WO2013050569A2 - Verfahren und vorrichtung zum montieren eines rotors einer windenergieanlage - Google Patents
Verfahren und vorrichtung zum montieren eines rotors einer windenergieanlage Download PDFInfo
- Publication number
- WO2013050569A2 WO2013050569A2 PCT/EP2012/069785 EP2012069785W WO2013050569A2 WO 2013050569 A2 WO2013050569 A2 WO 2013050569A2 EP 2012069785 W EP2012069785 W EP 2012069785W WO 2013050569 A2 WO2013050569 A2 WO 2013050569A2
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- rotor
- lifting
- rotor blade
- blade
- hub
- Prior art date
Links
- 238000000034 method Methods 0.000 title claims abstract description 27
- 239000000725 suspension Substances 0.000 claims description 2
- 239000004237 Ponceau 6R Substances 0.000 description 3
- 238000009434 installation Methods 0.000 description 3
- 238000010276 construction Methods 0.000 description 2
- 238000004146 energy storage Methods 0.000 description 2
- 101100008048 Caenorhabditis elegans cut-4 gene Proteins 0.000 description 1
- 230000006978 adaptation Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000004091 panning Methods 0.000 description 1
- 230000007704 transition Effects 0.000 description 1
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D1/00—Wind motors with rotation axis substantially parallel to the air flow entering the rotor
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D1/00—Wind motors with rotation axis substantially parallel to the air flow entering the rotor
- F03D1/06—Rotors
- F03D1/065—Rotors characterised by their construction elements
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/108—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means for lifting parts of wind turbines
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D13/00—Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
- F03D13/10—Assembly of wind motors; Arrangements for erecting wind motors
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F05—INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
- F05B—INDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
- F05B2230/00—Manufacture
- F05B2230/60—Assembly methods
- F05B2230/61—Assembly methods using auxiliary equipment for lifting or holding
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/72—Wind turbines with rotation axis in wind direction
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/728—Onshore wind turbines
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P70/00—Climate change mitigation technologies in the production process for final industrial or consumer products
- Y02P70/50—Manufacturing or production processes characterised by the final manufactured product
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y10—TECHNICAL SUBJECTS COVERED BY FORMER USPC
- Y10T—TECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION
- Y10T29/00—Metal working
- Y10T29/37—Impeller making apparatus
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y10—TECHNICAL SUBJECTS COVERED BY FORMER USPC
- Y10T—TECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION
- Y10T29/00—Metal working
- Y10T29/49—Method of mechanical manufacture
- Y10T29/49316—Impeller making
- Y10T29/49332—Propeller making
Definitions
- the present invention relates to a lifting traverse for lifting and handling a rotor blade and a handling arrangement with lifting traverse and rotor blade for handling a rotor blade.
- the invention also relates to a transport device for transporting a lifting traverse, a method for mounting rotor blades, a method for mounting a rotor, a method for dismantling rotor blades and a method for exchanging rotor blades.
- Wind turbines are well known and a common type is a so-called horizontal axis wind turbine, as shown in Fig. 1.
- a horizontal axis wind energy plant or a wind energy plant with a horizontal axis rotor is understood as an arrangement with a horizontal rotor axis in contrast to a type with a vertical rotor axis. It is not important to exactly horizontal alignment of the rotor axis, but only the basic type of system should be designated.
- Conventional horizontal axis wind turbines today have three rotor blades on which the following invention is concentrated, without being limited thereto. Insofar as later versions only make sense in connection with a horizontal axis rotor with three rotor blades, it can accordingly be assumed that the rotor has three rotor blades.
- the rotor of an Enercon E126 wind turbine has a diameter of 126 m.
- To handle a rotor of this size is difficult and in particular makes high demands on the necessary crane.
- such a rotor also has an enormous mass and thus an enormous weight.
- a type E 126 wind energy plant owned by Enercon can have a shaft height of over 130 r, which is three times the height of the training ship Gorch Fock.
- the height in which a part to be mounted is to lift as well as its load very significantly determine the required crane and thus its cost.
- An additional height of a few meters can sometimes lead to a crane of the next larger class being needed.
- the cranes used to set up large, modern wind turbines such as the E 126 are among the largest mobile cranes available.
- a rotor blade is installed individually on a rotor hub already mounted on the nacelle, only the weight of this one rotor blade needs to be lifted accordingly.
- a rotor blade can be mounted vertically from below on a correspondingly oriented rotor hub. In a three-bladed rotor but then the two remaining positions for the other two rotor blades are in a high position. To install the two rotor blades, the respective rotor blade would thus have to be raised correspondingly high, ie higher than the rotor axis, or the rotor hub would have to be rotated.
- this rotation of the rotor hub with an installed rotor blade requires a correspondingly high force in order to lift the already installed rotor blade in one rotation.
- a rotation can be carried out by means of the generator during engine operation.
- a corresponding installation of the generator would be required in this early stage of construction, including a connection to the power grid, to be fed into later, to obtain energy for this engine operation.
- the generators would need to be powered and powered accordingly for this particular requirement.
- a lifting traverse according to claim 1 is proposed.
- Such a lifting beam is intended for lifting and handling a rotor blade. It has a crane attachment means, with which the lifting crossmember can be attached to a crane, in particular can be attached. Furthermore, at least one blade attachment means is provided, with which the lifting cross member can be fastened to the rotor blade or vice versa.
