一种致裂相邻采煤工作面遗留充填墙体的方法Method for cracking residual filling wall of adjacent coal mining face
技术领域Technical field
本发明涉及一种致裂相邻采煤工作面遗留充填墙体的方法,尤其适用于深部煤层群的连续卸压开采。The invention relates to a method for cracking a residual filling wall of an adjacent coal mining face, and is particularly suitable for continuous pressure relief mining of a deep coal seam group.
背景技术Background technique
沿空留巷是沿采空区边缘构筑具有一定承载能力的墙体,将相邻采煤工作面回采巷道保留下来,作为本采煤工作面回采使用。它是深部煤层群连续卸压开采的关键技术之一,用于解决冲击矿压、煤与瓦斯突出、高瓦斯、高地压等安全难题。The retaining lane along the empty space is to construct a wall with a certain bearing capacity along the edge of the goaf, and retain the mining roadway of the adjacent coal mining face as the mining face of the coal mining face. It is one of the key technologies for continuous pressure relief mining of deep coal seams. It is used to solve the safety problems of rock burst, coal and gas outburst, high gas and high ground pressure.
目前采用水泥基类材料构筑沿空留巷墙体越来越普遍,尤其是深部矿区。水泥基类墙体速凝早强,辅以抗剪锚杆、三维加强筋等加强手段,基本能够保证两个采煤工作面回采巷道正常使用。虽然水泥基类墙体受两次采动影响萌生微裂隙,但仍持续增阻,并不能自破坏承载性能,在上下邻近煤层中形成了集中应力区,达不到连续卸压的目的,仍然是邻近煤层开采的安全隐患。因此,目前迫切需要提供一种方法,在本采煤工作面回采时,加剧致裂相邻采煤工作面遗留在采空区的充填墙体,破坏其承载能力。At present, it is more and more common to use cement-based materials to construct walls along the empty roadway, especially in deep mining areas. The cement-based wall is fast-setting and early-strength, supplemented by reinforcing bolts and three-dimensional reinforced ribs, which can basically ensure the normal use of the mining roadway of the two coal mining faces. Although the cement-based wall is affected by the two mining forces, it still increases the resistance and can not self-destruct the bearing capacity. The concentrated stress zone is formed in the upper and lower adjacent coal seams, which can not achieve the purpose of continuous pressure relief. It is a safety hazard adjacent to coal seam mining. Therefore, there is an urgent need to provide a method to aggravate the filling wall of the adjacent coal mining face left in the goaf when the mining face is recovered, and destroy its bearing capacity.
发明内容Summary of the invention
技术问题:本发明的目的是克服已有技术中的不足,提供一种致裂相邻采煤工作面遗留充填墙体的方法。Technical Problem: The object of the present invention is to overcome the deficiencies in the prior art and to provide a method for cracking a residual filling wall of an adjacent coal mining face.
