CN201598619U - Dam body water draining structure - Google Patents

Dam body water draining structure Download PDF

Info

Publication number
CN201598619U
CN201598619U CN2010201026881U CN201020102688U CN201598619U CN 201598619 U CN201598619 U CN 201598619U CN 2010201026881 U CN2010201026881 U CN 2010201026881U CN 201020102688 U CN201020102688 U CN 201020102688U CN 201598619 U CN201598619 U CN 201598619U
Authority
CN
China
Prior art keywords
dam body
dam
water draining
elevation
rhone
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010201026881U
Other languages
Chinese (zh)
Inventor
王淡善
徐德芳
郑子祥
郑鹏翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hydrochina East China Engineering Corp
Original Assignee
Hydrochina East China Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hydrochina East China Engineering Corp filed Critical Hydrochina East China Engineering Corp
Priority to CN2010201026881U priority Critical patent/CN201598619U/en
Application granted granted Critical
Publication of CN201598619U publication Critical patent/CN201598619U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Building Environments (AREA)

Abstract

The utility model relates to a dam body water draining structure, aiming at providing a dam body water draining structure with simple and perfect structure and good water draining effect so as to achieve the purposes of reducing the hydraulic gradient generated by a curtain body and reducing uplift pressure of a dam. The technical scheme for solving the problems is as follows: the dam body water draining structure is provided with a dam body and internally provided with a basic gallery, and top part of the dam body is communicated with the basic gallery by water draining pipes which are vertically distributed. The dam body water draining structure is characterized in that a group of water draining holes which are distributed in a sector manner are drilled at the downstream side in the basic gallery; and the lowest height of the water draining hole is higher than the elevation of the basic gallery. The dam body water draining structure is mainly used for various dams.

Description

The dam body discharge structure
Technical field
The utility model relates to a kind of dam body discharge structure, mainly is applicable in the various dams.
Background technology
Along with the dam increase of service time, inevitably various seepages can appear, influence the safety of dam, therefore, in order to prevent dam generation seepage, mostly adopt on the engineering at present and earlier block up the method for afterwards arranging, reduce the probability of dam generation seepage, promptly carry out curtain grouting, arrange in the downstream that then drainage system carries out draining at the dam upstream side.The dam body drain hole generally adopts dam crest to be drilled with or the formation of pre-buried vertical drain at present, and is nearer as distance dam body curtain, then the curtain body produced bigger waterpower tonsure, thereby quickens the destruction of curtain, shortens the life-span of curtain.
Summary of the invention
The technical problems to be solved in the utility model is: provide a kind of perfect, dam body discharge structure that drainage effect is good simple in structure at the problem of above-mentioned existence, reduce waterpower tonsure that the curtain body produces and the purpose that reduces uplift pressure in the dam to reach.
The technical scheme that the utility model adopted is: the dam body discharge structure, has dam body, basic gallery is offered in its inside, the dam body top is communicated with basic gallery by the gutter of vertically arranging, it is characterized in that: be drilled with one group of drain hole that is fan-shaped distribution to the downstream in the described basic gallery, the lowest elevation of drain hole is higher than the elevation of basic gallery.
Described drain hole has 1-3 row, and the elevation angle is the 30-60 degree, and the distance between adjacent each drain hole of every row is 2-3m, and the diameter of drain hole is 110mm-150mm.
Described basic gallery below is drilled with the drainage channel that is communicated with the dam foundation and basic gallery, and the degree of depth that this drainage channel gos deep into the dam foundation is the 0.4-0.6 times of dam foundation curtain degree of depth.
Collector drain is offered in the inner close downstream of described dam body, and is drilled with one group of rhone that is fan-shaped distribution to upstream side in this collector drain, and the lowest elevation of rhone is higher than the elevation of collector drain.
Described rhone is established a row, the elevation angle 30 degree, and the distance between adjacent each rhone is 2.25m, aperture 130mm, and be that the several rows of water holes of 30 degree intersect and link to each other with the elevation angle.
The beneficial effects of the utility model are: the utility model is drilled with one group of drain hole that is fan-shaped distribution to the downstream in basic gallery, dam body percolating water is collected to basic gallery in the dam by fan-shaped drain hole, concentrate discharging, effectively reduce the dam body downstream seepage flow point height that goes out to escape, thereby reduced uplift pressure in the dam, especially at cold district, can effectively solve concrete freeze thawing, problem of frost heave that the dam body seepage causes.
Description of drawings
Fig. 1 is a profile of the present utility model.
The specific embodiment
As shown in Figure 1, present embodiment has dam body 1, basic gallery 2 is offered in its inside, dam body 1 top is communicated with basic gallery 2 by the gutter of vertically arranging 3, be drilled with one group of drain hole 4 that is fan-shaped distribution to the downstream in the described basic gallery 2, the lowest elevation of drain hole 4 is higher than the elevation of basic gallery 2.In this example, this group drain hole 4 has two rows, and wherein a row elevation angle is 30 degree, and another row elevation angle is 60 degree, and each distance of arranging between two adjacent drain holes 4 is 2.25m, and the diameter of drain hole 4 is 110mm.
Collector drain 5 is offered in described dam body 1 inner close downstream, and is drilled with one group of rhone 8 that is fan-shaped distribution to upstream side in this collector drain, and the lowest elevation of rhone 8 is higher than the elevation of collector drain 5.In this example, this group rhone 8 has a row, and its elevation angle is 30 degree, and the distance between adjacent each rhone 8 is 2.25m, and the diameter of rhone 8 is 130mm, and this group rhone 8 and the elevation angle also are 30 to spend and intersect with the several rows of water hole 4 of basic gallery 2 connections and link to each other.
The drainage channel 6 that a row is communicated with the dam foundation 7 and basic gallery 2 is established in described basic gallery 2 belows sidetracking downstream, in this example, the diameter of drainage channel 6 is 110mm, distance between adjacent each drainage channel 6 is 3m, the angle of this drainage channel and vertical direction is 30 degree and gos deep into the certain degree of depth of the dam foundation and (be generally the degree of depth of 0.4-0.6 times of dam foundation curtain, get the degree of depth of 0.5 times of dam foundation curtain in this example), make dam body, drain in dam foundation form complete drainage system.In actual use, need in basic gallery 2, arrange suction pump, in the water suction basis gallery 2 that infiltrates in the drainage channel 6, concentrate discharging.
During draining, most of percolating water is collected to basic gallery 2 by gutter 3, drain hole 4 and drainage channel 6 respectively, concentrates discharging, and fraction percolating water then is collected to collector drain 5 by rhone 8, concentrates discharging.