- the lifting traverse also has a longitudinal pivoting means, by means of which the rotor blade carried by the lifting traverse can be pivoted about a longitudinal axis of the rotor blade.
- the lifting traverse with this longitudinal pivoting means is designed so that it holds a rotor blade, for example, horizontally and thereby pivots or rotates in this horizontal position about the horizontal rotor blade axis.
- a transverse pivoting means is provided for pivoting the rotor blade carried by the lifting traverse about a transverse axis, which is formed transversely to the longitudinal axis. It does not depend on an exact 90 ° arrangement of the transverse axis to the longitudinal axis, but that the rotor blade can be pivoted by means of the transverse pivoting means in particular so that the longitudinal axis is changed, in particular raised or lowered.
- the longitudinal pivoting means and the transverse pivoting means are thus provided to exert two different pivoting movements of the rotor blade, which may have different purposes, as will be explained below.
- the longitudinal pivot means comprises an actuator for actively pivoting the rotor blade.
- the longitudinal pivoting means can thus actively exert a force, in particular by means of a motor and / or hydraulic drive, in particular to apply work in order to pivot the rotor blade about the longitudinal axis.
- the longitudinal pivoting means is formed at least by such an actuator and may have additional elements, in particular fastening elements.
- the transverse pivoting means is designed for passive pivoting and has a brake and additionally or alternatively a locking means or locking means for detecting or setting the lifting beam in at least two mutually different pivoting positions.
- the Querschwenksch does not have that extent via an actuator that can actively exercise a force, in particular work, but only by passive means that allow a corresponding panning and can lead. Accordingly, on the one hand, a corresponding pivot axis is realized and, on the other hand, a brake can brake or stop an otherwise caused pivotal movement. If a desired end position is reached, a corresponding setting means is proposed for setting, such as a prepared for temporary bolting locking means.
- a pivoting movement is caused by external forces, such as a weight, but guided by the transverse pivoting means, namely in particular with respect to the direction of movement and respect lent movement speed, including the ability to stop the pivotal movement.
- the transverse pivoting means is formed at least by a pivot joint which creates a corresponding pivot axis, and may comprise additional elements, in particular elements described for braking the pivoting movement or for fixing a pivoted position.
- the lifting cross member is characterized by an upper and a lower supporting frame section. The upper support frame section is to be connected to the crane and the lower support frame section is to be connected to the rotor blade.
- the transverse pivoting means is thereby prepared for carrying out a pivoting movement of the lower supporting frame section relative to the upper supporting frame section.
- a locking disc may be provided which is prepared for fixing different pivotal positions of the lower support frame portion relative to the upper support frame portion.
- a brake such as a jaw brake on the locking plate attack and thus achieve the braking or fixing the pivot position.
- the locking disk may have bores into which a bolt or pin for fixing a pivoting position can be inserted.
- the lifting traverse is characterized in that three sheet fastening means are provided and each having a carrying loop for releasably securing a rotor blade.
- each carrying loop is in particular intended to cooperate with a bolt, pin or similar counterpart on the rotor blade.
- a bolt or pin can be provided for each carrying strap, which is carried out by the carrying strap in order to hold the carrying loop and thereby establish a connection between the lifting traverse and the rotor blade.
- the longitudinal pivoting means preferably has a linear actuator, in particular a hydraulic cylinder for lifting and lowering one of the sheet fastening means.
- the linear actuator is disposed between the support loop of the corresponding one blade attachment means and the lower support frame portion.
- three attachment means are provided on the lifting crosshead and thus in use three attachment points on the rotor blade.
- the linear actuator cooperates with one of the three blade attachment means and can lift or lower a carrying loop and thus an attachment point.
- the fact that the other two attachment points - remain unchanged in position relative to the lower support frame portion of the lifting traverse - a pivotal movement of the rotor blade can be achieved by this linear actuator.
- Corresponding drive means may be arranged on the lifting crossmember.
- energy storage such as electrical energy storage when using an electric motor and / or a pressure accumulator may be provided when using a hydraulic cylinder and the control can be operated, for example, radio remote controlled by service personnel on the ground or in the crane.
- the crane attachment means comprise at least one suspension section, in particular a ring, an eye or a shackle for suspending the lifting cross member on the crane.
- a handling arrangement for handling a rotor blade of a wind energy plant is proposed. Part of this handling arrangement is a lifting traverse and the rotor blade temporarily attached thereto, as well as a release device for releasing the connection between the rotor blade and the lifting traverse.
- the connection between the lifting traverse and the rotor blade is achieved by means of at least one bolt, pin or similar element.
- the connection is made such that the lifting crosspiece has at least one loop or eyelet, in particular a plurality of loops or eyes, and the bolt extends through each loop or eyelet in order to thereby establish the connection.
- a release device for releasing the connection between the rotor blade and the lifting crossmember is provided.
- This release device has a traction means with which the pin or pin can be pulled out of the loop, thereby releasing the respective connection.
- This pulling device can thus be configured such that no persons, such as service employees or employees of the construction team, have to stop directly at the connection point. more an operation can be made remotely such as from the rotor hub out. For this purpose, a correspondingly long tug may be provided or it is another remote release or remote control provided.
- the rotor blade has an aerodynamic blade surface and an interior space disposed thereunder, the blade surface having at least one opening for passing a blade attachment means of the lifting beam, such as a mounting loop.
