WO2014131272A1 - 设外部蒸汽加热器的锅炉 - Google Patents
设外部蒸汽加热器的锅炉 Download PDFInfo
- Publication number
- WO2014131272A1 WO2014131272A1 PCT/CN2013/082337 CN2013082337W WO2014131272A1 WO 2014131272 A1 WO2014131272 A1 WO 2014131272A1 CN 2013082337 W CN2013082337 W CN 2013082337W WO 2014131272 A1 WO2014131272 A1 WO 2014131272A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- external steam
- steam heater
- flue
- heating surface
- boiler
- Prior art date
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F22—STEAM GENERATION
- F22B—METHODS OF STEAM GENERATION; STEAM BOILERS
- F22B21/00—Water-tube boilers of vertical or steeply-inclined type, i.e. the water-tube sets being arranged vertically or substantially vertically
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F22—STEAM GENERATION
- F22G—SUPERHEATING OF STEAM
- F22G7/00—Steam superheaters characterised by location, arrangement, or disposition
- F22G7/12—Steam superheaters characterised by location, arrangement, or disposition in flues
Definitions
- This invention relates to a boiler with an external steam heater, and more particularly to a boiler with an external steam heater that is separated by a tail flue and whose flow rate is adjustable, and belongs to the technical field of boilers. Background technique
- the flue gas baffle temperature adjustment method is widely used.
- the boiler adopting the flue gas baffle to adjust the reheat steam temperature mode the tail flue is divided into two flue pipes, which are called the tail front flue and the tail rear flue.
- Different heating surfaces are arranged in the front front flue and the rear rear flue, and the flue gas temperature regulating baffle is arranged below the separating flue.
- two-stage (or two-part) reheater heating surfaces are generally arranged.
- the low temperature (or first part) reheater is placed in the tail front flue and the high temperature (or second part) reheater is placed in the horizontal flue before the tail flue.
- a low temperature superheater is arranged in the rear flue of the tail.
- the economizers are respectively arranged below the low temperature reheater of the tail front flue, below the low temperature superheater of the rear flue or separately below the low temperature superheater in the rear flue of the tail.
- FIG. 1 it is a schematic diagram of the structure of a conventional double-flue boiler.
- the steam from the high-pressure cylinder of the steam turbine enters the reheat steam inlet header 15 and is heated by the low-temperature reheater 6.1 to enter the low-temperature reheater outlet header 16 and is led to the high-temperature reheater inlet header 17 by the pipeline.
- the high temperature reheater 18 is heated to the desired steam temperature, it reaches the high temperature reheater outlet header 19.
- the high temperature reheat steam that meets the parameter requirements is introduced into the subsequent system, and generally enters the steam turbine intermediate pressure cylinder to continue work.
- the low temperature reheater 6.1 is installed with a front flue economizer 6.2, and the other side of the low temperature reheater 6.1 is a second low temperature superheater 7.1 separated by a partition wall 5, the second low temperature superheater 7.1 A rear flue economizer 7.2 is installed below.
- the conventional flue gas baffle temperature regulating boiler described above is mainly used in a power station boiler. After the superheated steam generated by the boiler is worked by the steam turbine high pressure cylinder, the exhaust steam enters the boiler reheater to be heated again, and the reheat steam generated is generated. The steam enters the steam turbine intermediate pressure cylinder to continue work.
- the reheat steam outlet temperature is the same as or similar to the superheated steam outlet temperature.
- the ratio of the reheat steam flow to the superheated steam flow does not change much with the boiler load.
- the ratio of the reheat steam heat absorption to the total boiler heat absorption varies with the boiler load. Not large, the fluctuation range is in the range of ⁇ 5%.
- Heating of external steam generally requires heating it from a saturated state to steam with a certain degree of superheat or heating it from a state of low superheat to a higher temperature, but the required outlet temperature is compared with the superheated steam outlet temperature of the boiler. Still lower, generally lower than 450 ° C, and the boiler superheated steam outlet temperature is generally around 530 ⁇ 550 ° C.
- the reheater Since the reheat steam outlet temperature required for the reheat steam boiler of the existing power station is the same as or close to the superheated steam outlet temperature, it is also in the range of 530 to 550 ° C, so the reheater is generally divided into two stages (or two parts).
- the reheater is arranged on the heating surface, and the external steam heated by the non-power station boiler described above has a lower outlet temperature, generally lower than 450 ° C. Therefore, the original reheater heating surface is used for Heating the external steam does not result in a suitable outlet temperature.
