WO2012163266A1 - Method for discharging water from dam concrete placing area via concealed pipe - Google Patents

Method for discharging water from dam concrete placing area via concealed pipe Download PDF

Info

Publication number
WO2012163266A1
WO2012163266A1 PCT/CN2012/076188 CN2012076188W WO2012163266A1 WO 2012163266 A1 WO2012163266 A1 WO 2012163266A1 CN 2012076188 W CN2012076188 W CN 2012076188W WO 2012163266 A1 WO2012163266 A1 WO 2012163266A1
Authority
WO
WIPO (PCT)
Prior art keywords
dam
pipe
drainage
concrete
area
Prior art date
Application number
PCT/CN2012/076188
Other languages
French (fr)
Chinese (zh)
Inventor
戴志清
余英
孙昌忠
张开广
曹中升
韩炳兰
黄家权
林伟
Original Assignee
中国葛洲坝集团股份有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中国葛洲坝集团股份有限公司 filed Critical 中国葛洲坝集团股份有限公司
Publication of WO2012163266A1 publication Critical patent/WO2012163266A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages
    • E02B7/04Dams across valleys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Definitions

  • the invention relates to a water discharge method, in particular to a water culvert discharge method for a dam concrete warehouse area.
  • the large warehouse area requires a lot of manpower and material resources, and it takes a long time. These methods are labor-intensive and time-consuming. Very uneconomical.
  • the number of dam blocks is larger, the warehouse area is larger, and the water removal and discharge in the dam warehouse surface is very difficult. Frequently, due to improper arrangement, only the “displaced flow” disorder discharge method can be adopted.
  • the sewage is flooding everywhere, polluting the construction environment, and causing great interference to the subsequent processes. As a result, the dams are often repeatedly reclaimed when they are in the warehouse. Some of the water in the lower positions are extremely difficult to discharge, and the cost of disposal is very high.
  • the object of the present invention is to provide a method for discharging a water pipe of a dam concrete warehouse area, which adopts a three-dimensional drainage pipe network embedded in the concrete of the dam, and directs the water accumulated in each dam block to the drainage pipe through the drainage branch pipe, and then It is collected into the drainage supervisor, and finally concentrated to the water collection pit downstream of the dam, that is, dispersed drainage and concentrated discharge, which solves the problem of drainage of the concrete water in the dam concrete warehouse, and creates environmental conditions for dry construction of concrete pouring.
  • the quality of concrete pouring is guaranteed and construction disturbance is reduced.
  • the technical solution adopted by the present invention is: a method for discharging a water culvert of a dam concrete warehouse area, which is characterized by the following steps:
  • Step 1 Arrange the drainage supervisor in the predetermined area to connect the upstream and downstream of the dam;
  • Step 2 Drain the water supply pipe from the drainage main pipe to the left and right sides of the dam dam body, and connect the dam blocks in the area;
  • Step 3 Connect the vertical drainage branch pipe from the drainage pipe of each dam block to connect the concrete storage positions in the dam block.
  • the drainage main pipe is arranged along the river flow direction, gradually descending from the upstream of the dam to the downstream of the dam, the upstream nozzle is closed, and the downstream nozzle is led to the outside of the dam; the drainage branch is vertically arranged, and the drainage main pipe is inclined to be connected with the small inclination angle.
  • the drainage branch pipe is connected to the branch pipe and introduced into the adjacent corridor. After the completion of the project, cement mortar or thick cement slurry is used to block the buried drainage pipe network.
  • the drainage main pipe is installed in one position, and the drainage branch pipe is led layer by layer with the concrete pouring position.
  • the drain branch pipe outlet is beyond a certain height at the bottom of the discharge surface of the silo surface, and the steel mesh screen is spot welded at the top of the exposed nozzle.
  • the dam is divided into a plurality of dam blocks through longitudinal joints and transverse joints, and the drainage main pipe and the branch pipe wall in the two sides of the joint surface are wound with asphalt hemp.
  • the above-mentioned pre-buried drainage pipe network will continue to extend to all concrete pouring dams with the progress of concrete dam pouring, covering every new dam in the dam area.
  • the position of the concrete position is to be able to concentrate the accumulated water such as flushing water, rainwater and concrete bleeding in the construction of each dam block into the sump downstream of the dam, and then pump it out through the pump.
  • Concrete pouring creates environmental conditions for dry construction, which not only reduces construction disturbances, but also achieves civilized construction, and is also conducive to ensuring the quality of concrete pouring.
  • the drainage main pipe and the branch pipe are inclined to the exit side, and the characteristics of self-flow of accumulated water are beneficial to save a lot of manpower, material resources and energy.
