or more programs.
  • the processor 230 is connected to the communication module 210 and the memory 220 .
  • the processor 230 by executing at least one program, compares the output amount of the solar power source 111 and the output amount of the hydro power source 112 collected through the communication module 210 to the energy storage device 130 sets the primary charging target of the solar power generation source 111 and the output amount of the hydroelectric power generation source 112 is calculated cumulatively, the cumulative calculated output amount of the solar power generation source 111 and the hydroelectric power generation source 112 ) is compared to determine the dry season or the wet season, and the output of the distributed resource corresponding to the determined season result is set as the secondary charging target.
  • the processor 230 divides the output amount of the photovoltaic power source 111 by the rated output amount of the photovoltaic power source 111 for a preset first time period (eg, one day, 11 hours, etc.).
  • the primary charging target of the energy storage device 130 may be set by comparing an output value obtained by dividing the output amount of the hydro power source 112 for a preset first time by the rated output amount of the hydro power source 112 .
  • the processor 230 converts the output amount of the photovoltaic power generation source 111 accumulated for a preset second time period (eg, 7 days, 77 hours, etc.) into the rated output amount of the photovoltaic power source 111 .
  • a dry season or a wet season may be determined by comparing the divided output value with an output value obtained by dividing the output amount of the hydroelectric power generation source 112 accumulated for the second preset time by the rated output amount of the hydroelectric power generation source 112 .
  • the processor 230 may monitor the output amount of the distributed resource set as the set secondary charging target, and maintain or reset the set secondary charging target according to the presence or absence of an increase pattern of the output amount of the monitored distributed resource. have.
  • the processor 230 maintains the set secondary charging target when the output amount of the monitored distributed resource has an increase pattern and approaches the rated output, and the output amount of the monitored distributed resource has an increase pattern. In the case of having a decreasing pattern, the set secondary charging target may be reset.
  • the processor 230 compares the output amount of the photovoltaic power source 111 with the output amount of the hydroelectric power generation source 112 for each preset date or preset period to be the primary charging target of the energy storage device 130 . can be set.
  • the processor 230 may selectively discharge the energy storage device 130 based on the pattern of the load 140 connected to the energy storage device 130 and the determined dry season or wet season. .
  • the intelligent driving device 120 is an energy storage device 130 linked to a heterogeneous distributed resource 110 including a hydro power source 112 and a solar power source 111 .
  • a heterogeneous distributed resource 110 including a hydro power source 112 and a solar power source 111 .
  • the output of the heterogeneous distributed resource 110 varies according to the dry season and the wet season, it can be optimally managed.
  • the intelligent driving device 120 continuously monitors the output of the heterogeneous distributed resource 110 to calculate a stable charging value, and sets the output variable of the distributed resource of hydropower and solar power and , by selecting a stable value among hydraulic power and solar power output, the energy storage device 130 may be stably charged.
  • the dry season and the wet season are divided into a case in which there is only a dry season, a case in which there is a dry season and a rainy season together, a case in which there is only a rainy season, etc. according to environmental factors of the region.
  • the intelligent driving device 120 may set a stable charging target by determining a corresponding season by using the output values of hydraulic power and sunlight in consideration of local environmental factors.
  • the intelligent driving device 120 uses the output value of the hydroelectric power and the solar power generation source 111 even for an area where electricity and weather information cannot be received according to regional characteristics to be charged. can be set accurately.
  • a device is a device capable of calling a stored command from a storage medium and operating according to the called command, and may include an electronic device (eg, the electronic device A) according to the disclosed embodiments.
  • the processor may perform a function corresponding to the instruction by using other components directly or under the control of the processor.
  • Instructions may include code generated or executed by a compiler or interpreter.
  • the device-readable storage medium may be provided in the form of a non-transitory storage medium.
  • 'non-transitory' means that the storage medium does not include a signal and is tangible, and does not distinguish that data is semi-permanently or temporarily stored in the storage medium.
  • the method according to the various embodiments described above may be provided by being included in a computer program product.
  • Computer program products may be traded between sellers and buyers as merchandise.
  • the computer program product may be distributed in the form of a machine-readable storage medium (eg, compact disc read only memory (CD-ROM)) or online through an application store (eg, Play StoreTM).
  • an application store eg, Play StoreTM
  • at least a part of the computer program product may be temporarily stored or temporarily created in a storage medium such as a memory of a server of a manufacturer, a server of an application store, or a relay server.
  • the various embodiments described above are stored in a recording medium readable by a computer or a similar device using software, hardware, or a combination thereof. can be implemented in In some cases, the embodiments described herein may be implemented by the processor itself. According to the software implementation, embodiments such as the procedures and functions described in this specification may be implemented as separate software modules. Each of the software modules may perform one or more functions and operations described herein.
  • non-transitory computer-readable medium When the computer instructions stored in the non-transitory computer-readable medium are executed by the processor of the specific device, the specific device performs the processing operation in the device according to the various embodiments described above.
  • the non-transitory computer-readable medium does not store data for a short moment, such as a register, cache, memory, etc., but semi-permanently stores data and means a medium that can be read by a device.
  • Specific examples of the non-transitory computer-readable medium may include a CD, DVD, hard disk, Blu-ray disk, USB, memory card, ROM, and the like.
  • each of the components may be composed of a singular or a plurality of entities, and some sub-components of the above-described corresponding sub-components may be omitted, or other sub-components may be omitted. Components may be further included in various embodiments. Alternatively or additionally, some components (eg, a module or a program) may be integrated into a single entity to perform the same or similar functions performed by each corresponding component prior to integration. According to various embodiments, operations performed by a module, program, or other component may be sequentially, parallel, repetitively or heuristically executed, or at least some operations may be executed in a different order, omitted, or other operations may be added. can

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Charge And Discharge Circuits For Batteries Or The Like (AREA)

Abstract

본 발명은 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법 및 장치에 관한 것으로, 본 발명의 일 실시 예에 따른 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법은, 태양광 발전원의 출력량과 수력 발전원의 출력량을 비교하여 에너지 저장 장치의 1차 충전 대상을 설정하는 단계, 상기 태양광 발전원의 출력량과 상기 수력 발전원의 출력량을 누적 연산하고, 상기 누적 연산된 태양광 발전원의 출력량과 수력 발전원의 출력량을 비교하여 건기 시즌 또는 우기 시즌으로 판단하는 단계, 및 상기 판단된 시즌 결과에 대응되는 분산 자원의 출력을 2차 충전 대상으로 설정하는 단계를 포함한다.

