WO2014024665A1 PCT/JP2013/069766 JP2013069766W WO2014024665A1 WO 2014024665 A1 WO2014024665 A1 WO 2014024665A1 JP 2013069766 W JP2013069766 W JP 2013069766W WO 2014024665 A1 WO2014024665 A1 WO 2014024665A1
Authority
WO
WIPO (PCT)
Prior art keywords
meter reading
disconnection
distribution
distribution system
accident
Prior art date
Application number
PCT/JP2013/069766
Other languages
English (en)
French (fr)
Inventor
和利 土屋
山根 憲一郎
足立 昌宏
貢 台野
Original Assignee
株式会社日立製作所
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社日立製作所 filed Critical 株式会社日立製作所
Priority to US14/419,482 priority Critical patent/US20150212138A1/en
Publication of WO2014024665A1 publication Critical patent/WO2014024665A1/ja

Links

Images

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/50Testing of electric apparatus, lines, cables or components for short-circuits, continuity, leakage current or incorrect line connections
    • G01R31/54Testing for continuity
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/08Locating faults in cables, transmission lines, or networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R21/00Arrangements for measuring electric power or power factor
    • G01R21/133Arrangements for measuring electric power or power factor by using digital technique
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/08Locating faults in cables, transmission lines, or networks
    • G01R31/081Locating faults in cables, transmission lines, or networks according to type of conductors
    • G01R31/085Locating faults in cables, transmission lines, or networks according to type of conductors in power transmission or distribution lines, e.g. overhead