  • the branch pipe is connected to the drainage branch pipe and introduced into the adjacent corridor. After the completion of the project, the cement drainage mortar or thick cement slurry is used to block the pre-buried drainage pipe network, so that the dam concrete forms a whole structure and avoids local artificial presence in the dam body.
  • the cavity is conducive to ensuring the design requirements of the overall force structure of the dam.
  • the drainage supervisor is installed once, which is convenient for quickly establishing the preliminary sewage system and putting it into operation as soon as possible; the purpose of the drainage branch pipe stratification is to timely discharge the water accumulated in each warehouse surface as the construction progresses.
  • the discharge branch pipe mouth is slightly higher than the receiving face, which can effectively prevent the pipe mouth from being buried in the concrete during the pouring and cutting process; the spot welding the steel mesh at the top of the pipe mouth can prevent the foreign matter from falling into the drainage branch pipe and causing the blockage phenomenon. .
  • the construction time of each dam is divided into several successive steps. After the concrete is solidified, the joint between the two adjacent dams will open and become larger. This tension may cause the pre-buried pipe spanning the seam surface to be cracked or even directly broken. Therefore, the drainage main pipe and the branch pipe in the range of 1 m on both sides of the seam surface may be lubricated to the outer wall of the pipe, thereby Prevent the embedded pipeline from cracking or even pulling off directly.
  • the method for discharging the underground pipe of the dam concrete warehouse area is as follows:
  • the branch pipe is connected to each position in the dam block layer by layer with the concrete pouring position.
  • the drainage main pipe, the drainage pipe and the drainage branch pipe can be selected from different sizes of steel pipes such as DN400, DN300 and DN200.
  • the drainage main pipe is arranged along the river direction, gradually descending from the upstream of the dam to the downstream of the dam, the upstream nozzle is closed, and the downstream nozzle leads to the sump outside the dam; the drainage branch is arranged perpendicular to the river direction with a small inclination
  • the drainage main pipe is inclined to be connected with it; the drainage branch pipe is vertically arranged, and the branch steel pipe is connected to the adjacent corridor to be used as a drainage pipe after the completion of the project.
  • the smaller angle of inclination is to achieve an angle of inclination that facilitates water flow.
  • the drainage supervisor shall be installed in place at one time, and the drainage branch pipe shall be led layer by layer with the concrete pouring position.
  • the drainage pipe on both sides of the drainage main pipe should be staggered to avoid the formation of cross joints; the drainage branch pipe mouth is beyond the discharge surface of the silo surface (before the concrete is poured and closed, the slope reserved within the diameter of about 2m around the nozzle is about 1: 2" "dish” type drainage pit) about 10cm at the bottom, spot welded steel mesh at the top of the exposed nozzle.
  • the drainage pipe is pre-buried inside the dam body, and a certain area is gradually formed until the three-dimensional drainage pipe network covering the entire dam.
  • the drainage main pipe is firstly installed in place according to the principle of gradually lowering from the upstream of the dam to the downstream of the dam; then the self-draining main pipe leads the drainage pipe to the left and right sides of the dam, connecting the dams in the area;
  • the vertical drainage branch pipe is connected from the drainage pipe of each dam block, and the concrete pouring position is led layer by layer to connect the concrete positions in the dam block.
  • the direction and inclination of the embedded pipeline are carefully arranged.
  • the water in the warehouse area flows into the drainage branch pipe from the drainage pit of the warehouse face, and then flows into the drainage main pipe of the drainage main pipe through the drainage branch pipe to realize the dispersed drainage and centralized discharge.
  • the method of the invention is used in the concrete pouring construction process of the dam, and the above-mentioned pre-buried drainage pipe network is continuously extended to all the concrete pouring dams with the progress of the concrete pouring of the dam, covering all the dam areas in an all-round way.
  • the newly-cast concrete position solves the drainage problem of large-area water accumulation in the concrete dam surface of the dam, which is conducive to ensuring the quality of concrete pouring.
  • the cement drainage mortar or thick cement slurry is used to block the pre-buried drainage pipe network, so that the dam concrete forms an overall structure, avoiding the existence of artificial “cavities” in the dam body, which is beneficial to ensure the design of the overall dam structure. Claim.