Description

이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법 및 장치
본 특허와 관련된 연구는 산업통상자원부(연구관리 전문기관: 한국에너지기술평가원) 주관 하에 산업기술혁신사업 계획서(과제명: 글로벌 분산전원 시장 진출을 위한 신재생에너지 융복합 해외 실증, 과제고유번호: 2018301041150)의 지원에 의해 이루어진 것이다.
본 발명은 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법 및 장치에 관한 것이다.
에너지 산업의 발달과 국가 제도적인 변화에 따라, 신재생 에너지의 도입이 늘어나고 에너지 체계가 분산화 되면서 에너지 저장 장치의 도입이 점차 증가하고 있다. 일반적으로 신재생 에너지는 자연에서 얻을 수 있는 에너지와 기존 에너지를 재활용해서 얻을 수 있는 에너지를 뜻한다. 기존 화석연료를 변환하여 이용하거나 햇빛, 물, 강수, 생물 유기체 등을 포함하여 재생이 가능한 에너지로 변환하여 이용하는 에너지를 말한다. 재생에너지에는 태양광, 태양열, 바이오, 풍력, 수력 등이 있고, 신에너지에는 연료전지, 수소에너지 등이 있다.
에너지 저장 장치(ESS: Energy Storage System)는 예를 들어 태양광으로 대표되는 신재생 에너지 발전 시스템과 전력 저장 시스템을 연계한 것으로, 충전 및 방전이 가능한 배터리에 신재생 에너지 또는 전력 계통의 잉여 전력을 저장하고 필요 시 부하에 전력을 공급하는 시스템이다.
대형 발전소 또는 관공서 뿐만 아니라 상업시설 및 가정에도 에너지 저장 장치를 도입하는 사례가 늘고 있다. 이는 분산 자원의 도입이 늘어날 뿐만 아니라 시간대별 차등 요금제 등 에너지 가격 체계의 변화로 인해 도입이 증가하고 있다. 에너지 저장 장치가 분산 자원이 발전한 전력을 단순히 저장하여 그 전력을 사용하는 목적뿐만 아니라, 전력 수급을 안정화하고 전력 피크 수요와 시간대별 수요를 조절함으로써 수요 절감과 전력 요금 절감을 할 수 있는 목적을 가지고 도입하는 경우가 확대되었기 때문이다. 또한, 에너지 저장 장치를 도입한 소규모 분산 자원에 대한 관심이 높아지면서 에너지 저장 장치에 대한 제어 및 예측 기술의 필요성이 증대되고 있다.
일반적으로 분산 자원과 연계된 에너지 저장 장치는 분산 자원에서 발전된 에너지 또는 계통의 전력으로 에너지 저장 장치를 충전하고, 부하에 전력 공급이 필요할 때 에너지 저장 장치를 통해 부하에 전력을 공급한다.
이종 분산 자원 및 에너지 저장 장치에 대한 관심이 점차 높아지고, 에너지 저장 장치가 복수의 전력 공급원을 통해 배터리를 충전하고 부하에 전력을 공급하면서 점차 시스템 복잡도가 높아지고 있다. 따라서 복수의 신재생 에너지가 결합된 신재생 에너지원의 특성에 따라 최적화되고 이종 분산 자원의 저장 및 소비를 보다 효율적으로 관리할 수 있는 기술이 요구된다. 여러 에너지 저장 장치의 제어 및 예측 기술이 개발되고 있으나, 이종 분산 자원이 결합되어 있는 경우라도 개별적인 분산 자원에 대한 발전 제어 및 전력 저장 동작만이 수행되고 있다.
한편, 태양광 발전원은 건기 시즌에는 정격 출력에 가까운 출력 값이 유지된다. 태양광 발전원은 우기 시즌에는 건기 시즌 대비하여 출력이 떨어지는 현상을 보인다. 반대로, 수력 발전원의 출력은 월 평균 일정한 출력 값을 유지하며, 우기 시즌 중에는 정격 출력에 가까운 출력 값이 유지된다. 반면, 수력 발전원의 출력은 건기 중에 출력 값이 저조하며, 갑작스런 날씨의 영향으로 단기간 내에 출력 값이 변동될 수 있다.
이와 같이, 수력 발전원과 태양광 발전원이 함께 에너지 저장 장치에 연계되어 운영을 할 경우, 건기와 우기에 따른 수력 발전원과 태양광 발전원의 출력이 계속 변하게 된다. 시즌 구분없이 에너지 저장 장치와 연계하여 운영하기 때문에, 시즌에 따라 출력이 불안정해질 수 있다. 건기 및 우기 시즌을 구분하여 태양광 발전원과 수력 발전원에 대한 에너지 저장 장치의 충전 알고리즘을 구분할 필요가 있다.
본 발명의 실시 예들은 태양광 발전원 및 수력 발전원이 건기 시즌 또는 우기 시즌에 따른 출력 변동이 심하기 때문에, 이종 분산 자원 중에 출력이 일정한 분산 자원을 선택하여 에너지 저장 장치를 충전함으로써, 각 발전원의 출력 값 변동에 따른 충전의 변화를 감소시킬 수 있는, 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법 및 장치를 제공하고자 한다.
본 발명의 실시 예들은 에너지 저장 장치를 충전하는 대상인 발전원의 출력 값이 일정하게 변화되어 에너지 저장 장치에 대한 일일 충전 값을 예상할 수 있는, 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법 및 장치를 제공하고자 한다.
본 발명의 실시 예들은 에너지 저장 장치에 일정한 충전 값을 결정할 수 있어, 성능 상태(SOH, State Of Health)에 영향을 미치는 적합한 충전 값을 판단할 수 있는, 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법 및 장치를 제공하고자 한다.
본 발명의 실시 예들은 우기 및 건기 시즌에 따른 에너지 저장 장치의 방전 출력 값을 설정하여, 설정된 변수 값에 따른 에너지 저장 장치의 출력 부하 값을 결정할 수 있는, 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법 및 장치를 제공하고자 한다.
다만, 본 발명의 해결하고자 하는 과제는 이에 한정되는 것이 아니며, 본 발명의 사상 및 영역으로부터 벗어나지 않는 범위의 환경에서도 다양하게 확장될 수 있을 것이다.
본 발명의 일 실시 예에 따르면, 태양광 발전원 및 수력 발전원의 이종 분산 자원과 연계된 에너지 저장 장치의 운전 방법에 있어서, 태양광 발전원의 출력량과 수력 발전원의 출력량을 비교하여 에너지 저장 장치의 1차 충전 대상을 설정하는 단계; 상기 태양광 발전원의 출력량과 상기 수력 발전원의 출력량을 누적 연산하고, 상기 누적 연산된 태양광 발전원의 출력량과 수력 발전원의 출력량을 비교하여 건기 시즌 또는 우기 시즌으로 판단하는 단계; 및 상기 판단된 시즌 결과에 대응되는 분산 자원의 출력을 2차 충전 대상으로 설정하는 단계를 포함하는, 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법이 제공될 수 있다.
상기 1차 충전 대상을 설정하는 단계는, 기 설정된 제1 시간 동안의 태양광 발전원의 출력량을 상기 태양광 발전원의 정격 출력량으로 나눈 출력 값과, 기 설정된 제1 시간 동안의 수력 발전원의 출력량을 상기 수력 발전원의 정격 출력량으로 나눈 출력 값을 비교하여 에너지 저장 장치의 1차 충전 대상을 설정할 수 있다.
상기 건기 시즌 또는 우기 시즌으로 판단하는 단계는, 기 설정된 제2 시간 동안에 누적 연산된 태양광 발전원의 출력량을 상기 태양광 발전원의 정격 출력량으로 나눈 출력 값과, 기 설정된 제2 시간 동안에 누적 연산된 수력 발전원의 출력량을 상기 수력 발전원의 정격 출력량으로 나눈 출력 값을 비교하여 건기 시즌 또는 우기 시즌으로 판단할 수 있다.
상기 방법은, 상기 설정된 2차 충전 대상으로 설정된 분산 자원의 출력량을 모니터링하고, 상기 모니터링된 분산 자원의 출력량의 증가 패턴 유무에 따라 상기 설정된 2차 충전 대상을 유지하거나 재설정하는 단계를 더 포함할 수 있다.
상기 설정된 2차 충전 대상을 유지하거나 재설정하는 단계는, 상기 모니터링된 분산 자원의 출력량이 증가 패턴을 가지다가 정격 출력에 근접하는 경우 상기 설정된 2차 충전 대상을 유지하고, 상기 모니터링된 분산 자원의 출력량이 증가 패턴을 가지다가 감소 패턴을 가지는 경우 상기 설정된 2차 충전 대상을 재설정할 수 있다.
상기 1차 충전 대상을 설정하는 단계는, 기 설정된 날짜 또는 기 설정된 주기마다 태양광 발전원의 출력량과 수력 발전원의 출력량을 비교하여 에너지 저장 장치의 1차 충전 대상을 설정할 수 있다.
상기 방법은, 상기 에너지 저장 장치와 연결된 부하의 패턴과 상기 판단된 건기 시즌 또는 우기 시즌을 기초로 하여 상기 에너지 저장 장치를 선택적으로 방전시키는 단계를 더 포함할 수 있다.