- the interior has a fastening section for fastening the sheet fastening means.
- this attachment portion may include the described pin or pin and provide for this pin axial guidance.
- the attachment portion is correspondingly located in proximity, in particular below the openings of the aerodynamic blade surface, such that the loops of the blade attachment means can extend through these openings directly to the respective attachment portion.
- a transport device for transporting a lifting crossmember has a transport frame, which has receiving sections adapted to the lifting crosspiece.
- at least one support frame receptacle for receiving the lower support frame portion is provided and / or there is provided an actuator receptacle for receiving the actuator of the Leksschwenkm itel.
- a method for mounting rotor blades according to claim 10 is also proposed. Accordingly, a rotor hub already mounted on the nacelle of the wind power plant or the wind energy plant to be erected is aligned in a first mounting position.
- the rotor hub is oriented to have a mounting flange for securing a first rotor blade in a transverse transverse position in which the first rotor blade can be attached thereto in a horizontal orientation.
- this attachment portion for fixing the first rotor blade is aligned in a so-called 3 o'clock or 9 o'clock position.
- the first rotor blade is then lifted by means of a crane and a lifting cross beam and arranged for attachment to the rotor hub at the fixing section aligned at 3 o'clock and 9 o'clock, respectively, and then fastened there.
- the rotor blade is hereby horizontally right aligned and thus corresponds to this first mounting position of the rotor hub.
- this first rotor blade is fastened to the rotor hub, namely in particular mounted, then this first rotor blade is lowered by means of the lifting beam fastened to the crane so that the rotor hub rotates into a second assembly position.
- This second mounting position is prepared to mount a second rotor blade also in the horizontal orientation of a rotor hub. Accordingly, the first rotor blade is lowered so that the rotor hub, if it is provided for a total of three rotor blades, rotates by 60 °. In this new position, the rotor hub is then fixed, in particular, bolted.
- At least one, usually a plurality of bolts are arranged in the transition region between the rotor hub and the nacelle so that the rotor hub can not continue to rotate.
- a corresponding device may be provided which can fix the rotor hub for other purposes such as maintenance purposes.
- the lowering of the first mounted rotor blade is preferably carried out in that the lifting crossmember can perform a corresponding pivoting movement transversely to the rotor blade longitudinal axis.
- the lifting beam does not need to actively exercise any movement, because the rotor blade can lower by its weight. However, the lifting traverse allows the pivoting movement and can lead this.
- the lifting crosspiece can be released from the first rotor blade and used to receive the second rotor blade.
- it is initially lowered so that the weight of the rotor blade no longer loads on the lifting crosshead, but is now basically completely absorbed by the rotor hub.
- a release device is then actuated, which in particular pulls out bolts or pins from carrying loops of the sheet attachment means of the lifting cross member, thereby releasing the connection between the lifting cross member and the rotor blade.
- Such a release can be carried out in an advantageous manner, without personnel having to stay in this area of the rotor blade. In particular, no holding basket is required there for corresponding persons.
- the second rotor blade is raised in a substantially horizontal orientation by means of the crane and the lifting crosspiece and arranged and fastened to the correspondingly aligned fastening portion of the rotor hub.
- the mounted in 3 o'clock position first rotor blade was accordingly on a Lowered 5 o'clock position so that now the second rotor blade is mounted in 9 o'clock position.
- the rotor hub is still fixed in this position and thus can be solved by attaching the second rotor blade, the lifting beam of the second rotor blade and removed.
- it is provided to rotate the rotor hub by about 180 ° about a vertical axis after the release of the lifting beam of the first rotor blade.
- the installation of the second rotor blade is simplified, because now the second rotor blade is lifted and mounted there, where the first rotor blade was lifted and mounted. Since the rotor hub protrudes from the tower, these two positions are not completely identical but very similar.
- the second rotor blade can be provided in the same way on the ground, for example with a transport vehicle.
- the third rotor blade For mounting the third rotor blade, it is proposed to first mount a ballast arm on the rotor hub, namely on the still free third attachment area provided for the third rotor blade. After mounting the second rotor blade, this third fastening region is initially in a so-called 1 o'clock position, ie in a position in which it points upwards and is rotated by only 30 ° from a position pointing vertically upwards. To mount a rotor blade, so the third rotor blade in this position, it would have to be lifted very far. This may require a very large crane and incur correspondingly high costs, which should be avoided.
- ballast arm on the third mounting area in the 1 o'clock position.
- This ballast arm has a mounting flange similar to a rotor blade, but is otherwise much shorter than a rotor blade and may have a kinking or bent shape from its mounting flange.
- the ballast arm is designed so that it can be installed with the least possible crane height.
- this ballast arm is designed so that it can be lifted directly to the crane without using a lifting cross-beam and possibly has a functionality or part of the functionality of a lifting cross-beam, for example, by allowing a rotary or pivoting movement.
- the ballast arm is mounted, fixing the rotor hub - which is also known as bolting - can be solved.
- the ballast arm can then be lowered by the crane into a 3 o'clock position of this third attachment area. In this third mounting position, the rotor hub is then fixed again - namely, bolted - and the ballast arm can be removed again.
- the third rotor blade is mounted in a horizontal orientation.
- the rotor hub can also be rotated 180 ° about a vertical axis, in particular after the assembly of the second rotor blade and before assembly of the ballast arm, or at least prior to assembly of the third rotor blade.