Definitions

  • the present invention relates to a method of detecting a disconnection accident of a distribution line in a distribution system and identifying the disconnection point, and a distribution facility management system.
  • the present invention has been made to solve the above-mentioned problems, and a disconnection of a distribution line using a communication function-equipped meter device (AMI: Advanced Meter Infrastructure) installed in a power consumer connected to a distribution system.
  • AMI Advanced Meter Infrastructure
  • the purpose is to detect an accident and to identify the break point.
  • a disconnection accident detection method and a distribution facility management system of the present invention adopt, for example, the configuration described in the claims.
  • a sensor with a communication function is installed in a customer connected to a distribution system, and meter reading information detected by the sensor with a communication function is obtained through the communication system.
  • the present invention is characterized in that a disconnection of a distribution line is detected on the basis of a loss state of meter reading information.
  • disconnection detection of the distribution system divides the distribution system into appropriate sections, and compares the number of sensors with communication function that report the loss of meter reading information in the section with the number of sensors with communication function installed in the section. to decide.
  • the simultaneous loss number due to the communication failure is kept from the past history, and the disconnection detection of the distribution system is performed when the number of sensors with communication function reporting the loss is larger than the simultaneous loss number due to the communication failure.
  • disconnection detection of a distribution system changes the section of a distribution system one by one, and judges one by one in the section concerned.
  • the state where the meter reading information which the sensor with a communication function detected is zero is included in the defect
  • the distribution facility for acquiring meter reading information of the communication function-equipped sensor from the power distribution system in which the customer having the communication function-equipped sensor installed is interconnected via the communication system.
  • It is a management system, and it is a loss number operation part which calculates the number of loss of meter reading information obtained from a sensor with communication function, an accident loss number operation part which calculates the installation number of the sensor with communication function of distribution system, and the number of loss in accident And an accident determination unit that determines the disconnection accident of the distribution system by comparing the number of installation of the calculation unit and the number of defects of the calculation unit.
  • the system also includes a system information storage unit storing, for each section, the number of installed sensors with communication functions present in the section when the distribution system is divided into appropriate sections;
  • the accident determination unit compares the number of sensors with communication functions installed in each section with the number of defects in the number calculation unit in the sections by referring to And an accident determination unit for determining.
  • the apparatus further includes a defect information storage unit that stores the simultaneous defect count of meter reading information due to a communication failure from the meter reading information of a sensor with a communication function obtained through the communication system, and the accident determination unit If the number of readings stored in the loss information storage unit is smaller than the number of simultaneous loss of meter reading information due to a communication failure in the past, the determination of the disconnection accident of the distribution system is not performed.
  • the disconnection judgment result by the accident judgment unit is sent to the substation that feeds the power distribution system.
  • a sensor with a communication function is installed at a power consumer's house linked to a distribution system, acquires meter reading information at predetermined time intervals, and has a function to wirelessly communicate with other sensors with a communication function within a predetermined range. Mu.
  • the meter reading information is any one of the power consumption amount, the voltage value, and the current value of the power consumer home where the sensor with the communication function is installed.
  • the meter reading information from the sensor with a communication function is totaled in the meter reading information totaling unit, and a plurality of meter reading information totaling units are installed in the power distribution system per one feeder, and the meter reading device installed within a predetermined range It has a function of collecting meter reading information at predetermined time intervals using a wireless communication function.
  • system information storage unit holds the configuration of the distribution system, the transformer installed in the distribution system, and the interconnection information of the transformer and the meter connected to the downstream of the system from the transformer.
  • the accident determination unit compares the loss state of the meter reading information measured by the sensor with the communication function with the loss state of the meter reading information in the case where disconnection is assumed at an appropriate location of the distribution system. When a certain determination index reaches a predetermined value, it is determined that a disconnection has occurred in the distribution system.
  • the accident determination unit compares the loss state of the meter reading information measured by the sensor with the communication function with the loss state of the meter reading information in the case where disconnection is assumed at an appropriate location of the distribution system, When the combination of the attached sensors agrees with the combination of the meter reading devices missing at the time of the latter assumed disconnection, it is determined that the disconnection occurs at the assumed location.
  • the number of measuring instruments (sensors) introduced into the distribution system can be reduced, equipment investment can be suppressed, and a disconnection accident can be detected with high accuracy.
  • FIGS. 1 to 10 a distribution facility management system having a disconnection accident detection method and a disconnection accident detection method according to an embodiment of the present invention will be described in detail with reference to FIGS. 1 to 10.
  • the same functional parts are denoted by the same reference numerals, and duplicate explanations are omitted.
  • a sensor with a communication function installed in each customer is used to detect disconnection of a distribution line.
  • the sensor with communication function performs meter reading of water, gas, electricity and the like, and transmits meter reading information to the central side via a communication path such as a distribution line or a wireless communication path.
  • a sensor with a communication function generally operates by receiving power supply from a distribution line. For this reason, when the distribution line is disconnected, the sensor with communication function can not send out the meter reading information, and as a result, a loss of meter reading information occurs on the center side.
  • the present invention utilizes this to detect a break in the distribution line.
  • a sensor with communication function (hereinafter referred to as a meter-reading apparatus) 6 installed at each customer is shown.
  • the meter reading information such as water, gas, electricity, etc. measured here is counted by the meter reading information totaling unit 12 installed in a plurality of places (for example, on the power distribution system) via the communication path 20 It is read into the part 10 one by one.
  • a plurality of meter reading information aggregation units 12 are installed in a distribution system per one feeder, and collect meter reading information measured by a meter reading device installed within a predetermined range at predetermined time intervals using a wireless communication function. It has a function.
  • a distribution line or a wireless communication path can be used as the communication path 20 between the meter reading device 6 and the meter reading information aggregation unit 12, and meter reading information is transmitted and received by communication with each other.
  • meter-reading information of each meter-reading apparatus is sequentially passed toward the nearby meter-reading apparatus 6 from the remote meter-reading apparatus 6.
  • the meter reading information of all the meter reading devices 6 are sequentially collected in the meter reading information aggregation unit 12 and read into the disconnection detection unit 10.
  • the communication method between the meter reading device 6 and the meter reading information collecting unit 12 is a method in which the parent device (meter reading information collecting unit 12) periodically calls the child device (meter reading device 6) to collect information It may be any method of transmitting information in a cycle.
  • the disconnection accident detection calculation function is provided in the central disconnection detection unit 10 as shown in FIG.
  • the disconnection detection unit 10 performs a reading operation when a disconnection accident in a predetermined section on the distribution system is assumed, and the disconnection number calculation unit 101 that calculates the number (actual number of defects) of the meter reading device 6 in which the reading information is lost.
  • An accident defect number calculation unit 102 that calculates the number of meter reading devices 6 in which information is lost (the number of case defects) and a distribution line that constitutes a distribution system using the ratio of the actual defect number and the case defect number. It has the accident determination part 103 which determines whether it was disconnected. Note that the system information of the system information storage unit 13 is referred to for the determination of the accident determination unit 103.
  • the number of actual defects is the number of the meter devices 6 in which defects are actually observed.
  • the number of defects is the total number of meter reading devices 6 installed in this section assuming a disconnection occurrence point.
  • the disconnection accident detection calculation function of the present invention will be described in detail below, but before that, an example of a distribution system to which the disconnection accident detection calculation function of the present invention is applied and a communication path to be used will be described.
  • FIG. 3 shows an example of a distribution system configuration comprised of a high voltage distribution system and a low voltage distribution system.
  • the transformer 2 in the distribution substation is sequentially interconnected to the pole transformer 3 via the distribution line 4.
  • the interconnection between them constitutes a high voltage distribution system.
  • the high voltage distribution system of FIG. 3 is connected in series in the order of 2-4a-3a-4c-3c-4d-3d, and is branched into 4a-4b-3b, and is branched into 4d-4e-3e. Case is shown.
  • each pole transformer 3 converts a high voltage to a low voltage and configures a low voltage distribution system with the customer 5.
  • a configuration of a low voltage distribution system 7b interconnected with the pole transformer 3b is shown in FIG.
  • Electric power consumers 5b1 and 5b2 are connected to the low voltage distribution system 7b via low voltage distribution lines 37, and meter reading devices 6b1 and 6b2 are installed on the electric power consumers 5b1 and 5b2, respectively.
  • the low voltage distribution system is similarly configured for the pole transformers 3a, 3c, 3d and 3e, and the power consumer 6 equipped with the meter detection device 6 is interconnected.
  • a unique identification code ID is assigned to the meter reading device 6 in order to perform communication using the communication path 20.
  • the meter reading devices 6b1 and 6b2 are defined as "0004" and "0005", respectively.
  • the same identification code ID is also given to the meter reading device 6 in the other pole transformers 3a, 3c, 3d, 3e.
  • FIG. 4 is a table showing the correspondence between the identification code ID of the meter reading device 6 and each pole transformer 3 for supplying power to the meter reading device.
  • pole transformers 3a to 3e are described on the left side, and a meter reading device linked to each pole transformer is described on the right side using an identification code ID.
  • identification code IDs are defined as "0001", “0002”, and "0003" for power demand homes linked to the low voltage distribution system of the pole transformer. It can be seen that three meter reading devices 6a1, 6a2, 6a3 are installed and electrically connected to the distribution system.
  • Binding data representing the connection relationship between the pole transformer 3 and the meter reading device 6 is stored in the system information storage unit 13 described in FIGS. 1 and 2.
  • FIG. 3 and 4 show an example of the connection relationship between the pole transformer and the meter reading device on the distribution system side, while an example of the connection relationship between the meter reading device and the meter reading information totaling unit on the communication system side It is shown in FIG.
  • FIG. 5 is an explanatory view showing an example of a communication route of meter reading information configured between meter reading devices having a wireless communication function.
  • the meter reading devices 6 in this figure each have a wireless communication function, and automatically transmit a wireless communication route 20 for transmitting the meter reading information measured by each meter reading device to the meter reading information totaling unit 12 between the meter reading devices at relatively short distances. Generate with That is, meter reading information is transmitted and received by multihop communication between meter reading devices.
  • the meter reading devices 6 d 1, 6 d 2 and 6 d 3 are arranged at the first hop position with respect to the meter reading information totaling unit 12. Further, from each of the meter reading devices 6d1, 6d2 and 6d3 at the first stage hop position, the meter reading devices 6c1 and 6c2 and 6e1 and 6c3 and 6c4 are disposed at the second hop position. Although the meter-reading device is similarly disposed at the position where the number of hops is the third or more stage, the detailed description will be omitted with reference to FIG.
  • the meter reading information of the meter reading device at the end of the communication route is transmitted to the meter reading device above the communication route, and the meter reading device receiving the meter reading information additionally transmits its meter reading information to the meter reading device above.
  • the meter reading device 6b2 at the fourth stage hop position transmits meter reading information to the meter reading device 6a3 at the upper third stage hop position.
  • the meter reading device 6a3 at the third stage hop position superimposes the received meter reading information of the lower meter reading device 6b2 and the meter reading information of itself 6a3 to the meter reading device 6C1 at the higher second stage hop position and transmits.
  • the meter reading device 6c1 at the second stage hop position superimposes the received meter reading information of the lower meter reading devices 6b2 and 6a3 and the meter reading information of itself 6c1 on the meter reading device 6d1 at the further higher first stage hop position. Send.
  • the meter reading device 6d1 at the highest first stage hop position transmits the reception information from the lower order and the information of the self 6d1 to the meter reading information totaling unit 12 this time.
  • the meter reading device 6a1 combines the meter reading information received from the meter reading device 6c2 of another route in addition to the information received by the route of the lower meter reading devices 6b2, 6a3 and 6c1, and adds the meter reading information aggregation unit It will be sent to Twelve.
  • the other meter reading positions 6d2 and 6d3 at the first stage position also constitute the multi-hop wireless communication channel according to the same idea as described above, but here the detailed explanation will be omitted with reference to FIG.
  • the wireless communication route of the meter reading device in the present invention constitutes a dendritic structure, and by transmitting the meter reading information to the meter reading information collecting unit 12 sequentially from the remote meter reading device by multi-hop communication, power distribution It is possible to collect meter reading information in the system.
  • the distribution system configuration and the communication path configuration are different from each other, and the communication path is not formed along the distribution system configuration.
  • the distribution system configuration and the communication path configuration may be appropriately changed and operated depending on the respective circumstances. For example, the power distribution route of the pole transformer is changed by switching the distribution system, or a communication channel is searched for a frequency channel having a better reception environment, and the connection destination is changed to a higher level meter.
  • transmission and reception of meter reading information is performed periodically in time, and is repeatedly performed according to, for example, a predetermined meter reading cycle of automatic meter reading.
  • meter reading information of each part of the distribution system at the same time is counted in the meter reading information totaling unit 12 at predetermined intervals.
  • FIG. 6 is a diagram showing, in time series, meter reading information collected from a plurality of meter reading devices at the same time.
  • meter reading information in units of 30 minutes is displayed as the presence or absence of defect information.
  • the hatched portion indicates a defect state, and the blank portion indicates that some meter reading information is received.
  • the loss information is grasped and recorded as a state of each time by the pole transformer and the meter reading device (identification code ID) supplied with power by the pole transformer.
  • Table 50 shown in FIG. 6 shows a list 51 of pole transformers installed in the power distribution system and a meter reading device list 52 installed in a power demand home connected to each pole transformer on the vertical axis. .
  • the horizontal axis of the table 50 shown in FIG. 6 indicates the acquisition of the meter reading information corresponding to the meter reading cycle of each meter reading device and the defect state.
  • the meter reading cycle of the meter reading device is, for example, a 2-minute cycle, but in an actual operation, the meter reading cycle may be 1 minute, 3 minutes, 5 minutes, 10 minutes, 15 minutes, 20 minutes or the like.
  • a deficient state from 0:00 to 5:00 on a certain day is shown in a table in units of 30 minutes.
  • a blank frame (mass: for example 54) in the table means that the meter reading information totaling unit 12 has acquired the meter reading information measured by the meter reading device.
  • a hatched frame means that the meter reading information totaling unit 12 could not acquire the meter reading information measured by the meter reading device (loss).