한편, 본 발명의 다른 실시 예에 따르면, 태양광 발전원 및 수력 발전원의 이종 분산 자원과 연계된 에너지 저장 장치; 상기 태양광 발전원 및 상기 수력 발전원의 이종 분산 자원과 통신하는 통신 모듈; 하나 이상의 프로그램을 저장하는 메모리; 및 상기 저장된 하나 이상의 프로그램을 실행하는 프로세서를 포함하고, 상기 프로세서는, 상기 통신 모듈을 통해 수집된 태양광 발전원의 출력량과 수력 발전원의 출력량을 비교하여 에너지 저장 장치의 1차 충전 대상을 설정하고, 상기 태양광 발전원의 출력량과 상기 수력 발전원의 출력량을 누적 연산하고, 상기 누적 연산된 태양광 발전원의 출력량과 수력 발전원의 출력량을 비교하여 건기 시즌 또는 우기 시즌으로 판단하고, 상기 판단된 시즌 결과에 대응되는 분산 자원의 출력을 2차 충전 대상으로 설정할 수 있다.
상기 프로세서는, 기 설정된 제1 시간 동안의 태양광 발전원의 출력량을 상기 태양광 발전원의 정격 출력량으로 나눈 출력 값과, 기 설정된 제1 시간 동안의 수력 발전원의 출력량을 상기 수력 발전원의 정격 출력량으로 나눈 출력 값을 비교하여 에너지 저장 장치의 1차 충전 대상을 설정할 수 있다.
상기 프로세서는, 기 설정된 제2 시간 동안에 누적 연산된 태양광 발전원의 출력량을 상기 태양광 발전원의 정격 출력량으로 나눈 출력 값과, 기 설정된 제2 시간 동안에 누적 연산된 수력 발전원의 출력량을 상기 수력 발전원의 정격 출력량으로 나눈 출력 값을 비교하여 건기 시즌 또는 우기 시즌으로 판단할 수 있다.
상기 프로세서는, 상기 설정된 2차 충전 대상으로 설정된 분산 자원의 출력량을 모니터링하고, 상기 모니터링된 분산 자원의 출력량의 증가 패턴 유무에 따라 상기 설정된 2차 충전 대상을 유지하거나 재설정할 수 있다.
상기 프로세서는, 상기 모니터링된 분산 자원의 출력량이 증가 패턴을 가지다가 정격 출력에 근접하는 경우 상기 설정된 2차 충전 대상을 유지하고, 상기 모니터링된 분산 자원의 출력량이 증가 패턴을 가지다가 감소 패턴을 가지는 경우 상기 설정된 2차 충전 대상을 재설정할 수 있다.
상기 프로세서는, 기 설정된 날짜 또는 기 설정된 주기마다 태양광 발전원의 출력량과 수력 발전원의 출력량을 비교하여 에너지 저장 장치의 1차 충전 대상을 설정할 수 있다.
상기 프로세서는, 상기 에너지 저장 장치와 연결된 부하의 패턴과 상기 판단된 건기 시즌 또는 우기 시즌을 기초로 하여 상기 에너지 저장 장치를 선택적으로 방전 시킬 수 있다.
개시된 기술은 다음의 효과를 가질 수 있다. 다만, 특정 실시 예가 다음의 효과를 전부 포함하여야 한다거나 다음의 효과만을 포함하여야 한다는 의미는 아니므로, 개시된 기술의 권리 범위는 이에 의하여 제한되는 것으로 이해되어서는 아니 될 것이다.
본 발명의 실시 예들은 태양광 발전원 및 수력 발전원이 건기 시즌 또는 우기 시즌에 따른 출력 변동이 심하기 때문에, 이종 분산 자원 중에 출력이 일정한 분산 자원을 선택하여 에너지 저장 장치를 충전함으로써, 각 발전원의 출력 값 변동에 따른 충전의 변화를 감소시킬 수 있다.
본 발명의 실시 예들은 에너지 저장 장치를 충전하는 대상인 발전원의 출력 값이 일정하게 변화되어 에너지 저장 장치에 대한 일일 충전 값을 예상할 수 있다.
본 발명의 실시 예들은 에너지 저장 장치에 일정한 충전 값을 결정할 수 있어, 성능 상태(SOH, State Of Health)에 영향을 미치는 적합한 충전 값을 판단할 수 있다.
본 발명의 실시 예들은 우기 및 건기 시즌에 따른 에너지 저장 장치의 방전 출력 값을 설정하여, 설정된 변수 값에 따른 에너지 저장 장치의 출력 부하 값을 결정할 수 있다.
도 1은 본 발명의 일 실시 예에 따른 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 시스템의 구성을 나타낸 구성도이다.
도 2는 본 발명의 일 실시 예에 따른 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법에 대한 흐름도이다.
도 3은 본 발명의 일 실시 예에 따른 에너지 저장 장치의 지능형 운전 방법에서 충전 대상 설정 동작 및 시즌 판단 동작에 대한 상세 흐름도이다.
도 4는 본 발명의 일 실시 예에 따른 충전 대상 검증 및 유지 동작에 대한 흐름도이다.
도 5는 본 발명의 일 실시 예에 따른 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 장치의 구성을 나타낸 구성도이다.
[부호의 설명]
100: 지능형 운전 시스템
110: 이종 분산 자원
111: 태양광 발전원
112: 수력 발전원
120: 지능형 운전 장치
130: 에너지 저장 장치
140: 부하
210: 통신 모듈
220: 메모리
230: 프로세서
본 발명은 다양한 변환을 가할 수 있고 여러가지 실시 예를 가질 수 있는 바, 특정 실시 예들을 도면에 예시하고 상세한 설명에 구체적으로 설명하고자 한다. 그러나 이는 본 발명을 특정한 실시 형태에 대해 한정하려는 것이 아니며, 본 발명의 기술적 사상 및 기술 범위에 포함되는 모든 변환, 균등물 내지 대체물을 포함하는 것으로 이해될 수 있다. 본 발명을 설명함에 있어서 관련된 공지 기술에 대한 구체적인 설명이 본 발명의 요지를 흐릴 수 있다고 판단되는 경우 그 상세한 설명을 생략한다.
제1, 제2 등의 용어는 다양한 구성요소들을 설명하는데 사용될 수 있지만, 구성요소들이 용어들에 의해 한정되는 것은 아니다. 용어들은 하나의 구성요소를 다른 구성요소로부터 구별하는 목적으로만 사용된다.
본 발명에서 사용한 용어는 단지 특정한 실시 예를 설명하기 위해 사용된 것으로, 본 발명을 한정하려는 의도가 아니다. 본 발명에서 사용한 용어는 본 발명에서의 기능을 고려하면서 가능한 현재 널리 사용되는 일반적인 용어들을 선택하였으나 이는 당 분야에 종사하는 기술자의 의도, 판례, 또는 새로운 기술의 출현 등에 따라 달라질 수 있다. 또한, 특정한 경우는 출원인이 임의로 선정한 용어도 있으며, 이 경우 해당되는 발명의 설명 부분에서 상세히 그 의미를 기재할 것이다. 따라서 본 발명에서 사용되는 용어는 단순한 용어의 명칭이 아닌, 그 용어가 가지는 의미와 본 발명의 전반에 걸친 내용을 토대로 정의되어야 한다.
단수의 표현은 문맥상 명백하게 다르게 뜻하지 않는 한, 복수의 표현을 포함한다. 본 발명에서, "포함하다" 또는 "가지다" 등의 용어는 명세서 상에 기재된 특징, 숫자, 단계, 동작, 구성요소, 부품 또는 이들을 조합한 것이 존재함을 지정하려는 것이지, 하나 또는 그 이상의 다른 특징들이나 숫자, 단계, 동작, 구성요소, 부품 또는 이들을 조합한 것들의 존재 또는 부가 가능성을 미리 배제하지 않는 것으로 이해되어야 한다.
이하, 본 발명의 실시 예들을 첨부 도면을 참조하여 상세히 설명하기로 하며, 첨부 도면을 참조하여 설명함에 있어, 동일하거나 대응하는 구성요소는 동일한 도면 번호를 부여하고 이에 대한 중복되는 설명은 생략하기로 한다.
도 1은 본 발명의 일 실시 예에 따른 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 시스템의 구성을 나타낸 구성도이다.
도 1에 도시된 바와 같이, 본 발명의 일 실시 예에 따른 에너지 저장 장치(130)의 지능형 운전 시스템(100)은 이종 분산 자원(110), 지능형 운전 장치(120), 및 에너지 저장 장치(130)를 포함한다. 그러나 도시된 구성요소 모두가 필수 구성요소인 것은 아니다. 도시된 구성요소보다 많은 구성요소에 의해 에너지 저장 장치(130)의 지능형 운전 시스템(100)이 구현될 수도 있고, 그보다 적은 구성요소에 의해서도 에너지 저장 장치(130)의 지능형 운전 시스템(100)이 구현될 수 있다.
이하, 도 1의 에너지 저장 장치(130)의 지능형 운전 시스템(100)의 각 구성요소들의 구체적인 구성 및 동작을 설명한다.
이종 분산 자원(110)은 태양광, 수력, 풍력, 조력 등과 같은 이종 분산 자원을 이용하여 발전을 수행하는 발전 설비를 나타낸다. 이종 분산 자원(110)은 서로 다른 종류의 분산 자원을 발전시킬 수 있는 발전원을 포함할 수 있다. 추가로 이종 분산 자원(110)은 자연 에너지를 전기 에너지 또는 열에너지 등으로 변환할 수 있는 구성을 포함할 수 있다. 본 발명의 일 실시예에서는 이종 분산 자원(110)으로 태양광 발전원(111)과 수력 발전원(112)을 예시로 지정하기로 한다. 이종 분산 자원(110)은 태양광 발전원(111) 및 수력 발전원(112)을 포함한다.