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Sewage (AREA)

Abstract

A method for discharging water from a dam concrete placing area via a concealed pipe, comprising: arranging a primary water discharge pipe in a predetermined area to communicate the upstream and the downstream of the dam; laying secondary pipes for water discharge from the main water discharge pipe to the left side and the right side of the dam body to communicate with each dam block in the area; and connecting vertical tertiary pipes for water discharge from the secondary water discharge pipes on each dam block to communicate with each concrete placing space in the dam block. By adopting the method for discharging water from the dam concrete placing area via the concealed pipe, during the concrete pouring construction process of the dam, the embedded water discharge pipe network extends and expands to all poured concrete dam blocks with the progression of the dam body concrete pouring, thereby completely covering each new concrete pouring space within the dam area, solving the problem of large-area water deposit on the dam concrete placing area, creating a dry construction environment for concrete pouring, ensuring concrete pouring quality, reducing construction interference, and achieving civilized construction.

Description

大坝混凝土仓面积水暗管排放方法  Dam concrete discharge bin area water pipe discharge method 技术领域Technical field
本发明涉及一种积水排放方法,特别是一种大坝混凝土仓面积水暗管排放方法。  The invention relates to a water discharge method, in particular to a water culvert discharge method for a dam concrete warehouse area.
背景技术Background technique
在混凝土大坝工程施工中,仓面冲洗、下雨、混凝土泌水等都会造成仓面积水,在仓面形成许多大小不一的“水坑”甚至“水塘”,导致不能及时覆盖新浇混凝土,既影响工程施工进度和混凝土浇筑质量,也影响现场的文明施工。因此,在混凝土浇筑前,需将这些积水排除干净。常用的清除仓面积水的方法主要有:使用小潜水泵抽水、人工使用扫帚扫除、人工舀水、采用棉纱或破布蘸除等,但这些方法都只适用于处理单个坝块的小范围内的积水,对于具有一定规模的大坝而言,由于坝块的数量很多,仓面面积大,需要投入大量的人力、物力,花费的时间也很长,这些方法既费工、费时,又很不经济。尤其是大型大坝工程,坝块的数量更多,仓面面积更大,大坝仓面内的积水清除、排放非常困难,经常因安排不当只能采取“放任自流”的无序排放方式,污水四处泛滥,污染施工作业环境,对后续工序干扰很大,造成各坝块备仓时往往重复进行积水处理,部分位于低处的仓位积水排放异常艰难,处理的成本很大。 In the construction of concrete dams, the flushing of the warehouse surface, the raining, the bleeding of the concrete, etc. will cause the water in the warehouse area, and many “water puddles” and even “water ponds” of different sizes will be formed on the warehouse surface, which will not cover the new watering in time. Concrete not only affects the construction progress and concrete pouring quality, but also affects the civilized construction of the site. Therefore, it is necessary to remove the accumulated water before the concrete is poured. Commonly used methods for clearing warehouse area water include: pumping with small submersible pumps, manually using broom sweeps, artificial drowning, using cotton yarn or rags, etc., but these methods are only suitable for processing small dams within a small range. For the dams with a certain scale, due to the large number of dams, the large warehouse area requires a lot of manpower and material resources, and it takes a long time. These methods are labor-intensive and time-consuming. Very uneconomical. Especially for large-scale dam projects, the number of dam blocks is larger, the warehouse area is larger, and the water removal and discharge in the dam warehouse surface is very difficult. Frequently, due to improper arrangement, only the “displaced flow” disorder discharge method can be adopted. The sewage is flooding everywhere, polluting the construction environment, and causing great interference to the subsequent processes. As a result, the dams are often repeatedly reclaimed when they are in the warehouse. Some of the water in the lower positions are extremely difficult to discharge, and the cost of disposal is very high.
发明内容Summary of the invention
本发明的目的是提供一种大坝混凝土仓面积水暗管排放方法,采用预埋在大坝混凝土内的立体排水管网,将每一坝块的积水通过排水支管引至排水分管,再汇集至排水主管,最后集中引排至大坝下游的集水坑处,即分散引流、集中排放,解决了大坝混凝土仓面积水的排水问题,给混凝土浇筑创造了干地施工的环境条件,保证了混凝土浇筑质量,减少了施工干扰。 The object of the present invention is to provide a method for discharging a water pipe of a dam concrete warehouse area, which adopts a three-dimensional drainage pipe network embedded in the concrete of the dam, and directs the water accumulated in each dam block to the drainage pipe through the drainage branch pipe, and then It is collected into the drainage supervisor, and finally concentrated to the water collection pit downstream of the dam, that is, dispersed drainage and concentrated discharge, which solves the problem of drainage of the concrete water in the dam concrete warehouse, and creates environmental conditions for dry construction of concrete pouring. The quality of concrete pouring is guaranteed and construction disturbance is reduced.
为解决上述技术问题,本发明采取的技术方案是:大坝混凝土仓面积水暗管排放方法,其特征在于由以下步骤组成:In order to solve the above technical problems, the technical solution adopted by the present invention is: a method for discharging a water culvert of a dam concrete warehouse area, which is characterized by the following steps:
步骤1:在预定区域布置排水主管,连通大坝上下游;Step 1: Arrange the drainage supervisor in the predetermined area to connect the upstream and downstream of the dam;
步骤2:从排水主管向大坝坝体左右两侧引排水分管,连通区域内各坝块;Step 2: Drain the water supply pipe from the drainage main pipe to the left and right sides of the dam dam body, and connect the dam blocks in the area;