Claims (6)

1. dam body discharge structure, has dam body (1), basic gallery (2) is offered in its inside, dam body (1) top is communicated with basic gallery (2) by the gutter of vertically arranging (3), it is characterized in that: be drilled with one group of drain hole (4) that is fan-shaped distribution to the downstream in the described basic gallery (2), the lowest elevation of drain hole (4) is higher than the elevation of basic gallery (2).
2. dam body discharge structure according to claim 1 is characterized in that: described drain hole (4) has 1-3 row, and the elevation angle is the 30-60 degree, and the distance between adjacent each drain hole of every row (4) is 2-3m, and the diameter of drain hole (4) is 110mm-150mm.
3. dam body discharge structure according to claim 1 and 2, it is characterized in that: described basic gallery (2) below is drilled with the drainage channel (6) that is communicated with the dam foundation (7) and basic gallery (2), and the degree of depth that this drainage channel gos deep into the dam foundation is the 0.4-0.6 times of dam foundation curtain degree of depth.
4. dam body discharge structure according to claim 1 and 2, it is characterized in that: described dam body (1) is inner near offering collector drain (5) in the downstream, and in this collector drain, being drilled with one group of rhone (8) that is fan-shaped distribution to upstream side, the lowest elevation of rhone (8) is higher than the elevation of collector drain (5).
5. dam body discharge structure according to claim 3, it is characterized in that: described dam body (1) is inner near offering collector drain (5) in the downstream, and in this collector drain, being drilled with one group of rhone (8) that is fan-shaped distribution to upstream side, the lowest elevation of rhone (8) is higher than the elevation of collector drain (5).
6. dam body discharge structure according to claim 4, it is characterized in that: described rhone (8) is established a row, the elevation angle 30 degree, and the distance between adjacent each rhone (8) is 2.25m, aperture 130mm, and be that the several rows of water holes (4) of 30 degree intersect and link to each other with the elevation angle.
CN2010201026881U 2010-01-22 2010-01-22 Dam body water draining structure Expired - Fee Related CN201598619U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010201026881U CN201598619U (en) 2010-01-22 2010-01-22 Dam body water draining structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010201026881U CN201598619U (en) 2010-01-22 2010-01-22 Dam body water draining structure