技术方案:本发明的致裂相邻采煤工作面遗留充填墙体的方法如下:Technical Solution: The method for leaving the wall of the adjacent coal mining face of the present invention is as follows:
a、根据充填墙体尺寸、构筑方式和前期破损状态,设计钻孔布置方式和参数、装药量;a. According to the size of the filling wall, the construction method and the damage state in the early stage, design the drilling arrangement, parameters and charge amount;
b、超前采煤工作面,在巷内向相邻采煤工作面保留复用的充填墙体施工1~3排倾斜下向的钻孔;b. Advance coal mining face, in the lane to the adjacent coal mining face to retain the reuse of the filling wall construction 1 to 3 rows of inclined downward drilling;
c、采煤、装药作业同步进行,装药步距不大于端头液压支架的推移步距,对端头液压支架架内后方的1~2列钻孔灌浆装药;所述灌浆浆体由SCA-Ⅰ或SCA-Ⅱ型静力破碎剂拌水制成,钻孔孔口用黄泥或聚氨酯泡沫进行封孔;c. Coal mining and charging operations are carried out simultaneously, the charging step is not greater than the stepping distance of the end hydraulic support, and 1 to 2 rows of drilling and grouting charges are arranged inside the end of the hydraulic support frame; the grouting slurry Made of SCA-I or SCA-II type static breaker, the hole is sealed with yellow mud or polyurethane foam;
d、随着采煤工作面的推进,端头液压支架架内后方已装药的钻孔进入采煤工作面后方,3~8h后产生膨胀压力,利用充填墙体前期矿压萌生的微裂隙,加剧充填墙体开裂,结合滞后采动应力影响,遗留充填墙体最终破碎;d. With the advancement of the coal mining face, the drilled hole in the inner end of the end hydraulic support frame enters the rear of the coal mining face, and the expansion pressure is generated after 3 to 8 hours, and the micro-cracks initiated by the mining pressure in the early stage of the filling wall are used. Intensifying the cracking of the filling wall, combined with the influence of the delayed mining stress, and the remaining filling wall is finally broken;
e、重复步骤b、c,直至完成致裂相邻采煤工作面遗留充填墙体。e. Repeat steps b and c until the completion of the cracking of the adjacent coal mining face leaving the filling wall.
所述倾斜下向的钻孔倾斜角度为10~25°,孔径为40~100mm,孔距为0.4~0.8m,排距为0.3~0.7m,孔眼距顶、底板0.5~1.0m,孔底距充填墙体的采空区侧面为20~30cm。The inclined downward drilling hole has an inclination angle of 10 to 25°, a hole diameter of 40 to 100 mm, a hole pitch of 0.4 to 0.8 m, a row spacing of 0.3 to 0.7 m, a hole pitch of the top and a bottom plate of 0.5 to 1.0 m, and a bottom of the hole. The side of the gob from the filling wall is 20 to 30 cm.
所述灌浆浆体的水剂比为0.25~0.35,单位体积充填墙体静态破碎剂的装药量为10~25kg。
The water agent ratio of the grouting slurry is 0.25 to 0.35, and the charge amount of the static crushing agent per unit volume of the filling wall is 10 to 25 kg.
有益效果:由于采用了上述技术方案,本发明与现有技术相比:效果好,成本低,操作简易,安全可靠。具体优点如下:Advantageous Effects: Compared with the prior art, the present invention has the advantages of good effect, low cost, simple operation, safety and reliability. The specific advantages are as follows:
1)静力破碎剂膨胀力度大,利用充填墙体前期矿压萌生的微裂隙,加剧致裂相邻采煤工作面遗留在采空区的充填墙体,并结合滞后采动应力的作用,使充填墙体最终破碎。覆岩能够充分下沉,有效消除了墙体对上下邻近煤层中的应力集中影响,实现了连续卸压的目的,解决了邻近煤层开采的安全隐患。1) The static crushing agent has a large expansion force, and the micro-cracks initiated by the mining pressure in the early stage of the filling wall are used to aggravate the filling wall left in the goaf by the adjacent coal mining face, and combined with the effect of the lag mining stress. The resulting wall is finally broken. The overburden can fully sink, effectively eliminating the stress concentration effect of the wall on the upper and lower adjacent coal seams, achieving the purpose of continuous pressure relief, and solving the safety hazard of adjacent coal seam mining.
2)在静力破碎过程中,不产生飞石、粉尘、废气,安全系数高。2) In the static crushing process, no flying stones, dust, and exhaust gas are generated, and the safety factor is high.
3)超前钻孔倾斜10~25°,便于工人作业,并部分利用了墙体易发生沿45°斜截面脆性受拉破坏的特性,有效节约了破碎动力,降低了破碎成本。3) The pre-drilling hole is inclined by 10~25°, which is convenient for workers to work, and partially utilizes the characteristics that the wall body is prone to brittle tensile damage along the 45° oblique section, which effectively saves the crushing power and reduces the crushing cost.
