WO2014110878A1 - Auxiliary analysis method for optimization of current scheduling plan in wind-fire coordinated scheduling mode - Google Patents

Auxiliary analysis method for optimization of current scheduling plan in wind-fire coordinated scheduling mode Download PDF

Info

Publication number
WO2014110878A1
WO2014110878A1 PCT/CN2013/075498 CN2013075498W WO2014110878A1 WO 2014110878 A1 WO2014110878 A1 WO 2014110878A1 CN 2013075498 W CN2013075498 W CN 2013075498W WO 2014110878 A1 WO2014110878 A1 WO 2014110878A1
Authority
WO
WIPO (PCT)
Prior art keywords
unit
plan
optimization
period
wind power
Prior art date
Application number
PCT/CN2013/075498
Other languages
French (fr)
Chinese (zh)
Inventor
涂孟夫
陈之栩
刘军
丁恰
高宗和
戴则梅
王长宝
徐帆
张彦涛
李利利
Original Assignee
国电南瑞科技股份有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 国电南瑞科技股份有限公司 filed Critical 国电南瑞科技股份有限公司
Publication of WO2014110878A1 publication Critical patent/WO2014110878A1/en

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/008Circuit arrangements for ac mains or ac distribution networks involving trading of energy or energy transmission rights
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/004Generation forecast, e.g. methods or systems for forecasting future energy generation
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/381Dispersed generators
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/46Controlling of the sharing of output between the generators, converters, or transformers
    • H02J3/466Scheduling the operation of the generators, e.g. connecting or disconnecting generators to meet a given demand
    • H02J3/472For selectively connecting the AC sources in a particular order, e.g. sequential, alternating or subsets of sources
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2300/00Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation
    • H02J2300/20The dispersed energy generation being of renewable origin
    • H02J2300/28The renewable source being wind energy
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/76Power conversion electric or electronic aspects
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S50/00Market activities related to the operation of systems integrating technologies related to power network operation or related to communication or information technologies
    • Y04S50/10Energy trading, including energy flowing from end-user application to grid

Definitions

  • the invention relates to a power system dispatching automation technology, in particular to a method for optimizing an auxiliary analysis of a daily dispatching plan under a wind-fire coordinated scheduling mode.
  • Wind power has increased its installed capacity with the support of national policies. As of the end of 2011, the cumulative installed capacity of wind power exceeded 65 million kW, ranking first in the world. However, the average utilization hours of wind power decreased by 144 hours compared with the previous year, only 1903 hours, far from the expected target. Wind power has the characteristics of uncertainty, volatility and anti-peak shaving, and the accuracy of existing short-term wind power prediction is not high, which brings challenges to system backup, peak shaving and power balance. At the same time, the domestic power generation operating environment is dominated by large thermal power. In the northern regions where wind power is connected to the grid, the peak characteristics of wind power will further increase the peak-to-valley difference of the power grid. Due to factors such as peak shaving, transportation and spare capacity, some areas with high wind power penetration have serious wind abandonment. Wind power consumption has become the focus of the society, and it is a major problem that needs to be solved urgently in the current power grid dispatching operation.
  • SCUC Safety Constrained Units
  • SCED Safety Constrained Economic Dispatch
  • the present invention provides an optimization analysis method for a day-to-day scheduling plan under a coordinated mode of wind and fire, based on a power generation plan optimization result in a coordinated mode of intermittent energy and conventional energy, Under the condition that the power grid needs to abandon the wind, it can flexibly analyze the influence of various factors in the actual dispatch, dispatch various auxiliary adjustment channels, and improve the level of wind power received by the power grid.
  • the day-to-day scheduling plan optimization auxiliary analysis method includes the following steps:
  • the pre-issue electric plan optimization model is:
  • NT is the number of periods included in the system scheduling period; the number of units participating in the scheduling in the system;
  • l, tl, t, S period is the unit output increment in the segment s; w is the operating state of the unit in the period, 1 means running, 0
  • C ⁇ . is the cost of the unit/downtime
  • Tie tie , t TieP tie t , (tie, t) e ⁇ ( 11 )
  • corpse / ⁇ is the total load of the system power generation calibre
  • is the output of the unit during the period
  • pi 11111 is tl
  • ⁇ ⁇ Number of lines for the system and the external grid; lie
  • is the rotation standby calculation period (such as 5 minutes rotation, 30 minutes rotation)
  • ⁇ and ⁇ are the lower limit of the output and the upper limit of the output of the unit during the period
  • is the standby demand for the system to spin up and down during the period
  • I 1,0 I I is the time that the unit has been turned on and off at the initial time; 17. and ⁇ are the units at the beginning of the dispatch
  • TieP is the tie line ⁇ in the period tie, t
  • is a time set for the planning tie line
  • ⁇ ⁇ is the set of units that are willing to participate in the start and stop peaking, whether the unit starts and stops, the aof I I quantity, my and mz are the maximum allowable start and stop quantity;
  • ⁇ ⁇ is the maximum peak amplitude limit parameter of the unit during the period
  • rnWop is the maximum depth peaking unit number
  • T ie P,ie,, TieP i,t + Me Ptie , t - A Ptie, t t) G
  • 3 is the down-spinning standby variable with the period reduced, which is the lower-rotation reserve with the largest down period.
  • the wind power optimization aids the analysis decision at the cost of increasing the additional cost, and comprehensively considers various methods adopted by the grid to improve wind power consumption. After paying additional costs, the overall optimization goal is expressed when the wind power optimization auxiliary analysis decision is added:
  • F is the optimization target of the conventional safety-constrained unit combination
  • / ⁇ is the unit cost of the unit during the deep adjustment of the unit
  • is the additional unit cost of the unit deviating from the fixed output during the period.
  • ⁇ ' ⁇ is to adjust the unit cost of the contact line ⁇ in the time period, in order to reduce the risk cost of the unit system standby.
  • the invention solves the problem of optimizing the standby demand of the system, optimizing the external tie line to receive the power receiving plan, and deepening the peak level of the unit by analyzing and optimizing the standby demand of the power grid, and counting the auxiliary strategies for improving the wind power consumption, although the auxiliary strategy will generate certain The extra cost, but compared with the thermal power generation, the power generation cost is guaranteed to be the lowest in the case of wind power consumption.
  • Advantageous Effects The optimization analysis method for the day-to-day scheduling plan under the wind-fire coordination mode provided by the present invention is an optimized auxiliary analysis that comprehensively considers the coordination of intermittent energy and conventional energy, and improves the safe operation and economy of the power grid. The ability of the grid to accept wind power.
  • Figure 1 is a flow chart of the present invention.
  • FIG. 1 is a flow chart of a preferred embodiment of the method; in the preparation process of the grid pre-generation power generation plan optimization model, considering the sub-day wind power prediction situation and the available state of each conventional unit, load balance constraint, unit operation constraint, Factors such as grid security constraints may cause wind abandonment.
  • the auxiliary power generation planning optimization auxiliary analysis method in the case that the system needs to abandon the wind, optimizes the external contact line to receive the power receiving plan, optimizes the system standby demand, and performs deep adjustment on the unit. Peaks and other aspects improve the ability of the grid to absorb wind power.
  • the method specifically includes the following steps:
  • NT is the number of periods included in the system scheduling period; the number of units participating in the scheduling in the system;
  • the output of the unit is in the segment s; w is the operating state of the unit during the period, 1 means running, 0
  • C ⁇ . is the cost of the unit/downtime
  • Tietie tiet TieP tiet ⁇ ( ⁇ , ) ⁇ where corpse/ ⁇ is the total load of the system's power generation calibre; ⁇ is the output of the unit during the time period, pi 11111 is tl, t I unit / minimum technical output (corresponding to the baseline cost) ⁇ ⁇ .
  • I 1,0 I I is the time that the unit has been turned on and off at the initial time; 17. and ⁇ are the units at the beginning of the dispatch
  • TieP is the tie line ⁇ in the period tie, t
  • ⁇ ⁇ is a time set for the planning contact line
  • wind power optimization auxiliary analysis parameters include start-stop unit, maximum start-stop group number, adjustable peak unit, maximum peak-sharing unit number Quantity, adjustable fixed output unit and tie line, adjustable ratio of system backup, etc.;
  • ⁇ ⁇ is the set of units that are willing to participate in the start and stop peaking, and the amount of aof that is the start or stop of the unit, my and mz are the maximum allowable number of start and stop;
  • ⁇ ⁇ is the maximum peak amplitude limit parameter of the unit during the period
  • rnWop is the maximum depth peaking unit number
  • T ie P,ie,, TieP i,t + Me Ptie , t - A Ptie, t t) G
  • 3 is the down-spinning standby variable with the period reduced, which is the lower-rotation reserve with the largest down period.
  • the wind power optimization aids the analysis decision at the cost of increasing the additional cost, and comprehensively considers various methods adopted by the grid to improve wind power consumption. After paying additional costs, the overall optimization goal is expressed when the wind power optimization auxiliary analysis decision is added:
  • F is the optimization target of the conventional safety-constrained unit combination
  • / ⁇ is the unit cost of the unit during the deep adjustment of the unit
  • is the additional unit cost of the unit deviating from the fixed output during the period.
  • ⁇ ' ⁇ is to adjust the unit cost of the contact line ⁇ in the time period, in order to reduce the risk cost of the unit system standby.
  • the technical solution is applied in a network level power grid dispatching planning system, and the application effect is in line with expectations.
  • the practical application shows that the invention can connect as much wind power as possible to the power grid under the premise of satisfying various constraints such as system balance constraints, unit operation constraints, grid safety constraints and environmental constraints; it can effectively improve the new energy Utilization, reducing power generation costs.
  • This method studies and attempts to optimize the auxiliary analysis method of power generation plan under the actual grid data, and explores the auxiliary analysis method for improving the grid to absorb wind power under the intermittent energy and conventional energy coordinated scheduling mode. Under the conditions of ensuring safe operation of the power grid, connect as much wind power as possible to the power grid to improve economic efficiency. At the same time, the method has the characteristics of low calculation intensity and strong adaptability, and is more suitable for popularization and application in the dispatching institutions with large wind power access power in China.

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

Disclosed is an auxiliary analysis method for optimization of a current scheduling plan in a wind-fire coordinated scheduling mode, which aims at minimizing the power generation cost of a system, and comprehensively considers factors such as a connection line plan, a spare plan, and deep peak regulation of a unit under the circumstance that wind abandonment may occur in a power grid, so as to ensure that wind power is integrated into the power grid as much as possible, thereby improving the utilization of intermittent-type energy sources and increasing economic benefits. Meanwhile, the method has the characteristics of low computing intensity and strong adaptability, and is more suitable for being promoted and applied to scheduling mechanisms with large wind-power integration power in China.