步骤3:从各坝块的排水分管上接竖向排水支管,连通坝块内各混凝土仓位。Step 3: Connect the vertical drainage branch pipe from the drainage pipe of each dam block to connect the concrete storage positions in the dam block.
所述排水主管顺河流流向布置,从坝上游至坝下游逐渐走低,上游管口封闭,下游管口通向坝外;排水分管垂直主管布置,以较小的倾角倾向排水主管并与之连通。The drainage main pipe is arranged along the river flow direction, gradually descending from the upstream of the dam to the downstream of the dam, the upstream nozzle is closed, and the downstream nozzle is led to the outside of the dam; the drainage branch is vertically arranged, and the drainage main pipe is inclined to be connected with the small inclination angle.
所述排水支管上接分支管并引入近处的廊道,工程完工后采用水泥砂浆或浓水泥浆封堵预埋的排水管网。The drainage branch pipe is connected to the branch pipe and introduced into the adjacent corridor. After the completion of the project, cement mortar or thick cement slurry is used to block the buried drainage pipe network.
所述排水主管一次安装到位,排水支管随混凝土浇筑仓位逐层上引。The drainage main pipe is installed in one position, and the drainage branch pipe is led layer by layer with the concrete pouring position.
所述排水支管管口超出仓面排水坑底部一定高度,在外露的管口顶部点焊钢筋滤网。The drain branch pipe outlet is beyond a certain height at the bottom of the discharge surface of the silo surface, and the steel mesh screen is spot welded at the top of the exposed nozzle.
所述大坝通过纵缝、横缝分为多个坝块,缝面两侧范围内的排水主管、分管管壁缠绕沥青麻丝。The dam is divided into a plurality of dam blocks through longitudinal joints and transverse joints, and the drainage main pipe and the branch pipe wall in the two sides of the joint surface are wound with asphalt hemp.
本发明大坝混凝土仓面积水暗管排放方法的有益效果如下:The beneficial effects of the method for discharging the water pipe in the dam concrete warehouse area of the present invention are as follows:
1、在大坝混凝土浇筑施工过程中,上述预埋的排水管网随坝体混凝土的浇筑进展而不断延伸拓展至所有的混凝土浇筑坝块,全方位覆盖了大坝区域内的每一个新浇混凝土仓位,其作用是能够将每一坝块施工中的仓面冲洗水、雨水、混凝土泌水等积水集中引排到大坝下游的集水坑中,再通过水泵抽排出去,从而为混凝土浇筑创造了干地施工的环境条件,不仅减少了施工干扰,实现文明施工,也有利于保证混凝土的浇筑质量。1. During the dam concrete pouring construction process, the above-mentioned pre-buried drainage pipe network will continue to extend to all concrete pouring dams with the progress of concrete dam pouring, covering every new dam in the dam area. The position of the concrete position is to be able to concentrate the accumulated water such as flushing water, rainwater and concrete bleeding in the construction of each dam block into the sump downstream of the dam, and then pump it out through the pump. Concrete pouring creates environmental conditions for dry construction, which not only reduces construction disturbances, but also achieves civilized construction, and is also conducive to ensuring the quality of concrete pouring.
2、排水主管、分管均向出口侧倾斜,利用积水自流的特性,有利于节约大量的人力、物力和能源。在排水支管上接分支管并引入近处的廊道,工程完工后采用水泥砂浆或浓水泥浆封堵预埋的排水管网,使大坝混凝土形成整体结构,避免坝体内局部存在人为的“空腔”,有利于保证大坝整体受力结构的设计要求。2. The drainage main pipe and the branch pipe are inclined to the exit side, and the characteristics of self-flow of accumulated water are beneficial to save a lot of manpower, material resources and energy. The branch pipe is connected to the drainage branch pipe and introduced into the adjacent corridor. After the completion of the project, the cement drainage mortar or thick cement slurry is used to block the pre-buried drainage pipe network, so that the dam concrete forms a whole structure and avoids local artificial presence in the dam body. The cavity is conducive to ensuring the design requirements of the overall force structure of the dam.
3、排水主管一次安装完成,便于迅速建立初步的排污体系,并尽早投入运行;排水支管分层上引的目的在于随着施工的进展对每个仓面的积水及时引排。3. The drainage supervisor is installed once, which is convenient for quickly establishing the preliminary sewage system and putting it into operation as soon as possible; the purpose of the drainage branch pipe stratification is to timely discharge the water accumulated in each warehouse surface as the construction progresses.
4、排水支管管口较收仓面略高,可有效防止浇筑下料过程中将管口埋入混凝土内;管口顶部点焊钢筋滤网,可防止异物掉入排水支管内而造成堵塞现象。4. The discharge branch pipe mouth is slightly higher than the receiving face, which can effectively prevent the pipe mouth from being buried in the concrete during the pouring and cutting process; the spot welding the steel mesh at the top of the pipe mouth can prevent the foreign matter from falling into the drainage branch pipe and causing the blockage phenomenon. .
5、由于设计的纵缝、横缝将大坝分为若干坝块,各坝块的施工时间有先后之分,混凝土凝固后,两相邻坝块之间的分缝就会张开变大,这种张力有可能将跨过缝面的预埋管道拉裂甚至直接拉断,因此对缝面两侧各1米范围内的排水主管、分管缠绕沥青麻丝可以对管道外壁加以润滑,从而防止预埋管道拉裂甚至直接拉断。5. Because the longitudinal and transverse joints of the design divide the dam into several dams, the construction time of each dam is divided into several successive steps. After the concrete is solidified, the joint between the two adjacent dams will open and become larger. This tension may cause the pre-buried pipe spanning the seam surface to be cracked or even directly broken. Therefore, the drainage main pipe and the branch pipe in the range of 1 m on both sides of the seam surface may be lubricated to the outer wall of the pipe, thereby Prevent the embedded pipeline from cracking or even pulling off directly.
实施方式Implementation
大坝混凝土仓面积水暗管排放方法,步骤如下: The method for discharging the underground pipe of the dam concrete warehouse area is as follows:
1)、在大坝某区域布置排水主管连通大坝上下游;从排水主管上向坝体左右两侧引排水分管,连通区域内各坝块;从各坝块的排水分管上引竖向排水支管,并随混凝土浇筑仓位逐层上引连通坝块内各仓位。排水主管、排水分管和排水支管可视工程规模选用DN400、DN300、DN200等不同尺寸的钢管。1) Arrange the drainage main pipe to connect the upstream and downstream of the dam in a certain area of the dam; draw the drainage pipe from the drainage main pipe to the left and right sides of the dam body, connect the dam blocks in the area; and lead the vertical drainage from the drainage pipe of each dam block The branch pipe is connected to each position in the dam block layer by layer with the concrete pouring position. The drainage main pipe, the drainage pipe and the drainage branch pipe can be selected from different sizes of steel pipes such as DN400, DN300 and DN200.
2)、排水主管顺河流向布置,从坝上游至坝下游逐渐走低,上游管口封闭,下游管口通向坝外的集水坑处;排水分管垂直于河流向布置,以较小的倾角倾向排水主管并与之连通;排水支管竖向布置,并接分支钢管入近处的廊道,作为工程完工后封堵排水管用。 所述的较小的倾角为达到便于水流动的倾角。2) The drainage main pipe is arranged along the river direction, gradually descending from the upstream of the dam to the downstream of the dam, the upstream nozzle is closed, and the downstream nozzle leads to the sump outside the dam; the drainage branch is arranged perpendicular to the river direction with a small inclination The drainage main pipe is inclined to be connected with it; the drainage branch pipe is vertically arranged, and the branch steel pipe is connected to the adjacent corridor to be used as a drainage pipe after the completion of the project. The smaller angle of inclination is to achieve an angle of inclination that facilitates water flow.
3)、根据大坝浇筑分层情况,将排水主管一次布置安装到位,排水支管则随混凝土浇筑仓位逐层上引。3) According to the stratification of the dam, the drainage supervisor shall be installed in place at one time, and the drainage branch pipe shall be led layer by layer with the concrete pouring position.
4)、排水主管两侧排水分管需错开布置,避免形成十字接头;排水支管管口超出仓面排水坑(混凝土浇筑收仓前,在管口周围约2m直径范围内预留的坡度约1:2的“碟”型排水坑)底部10cm左右,在外露的管口顶部点焊钢筋滤网。4), the drainage pipe on both sides of the drainage main pipe should be staggered to avoid the formation of cross joints; the drainage branch pipe mouth is beyond the discharge surface of the silo surface (before the concrete is poured and closed, the slope reserved within the diameter of about 2m around the nozzle is about 1: 2" "dish" type drainage pit) about 10cm at the bottom, spot welded steel mesh at the top of the exposed nozzle.
5)、排水主管和分管过缝时,缝面两侧各1米范围内的管壁缠绕沥青麻丝;工程完工后,自坝体廊道内的分支管灌入水泥砂浆(或浓水泥浆)回填封堵排水管网。5) When the drainage main pipe and the branch pipe are over-seamed, the pipe wall within 1 m on both sides of the seam surface is wound with asphalt hemp; after the completion of the project, the branch pipe in the dam body gallery is filled with cement mortar (or thick cement slurry) Backfill and seal the drainage pipe network.
本发明的实施简要步骤:Brief steps of the implementation of the invention:
1)、分区域规划:1) Sub-regional planning:
在坝体内部预埋排水管路,逐渐形成某一区域直至覆盖整个大坝的立体排水管网。The drainage pipe is pre-buried inside the dam body, and a certain area is gradually formed until the three-dimensional drainage pipe network covering the entire dam.
2)、分阶段实施:2), phased implementation:
根据大坝浇筑分层情况,先将排水主管按从坝上游至坝下游逐渐走低的原则一次布置安装到位;再自排水主管向坝体左右两侧引排水分管,连通区域内各坝块;最后从各坝块的排水分管上接竖向排水支管,随混凝土浇筑仓位逐层上引,连通坝块内各混凝土仓位。According to the stratification of the dam, the drainage main pipe is firstly installed in place according to the principle of gradually lowering from the upstream of the dam to the downstream of the dam; then the self-draining main pipe leads the drainage pipe to the left and right sides of the dam, connecting the dams in the area; The vertical drainage branch pipe is connected from the drainage pipe of each dam block, and the concrete pouring position is led layer by layer to connect the concrete positions in the dam block.
3)、合理布置:3) Reasonable arrangement:
结合坝体结构特点细致安排预埋管路走向、倾角。According to the structural characteristics of the dam, the direction and inclination of the embedded pipeline are carefully arranged.
4)、有序引排:4), orderly arrangement:
仓面积水由仓面排水坑流入各排水支管,再经排水支管汇入排水主管排至坝外集水坑中,实现分散引流、集中排放。 The water in the warehouse area flows into the drainage branch pipe from the drainage pit of the warehouse face, and then flows into the drainage main pipe of the drainage main pipe through the drainage branch pipe to realize the dispersed drainage and centralized discharge.
工业实用性Industrial applicability
本发明的方法在大坝混凝土浇筑施工过程中,上述预埋的排水管网随坝体混凝土的浇筑进展而不断延伸拓展至所有的混凝土浇筑坝块,全方位覆盖了大坝区域内的每一个新浇混凝土仓位,解决了大坝混凝土仓面大面积积水的排水问题,有利于保证混凝土的浇筑质量。工程完工后采用水泥砂浆或浓水泥浆封堵预埋的排水管网,使大坝混凝土形成整体结构,避免坝体内局部存在人为的“空腔”,有利于保证大坝整体受力结构的设计要求。The method of the invention is used in the concrete pouring construction process of the dam, and the above-mentioned pre-buried drainage pipe network is continuously extended to all the concrete pouring dams with the progress of the concrete pouring of the dam, covering all the dam areas in an all-round way. The newly-cast concrete position solves the drainage problem of large-area water accumulation in the concrete dam surface of the dam, which is conducive to ensuring the quality of concrete pouring. After the completion of the project, the cement drainage mortar or thick cement slurry is used to block the pre-buried drainage pipe network, so that the dam concrete forms an overall structure, avoiding the existence of artificial “cavities” in the dam body, which is beneficial to ensure the design of the overall dam structure. Claim.