부하(140)는 전력을 소비하는 수용가를 나타내며, 가정, 빌딩, 공장 등의 전력을 소비하는 시설을 나타낸다. 가정용 또는 산업용 설비가 전력의 소비 주체가 될 수 있으며, 각 소비 주체의 종류 및 시간에 따라 필요한 전력량, 전압 등의 구체적인 요구 사항이 달라질 수 있다.
에너지 저장 장치(130)는 이종 분산 자원(110)에서 생산된 전력을 구비된 배터리에 충전하여 에너지를 저장한다. 에너지 저장 장치(130)는 지능형 운전 장치(120)의 제어에 따라 배터리를 방전시켜 저장된 전력을 부하(140)나 전력망으로 공급할 수 있다. 에너지 저장 장치(130)는 배터리, PCS(Power Conditioning System) 및 BMS(Battery Management System)를 포함할 수 있다.
본 발명의 일 실시 예에 따른 지능형 운전 장치(120)는 이종의 분산 자원(예컨대, 태양광 및 수력)을 결합한 이종 발전원 운영에 있어, 이종 분산 자원(110)의 출력량을 기반으로 에너지 저장 장치(130)의 충전 운전 및 방전 운전을 제어함으로써, 출력 값 변동에 따른 충전의 변화가 없는 충전 대상을 통해 에너지 저장 장치(130)를 충전할 수 있다.
우기 시즌에는 태양광 발전은 미비하지만, 풍부해진 강수량으로 인한 수력 발전량의 증가로 에너지 저장 장치(130)를 충전할 수 있는 조건이 성립된다.
반면, 건기 시즌에는 부족한 강수량으로 인한 수력의 발전은 미비하지만, 풍부해진 일사량으로 인한 태양광 발전량의 증가로 에너지 저장 장치(130)를 충전할 수 있는 조건이 성립된다.
또한, 건기 및 우기 시즌에 영향을 많이 받는 지역일수록 에너지 저장 장치(130)에 방전량이 시즌 별로 일정한 패턴을 보이기 때문에, 지능형 운전 장치(120)는 시즌 별 에너지 저장 장치(130)에 방전량을 변경하여 운영할 수 있다.
본 발명의 일 실시 예에 따른 지능형 운전 장치(120)는 시즌에 따른 충전 알고리즘을 구분하여 운전을 할 경우, 에너지 저장 장치(130)의 일일 충전량(Wh)과 충전 값(Power)을 예측할 수 있다.
본 발명의 일 실시 예에 따른 지능형 운전 장치(120)는 수력과 태양광으로 연계된 이종 분산 자원(110)에 에너지 저장 장치(130)를 효과적으로 운영하기 위해서, 지능형 운전 알고리즘을 수행하여 시즌 별로 변화하는 이종 분산 자원(110)의 발전량과 부하(140)의 패턴을 판단하여 에너지 저장 장치(130)를 효과적으로 운영할 수 있다.
한편, 지능형 운전 장치(120)는 태양광 발전원(111)과 수력 발전원(112)이 연계된 에너지 저장 장치(130)의 구조에 있어 태양광 및 수력 발전원(112)의 출력에 대한 설정 값을 구할 수 있다.
태양광 발전원(111)의 정격 출력은 다음과 같다. 태양광 발전원(111)의 출력량 P[nx]는 n시간 동안에 출력되는 수력 발전원(112)의 총합을 n시간 동안 나눈 값을 나타낸다. 태양광 발전원(111)의 일일 출력량 P[dx]는 하루 24시간 동안에 출력되는 태양광 발전원(111)의 총합을 더한 값을 나타낸다. 태양광 발전원(111)의 출력 H[sx]는 태양광 출력의 정격 출력을 의미한다.
수력 발전원(112)의 정격 출력은 다음과 같다. 수력 발전원(112)의 출력량 H[nx]는 n시간 동안에 출력되는 수력 발전원(112)의 총합을 n시간 동안 나눈 값을 나타낸다. 수력 발전원(112)의 일일 출력량 H[dx]는 하루 24시간 동안에 출력되는 수력 발전원(112)의 출력량 총합을 더한 값을 나타낸다. 수력 출력 H[sx]는 수력 출력의 정격 출력을 의미한다.
실시 예들에 따르면, 지능형 운전 장치(120)는 태양광 발전원(111)의 출력량과 수력 발전원(112)의 출력량을 비교하여 에너지 저장 장치(130)의 1차 충전 대상을 설정한다. 그리고 지능형 운전 장치(120)는 태양광 발전원(111)의 출력량과 수력 발전원(112)의 출력량을 누적 연산하고, 그 누적 연산된 태양광 발전원(111)의 출력량과 수력 발전원(112)의 출력량을 비교하여 건기 시즌 또는 우기 시즌으로 판단한다. 이어서, 지능형 운전 장치(120)는 판단된 시즌 결과에 대응되는 분산 자원의 출력을 2차 충전 대상으로 설정한다.
여기서, 지능형 운전 장치(120)는 기 설정된 제1 시간(예컨대, 하루, 24시간, 11시간 등) 동안의 태양광 발전원(111)의 출력량을 태양광 발전원(111)의 정격 출력량으로 나눈 출력 값과, 기 설정된 제1 시간 동안의 수력 발전원(112)의 출력량을 상기 수력 발전원(112)의 정격 출력량으로 나눈 출력 값을 비교하여 에너지 저장 장치(130)의 1차 충전 대상을 설정할 수 있다.
지능형 운전 장치(120)는 기 설정된 제2 시간(예컨대, 7일, 168시간, 77시간 등) 동안에 누적 연산된 태양광 발전원(111)의 출력량을 태양광 발전원(111)의 정격 출력량으로 나눈 출력 값과, 기 설정된 제2 시간 동안에 누적 연산된 수력 발전원(112)의 출력량을 수력 발전원(112)의 정격 출력량으로 나눈 출력 값을 비교하여 건기 시즌 또는 우기 시즌으로 판단할 수 있다.
실시 예들에 따르면, 지능형 운전 장치(120)는 스케줄 운전에 따른 에너지 저장 장치(130)의 운전 알고리즘을 수행할 수 있다. 종래의 에너지 저장 장치(130)를 충전하는 대상을 건기와 우기에 따라 결정하는 데 있어, 스케줄 알고리즘은 특정 날짜를 지정하여 날짜에 해당되는 대상을 사전에 정의하여 운전을 가지는 알고리즘이다. 본 발명의 일 실시 예에 따른 지능형 운전 장치(120)는 특정 날짜에 스케줄 알고리즘을 적용하는 것이 아닌, 해당되는 날짜(예컨대, 매월 1일, 매월 주기적인 지정 날짜 등)에 수력 발전원(112)과 태양광 발전원(111)의 출력량과 정격 출력량을 비교하여 비교 우위에 있는 값을 선택하여 에너지 저장 장치(130)에 충전하는 충전 대상을 결정할 수 있다.
실시 예들에 따르면, 지능형 운전 장치(120)는 건기 시즌과 우기 시즌에 예정된 에너지 저장 장치(130)의 자동 선택 방전 알고리즘을 수행할 수 있다. 지능형 운전 장치(120)는 에너지 저장 장치(130)와 연결된 부하(140)의 특성이나 패턴을 고려하여 선택적으로 방전 동작을 수행할 수 있다. 예를 들면, 부하(140)가 상업용 건물인 경우 상업용 건물에 해당하는 부하 패턴과 건기 시즌과 우기 시즌에 예정된 방전 계획을 기반으로 방전 동작을 수행할 수 있다. 또는 부하(140)가 가정용 건물인 경우 가정용 건물에 해당하는 부하 패턴과 건기 시즌과 우기 시즌에 예정된 방전 계획을 기반으로 방전 동작을 수행할 수 있다.
도 2는 본 발명의 일 실시 예에 따른 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법에 대한 흐름도이다.
도 2에 도시된 바와 같이, 단계 S101에서, 지능형 운전 장치(120)는 운영 상태를 대기한다.
단계 S102에서, 지능형 운전 장치(120)는 이종 분산 자원(110)의 출력량을 비교하여 1차 충전 대상을 설정한다.
단계 S103에서, 지능형 운전 장치(120)는 이종 분산 자원(110)의 출력량을 누적 연산한다.
단계 S104에서, 지능형 운전 장치(120)는 누적 연산된 이종 분산 자원(110)의 출력량을 비교하여 건기 시즌 또는 우기 시즌으로 판단한다.
단계 S105에서, 지능형 운전 장치(120)는 시즌 판단 결과에 대응되는 분산 자원의 출력을 2차 충전 대상으로 설정한다.
단계 S106에서, 지능형 운전 장치(120)는 2차 충전 대상을 유지한다.
도 3은 본 발명의 일 실시 예에 따른 에너지 저장 장치의 지능형 운전 방법에서 충전 대상 설정 동작 및 시즌 판단 동작에 대한 상세 흐름도이다.
도 3에 도시된 바와 같이, 단계 S201에서, 지능형 운전 장치(120)는 운영 상태를 대기한다.
단계 S202에서, 지능형 운전 장치(120)는 태양광 발전원(111)의 출력 값이 수력 발전원(112)의 출력 값을 초과하는지를(P[X] > H[X]) 확인한다.
단계 S203에서, 태양광 발전원(111)의 출력 값이 수력 발전원(112)의 출력 값을 초과하면, 지능형 운전 장치(120)는 태양광 발전원(111)의 출력을 1차 충전 대상으로 설정한다. 여기서, 태양광 발전원(111)의 출력 값 P[X]은 n 시간 동안의 태양광 발전원(111)의 출력량 P[nx]를 태양광 발전원(111)의 정격 출력량 P[sx]로 나눈 출력 값(P[nx]/P[sx])으로 나타내진다. 수력 발전원(112)의 출력 값 H[X]은 n 시간 동안의 수력 발전원(112)의 출력량 H[nx]를 수력 발전원(112)의 정격 출력량 H[sx]로 나눈 출력 값(H[nx]/H[sx])으로 나타내진다. 지능형 운전 장치(120)는 수력 발전원(112)과 태양광 발전원(111)의 출력에 해당하는 시간을 구성 시에는 출력값의 변동이 적용되지 않는 시간 단위 이상의 누적 출력 값을 이용하여 1차 충전 대상을 결정할 수 있다.