Description

风火协调调度模式下日前调度计划优化辅助分析方法 技术领域  Auxiliary analysis method for dispatching plan optimization under the wind-fire coordination mode
本发明涉及电力系统调度自动化技术,尤其涉及一种风火协调调度模式下日前调度 计划优化辅助分析方法。  The invention relates to a power system dispatching automation technology, in particular to a method for optimizing an auxiliary analysis of a daily dispatching plan under a wind-fire coordinated scheduling mode.
背景技术 Background technique
风电作为技术最成熟的新能源利用方式之一,在国家的政策支持下装机容量大幅度 增长。 截至 2011年底, 风电累计装机容量超过 6500万 kW, 居世界第一, 但风电平均 利用小时数比上年降低 144小时, 仅为 1903小时, 远未达到预期目标。 风力发电具有 不确定性、 波动性、 反调峰性等特点, 而且现有短期风功率预测准确度不高, 给系统备 用、 调峰、 电力平衡等方面带来挑战。 同时, 国内发电运行环境以大火电为主, 在风电 并网规模较大的北方地区,风电的反调峰特性会进一步加大电网的峰谷差。受电网调峰、 输送和备用能力等因素的限制, 部分风电渗透率高的地区存在着较为严重的弃风现象。 风电消纳已成为社会普遍关注的焦点, 是当前电网调度运行迫切需要解决的重大问题。  As one of the most mature new energy utilization methods, wind power has increased its installed capacity with the support of national policies. As of the end of 2011, the cumulative installed capacity of wind power exceeded 65 million kW, ranking first in the world. However, the average utilization hours of wind power decreased by 144 hours compared with the previous year, only 1903 hours, far from the expected target. Wind power has the characteristics of uncertainty, volatility and anti-peak shaving, and the accuracy of existing short-term wind power prediction is not high, which brings challenges to system backup, peak shaving and power balance. At the same time, the domestic power generation operating environment is dominated by large thermal power. In the northern regions where wind power is connected to the grid, the peak characteristics of wind power will further increase the peak-to-valley difference of the power grid. Due to factors such as peak shaving, transportation and spare capacity, some areas with high wind power penetration have serious wind abandonment. Wind power consumption has become the focus of the society, and it is a major problem that needs to be solved urgently in the current power grid dispatching operation.
随着智能电网调度技术支持系统的建设和电网调度精益化的发展,安全约束机组组 合(SCUC)和安全约束经济调度(SCED) 已经在调度计划生产中得到应用, 但目前我 国调度计划一般采用长、 中、 短周期计划相结合的方式, 在日前计划中完全采用 SCUC 方法, 对风电的消纳最为有利, 但对电网生产计划冲击很大, 在实际生产中存在较大的 困难; 而 SCED方法不改变机组启停计划, 一定程度上影响了风电的消纳。  With the development of smart grid dispatching technical support system and the development of lean grid scheduling, Safety Constrained Units (SCUC) and Safety Constrained Economic Dispatch (SCED) have been applied in the production of dispatching plans, but at present, China's dispatching plans are generally long. The combination of medium and short-cycle plans, the SCUC method is fully adopted in the previous plan, which is most beneficial to the consumption of wind power, but it has a great impact on the grid production plan, and there are great difficulties in actual production; and the SCED method Does not change the start and stop plan of the unit, which has affected the consumption of wind power to a certain extent.
风电接纳能力不足主要受制于电网结构薄弱, 以及电源布局不合理, 无法满足高渗 透率新能源发电接入后的电网频率电压和供电可靠性要求。但机组启停和出力计划安排 对新能源接纳也有非常明显的影响, 通过与常规能源发电的协调优化, 有助于挖掘电网 潜力, 提升新能源发电接纳能力。  The lack of wind power acceptance is mainly due to the weak grid structure and unreasonable power supply layout, which cannot meet the grid frequency voltage and power supply reliability requirements of high-permeability new energy power generation. However, the start-stop and output plan of the unit also has a very obvious impact on the acceptance of new energy. Through coordination and optimization with conventional energy power generation, it is helpful to tap the potential of the power grid and enhance the capacity of new energy power generation.
发明内容 Summary of the invention
发明目的: 为了克服现有技术中存在的不足, 本发明提供一种风火协调调度模式下 日前调度计划优化辅助分析方法,基于间歇式能源与常规能源协调调度模式下的发电计 划优化结果, 在电网需要弃风的条件下, 能够灵活分析实际调度中各种因素的影响, 调 度各种辅助调整途径, 提升电网接纳风电的水平。  OBJECT OF THE INVENTION In order to overcome the deficiencies in the prior art, the present invention provides an optimization analysis method for a day-to-day scheduling plan under a coordinated mode of wind and fire, based on a power generation plan optimization result in a coordinated mode of intermittent energy and conventional energy, Under the condition that the power grid needs to abandon the wind, it can flexibly analyze the influence of various factors in the actual dispatch, dispatch various auxiliary adjustment channels, and improve the level of wind power received by the power grid.
技术方案: 为实现上述目的, 本发明采用的技术方案为:  Technical Solution: In order to achieve the above object, the technical solution adopted by the present invention is:
风火协调调度模式下日前调度计划优化辅助分析方法, 包括如下步骤:  In the wind-fire coordination mode, the day-to-day scheduling plan optimization auxiliary analysis method includes the following steps:
( 1 ) 基于实际电网的物理模型和经济模型, 考虑系统平衡约束、 机组运行约束、 电网安全约束, 建立以系统发电成本最小为目标的风火协调调度日前发电计划优化模 型, 所述发日前电计划优化模型为: (1) Based on the physical model and economic model of the actual power grid, considering the system balance constraints, unit operation constraints, and grid security constraints, establish a wind power coordination scheduling day-to-day power generation plan optimization model with the minimum system power generation cost as the goal. Type, the pre-issue electric plan optimization model is:
目标函数:
Figure imgf000004_0001
Objective function:
Figure imgf000004_0001
其中, NT为系统调度周期所含时段数; 为系统中参与调度的机组数; Ν  Where NT is the number of periods included in the system scheduling period; the number of units participating in the scheduling in the system;
T I s为机 组发电成本分段数; c 为机组 在分段 s内的发电成本, 按分段递增; I 为机组 在  T I s is the number of power generation cost segments of the unit; c is the power generation cost of the unit in the segment s, increasing in increments; I is the unit
l,t l,t,S 时段 处于分段 s内的机组出力增量; w 为机组 在时段 的运行状态, 1表示运行, 0表 l, tl, t, S period is the unit output increment in the segment s; w is the operating state of the unit in the period, 1 means running, 0
l,t  l,t
示停运; C.为机组在最低技术出力时的发电成本; y 为机组 在时段 是否有停机到开 Showdown; C. Power generation cost for the unit at the lowest technical output; y for the unit During the period Whether there is a shutdown to open
I i,t  I i,t
机状态变化的标志; Ce7 ^为机组 的启动成本; z 为机组在时段 是否有开机到停机 The sign of the change of the machine state; C e7 ^ is the starting cost of the unit; z is the start-to-stop of the unit during the period
S1 ,ι i,t  S1 , ι i,t
状态变化的标志; C^ .为机组 /的停机成本; The sign of the state change; C^. is the cost of the unit/downtime;
SD,i  SD,i
约束条件:  Restrictions:
Ντ N, Ν τ N,
TIE  TIE
∑ Pi,t+tiePtie,t=PDt (2) i=l tie=l ∑ Pi,t +tie Ptie,t= PD t (2) i=l tie=l
Figure imgf000004_0002
Figure imgf000004_0002
<RD.-u- 國 賺  <RD.-u- Country Earn
I (6) (1— uit) = 0 TUt =max{0,min[N ,( [/ 11 -Γ[/ )·Μ· Q]} (7) ί=1 ' I (6) (1—u it ) = 0 TU t =max{0,min[N ,( [/ 11 -Γ[/ )·Μ· Q ]} (7) ί=1 '
ΓΖ).  ΓΖ).
∑ u-=0; TD.=max{0,mm[NT,(TD^mn-TD9)-(l-u. n)]} (8) t=i
Figure imgf000004_0003
ζ"+ ∑ yi t<\ V ,t = r ;+l,...,Nr ( 10)
∑ u- =0; TD.=max{0,mm[N T ,(TD^ mn -TD9)-(lu. n )]} (8) t=i
Figure imgf000004_0003
ζ"+ ∑ y it <\ V , t = r ; +l,...,N r ( 10)
' τ=ΐ+1 ' ' τ=ΐ+1 '
tieptie,t = TiePtie t , (tie, t) e ΤΡΙαη ( 11 ) 其中, 尸/^为时段 系统发电口径的总负荷; ρ 为机组 在时段 的出力, pi11111为 t l,t I 机组 /最低技术出力 (对应基准成本时的出力); Ντ. 为系统与外部电网的联络线数; lie Tie tie , t = TieP tie t , (tie, t) e ΤΡΙαη ( 11 ) where corpse / ^ is the total load of the system power generation calibre; ρ is the output of the unit during the period, pi 11111 is tl, t I unit / Minimum technical output (output corresponding to the baseline cost); Ν τ . Number of lines for the system and the external grid; lie
为联络线^在时段 的送 /受电计划; ΤίΓ为旋转备用计算周期 (如 5分钟旋备、 30分钟旋备), ^^^和^^^为机组 在时段 的出力下限和出力上限; 和 为机组 在时段 能提供的上旋和下旋备用, ρ 、 为系统在时段 上旋和下旋的备用需求;  For the contact line ^ delivery/receiving plan during the period; ΤίΓ is the rotation standby calculation period (such as 5 minutes rotation, 30 minutes rotation), ^^^ and ^^^ are the lower limit of the output and the upper limit of the output of the unit during the period; And for the unit to provide the upper and lower rotation reserve during the period, ρ, is the standby demand for the system to spin up and down during the period;
717.为机组 最小持续运行时间,在计算前需要根据初始运行时间进行扣减;式中 71/ !^n717. For the minimum continuous running time of the unit, it needs to be deducted according to the initial running time before calculation; where 71/ !^n
I I I I
和 Z)min分别为机组 的最小开机和停机时间, 机组 的初始状态; 7T/Q和 r)QAnd Z) min are the minimum start-up and downtime of the unit, the initial state of the unit; 7T/ Q and r) Q points
I 1,0 I I 别为机组 在初始时刻已经开机和停机的时间; 17.和 ΓΖ 分别为机组 在调度初期为满 I 1,0 I I is the time that the unit has been turned on and off at the initial time; 17. and ΓΖ are the units at the beginning of the dispatch
I I  I I
足最小运行时间或停运时间而必须继续运行和停运的时间; TieP 为联络线^在时段 tie,t The minimum run time or outage time must continue to run and stop; TieP is the tie line ^ in the period tie, t
的交易计划; Φ^^ 为计划联络线一时间集合;  Trading plan; Φ^^ is a time set for the planning tie line;
(2)求解日前发电计划优化模型, 根据计算结果确定是否需要弃风, 如需要弃风, 进行风电优化辅助分析, 设置风电优化辅助分析参数, 所述风电优化辅助分析参数包括 可启停的机组、 最大启停机组数量、 可调峰机组、 最大调峰机组数量、 可调整计划的固 定出力机组和联络线、 系统备用的可调整比例; (2) Solving the day-to-day power generation plan optimization model, determining whether wind is needed according to the calculation result, if wind is needed, performing wind power optimization auxiliary analysis, setting wind power optimization auxiliary analysis parameters, the wind power optimization auxiliary analysis parameters including start-stop unit , the maximum number of start-stop groups, the adjustable peak unit, the maximum number of peak-sharing units, the fixed-planning unit and the tie line of the adjustable plan, and the adjustable ratio of the system standby;
(3) 根据风电接纳优化辅助分析参数构造多个辅助分析案例, 分析提高风电消纳 的途径;  (3) Constructing multiple auxiliary analysis cases based on wind power acceptance optimization auxiliary analysis parameters, and analyzing ways to improve wind power consumption;
(4) 采用风电优化辅助分析优化模型对所有辅助分析案例进行优化求解, 统计分 析在各机组启停调峰、 机组深度调峰、 机组固定计划调整、 联络线计划调整、 备用不同 比例调整的情况下, 风电消纳变化情况;  (4) Using the wind power optimization auxiliary analysis optimization model to optimize the solution for all auxiliary analysis cases, statistical analysis of the start and stop peaking of each unit, unit deep peak shaving, unit fixed plan adjustment, tie line plan adjustment, standby different proportion adjustment Next, the wind power consumption changes;