- the object of the present invention is to solve the problem that the original reheater heating surface is used for heating external steam, and the suitable outlet temperature cannot be obtained; the separate saturated steam superheating furnace is provided, but the problem of large area, complicated system and high cost is
- the utility model provides a boiler with an external steam heater which has a simple structure, small footprint, cost saving and good regulation.
- the present invention provides a boiler provided with an external steam heater, comprising a furnace, the furnace is connected to the tail flue, and the middle portion of the tail flute is divided into a tail front flue and a rear rear smoke through the partition wall.
- a first heating surface is arranged in the front flue of the tail
- a first flue gas regulating baffle is arranged below the first heating surface
- a second heating surface is arranged in the rear flue
- a second heating surface is arranged below the second heating surface.
- the external steam heater heating surface is only disposed in the first heating surface or the second heating surface, and the external steam heater comprises an external steam heater inlet header and an external steam heater outlet header
- the external steam heater inlet header and the external steam heater outlet header are respectively connected to both ends of the external steam heater heating surface.
- the first heating surface is solely an external steam heater heating surface or is composed of an external steam heater heating surface and a first economizer
- the second heating surface is separately a second economizer or a low temperature superheater.
- the second economizer composition is solely an external steam heater heating surface or is composed of an external steam heater heating surface and a first economizer
- the second heating surface is separately a second economizer or a low temperature superheater.
- the second economizer composition is separately a second economizer or a low temperature superheater.
- the first heating surface is solely a first economizer or consists of a low temperature superheater and a first economizer
- the second heating surface is solely an external steam heater heating surface or an external steam heater heating surface.
- the second economizer composition is solely a first economizer or consists of a low temperature superheater and a first economizer
- the main steam pressure in the furnace is at least 8 MPa.
- the invention adds an external steam heater heating surface in a mature boiler, which is arranged in a single-stage heating surface, and the external steam heater outlet is no longer connected to the heating surface of other boilers, and can pass the single cigarette in the existing boiler.
- the channels are separated, and an external steam heater heating surface is arranged in one of the separated flue to meet the requirement of heating the steam to a specific parameter to meet the demand for steam parameters in the non-power station system; setting the flue gas temperature regulating baffle through the baffle
- the opening degree controls the distribution of the flue gas of the front and rear flue of the tail, thereby adjusting the heat absorption of the heating surface of the external steam heater to achieve the purpose of adjusting the outlet temperature, and has good regulation performance.
- the invention can achieve the effect of generating the rated parameter steam without increasing or decreasing the floor space and adding no additional boiler system, and has the advantages of simple system structure, convenient implementation and cost saving.
- Figure 1 is a schematic view showing the structure of a conventional double flue boiler
- Figure 2 is a schematic view showing the structure of a boiler with an external steam heater.
- 1 is the furnace
- 2 is the tail flue
- 3 is the tail front flue
- 4 is the tail rear flue
- 5 is the partition wall
- 6 is the first heating surface
- 6.1 is the low temperature reheater
- 6.2 is the front flue coal
- ⁇ is the second heating surface
- 7.1 is the second low temperature superheater
- 7.2 is the rear flue economizer
- 8 is the first flue gas regulating baffle
- 9 is the second flue gas regulating baffle
- 10 is the screen type Superheater
- 11 is high temperature superheater
- 12 is first low temperature superheater
- 13 is external
- 14 is the external steam heater outlet header.
- 15 is a reheat steam inlet header
- 16 is a low temperature reheater outlet header
- 17 is a high temperature reheater inlet header
- 18 is a high temperature reheater
- 19 is a high temperature reheater outlet header.
- the present invention is a boiler provided with an external steam heater for generating main steam (superheated steam) having a pressure of not less than 8. OMPa.
- the present invention utilizes the original power boiler equipment in which a primary heating surface is added to heat the external steam to the desired parameters.
- the original power boiler tail is designed as a single flue, in which an economizer is placed.
- the original tail flue 2 is divided into a tail front flue 3 and a rear rear flue 4 .
- An external steam heater heating surface is added to one of the divided flue, that is, the first heating surface 6 or the second heating surface 7 includes an external steam heater heating surface, and the external steam heater heating surface is only installed in the first heating Inside the face 6 or the second heated face 7.