단계 S204에서, 지능형 운전 장치(120)는 태양광 발전원(111)의 출력 값을 누적 연산한다.
단계 S205에서, 지능형 운전 장치(120)는 하루 동안의 태양광 발전원(111)의 일일 출력 값이 수력 발전원(112)의 일일 출력 값을 초과하는지를(P[dX] > H[dX])인지를 확인한다.
단계 S206에서, 하루 동안의 태양광 발전원(111)의 일일 출력 값이 수력 발전원(112)의 일일 출력 값을 초과하면, 지능형 운전 장치(120)는 7일 동안의 태양광 발전원(111)의 출력 값이 수력 발전원(112)의 출력 값을 초과하는지를(P[7dX] > H[7dX])확인한다. 반면, 하루 동안의 태양광 발전원(111)의 일일 출력 값이 수력 발전원(112)의 일일 출력 값을 초과하지 않으면, 지능형 운전 장치(120)는 단계 S202부터 다시 수행하여 출력 값을 비교한다. 이는 하루 동안 발전원의 출력 값이 변동되어 출력 값을 다시 비교해야 되는 것을 나타낸다.
단계 S207에서, 7일 동안의 태양광 발전원(111)의 출력 값이 수력 발전원(112)의 출력 값을 초과하면, 지능형 운전 장치(120)는 건기 시즌으로 판단한다. 지능형 운전 장치(120)는 일정 시간 또는 일일 출력 값 데이터가 아닌 기 설정된 시간 이상의 주 단위 이상의 누적 연산된 출력 값 데이터를 기초로 하여 시즌을 판단할 수 있다. 변형 예로, 지능형 운전 장치(120)는 7일 동안의 태양광 발전원(111)의 출력 값이 수력 발전원(112)의 출력 값을 초과하는지를(P[7dX] > H[7dX])확인하고, 7일 중에서 초반 기간 동안의 일일 출력값 보다 최근 기간 동안의 일일 출력 값에 가중치를 두어서 7일 동안의 태양광 발전원(111)의 출력 값을 산출할 수 있다. 예컨대, 7일 중에서 초반 3일 동안의 일일 출력값 보다 최근 4일 동안의 일일 출력 값에 가중치를 높게 설정하고, 설정된 가중치를 기반으로 7일 동안의 태양광 발전원(111)의 출력 값을 산출할 수 있다. 이는 7일 중에서 과거 기간보다는 현재와 가까운 최근 기간의 일일 출력 값에 더 높은 가중치를 두어 현재 시즌을 정확하게 판단하기 위함이다.
단계 S208에서, 지능형 운전 장치(120)는 건기 시즌에 대응되는 태양광 발전원(111)의 출력을 2차 충전 대상으로 설정한다.
이와 같이, 지능형 운전 장치(120)는 수력 발전원(112)과 태양광 발전원(111)의 출력 값이 급격하게 변동할 수 있기에 1차 충전 대상으로 결정된 충전 대상을 유지하여 에너지 저장 장치(130)를 충전한다. 그리고 지능형 운전 장치(120)는 시간 단위의 값을 계속 비교하여 77시간(태양광 일출~일몰 시간 기준으로 하루 11시간으로 봤을 경우)이상 유지될 경우, 우위에 있는 출력 값을 가진 발전원을 2차 충전 대상으로 결정한다. 여기서, 지능형 운전 장치(120)는 태양광이 발전하는 시간대(예컨대, 오전 7~오후 18시: 총 11시간)를 기준으로 하여 1주일(11시간×7일)인 77시간의 출력 값으로 2차 충전 대상을 판단할 수 있다.
한편, 단계 S209에서, 태양광 발전원(111)의 출력 값이 수력 발전원(112)의 출력 값을 초과하지 않으면, 지능형 운전 장치(120)는 수력 발전원(112)의 출력을 1차 충전 대상으로 설정한다.
단계 S210에서, 지능형 운전 장치(120)는 수력 발전원(112)의 출력 값을 누적 연산한다.
단계 S211에서, 지능형 운전 장치(120)는 하루 동안의 수력 발전원(112)의 일일 출력 값이 태양광 발전원(111)의 일일 출력 값을 초과하는지를(H[dX] > P[dX])인지를 확인하고, 단계 S206을 수행한다.
단계 S206에서, 하루 동안의 수력 발전원(112)의 일일 출력 값이 태양광 발전원(111)의 일일 출력 값을 초과하면, 지능형 운전 장치(120)는 7일 동안의 태양광 발전원(111)의 출력 값이 수력 발전원(112)의 출력 값을 초과하는지를(P[7dX] > H[7dX])확인한다. 반면, 하루 동안의 수력 발전원(112)의 일일 출력 값이 태양광 발전원(111)의 일일 출력 값을 초과하지 않으면, 지능형 운전 장치(120)는 단계 S202부터 다시 수행하여 출력 값을 비교한다. 이는 하루 동안 발전원의 출력 값이 변동되어 출력 값을 다시 비교해야 되는 것을 나타낸다.
단계 S212에서, 7일 동안의 태양광 발전원(111)의 출력 값이 수력 발전원(112)의 출력 값을 초과하지 않으면, 지능형 운전 장치(120)는 우기 시즌으로 판단한다.
단계 S214에서, 지능형 운전 장치(120)는 우기 시즌에 대응되는 수력 발전원(112)의 출력을 2차 충전 대상으로 설정한다.
도 4는 본 발명의 일 실시 예에 따른 충전 대상 검증 및 유지 동작에 대한 흐름도이다.
도 4에 도시된 바와 같이, 단계 S301에서, 지능형 운전 장치(120)는 설정된 2차 충전 대상에 따라 에너지 저장 장치(130) 충전한다.
단계 S302에서, 지능형 운전 장치(120)는 설정된 2차 충전 대상의 출력 값을 모니터링한다.
단계 S303에서, 지능형 운전 장치(120)는 출력 값의 증가 패턴이 있는지를 확인한다.
단계 S304에서, 출력 값의 증가 패턴이 있으면, 지능형 운전 장치(120)는 2차 충전 대상을 유지한다.
단계 S305에서, 출력 값의 증가 패턴이 없으면, 지능형 운전 장치(120)는 2차 충전 대상을 재설정하고, 출 력값의 증가 패턴을 확인하는 단계 S303을 다시 수행한다.
이와 같이, 지능형 운전 장치(120)는 우기 시즌 또는 건기 시즌을 검증할 수 있다.
일례로, 지능형 운전 장치(120)는 태양광 발전원(111)의 일일 출력 값을 확인하여 증가 패턴을 보일 경우 건기 시즌으로 판단할 수 있다. 반대로, 지능형 운전 장치(120)는 수력 발전원(112)의 일일 출력 값을 확인하여 증가 패턴을 보일 경우 우기 시즌으로 판단할 수 있다.
변형 예로, 지능형 운전 장치(120)는 태양광의 일일 출력 값 P[dx]과 수력 발전원(112)의 일일 출력 값 P[dx]을 누적 비교한다. 그리고 지능형 운전 장치(120)는 어느 하나의 발전원의 일일 출력 값이 정격 출력(P[sx] 또는 H[sx])의 값에 증가하고, 정격 출력에 가까운 출력 값을 기 설정된 시간 동안 계속 유지하면 해당되는 시즌으로 판단할 수 있다. 태양광 및 수력의 출력 값은 일정 기간 증가 패턴을 보이지만, 정격 출력에 가까워 졌을 경우 증가 패턴을 보이지 않을 수 있다.
도 5는 본 발명의 일 실시 예에 따른 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 장치의 구성을 나타낸 구성도이다.
도 5에 도시된 바와 같이, 본 발명의 일 실시 예에 따른 지능형 운전 장치(120)는 통신 모듈(210), 메모리(220) 및 프로세서(230)를 포함한다. 그러나 도시된 구성요소 모두가 필수 구성요소인 것은 아니다. 도시된 구성요소보다 많은 구성요소에 의해 지능형 운전 장치(120)가 구현될 수도 있고, 그보다 적은 구성요소에 의해서도 지능형 운전 장치(120)가 구현될 수 있다.
이하, 도 5의 지능형 운전 장치(120)의 각 구성요소들의 구체적인 구성 및 동작을 설명한다.
에너지 저장 장치(130)는 태양광 발전원(111) 및 수력 발전원(112)의 이종 분산 자원(110)과 연계되어 있다.
통신 모듈(210)은 태양광 발전원(111) 및 수력 발전원(112)의 이종 분산 자원(110)과 통신한다. 통신 모듈(210)은 이종 분산 자원(110)과 대응되는 각각의 출력량을 수신한다. 또는 통신 모듈(210)은 이종 분산 자원(110)과 관련된 다양한 정보를 수신하거나, 에너지 저장 장치(130) 또는 외부 서버(예컨대, 전력 서버, 기상 서버 등)과 통신할 수 있다.
메모리(220)는 하나 이상의 프로그램을 저장한다.