4)工人超前采煤工作面或端头液压支架架内作业,作业安全。4) The worker is working ahead of the coal mining face or the end hydraulic support frame for safe operation.
5)工序简单,方便操作,工人作业强度低,作业时间少。5) The process is simple and convenient to operate, the worker has low work intensity and less work time.
附图说明DRAWINGS
图1是本发明的采煤工作面回采时俯视示意图;1 is a schematic plan view of the coal mining face of the present invention when it is recovered;
图2是本发明的端头液压支架附近钻孔布置示意图;Figure 2 is a schematic view showing the arrangement of drilling holes near the end hydraulic support of the present invention;
图3是本发明的墙体钻孔剖视示意图。Figure 3 is a schematic cross-sectional view of a wall of the present invention.
图中:1-充填墙体;2-钻孔;3-采煤工作面;4-相邻采煤工作面;5-静力破碎剂;6-端头液压支架;7-黄泥或聚氨酯泡沫。In the figure: 1-fill wall; 2-hole; 3- coal face; 4- adjacent coal face; 5-static breaker; 6-end hydraulic support; 7-yellow mud or polyurethane foam.
具体实施方式detailed description
下面结合附图对本发明的一个实施例作进一步的描述:An embodiment of the present invention will be further described below with reference to the accompanying drawings:
本发明的致裂相邻采煤工作面遗留充填墙体的方法,具体步骤如下:The method for cracking the adjacent coal mining face leaving the wall in the present invention, the specific steps are as follows:
a、根据充填墙体1尺寸、构筑方式和前期破损状态,设计钻孔2布置方式和参数、装药量;a. According to the size, construction mode and pre-destruction state of the filling wall 1, design the layout, parameters and loading amount of the drilling hole 2;
b、超前采煤工作面3,在巷内向相邻采煤工作面4保留复用的充填墙体1施工1~3排倾斜下向的钻孔2;所述倾斜下向的钻孔2倾斜角度为10~25°,孔径为40~100mm,孔距为0.4~0.8m,排距为0.3~0.7m,孔眼距顶、底板0.5~1.0m,孔底距充填墙体1的采空区侧面为20~30cm。b. Advance coal mining face 3, in the lane to the adjacent coal mining face 4, the multiplexed filling wall 1 is reserved for construction 1 to 3 rows of inclined downward drilling 2; the inclined downward drilling 2 is inclined The angle is 10~25°, the aperture is 40-100mm, the pitch is 0.4-0.8m, the row spacing is 0.3-0.7m, the hole is 0.5~1.0m from the top and the bottom plate, and the hole bottom is filled with the gob of the wall 1. The side is 20 to 30 cm.
c、采煤、装药作业同步进行,装药步距不大于端头液压支架6的推移步距,对端头液压支架6架内后方的1~2列钻孔2灌浆装药;所述灌浆浆体由SCA-Ⅰ或SCA-Ⅱ型静力破碎剂5拌水制成,钻孔孔口用黄泥或聚氨酯泡沫7进行封孔;所述灌浆浆体的水剂比为0.25~0.35,单位体积充填墙体1静态破碎剂5的装药量为10~25kg。
c. Coal mining and charging operations are carried out simultaneously, the charging step is not greater than the stepping distance of the end hydraulic support 6, and the first to second rows of bores 2 of the end of the hydraulic support 6 are filled with grouting charge; The grouting slurry is prepared by mixing water with SCA-I or SCA-II type static breaking agent 5, and the drilling hole is sealed with yellow mud or polyurethane foam 7; the ratio of water to the grouting slurry is 0.25-0.35 The filling amount of the static crushing agent 5 per unit volume of the filling wall 1 is 10 to 25 kg.