- the lifting crosspiece rotates the respective raised and mounted rotor blade about a longitudinal axis, namely about its rotor blade axis, around the rotor blade axis such that the rotor blade has the lowest possible wind resistance.
- This movement can preferably actively execute the lifting crosspiece by actuating an actuator of a longitudinal pivoting means.
- a hoisting truss according to at least one of the embodiments described above is used and / or a handling arrangement as described above is used.
- a method for mounting a rotor hub is also proposed.
- the rotor hub is mounted on the nacelle and then successively the rotor blades are successively mounted on the rotor hub. This mounting is accomplished by a method of mounting rotor blades as described above in accordance with at least one of the embodiments.
- a method for dismantling rotor blades is proposed, which basically corresponds to the described method for mounting rotor blades mutatis mutandis in reverse order. Accordingly, it is initially possible to remove a third rotor blade in a horizontal position, that is, for example, in the 3 o'clock position when the rotor hub is fixed. Then a ballast arm is mounted there, while still being held by the crane, while the fixing of the rotor hub is released. The ballast arm is then raised to a 1 o'clock position by means of the crane, so that the second rotor sheet takes a 9 o'clock position. In this position the rotor hub is fixed, the ballast arm removed and the second rotor blade dismantled.
- the ballast arm is then mounted in the 9 o'clock position and the rotor hub is then released again and rotated by the ballast arm so that the remaining rotor blade is in a 3 o'clock position.
- the rotor hub is then fixed and dismantled the last rotor blade.
- Fig. 1 shows a horizontal axis wind energy plant with three rotor blades installed.
- Fig. 2 shows schematically in a perspective view of a lifted lifting beam rotor blade.
- Fig. 3 shows the lifting beam with rotor blade of Fig. 2 with the rotor blade in a rotated about its rotor axis position.
- Fig. 4 shows a mounted on a transport frame lifting beam in a perspective view.
- Fig. 5 shows a section of an interior of a rotor blade with mounting portions in a perspective view.
- FIG. 1 shows a wind energy plant 100 with a tower 102 and a nacelle 104.
- a rotor 106 with three rotor blades 108 and a spinner 110 is arranged on the nacelle 104.
- the rotor 106 is set in rotation by the wind in rotation and thereby drives a generator in the nacelle 104 at.
- Fig. 2 shows a lifting beam 1, on which a rotor blade 2 is arranged and is lifted and held by the lifting beam 1.
- the representation is perspective and the rotor blade 2 is in a substantially horizontal orientation, relative to the rotor blade longitudinal axis.
- the lifting beam 1 has an upper supporting frame cut 4, for attaching to a crane.
- the lifting traverse is attached to a crane, which for the sake of simplicity is not shown in FIGS. 2 and 3.
- For attachment to the crane eyelets 6 are provided, which can also be referred to as Anpick.
- a lower support frame portion 8 is provided below the upper support frame portion 4 and approximately transversely thereto.
- the lower support frame section 8 can be pivoted relative to the upper support frame section 4, namely about an axis which is substantially transverse to the rotor blade longitudinal axis.
- a braking device 10 is provided, which may also be referred to as a locking device.
- three blade attachment means 12 are provided, which are provided for simplicity with the same reference numerals having elongated cables with round slings. These elongate cables are guided through openings 14 in the rotor blade surface 16 and have in the interior of the rotor blade 2 round slings for attachment.
- One of the blade attachment means 12 has a hydraulic cylinder 18 as an actuator in order to be able to actively change the relevant blade attachment means 12 in length. By such a change in length, the rotor blade 2 can be pivoted about its rotor blade axis.
- FIG. 3 shows such a position of the rotor blade 2 pivoted about the rotor blade longitudinal axis.
- the hydraulic cylinder 18 is contracted relative to the position of FIG. 2, whereby the corresponding blade attachment means 12 has shortened, whereby the pivoted or rotated position of FIG 3 was reached.
- the rotor blade 2 can be raised by means of a mounting crane and the lifting beam 2.
- the round loops of the blade attachment means 12 are connected to the rotor blade 2 by locking bolts.
- the hydraulic cylinder 18 the rotor blade 2 is rotated about the blade axis in order to provide as possible a small windage surface.
- the lifting beam 1 is prepared ready for transport on a transport frame 20 for transport on a vehicle.
- the lower support frame section 8 is pivotable relative to the upper support frame section 4 via a pivot joint 22.
- the brake device 10 comprises a brake disc 24 and a brake means 26 which engages the brake disc 24 and thereby can control the pivoting movement.
- the lower support frame section 8 has two blade attachment eyes 28, one of which can be seen and another is arranged behind the transport box 30. Both Blattbefest Trents Hampshire 28 are arranged on a longitudinal beam 32, which essentially forms the lower support frame section 8.
- the third sheet attachment means 12 is directly attached to the upper support frame portion 4, namely immediately below the cross member 34, which forms an integral part of the upper support frame portion 4.
- This attached to the cross member 34 blade attachment means 12 has the hydraulic cylinder 18, which is arranged here in a transport position.
- the sheet fastening means 12 additionally comprise ropes with round slings. These cables are shown in Figures 2 and 3, but can be transported separately during transport on the transport frame 20 and housed for example in the transport box 30.
- the attachment portions 50 are attached to internal structures such as stiffening ribs 52.