(5) 根据统计分析结果判断是否存在提高风电消纳的可行方法, 若存在, 则分析 确定日前发电计划优化编制采用的提高风电消纳的方法,修改日前发电计划优化编制条 件, 优化编制新的日前发电计划。 ( a) 对于机组启停调峰, 主要针对中小机组, 在构造辅助分析案例时, 需要在风 电优化辅助分析优化模型中增加如下约束条件: (5) According to the results of statistical analysis, it is judged whether there is a feasible method to improve wind power consumption. If it exists, it analyzes and determines the method of improving wind power consumption adopted by the optimization plan of the previous power generation plan, modifies the preparation conditions of the previous power generation plan, and optimizes the preparation of new A few days ago, the power generation plan. (a) For the start and stop peaking of the unit, mainly for small and medium-sized units, in the case of structural auxiliary analysis cases, the following constraints must be added to the wind power optimization auxiliary analysis optimization model:
yf^ zf^ {0, 1}
Figure imgf000006_0001
i=l
Figure imgf000006_0002
mz
Yf^ zf^ {0, 1}
Figure imgf000006_0001
i=l
Figure imgf000006_0002
mz
i=l  i=l
其中, Φ ^是愿意参加启停调峰的机组集合, 为机组 是否启机和停机的变 aof I I 量, my和 mz为最大允许启机和停机数量;  Among them, Φ ^ is the set of units that are willing to participate in the start and stop peaking, whether the unit starts and stops, the aof I I quantity, my and mz are the maximum allowable start and stop quantity;
(b ) 对于部分大中火机组深调峰, 在构造辅助分析案例时, 需要在风电优化辅助 分析优化模型中增加如下约束条件:
Figure imgf000006_0003
(b) For some large and medium-sized fire units to deep-tune peaks, in the case of constructing auxiliary analysis cases, the following constraints must be added to the wind power optimization auxiliary analysis optimization model:
Figure imgf000006_0003
viopi t < viopfi · viopli t
Figure imgf000006_0004
< mviop 其中, Φ . 可承担深度调峰任务的机组, 为机组 在时段 的深度调峰幅度, vioa i,t
Viopi t < viopfi · viopli t
Figure imgf000006_0004
< mviop where Φ . The unit that can undertake the task of deep peak shaving, which is the peak amplitude of the unit during the period, vioa i,t
机组 是否深度调峰的标志变量, νΰψ^为机组 在时段 最大调峰幅度限值参 数, rnWop为最大深度调峰机组数量; Whether the unit has a deep peak peaking variable, νΰψ^ is the maximum peak amplitude limit parameter of the unit during the period, and rnWop is the maximum depth peaking unit number;
( c ) 对于机组固定计划调整, 在风电消纳困难的情况下, 适当调整这类机组的固 定计划, 电网支付偏离经济运行的额外成本, 有利于提高电网消纳风电的能力, 在构造 辅助分析案例时, 需要在风电优化辅助分析优化模型中增加如下约束条件: (c) For the fixed plan adjustment of the unit, in the case of difficult wind power consumption, properly adjust the fixed plan of such units, and the grid payment deviates from the extra cost of economic operation, which is conducive to improving the ability of the grid to absorb wind power. In the case of case, the following constraints need to be added to the wind power optimization auxiliary analysis optimization model:
Ρυ = Ρυ +
Figure imgf000006_0005
V(i, i) e Φρ1αη n Φ „ (d) 对于优化外部联络线送受电计划, 在构造辅助分析案例时, 需要在风电优化 辅助分析优化模型中增加如下约束条件:
Ρ υ = Ρ υ +
Figure imgf000006_0005
V(i, i) e Φ ρ1αη n Φ „ (d) For optimizing the external tie line transmission and reception plan, when constructing the auxiliary analysis case, the following constraints need to be added to the wind power optimization auxiliary analysis optimization model:
tieP,ie,, = TiePi,t + MePtie,t - APtie,t
Figure imgf000007_0001
t) G
T ie P,ie,, = TieP i,t + Me Ptie , t - A Ptie, t
Figure imgf000007_0001
t) G
(e) 对于优化系统备用需求, 考虑备用可调整, 在构造辅助分析案例时, 需要将 系统下旋备用约束表示为: (e) For optimizing system backup requirements, consider alternate adjustments. When constructing an auxiliary analysis case, you need to express the system spin-off standby constraint as:
f» _ f» _
Figure imgf000007_0002
Figure imgf000007_0002
其中, 3为时段 降低的下旋备用变量, 为时段 最大可下调的下旋备用量。 所述风电优化辅助分析决策以增加额外成本为代价,综合考虑电网提高风电消纳而 采用的各种方法, 支付额外成本后, 在增加风电优化辅助分析决策时总的优化目标表示 为: Among them, 3 is the down-spinning standby variable with the period reduced, which is the lower-rotation reserve with the largest down period. The wind power optimization aids the analysis decision at the cost of increasing the additional cost, and comprehensively considers various methods adopted by the grid to improve wind power consumption. After paying additional costs, the overall optimization goal is expressed when the wind power optimization auxiliary analysis decision is added:
Figure imgf000007_0003
Figure imgf000007_0003
e^atiet-l t-l  E^atiet-l t-l
其中 , 为日前调度计划优化辅助分析的广义优化目标, F为常规安全约束机组 组合的优化目标, /^为机组 在时段 深调峰单位成本, αρ^为机组 在时段 偏离固 定出力的额外单位成本, ^'^^为调整联络线^在时段 计划的单位成本, 为降低 单位系统备用的风险成本。  Among them, for the general optimization objective of the auxiliary analysis for the previous scheduling plan, F is the optimization target of the conventional safety-constrained unit combination, /^ is the unit cost of the unit during the deep adjustment of the unit, and αρ^ is the additional unit cost of the unit deviating from the fixed output during the period. , ^'^^ is to adjust the unit cost of the contact line ^ in the time period, in order to reduce the risk cost of the unit system standby.
间歇式能源将在未来能源结构中占据重要地位, 但是作为其代表的风电具有随机 性、 波动性和间歇性, 与常规能源相比, 可靠性较低。 本发明在指定发电计划时, 充分 协调考虑各种复杂因素, 保障尽可能多的风电安全接入电网。  Intermittent energy will play an important role in the future energy structure, but wind power, as its representative, is random, volatility and intermittent, and has lower reliability than conventional energy. When the power generation plan is specified, the present invention fully coordinates various complicated factors to ensure that as many wind powers as possible are safely connected to the power grid.
本发明在电网需要弃风的情况下, 通过分析优化系统备用需求, 优化外部联络线送 受电计划, 机组深调峰等策略, 统计出可以提高消纳风电的辅助策略, 虽然辅助策略会 产生一定的额外费用, 但与火电机组发电相比, 在尽可多消纳风电情形下保证发电成本 最低。 有益效果: 本发明提供的风火协调调度模式下日前调度计划优化辅助分析方法, 是 经过综合考虑间歇式能源和常规能源协调的优化辅助分析,在保证电网安全运行及经济 性的条件下, 提高了电网接纳风电的能力。 The invention solves the problem of optimizing the standby demand of the system, optimizing the external tie line to receive the power receiving plan, and deepening the peak level of the unit by analyzing and optimizing the standby demand of the power grid, and counting the auxiliary strategies for improving the wind power consumption, although the auxiliary strategy will generate certain The extra cost, but compared with the thermal power generation, the power generation cost is guaranteed to be the lowest in the case of wind power consumption. Advantageous Effects: The optimization analysis method for the day-to-day scheduling plan under the wind-fire coordination mode provided by the present invention is an optimized auxiliary analysis that comprehensively considers the coordination of intermittent energy and conventional energy, and improves the safe operation and economy of the power grid. The ability of the grid to accept wind power.
附图说明 DRAWINGS
图 1为本发明流程图。  Figure 1 is a flow chart of the present invention.
具体实施方式 Detailed ways
下面结合附图对本发明作更进一步的说明。  The present invention will be further described below in conjunction with the accompanying drawings.
一种间歇式能源与常规能源协调调度模式下日前调度计划优化辅助分析方法,如图 An auxiliary auxiliary analysis method for daily dispatching plan under the coordinated mode of intermittent energy and conventional energy, as shown in the figure
1所示为该方法的一个优选实施案例的流程图; 在电网日前发电计划优化模型的编制过 程中, 考虑次日风功率预测情况和各常规机组的可用状态, 负荷平衡约束、 机组运行约 束、 电网安全约束等因素, 可能出现弃风的情形。 1 is a flow chart of a preferred embodiment of the method; in the preparation process of the grid pre-generation power generation plan optimization model, considering the sub-day wind power prediction situation and the available state of each conventional unit, load balance constraint, unit operation constraint, Factors such as grid security constraints may cause wind abandonment.
本发明的间歇式能源与常规能源协调调度模式下日前发电计划优化辅助分析方法, 在系统如果需要弃风的情形下, 从优化外部联络线送受电计划, 优化系统备用需求, 对 机组进行深度调峰等各方面提高电网消纳风电的能力。 本方法具体包括如下步骤: In the intermittent energy source and conventional energy coordinated scheduling mode of the present invention, the auxiliary power generation planning optimization auxiliary analysis method, in the case that the system needs to abandon the wind, optimizes the external contact line to receive the power receiving plan, optimizes the system standby demand, and performs deep adjustment on the unit. Peaks and other aspects improve the ability of the grid to absorb wind power. The method specifically includes the following steps:
( 1 ) 基于实际电网的物理模型和经济模型, 考虑系统平衡约束、 机组运行约束、 电网安全约束, 建立以系统发电成本最小为目标的风火协调调度日前发电计划优化模 型, 所述发日前电计划优化模型为: (1) Based on the physical model and economic model of the actual power grid, considering the system balance constraint, unit operation constraints, and grid security constraints, establish a wind power coordination scheduling power generation plan optimization model with the minimum system power generation cost as the target. The plan optimization model is:
目标函数:
Figure imgf000008_0001
Objective function:
Figure imgf000008_0001
其中, NT为系统调度周期所含时段数; 为系统中参与调度的机组数; Ν  Where NT is the number of periods included in the system scheduling period; the number of units participating in the scheduling in the system;
T I s为机 组发电成本分段数; c 为机组 在分段 s内的发电成本, 按分段递增; I 为机组 在  T I s is the number of power generation cost segments of the unit; c is the power generation cost of the unit in the segment s, increasing in increments; I is the unit
l,t l,t,S  l,t l,t,S
时段 处于分段 s内的机组出力增量; w 为机组 在时段 的运行状态, 1表示运行, 0表 The output of the unit is in the segment s; w is the operating state of the unit during the period, 1 means running, 0
l ,t  l ,t
示停运; C.为机组在最低技术出力时的发电成本; y 为机组 在时段 是否有停机到开 Showdown; C. Power generation cost for the unit at the lowest technical output; y for the unit During the period Whether there is a shutdown to open
I i,t  I i,t
机状态变化的标志; Ce7 ^为机组 的启动成本; z 为机组在时段 是否有开机到停机 The sign of the change of the machine state; C e7 ^ is the starting cost of the unit; z is the start-to-stop of the unit during the period
S1 ,ι i,t  S1 , ι i,t
状态变化的标志; C^ .为机组 /的停机成本; The sign of the state change; C^. is the cost of the unit/downtime;
SD,i  SD,i
约束条件:  Restrictions:
a. 发用电平衡约束: ΝΉΕ a. Power balance constraint: Ν ΉΕ
∑ Pj + ∑ tieptie t=PDt i=l ' tie=l ' , ∑ Pj + ∑ tiep tie t = PD t i=l 'tie=l ' ,
Figure imgf000009_0001
Figure imgf000009_0001
r^t < min(«. · p^ x -p. ,RU. RT)
Figure imgf000009_0002
r^ t < min(«. · p^ x -p. , RU. RT)
Figure imgf000009_0002
i=\ i=\
min(w C 'RT)min( w C ' RT )
Figure imgf000009_0003
Figure imgf000009_0003
i=l ,  i=l ,
行约束:Row constraint:
Figure imgf000009_0004
- 1 — rfax'd-" — 1)
Figure imgf000009_0005
Figure imgf000009_0004
- 1 — rfax'd-" — 1)
Figure imgf000009_0005
PL - 1 +纖-(1- ",',H) - p{ t <RDi t + PL - 1 + fiber - (1- ", ', H) - p { t <RD it +
Pi,t- ·Μ . max '(1— M,. t ) y(l-M.r) = 0 TU. =max{0,min[Nr ,(Γί/™η -Tu9).u. n]} Pi, t- · Μ. Max ' (1- M ,. t) y (lM. R) = 0 TU. = Max {0, min [N r, (Γί / ™ η -Tu9). U. N] }
∑ ui t =0; m =max{0,min[Nr,(r ?llin -ΓΖ) )·(1-«. Q )] } '■ t + TU, + 1, ..·, Nr ∑ u it =0; m =max{0,min[N r ,(r ? llin -ΓΖ) )·(1-«. Q )] } '■ t + TU, + 1, ..·, N r