프로세서(230)는 통신 모듈(210) 및 메모리(220)와 연결된다. 프로세서(230)는, 적어도 하나의 프로그램을 실행함으로써, 통신 모듈(210)을 통해 수집된 태양광 발전원(111)의 출력량과 수력 발전원(112)의 출력량을 비교하여 에너지 저장 장치(130)의 1차 충전 대상을 설정하고, 태양광 발전원(111)의 출력량과 수력 발전원(112)의 출력량을 누적 연산하고, 누적 연산된 태양광 발전원(111)의 출력량과 수력 발전원(112)의 출력량을 비교하여 건기 시즌 또는 우기 시즌으로 판단하고, 그 판단된 시즌 결과에 대응되는 분산 자원의 출력을 2차 충전 대상으로 설정한다.
실시 예들에 따르면, 프로세서(230)는 기 설정된 제1 시간(예컨대, 하루, 11시간 등) 동안의 태양광 발전원(111)의 출력량을 태양광 발전원(111)의 정격 출력량으로 나눈 출력 값과, 기 설정된 제1 시간 동안의 수력 발전원(112)의 출력량을 수력 발전원(112)의 정격 출력량으로 나눈 출력 값을 비교하여 에너지 저장 장치(130)의 1차 충전 대상을 설정할 수 있다.
실시 예들에 따르면, 프로세서(230)는 기 설정된 제2 시간(예컨대, 7일, 77시간 등) 동안에 누적 연산된 태양광 발전원(111)의 출력량을 태양광 발전원(111)의 정격 출력량으로 나눈 출력 값과, 기 설정된 제2 시간 동안에 누적 연산된 수력 발전원(112)의 출력량을 수력 발전원(112)의 정격 출력량으로 나눈 출력 값을 비교하여 건기 시즌 또는 우기 시즌으로 판단할 수 있다.
실시 예들에 따르면, 프로세서(230)는 설정된 2차 충전 대상으로 설정된 분산 자원의 출력량을 모니터링하고, 그 모니터링된 분산 자원의 출력량의 증가 패턴 유무에 따라 그 설정된 2차 충전 대상을 유지하거나 재설정할 수 있다.
실시 예들에 따르면, 프로세서(230)는 모니터링된 분산 자원의 출력량이 증가 패턴을 가지다가 정격 출력에 근접하는 경우 그 설정된 2차 충전 대상을 유지하고, 모니터링된 분산 자원의 출력량이 증가 패턴을 가지다가 감소 패턴을 가지는 경우 그 설정된 2차 충전 대상을 재설정할 수 있다.
실시 예들에 따르면, 프로세서(230)는 기 설정된 날짜 또는 기 설정된 주기마다 태양광 발전원(111)의 출력량과 수력 발전원(112)의 출력량을 비교하여 에너지 저장 장치(130)의 1차 충전 대상을 설정할 수 있다.
실시 예들에 따르면, 프로세서(230)는 에너지 저장 장치(130)와 연결된 부하(140)의 패턴과 판단된 건기 시즌 또는 우기 시즌을 기초로 하여 상기 에너지 저장 장치(130)를 선택적으로 방전 시킬 수 있다.
이와 같이, 본 발명의 일 실시 예에 따른 지능형 운전 장치(120)는 수력 발전원(112)과 태양광 발전원(111)이 포함된 이종 분산 자원(110)에 연계된 에너지 저장 장치(130)를 운전하는 방법에 있어서, 건기 및 우기 시즌에 따른 이종 분산 자원(110)의 출력이 변동됨에 따라 이를 최적으로 관리할 수 있다.
또한, 본 발명의 일 실시 예에 따른 지능형 운전 장치(120)는 이종 분산 자원(110)의 출력을 계속 모니터링하여 안정적인 충전 값을 산정하는 데 있어, 수력 및 태양광의 분산 자원의 출력 변수를 설정하고, 수력과 태양광 출력 중에서 안정적인 값을 선택함으로써, 에너지 저장 장치(130)를 안정적으로 충전할 수 있다.
또한, 건기와 우기 시즌이 지역의 환경적인 요인에 따라 건기 시즌만 있는 경우, 건기 및 우기 시즌이 함께 있는 경우, 우기 시즌만 있는 경우 등으로 구분된다. 본 발명의 일 실시 예에 따른 지능형 운전 장치(120)는 지역의 환경적인 요인을 고려하여 수력과 태양광의 출력 값을 이용하여 해당 시즌을 판단하여 안정적인 충전 대상을 설정할 수 있다.
또한, 본 발명의 일 실시 예에 따른 지능형 운전 장치(120)는 지역 특성에 따라 전기 및 기상 정보를 받을 수 없는 지역에 대해서도, 수력과 태양광 발전원(111)의 출력 값을 이용하여 충전 대상을 정확하게 설정할 수 있다.
한편, 본 발명의 일 실시 예에 따르면, 이상에서 설명된 다양한 실시 예들은 기기(machine)(예: 컴퓨터)로 읽을 수 있는 저장 매체(machine-readable storage media)에 저장된 명령어를 포함하는 소프트웨어로 구현될 수 있다. 기기는, 저장 매체로부터 저장된 명령어를 호출하고, 호출된 명령어에 따라 동작이 가능한 장치로서, 개시된 실시 예들에 따른 전자 장치(예: 전자 장치(A))를 포함할 수 있다. 명령이 프로세서에 의해 실행될 경우, 프로세서가 직접, 또는 프로세서의 제어 하에 다른 구성요소들을 이용하여 명령에 해당하는 기능을 수행할 수 있다. 명령은 컴파일러 또는 인터프리터에 의해 생성 또는 실행되는 코드를 포함할 수 있다. 기기로 읽을 수 있는 저장 매체는, 비일시적(non-transitory) 저장매체의 형태로 제공될 수 있다. 여기서, '비일시적'은 저장 매체가 신호(signal)를 포함하지 않으며 실재(tangible)한다는 것을 의미할 뿐 데이터가 저장매체에 반영구적 또는 임시적으로 저장됨을 구분하지 않는다.
또한, 본 발명의 일 실시 예에 따르면, 이상에서 설명된 다양한 실시 예들에 따른 방법은 컴퓨터 프로그램 제품(computer program product)에 포함되어 제공될 수 있다. 컴퓨터 프로그램 제품은 상품으로서 판매자 및 구매자 간에 거래될 수 있다. 컴퓨터 프로그램 제품은 기기로 읽을 수 있는 저장 매체(예: compact disc read only memory (CD-ROM))의 형태로, 또는 어플리케이션 스토어(예: 플레이 스토어TM)를 통해 온라인으로 배포될 수 있다. 온라인 배포의 경우에, 컴퓨터 프로그램 제품의 적어도 일부는 제조사의 서버, 어플리케이션 스토어의 서버, 또는 중계 서버의 메모리와 같은 저장 매체에 적어도 일시 저장되거나, 임시적으로 생성될 수 있다.
또한, 본 발명의 일 실시 예에 따르면, 이상에서 설명된 다양한 실시 예들은 소프트웨어(software), 하드웨어(hardware) 또는 이들의 조합을 이용하여 컴퓨터(computer) 또는 이와 유사한 장치로 읽을 수 있는 기록 매체 내에서 구현될 수 있다. 일부 경우에 있어 본 명세서에서 설명되는 실시 예들이 프로세서 자체로 구현될 수 있다. 소프트웨어적인 구현에 의하면, 본 명세서에서 설명되는 절차 및 기능과 같은 실시 예들은 별도의 소프트웨어 모듈들로 구현될 수 있다. 소프트웨어 모듈들 각각은 본 명세서에서 설명되는 하나 이상의 기능 및 동작을 수행할 수 있다.
한편, 상술한 다양한 실시 예들에 따른 기기의 프로세스 동작을 수행하기 위한 컴퓨터 명령어(computer instructions)는 비일시적 컴퓨터 판독 가능 매체(non-transitory computer-readable medium)에 저장될 수 있다. 이러한 비일시적 컴퓨터 판독 가능 매체에 저장된 컴퓨터 명령어는 특정 기기의 프로세서에 의해 실행되었을 때 상술한 다양한 실시 예에 따른 기기에서의 처리 동작을 특정 기기가 수행하도록 한다. 비일시적 컴퓨터 판독 가능 매체는 레지스터, 캐쉬, 메모리 등과 같이 짧은 순간 동안 데이터를 저장하는 매체가 아니라 반영구적으로 데이터를 저장하며, 기기에 의해 판독(reading)이 가능한 매체를 의미한다. 비일시적 컴퓨터 판독 가능 매체의 구체적인 예로는, CD, DVD, 하드 디스크, 블루레이 디스크, USB, 메모리카드, ROM 등이 있을 수 있다.
또한, 상술한 다양한 실시 예들에 따른 구성 요소(예: 모듈 또는 프로그램) 각각은 단수 또는 복수의 개체로 구성될 수 있으며, 전술한 해당 서브 구성 요소들 중 일부 서브 구성 요소가 생략되거나, 또는 다른 서브 구성 요소가 다양한 실시 예에 더 포함될 수 있다. 대체적으로 또는 추가적으로, 일부 구성 요소들(예: 모듈 또는 프로그램)은 하나의 개체로 통합되어, 통합되기 이전의 각각의 해당 구성 요소에 의해 수행되는 기능을 동일 또는 유사하게 수행할 수 있다. 다양한 실시 예들에 따른, 모듈, 프로그램 또는 다른 구성 요소에 의해 수행되는 동작들은 순차적, 병렬적, 반복적 또는 휴리스틱하게 실행되거나, 적어도 일부 동작이 다른 순서로 실행되거나, 생략되거나, 또는 다른 동작이 추가될 수 있다.
이상에서는 본 발명의 바람직한 실시 예에 대하여 도시하고 설명하였지만, 본 발명은 상술한 특정의 실시 예에 한정되지 아니하며, 청구범위에서 청구하는 본 발명의 요지를 벗어남이 없이 당해 개시에 속하는 기술분야에서 통상의 지식을 가진 자에 의해 다양한 변형 실시가 가능한 것은 물론이고, 이러한 변형실시들은 본 발명의 기술적 사상이나 전망으로부터 개별적으로 이해되어져서는 안될 것이다.