- the fastening sections each comprise two retaining walls 54, each of which has two bores 56 arranged in alignment. Another pair of bores 56 may be provided to change, for example, the attachment position. However, such a further bore pair of each fastening section 50 is not absolutely necessary.
- a bolt device 58 each with a pretensioned bolt 60, is provided.
- a pulling device such as a rope can be arranged to pull the bolt for releasing a retaining loop in the opening direction 62.
- Fig. 5 shows the opened state. In this state, a retaining loop between two holes 56 and thus between two retaining walls 54 are arranged.
- the prestressed bolt 60 is then pushed through in each case the corresponding two bores 56, in order thereby to receive the carrying loop arranged there.
- the bolt 60 are pulled in the opening direction 62 and a corresponding support loop would be released again.
- the lifting beam hangs on the crane hook of the assembly crane.
- the lifting beam is connected to the rotor blade by means of round slings and the rotor blade is lifted by means of the lifting beam.
- This guide cables can be attached to the lifting beam.
- the lifting beam is then raised further, so that the round slings are pulled out of the rotor blade.
- the proposed solution also makes it possible to use the lifting beam to lower or raise the rotor blade by a certain angle. After the rotor blade has been lowered, the carrier of the lifting traverse, which is rotatably or pivotally mounted, is held in its position by a braking device.
- the pickup points are unlocked and the crossbar is released from the rotor blade.
- the reduction of unit weights for the assembly crane can be achieved by the proposed solution.
- the use of cranes can be avoided and when lifting the rotor blades can be manipulated their orientation, at the same time only a crane hook is necessary.
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Sustainable Development (AREA)
- Sustainable Energy (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- General Engineering & Computer Science (AREA)
- Wind Motors (AREA)
Abstract
Description
Claims
Priority Applications (15)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
NZ622806A NZ622806B2 (en) | 2011-10-07 | 2012-10-05 | Method and device for mounting a rotor of a wind energy plant |
CA2848822A CA2848822C (en) | 2011-10-07 | 2012-10-05 | Method and device for mounting a rotor of a wind energy plant |
JP2014533930A JP5925323B2 (ja) | 2011-10-07 | 2012-10-05 | 風力発電プラントのロータ取り付け方法および装置 |
EP17153315.1A EP3211217B1 (de) | 2011-10-07 | 2012-10-05 | Verfahren und vorrichtung zum montieren eines rotors einer windenergieanlage |
BR112014008051A BR112014008051A2 (pt) | 2011-10-07 | 2012-10-05 | método e dispositivo para montar um rotor de uma instalação de energia eólica |
ES12778261.3T ES2689264T3 (es) | 2011-10-07 | 2012-10-05 | Procedimiento y dispositivo para el montaje de un rotor en una instalación de energía eólica |
US14/349,577 US10119519B2 (en) | 2011-10-07 | 2012-10-05 | Method and device for mounting a rotor of a wind energy plant |
AU2012320439A AU2012320439B2 (en) | 2011-10-07 | 2012-10-05 | Method and device for mounting a rotor of a wind energy plant |
DK12778261.3T DK2764237T3 (en) | 2011-10-07 | 2012-10-05 | Method and device for mounting a rotor of a wind power plant |
EP12778261.3A EP2764237B1 (de) | 2011-10-07 | 2012-10-05 | Verfahren und vorrichtung zum montieren eines rotors einer windenergieanlage |
MX2014003921A MX352537B (es) | 2011-10-07 | 2012-10-05 | Método y dispositivo para montar un rotor de una planta de energía eólica. |
RU2014117957/06A RU2600848C2 (ru) | 2011-10-07 | 2012-10-05 | Способ и устройство для монтажа ротора ветроэнергетической установки |
KR1020147012138A KR101671596B1 (ko) | 2011-10-07 | 2012-10-05 | 풍력 발전 설비의 로터 설치 방법 및 그 장치 |
CN201280049414.2A CN103987957B (zh) | 2011-10-07 | 2012-10-05 | 用于安装风能设备的转子的方法和设备 |
ZA2014/02089A ZA201402089B (en) | 2011-10-07 | 2014-03-24 | Method and device for mounting a rotor of a wind energy plant |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE102011084140A DE102011084140A1 (de) | 2011-10-07 | 2011-10-07 | Verfahren und Vorrichtung zum Montieren eines Rotors einer Windenergieanlage |
DE102011084140.7 | 2011-10-07 |
Publications (2)
Publication Number | Publication Date |
---|---|
WO2013050569A2 true WO2013050569A2 (de) | 2013-04-11 |