Figure imgf000009_0006
min{NrJ+rZ)÷mii-l}
,
Figure imgf000009_0006
Min{N r J+rZ)÷ mii -l}
+ ∑ y. <1 /i,t = TD.+l,...,N.  + ∑ y. <1 /i,t = TD.+l,...,N.
r=t+l
Figure imgf000010_0001
+ J≤1 uit =0 t) Φο
Figure imgf000010_0002
r=t+l
Figure imgf000010_0001
+ J ≤1 u it =0 t) Φ ο
Figure imgf000010_0002
c. 联络线送 /受电计划约束: c. Contact line delivery / power receiving plan constraints:
tieptiet = TiePtiet ν(^, )εΦ 其中, 尸/^为时段 系统发电口径的总负荷; ρ 为机组 在时段 的出力, pi11111为 t l,t I 机组 /最低技术出力 (对应基准成本时的出力); Ντ. 为系统与外部电网的联络线数; lie Tietie tiet = TieP tiet ν(^, )εΦ where corpse/^ is the total load of the system's power generation calibre; ρ is the output of the unit during the time period, pi 11111 is tl, t I unit / minimum technical output (corresponding to the baseline cost)出τ . The number of lines connecting the system to the external grid; lie
为联络线^在时段 的送 /受电计划; 为旋转备用计算周期 (如 5分钟旋备、 30分钟旋备), 1^11和/^^^为机组 在时段 的出力下限和出力上限; 和 为机组 在时段 能提供的上旋和下旋备用, Ρ 、 为系统在时段 上旋和下旋的备用需求; 717.为机组 最小持续运行时间,在计算前需要根据初始运行时间进行扣减;式中 71/ !^nFor the contact line ^ delivery/reception plan during the period; for the rotation reserve calculation period (such as 5 minutes rotation, 30 minutes rotation), 1 ^ 11 and /^^^ are the lower limit of the output and the upper limit of the output of the unit during the period; And for the unit to provide the upper and lower rotation reserve during the period, Ρ, for the system in the period of the spin up and down the standby demand; 717. for the minimum operating time of the unit, the calculation needs to be deducted according to the initial running time ;式71/ !^n
I I I I
和 Z)min分别为机组 的最小开机和停机时间, 机组 的初始状态; 7T/Q和 r)QAnd Z) min are the minimum start-up and downtime of the unit, the initial state of the unit; 7T/ Q and r) Q points
I 1,0 I I 别为机组 在初始时刻已经开机和停机的时间; 17.和 ΓΖ 分别为机组 在调度初期为满 I 1,0 I I is the time that the unit has been turned on and off at the initial time; 17. and ΓΖ are the units at the beginning of the dispatch
I I  I I
足最小运行时间或停运时间而必须继续运行和停运的时间; TieP 为联络线^在时段 tie,t The minimum run time or outage time must continue to run and stop; TieP is the tie line ^ in the period tie, t
的交易计划; Φ^ ^为计划联络线一时间集合;  Trading plan; Φ^ ^ is a time set for the planning contact line;
(2) 在日前发电计划优化编制完成后, 看是否需要弃风, 如需要弃风, 则初步分 析日前发电计划影响风电消纳的原因, 判断是否需要进行风电优化辅助分析; (2) After the completion of the optimization plan for the power generation plan, it is necessary to see whether it is necessary to abandon the wind. If it is necessary to abandon the wind, it will initially analyze the reasons for the impact of wind power consumption on the current power generation plan, and determine whether wind power optimization and auxiliary analysis is needed.
(3) 若需要进行风电优化辅助分析, 则设置风电优化辅助分析参数, 所述风电优 化辅助分析参数包括可启停的机组、 最大启停机组数量、 可调峰机组、 最大调峰机组数 量、 可调整计划的固定出力机组和联络线、 系统备用的可调整比例等; (3) If wind power optimization auxiliary analysis is needed, set wind power optimization auxiliary analysis parameters, the wind power optimization auxiliary analysis parameters include start-stop unit, maximum start-stop group number, adjustable peak unit, maximum peak-sharing unit number Quantity, adjustable fixed output unit and tie line, adjustable ratio of system backup, etc.;
(4) 根据风电接纳优化辅助分析参数构造多个辅助分析案例, 主要从以下几个方 面提高风电消纳的途径:  (4) According to the wind power acceptance optimization auxiliary analysis parameters to construct a number of auxiliary analysis cases, mainly to improve the way of wind power consumption from the following aspects:
(a) 对于机组启停调峰, 主要针对中小机组, 在构造辅助分析案例时, 需要在风 电优化辅助分析优化模型中增加如下约束条件:  (a) For the start and stop peaking of the unit, mainly for small and medium-sized units, when constructing the auxiliary analysis case, the following constraints must be added to the wind power optimization auxiliary analysis optimization model:
«. 0,1}
Figure imgf000011_0001
i=l
«. 0,1}
Figure imgf000011_0001
i=l
Figure imgf000011_0002
Figure imgf000011_0002
其中, Φ ^是愿意参加启停调峰的机组集合, 为机组 是否启机和停机的变 aof 量, my和 mz为最大允许启机和停机数量;  Among them, Φ ^ is the set of units that are willing to participate in the start and stop peaking, and the amount of aof that is the start or stop of the unit, my and mz are the maximum allowable number of start and stop;
(b) 对于部分大中火机组深调峰, 需要在风电优化辅助分析优化模型中增加如下 约束条件: p <p^*u -viopu viopi t < viopfi · viopli t
Figure imgf000011_0003
< mviop 其中, Φ . 可承担深度调峰任务的机组, 为机组 在时段 的深度调峰幅度, νιοα i,t
(b) For some large and medium-sized fire units to deep-tune peaks, the following constraints need to be added to the wind power optimization auxiliary analysis optimization model: p <p^*u -viop u viopi t < viopfi · viopli t
Figure imgf000011_0003
< mviop where Φ . The unit that can undertake the task of deep peak shaving, which is the depth peak amplitude of the unit during the period, νιοα i,t
机组 是否深度调峰的标志变量, νΰψ^为机组 在时段 最大调峰幅度限值参 数, rnWop为最大深度调峰机组数量; Whether the unit has a deep peak peaking variable, νΰψ^ is the maximum peak amplitude limit parameter of the unit during the period, and rnWop is the maximum depth peaking unit number;
(c) 对于机组固定计划调整, 在风电消纳困难的情况下, 适当调整这类机组的固 定计划, 电网支付偏离经济运行的额外成本, 有利于提高电网消纳风电的能力, 需要在 风电优化辅助分析优化模型中增加如下约束条件: (c) For the fixed plan adjustment of the unit, in the case of difficult wind power consumption, the fixed plan of such units should be properly adjusted, and the additional cost of the grid payment deviating from the economic operation will help improve the ability of the grid to absorb wind power. The following constraints are added to the wind power optimization aided analysis optimization model:
Ρυ = Ρυ +
Figure imgf000012_0001
V(i,i) e Φρ1αη n Φ „
Ρ υ = Ρ υ +
Figure imgf000012_0001
V(i,i) e Φ ρ1αη n Φ „
( d) 对于优化外部联络线送受电计划, 需要在风电优化辅助分析优化模型中增加 如下约束条件: (d) For optimizing the external tie line transmission and reception plan, the following constraints need to be added to the wind power optimization auxiliary analysis optimization model:
tieP,ie,, = TiePi,t + MePtie,t - APtie,t
Figure imgf000012_0002
t) G
T ie P,ie,, = TieP i,t + Me Ptie , t - A Ptie, t
Figure imgf000012_0002
t) G
(e) 对于优化系统备用需求, 考虑备用可调整, 在构造辅助分析案例时, 需要将 系统下旋备用约束表示为: (e) For optimizing system backup requirements, consider alternate adjustments. When constructing an auxiliary analysis case, you need to express the system spin-off standby constraint as:
f» _
Figure imgf000012_0003
f» _
Figure imgf000012_0003
其中, 3为时段 降低的下旋备用变量, 为时段 最大可下调的下旋备用量。 所述风电优化辅助分析决策以增加额外成本为代价,综合考虑电网提高风电消纳而 采用的各种方法, 支付额外成本后, 在增加风电优化辅助分析决策时总的优化目标表示 为: Among them, 3 is the down-spinning standby variable with the period reduced, which is the lower-rotation reserve with the largest down period. The wind power optimization aids the analysis decision at the cost of increasing the additional cost, and comprehensively considers various methods adopted by the grid to improve wind power consumption. After paying additional costs, the overall optimization goal is expressed when the wind power optimization auxiliary analysis decision is added:
Figure imgf000012_0004
Figure imgf000012_0004
e^atiet-l t-l  E^atiet-l t-l
其中 , 为日前调度计划优化辅助分析的广义优化目标, F为常规安全约束机组 组合的优化目标, /^为机组 在时段 深调峰单位成本, αρ^为机组 在时段 偏离固 定出力的额外单位成本, ^'^^为调整联络线^在时段 计划的单位成本, 为降低 单位系统备用的风险成本。  Among them, for the general optimization objective of the auxiliary analysis for the previous scheduling plan, F is the optimization target of the conventional safety-constrained unit combination, /^ is the unit cost of the unit during the deep adjustment of the unit, and αρ^ is the additional unit cost of the unit deviating from the fixed output during the period. , ^'^^ is to adjust the unit cost of the contact line ^ in the time period, in order to reduce the risk cost of the unit system standby.
( 5 ) 采用风电优化辅助分析优化模型对所有辅助分析案例进行优化求解, 统计分 析在各机组启停调峰、 机组深度调峰、 机组固定计划调整、 联络线计划调整、 备用不同 比例调整的情况下, 风电消纳变化情况;  (5) Using wind power optimization analysis and optimization model to optimize all auxiliary analysis cases, statistical analysis of the start and stop peaking of each unit, unit deep peak shaving, unit fixed plan adjustment, tie line plan adjustment, standby different proportion adjustment Next, the wind power consumption changes;
( 6 ) 根据统计分析结果判断是否存在提高风电消纳的可行方法, 若存在, 则分析 确定日前发电计划优化编制采用的提高风电消纳的方法,修改日前发电计划优化编制条 件, 优化编制新的日前发电计划。 (6) Judging whether there is a feasible method for improving wind power consumption based on statistical analysis results, if any, then analyzing Determine the method for improving wind power consumption adopted in the optimization plan of the previous power generation plan, modify the preparation conditions for the previous power generation plan, and optimize the preparation of the new day-to-day power generation plan.
实际应用效果  Practical application effect
本技术方案在某网级电网调度计划系统中得到应用, 应用效果符合预期。 实际应用 表明, 本发明能够在满足系统平衡约束、 机组运行约束、 电网安全约束和环保约束等各 类约束的前提下,将尽可能多的风电安全的接入电网;能够有效提高对新能源的利用率, 降低发电成本。  The technical solution is applied in a network level power grid dispatching planning system, and the application effect is in line with expectations. The practical application shows that the invention can connect as much wind power as possible to the power grid under the premise of satisfying various constraints such as system balance constraints, unit operation constraints, grid safety constraints and environmental constraints; it can effectively improve the new energy Utilization, reducing power generation costs.
本方法在实际电网数据下开展的发电计划优化辅助分析方法的研究和尝试,摸索出 间歇式能源和常规能源协调调度模式下提高电网消纳风电的辅助分析方法。在保证电网 安全运行的条件下, 将尽可能多的风电接入电网, 提高经济效益。 同时, 该方法具有计 算强度低、 适应性强的特点, 更加适合在我国风电接入功率较大的调度机构推广应用。  This method studies and attempts to optimize the auxiliary analysis method of power generation plan under the actual grid data, and explores the auxiliary analysis method for improving the grid to absorb wind power under the intermittent energy and conventional energy coordinated scheduling mode. Under the conditions of ensuring safe operation of the power grid, connect as much wind power as possible to the power grid to improve economic efficiency. At the same time, the method has the characteristics of low calculation intensity and strong adaptability, and is more suitable for popularization and application in the dispatching institutions with large wind power access power in China.
以上所述仅是本发明的优选实施方式, 应当指出: 对于本技术领域的普通技术人员 来说, 在不脱离本发明原理的前提下, 还可以做出若干改进和润饰, 这些改进和润饰也 应视为本发明的保护范围。  The above description is only a preferred embodiment of the present invention, and it should be noted that those skilled in the art can also make several improvements and retouchings without departing from the principles of the present invention. It should be considered as the scope of protection of the present invention.