Claims (6)

  1. 大坝混凝土仓面积水暗管排放方法,其特征在于由以下步骤组成:The dam concrete warehouse area water pipe discharge method is characterized by the following steps:
    步骤1:在预定区域布置排水主管,连通大坝上下游;Step 1: Arrange the drainage supervisor in the predetermined area to connect the upstream and downstream of the dam;
    步骤2:从排水主管向大坝坝体左右两侧引排水分管,连通区域内各坝块;Step 2: Drain the water supply pipe from the drainage main pipe to the left and right sides of the dam dam body, and connect the dam blocks in the area;
    步骤3:从各坝块的排水分管上接竖向排水支管,连通坝块内各混凝土仓位。Step 3: Connect the vertical drainage branch pipe from the drainage pipe of each dam block to connect the concrete storage positions in the dam block.
  2. 根据权利要求1所述大坝混凝土仓面积水暗管排放方法,其特征在于:所述排水主管顺河流流向布置,从坝上游至坝下游逐渐走低,上游管口封闭,下游管口通向坝外;排水分管垂直主管布置,以较小的倾角倾向排水主管并与之连通。The dam concrete warehouse area water pipe discharging method according to claim 1, wherein the drainage main pipe is arranged along the river flow direction, gradually descending from the upstream of the dam to the downstream of the dam, the upstream pipe port is closed, and the downstream pipe port is led to the dam. Outside; the drainage branch is vertically oriented and tends to be connected to and connected to the drain main with a small angle of inclination.
  3. 根据权利要求1所述大坝混凝土仓面积水暗管排放方法,其特征在于:所述排水支管上接分支管并引入近处的廊道,工程完工后采用水泥砂浆或浓水泥浆封堵预埋的排水管网。The dam concrete warehouse area water pipe discharge method according to claim 1, wherein the drainage branch pipe is connected to the branch pipe and introduced into the adjacent corridor, and the cement mortar or the thick cement slurry is used to block the pre-construction after the completion of the project. Buried drainage pipe network.
  4. 根 据权利要求1或2或3所述大坝混凝土仓面积水暗管排放方法,其特征在于:所述排水主管一次安装到位,排水支管随混凝土浇筑仓位逐层上引。root The method according to claim 1 or 2 or 3, wherein the drainage main pipe is installed in one position, and the drainage branch pipe is led to the concrete pouring position.
  5. 根据权利要求1或2或3所述大坝混凝土仓面积水暗管排放方法,其特征在于:所述排水支管管口超出仓面排水坑底部一定高度,在外露的管口顶部点焊钢筋滤网。The method for discharging a dam concrete warehouse area water dark pipe according to claim 1 or 2 or 3, wherein the drain branch pipe mouth exceeds a certain height of the bottom of the tank face drainage pit, and the spot steel bar is welded at the top of the exposed pipe mouth. network.
  6. 根据权利要求1所述混凝土大坝混凝土仓面积水暗管排放方法,其特征在于:所述大坝通过纵缝、横缝分为多个坝块,缝面两侧范围内的排水主管、分管管壁缠绕沥青麻丝。The concrete dam area water pipe discharge method according to claim 1, wherein the dam is divided into a plurality of dam blocks through longitudinal joints and transverse joints, and drainage mains and pipes in the range of both sides of the joint surface. The pipe wall is wound with asphalt and hemp.
PCT/CN2012/076188 2011-05-30 2012-05-29 Method for discharging water from dam concrete placing area via concealed pipe WO2012163266A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN2011101407632A CN102287003B (en) 2011-05-30 2011-05-30 Dam concrete cabin surface water accumulation hidden pipe discharge method
CN201110140763.2 2011-05-30