WO2013050569A3 WO2013050569A3 (de) | 2013-10-24 |
Family
ID=47076168
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/EP2012/069785 WO2013050569A2 (de) | 2011-10-07 | 2012-10-05 | Verfahren und vorrichtung zum montieren eines rotors einer windenergieanlage |
Country Status (19)
Country | Link |
---|---|
US (1) | US10119519B2 (de) |
EP (2) | EP3211217B1 (de) |
JP (1) | JP5925323B2 (de) |
KR (1) | KR101671596B1 (de) |
CN (1) | CN103987957B (de) |
AR (1) | AR088248A1 (de) |
AU (1) | AU2012320439B2 (de) |
BR (1) | BR112014008051A2 (de) |
CA (1) | CA2848822C (de) |
CL (1) | CL2014000839A1 (de) |
DE (1) | DE102011084140A1 (de) |
DK (2) | DK3211217T3 (de) |
ES (2) | ES2735201T3 (de) |
MX (1) | MX352537B (de) |
PT (2) | PT3211217T (de) |
RU (1) | RU2600848C2 (de) |
TW (1) | TWI576510B (de) |
WO (1) | WO2013050569A2 (de) |
ZA (1) | ZA201402089B (de) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2014202691A1 (de) * | 2013-06-21 | 2014-12-24 | Wobben Properties Gmbh | Verfahren zum montieren eines windenergieanlagen-rotorblattes sowie windenergieanlagen-rotorblatt |
EP2832676A1 (de) * | 2013-07-29 | 2015-02-04 | Siemens Aktiengesellschaft | Rotorblattgreifvorrichtung |
US9759074B2 (en) | 2011-06-03 | 2017-09-12 | Wobben Properties Gmbh | Wind turbine rotor blade and method for installing a wind turbine rotor blade |
Families Citing this family (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US10393091B2 (en) * | 2011-05-27 | 2019-08-27 | Vestas Wind Systems A/S | Apparatus for manipulating a wind turbine blade and method of blade handling |
DE202014101161U1 (de) | 2014-03-13 | 2015-06-16 | Ematec Manfred Eberhard Maschinen- Und Greiftechnik E.K. | Hebezeug |
DK178141B1 (en) * | 2014-06-03 | 2015-06-22 | Envision Energy | Wind turbine blade lifting device and a method for lifting a wind turbine blade |
DE102016200160A1 (de) | 2016-01-08 | 2017-07-13 | Wobben Properties Gmbh | Hebevorrichtung zum Heben einer Komponente einer Windenergieanlage und Verfahren zum Montieren von Komponenten einer Windenergieanlage |
DE102016110747A1 (de) | 2016-06-10 | 2017-12-14 | Wobben Properties Gmbh | Rotorblatt, Windenergieanlage sowie Verfahren zur Montage und zur Herstellung eines Rotorblattes |
DE102016111514A1 (de) * | 2016-06-23 | 2017-12-28 | Wobben Properties Gmbh | Verfahren zum Errichten einer Windenergieanlage und Hebetraverse zur Montage eines Rotorblatts einer Windenergieanlage |
CN106224170B (zh) * | 2016-07-21 | 2019-01-29 | 新疆金风科技股份有限公司 | 风力发电机组叶轮组对装置及叶轮组对方法 |
DE102016114717A1 (de) * | 2016-08-09 | 2018-02-15 | Wobben Properties Gmbh | Leuchtelement und Verfahren zur Beleuchtung eines Bauteils einer Windenergieanlage, sowie Bauteile für eine Windenergieanlage und Windenergieanlage |
CN110036198A (zh) * | 2016-11-11 | 2019-07-19 | 西门子歌美飒可再生能源公司 | 转子叶片组件 |
KR102176566B1 (ko) * | 2019-08-21 | 2020-11-09 | 두산중공업 주식회사 | 풍력 발전기의 블레이드 설치 장치 |
DK181535B1 (en) * | 2022-09-27 | 2024-04-10 | Danhydra As | Lifting yoke |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE20109835U1 (de) | 2001-06-15 | 2002-01-24 | Gerken Gmbh | Arbeitsbühne |
EP2003333A1 (de) | 2007-06-15 | 2008-12-17 | Siemens Aktiengesellschaft | Verfahren zur Montage von mindestens zwei Komponenten einer Windturbine und Verwendung einer Handhabungsvorrichtung |
DE102008033857A1 (de) | 2008-07-19 | 2010-01-21 | GEO Gesellschaft für Energie und Ökologie mbH | Vorrichtung zum Montieren der Rotorblätter einer Windenergieanlage |
DE202010003033U1 (de) | 2010-02-17 | 2010-05-27 | Nordex Energy Gmbh | Hebezeug zur Positionierung eines Rotorblatts einer Windenergieanlage |
DE10305543C5 (de) | 2003-02-10 | 2011-04-28 | Aloys Wobben | Verfahren zur Montage von Rotorblättern sowie ein Rotorblatt für eine Windenergieanlage |
Family Cites Families (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2050464C1 (ru) | 1991-12-20 | 1995-12-20 | Герман Алексеевич Чикин | Ветродвигатель |
DE4426351B4 (de) | 1994-07-25 | 2006-04-06 | Alstom | Brennkammer für eine Gasturbine |
EP1716334A1 (de) | 2004-01-26 | 2006-11-02 | Vestas Wind Systems A/S | Verfahren zur handhabung des rotorblatts einer windenergieanlage sowie vorrichtung hierzu |
US7000396B1 (en) * | 2004-09-02 | 2006-02-21 | General Electric Company | Concentric fixed dilution and variable bypass air injection for a combustor |
DK200501312A (da) | 2005-09-21 | 2007-03-22 | Lm Glasfiber As | Fastgörelsesanordninger på vinge |