Claims

WO 2014/110878 +T +»、 PCT/CN2013/075498 权 利 要 求 书 WO 2014/110878 +T +», PCT/CN2013/075498 Claims
1、 风火协调调度模式下日前调度计划优化辅助分析方法, 其特征在于: 包括如下 步骤: 1. The auxiliary analysis method for the optimization of the dispatching plan in the wind-fire coordination mode, which is characterized by the following steps:
(1) 基于实际电网的物理模型和经济模型, 考虑系统平衡约束、 机组运行约束、 电网安全约束, 建立以系统发电成本最小为目标的风火协调调度日前发电计划优化模 型, 所述日前发电计划优化模型为:  (1) Based on the physical model and economic model of the actual power grid, considering the system balance constraint, unit operation constraints, and grid security constraints, establish a wind power coordination scheduling power generation plan optimization model with the minimum system power generation cost as the target, the day-to-day power generation plan The optimization model is:
目标函数:
Figure imgf000014_0001
Objective function:
Figure imgf000014_0001
其中, NT为系统调度周期内所含时段数; I为系统中参与调度的机组数; Ν  Where NT is the number of time periods included in the system scheduling period; I is the number of units participating in the scheduling in the system;
T s为 机组发电成本分段数; c 为机组 在分段 s内的发电成本,按分段递增; I 为机组 在  T s is the number of power generation costs of the unit; c is the power generation cost of the unit in the segment s, increasing in increments; I is the unit
l,t l,t,S  l,t l,t,S
时段 处于分段 s内的机组出力增量; w 为机组 在时段 的运行状态, 1表示运行, 0表 The output of the unit is in the segment s; w is the operating state of the unit during the period, 1 means running, 0
l,t  l,t
示停运; C.为机组在最低技术出力时的发电成本; y 为机组 在时段 是否有停机到开 Showdown; C. Power generation cost for the unit at the lowest technical output; y for the unit During the period Whether there is a shutdown to open
I i,t  I i,t
机状态变化的标志; Ce7 ^为机组 的启动成本; z 为机组在时段 是否有开机到停机 The sign of the change of the machine state; C e7 ^ is the starting cost of the unit; z is the start-to-stop of the unit during the period
S1 ,ι i,t  S1 , ι i,t
状态变化的标志; (^ .为机组 的停机成本; 约束条件: Sign of state change; (^. is the cost of downtime for the unit; Constraints:
TIE  TIE
∑ Pi,t+tiePtie,t=PDt (2) i=l tie=l ∑ Pi,t +tie Ptie,t= PD t (2) i=l tie=l
Figure imgf000014_0002
Figure imgf000014_0002
<RD.-u- 賺  <RD.-u- earn
I 'i.t+Pi (6) (1— uit) = 0 TUt =max{0,min[N ,( [/ 11 -Γ[/ )·Μ· Q]} (7) ί=1 ' I 'it + Pi (6) (1— u it ) = 0 TU t =max{0,min[N ,( [/ 11 -Γ[/ )·Μ· Q ]} (7) ί=1 '
ΓΖ).  ΓΖ).
∑ u-=0; TD.=max{0,mm[NT,(TD^mn-TD9)-(l-u. n)]} (8) t=i 权 利 要 求 书 ∑ u- =0; TD.=max{0,mm[N T ,(TD^ mn -TD9)-(lu. n )]} (8) t=i Claim
+ ? <1; Vi,t = r[/;+l,...,Nr (9)
Figure imgf000015_0001
t+ ∑ yt t<\ V ,t = r ; +l,...,Nr ( 10)
+ ? <1; Vi,t = r[/ ; +l,...,N r (9)
Figure imgf000015_0001
t+ ∑ y tt <\ V , t = r ; +l,...,N r ( 10)
T=t+1 ' tieptie't = TiePtie't V(ie, e ΦΤΡΙαη ( 11 ) 其中, 尸/^为时段 系统发电口径的总负荷; ρ 为机组 在时段 的出力, ρ™11为 t l,t I 机组 /最低技术出力; N 为系统与外部电网的联络线数; tiep f为联络线^在时段 ί 的送 /受电计划; 为旋转备用计算周期, 和 p^ax为机组 在时段 的出力下限 T=t+1 'tiep tie ' t = TieP tie ' t V(ie, e Φ ΤΡΙαη ( 11 ) where corpse / ^ is the total load of the system power generation caliber; ρ is the output of the unit during the period, ρTM 11 For tl, t I unit / minimum technical output; N is the number of lines of contact between the system and the external grid; tiep f is the tie line ^ during the time period ί transmission / receiving plan; for the rotating standby calculation cycle, and p ^ ax unit The lower limit of the output during the period
ι,ΐ ι,ΐ  Ip,ΐ ι,ΐ
和出力上限; 和 为机组 在时段 能提供的上旋和下旋备用, 、 R 为系统在时 段 上旋和下旋的备用需求; τυ.为机组 最小持续运行时间, 在计算前需要根据初始 And the upper limit of the output; and the upper and lower rotations that can be provided for the unit during the period, R is the standby demand for the system to rotate up and down during the time period; τυ. is the minimum continuous running time of the unit, which needs to be based on the initial
I  I
运行时间进行扣减; 式中 7I/min和 Z)min分别为机组 的最小开机和停机时间, W.nThe operating time is deducted; where 7I/ min and Z) min are the minimum start-up and downtime of the unit, respectively. W. n is
I I ι,ΰ 机组 的初始状态; ΤΤ/^ΒΓ^分别为机组 在初始时刻已经开机和停机的时间; 717.和  I I ι,ΰ The initial state of the unit; ΤΤ/^ΒΓ^ is the time that the unit has been turned on and off at the initial time; 717.
ΓΖ 分别为机组 /在调度初期为满足最小运行时间或停运时间而必须继续运行和停运的ΓΖ respectively for the unit / in the initial stage of scheduling, to meet the minimum running time or outage time must continue to run and stop
I I
时间; TiePt. 为联络线^在时段 的交易计划; 4 P, 为计划联络线一时间集合; tie.t IP lan Time; TieP t . for the contact line ^ trading plan in the time period; 4 P , a set of time for the planned contact line; tie.t IP lan
(2)求解日前发电计划优化模型, 根据计算结果确定是否需要弃风, 如需要弃风, 进行风电优化辅助分析, 设置风电优化辅助分析参数, 所述风电优化辅助分析参数包括 可启停的机组、 最大启停机组数量、 可调峰机组、 最大调峰机组数量、 可调整计划的固 定出力机组和联络线、 系统备用的可调整比例;  (2) Solving the day-to-day power generation plan optimization model, determining whether wind is needed according to the calculation result, if wind is needed, performing wind power optimization auxiliary analysis, setting wind power optimization auxiliary analysis parameters, the wind power optimization auxiliary analysis parameters including start-stop unit , the maximum number of start-stop groups, the adjustable peak unit, the maximum number of peak-sharing units, the fixed-planning unit and the tie line of the adjustable plan, and the adjustable ratio of the system standby;
(3) 根据风电接纳优化辅助分析参数构造多个辅助分析案例, 分析提高风电消纳 的途径;  (3) Constructing multiple auxiliary analysis cases based on wind power acceptance optimization auxiliary analysis parameters, and analyzing ways to improve wind power consumption;
(4) 采用风电优化辅助分析优化模型对所有辅助分析案例进行优化求解, 统计分 析在各机组启停调峰、 机组深度调峰、 机组固定计划调整、 联络线计划调整、 备用不同 比例调整的情况下, 风电消纳变化情况;  (4) Using the wind power optimization auxiliary analysis optimization model to optimize the solution for all auxiliary analysis cases, statistical analysis of the start and stop peaking of each unit, unit deep peak shaving, unit fixed plan adjustment, tie line plan adjustment, standby different proportion adjustment Next, the wind power consumption changes;
(5) 根据统计分析结果判断是否存在提高风电消纳的可行方法, 若存在, 则分析 确定日前发电计划优化编制采用的提高风电消纳的方法,修改日前发电计划优化编制条 WO 2014/110878 +T +»、 PCT/CN2013/075498 (5) According to the results of statistical analysis, it is judged whether there is a feasible method to improve wind power consumption. If it exists, it analyzes and determines the method of improving wind power consumption adopted by the optimization plan of the previous power generation plan, and modifies the optimization plan of the previous power generation plan. WO 2014/110878 +T +», PCT/CN2013/075498
权 利 要 求 书  Claims
件, 优化编制新的日前发电计划。 , optimize the preparation of a new day-to-day power generation plan.
2、 根据权利要求 1所述的风火协调调度模式下日前调度计划优化辅助分析方法, 其特征在于: 所述步骤 (3) 中风电接纳优化分析参数包括如下约束中的部分或全部:  2. The method for optimizing the auxiliary scheduling of the dispatching plan in the wind-fire coordination mode according to claim 1, wherein: the wind power receiving optimization analysis parameter in the step (3) comprises part or all of the following constraints:
(a) 对于机组启停调峰, 在构造辅助分析案例时包括如下约束条件:  (a) For the start and stop peaking of the unit, the following constraints are included in the construction of the auxiliary analysis case:
yf^zf^ {0,1}  Yf^zf^ {0,1}
'。f '. f
Figure imgf000016_0001
Figure imgf000016_0001
其中, Φ ^是愿意参加启停调峰的机组集合, 为机组 是否启机和停机的变 aof 量, my和 mz为最大允许启机和停机数量;  Among them, Φ ^ is the set of units that are willing to participate in the start and stop peaking, and the amount of aof that is the start or stop of the unit, my and mz are the maximum allowable number of start and stop;
(b) 对于机组深调峰, 在构造辅助分析案例时包括如下约束条件: p <p^*u -viopu viopi t < viopfi · viopli t < mviop(b) For the deep peak adjustment of the unit, the following constraints are included in the construction of the auxiliary analysis case: p <p^*u -viop u viopi t < viopfi · viopli t < mviop
Figure imgf000016_0002
Figure imgf000016_0002
其中, Φ . 可承担深度调峰任务的机组, 为机组 在时段 的深度调峰幅度, νιοα i,t  Among them, Φ. The unit that can undertake the task of deep peak shaving, which is the depth peak amplitude of the unit during the period, νιοα i,t
机组 是否深度调峰的标志变量, νΰψ^为机组 在时段 最大调峰幅度限值参 数, rnWop为最大深度调峰机组数量; Whether the unit has a deep peak peaking variable, νΰψ^ is the maximum peak amplitude limit parameter of the unit during the period, and rnWop is the maximum depth peaking unit number;
(c) 对于机组固定计划调整, 在构造辅助分析案例时包括如下约束条件: (c) For the fixed plan adjustment of the unit, the following constraints are included in the construction of the auxiliary analysis case:
Pi,t = Pt + Pl - PU V(") e n Pi,t = Pt + Pl - PU V (") en
(d)对于优化外部联络线送受电计划, 在构造辅助分析案例时包括如下约束条件: WO 2014/110878 +T +»、 PCT/CN2013/075498 (d) For optimizing the external tie-line transmission and reception plan, the following constraints are included in the construction of the auxiliary analysis case: WO 2014/110878 +T +», PCT/CN2013/075498
权 利 要 求 书  Claims
tieptie,t = TiePi t + Mep e t - Aptie t (tie, t) e α& Tie tie , t = TieP it + Mep et - Ap tie t (tie, t) e α&
(e) 对于优化系统备用需求, 考虑备用可调整, 在构造辅助分析案例时将系统下 旋备用约束表示为: (e) For optimizing system backup requirements, consider alternately adjustable, and when constructing the auxiliary analysis case, represent the system spin-off standby constraint as:
f» _
Figure imgf000017_0001
f» _
Figure imgf000017_0001
其中, 3为时段 降低的下旋备用变量, 为时段 最大可下调的下旋备用量。 Among them, 3 is the down-spinning standby variable with the period reduced, which is the lower-rotation reserve with the largest down period.
3、 根据权利要求 1所述的风火协调调度模式下日前调度计划优化辅助分析方法, 其特征在于: 所述风电优化辅助分析决策以增加额外成本为代价, 综合考虑电网提高风 电消纳而采用的各种方法, 支付额外成本后, 在增加风电优化辅助分析决策时总的优化 目标表示为: 3. The method for optimizing the auxiliary scheduling of the day-to-day scheduling plan according to the wind-fire coordination mode according to claim 1, wherein: the wind power optimization auxiliary analysis decision is at the cost of increasing additional cost, and comprehensively considering the power grid to improve wind power consumption. After various methods, after paying additional costs, the overall optimization goal when increasing wind power optimization analysis analysis decisions is expressed as:
T I T T I T
N N N + NNN +
mnF. =F+ ∑ ∑ viq? -ψκ +∑ ∑ ( + . )·αρ.  mnF. =F+ ∑ ∑ viq? -ψκ +∑ ∑ ( + . )·αρ.
ί Φ . t=l " i=\t=\ ', ', "
Figure imgf000017_0002
ί Φ . t=l " i=\t=\ ', ', "
Figure imgf000017_0002
e^atiet-l t-l  E^atiet-l t-l
其中 , 为日前调度计划优化辅助分析的广义优化目标, F为常规安全约束机组 组合的优化目标, /^为机组 在时段 深调峰单位成本, αρ^为机组 在时段 偏离固 定出力的额外单位成本, ^'^^为调整联络线^在时段 计划的单位成本, 为降低 单位系统备用的风险成本。  Among them, for the general optimization objective of the auxiliary analysis for the previous scheduling plan, F is the optimization target of the conventional safety-constrained unit combination, /^ is the unit cost of the unit during the deep adjustment of the unit, and αρ^ is the additional unit cost of the unit deviating from the fixed output during the period. , ^'^^ is to adjust the unit cost of the contact line ^ in the time period, in order to reduce the risk cost of the unit system standby.
PCT/CN2013/075498 2013-01-16 2013-05-10 Auxiliary analysis method for optimization of current scheduling plan in wind-fire coordinated scheduling mode WO2014110878A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201310015356.8A CN103077430B (en) 2013-01-16 2013-01-16 Under wind-fire coordinated dispatching mode, operation plan optimizes aided analysis method a few days ago
CN201310015356.8 2013-01-16