- the external steam heater heating surface is arranged as a single-stage heating surface, and the medium in the external steam heater heating surface has independent inlets and outlets, that is, the external steam heater inlet header 13 and the external steam heater outlet header 14 , external steam
- the heater inlet header 13 and the external steam heater outlet header 14 are respectively connected to both ends of the external steam heater heating surface, and are no longer connected to other boiler heating surfaces, and the outlet medium satisfies the parameters of the subsequent system.
- the external steam After the external steam is introduced into the external steam heater inlet header 13 , it is heated to the desired steam temperature by the external steam heater heating surface, and then enters the external steam heater outlet header 14 and is led out to the subsequent process system.
- FIG. 2 it is a schematic structural view of a boiler with an external steam heater.
- the furnace 1 is connected to the tail flue 2, and the middle portion of the tail flue 2 of the superheated steam boiler which produces only one parameter is divided by the partition wall 5 into the tail front flue 3 and the rear rear flue 4, and the tail front flue 3
- a first heating surface 6 is mounted therein, a first flue gas regulating baffle 8 is mounted under the first heating surface 6, a second heating surface 7 is mounted in the rear rear flue 4, and a second second surface is mounted below the second heating surface 7.
- the flue gas regulating baffle 9, the lower front flue 3 and the lower rear flue 4 are merged into the tail flue 2.
- the external steam heater heating surface may be arranged in any of the separate flue gases, either in the tail front flue 3 or in the rear rear flue 4, depending on the orientation of the inlet steam duct and the ease of arrangement.
- An economizer can be placed in the lower part of the external steam heater heating surface. Separated in another In the flue, the boiler economizer can be arranged according to the needs of the boiler design, or the boiler superheater is arranged on the upper part, and the boiler economizer is arranged on the lower part.
- one of the first heated surface 6 and the second heated surface 7 is separately an external steam heater heating surface or an external steam heater heating surface combined with an economizer, and the other is an economizer or a low temperature superheater and the province alone. Coal combination.
- the steam at the outlet of the external steam heater needs to be taken out of the boiler flue 2.
- the external steam heater heating surface is arranged in the tail front flue 3
- the steam can be taken out through the front flue front wall or the tail flue roof.
- the external steam heater heating surface is arranged in the rear rear flue 4
- the steam can be taken out through the rear flue back wall or the tail flue roof.
- the external steam heater heating surface is used to heat the steam from the system other than the boiler or the steam of the boiler itself after decompression or decompression and decompression to the required temperature, and the inlet parameter is saturated or superheated. , its export parameters are overheated. .
- the medium on the heating surface of the external steam heater has separate inlets and outlets, and its outlet is not connected to the other heated surfaces of the boiler.
- the flue gas conditioning baffle is used to regulate the steam temperature at the outlet of the external steam heater at a nominal value.
- the temperature regulation of the outlet medium of the external steam heater is performed by the flue gas regulating baffle.
- the flue gas flow rate through the tail front flue 3 and the rear rear flue 4 is adjusted by adjusting the flue gas adjusting baffle opening to adjust the heat absorption of the external steam heater heating surface to obtain the desired outlet medium temperature.
- the invention relates to a boiler with an external steam heater, comprising a furnace 1 and a tail flue 2, wherein the fuel is burned in the furnace 1 to generate flue gas, as shown in Fig. 2, the direction of the arrow is the direction of entry of the flue gas, the flue gas After entering the tail flue 2, the screen superheater 10, the high temperature superheater 11 and the first low temperature superheater 12 are arranged in this order from the upper part of the furnace 1 to the tail flue 2 in order of the flue gas entering.
- the tail flue 2 is divided into a tail front flue 3 and a rear rear flue 4 through a partition wall 5, and an economizer is arranged in the tail front flue 3; an external steam heater heating surface is arranged in the rear rear flue 4.
- a first flue gas regulating baffle 8 and a second flue gas regulating baffle 9 are respectively disposed at a lower portion of the tail front flue 3 and the rear rear flue 4, and the flue gas flows through the first flue gas regulating baffle 8 and the second flue.
- the gas regulating baffle 9 is then recombined in the tail flue 2.
- the exiting flue gas flows through the air preheater and exits the boiler.
- the boiler generates a total of two parameter grade steam
- the first parameter grade is the high pressure superheated steam parameter, mainly the high pressure boiler feed water (pressure 14.0 MPa, temperature 200 ° C) through the economizer, evaporator and superheater After heating, high pressure superheated steam is produced.