JP4885073B2 (ja) | 2007-06-20 | 2012-02-29 | 三菱重工業株式会社 | 風車回転翼の吊下げ装置、風車回転翼の取付け方法、および風力発電装置の建設方法 |
JP4959439B2 (ja) | 2007-06-22 | 2012-06-20 | 三菱重工業株式会社 | 風力発電装置 |
DE102009005632B4 (de) * | 2009-01-21 | 2017-06-01 | Senvion Gmbh | Handhabung von Rotorblättern |
JP5246555B2 (ja) * | 2009-05-12 | 2013-07-24 | 日通商事株式会社 | 風力発電設備におけるブレードの吊上げ方法とその吊上げ装置 |
US8596700B2 (en) * | 2009-08-14 | 2013-12-03 | Mjt Holdings, Llc | Tower erection lift kit tools |
GB0920094D0 (en) | 2009-11-17 | 2009-12-30 | Alstom Technology Ltd | Reheat combustor for a gas turbine engine |
EP2385303A1 (de) * | 2010-05-03 | 2011-11-09 | Alstom Technology Ltd | Verbrennungsvorrichtung für eine Gasturbine |
DK2616671T3 (en) * | 2010-09-15 | 2017-09-25 | Vestas Wind Sys As | WINDMILL LIFTING STRUCTURES, LIFTING DEVICES AND METHODS FOR WING MANAGEMENT |
DE102011076937B3 (de) | 2011-06-03 | 2012-12-06 | Aloys Wobben | Windenergieanlagen-Rotorblatt und Verfahren zur Montage eines Windenergieanlagen-Rotorblattes |
-
2011
- 2011-10-07 DE DE102011084140A patent/DE102011084140A1/de not_active Withdrawn
-
2012
- 2012-10-05 CA CA2848822A patent/CA2848822C/en not_active Expired - Fee Related
- 2012-10-05 PT PT17153315T patent/PT3211217T/pt unknown
- 2012-10-05 KR KR1020147012138A patent/KR101671596B1/ko active IP Right Grant
- 2012-10-05 TW TW101137010A patent/TWI576510B/zh not_active IP Right Cessation
- 2012-10-05 PT PT12778261T patent/PT2764237T/pt unknown
- 2012-10-05 DK DK17153315.1T patent/DK3211217T3/da active
- 2012-10-05 AU AU2012320439A patent/AU2012320439B2/en not_active Ceased
- 2012-10-05 EP EP17153315.1A patent/EP3211217B1/de active Active
- 2012-10-05 RU RU2014117957/06A patent/RU2600848C2/ru not_active IP Right Cessation
- 2012-10-05 AR ARP120103718A patent/AR088248A1/es unknown
- 2012-10-05 BR BR112014008051A patent/BR112014008051A2/pt not_active Application Discontinuation
- 2012-10-05 CN CN201280049414.2A patent/CN103987957B/zh not_active Expired - Fee Related
- 2012-10-05 ES ES17153315T patent/ES2735201T3/es active Active
- 2012-10-05 JP JP2014533930A patent/JP5925323B2/ja not_active Expired - Fee Related
- 2012-10-05 DK DK12778261.3T patent/DK2764237T3/en active
- 2012-10-05 ES ES12778261.3T patent/ES2689264T3/es active Active
- 2012-10-05 US US14/349,577 patent/US10119519B2/en active Active
- 2012-10-05 WO PCT/EP2012/069785 patent/WO2013050569A2/de active Application Filing
- 2012-10-05 EP EP12778261.3A patent/EP2764237B1/de active Active
- 2012-10-05 MX MX2014003921A patent/MX352537B/es active IP Right Grant
-
2014
- 2014-03-24 ZA ZA2014/02089A patent/ZA201402089B/en unknown
- 2014-04-04 CL CL2014000839A patent/CL2014000839A1/es unknown
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE20109835U1 (de) | 2001-06-15 | 2002-01-24 | Gerken Gmbh | Arbeitsbühne |
DE10305543C5 (de) | 2003-02-10 | 2011-04-28 | Aloys Wobben | Verfahren zur Montage von Rotorblättern sowie ein Rotorblatt für eine Windenergieanlage |
EP2003333A1 (de) | 2007-06-15 | 2008-12-17 | Siemens Aktiengesellschaft | Verfahren zur Montage von mindestens zwei Komponenten einer Windturbine und Verwendung einer Handhabungsvorrichtung |
DE102008033857A1 (de) | 2008-07-19 | 2010-01-21 | GEO Gesellschaft für Energie und Ökologie mbH | Vorrichtung zum Montieren der Rotorblätter einer Windenergieanlage |
DE202010003033U1 (de) | 2010-02-17 | 2010-05-27 | Nordex Energy Gmbh | Hebezeug zur Positionierung eines Rotorblatts einer Windenergieanlage |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9759074B2 (en) | 2011-06-03 | 2017-09-12 | Wobben Properties Gmbh | Wind turbine rotor blade and method for installing a wind turbine rotor blade |
WO2014202691A1 (de) * | 2013-06-21 | 2014-12-24 | Wobben Properties Gmbh | Verfahren zum montieren eines windenergieanlagen-rotorblattes sowie windenergieanlagen-rotorblatt |
CN105324576A (zh) * | 2013-06-21 | 2016-02-10 | 乌本产权有限公司 | 用于安装风能设备转子叶片的方法以及风能设备转子叶片 |
JP2016522355A (ja) * | 2013-06-21 | 2016-07-28 | ヴォッベン プロパティーズ ゲーエムベーハーWobben Properties Gmbh | 風力発電装置ロータブレードの取付方法及び風力発電装置ロータブレード |
AU2014283275B2 (en) * | 2013-06-21 | 2017-03-30 | Wobben Properties Gmbh | Method for mounting a wind turbine rotor blade, and wind turbine rotor blade |
RU2635003C2 (ru) * | 2013-06-21 | 2017-11-08 | Воббен Пропертиз Гмбх | Способ монтажа лопасти ротора ветроэнергетической установки, а также лопасть ротора ветроэнергетической установки |
KR101815361B1 (ko) * | 2013-06-21 | 2018-01-30 | 보벤 프로퍼티즈 게엠베하 | 풍력 발전 설비용 로터 블레이드의 설치 방법, 그리고 풍력 발전 설비용 로터 블레이드 |