  • the meter reading information measured by the meter reading device 6a2 "0002" at the measurement time 2:00 or 4:00 does not reach the meter reading information totaling unit 12, and the wire breakage detecting unit 10 loses meter reading information.
  • a plurality of meter reading devices may be lost (simultaneous removal) in the same time zone.
  • the number-of-defects calculator 101 included in the disconnection detection unit 10 calculates the number of defects in the meter reading information in accordance with the meter reading cycle. That is, in the present embodiment, the number of defects of meter reading information transmitted every two minutes is calculated each time. In this manner, it is possible to confirm the acquisition / deletion state of the meter reading information measured by each of the meter reading devices.
  • the table of FIG. 6 for displaying acquisition and missing state of meter reading information of each meter reading device is displayed on a display of a terminal PC or portable terminal connected to a distribution facility management system, a large monitor, etc. May be
  • the loss means that information to be obtained at a predetermined time is not aggregated.
  • the causes that can not be counted exist on both the distribution side and the communication side. Among these, there are disconnections of distribution lines as a condition on the distribution side.
  • Most meter-reading devices 6 are supplied with power from the distribution system and are in operation, and do not have other power sources such as storage batteries. For this reason, if the power distribution system is disconnected, the power supply to the meter reading device 6 is cut off, so that the information transmission through the communication path can not be performed. That is, the meter reading information totaling unit 12 does not total the information to be obtained at the predetermined time.
  • the state it is preferable to include a state in which the power detection information is zero as the state to be defined as the missing state. For example, if it is assumed that a meter reading device that checks power is equipped with another power source such as a battery, communication is possible even in a disconnected state of the power distribution system, and zero is provided as power detection information. .
  • the correspondence between the transformer and the meter reading device shown in FIG. 4 is used, and disconnection detection of a distribution line is executed as follows using defect information detected at a constant cycle.
  • the number-of-deletions calculator 101 in FIG. 1 grasps the number of defects at each measurement time. This is explained, for example, in the example of data every 30 minutes in FIG. 6, as shown in the column of the number of defects in FIG. 6, the number of defects at measurement time 0:00 is "0", 0:30 for "5", It becomes 3, 1, 4, 0, 8, 1, 4, 1, 2, 5, 1, 4, 5 in total every 30 minutes.
  • the number-of-accidents-in-operation calculation unit 102 reads predetermined system information from the system information storage unit 13, and similarly calculates the number of case defects for each predetermined section.
  • the system information storage unit 13 stores the relationship of FIG.
  • the entire area of the distribution system of FIG. 3 is assumed as a predetermined section. That is, it is assumed that the distribution line 4a immediately below the substation 2 is disconnected. Since the number of missing cases is the total number of meter reading devices 6 installed in this section, three meter reading devices connected to pole transformer A, two pole transformer B, and pole poles
  • the total number of cases is 13: four transformers C, three pole transformers D, and one pole transformer E, a total of 13 cases.
  • the possibility of the disconnection of the power distribution line is high when a considerable number of meter reading devices in this section are in a defective state. For example, in the state of 3:00 in FIG. 6, eight out of the thirteen meter reading devices are missing, and disconnection is suspected.
  • the determination index ⁇ ⁇ where the actual loss number is the numerator and the case loss number is the denominator, is sequentially calculated for each predetermined interval at each predetermined interval, In this case, it is determined that the wire is broken.
  • the disconnection location on a distribution system can also be pinpointed by collating with the determination index for every area at that time. Since the judgment index ⁇ is in the range of 0.0 to 1.0, it is possible to arbitrarily set the threshold value in the range of 0.0 ⁇ ⁇ 1.0.
  • FIG. 7 is an explanatory view showing an example of the determination index calculated by the accident determination unit 103.
  • FIG. 7 is a line graph 60 showing the time change of the determination index ⁇ ⁇ corresponding to the meter reading cycle.
  • the vertical axis 601 is the judgment index ⁇
  • the horizontal axis 602 is the time, which is the judgment index ⁇ ⁇ every 30 minutes.
  • the broken lines 603, 604, and 605 described in the graph 60 are the judgment indexes ⁇ for each of the predetermined sections on the system, and are calculated by the equation (1).
  • Equation 1] ⁇ LER / LAC (1)
  • LER of the numerator is the number of real defects
  • LAC of the denominator is the number of case defects.
  • the judgment index ⁇ can be in the range of the following equation (2).
  • the state of the judgment indicators 606 and 607 surrounded by a solid line indicates that a disconnection accident has occurred.
  • the judgment indices 604 and 605 indicate 0.6 to 0.8, but since they are not 1.0, only the number of simultaneous loss due to communication failure etc. is large Therefore, it determines that it is not a disconnection accident.
  • FIG. 2 is a block diagram showing an outline of the disconnection accident detection method according to the embodiment.
  • the disconnection accident detection method at this time is provided in the distribution facility management system as the disconnection detection unit 10 as shown in FIG.
  • the disconnection detection unit 10 in this case includes the loss number calculation unit 101 that calculates the actual loss number as in the embodiment of FIG. 1, the accident loss number calculation unit 102 that calculates the case loss number, and the actual loss number.
  • the accident determination unit 103 that determines whether the distribution line that constitutes the distribution system is broken using the ratio of the number of cases and the number of case defects, and a threshold for preventing the actual loss due to communication failure from being determined as a disconnection accident.
  • a correction term calculation unit 201 that calculates
  • the disconnection detection unit 10 of this example includes a meter reading information storage unit 21 and a defect information storage unit 22 as an external database in addition to the system information storage unit 13 of FIG. 1 and cooperates with these to obtain necessary information.
  • the meter reading information storage unit 21, the system information storage unit 13, and the loss information storage unit 22 are records such as an auxiliary storage device such as a hard disk drive (HDD) or flash memory constituting a server etc., and a main storage device such as a main memory. Composed of media.
  • HDD hard disk drive
  • main storage device such as a main memory. Composed of media.
  • the meter reading information storage unit 21 stores the meter reading information collected by the meter reading information collecting unit 12.
  • the system information storage unit 13 includes the configuration of the distribution system, the specifications of distribution devices installed in the distribution system such as distribution lines, pole transformers, switches and the like, management numbers such as IDs, installation locations, years of installation, years of operation Remember etc.
  • the defect information storage unit 22 stores a past defect state of a predetermined meter-reading device 6.
  • the defect state stored in the defect information storage unit 22 is, for example, the combination of the actual number of defects and the number of simultaneously missing (simultaneous) reading devices (simultaneous deletion pattern). Classified into two categories such as “Defect due to” and “Communication failure” and stored.
  • the correction term calculation unit 201 reads, for the target distribution system, among the past simultaneous loss patterns stored in the loss information storage unit 22, a simultaneous loss pattern having the largest number of actual losses due to a communication failure, and reads the correction term ⁇ .
  • the correction term calculation unit 201 refers to the loss information storage unit 22 to know that the past maximum value of the actual loss number simultaneously lost due to, for example, communication failure is 8 (units). In this case, it is determined that up to eight simultaneous defects occur frequently even in the case of communication failure, and a correction term ⁇ for correcting the determination index ⁇ is set so as not to determine eight or less simultaneous defects as “breakage”.
  • the determination result of the disconnection by the disconnection detection unit 10 is output to the alarm issuing unit 202 and the disconnection point display unit 203.
  • the alarm issuing unit 202 is provided in a sales office or the like in which a worker is resident, and issues an alarm when it receives a determination result of “disconnection accident occurrence” from the disconnection detection unit 10 provided in the distribution facility management system. It is possible to aurally inform personnel and others of the disconnection accident.
  • the disconnection point display unit 203 is also provided in the sales office or the like, and can visually notify a worker or the like of the occurrence of a disconnection accident.
  • the disconnection point display unit 203 is, for example, a terminal PC connected to the power distribution facility management system, a display of a portable terminal, a large monitor, or the like.
  • FIG. 8 is an explanatory view showing a disconnection accident case.
  • FIG. 8 is an example of the same distribution system as FIG. 3, and is a distribution line 4a-4e that interconnects the transformer 2 of the distribution substation, the pole transformers 3a to 3e, and the pole transformers 3a to 3e.
  • Configure. X marks F1, F2 and F3 shown on each section in FIG. 8 indicate locations where disconnection accidents are assumed to occur, and each disconnection accident occurs separately or simultaneously, but in the present embodiment, each disconnection accident is individualized. It is assumed that it occurred in
  • the table 70 of FIG. 9 is a diagram showing an example of acquisition of the same meter reading information as shown in FIG. 5 and an example of a defect state.
  • the regions 705, 704, and 706 of the defect surrounded by black frames correspond to the disconnection points F1, F2, and F3 in FIG. 8, respectively.
  • the meter reading device 6 of the pole transformer A (3a) and the pole transformer B (3b) is not in the defect state, and the pole transformers C (3c), D (3d), E (3e) Since all the meter reading devices 6 are in the defective state, the electricity is communicated to the distribution lines 4a and 4b, and the electricity is not communicated to the distribution lines 4c, 4d and 4e, so that the disconnection point F2 can be identified.
  • a disconnection accident case 2 it is assumed that a disconnection occurs in a time zone of 6:00 to 6:30 on the distribution line 4b upstream of the pole transformer B (3b) (a disconnection point F1).
  • meter reading devices 0004 and 0005 linked to pole transformer B (3b) do not operate.
  • FIG. 10 is an explanatory diagram showing an example of correction term calculation in the correction term calculation unit 201.
  • the correction term ⁇ is defined as the step function 803 of equation (4).
  • the threshold 804 of the step function will be described.
  • the maximum value of the number of meter reading devices (the number of simultaneous defects) when the meter reading information is simultaneously lost due to a communication failure is adopted.
  • the maximum value NMAX of the number of simultaneous defects is eight. In other words, up to eight units means that there is a possibility that the meter reading information may be lost simultaneously due to communication failure. Therefore, the determination index of the equation (1) is corrected as shown in the equation (5) using the correction term ⁇ so as not to erroneously determine that eight or less simultaneous defects due to communication failure or the like are “broken line accidents”.
  • LER / LAC ⁇ ⁇ (5)
  • size N made into the threshold value in the present Example can be set arbitrarily. Designate any numerical value based on the number of meter reading devices distributed in the target distribution system or feeder at the same time. Moreover, you may set not only the number of simultaneous defect
  • the numerical value of the step function of the correction term ⁇ may be other than 0 and 1 as long as it is possible to reduce the erroneous determination of “determining a lost state due to communication failure as a disconnection accident”.
  • first-order, second-order, high-order functions, exponential functions, logarithmic functions, etc. may be used.
  • FIG. 11 is a flowchart showing a disconnection accident detection process implemented in the power distribution facility management system.
  • the disconnection accident detection processing is started when the meter reading information of the meter reading device is input to the wire breakage detection unit 10, and the processing is repeatedly executed according to the meter reading period or the communication period of the meter reading device.
  • the disconnection accident detection process detects a disconnection of a distribution line that constitutes a distribution system, and identifies a disconnection point.
  • the meter reading information of each of the meter reading devices 6 collected by the meter reading information collecting unit 12 is read and acquired.
  • step S 903 system information is read and acquired from the system information storage unit 13 which is one of the databases.
  • the system information is information on the distribution system and the devices constituting the distribution system including the configuration of the distribution system, the installation location and installation years of the devices, specifications, operation parameters and the like shown in FIG. 3.
  • the linking information of the pole transformer shown in FIG. 4 Table 13 and the meter connection device linked to the pole transformer, and the distribution system shown in 4a to 4e of FIG. Includes information on the predetermined section separated by.
  • the at-accident loss number computing unit 102 computes the number of defects corresponding to the predetermined section of the distribution system or the case of the disconnection accident assumed in advance. Do.
  • step S 905 the correction term calculation unit 201 reads and acquires the maximum value NMAX of the number of simultaneous deficits in the past from the deficit information storage unit 22 which is one of the databases.
  • step S906 the correction term calculation unit 201 defines a correction term ⁇ based on the simultaneous defect number maximum value NMAX read in step S905 (see FIG. 10).
  • step S 907 the accident determination unit 103 calculates the actual number of defects LER calculated in step S 902, the number of case defects LAC calculated in step S 904, and the correction term defined in step S 906.
  • the judgment index ⁇ is calculated from equation (5) using ⁇ .
  • step S 908 the accident determination unit 103 determines whether the calculated determination index ⁇ ⁇ ⁇ ⁇ ⁇ satisfies the disconnection accident determination condition defined by equation (6) or (7).
  • equation 7 ACC ACC ⁇ 1.0 1.0 (7)
  • equation (8) means that a disconnection accident has occurred.
  • (6) Formula and (7) Formula which are disconnection accident determination conditions shall set any one.
  • ⁇ ACC can be set arbitrarily based on equation (9). [Equation 9] 0.0 ⁇ ACC ⁇ 1.0 (9) As a result of the determination in step S 908, when it is determined that the disconnection accident has occurred by satisfying equation (6) or (7), the disconnection location display unit 203 displays the disconnection location in step S 909, and the step In S910, an alarm is issued to notify that a disconnection accident has occurred.
  • step S908 if it is determined in step S908 that equation (6) or (7) is not satisfied, and it is determined that a disconnection accident has not occurred, the processing returns to the beginning of the disconnection accident detection processing, and processing is again performed from steps S901, S903, and S905. To start.
  • the alarm issuing unit 202, and the disconnection point display unit 203 described above it is determined whether a disconnection accident has occurred based on the loss state of the meter reading information.
  • the disconnection can be detected by using a meter-reading device with a communication function installed in a home of a power consumer.
  • FIG. 12 is a flowchart showing an accident determination process in the disconnection accident detection method.
  • the disconnection accident determination process is started when the actual number of defects calculated by the defect number calculation unit 101 is input to the accident determination unit 103, and the process is repeatedly executed according to the meter reading cycle or the communication cycle of the meter reading device. .
  • the accident determination processing is to detect a break in a distribution line that constitutes a distribution system.
  • step 1001 the actual number of defects LER calculated by the number-of-deletions calculator 101 is read and acquired.
  • step 1002 the number of case defects LAC calculated by the number-of-accidents calculating unit 102 is read and acquired.
  • step 1003 the correction term ⁇ calculated by the correction term calculation unit 201 is read and acquired.
  • step 1004 the determination index ⁇ for each predetermined interval is calculated based on equation (5).
  • step 1005 it is determined whether the determination index ⁇ calculated in step 1004 satisfies the accident determination condition (6) or (7).
  • the signal of the disconnection accident flag ON is output to the alarm issuing unit 202 and the disconnection point display unit 203, and the accident determination processing is ended.
  • the distribution facility management system of the present invention described in detail above has many parts shared with a meter reading system that reads electric quantity, gas quantity, water quantity, etc. from meter reading information of a sensor with communication function installed in each customer . Therefore, for example, in the case of an electric quantity measuring system for measuring an electric quantity, a power distribution facility management system is additionally provided and used in a sales office of a power company or the like.
  • the disconnection accident detection information is transferred to the substation and used.
  • the alarm issuing unit 202 and the disconnection point display unit 203 in FIG. 2 may be provided in the substation.
  • Disconnection detection unit in the distribution facility management system (minimum configuration)
  • 6 Metering device
  • 12 Meter reading information aggregation unit
  • 13 System information storage unit
  • 20 Disconnection detection unit in distribution facility management system
  • 21 Meter reading information ( Meter reading value storage unit
  • 22 Defect information storage unit
  • 101 Meter reading data defect number calculation unit
  • 102 Accident meter reading data defect number calculation unit
  • 103 Accident determination unit
  • 201 Correction term calculation unit
  • 202 Alarm issuance Part
  • 203 Disconnected point display part