Publications (1)

Publication Number Publication Date
CN201598619U true CN201598619U (en) 2010-10-06

Family

ID=42809669

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010201026881U Expired - Fee Related CN201598619U (en) 2010-01-22 2010-01-22 Dam body water draining structure

Country Status (1)

Country Link
CN (1) CN201598619U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102287003A (en) * 2011-05-30 2011-12-21 中国葛洲坝集团股份有限公司 Dam concrete cabin surface water accumulation hidden pipe discharge method
CN102776894A (en) * 2012-08-28 2012-11-14 中国水电顾问集团中南勘测设计研究院 Dam foundation uplift pressure regulation device
CN104790422A (en) * 2015-05-05 2015-07-22 中国电建集团中南勘测设计研究院有限公司 Control system for dam foundation stratum uplift deformation
CN109555087A (en) * 2019-01-04 2019-04-02 长江勘测规划设计研究有限责任公司 The two dam structures and its application method of runtime not pump drainage turn(a)round interim pump drainage

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102287003A (en) * 2011-05-30 2011-12-21 中国葛洲坝集团股份有限公司 Dam concrete cabin surface water accumulation hidden pipe discharge method
CN102287003B (en) * 2011-05-30 2013-06-26 中国葛洲坝集团股份有限公司 Dam concrete cabin surface water accumulation hidden pipe discharge method
CN102776894A (en) * 2012-08-28 2012-11-14 中国水电顾问集团中南勘测设计研究院 Dam foundation uplift pressure regulation device
CN104790422A (en) * 2015-05-05 2015-07-22 中国电建集团中南勘测设计研究院有限公司 Control system for dam foundation stratum uplift deformation
CN104790422B (en) * 2015-05-05 2017-05-10 中国电建集团中南勘测设计研究院有限公司 Control system for dam foundation stratum uplift deformation
CN109555087A (en) * 2019-01-04 2019-04-02 长江勘测规划设计研究有限责任公司 The two dam structures and its application method of runtime not pump drainage turn(a)round interim pump drainage
CN109555087B (en) * 2019-01-04 2024-04-12 长江勘测规划设计研究有限责任公司 Two-way dam structure with temporary pumping and draining function in non-pumping and draining maintenance period in operation period and application method of two-way dam structure

Similar Documents

Publication Publication Date Title
CN104480974B (en) Reverse seepage drain system suitable for upstream type tailings pond and upstream type tailings pond
CN206233951U (en) Depressurize drainage system in a kind of high-speed railway double track tunnel base
CN201598619U (en) Dam body water draining structure
CN102966082A (en) Aeration facility with downward-bent base slab
CN109267549A (en) A kind of diversion tunnel structure
CN102535491A (en) Embedded water permeable plate water collection siphon drainage method for side slope ground water interception
CN104652383A (en) Tailings pond dam body free draining device
CN203768881U (en) Water seepage draining device for corridors of mountain and dam body
CN204326026U (en) A kind of multi-stage telescopic steel dam
CN206233950U (en) Depressurize drainage system in a kind of high-speed railway single-track tunnel base
CN203530921U (en) Water-permeable pile foundation spur dike
CN103614986B (en) It a kind of is applicable to the pressure free current inlet method that Tailings Dam drains off floodwaters
CN107503330A (en) It is weak in hole to there is pressure is prominent to fall expansion type jet stiling basin energy-dissipating system
CN210122706U (en) Check dam structure of hydraulic and hydroelectric engineering
CN209194485U (en) A kind of diversion tunnel structure
CN209724412U (en) A kind of tunnel drainage system in inrush during tunneling
CN207436077U (en) A kind of drainage of foundation pit structure
CN207295638U (en) The draining deep layer tunnel of small flow channel is set
CN206655300U (en) A kind of new combined seeping water discharging device
CN206721905U (en) A kind of annular subregion waterpower is broken ground grooving apparatus
RU165960U1 (en) FILL DEVICE WITH COOLING SYSTEM
CN219973102U (en) Gravity dam foundation drainage device is strengthened
CN203429777U (en) Water distribution unit
CN203729261U (en) Floating type self-adjustment water stopping dam
CN205100354U (en) Side slope with escape canal

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20101006

Termination date: 20190122

CF01 Termination of patent right due to non-payment of annual fee