WO2011160625A3 - Method for rehabilitating a track system having a ballast bed - Google Patents
Method for rehabilitating a track system having a ballast bed Download PDFInfo
- Publication number
- WO2011160625A3 WO2011160625A3 PCT/DE2011/075142 DE2011075142W WO2011160625A3 WO 2011160625 A3 WO2011160625 A3 WO 2011160625A3 DE 2011075142 W DE2011075142 W DE 2011075142W WO 2011160625 A3 WO2011160625 A3 WO 2011160625A3
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- track
- ballast
- ballast bed
- rehabilitating
- substructure
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B1/00—Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
- E01B1/001—Track with ballast
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B27/00—Placing, renewing, working, cleaning, or taking-up the ballast, with or without concurrent work on the track; Devices therefor; Packing sleepers
- E01B27/06—Renewing or cleaning the ballast in situ, with or without concurrent work on the track
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B29/00—Laying, rebuilding, or taking-up tracks; Tools or machines therefor
- E01B29/005—Making of concrete parts of the track in situ
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Machines For Laying And Maintaining Railways (AREA)
- Railway Tracks (AREA)
Abstract
The invention relates to a method for rehabilitating a track system (01), which comprises a substructure (02) and a superstructure (03) lying on the substructure. The superstructure has a ballast bed (04) and a track (06) arranged on the ballast bed. The track comprises rails (08), which are fastened in the track direction on crossties (07) arranged perpendicularly to the track direction. In the method, ballast stones (05) of the ballast bed (04) are at least partially removed and put back in. The method comprises the following method steps: removing the ballast, ramming supports (09) into the existing substructure (02) next to the rails (08) and at a distance from each other in the track direction, arranging formwork elements (11) against the supports (09), reinstalling the ballast between the formwork elements (11), and reestablishing the desired position of the track (06) according to the track position and track direction.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE102010030334.8 | 2010-06-22 | ||
DE102010030334A DE102010030334A1 (en) | 2010-06-22 | 2010-06-22 | Method for rehabilitating a track system with a ballast bed |
Publications (2)
Publication Number | Publication Date |
---|---|
WO2011160625A2 WO2011160625A2 (en) | 2011-12-29 |
WO2011160625A3 true WO2011160625A3 (en) | 2012-04-05 |
Family
ID=44946926
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/DE2011/075142 WO2011160625A2 (en) | 2010-06-22 | 2011-06-20 | Method for rehabilitating a track system having a ballast bed |
Country Status (2)
Country | Link |
---|---|
DE (1) | DE102010030334A1 (en) |
WO (1) | WO2011160625A2 (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE202012101947U1 (en) | 2012-03-30 | 2012-09-19 | Sächsische Bau GmbH | Device for track lengthening |
IT201800006889A1 (en) * | 2018-07-03 | 2020-01-03 | EQUIPMENT AND METHOD FOR THE RESTORATION OF THE BASE OF A RAILWAY LINE |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0237519A1 (en) * | 1986-03-07 | 1987-09-16 | Gerhard Dipl.-Ing. Dr. Schwarz | Noise protection device for multiple-track railway stretches |
DE4104683A1 (en) * | 1991-02-15 | 1992-08-20 | Wayss & Freytag Ag | Rail road bed - uses liq. mortar to form a plate in upper section of the ballast, with structured ballast particles to prevent downwards dispersion |
DE4429248A1 (en) * | 1993-08-24 | 1995-03-02 | Hermann Claus | Method for producing or renewing a side path running along a railway embankment |
DE29712802U1 (en) * | 1997-07-19 | 1997-09-25 | Ibb Ingenieur-, Brücken- und Tiefbau GmbH, 01159 Dresden | Ballast bracket |
DE10235063A1 (en) * | 2002-07-31 | 2004-02-19 | Kipper, René, Dipl.-Ing.(FH) | Optimization of sheet pile walls for central core structure for railway tracks with sheet pile walls set at greater depths or shortened, and left in track bed for extra support |
JP2005068904A (en) * | 2003-08-27 | 2005-03-17 | Aren:Kk | Labor-saving track constructing sheet and construction method |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE4100881A1 (en) | 1991-01-14 | 1992-07-16 | Cronau Heinrich Gmbh | Permanent way for railway high speed trains - consists of precast concrete trough sections laid end on end and filled with ballast bed |