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

 本発明は、配電系統に連系する電力需要家に設置される通信機能付きの検針装置を利用して配電線の断線事故を検出し、断線箇所を特定する。 通信機能付きセンサを設置した需要家が連系された配電系統から、通信系統を介して前記通信機能付きセンサの検針情報を入手する配電設備管理システムであって、通信機能付きセンサから得た検針情報の欠損数を求める欠損数演算部101と、配電系統の通信機能付きセンサの設置数を求める事故時欠損数演算部102と、事故時欠損数演算部102の設置数と欠損数演算部101の欠損数を比較して配電系統の断線事故を判定する事故判定部103とを備える。

Description

配電系統の断線事故検出方法および配電設備管理システム
 本発明は、配電系統における配電線の断線事故を検出し、断線箇所を特定する方法および配電設備管理システムに関する。
 配電系統で断線事故が発生すると、人間が断線した電線に触れて感電する可能性がある。そのため、断線事故を早急に検出することが電力系統の安全性の観点で重要となる。
 しかしながら、配電線の断線事故を検出することは難しい。例えば、電線が被覆されていることにより、断線して地面に垂れ下がった際に地絡せず、系統の電圧や電流などが通常時の数値と変わらないため、断線事故を検出できないことが多い。
 そこで、センサを駆使した様々な断線事故検出方法が検討されてきた。例えば、特許文献1に記載の断線検出システムでは、配電線により供給される電力を計量し、その計量データを送信する通信部を有する複数の通信機能付き計量器と、各通信機能付き計量器から送信されたデータを受診可能な管理所を備えている。各計量器は、配電線上に設置され、配電線の電圧を検出する。その電圧検出結果に基づいて、配電線の断線箇所を判定する。
特開2007-282452号公報
 しかしながら、特許文献1に係る技術では、配電線の断線事故を検出するために配電線上に新たに計量器(センサ)を複数設置する必要がある。そのため、配電設備の管理において設備投資が増大するという問題がある。また、配電系統に同期発電機や誘導発電機等が連系する場合、断線事故が発生しても電圧が異常値を示さないことがあり、断線事故を検出することが難しい。
 本発明は前記課題を解決するためになされたものであり、配電系統に連系する電力需要家に設置される通信機能付きの検針装置(AMI:Advanced Meter Infrastructure)を利用して配電線の断線事故を検出し、断線箇所を特定することを目的とする。
 前記課題を解決するために、本発明の断線事故検出方法および配電設備管理システムは、例えば特許請求の範囲に記載の構成を採用する。
 請求項1に記載の断線事故検出方法の発明では、配電系統に連系された需要家に通信機能付きセンサを設置し、通信機能付きセンサが検出した検針情報を通信系統を介して入手するとともに、検針情報の欠損状態に基づいて、配電線の断線を検出することを特徴とする。
 また配電系統の断線検出は、配電系統を適宜の区間にわけ、当該区間での検針情報の欠損を報告する通信機能付きセンサ数と、当該区間に設置された通信機能付きセンサ数を比較して判断する。
 また通信障害による同時欠損数を過去履歴から保持しておき、配電系統の断線検出は、欠損を報告する通信機能付きセンサ数が、通信障害による同時欠損数よりも多いときに実施される。
 また配電系統の断線検出は、配電系統の区間を順次変更し、当該区間ごとに逐次判断する。
 また検針情報の欠損状態には、通信機能付きセンサが検出した検針情報がゼロである状態を含む。
 請求項7に記載の配電設備管理システムの発明では、通信機能付きセンサを設置した需要家が連系された配電系統から、通信系統を介して前記通信機能付きセンサの検針情報を入手する配電設備管理システムであって、通信機能付きセンサから得た検針情報の欠損数を求める欠損数演算部と、配電系統の通信機能付きセンサの設置数を求める事故時欠損数演算部と、事故時欠損数演算部の設置数と欠損数演算部の欠損数を比較して配電系統の断線事故を判定する事故判定部とを備える。
 また配電系統を適宜の区間に分けたときにその区間に存在する通信機能付きセンサの設置数を区間ごとに記憶された系統情報記憶部を備え、事故時欠損数演算部は、系統情報記憶部を参照して区間ごとの通信機能付きセンサ設置数を求め、事故判定部は区間ごとの通信機能付きセンサ設置数と当該区間における欠損数演算部の欠損数を比較して配電系統の断線事故を判定する事故判定部とを備える。
 また通信系統を介して入手した通信機能付きセンサの検針情報から、過去の通信障害による検針情報の同時欠損数を記憶する欠損情報記憶部を備え、事故判定部は、欠損数演算部の欠損数が欠損情報記憶部に保持された過去の通信障害による検針情報の同時欠損数よりも少ないときには、配電系統の断線事故の判定を行わない。
 また事故判定部による断線事故判定結果が、配電系統に給電する変電所に送られる。
 また通信機能付きセンサは、配電系統と連系する電力需要家宅に設置され、所定の時間間隔で検針情報を取得し、所定範囲内の他の通信機能付きセンサと無線通信するための機能を有するム。
 また検針情報とは、通信機能付きセンサが設置された電力需要家宅の電力消費量、もしくは電圧値、電流値のうちいずれかである。
 また通信機能付きセンサからの検針情報は検針情報集計部において集計され、検針情報集計部は、1フィーダあたりの配電系統に複数個設置され、所定の範囲内に設置されている検針装置が計測した検針情報を、無線通信機能を用いて所定の時間間隔で収集する機能を有する。
 また系統情報記憶部には、配電系統の構成、および配電系統に設置された変圧器、変圧器と変圧器より系統下流に連系する検針装置との連系情報が保持されている。
 また事故判定部は、通信機能付きセンサで計測する検針情報の欠損状態と、配電系統の適当な箇所で断線を想定した場合の検針情報の欠損状態とを比較し、2つの欠損状態の比である判定指標が所定値となった場合に、配電系統において断線が発生したと判定する。
 また事故判定部は、通信機能付きセンサで計測する検針情報の欠損状態と、配電系統の適当な箇所で断線を想定した場合の検針情報の欠損状態とを比較し、前者の欠損状態に通信機能付きセンサの組み合わせが、後者の断線想定時に欠損する検針装置の組み合わせと所定の割合で一致したときに、想定箇所で断線したと判定する。
 本発明によれば、配電系統への計量器(センサ)導入数を低減し、設備投資を抑制することができるともに、高精度に断線事故を検出できる。
本発明の断線検出に関する機能ブロック構成を示す図。 本発明の断線検出に関する他の機能ブロック構成を示す図。 高圧配電系統と低圧配電系統で構成された配電系統構成の一例を示す図。 検針装置の識別符号と柱上変圧器との対応関係を示す図。 無線による通信路系統成の一例を示す図。 複数の検針装置から集計した検針情報を時系列的に示した図。 事故判定部で演算される判定指標の一例を表す図。 断線事故事例を表す説明図。 検針情報の取得および欠損状態の一例を表す図。 補正項演算部における補正項演算の一実施例を表す説明図。 断線事故検出処理を示すフローチャート。 事故判定処理を示すフローチャート。
 以下、本発明の実施形態に係る断線事故検出方法および断線事故検出方法を有する配電設備管理システムついて、図1~図10を参照して詳細に説明する。なお、図1~図10のそれぞれにおいて、共通する機能部には同一の符号を付し、重複した説明を省略する。
 本発明では配電線の断線検出のために、各需要家に設置される通信機能付センサを利用する。通信機能付センサは、水道、ガス、電気などの検針をして、配電線路あるいは無線通信路などの通信路を介して検針情報を中央側に送信する。
 通信機能付センサは、一般には配電線から電力供給を受けて作動している。このため、配電線の断線時には、通信機能付センサは検針情報の送出が行えず、この結果中央側には検針情報の欠損状態が発生する。本発明ではこのことを利用して配電線の断線を検知する。
 はじめに、本発明の断線検出に関する機能ブロック構成について図1を参照して説明する。図1の左側には、各需要家に設置された通信機能付センサ(以下検針装置と称する)6が示されている。ここで計測された水道、ガス、電気などの検針情報は、通信路20を介して適宜の個所(例えば配電系統上)に複数設置された検針情報集計部12で集計され、中央側の断線検出部10に逐次読み込まれる。
 検針情報集計部12は、1フィーダあたりの配電系統に複数個設置され、所定の範囲内に設置されている検針装置が計測した検針情報を、無線通信機能を用いて所定の時間間隔で収集する機能を有する。
 検針装置6と検針情報集計部12の間の通信路20としては配電線路あるいは無線通信路などが利用可能であり、互いに通信により検針情報を送受信している。これにより、遠方の検針装置6から近傍の検針装置6へ向かって各検針装置の検針情報が順次渡される。
最終的に全ての検針装置6の検針情報が検針情報集計部12に逐次集約され、断線検出部10に読み込まれる。
 なお検針装置6と検針情報集計部12の間の通信方法は、親装置(検針情報集計部12)が子装置(検針装置6)を定期的に呼び出して情報を収集する方式、子装置が所定周期で情報を送信する方式のいずれであってもよい。
 断線事故検出演算機能は、図1に示すように中央の断線検出部10に備えられる。断線検出部10は、検針情報が欠損した検針装置6の個数(実欠損数とする)を演算する欠損数演算部101と、配電系統上の所定の区間での断線事故を想定した時に、検針情報が欠損する検針装置6の個数(ケース欠損数とする)を演算する事故時欠損数演算部102と、前記実欠損数とケース欠損数の比を用いて、配電系統を構成する配電線が断線したかどうかを判定する事故判定部103を有する。なお事故判定部103の判定には系統情報記憶部13の系統情報を参照する。
 ここで、実欠損数とケース欠損数の意味については後で詳述するが、ごく簡単に説明しておくと、実欠損数は実際に欠損が観測された検針装置6の個数であり、ケース欠損数は断線発生点を想定したときにこの区間内に設置されている検針装置6の総数である。
 以下本発明の断線事故検出演算機能について詳細に説明するが、その前に本発明の断線事故検出演算機能を適用する配電系統と、使用する通信路について一例をあげて説明しておく。
 まず図3は、高圧配電系統と低圧配電系統で構成された配電系統構成の一例を示している。この例の配電系統では、配電変電所内の変圧器2から、配電線4を介して柱上変圧器3に順次連系する。この間の連系が高圧配電系統を構成している。具体的には図3の高圧配電系統は、2-4a-3a-4c-3c-4d-3dの順に直列に接続され、かつ4a-4b-3bに分岐し、また4d-4eー3eに分岐して構成された事例を示している。
 これに対し、各柱上変圧器3では高電圧を低電圧に変換して、需要家5との間に低圧配電系統を構成する。図3には柱上変圧器3と需要家5の間の連系の一例として、柱上変圧器3bに連系する低圧配電系統7bの構成が示されている。低圧配電系統7bには、低圧配電線37を介して電力需要家5b1、5b2が接続されており、電力需要家5b1、5b2にはそれぞれ検針装置6b1、6b2が設置されている。
 なお図3には表記していないが、同様に柱上変圧器3a、3c、3d、3eについても低圧配電系統を構成し、それぞれ検針装置6を備えた電力需要家6が連系されている。ここで検針装置6には、通信路20を用いた通信を行うために固有の識別符号IDが付与されており、例えば検針装置6b1、6b2はそれぞれ「0004」、「0005」と定義されている。同様の識別符号IDは、他の柱上変圧器3a、3c、3d、3e内の検針装置6についても付与されている。
 図4は、検針装置6の識別符号IDと、当該検針装置に電力供給する各柱上変圧器3との対応関係を表にしたものである。図4では、左側に柱上変圧器3a~3eを記載し、右側に各柱上変圧器と連系する検針装置を識別符号IDを用いて記載している。例えば、柱上変圧器A(3a)の場合、この柱上変圧器の低圧配電系統に連系する電力需要家宅には識別符号IDが「0001」、「0002」、「0003」と定義された3台の検針装置6a1、6a2、6a3が設置されており、配電系統と電気的に接続されていることがわかる。なお、他の柱上変圧器C(3c)、D(3d)、E(3e)と検針装置6の間でも同様な対応関係が設定されているが、ここでは対応関係の逐一の説明は図4の図示をもって省略する。この柱上変圧器3と検針装置6との接続関係を表す紐付けのデータが図1および図2に記載の系統情報記憶部13に記憶されている。
 図3、図4は配電系統側における柱上変圧器と検針装置との接続関係の一例を示しているが、これに対し通信系統側における検針装置と検針情報集計部との接続関係の一例が図5に示されている。
 図5は、無線による通信機能を持つ検針装置間で構成される検針情報の通信ルートの一例を表す説明図である。この図の検針装置6はそれぞれ無線通信機能を持ち、比較的近い距離にある検針装置間で、各検針装置が計測した検針情報を検針情報集計部12に送信するための無線通信ルート20を自動で生成する。つまり、検針情報は検針装置間のマルチホップ通信により送受信される。
 図4の例では、検針情報集計部12に対してホップ数が第1段の位置に検針装置6d1、6d2、6d3が配置されている。さらにこれら第1段ホップ位置の検針装置6d1、6d2、6d3のそれぞれから、ホップ数が第2段の位置に検針装置6c1と6c2、6e1と6c3、6c4が配置されている。ホップ数が第3段以上の位置にも同様にして検針装置が配置されているが、図5の図示を持って詳細説明を省略する。
 これにより通信ルート末端の検針装置の検針情報を通信ルート上位の検針装置に送信し、該検針情報を受診した検針装置は、さらに上位の検針装置へ自身の検針情報を上乗せして送信する。例えば、第4段ホップ位置にある検針装置6b2は、上位の第3段ホップ位置にある検針装置6a3に検針情報を送信する。第3段ホップ位置にある検針装置6a3はさらに上位の第2段ホップ位置にある検針装置6C1へ、受信した下位の検針装置6b2の検針情報と自身6a3の検針情報を上乗せして送信する。同様に第2段ホップ位置の検針装置6c1は、さらに上位の第1段ホップ位置にある検針装置6d1へ、受信した下位の検針装置6b2、6a3の検針情報と自身6c1の検針情報を上乗せして送信する。
 最上位の第1段ホップ位置にある検針装置6d1は、同様にして下位からの受信情報と自己6d1の情報を今度は検針情報集計部12に対して送信する。ただしこの場合には、検針装置6a1は、下位の検針装置6b2、6a3、6c1のルートで受信した情報のほかに、別ルートの検針装置6c2から受信した検針情報を合わせて上位の検針情報集計部12に対して送信することになる。
 他の第1段位置の検針装置6d2、6d3も以上説明したと同じ考えに従いマルチホップ無線通信路を構成するが、ここでは図5の図示を持って詳細説明を省略する。
 このようにして本発明における検針装置の無線通信ルートは樹枝状構造を構成し、マルチホップ通信にて、検針情報集計部12に対して遠方の検針装置から順に検針情報を送信することで、配電系統内の検針情報を収集することができる。
 以上、配電系統構成の一例を図3で、通信路構成の一例を図5で説明した。この例からも明らかなように、配電系統構成と通信路構成は別異に構成されており、配電系統構成に沿って通信路が形成されるわけではない。かつ、これらの配電系統構成と通信路構成は、それぞれの事情により適宜構成変更されて運用されることがある。例えば、配電系統の切り替えにより柱上変圧器の給電ルートを変更し、あるいは通信路ではより受信環境の良い周波数チャネルを求めて上位の検針装置に接続先を変更するといったことが発生する。
 然しながら、配電系統構成と通信路構成が別異に構成され、かつ適宜変更されることがあったとしても、図4の柱上変圧器と検針装置の配置関係は固定されたままである。従って、配電系統構成と通信路構成の間の関係を、図4の表により対応づけて把握することが可能である。
 ところで、検針情報の送受信は時間周期的に実施され、例えば自動検針の所定の検針周期に合わせて繰り返し実施される。これにより、検針情報集計部12には同一時刻における配電系統各所の検針情報が、所定周期ごとに集計されることになる。
 図6は、同時刻に複数の検針装置から集計した検針情報を時系列的に示した図である。
図では例えば、30分単位での検針情報を欠損情報の有無として表示している。斜線の部分が欠損状態を表しており、空白の部分は何らかの検針情報が受信されていることを表している。この欠損情報は、柱上変圧器とこれにより給電される検針装置(識別符号ID)ごとに、各時刻の状態として検針情報集計部12に把握され、記録される。
 図6に示す表50は、縦軸に配電系統に設置された柱上変圧器の一覧51と各柱上変圧器と連系する電力需要家宅に設置されている検針装置一覧52を示している。図6に示す表50の横軸には、各検針装置の検針周期に対応した検針情報の取得および欠損状態を示している。検針装置の検針周期は例えば2分周期であるが、実際の運用においては、1分、3分、5分、10分、15分、20分などの検針周期でもよい。なお、図6では説明の都合上、ある日の0時00分から7時00分までの欠損状態を、30分単位で示した表としている。
 表内の空欄の枠(マス:例えば54)は、検針情報集計部12が、当該の検針装置が計測した検針情報を取得したことを意味する。一方、斜線の枠(マス:例えば55)は、検針情報集計部12が、検針装置が計測した検針情報を取得できなかった(欠損)ことを意味する。