- the parameters of the outlet superheated steam are: flow rate 600t/h, pressure 12.5MPa, temperature 540°C.
- the device 12 belongs to the heating surface of this parameter level.
- the second parameter grade is the medium pressure parameter, the flow rate is 250t/h, the inlet pressure is 2.6MPa, the inlet temperature is the saturation temperature, and the outlet temperature is 340°C.
- the steam source of the medium pressure parameter is steam of other process systems outside the boiler, and the heat absorption inside the boiler is completed by the external steam heater heating surface.
- the boiler needs to control the superheated steam temperature and the medium pressure steam temperature to reach the rated value during operation.
- the above-mentioned medium-pressure parameter steam has constant pressure and temperature parameters, and its flow rate fluctuates in the range of 200-300 t/h with the demand of other process systems outside the boiler, but there is no specific steam flow and boiler load at the boiler superheated steam outlet. The relationship does not decrease as the boiler load decreases.
- the first flue gas regulating baffle 8 and the second are provided. Flue gas regulating baffle 9.
- the external steam heater is adjusted by adjusting the opening of the flue gas regulating baffle to adjust the flow of flue gas flowing through the heating surface of the external steam heater.
- the heat absorbed by the heated surface achieves the purpose of controlling the temperature of the outlet of the external steam heater.
- the opening degree of the flue gas regulating baffle changes, the amount of flue gas flowing through the economizer in the front flue 3 of the tail also changes accordingly, affecting the heat absorption of the economizer, and thus the influence on the superheated steam temperature is overheated.
- the two-stage water spray desuperheater configured in the steam system is adjusted to ensure that the steam temperature of the superheated steam outlet also reaches the rated parameter.
- the invention relates to a boiler with an external steam heater.
- the economizer is arranged in the tail front flue 3, and the boiler superheater is arranged on the upper part of the economizer; the external steam heater heating surface is arranged in the rear rear flue 4, An economizer is installed in the lower part of the heating surface of the external steam heater. That is, the first heating surface 6 is composed of a low temperature superheater and a first economizer, and the second heating surface 7 is composed of an external steam heater heating surface and a second economizer. Others are the same as in the first embodiment.
- the invention relates to a boiler with an external steam heater.
- the economizer is arranged in the tail front flue 3; the outer steam heater heating surface is arranged in the rear rear flue 4, and the lower part of the external steam heater heating surface is installed.
- Economizer That is, the first heat receiving surface 6 is solely the first economizer, and the second heating surface 7 is composed of the outer steam heater heating surface and the second economizer. Others are the same as in the first embodiment.
- the invention relates to a boiler with an external steam heater, and an economizer is arranged in the tail front flue 3,
- the boiler superheater is arranged on the upper part of the coal machine;
- the external steam heater heating surface is arranged in the rear rear flue 4. That is, the first heat receiving surface 6 is composed of a low temperature superheater and a first economizer, and the second heating surface 7 is solely an external steam heater heating surface.
- Others are the same as in the first embodiment.
- the invention relates to a boiler with an external steam heater.
- the economizer is arranged in the rear rear flue 4, and the boiler superheater is arranged on the upper part of the economizer; the external steam heater heating surface is arranged in the tail front flue 3,
- An economizer is installed in the lower part of the heating surface of the external steam heater. That is, the second heat receiving surface 7 is composed of a low temperature superheater and a second economizer, and the first heating surface 6 is composed of an external steam heater heating surface and a first economizer. Others are the same as in the first embodiment.
- the invention is a boiler with an external steam heater, and an economizer is arranged in the rear rear flue 4; an external steam heater heating surface is arranged in the tail front flue 3. That is, the second heat receiving surface 7 is solely the second economizer, and the first heating surface 6 is solely the external steam heater heating surface. Others are the same as in the first embodiment.
- the invention relates to a boiler with an external steam heater, and an economizer is arranged in the rear rear flue 4; an external steam heater heating surface is arranged in the tail front flue 3, and a lower part of the external steam heater heating surface is installed.
- Economizer That is, the second heat receiving surface 7 is solely a second economizer, and the first heating surface 6 is composed of an external steam heater heating surface and a first economizer. Others are the same as in the first embodiment.
- the invention relates to a boiler with an external steam heater.