DE4138068C2 (en) | 1991-11-19 | 1995-08-17 | Deutsche Asphalt Gmbh | Process for the solidification of structures made of pourable materials |
JPH09268501A (en) * | 1996-04-02 | 1997-10-14 | Mitsubishi Heavy Ind Ltd | Labor-saving track and construction method therefor |
DE19741020A1 (en) | 1997-09-18 | 1999-04-08 | Georg Groetz | Track system for rail-bound vehicles |
DE10261641A1 (en) | 2002-12-27 | 2004-07-08 | Max Bögl Bauunternehmung GmbH & Co. KG | Method of making a slab track and track |
DE102005055575B4 (en) | 2005-11-18 | 2016-10-06 | Rail.One Gmbh | Roadway for rail vehicles and method for their production |
DE102008016953A1 (en) | 2008-04-01 | 2009-10-08 | Railone Gmbh | Fixed carriageway for rail vehicles |
-
2010
- 2010-06-22 DE DE102010030334A patent/DE102010030334A1/en not_active Ceased
-
2011
- 2011-06-20 WO PCT/DE2011/075142 patent/WO2011160625A2/en active Application Filing
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0237519A1 (en) * | 1986-03-07 | 1987-09-16 | Gerhard Dipl.-Ing. Dr. Schwarz | Noise protection device for multiple-track railway stretches |
DE4104683A1 (en) * | 1991-02-15 | 1992-08-20 | Wayss & Freytag Ag | Rail road bed - uses liq. mortar to form a plate in upper section of the ballast, with structured ballast particles to prevent downwards dispersion |
DE4429248A1 (en) * | 1993-08-24 | 1995-03-02 | Hermann Claus | Method for producing or renewing a side path running along a railway embankment |
DE29712802U1 (en) * | 1997-07-19 | 1997-09-25 | Ibb Ingenieur-, Brücken- und Tiefbau GmbH, 01159 Dresden | Ballast bracket |
DE10235063A1 (en) * | 2002-07-31 | 2004-02-19 | Kipper, René, Dipl.-Ing.(FH) | Optimization of sheet pile walls for central core structure for railway tracks with sheet pile walls set at greater depths or shortened, and left in track bed for extra support |
JP2005068904A (en) * | 2003-08-27 | 2005-03-17 | Aren:Kk | Labor-saving track constructing sheet and construction method |
Also Published As
Publication number | Publication date |
---|---|
DE102010030334A1 (en) | 2011-12-22 |
WO2011160625A2 (en) | 2011-12-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
TW200718830A (en) | Fixed carriageway for rail vehicles | |
DK2740842T3 (en) | Method of converting a ballast track to a fixed track | |
ZA200607487B (en) | Turnout/crossover section for railway track | |
EA201590938A1 (en) | RAIL TRANSPORT SYSTEM FOR THE TRUCK MACHINE | |
BR112013016308A2 (en) | method for producing a slab railway | |
GB201210435D0 (en) | System and method for railroad track tie plate collection from a rail bed | |
IL284085A (en) | Recess structure for reinforcing connection between railway sleeper and track bed, and construction method | |
IL183803A0 (en) | Concrete carriageway for rail vehicles | |
ZA200906047B (en) | Concrete sleeper and method for producing the same | |
PT1869253E (en) | Solid railway for track vehicles, and method for the production thereof | |
ZA200904763B (en) | Movable continuous conveyor and method for operating a movable continuous conveyor | |
EP1785333A4 (en) | Track rail maintenance system and track rail maintenance method | |
PL1607523T3 (en) | A machine for exchanging damaged ties of a railroad track. | |
WO2011160625A3 (en) | Method for rehabilitating a track system having a ballast bed | |
EP2233638A3 (en) | Machine for positioning and squaring crossties of railway tracks | |
DE502005008352D1 (en) | ||
GB0522712D0 (en) | Method of laying a plurality of railway sleepers | |
MX2010007031A (en) | Method for the installation of railway tracks on ballast, without an auxiliary track. | |
RU2010118262A (en) | METHOD FOR INSTALLING ADJUSTMENTS OF INTERMEDIATE SUPPORTS AND SPAN STRUCTURES OF RAILWAY BRIDGE | |
US11124923B2 (en) | Method and track-building machine for renewing sleepers of a track formed from rails and the sleepers | |
SI1718802T1 (en) | Double cross sleeper for a ballasted track | |
ATE435334T1 (en) | METHOD FOR CONSTRUCTING A RAIL TRACK FOR RAILWAYS AND THE LIKE. AND A RAILWAY BUILT BY THIS METHOD | |
ATE469268T1 (en) | REPORTING THRESHOLD | |
JP5843743B2 (en) | Track cant change method | |
GB2420142B (en) | Method of installing or repairing railway rail track |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
122 | Ep: pct application non-entry in european phase |
Ref document number: 11782028 Country of ref document: EP Kind code of ref document: A2 |