Claims (14)

  1. 태양광 발전원 및 수력 발전원의 이종 분산 자원과 연계된 에너지 저장 장치의 운전 방법에 있어서,
    태양광 발전원의 출력량과 수력 발전원의 출력량을 비교하여 에너지 저장 장치의 1차 충전 대상을 설정하는 단계;
    상기 태양광 발전원의 출력량과 상기 수력 발전원의 출력량을 누적 연산하고, 상기 누적 연산된 태양광 발전원의 출력량과 수력 발전원의 출력량을 비교하여 건기 시즌 또는 우기 시즌으로 판단하는 단계; 및
    상기 판단된 시즌 결과에 대응되는 분산 자원의 출력을 2차 충전 대상으로 설정하는 단계를 포함하는, 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법.
  2. 제1항에 있어서,
    상기 1차 충전 대상을 설정하는 단계는,
    기 설정된 제1 시간 동안의 태양광 발전원의 출력량을 상기 태양광 발전원의 정격 출력량으로 나눈 출력 값과, 기 설정된 제1 시간 동안의 수력 발전원의 출력량을 상기 수력 발전원의 정격 출력량으로 나눈 출력 값을 비교하여 에너지 저장 장치의 1차 충전 대상을 설정하는, 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법.
  3. 제1항에 있어서,
    상기 건기 시즌 또는 우기 시즌으로 판단하는 단계는,
    기 설정된 제2 시간 동안에 누적 연산된 태양광 발전원의 출력량을 상기 태양광 발전원의 정격 출력량으로 나눈 출력 값과, 기 설정된 제2 시간 동안에 누적 연산된 수력 발전원의 출력량을 상기 수력 발전원의 정격 출력량으로 나눈 출력 값을 비교하여 건기 시즌 또는 우기 시즌으로 판단하는, 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법.
  4. 제1항에 있어서,
    상기 설정된 2차 충전 대상으로 설정된 분산 자원의 출력량을 모니터링하고, 상기 모니터링된 분산 자원의 출력량의 증가 패턴 유무에 따라 상기 설정된 2차 충전 대상을 유지하거나 재설정하는 단계를 더 포함하는, 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법.
  5. 제4항에 있어서,
    상기 설정된 2차 충전 대상을 유지하거나 재설정하는 단계는,
    상기 모니터링된 분산 자원의 출력량이 증가 패턴을 가지다가 정격 출력에 근접하는 경우 상기 설정된 2차 충전 대상을 유지하고, 상기 모니터링된 분산 자원의 출력량이 증가 패턴을 가지다가 감소 패턴을 가지는 경우 상기 설정된 2차 충전 대상을 재설정하는, 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법.
  6. 제1항에 있어서,
    상기 1차 충전 대상을 설정하는 단계는,
    기 설정된 날짜 또는 기 설정된 주기마다 태양광 발전원의 출력량과 수력 발전원의 출력량을 비교하여 에너지 저장 장치의 1차 충전 대상을 설정하는, 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법.
  7. 제1항에 있어서,
    상기 에너지 저장 장치와 연결된 부하의 패턴과 상기 판단된 건기 시즌 또는 우기 시즌을 기초로 하여 상기 에너지 저장 장치를 선택적으로 방전시키는 단계를 더 포함하는, 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법.
  8. 태양광 발전원 및 수력 발전원의 이종 분산 자원과 연계된 에너지 저장 장치;
    상기 태양광 발전원 및 상기 수력 발전원의 이종 분산 자원과 통신하는 통신 모듈;
    하나 이상의 프로그램을 저장하는 메모리; 및
    상기 저장된 하나 이상의 프로그램을 실행하는 프로세서를 포함하고,
    상기 프로세서는,
    상기 통신 모듈을 통해 수집된 태양광 발전원의 출력량과 수력 발전원의 출력량을 비교하여 에너지 저장 장치의 1차 충전 대상을 설정하고,
    상기 태양광 발전원의 출력량과 상기 수력 발전원의 출력량을 누적 연산하고, 상기 누적 연산된 태양광 발전원의 출력량과 수력 발전원의 출력량을 비교하여 건기 시즌 또는 우기 시즌으로 판단하고,
    상기 판단된 시즌 결과에 대응되는 분산 자원의 출력을 2차 충전 대상으로 설정하는, 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 장치.
  9. 제8항에 있어서,
    상기 프로세서는,
    기 설정된 제1 시간 동안의 태양광 발전원의 출력량을 상기 태양광 발전원의 정격 출력량으로 나눈 출력 값과, 기 설정된 제1 시간 동안의 수력 발전원의 출력량을 상기 수력 발전원의 정격 출력량으로 나눈 출력 값을 비교하여 에너지 저장 장치의 1차 충전 대상을 설정하는, 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 장치.
  10. 제8항에 있어서,
    상기 프로세서는,
    기 설정된 제2 시간 동안에 누적 연산된 태양광 발전원의 출력량을 상기 태양광 발전원의 정격 출력량으로 나눈 출력 값과, 기 설정된 제2 시간 동안에 누적 연산된 수력 발전원의 출력량을 상기 수력 발전원의 정격 출력량으로 나눈 출력 값을 비교하여 건기 시즌 또는 우기 시즌으로 판단하는, 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 장치.
  11. 제8항에 있어서,
    상기 프로세서는,
    상기 설정된 2차 충전 대상으로 설정된 분산 자원의 출력량을 모니터링하고, 상기 모니터링된 분산 자원의 출력량의 증가 패턴 유무에 따라 상기 설정된 2차 충전 대상을 유지하거나 재설정하는, 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 장치.
  12. 제11항에 있어서,
    상기 프로세서는,
    상기 모니터링된 분산 자원의 출력량이 증가 패턴을 가지다가 정격 출력에 근접하는 경우 상기 설정된 2차 충전 대상을 유지하고, 상기 모니터링된 분산 자원의 출력량이 증가 패턴을 가지다가 감소 패턴을 가지는 경우 상기 설정된 2차 충전 대상을 재설정하는, 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 장치.
  13. 제8항에 있어서,
    상기 프로세서는,
    기 설정된 날짜 또는 기 설정된 주기마다 태양광 발전원의 출력량과 수력 발전원의 출력량을 비교하여 에너지 저장 장치의 1차 충전 대상을 설정하는, 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 장치.
  14. 제8항에 있어서,
    상기 프로세서는,
    상기 에너지 저장 장치와 연결된 부하의 패턴과 상기 판단된 건기 시즌 또는 우기 시즌을 기초로 하여 상기 에너지 저장 장치를 선택적으로 방전시키는, 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 장치.
PCT/KR2019/018455 2019-12-23 2019-12-26 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법 및 장치 Ceased WO2021132759A1 (ko)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR10-2019-0173302 2019-12-23
KR1020190173302A KR102284303B1 (ko) 2019-12-23 2019-12-23 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법 및 장치