d、随着采煤工作面3的推进,端头液压支架6架内后方已装药的钻孔2进入采煤工作面3后方,3~8h后产生膨胀压力,利用充填墙体1前期矿压萌生的微裂隙,加剧充填墙体(1)开裂,结合滞后采动应力影响,遗留充填墙体1最终破碎;d. With the advancement of the coal mining face 3, the borehole 2, which has been filled in the rear of the 6-end hydraulic support, enters the rear of the coal mining face 3, and after 3 to 8 hours, the expansion pressure is generated, and the front wall of the filling wall 1 is utilized. The micro-cracks generated by the pressure increase the cracking of the filling wall (1), combined with the influence of the lag mining stress, and the remaining filling wall 1 is finally broken;
e、重复步骤b、c,直至完成致裂相邻采煤工作面遗留充填墙体。e. Repeat steps b and c until the completion of the cracking of the adjacent coal mining face leaving the filling wall.
实施例1、某矿相邻采煤工作面4保留复用的充填墙体1宽×高=3m×2.6m,采用泵送C30膏体材料构筑,并辅以抗剪锚杆。本采煤工作面3回采时,应力集中峰值出现在超前工作面13m,应力集中系数达1.67,此处附近充填墙体1整体质量良好,表面出现少量裂纹。 Embodiment 1. A filling wall of a mine adjacent to the coal mining face 4 is multiplexed with a width × height = 3 m × 2.6 m, and is constructed by pumping C30 paste material and supplemented with a shear anchor. When the coal mining face is recovered, the stress concentration peak appears at the leading working face of 13m, and the stress concentration factor reaches 1.67. Here, the overall quality of the filling wall 1 is good, and a small amount of cracks appear on the surface.
超前采煤工作面3距离30m,在巷内向充填墙体1施工2排倾斜下向钻孔2,倾斜角度15°,孔径50mm,孔距0.6m,排距0.6m,孔眼距顶板1.0m,距底板1.0m,孔底距充填墙体1另一侧25cm。The coal face of the advanced coal face is 3m away from the surface of the filling wall 1 and 2 rows of inclined downward boreholes 2, the inclination angle is 15°, the aperture is 50mm, the hole spacing is 0.6m, the row spacing is 0.6m, and the hole is 1.0m from the top plate. 1.0m from the bottom plate, the bottom of the hole is 25cm away from the other side of the wall 1.
采煤、装药作业同步进行。根据装药步距不大于端头液压支架6的推移步距的原则,端头液压支架6的推移步距0.6m,确定对端头液压支架6架内后方的1列钻孔灌浆装药。采用SCA-Ⅱ型静力破碎剂5,水剂比0.3左右,孔口留约10cm用黄泥7进行封孔。单位体积充填墙体1静态破碎剂5的装药量10~25kg。Coal mining and charging operations are carried out simultaneously. According to the principle that the charging step is not more than the stepping distance of the end hydraulic support 6, the stepping distance of the end hydraulic support 6 is 0.6 m, and it is determined that one row of the bore grouting charge is arranged inside the rear end of the hydraulic bracket 6 of the end. SCA-II type static breaking agent 5 is used, the water agent ratio is about 0.3, and the orifice is about 10 cm, and the yellow mud 7 is used for sealing. The volume of the static crushing agent 5 per unit volume of the filling wall 1 is 10 to 25 kg.
随着采煤工作面3的推进,已经装药的钻孔2进入采煤工作面3后方,3~8h后产生膨胀压力,利用充填墙体1前期矿压萌生的微裂隙,加剧充填墙体1开裂。结合滞后采动应力影响,遗留充填墙体1最终破碎。With the advancement of the coal mining face 3, the already-filled borehole 2 enters the rear of the coal mining face 3, and after 3 to 8 hours, the expansion pressure is generated, and the micro-cracks initiated by the pre-mineral pressure of the filling wall 1 are used to intensify the filling wall. 1 cracking. Combined with the influence of the lag mining stress, the remaining filling wall 1 is finally broken.
如图1、图2、图3所示。
As shown in Figure 1, Figure 2, Figure 3.