Publications (1)

Publication Number Publication Date
WO2012163266A1 true WO2012163266A1 (en) 2012-12-06

Family

ID=45333733

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2012/076188 WO2012163266A1 (en) 2011-05-30 2012-05-29 Method for discharging water from dam concrete placing area via concealed pipe

Country Status (2)

Country Link
CN (1) CN102287003B (en)
WO (1) WO2012163266A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111733717A (en) * 2020-05-21 2020-10-02 中国市政工程中南设计研究总院有限公司 Method for perforating concrete box culvert and inspection well on wall plate without stopping production and steel formwork

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102287003B (en) * 2011-05-30 2013-06-26 中国葛洲坝集团股份有限公司 Dam concrete cabin surface water accumulation hidden pipe discharge method
CN105603932A (en) * 2016-02-15 2016-05-25 成都格瑞思文化传播有限公司 Rushing-proof water conservancy dam
CN107894721B (en) * 2017-12-20 2023-07-18 清华大学 Control system and method for arch dam transverse seam opening time

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2137417A1 (en) * 1971-07-27 1973-02-08 Gruen & Bilfinger Ag LAYING OF PIPES FOR DRAINING GROUNDWATER AND Leachate
US4820080A (en) * 1986-03-21 1989-04-11 Comporgan System House Process for the construction of a drain system
CN101429759A (en) * 2008-12-12 2009-05-13 中国葛洲坝集团股份有限公司 Inverse drainage processing method in high concrete panel rock-fill dam construction period
CN101575843A (en) * 2009-06-02 2009-11-11 广东水电二局股份有限公司 Roller compacted concrete dam and construction method thereof
CN201627258U (en) * 2010-04-15 2010-11-10 中国葛洲坝集团股份有限公司 Device for discharging water from storehouse surface during large-scale concrete construction
CN102287003A (en) * 2011-05-30 2011-12-21 中国葛洲坝集团股份有限公司 Dam concrete cabin surface water accumulation hidden pipe discharge method