US9926907B2 (en) | 2013-06-21 | 2018-03-27 | Wobben Properties Gmbh | Method for mounting a wind turbine rotor blade, and wind turbine rotor blade |
EP2832676A1 (de) * | 2013-07-29 | 2015-02-04 | Siemens Aktiengesellschaft | Rotorblattgreifvorrichtung |
US9440821B2 (en) | 2013-07-29 | 2016-09-13 | Siemens Aktiengesellschaft | Blade gripping device with rectangular carrying structure |
Also Published As
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP2764237B1 (de) | Verfahren und vorrichtung zum montieren eines rotors einer windenergieanlage | |
EP2591228B1 (de) | Windenergieanlage und verfahren zur verstellung der rotordrehachse | |
EP2072812B1 (de) | Verfahren und Einrichtung zur Handhabung einer Rotornabe einer Windenergieanlage | |
DE60011737T3 (de) | Methode zum Montieren der Komponenten einer Windkraftanlage | |
EP2807107B1 (de) | Verfahren und vorrichtung zum montieren einer rotornabe einer windenergieanlage | |
EP2507514B1 (de) | Windenergieanlage mit hebevorrichtung | |
EP2723670B1 (de) | Lasthandhabungsvorrichtung zum anheben und verfahren zur montage von rotorblättern einer windenergieanlage | |
EP2702266B1 (de) | Windenergieanlage | |
WO2012152446A1 (de) | Turmdrehkran | |
EP3805553B1 (de) | Verfahren zur montage von rotorblättern einer windenergieanlage | |
WO2019096624A1 (de) | Flanschgestell und montageset zur vormontage und/oder zum transport und/oder zur montage eines turmsegments für eine windenergieanlage sowie verfahren | |
DE102009011478A1 (de) | Handhabungsvorrichtung für Rotorblattlager | |
DE102010016840A1 (de) | Montagevorrichtung | |
DE102016222211A1 (de) | Hebeanordnung | |
EP3942175B1 (de) | Verfahren zur montage von rotorblättern einer windenergieanlage | |
DE202011001850U1 (de) | Kran | |
WO2008009352A9 (de) | Anordnung einer hebeeinrichtung an einem rotorblatt einer windenergieanlage sowie verfahren | |
EP2377800B1 (de) | Verfahren zur Anordnung einer Anzeigeeinheit an einem Turmdrehkran | |
DE102022103727A1 (de) | Auslösevorrichtung für eine Hebekippvorrichtung zum Lösen der Hebekippvorrichtung von einem Generatorsegment, Hebekippvorrichtung zum Heben und Kippen eines Generatorsegments, Verfahren zum Heben und Kippen eines Generatorsegments, und Verfahren zur Montage einer Hebekippvorrichtung an einem demontierten Generatorsegment | |
EP3284947A1 (de) | Windenergieanlage und verfahren zur montage der windenergieanlage | |
DE202022105558U1 (de) | Manschette und Manschettenmontagevorrichtung | |
WO2024047070A1 (de) | Verfahren und kran zum aufbauen eines turms | |
WO2021104999A1 (de) | Kran mit wippbarer auslegerverlängerung sowie verfahren zur montage eines wippauslegers | |
WO2010079150A2 (de) | Verfahren zum vertikalen bewegen von lasten entlang einer windenergieanlage |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
ENP | Entry into the national phase |
Ref document number: 2848822 Country of ref document: CA |
|
WWE | Wipo information: entry into national phase |
Ref document number: MX/A/2014/003921 Country of ref document: MX |
|
WWE | Wipo information: entry into national phase |
Ref document number: 14349577 Country of ref document: US |
|
ENP | Entry into the national phase |
Ref document number: 2014533930 Country of ref document: JP Kind code of ref document: A |
|
WWE | Wipo information: entry into national phase |
Ref document number: 2014000839 Country of ref document: CL |
|
ENP | Entry into the national phase |
Ref document number: 2012320439 Country of ref document: AU Date of ref document: 20121005 Kind code of ref document: A |
|
WWE | Wipo information: entry into national phase |
Ref document number: 2012778261 Country of ref document: EP |
|
ENP | Entry into the national phase |
Ref document number: 20147012138 Country of ref document: KR Kind code of ref document: A |
|
ENP | Entry into the national phase |
Ref document number: 2014117957 Country of ref document: RU Kind code of ref document: A |
|
REG | Reference to national code |
Ref country code: BR Ref legal event code: B01A Ref document number: 112014008051 Country of ref document: BR |
|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 12778261 Country of ref document: EP Kind code of ref document: A2 |
|
ENP | Entry into the national phase |
Ref document number: 112014008051 Country of ref document: BR Kind code of ref document: A2 Effective date: 20140403 |