 例として、図5に示した通信ルートを参照して説明する。図6の表50において、検針装置6a2「0002」に着目すると、各計測時刻0:00や1:00に計測した検針情報は、検針装置6C4「0009」および6d3「0012」を通して検針情報集計部12まで送信されており、断線検出部10において検針情報を取得したこととなる。
 一方、検針装置6a2「0002」が計測時刻2:00や4:00に計測した検針情報は検針情報集計部12まで届かず、断線検出部10においては検針情報が欠損した状態となる。また、同じ時間帯で複数の検針装置が欠損状態となる(同時欠損)場合もある。
 ただし、実際には、断線検出部10が有する欠損数演算部101では、検針周期に合わせて、検針情報の欠損数を演算する。つまり、本実施例においては、2分毎に送信されてくる検針情報の欠損数をその都度演算する。このようにして、各検針装置が計測する検針情報の取得・欠損状態を確認することができる。
 なお、本発明では、各検針装置の検針情報の取得および欠損状態を表示する図6の表を、例えば、配電設備管理システムと接続する端末PCや携帯端末のディスプレイ、大型モニタなどに出力表示してもよい。
 なおここで欠損とは、所定時刻に得られるべき情報が集計されない状態を意味している。集計できない原因は、配電側と通信側の双方に存在する。このうち配電側の事情としては配電線の断線がある。殆どの検針装置6は、配電系統から給電されて稼働しており、蓄電池などの他電源を備えていない。このため、配電系統が断線すると検針装置6への電力供給が断たれるので、通信路による情報送信が行えない。つまり、検針情報集計部12には所定時刻に得られるべき情報が集計されないことになる。
 通信側の事情として、何らかの通信障害が発生すれば、受信不良により所定時刻に得られるべき情報が集計されない状態となる。
 また、欠損状態に定義すべき状態としては、電力検出情報がゼロの状態を含めておくのがよい。例えば電力を検診する検針装置が電池などの他電源を備える場合を想定すると、配電系統断線状態でも通信が可能であり、電力検出情報としてゼロを与えるので、この事例も把握することが可能である。
 本発明では、図4の変圧器と検針装置の対応関係を利用し、一定周期で検知した欠損情報を用いて配電線の断線検出を以下のようにして実行する。
 まず図1の欠損数演算部101では、計測時刻ごとに欠損数を把握する。これは例えば図6の30分ごとのデータの例で説明すると、図6の欠損数の欄に示すように計測時刻0:00の欠損数は「0」、0:30では「5」、以下30分ごとの集計では3、1、4、0,8、1、4、1,2,5,1,4,5となる。
 次に事故時欠損数演算部102では、系統情報記憶部13から所定の系統情報を読み込み、同様に所定区間毎のケース欠損数を演算する。なお先に説明したように系統情報記憶部13には図4の関係が記憶されている。ここでは例えば所定区間として、図3の配電系統の全域を想定する。つまり、変電所2直下の配電線4aが断線したものと想定する。ケース欠損数とは、この区間に設置されている検針装置6の総数であるので、柱上変圧器Aに接続された3台の検針装置と、柱上変圧器Bの2台と、柱上変圧器Cの4台と、柱上変圧器Dの3台と、柱上変圧器Eの1台の、合計13台がケース欠損数ということになる。
 本発明では、この区間の検針装置の相当数が欠損状態であるときに配電線路の断線の可能性が高いと考えている。例えば、図6の3:00の状態では、13台の検針装置のうちの8台が欠損しており、断線が疑われる。
 このことから図1の事故判定部103では、実欠損数を分子、ケース欠損数を分母にとった判定指標ρを所定区間毎、所定時刻毎に逐次演算し、判定指標ρが閾値を超えた場合に断線と判定する。
 また、そのときに区間毎の判定指標で照合することにより、配電系統上の断線箇所も特定することができる。なお、判定指標ρは0.0~1.0の範囲であるため、閾値としては0.0<ρ≦1.0の範囲で任意に設定することが可能である。
 図7は、事故判定部103で演算される判定指標の一例を表す説明図である。図7は、前記検針周期に対応した判定指標ρの時間変化を示した折れ線グラフ60である。縦軸601は判定指標ρ、横軸602は時間であり30分刻みの判定指標ρである。グラフ60に記載の折れ線603、604、605がそれぞれ系統上の前記所定区間毎の判定指標ρであり、(1)式で計算される。
[数1]
             ρ=LER/LAC     ・・・(1)
 ここで、分子のLERは前記実欠損数、分母のLACは前記ケース欠損数である。基本的にLAC≧LERの関係があり、(1)式から分かるように判定指標ρは以下の(2)式の範囲を取りうる。
[数2]
             0.0≦ρ≦1.0     ・・・(2)
 本発明の判定において、その一例では(1)式から分かるように、本判定指標ρが1.0より小さい場合は、断線事故が発生していない状態、判定指標ρが1.0となった時はLER=LACであるため、断線事故と判定する(事故判定条件)。グラフ60の場合、実線で囲んだ判定指標606や607の状態は断線事故であることを示す。
 これに対し、点線で囲んだ判定指標608の状態では、判定指標604や605が0.6~0.8を示しているが、1.0ではないため通信障害等による同時欠損数が多いだけで、断線事故ではないと判定する。
 ただし、判定指標ρの事故判定条件として(3)式のように任意の範囲を設定できるものとし、ρACCは事故判定条件の下限値である。
[数3]
             ρACC≦ρ≦1.0     ・・・(3)
 本発明の判定において、他の一例では判定指標が1ではないが、高い数値であるときには後流域での断線の可能性が高いと考える。つまり、図3の配電線4aでの断線を想定して判定指標ρを求めた時に、図6の3:00のようにρ=0.6(8/13)である場合に、この想定区間での断線事故ではないが、下流側での断線の可能性が高い。係る状態では、本発明では想定区間を下流側に変更して継続実施することで、断線区間特定に至ることが可能である。
 以上、(1)式のような検針情報の実欠損数と前記所定区間毎のケース欠損数を比較することで配電系統の断線事故を検出することが可能となる。
 次に、同じく本発明の実施形態である配電設備管理システムに備わる断線事故検出方法の機能ブロック構成について図2を参照して説明する。
 図2は、実施形態に係る断線事故検出方法の概要を示すブロック図である。このときの断線事故検出方法は、図2に示すように断線検出部10として配電設備管理システムに備得られている。
 この事例での断線検出部10は、図1の実施例と同様に実欠損数を演算する欠損数演算部101と、ケース欠損数を演算する事故時欠損数演算部102と、前記実欠損数とケース欠損数の比を用いて、配電系統を構成する配電線が断線したかどうかを判定する事故判定部103を備え、さらに通信障害による実欠損を断線事故と判定しないようにするための閾値を演算する補正項演算部201を有する。
 またこの事例の断線検出部10は、外部データベースとして図1の系統情報記憶部13以外に、検針情報記憶部21、および欠損情報記憶部22を備えており、これらと連携して必要な情報を送受信する。なお検針情報憶部21、系統情報記憶部13、欠損情報記憶部22は、サーバーなどを構成するHDD(Hard Disk Drive)やフラッシュメモリなどの補助記憶装置、メインメモリなどの主記憶装置などの記録媒体により構成される。
 外部データベースのうち、検針情報記憶部21は、検針情報集計部12で収集した検針情報を記憶する。系統情報記憶部13は、配電系統の構成、配電線、柱上変圧器、開閉器などの配電系統に設置されている配電機器の仕様、ID等の管理番号、設置場所、設置年数、稼働年数などを記憶する。欠損情報記憶部22は、所定の検針装置6の過去の欠損状態を記憶する。
 欠損情報記憶部22に記憶される欠損状態とは、例えば、実欠損数および同時に欠損(同時欠損)した検針装置の組み合わせと数(同時欠損パターン)であり、欠損の原因を「断線などの事故による欠損」と、「通信障害」などの2つのカテゴリに分類して記憶する。
 補正項演算部201では、対象の配電系統に対して、欠損情報記憶部22に記憶する過去の同時欠損パターンのうち、通信障害による実欠損数が最大である同時欠損パターンを読み込み、補正項σを設定する。
 補正項演算部201では、欠損情報記憶部22を参照して、例えば通信障害が原因で同時欠損した実欠損数の過去最大値が8(台)であったことを知る。この場合、8台までの同時欠損は通信障害でも頻繁に発生すると判断して、8台以下の同時欠損を「断線」と判定しないように、判定指標ρを補正する補正項σを設定する。
 断線検出部10で断線判定した結果は、警報発令部202と断線箇所表示部203に出力される。警報発令部202は、作業員が常駐する営業事務所などに備わっており、配電設備管理システムに備わる断線検出部10から「断線事故発生」という判定結果を受けた場合に、警報を出し、作業員等に断線事故を聴覚的に知らせることができる。断線箇所表示部203も同様に、前記営業事務所等に備わっており、作業員等に断線事故の発生を視覚的に知らせることができる。断線箇所表示部203は、例えば、配電設備管理システムと接続する端末PCや携帯端末のディスプレイ、大型モニタなどである。
 図8は、断線事故事例を表す説明図である。図8は、図3と同じ配電系統の一例であり、配電変電所の変圧器2と、柱上変圧器3a~3e、各柱上変圧器3a~3eを連系する配電線4a~4eで構成する。図8の各区間上に示した×印F1,F2,F3は断線事故の発生を想定した箇所を示しており、各断線事故は別々もしくは同時に発生するが、本実施例では各断線事故は個別に発生したものとして説明する。
 図9の表70は、図5で示したものと同じ検針情報の取得および欠損状態の一例を表す図である。この図において黒枠で囲った欠損の領域705,704,706が、図8の断線箇所F1,F2,F3にそれぞれ対応している。
 例えば、断線事故事例1として、図8において、柱上変圧器A(3a)と柱上変圧器C(3c)の区間(配電線4C)上で、3:00~3:30の時間帯で断線したとする(断線箇所F2)。この場合、配電系統において断線箇所F2より下流にある柱上変圧器C(3c)と柱上変圧器D(3d)と柱上変圧器E(3e)には電気が流れない。つまり、この3つの柱上変圧器3c、3d、3eに連系する検針装置は動作しないため検針装置6からの検針情報を取得できないことになる。
 従って、図9の表70の3:00の時間帯の検針情報において、柱上変圧器C(3c)に連系する検針装置0006、0007、0008、0009、柱上変圧器D(3d)に連系する検針装置0010、006、0012、柱上変圧器E(3e)に連系する検針装置0013の検針情報が同時に欠損した状態704となる。
 つまり、このようにある時間帯で複数の検針情報が同時に欠損した場合、断線事故と判定することができる。また、表70に示すように、柱上変圧器と該柱上変圧器に連系する検針装置に基づいて、検針装置の同時欠損パターン704などから、断線箇所を特定することが可能である。
 本実施例では、柱上変圧器A(3a)と柱上変圧器B(3b)の検針装置6は欠損状態ではなく、柱上変圧器C(3c)、D(3d)、E(3e)の検針装置6が全て欠損状態であることから、配電線4a、4bには電気が通じており、配電線4c、4d、4eには電気が通じていないことから断線箇所F2を特定できる。
 次に、断線事故事例2として、柱上変圧器B(3b)より上流の配電線4b上で、6:00~6:30の時間帯で断線したとする(断線箇所F1)。この場合、配電系統において断線箇所F1より下流にある柱上変圧器B(3b)には電気が流れないため、柱上変圧器B(3b)に連系する検針装置0004と0005は動作しないため、検針装置からの検針情報を取得できない。従って、図9の表70の6:00~6:30の時間帯の検針情報において、検針装置0004と0005の検針情報が同時に欠損した状態705となる。
 同様に、断線事故事例3として、配電線4e上で6:00~6:30の時間帯で断線事故が発生した場合(断線箇所F3)、断線箇所F3より下流の柱上変圧器E(3e)には電気が流れないため、該柱上変圧器E(3e)に連系する検針装置0013には電気が流れず動作しない。つまり、検針装置0013からの検針情報を取得できない。従って、図9の表70において、6:00~6:30の検針情報において、検針装置0013の検針情報は欠損状態706となる。
 以上、説明したように、柱上変圧器と柱上変圧器に連系する検針装置と、検針装置の欠損状態から断線事故を判定し、断線箇所を特定することが可能である。
 図10は、補正項演算部201における補正項演算の一実施例を表す説明図である。図10は補正項σを示すグラフであり、縦軸801に補正項σ、横軸802に同時欠損台数(断線事故規模)Nをとる。本実施例では、補正項σを(4)式のステップ関数803として定義する。
[数4]
             σ=0 (N≦8)   
             σ=1 (N>8)   ・・・(4)
 ステップ関数の閾値804について説明する。本実施例では、通信障害により検針情報が同時に欠損したときの検針装置の数(同時欠損数)の最大値を採用している。本実施例が対象とした配電系統では、同時欠損数の最大値NMAXは8である。つまり、最大8台までは、通信障害により検針情報が同時に欠損する可能性があることを意味する。従って、通信障害などによる8台以下の同時欠損を「断線事故」と誤判定しないように、補正項σを用いて、(1)式の判定指標を(5)式のように補正する。
[数5]
             ρ=LER/LAC × σ ・・・(5)
 (4)式および(5)式から、8台以下の同時欠損に対して判定指標はρ=0となる。
従って、検針装置8台以下の同時欠損に対しては断線事故と判定しないように補正する。
このように判定指標ρを補正することで、通信障害などにより頻発する欠損を事故と判定することを防ぐことができる。
 なお、本実施例で閾値とした断線事故規模Nの値は任意に設定できる。対象とする配電系統もしくはフィーダ内に分布する検針装置が同時欠損したときの台数に基づいて任意の数値を指定する。また、同時欠損数に限らず任意の数値を設定してもよい。
 なお、「通信障害による欠損状態を断線事故と判定する」という誤判定を低減することが可能であれば、補正項σのステップ関数の数値は0および1以外でもよく、また、補正項σステップ関数以外に一次、二次、高次関数、指数関数、対数関数などでもよい。
 次に、断線検出部10における断線事故検出処理について図11を参照して説明する。
図11は、配電設備管理システムに実装された断線事故検出処理を示すフローチャートである。
 この断線事故検出処理は、検針装置の検針情報が断線検出部10へ入力された時点で開始され、検針装置の検針周期もしくは通信周期に合わせて処理を繰り返し実行する。この断線事故検出処理は、配電系統を構成する配電線の断線を検出し、断線箇所を特定するものである。
 図11の最初のステップS901では、検針情報集計部12で集計した各検針装置6の検針情報を読み込み取得する。
 この取り込みに続いてステップS902において、欠損数演算部101は、ステップS901で取得した検針情報のうち、検針情報が欠損している数(実欠損数)を演算する。
その際に、柱上変圧器毎に区切った所定区間毎に欠損数を演算する。欠損数の演算方法の一例としては、欠損時に送信される信号(欠損フラグ:fDATALACK=1)をカウントする方法などがある。
 一方、ステップS903においては、データベースの1つである系統情報記憶部13から系統情報を読み込み取得する。系統情報とは、図3で示す配電系統の構成や機器の設置場所や設置年数、仕様、動作パラメータなどを含む配電系統および系統を構成する機器に関する情報である。ここでは、特に、図4表13に示される柱上変圧器と該柱上変圧器に連系する検針装置との紐付情報と、図3の4a~4eに示される配電系統を柱上変圧器で区切った所定区間に関する情報を含む。
 この取り込みに続いて次にステップS904において、事故時欠損数演算部102はステップS903で取得した系統情報に基づいて、配電系統の所定区間もしくは予め想定した断線事故のケースに応じた欠損数を演算する。
 また一方、ステップS905において、補正項演算部201は、データベースの1つである欠損情報記憶部22より過去の同時欠損数の最大値NMAXを読み込み取得する。
 この取り込みに続いてステップS906において、補正項演算部201は、ステップS905で読み込んだ同時欠損数最大値NMAXに基づいて、補正項σを定義する(図10参照)。
 上記一連のデータ入力とその加工処理後に、ステップS907にて、事故判定部103は、ステップS902で演算した実欠損数LERとステップS904で演算したケース欠損数LACと、ステップS906で定義した補正項σを用いて、(5)式より判定指標ρを演算する。
 ステップS908において、事故判定部103は、演算した判定指標ρが(6)式もしくは(7)式で定義される断線事故判定条件を満たすか否かを判定する。
[数6]
              ρ=1.0         ・・・(6)
[数7]
              ρACC≦ρ≦1.0     ・・・(7)
 ここで(6)式は、実欠損数LERとケース欠損数LACの関係が(8)式となり、断線事故が発生したことを意味する。
[数8]
              LER=LAC       ・・・(8)
 なお、断線事故判定条件である(6)式と(7)式はどちらか一方を設定するものとする。
 ρACCは(9)式に基づいて任意に設定できる。
[数9]         0.0<ρACC<1.0   ・・・(9)