- An economizer is arranged in the rear rear flue 4, and a boiler superheater is arranged on the upper part of the economizer; an external steam heater heating surface is arranged in the tail front flue 3. That is, the second heat receiving surface 7 is composed of a low temperature superheater and a second economizer, and the first heating surface 6 is solely a heating surface of the external steam heater. Others are the same as in the first embodiment.
Abstract
Description
Claims
Priority Applications (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
PL409452A PL225907B1 (pl) | 2013-02-27 | 2013-03-27 | Kociol wyposazony w podgrzewacz pary zewnetrznej |
MYPI2014703873A MY183738A (en) | 2013-02-27 | 2013-08-27 | Boiler provided with external steam heater |
ZA2014/06666A ZA201406666B (en) | 2013-02-27 | 2014-09-11 | Boiler provided with external steam heater |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310060937.3A CN103134045B (zh) | 2013-02-27 | 2013-02-27 | 设外部蒸汽加热器的锅炉 |
CN201310060937.3 | 2013-02-27 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2014131272A1 true WO2014131272A1 (zh) | 2014-09-04 |
Family
ID=48494221
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/CN2013/082337 WO2014131272A1 (zh) | 2013-02-27 | 2013-08-27 | 设外部蒸汽加热器的锅炉 |
Country Status (5)
Country | Link |
---|---|
CN (1) | CN103134045B (zh) |
MY (1) | MY183738A (zh) |
PL (1) | PL225907B1 (zh) |
WO (1) | WO2014131272A1 (zh) |
ZA (1) | ZA201406666B (zh) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103134045B (zh) * | 2013-02-27 | 2015-02-18 | 上海锅炉厂有限公司 | 设外部蒸汽加热器的锅炉 |
CN103925588A (zh) * | 2014-04-08 | 2014-07-16 | 常州市锅炉设备有限公司 | 膜式壁炉膛式热能中心 |
CA2983204C (en) * | 2015-06-30 | 2020-03-10 | Uop Llc | Film temperature optimizer for fired process heaters |
CN107990303A (zh) * | 2017-12-28 | 2018-05-04 | 华西能源工业股份有限公司 | 一种垃圾焚烧电厂用双烟道布置的超高压带再热器的锅炉 |
CN109973981A (zh) * | 2019-04-03 | 2019-07-05 | 哈尔滨锅炉厂有限责任公司 | 200mw等级的高效亚临界锅炉 |
CN113513747A (zh) * | 2021-06-03 | 2021-10-19 | 江联重工集团股份有限公司 | 一种垃圾焚烧余热锅炉外置式再热蒸汽加热系统 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS61289205A (ja) * | 1985-06-18 | 1986-12-19 | 三菱重工業株式会社 | 多種燃料を使用する変圧運転形貫流ボイラ |
JPH0882405A (ja) * | 1994-09-12 | 1996-03-26 | Ishikawajima Harima Heavy Ind Co Ltd | 変圧貫流ボイラの後部伝熱部構造 |
CN102901081A (zh) * | 2012-11-12 | 2013-01-30 | 上海智申系统工程有限公司 | 一种炉内受热面全水平布置的双烟道二次再热直流锅炉 |
CN103134045A (zh) * | 2013-02-27 | 2013-06-05 | 上海锅炉厂有限公司 | 设外部蒸汽加热器的锅炉 |
CN203147737U (zh) * | 2013-02-27 | 2013-08-21 | 上海锅炉厂有限公司 | 一种设外部蒸汽加热器的锅炉 |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3015602B2 (ja) * | 1992-09-17 | 2000-03-06 | 三菱重工業株式会社 | 蒸気温度制御装置 |
JP2003042406A (ja) * | 2001-07-27 | 2003-02-13 | Babcock Hitachi Kk | ボイラ装置の制御方法および制御装置 |
CN201103894Y (zh) * | 2007-12-04 | 2008-08-20 | 安庆林 | 饱和蒸汽加热炉 |
CN202109457U (zh) * | 2011-05-27 | 2012-01-11 | 华西能源工业股份有限公司 | 一种用于煤气锅炉的大比例热负荷调节装置 |
CN202442323U (zh) * | 2012-02-28 | 2012-09-19 | 北京京诚科林环保科技有限公司 | 一种蒸汽过热装置 |
-
2013
- 2013-02-27 CN CN201310060937.3A patent/CN103134045B/zh active Active
- 2013-03-27 PL PL409452A patent/PL225907B1/pl unknown