Publications (1)

Publication Number Publication Date
WO2021132759A1 true WO2021132759A1 (ko) 2021-07-01

Family

ID=76574845

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/KR2019/018455 Ceased WO2021132759A1 (ko) 2019-12-23 2019-12-26 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법 및 장치

Country Status (2)

Country Link
KR (1) KR102284303B1 (ko)
WO (1) WO2021132759A1 (ko)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116985665A (zh) * 2023-08-31 2023-11-03 广东好易点科技有限公司 一种充电桩管理方法、装置、系统和介质

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102917369B1 (ko) * 2023-10-31 2026-01-23 한국전력공사 최적 유연성 계산 시스템 및 방법

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120065820A (ko) * 2010-12-13 2012-06-21 (주)청파이엠티 하이브리드 재생에너지 발전장치 및 그 발전량 측정장비
JP2013027155A (ja) * 2011-07-21 2013-02-04 Hitachi Consumer Electronics Co Ltd 電力制御装置
KR20130104771A (ko) * 2012-03-15 2013-09-25 삼성에스디아이 주식회사 에너지 저장 시스템 및 그의 제어 방법
JP2013192401A (ja) * 2012-03-14 2013-09-26 Toshiba Corp 電力需給制御装置
KR101988485B1 (ko) * 2018-12-21 2019-06-12 (주)대현엔지니어링 태양광발전과 에너지저장장치의 지능적 연계를 위한 pms 기반의 능동형 수배전반

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120065820A (ko) * 2010-12-13 2012-06-21 (주)청파이엠티 하이브리드 재생에너지 발전장치 및 그 발전량 측정장비
JP2013027155A (ja) * 2011-07-21 2013-02-04 Hitachi Consumer Electronics Co Ltd 電力制御装置
JP2013192401A (ja) * 2012-03-14 2013-09-26 Toshiba Corp 電力需給制御装置
KR20130104771A (ko) * 2012-03-15 2013-09-25 삼성에스디아이 주식회사 에너지 저장 시스템 및 그의 제어 방법
KR101988485B1 (ko) * 2018-12-21 2019-06-12 (주)대현엔지니어링 태양광발전과 에너지저장장치의 지능적 연계를 위한 pms 기반의 능동형 수배전반

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116985665A (zh) * 2023-08-31 2023-11-03 广东好易点科技有限公司 一种充电桩管理方法、装置、系统和介质

Also Published As

Publication number Publication date
KR20210081092A (ko) 2021-07-01
KR102284303B1 (ko) 2021-08-03

Similar Documents

Publication Publication Date Title
EP2475060B1 (en) Energy storage system
CN103477527B (zh) 控制设备、电力控制系统和电力控制方法
WO2019225834A1 (ko) 에너지 저장 장치와 태양광 발전을 이용한 전력 공급 제어 시스템 및 방법
US20190340545A1 (en) Electric power management system for reducing large and rapid change in power received from electricity delivery system
JP7513529B2 (ja) 電力制御システムおよび電力制御方法
WO2017142241A1 (ko) 신재생 에너지 연계형 ess의 전력 관리 방법
US20110140648A1 (en) Energy storage system of apartment building, integrated power management system, and method of controlling the system
CN114402526B (zh) 一种通过使用分线将光伏列阵串并联混接以获取充电电流最大化的设备、方法与装置
JP6543145B2 (ja) ピーク電力予測装置、電力管理システム及びピーク電力予測方法
WO2021100956A1 (ko) 산업단지 마이크로그리드 내 중소 업체의 re100 참여를 위한 가상발전소 운영 시스템 및 방법
WO2013094838A1 (ko) 단위 그룹별 최대전력점 추종을 수행하는 태양광 발전 시스템
WO2022196846A1 (ko) 에너지저장시스템 계층형 관리시스템
JP7495392B2 (ja) 電力制御システムおよび電力制御方法
WO2019107632A1 (ko) 발전 레퍼런스를 추종하는 태양광/ess 장치의 에너지 관리 시스템 및 그 제어방법
WO2017159982A1 (ko) 마이크로그리드 운영 시스템 및 방법
WO2025116071A1 (ko) 디지털트윈 기반 융복합형 마을단위 마이크로그리드 운영 시스템 및 방법
WO2025053350A1 (ko) 고효율 하베스팅 제어 알고리즘에 의한 태양광 출력 전력을 제어하는 전자 장치 및 그 전자 장치의 제어 방법
WO2019221361A1 (ko) 전력 관리 시스템
WO2019151675A1 (ko) 태양광발전 장치
KR20160098824A (ko) 태양광발전 시스템
KR102284303B1 (ko) 이종 분산 자원과 연계된 에너지 저장 장치의 지능형 운전 방법 및 장치
WO2020032433A1 (ko) 태양광 발전 시스템 및 그 제어 방법
WO2023113248A1 (ko) 이종 배터리의 연계를 위한 전력 변환 시스템 기반의 에너지 저장 시스템을 운용하는 전력 운용 장치에서 수행되는 전력 운용 방법 및 전력 운용 장치
KR20160128706A (ko) 하이브리드 에너지 저장 시스템의 제어 장치 및 제어 방법
WO2025018752A1 (ko) 에너지 저장 시스템의 운영 지원 장치 및 방법

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 19957153

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 19957153

Country of ref document: EP

Kind code of ref document: A1