 ステップS908の判定の結果、(6)式もしくは(7)式を満たし、断線事故が発生したと判定された場合は、ステップS909において、断線箇所表示部203にて、断線箇所を表示し、ステップS910において、断線事故が発生した旨を知らせるための警報を発令する。
 一方、ステップS908において、(6)もしくは(7)式を満たさず、断線事故が発生していないと判定された場合は、断線事故検出処理の最初に戻り、再度ステップS901、 S903、 S905より処理を開始する。
 以上説明した断線検出部10および警報発令部202、断線箇所表示部203における断線事故検出処理は、前述したように、検針情報の欠損状態に基づいて断線事故が発生したか否かを判定することにより、電力需要家宅に設置される通信機能付きの検針装置を用いて断線を検出することができる。
 次に、事故判定部103における断線事故判定処理について図12を参照して説明する。図12は、断線事故検出方法における事故判定処理を示すフローチャートである。
 該断線事故判定処理は、欠損数演算部101で演算された実欠損数が事故判定部103へ入力された時点で開始され、前記検針装置の検針周期もしくは通信周期に合わせて処理を繰り返し実行する。この事故判定処理は、配電系統を構成する配電線の断線を検出するものである。
 ステップ1001において、欠損数演算部101で演算された実欠損数LERを読み込み取得する。
 ステップ1002において、事故時欠損数演算部102で演算されたケース欠損数LACを読み込み取得する。
 ステップ1003において、補正項演算部201で演算された補正項σを読み込み取得する。
 ステップ1004において、所定区間毎の判定指標ρを(5)式に基づいて演算する。
 ステップ1005において、ステップ1004において演算した判定指標ρが事故判定条件(6)式もしくは(7)式を満たすか否かを判定する。
 ステップ1005の判定の結果、(6)式もしくは(7)式の事故判定条件を満たし、断線事故が発生したと判定する場合、ステップ1006において、断線事故フラグfLINEBREAKをON(fLINEBREAK=1)とする。前記断線事故フラグONの信号を警報発令部202および断線箇所表示部203に出力し、事故判定処理を終了する。
 ステップ1005の判定の結果、(6)式もしくは(7)式のいずれも満たさず、断線事故が発生していないと判定した場合は、断線事故フラグfLINEBREAKをOFF(fLINEBREAK=0)とし、事故判定処理を終了する。
 以上詳細に説明した本発明の配電設備管理システムは、各需要家に設置された通信機能付きセンサの検針情報から電気量、ガス量、水道量などの検針を行う検針システムと共用する部分が多い。このため例えば電気量の検針を行う電気量検針システムであれば、配電設備管理システムも付随して電力会社の営業所などに設置されて利用されることになる。
 但し、断線事故情報を実際に利用するのは営業所ではなく変電所であるので、断線事故検出情報は変電所に転送されて利用されることになる。このためには、図2の警報発令部202や断線個所表示部203は変電所内に設けられるのが良い。
10:配電設備管理システム内断線検出部(最小構成),6:検針装置,12:検針情報集計部,13:系統情報記憶部,20:配電設備管理システム内断線検出部,21:検針情報(検針値)記憶部,22:欠損情報記憶部,101:検針データ欠損数演算部,102:事故時検針データ欠損数演算部,103:事故判定部,201:補正項演算部,202:警報発令部,203:断線箇所表示部