Publications (1)

Publication Number Publication Date
WO2014110878A1 true WO2014110878A1 (en) 2014-07-24

Family

ID=48153952

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2013/075498 WO2014110878A1 (en) 2013-01-16 2013-05-10 Auxiliary analysis method for optimization of current scheduling plan in wind-fire coordinated scheduling mode

Country Status (2)

Country Link
CN (1) CN103077430B (en)
WO (1) WO2014110878A1 (en)

Cited By (44)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104573844A (en) * 2014-10-27 2015-04-29 国家电网公司 Quarterly power transmission and transformation integrated maintenance optimization method based on genetic algorithm
CN107565576A (en) * 2017-09-21 2018-01-09 国网福建省电力有限公司 A kind of active distribution network reactive Voltage Optimum method that more active management means are mutually coordinated
CN108108995A (en) * 2017-11-15 2018-06-01 中国电力科学研究院有限公司 A kind of fired power generating unit price quoting method and device based on new energy power prediction
CN110222433A (en) * 2019-06-12 2019-09-10 东北大学 A kind of probabilistic home intelligent power optimization method of consideration user power utilization behavior
CN110288128A (en) * 2019-05-31 2019-09-27 沈阳工程学院 A kind of heat accumulation thermoelectricity unit Power control model based on the economic adjustment factor
CN110311425A (en) * 2019-06-18 2019-10-08 国网山西省电力公司 Consider that the wind fire of peak regulation ancillary service quotation is deep and adjusts electric power optimal control method
CN110365057A (en) * 2019-08-14 2019-10-22 南方电网科学研究院有限责任公司 Distributed energy participation power distribution network peak regulation scheduling optimization method based on reinforcement learning
CN110555590A (en) * 2019-07-31 2019-12-10 云南电网有限责任公司 secondary clearing method for watershed cascade upstream and downstream power stations participating in electric power spot market
CN110555757A (en) * 2019-09-09 2019-12-10 国家电网公司西北分部 Electric quantity bank spot transaction method suitable for high-proportion new energy participation
CN111291942A (en) * 2020-03-05 2020-06-16 燕山大学 Two-stage scheduling method and system of comprehensive energy system considering demand response
CN111414697A (en) * 2020-03-24 2020-07-14 上海电力大学 N-x robust optimization scheduling method considering interruptible load uncertainty
CN111652447A (en) * 2020-07-02 2020-09-11 东北大学 Comprehensive energy system economic dispatching method based on distributed neural dynamic optimization
CN111724254A (en) * 2020-05-27 2020-09-29 中国南方电网有限责任公司 Method, system, device and medium for peak regulation auxiliary service and electric energy combined clearing
CN111817295A (en) * 2020-07-07 2020-10-23 上海惠安系统控制有限公司 Control method for unit participating in deep peak shaving in plant-level AGC mode
CN111860965A (en) * 2020-06-24 2020-10-30 东南大学 User comprehensive energy system optimal scheduling method considering energy storage multi-type services
CN111898795A (en) * 2020-06-09 2020-11-06 东南大学 Optimized scheduling method for electrical hydrogen production/methane system considering hydrogen storage tanks in multiple operation modes
CN111917140A (en) * 2020-07-17 2020-11-10 兰州理工大学 Two-layer optimized scheduling model of new energy complementary power generation system
CN112184016A (en) * 2020-09-28 2021-01-05 中国电建集团贵阳勘测设计研究院有限公司 Method for conveniently judging water-light complementary integrated photovoltaic scale under complex power grid
CN112564165A (en) * 2020-11-26 2021-03-26 云南电网有限责任公司 Method for monitoring wind power consumption capability of combined heat and power system with additional heat source
CN112699519A (en) * 2020-08-20 2021-04-23 国家电网公司西北分部 Cross-provincial peak regulation auxiliary service market clearing method considering power grid safety constraint
CN112736984A (en) * 2020-12-09 2021-04-30 国网辽宁省电力有限公司锦州供电公司 Method for improving wind curtailment absorption capacity of electric-thermal comprehensive energy system
CN112803500A (en) * 2021-03-23 2021-05-14 国网山西省电力公司 Method and system for constructing electric energy and deep peak regulation combined clearing model
CN113112063A (en) * 2021-04-07 2021-07-13 国网新疆电力有限公司经济技术研究院 Multi-scene robust scheduling method and device containing wind power system
CN113255984A (en) * 2021-05-19 2021-08-13 沈阳工业大学 Cluster optimization scheduling method for sea water desalination load absorption of abandoned wind power
CN113298396A (en) * 2021-05-31 2021-08-24 东南大学 Comprehensive energy system optimization method, system and device based on gas-heat inertia
CN113642829A (en) * 2021-06-23 2021-11-12 东南大学 Comprehensive energy system optimization scheduling method considering combined heat and power generation multi-heating mode
CN113708394A (en) * 2021-08-04 2021-11-26 大连理工大学 Joint scheduling method for hundred megawatt energy storage participating peak shaving and frequency response auxiliary service
CN113763206A (en) * 2021-09-10 2021-12-07 国网上海市电力公司 Power grid low-carbon scheduling method based on unit carbon emission characteristics
CN113765098A (en) * 2021-08-19 2021-12-07 国网陕西省电力公司电力科学研究院 Load-source interactive peak regulation control method based on demand side load response
CN114039378A (en) * 2021-09-18 2022-02-11 国网重庆市电力公司市南供电分公司 Wind-fire-storage combined scheduling method and system capable of interrupting load and storage medium
CN114050609A (en) * 2021-11-05 2022-02-15 国网江苏省电力有限公司盐城供电分公司 Adaptive robust day-ahead optimal scheduling method for high-proportion new energy power system
CN114091263A (en) * 2021-11-23 2022-02-25 中国电力科学研究院有限公司 Simulation analysis method, system and storage medium for power transmission and reception capacity of dual-tie-line power grid
CN114172210A (en) * 2021-11-30 2022-03-11 国网山东省电力公司青岛供电公司 Power grid planning method and system considering power supply uncertainty
CN114221389A (en) * 2021-11-30 2022-03-22 国网江苏省电力有限公司经济技术研究院 New energy maximum consumption capacity analysis method
CN114336663A (en) * 2022-01-07 2022-04-12 华北电力科学研究院有限责任公司 Novel power system source network collaborative planning method and device
CN114493104A (en) * 2021-12-22 2022-05-13 中国南方电网有限责任公司 Day-ahead power generation plan optimization method and system
CN114648195A (en) * 2020-12-21 2022-06-21 国网辽宁省电力有限公司大连供电公司 Intelligent cooperative regulation and control method for energy storage power station in power grid multi-level auxiliary service
CN114862622A (en) * 2022-05-09 2022-08-05 国网湖北省电力有限公司咸宁供电公司 Sensitivity and cost considered method for improving new energy consumption capability of regional power grid
CN114912264A (en) * 2022-05-06 2022-08-16 国网湖北省电力有限公司孝感供电公司 Daily optimal scheduling method for electric power system avoiding vibration region of hydroelectric generating set
CN115907232A (en) * 2023-01-05 2023-04-04 中国电力科学研究院有限公司 Regional comprehensive energy system cluster collaborative optimization method, system, equipment and medium
CN116526584A (en) * 2023-07-04 2023-08-01 广东电网有限责任公司广州供电局 Green power traceability-based virtual power plant quick response regulation and control method
CN116613750A (en) * 2023-07-18 2023-08-18 山东大学 Integrated scheduling method, system, terminal equipment and medium for power system
CN117196686A (en) * 2023-11-08 2023-12-08 国网湖北省电力有限公司经济技术研究院 Deep peak-shaving market sequential clearing method based on electric energy and frequency modulation combined market
CN118246718A (en) * 2024-05-30 2024-06-25 中国电建集团西北勘测设计研究院有限公司 Sha Gehuang new energy base outgoing curve optimization method and device