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1117367A1 (en) * 1983-06-27 1984-10-07 Грузинский Ордена Трудового Красного Знамени Научно-Исследовательский Институт Энергетики И Гидротехнических Сооружений Dam
SU1372000A1 (en) * 1986-01-06 1988-02-07 Всесоюзный научно-исследовательский институт гидротехники им.Б.Е.Веденеева Earth-fill dam
CN201598619U (en) * 2010-01-22 2010-10-06 中国水电顾问集团华东勘测设计研究院 Dam body water draining structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2137417A1 (en) * 1971-07-27 1973-02-08 Gruen & Bilfinger Ag LAYING OF PIPES FOR DRAINING GROUNDWATER AND Leachate
US4820080A (en) * 1986-03-21 1989-04-11 Comporgan System House Process for the construction of a drain system
CN101429759A (en) * 2008-12-12 2009-05-13 中国葛洲坝集团股份有限公司 Inverse drainage processing method in high concrete panel rock-fill dam construction period
CN101575843A (en) * 2009-06-02 2009-11-11 广东水电二局股份有限公司 Roller compacted concrete dam and construction method thereof
CN201627258U (en) * 2010-04-15 2010-11-10 中国葛洲坝集团股份有限公司 Device for discharging water from storehouse surface during large-scale concrete construction
CN102287003A (en) * 2011-05-30 2011-12-21 中国葛洲坝集团股份有限公司 Dam concrete cabin surface water accumulation hidden pipe discharge method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111733717A (en) * 2020-05-21 2020-10-02 中国市政工程中南设计研究总院有限公司 Method for perforating concrete box culvert and inspection well on wall plate without stopping production and steel formwork
CN111733717B (en) * 2020-05-21 2021-09-10 中国市政工程中南设计研究总院有限公司 Method for perforating concrete box culvert and inspection well on wall plate without stopping production and steel formwork

Also Published As

Publication number Publication date
CN102287003A (en) 2011-12-21
CN102287003B (en) 2013-06-26

Similar Documents

Publication Publication Date Title
CN204000956U (en) A kind of basement bottom plate rear pouring tape structure
CN107859064B (en) Waterproof structure for connection of prefabricated pipe gallery and cast-in-situ pipe gallery and construction method
CN106193132B (en) Pressure relief anti-floating system for bottom plate of deep foundation pit high-water-level building and pressure relief anti-floating method thereof
CN109736340B (en) Dewatering device and method for guaranteeing integrity of cushion layer by reserving dewatering well on foundation slab
WO2012163266A1 (en) Method for discharging water from dam concrete placing area via concealed pipe
CN111519734B (en) Silt dredging method for river channel hidden culvert
CN111765318A (en) Pipeline flow guide structure for pipeline repair
CN201810345U (en) Sludge discharging system of mine sump
CN104846935A (en) High-position pool seepage treatment and transformation method
CN105696612A (en) Assembled foundation pit drainage and protection system suitable for industrial production
CN207260174U (en) Foundation pit drainage system
CN212956838U (en) Super high-rise construction floor water interception structure
CN209509149U (en) One kind can have enough to meet the need automatic adjustable regularization staircase and cut off the water supply high-altitude spray system
CN211368952U (en) Hidden rainwater collection device
CN210621879U (en) Steel construction vestibule drainage structures system
CN106193609A (en) High-rise concrete pump pipe tailing recycling and reusing system and method for recycling high-rise concrete pump pipe tailing
CN203756235U (en) Lateral drainage device of tunnel
CN206128648U (en) High -rise concrete pump pipe tails is retrieved and system of recycling
CN207194952U (en) A kind of flood mine working bottom plate is harnessed the river structure
CN106869301B (en) Old residential quarters septic tank cleaning method
CN112227395A (en) Well sealing device and method for large-water-pressure-drop well in building raft
CN207109987U (en) A kind of hondo formula closure works system
CN219909229U (en) Tailing pond drainage tower capable of tightly installing arch bars
CN205502045U (en) Drainage of assembled foundation ditch and protective system suitable for industrial production
CN104963383B (en) A kind of pressure conduit inverted siphon hydraulic automatism erosion and deposition device

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 12792308

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 12792308

Country of ref document: EP

Kind code of ref document: A1