Claims (16)

  1.  配電系統に連系された需要家に通信機能付きセンサを設置し、該通信機能付きセンサが検出した検針情報を通信系統を介して入手するとともに、検針情報の欠損状態に基づいて、前記配電系統の断線を検出することを特徴とする配電系統の断線事故検出方法。
  2.  請求項1に記載の配電系統の断線事故検出方法であって、
     前記配電系統の断線検出は、検針情報の欠損を示す前記の通信機能付きセンサ数と、
    前記配電系統に設置された前記の通信機能付きセンサ数を比較して判断することを特徴とする配電系統の断線事故検出方法。
  3.  請求項2に記載の配電系統の断線事故検出方法であって、
     前記配電系統の断線検出は、前記配電系統を適宜の区間にわけ、当該区間での検針情報の欠損を報告する前記の通信機能付きセンサ数と、当該区間に設置された前記の通信機能付きセンサ数を比較して判断することを特徴とする配電系統の断線事故検出方法。
  4.  請求項2に記載の配電系統の断線事故検出方法であって、
     通信障害による同時欠損数を過去履歴から保持しておき、前記配電系統の断線検出は、欠損を報告する前記の通信機能付きセンサ数が、前記通信障害による同時欠損数よりも多いときに実施されることを特徴とする配電系統の断線事故検出方法。
  5.  請求項3に記載の配電系統の断線事故検出方法であって、
     前記配電系統の断線検出は、前記配電系統の区間を順次変更し、当該区間ごとに逐次判断することを特徴とする配電系統の断線事故検出方法。
  6.  請求項1に記載の配電系統の断線事故検出方法であって、
    前記検針情報の欠損状態には、前記通信機能付きセンサが検出した検針情報がゼロである状態を含むことを特徴とする配電系統の断線事故検出方法。
  7.  通信機能付きセンサを設置した需要家が連系された配電系統から、通信系統を介して前記通信機能付きセンサの検針情報を入手する配電設備管理システムであって、
     前記通信機能付きセンサから得た検針情報の欠損数を求める欠損数演算部と、前記配電系統の通信機能付きセンサの設置数を求める事故時欠損数演算部と、該事故時欠損数演算部の前記設置数と前記欠損数演算部の欠損数を比較して前記配電系統の断線事故を判定する事故判定部とを備える配電設備管理システム。
  8.  請求項7に記載の配電設備管理システムであって、
     前記配電系統を適宜の区間に分けたときにその区間に存在する前記通信機能付きセンサの設置数を区間ごとに記憶された系統情報記憶部を備え、
     前記事故時欠損数演算部は、前記系統情報記憶部を参照して区間ごとの通信機能付きセンサ設置数を求め、前記事故判定部は区間ごとの通信機能付きセンサ設置数と当該区間における前記欠損数演算部の欠損数を比較して前記配電系統の断線事故を判定する事故判定部とを備える配電設備管理システム。
  9.  請求項7に記載の配電設備管理システムであって、
     前記通信系統を介して入手した通信機能付きセンサの検針情報から、過去の通信障害による検針情報の同時欠損数を記憶する欠損情報記憶部を備え、
     前記事故判定部は、前記欠損数演算部の欠損数が前記欠損情報記憶部に保持された過去の通信障害による検針情報の同時欠損数よりも少ないときには、前記配電系統の断線事故の判定を行わないことを特徴とする配電設備管理システム。
  10.  請求項7に記載の配電設備管理システムであって、
     前記事故判定部による断線事故判定結果が、前記配電系統に給電する変電所に送られることを特徴とする配電設備管理システム。
  11.  請求項7に記載の配電設備管理システムであって、
     前記通信機能付きセンサは、前記配電系統に連系する電力需要家宅に設置され、所定の時間間隔で検針情報を取得し、所定範囲内の他の通信機能付きセンサと無線通信するための機能を有することを特徴とする配電設備管理システム。
  12.  請求項7に記載の配電設備管理システムであって、
     前記検針情報とは、前記通信機能付きセンサが設置された電力需要家宅の電力消費量、もしくは電圧値、電流値のうちいずれかであることを特徴とする配電設備管理システム。
  13.  請求項7に記載の配電設備管理システムであって、
     前記通信機能付きセンサからの検針情報は検針情報集計部において集計され、該検針情報集計部は、1フィーダあたりの配電系統に複数個設置され、所定の範囲内に設置されている検針装置が計測した検針情報を、無線通信機能を用いて所定の時間間隔で収集する機能を有することを特徴とする配電設備管理システム。
  14.  請求項8に記載の配電設備管理システムであって、
     前記系統情報記憶部には、配電系統の構成、および配電系統に設置された変圧器、該変圧器と変圧器より系統下流に連系する検針装置との連系情報は保持されていることを特徴とする配電設備管理システム。
  15.  請求項7に記載の配電設備管理システムであって、
     前記事故判定部は、前記通信機能付きセンサで計測する検針情報の欠損状態と、前記配電系統の適当な箇所で断線を想定した場合の検針情報の欠損状態とを比較し、
     前記2つの欠損状態の比である判定指標が所定値となった場合に、前記配電系統において断線が発生したと判定することを特徴とする配電設備管理システム。
  16.  請求項7に記載の配電設備管理システムであって、
     前記事故判定部は、前記通信機能付きセンサで計測する検針情報の欠損状態と、前記配電系統の適当な箇所で断線を想定した場合の検針情報の欠損状態とを比較し、
     前者の欠損状態に通信機能付きセンサの組み合わせが、後者の断線想定時に欠損する検針装置の組み合わせと所定の割合で一致したときに、前記想定箇所で断線したと判定することを特徴とする配電設備管理システム。
PCT/JP2013/069766 2012-08-08 2013-07-22 配電系統の断線事故検出方法および配電設備管理システム WO2014024665A1 (ja)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US14/419,482 US20150212138A1 (en) 2012-08-08 2013-07-22 Method for detecting open-circuit faults in electric power distribution system, and power distribution facilities management system