Families Citing this family (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103077430B (en) * 2013-01-16 2016-08-10 国电南瑞科技股份有限公司 Under wind-fire coordinated dispatching mode, operation plan optimizes aided analysis method a few days ago
CN103400304B (en) * 2013-07-10 2016-06-01 国电南瑞科技股份有限公司 Wind-powered electricity generation and conventional energy resources coordinated scheduling wind-powered electricity generation consistency rotate analytical procedure for subsequent use
CN103679284A (en) * 2013-11-18 2014-03-26 上海交通大学 Accommodated wind power accessed fixed interval rolling scheduling method
CN103986153B (en) * 2014-04-23 2016-06-29 清华大学 Within the scope of interconnection of bulk power grids, coordinate to carry out the optimization method of balance of electric power and ener
CN104299055B (en) * 2014-10-15 2017-08-29 国电南瑞科技股份有限公司 It is a kind of to suppress the generation schedule optimization method that unit is reversely adjusted in power plant
CN104616069B (en) * 2015-01-13 2017-11-10 国电南瑞科技股份有限公司 A kind of annual generation schedule rolls decomposition optimization
CN104659781B (en) * 2015-03-13 2017-01-04 广西大学 A kind of dispatching method tackling wind power change at random with least regulating amount
CN105207259B (en) * 2015-09-18 2018-03-06 北京北变微电网技术有限公司 Micro-grid system dispatching method under based on energy management and net state
CN105429172B (en) * 2015-11-18 2017-09-15 山东大学 The power generation dispatching method of strengthening system operational flexibility
CN105490309B (en) * 2015-12-21 2018-02-06 国网山西省电力公司大同供电公司 A kind of wind electricity digestion appraisal procedure based on peak load regulation network ability
CN105958499A (en) * 2016-05-03 2016-09-21 东南大学 Day-ahead scheduling method considering interruptible loads
CN106251074B (en) * 2016-08-01 2019-07-02 国网山东省电力公司经济技术研究院 A kind of method for building up and its calculation method of the advanced scheduling model of the power grid of collaboration
CN106845807B (en) * 2017-01-09 2020-08-11 北京清能互联科技有限公司 Settlement method and device based on peak regulation auxiliary service
CN107153885B (en) * 2017-03-31 2020-08-14 国电南瑞科技股份有限公司 Real-time power generation plan optimization method considering deep peak shaving of thermal power generating unit
CN110138019B (en) * 2019-06-04 2021-06-08 国网山东省电力公司电力科学研究院 Method for optimizing start and stop of unit
CN110957717A (en) * 2019-06-06 2020-04-03 国网辽宁省电力有限公司 Multi-target day-ahead optimal scheduling method for multi-power-supply power system
CN111130146B (en) * 2020-01-16 2021-07-20 南方电网科学研究院有限责任公司 Hydropower consumption method and device based on thermal power deep peak regulation
CN111835005B (en) * 2020-07-20 2021-09-10 中国电力工程顾问集团西北电力设计院有限公司 Method and device for determining power grid transmission capacity of new energy base and related equipment
CN112039127B (en) * 2020-08-24 2023-11-17 国网山东省电力公司潍坊供电公司 Day-ahead scheduling method and system considering wind power prediction error related characteristics
CN113690929A (en) * 2021-07-26 2021-11-23 南瑞集团有限公司 Rotary reserve capacity middle-term planning method and device for coordinating, preventing and controlling new energy abandonment and power failure risk
CN115036914B (en) * 2022-06-17 2024-04-30 国家电网公司华中分部 Power grid energy storage double-layer optimization method and system considering flexibility and new energy consumption

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102075014A (en) * 2011-01-06 2011-05-25 清华大学 Large grid real-time scheduling method for accepting access of wind power
CN103077430A (en) * 2013-01-16 2013-05-01 国电南瑞科技股份有限公司 Auxiliary analyzing method for day-ahead scheduling-plan optimization in mode of wind-fire coordinated scheduling

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101132948B1 (en) * 2010-05-13 2012-04-05 엘에스산전 주식회사 System, Apparatus and Method for Charge and Discharge Control of Electric Vehicle
CN102280878B (en) * 2011-07-26 2013-10-09 国电南瑞科技股份有限公司 Wind power penetration optimization evaluation method based on SCED

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102075014A (en) * 2011-01-06 2011-05-25 清华大学 Large grid real-time scheduling method for accepting access of wind power
CN103077430A (en) * 2013-01-16 2013-05-01 国电南瑞科技股份有限公司 Auxiliary analyzing method for day-ahead scheduling-plan optimization in mode of wind-fire coordinated scheduling

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
LEI, YU ET AL.: "A two-stage stochastic optimization of unit commitment considering wind power based on scenario analysis", POWER SYSTEM PROTECTION AND CONTROL, vol. 40, no. 23, pages 58 - 67 *
LI, FENG ET AL.: "Peak load regulation and economically-abandoned wind for power system with energy storage system and wind power access", CHINA ELECTRIC POWER, vol. 40, no. 10, October 2012 (2012-10-01), pages 1695 - 1700 *