- 2013-08-27 MY MYPI2014703873A patent/MY183738A/en unknown
- 2013-08-27 WO PCT/CN2013/082337 patent/WO2014131272A1/zh active Application Filing
-
2014
- 2014-09-11 ZA ZA2014/06666A patent/ZA201406666B/en unknown
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS61289205A (ja) * | 1985-06-18 | 1986-12-19 | 三菱重工業株式会社 | 多種燃料を使用する変圧運転形貫流ボイラ |
JPH0882405A (ja) * | 1994-09-12 | 1996-03-26 | Ishikawajima Harima Heavy Ind Co Ltd | 変圧貫流ボイラの後部伝熱部構造 |
CN102901081A (zh) * | 2012-11-12 | 2013-01-30 | 上海智申系统工程有限公司 | 一种炉内受热面全水平布置的双烟道二次再热直流锅炉 |
CN103134045A (zh) * | 2013-02-27 | 2013-06-05 | 上海锅炉厂有限公司 | 设外部蒸汽加热器的锅炉 |
CN203147737U (zh) * | 2013-02-27 | 2013-08-21 | 上海锅炉厂有限公司 | 一种设外部蒸汽加热器的锅炉 |
Also Published As
Publication number | Publication date |
---|---|
ZA201406666B (en) | 2019-05-29 |
MY183738A (en) | 2021-03-10 |
PL409452A1 (pl) | 2015-09-28 |
CN103134045A (zh) | 2013-06-05 |
CN103134045B (zh) | 2015-02-18 |
PL225907B1 (pl) | 2017-06-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2014131272A1 (zh) | 设外部蒸汽加热器的锅炉 | |
WO2014040491A1 (zh) | 一种具有两次再热器的塔式锅炉 | |
CN105805739B (zh) | 调节过热蒸汽温度的循环流化床燃烧方法 | |
CN104763485B (zh) | 一种补热型超高压/亚临界背压供热机组热力系统 | |
CN109084293A (zh) | 一种二次再热锅炉三挡板调温控制方法 | |
US9097418B2 (en) | System and method for heat recovery steam generators | |
US5269130A (en) | Method for operating a gas and steam turbine plant and gas and steam turbine plant operated according to the method | |
WO2012065356A1 (zh) | 一种循环流化床锅炉各级过热器的布置结构 | |
CN112682771B (zh) | 一种w型火焰二次再热超超临界锅炉及汽温调节方法 | |
US9739478B2 (en) | System and method for heat recovery steam generators | |
CN203147737U (zh) | 一种设外部蒸汽加热器的锅炉 | |
WO2018099345A1 (zh) | 低热值煤气发电系统以及发电方法 | |
CN106122938B (zh) | 一种可灵活调温的电站锅炉二次再热系统 | |
CN105953205A (zh) | 一种锅炉蒸汽温度调节系统及工作方法 | |
CN105953216A (zh) | 一种垃圾焚烧锅炉再热器的减温结构 | |
CS33090A3 (en) | Steam generator and method of its intermediate superheater temperature control | |
JP6516993B2 (ja) | コンバインドサイクルプラント並びにボイラの蒸気冷却方法 | |
JP2595046B2 (ja) | 再熱型コンバインドプラントの蒸気温度制御システム | |
JP4842007B2 (ja) | 排熱回収ボイラ | |
JP4718333B2 (ja) | 貫流式排熱回収ボイラ | |
CN102913892A (zh) | 一种具有再热器的t型锅炉 | |
CN109063286A (zh) | 一种给水温度变化对锅炉过再热蒸汽温度的定量计算方法 | |
CN208312354U (zh) | 一种二次再热发电系统 | |
CN208794441U (zh) | 采用烟气挡板与再循环耦合调温的超临界co2试验锅炉 | |
GB744797A (en) | Improvements in forced flow, once-through tubulous vapour generating and vapour heating units and to a method of operation thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
WWE | Wipo information: entry into national phase |
Ref document number: P.409452 Country of ref document: PL Ref document number: 409452 Country of ref document: PL |
|
WWE | Wipo information: entry into national phase |
Ref document number: 2014/12163 Country of ref document: TR |
|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 13876336 Country of ref document: EP Kind code of ref document: A1 |
|
WWE | Wipo information: entry into national phase |
Ref document number: IDP00201406829 Country of ref document: ID |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 13876336 Country of ref document: EP Kind code of ref document: A1 |