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2012175764A JP5952127B2 (ja) 2012-08-08 2012-08-08 配電系統の断線事故検出方法および配電設備管理システム
JP2012-175764 2012-08-08

Publications (1)

Publication Number Publication Date
WO2014024665A1 true WO2014024665A1 (ja) 2014-02-13

Family

ID=50067899

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2013/069766 WO2014024665A1 (ja) 2012-08-08 2013-07-22 配電系統の断線事故検出方法および配電設備管理システム

Country Status (3)

Country Link
US (1) US20150212138A1 (ja)
JP (1) JP5952127B2 (ja)
WO (1) WO2014024665A1 (ja)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104682566A (zh) * 2015-03-23 2015-06-03 北京天源科创风电技术有限责任公司 一种新能源电站故障识别和状态监测系统
CN107154674A (zh) * 2016-11-07 2017-09-12 厦门亿力吉奥信息科技有限公司 基于物联网的电网设备联动消缺方法及其架构
CN109075608A (zh) * 2016-03-17 2018-12-21 三菱电机株式会社 断线检测装置
WO2019171768A1 (ja) * 2018-03-07 2019-09-12 オムロン株式会社 配電網モニタリングシステム
CN110646690A (zh) * 2019-09-10 2020-01-03 国网浙江省电力有限公司电力科学研究院 基于特征电流信号的户变关系识别方法及系统

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5733449B1 (ja) * 2014-05-07 2015-06-10 日本電気株式会社 ノード、マスタ装置、ならびに通信制御システム、方法およびプログラム
JP6374266B2 (ja) * 2014-08-19 2018-08-15 関西電力株式会社 停電検知システム、通信装置、停電検知方法、及び、停電検知プログラム
CN106680616A (zh) * 2016-10-27 2017-05-17 北京智芯微电子科技有限公司 一种配电网的故障检测终端及系统
JP6903963B2 (ja) 2017-03-15 2021-07-14 オムロン株式会社 配電網モニタリングシステムおよび配電網モニタリング装置
JP6747347B2 (ja) * 2017-03-15 2020-08-26 オムロン株式会社 配電網モニタリングシステムおよび配電網モニタリング装置
JP6907726B2 (ja) * 2017-06-06 2021-07-21 中国電力株式会社 データ管理システム
JP2019161858A (ja) * 2018-03-13 2019-09-19 オムロン株式会社 配電網モニタリングシステム
CN109444800B (zh) * 2018-09-28 2021-11-19 国网湖南省电力有限公司 基于无线通信采集的台区识别方法
EP3731049A1 (en) * 2019-04-24 2020-10-28 ABB Power Grids Switzerland AG Substation equipment monitoring using a scada system
CN112198379B (zh) * 2020-09-14 2022-11-01 江阴长仪集团有限公司 一种基于电能计量技术的低压用电设备故障定位系统
BR102022003339A2 (pt) * 2021-02-24 2022-09-06 Siemens Aktiengesellschaft Gerenciamento de falha de circuito aberto em linhas de distribuição aéreas

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007282452A (ja) * 2006-04-11 2007-10-25 Chugoku Electric Power Co Inc:The 配電線の断線検出システム
JP2009033811A (ja) * 2007-07-25 2009-02-12 Fuji Electric Systems Co Ltd 計測・監視システム、その電力品質計測装置、プログラム
WO2011030558A1 (ja) * 2009-09-10 2011-03-17 Abe Rikiya 多端子型電力変換装置、多端子型電力授受装置及び電力ネットワークシステム
JP2011250580A (ja) * 2010-05-27 2011-12-08 Hitachi Ltd 配電系統断線検出装置,配電系統断線検出システム,検針装置,中継装置,制御装置及び配電系統断線検出方法
JP2012105463A (ja) * 2010-11-10 2012-05-31 Chugoku Electric Power Co Inc:The 異常判定システム

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2916075B2 (ja) * 1994-01-21 1999-07-05 関西電力株式会社 配電系統の断線検出方法
US5963457A (en) * 1994-03-18 1999-10-05 Hitachi, Ltd. Electrical power distribution monitoring system and method
JPH09251050A (ja) * 1996-03-14 1997-09-22 Sumitomo Electric Ind Ltd 送配電線の断線検出方法
US20010010032A1 (en) * 1998-10-27 2001-07-26 Ehlers Gregory A. Energy management and building automation system
US7283916B2 (en) * 2004-07-02 2007-10-16 Itron, Inc. Distributed utility monitoring, such as for monitoring the quality or existence of a electrical, gas, or water utility
JP5216511B2 (ja) * 2008-09-30 2013-06-19 アズビル株式会社 流量計測システム
US8751291B2 (en) * 2012-01-05 2014-06-10 General Electric Comany Economic analysis of grid infrastructure
WO2013186640A2 (en) * 2012-05-24 2013-12-19 Lundy Douglas H Threat detection system and method
US9228853B1 (en) * 2012-06-25 2016-01-05 Neptune Technology Group Inc. Method of computing quantity of unaccounted for water in water distribution

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007282452A (ja) * 2006-04-11 2007-10-25 Chugoku Electric Power Co Inc:The 配電線の断線検出システム
JP2009033811A (ja) * 2007-07-25 2009-02-12 Fuji Electric Systems Co Ltd 計測・監視システム、その電力品質計測装置、プログラム
WO2011030558A1 (ja) * 2009-09-10 2011-03-17 Abe Rikiya 多端子型電力変換装置、多端子型電力授受装置及び電力ネットワークシステム
JP2011250580A (ja) * 2010-05-27 2011-12-08 Hitachi Ltd 配電系統断線検出装置,配電系統断線検出システム,検針装置,中継装置,制御装置及び配電系統断線検出方法
JP2012105463A (ja) * 2010-11-10 2012-05-31 Chugoku Electric Power Co Inc:The 異常判定システム

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104682566A (zh) * 2015-03-23 2015-06-03 北京天源科创风电技术有限责任公司 一种新能源电站故障识别和状态监测系统
CN109075608A (zh) * 2016-03-17 2018-12-21 三菱电机株式会社 断线检测装置
CN107154674A (zh) * 2016-11-07 2017-09-12 厦门亿力吉奥信息科技有限公司 基于物联网的电网设备联动消缺方法及其架构
CN107154674B (zh) * 2016-11-07 2020-07-07 厦门亿力吉奥信息科技有限公司 基于物联网的电网设备联动消缺方法及其架构
WO2019171768A1 (ja) * 2018-03-07 2019-09-12 オムロン株式会社 配電網モニタリングシステム
CN110646690A (zh) * 2019-09-10 2020-01-03 国网浙江省电力有限公司电力科学研究院 基于特征电流信号的户变关系识别方法及系统
CN110646690B (zh) * 2019-09-10 2022-01-21 国网浙江省电力有限公司营销服务中心 基于特征电流信号的户变关系识别方法及系统

Also Published As

Publication number Publication date
US20150212138A1 (en) 2015-07-30
JP2014036482A (ja) 2014-02-24
JP5952127B2 (ja) 2016-07-13

Similar Documents

Publication Publication Date Title
WO2014024665A1 (ja) 配電系統の断線事故検出方法および配電設備管理システム
US10768212B2 (en) System and method for detecting theft of electricity with integrity checks analysis
US10746768B2 (en) System and method for detecting theft of electricity
JP2016523480A (ja) 配電グリッドにおける非技術的損失
US11125798B2 (en) Power distribution network monitoring system and power distribution network monitoring device
US11156641B2 (en) Power distribution network monitoring system for detecting abnormalities
KR101287627B1 (ko) 배전 선로 단선 감지 시스템
US11499994B2 (en) Power distribution network monitoring system and power distribution network monitoring device
JP2009118541A (ja) 給電状態収集システム
JP6809921B2 (ja) 配電異常検出システム、配電監視システム
JP6552715B2 (ja) 断線検出装置
US10951059B2 (en) Harmonic detection system
JP5854953B2 (ja) 断線検出装置
MX2010005727A (es) Vigilancia de voltaje en infraestructura de medicion avanzada.
CN105116359B (zh) 用电信息采集终端检测装置及系统
US10677825B2 (en) System and method for detecting theft of electricity using meter data disaggregation
CN112703744A (zh) 信息处理装置和异常可视化系统
JP2014150647A (ja) 停電区間判定システム
WO2019171768A1 (ja) 配電網モニタリングシステム
WO2019176313A1 (ja) 配電網モニタリングシステム
RO134712A0 (ro) Sistem inteligent smart grid, metodă şi aparat pentru măsurarea şi monitorizarea on-line a pierderilor de putere şi energie în sistemele de transport şi distribuţie a energiei electrice
CN213424198U (zh) 一种基于NB-IoT通信技术的安全抄表
CN106197699A (zh) 一种变电站电力设备实时状态更新系统
JP2014155198A (ja) 通信装置、通信システム、電力メータおよびプログラム
CN112485513A (zh) 用户用电监控系统和方法

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 13827684

Country of ref document: EP

Kind code of ref document: A1

WWE Wipo information: entry into national phase

Ref document number: 14419482

Country of ref document: US

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 13827684

Country of ref document: EP

Kind code of ref document: A1