Cited By (74)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104573844A (en) * 2014-10-27 2015-04-29 国家电网公司 Quarterly power transmission and transformation integrated maintenance optimization method based on genetic algorithm
CN107565576A (en) * 2017-09-21 2018-01-09 国网福建省电力有限公司 A kind of active distribution network reactive Voltage Optimum method that more active management means are mutually coordinated
CN107565576B (en) * 2017-09-21 2023-09-15 国网福建省电力有限公司 Reactive voltage optimization method for active power distribution network coordinated by multiple active management means
CN108108995A (en) * 2017-11-15 2018-06-01 中国电力科学研究院有限公司 A kind of fired power generating unit price quoting method and device based on new energy power prediction
CN110288128A (en) * 2019-05-31 2019-09-27 沈阳工程学院 A kind of heat accumulation thermoelectricity unit Power control model based on the economic adjustment factor
CN110222433B (en) * 2019-06-12 2022-12-13 东北大学 Household intelligent power utilization optimization method considering uncertainty of user power utilization behavior
CN110222433A (en) * 2019-06-12 2019-09-10 东北大学 A kind of probabilistic home intelligent power optimization method of consideration user power utilization behavior
CN110311425A (en) * 2019-06-18 2019-10-08 国网山西省电力公司 Consider that the wind fire of peak regulation ancillary service quotation is deep and adjusts electric power optimal control method
CN110311425B (en) * 2019-06-18 2022-12-20 国网山西省电力公司 Wind-fire deep-regulation power optimization control method considering peak regulation auxiliary service quotation
CN110555590A (en) * 2019-07-31 2019-12-10 云南电网有限责任公司 secondary clearing method for watershed cascade upstream and downstream power stations participating in electric power spot market
CN110555590B (en) * 2019-07-31 2023-04-07 云南电网有限责任公司 Secondary clearing method for watershed cascade upstream and downstream power stations participating in electric power spot market
CN110365057A (en) * 2019-08-14 2019-10-22 南方电网科学研究院有限责任公司 Distributed energy participation power distribution network peak regulation scheduling optimization method based on reinforcement learning
CN110365057B (en) * 2019-08-14 2022-12-06 南方电网科学研究院有限责任公司 Distributed energy participation power distribution network peak regulation scheduling optimization method based on reinforcement learning
CN110555757A (en) * 2019-09-09 2019-12-10 国家电网公司西北分部 Electric quantity bank spot transaction method suitable for high-proportion new energy participation
CN110555757B (en) * 2019-09-09 2022-04-08 国家电网公司西北分部 Electric quantity bank spot transaction method suitable for high-proportion new energy participation
CN111291942A (en) * 2020-03-05 2020-06-16 燕山大学 Two-stage scheduling method and system of comprehensive energy system considering demand response
CN111291942B (en) * 2020-03-05 2023-09-26 燕山大学 Two-stage scheduling method and system for comprehensive energy system considering demand response
CN111414697A (en) * 2020-03-24 2020-07-14 上海电力大学 N-x robust optimization scheduling method considering interruptible load uncertainty
CN111414697B (en) * 2020-03-24 2023-07-18 上海电力大学 N-x robust optimal scheduling method considering interruptible load uncertainty
CN111724254B (en) * 2020-05-27 2024-02-06 中国南方电网有限责任公司 Peak regulation auxiliary service and electric energy combined clearing method, system, device and medium
CN111724254A (en) * 2020-05-27 2020-09-29 中国南方电网有限责任公司 Method, system, device and medium for peak regulation auxiliary service and electric energy combined clearing
CN111898795B (en) * 2020-06-09 2024-06-04 东南大学 Electric hydrogen production/methane system optimal scheduling method considering hydrogen storage tanks with multiple operation modes
CN111898795A (en) * 2020-06-09 2020-11-06 东南大学 Optimized scheduling method for electrical hydrogen production/methane system considering hydrogen storage tanks in multiple operation modes
CN111860965B (en) * 2020-06-24 2023-11-14 东南大学 User comprehensive energy system optimization scheduling method considering energy storage multi-type service
CN111860965A (en) * 2020-06-24 2020-10-30 东南大学 User comprehensive energy system optimal scheduling method considering energy storage multi-type services
CN111652447B (en) * 2020-07-02 2023-08-04 东北大学 Comprehensive energy system economic dispatching method based on distributed neural dynamic optimization
CN111652447A (en) * 2020-07-02 2020-09-11 东北大学 Comprehensive energy system economic dispatching method based on distributed neural dynamic optimization
CN111817295B (en) * 2020-07-07 2024-03-19 上海惠安系统控制有限公司 Control method for deep peak regulation of unit participation under factory-level AGC mode
CN111817295A (en) * 2020-07-07 2020-10-23 上海惠安系统控制有限公司 Control method for unit participating in deep peak shaving in plant-level AGC mode
CN111917140B (en) * 2020-07-17 2023-01-10 兰州理工大学 Two-layer optimization scheduling model of new energy complementary power generation system
CN111917140A (en) * 2020-07-17 2020-11-10 兰州理工大学 Two-layer optimized scheduling model of new energy complementary power generation system
CN112699519A (en) * 2020-08-20 2021-04-23 国家电网公司西北分部 Cross-provincial peak regulation auxiliary service market clearing method considering power grid safety constraint
CN112184016A (en) * 2020-09-28 2021-01-05 中国电建集团贵阳勘测设计研究院有限公司 Method for conveniently judging water-light complementary integrated photovoltaic scale under complex power grid
CN112184016B (en) * 2020-09-28 2023-11-17 中国电建集团贵阳勘测设计研究院有限公司 Method for judging water-light complementary integrated photovoltaic scale under complex power grid
CN112564165A (en) * 2020-11-26 2021-03-26 云南电网有限责任公司 Method for monitoring wind power consumption capability of combined heat and power system with additional heat source
CN112736984B (en) * 2020-12-09 2023-09-01 国网辽宁省电力有限公司锦州供电公司 Method for improving wind-abandoning and absorbing capacity of electric-thermal comprehensive energy system
CN112736984A (en) * 2020-12-09 2021-04-30 国网辽宁省电力有限公司锦州供电公司 Method for improving wind curtailment absorption capacity of electric-thermal comprehensive energy system
CN114648195A (en) * 2020-12-21 2022-06-21 国网辽宁省电力有限公司大连供电公司 Intelligent cooperative regulation and control method for energy storage power station in power grid multi-level auxiliary service
CN112803500B (en) * 2021-03-23 2023-04-14 国网山西省电力公司 Method and system for constructing electric energy and deep peak shaving combined clearing model
CN112803500A (en) * 2021-03-23 2021-05-14 国网山西省电力公司 Method and system for constructing electric energy and deep peak regulation combined clearing model
CN113112063A (en) * 2021-04-07 2021-07-13 国网新疆电力有限公司经济技术研究院 Multi-scene robust scheduling method and device containing wind power system
CN113255984B (en) * 2021-05-19 2024-04-12 国网天津市电力公司滨海供电分公司 Cluster optimization scheduling method for sea water desalination load to consume abandoned wind power
CN113255984A (en) * 2021-05-19 2021-08-13 沈阳工业大学 Cluster optimization scheduling method for sea water desalination load absorption of abandoned wind power
CN113298396A (en) * 2021-05-31 2021-08-24 东南大学 Comprehensive energy system optimization method, system and device based on gas-heat inertia
CN113642829A (en) * 2021-06-23 2021-11-12 东南大学 Comprehensive energy system optimization scheduling method considering combined heat and power generation multi-heating mode
CN113642829B (en) * 2021-06-23 2024-05-24 东南大学 Comprehensive energy system optimal scheduling method considering cogeneration multi-heat supply mode
CN113708394A (en) * 2021-08-04 2021-11-26 大连理工大学 Joint scheduling method for hundred megawatt energy storage participating peak shaving and frequency response auxiliary service
CN113765098A (en) * 2021-08-19 2021-12-07 国网陕西省电力公司电力科学研究院 Load-source interactive peak regulation control method based on demand side load response
CN113765098B (en) * 2021-08-19 2024-03-05 国网陕西省电力公司电力科学研究院 Load source interaction peak shaving control method based on demand side load response
CN113763206A (en) * 2021-09-10 2021-12-07 国网上海市电力公司 Power grid low-carbon scheduling method based on unit carbon emission characteristics
CN114039378A (en) * 2021-09-18 2022-02-11 国网重庆市电力公司市南供电分公司 Wind-fire-storage combined scheduling method and system capable of interrupting load and storage medium
CN114050609B (en) * 2021-11-05 2023-11-24 国网江苏省电力有限公司盐城供电分公司 Adaptive robust day-ahead optimization scheduling method for high-proportion new energy power system
CN114050609A (en) * 2021-11-05 2022-02-15 国网江苏省电力有限公司盐城供电分公司 Adaptive robust day-ahead optimal scheduling method for high-proportion new energy power system
CN114091263B (en) * 2021-11-23 2024-03-01 中国电力科学研究院有限公司 Dual-tie-line power grid power transmission and reception capacity simulation analysis method, system and storage medium
CN114091263A (en) * 2021-11-23 2022-02-25 中国电力科学研究院有限公司 Simulation analysis method, system and storage medium for power transmission and reception capacity of dual-tie-line power grid
CN114221389A (en) * 2021-11-30 2022-03-22 国网江苏省电力有限公司经济技术研究院 New energy maximum consumption capacity analysis method
CN114172210B (en) * 2021-11-30 2023-12-05 国网山东省电力公司青岛供电公司 Power grid planning method and system considering power supply uncertainty
CN114172210A (en) * 2021-11-30 2022-03-11 国网山东省电力公司青岛供电公司 Power grid planning method and system considering power supply uncertainty
CN114221389B (en) * 2021-11-30 2024-02-27 国网江苏省电力有限公司经济技术研究院 New energy maximum capacity analysis method
CN114493104A (en) * 2021-12-22 2022-05-13 中国南方电网有限责任公司 Day-ahead power generation plan optimization method and system
CN114336663B (en) * 2022-01-07 2024-02-27 华北电力科学研究院有限责任公司 Collaborative planning method and device for power system source network
CN114336663A (en) * 2022-01-07 2022-04-12 华北电力科学研究院有限责任公司 Novel power system source network collaborative planning method and device
CN114912264B (en) * 2022-05-06 2024-07-26 国网湖北省电力有限公司孝感供电公司 Day-optimized scheduling method for electric power system avoiding vibration area of hydroelectric generating set
CN114912264A (en) * 2022-05-06 2022-08-16 国网湖北省电力有限公司孝感供电公司 Daily optimal scheduling method for electric power system avoiding vibration region of hydroelectric generating set
CN114862622A (en) * 2022-05-09 2022-08-05 国网湖北省电力有限公司咸宁供电公司 Sensitivity and cost considered method for improving new energy consumption capability of regional power grid
CN115907232B (en) * 2023-01-05 2023-06-09 中国电力科学研究院有限公司 Regional comprehensive energy system cluster collaborative optimization method, system, equipment and medium
CN115907232A (en) * 2023-01-05 2023-04-04 中国电力科学研究院有限公司 Regional comprehensive energy system cluster collaborative optimization method, system, equipment and medium
CN116526584A (en) * 2023-07-04 2023-08-01 广东电网有限责任公司广州供电局 Green power traceability-based virtual power plant quick response regulation and control method
CN116526584B (en) * 2023-07-04 2023-09-15 广东电网有限责任公司广州供电局 Green power traceability-based virtual power plant quick response regulation and control method
CN116613750A (en) * 2023-07-18 2023-08-18 山东大学 Integrated scheduling method, system, terminal equipment and medium for power system
CN116613750B (en) * 2023-07-18 2023-10-13 山东大学 Integrated scheduling method, system, terminal equipment and medium for power system
CN117196686A (en) * 2023-11-08 2023-12-08 国网湖北省电力有限公司经济技术研究院 Deep peak-shaving market sequential clearing method based on electric energy and frequency modulation combined market
CN117196686B (en) * 2023-11-08 2024-01-30 国网湖北省电力有限公司经济技术研究院 Deep peak-shaving market sequential clearing method based on electric energy and frequency modulation combined market
CN118246718A (en) * 2024-05-30 2024-06-25 中国电建集团西北勘测设计研究院有限公司 Sha Gehuang new energy base outgoing curve optimization method and device

Also Published As

Publication number Publication date
CN103077430B (en) 2016-08-10
CN103077430A (en) 2013-05-01

Similar Documents

Publication Publication Date Title
WO2014110878A1 (en) Auxiliary analysis method for optimization of current scheduling plan in wind-fire coordinated scheduling mode
Li et al. On enabling sustainable edge computing with renewable energy resources
Lin et al. Optimal charging control of energy storage and electric vehicle of an individual in the internet of energy with energy trading
CN103151803B (en) Method for optimizing wind power system-contained unit and backup configuration
CN104881716A (en) Optimization programming and evaluation method of micro-grid power supply
CN109256799A (en) A kind of New-energy power system Optimization Scheduling based on Sample Entropy
CN111799772B (en) Electric heating system optimal scheduling method considering depth peak shaving of unit
CN103414206A (en) Water, fire and light combined optimization power generation scheduling optimization method considering security constraints
CN103956773B (en) Backup configuration optimization method containing wind power system unit
CN111160880A (en) Block chain-based industrial user demand response-oriented transaction settlement control method
Tang et al. Optimal operation method for microgrid with wind/PV/diesel generator/battery and desalination
CN100499310C (en) Automatic power generation control advance control method for power system
CN111967986A (en) Electric power market clearing method, system, device and medium containing cascade hydropower
CN103927590A (en) Power system optimizing controlling and charge calculating method under situation of information asymmetry
Li et al. Optimal planning of dual-zero microgrid on an island towards net-zero carbon emission
CN114243691A (en) Low-carbon optimized scheduling method for power system
Hu et al. Capacity configuration optimization for island microgrid with wind/solar/pumped storage considering demand response
CN112234604A (en) Multi-energy complementary power supply base optimal configuration method, storage medium and equipment
CN116111597A (en) Method, system, memory and equipment for constructing tidal current section scene set of medium-long term scheduling plan
Zhao et al. Practice exploration and prospect analysis of virtual power plant in Shanghai
CN102904248A (en) Electric power system dispatching method based on wind electricity output uncertainty aggregation
CN107622331B (en) Optimization method and device for direct transaction mode of generator set and power consumer
CN111242450B (en) Method, system, device and medium for clearing hydroelectric generating set in real-time market
CN112491080A (en) New energy installation layout planning method and system
Norouzi et al. Overview of Modern Multi‐Dimension Energy Networks

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 13871964

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 13871964

Country of ref document: EP

Kind code of ref document: A1