US20070289966A1 - Liquid vessel liner and method of application - Google Patents
Liquid vessel liner and method of application Download PDFInfo
- Publication number
- US20070289966A1 US20070289966A1 US11/454,648 US45464806A US2007289966A1 US 20070289966 A1 US20070289966 A1 US 20070289966A1 US 45464806 A US45464806 A US 45464806A US 2007289966 A1 US2007289966 A1 US 2007289966A1
- Authority
- US
- United States
- Prior art keywords
- basin
- barrier coating
- liner
- coating
- panels
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C1/00—Pressure vessels, e.g. gas cylinder, gas tank, replaceable cartridge
- F17C1/02—Pressure vessels, e.g. gas cylinder, gas tank, replaceable cartridge involving reinforcing arrangements
- F17C1/04—Protecting sheathings
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B05—SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
- B05D—PROCESSES FOR APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
- B05D1/00—Processes for applying liquids or other fluent materials
- B05D1/02—Processes for applying liquids or other fluent materials performed by spraying
- B05D1/04—Processes for applying liquids or other fluent materials performed by spraying involving the use of an electrostatic field
- B05D1/06—Applying particulate materials
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B05—SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
- B05D—PROCESSES FOR APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
- B05D7/00—Processes, other than flocking, specially adapted for applying liquids or other fluent materials to particular surfaces or for applying particular liquids or other fluent materials
- B05D7/14—Processes, other than flocking, specially adapted for applying liquids or other fluent materials to particular surfaces or for applying particular liquids or other fluent materials to metal, e.g. car bodies
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B05—SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
- B05D—PROCESSES FOR APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
- B05D7/00—Processes, other than flocking, specially adapted for applying liquids or other fluent materials to particular surfaces or for applying particular liquids or other fluent materials
- B05D7/50—Multilayers
- B05D7/52—Two layers
- B05D7/54—No clear coat specified
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C1/00—Pressure vessels, e.g. gas cylinder, gas tank, replaceable cartridge
- F17C1/16—Pressure vessels, e.g. gas cylinder, gas tank, replaceable cartridge constructed of plastics materials
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24H—FLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
- F24H1/00—Water heaters, e.g. boilers, continuous-flow heaters or water-storage heaters
- F24H1/18—Water-storage heaters
- F24H1/181—Construction of the tank
- F24H1/183—Inner linings
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B05—SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
- B05D—PROCESSES FOR APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
- B05D7/00—Processes, other than flocking, specially adapted for applying liquids or other fluent materials to particular surfaces or for applying particular liquids or other fluent materials
- B05D7/22—Processes, other than flocking, specially adapted for applying liquids or other fluent materials to particular surfaces or for applying particular liquids or other fluent materials to internal surfaces, e.g. of tubes
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F28—HEAT EXCHANGE IN GENERAL
- F28F—DETAILS OF HEAT-EXCHANGE AND HEAT-TRANSFER APPARATUS, OF GENERAL APPLICATION
- F28F25/00—Component parts of trickle coolers
- F28F2025/005—Liquid collection; Liquid treatment; Liquid recirculation; Addition of make-up liquid
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y10—TECHNICAL SUBJECTS COVERED BY FORMER USPC
- Y10T—TECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION
- Y10T29/00—Metal working
- Y10T29/49—Method of mechanical manufacture
- Y10T29/49826—Assembling or joining
- Y10T29/49885—Assembling or joining with coating before or during assembling
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y10—TECHNICAL SUBJECTS COVERED BY FORMER USPC
- Y10T—TECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION
- Y10T29/00—Metal working
- Y10T29/49—Method of mechanical manufacture
- Y10T29/4998—Combined manufacture including applying or shaping of fluent material
Definitions
- the present invention relates to liners bonded to liquid containing metal structures and the method of applying and bonding the liner.
- Liquid holding structures such as cooling towers, evaporative condensers, and other evaporative systems for cooling or condensing and holding evaporative liquid are subjected to great mechanical stresses and exposure to corrosive environments. Chemicals used in the water to control water chemistries and to prevent biological growth can also work against the metal structure sections to promote corrosion unless carefully monitored. Such structures are usually made of treated steel, stainless steel, or plastic to protect the basin from corrosion. Plastic or polymer structures may be made from FRP or Polypropylene or similar materials. Fasteners are used to attach the panels together. The seams between the panels are usually sealed separately to give added protection to these areas. These metal structures are more likely to leak at or around the seams.
- the fasteners are positioned and inserted to seal the seams as well as hold the panels together.
- the fasteners may need a fastener hole formed in the aligned flanges.
- Stainless steel panels can be fastened together with to form the basin or vessel having good corrosion protection to some chemicals.
- most metal vessels also have square corners and joints making vessel cleaning difficult and drainage an issue as water can pool in a corner or at an angle joint.
- Single or multi piece plastic or polymer basins are susceptible to cracking, and may not be structurally sound when containing large volumes.
- the plastic structures may be flammable, expensive, and damaged by heat or thermal shifts due to climates that have wide temperature range swings.
- Coatings such as epoxy and polymer coatings on metal have weaknesses especially when the coating is below the water line and exposed to chemicals and the water continuously. Such exposure can results in blistering, cracking, and peeling of the coating and thus exposing the metal substrate to the water and chemicals. Lining the basins with materials such as polyurethane may be difficult because of long cure times and expensive surface preparation.
- the lined basins are still susceptible to compatibility with sealer material like tape, caulk, and other sealants used which may react with the barrier coating after installation.
- the polyurethane liners are known to flow through cracks and seams in their liquid state before curing causing uneven coating especially where the liner is needed most, at the seams. Adhesion of the liner to the substrate can also be a problem especially on the bottom and walls below the water level. Water and chemicals attacking the edge interface between the liner and the substrate can penetrate between the liner and the substrate causing corrosion behind the liner. This corrosive damage can be very hard to repair and may damage the integrity of surrounding areas.
- Steel structures have been used extensively in the prior art to build structures for holding liquid such as water and treated water for cooling and evaporative functions.
- a steel structure provides a cost/strength-valued construction, but must be insulated from the liquid.
- Those skilled in the art would recognize that the prior art teaches that corrosion protection is accomplished with a polymer coating the structure or an organic powder coating.
- Each coating requires several steps be satisfied. First, the surface must be thoroughly cleaned of all dirt, oil, oxidation products, and any other foreign matter. Second, sites to which the liner can bond must be available on the surface. Third, the coatings must be specially formulated to impart specific wear, adhesion, sealing, and corrosion resistant properties to the steel when applied in layered sequential coatings. Liner joints or seams below the water line can allow penetration of the liquid through the seam and behind the liner promoting corrosion and eventually causing a leak.
- the '637 patent discloses and claims a process for the application of an organic powder coating to galvanized steel comprising a four step process.
- the panels are acid cleaned to remove contaminates and thoroughly rinsed and dried to prepare the metal galvanized surface for adhesion of the powder coating.
- the powder coating uses the galvanized layer as a back up corrosion resistant layer to protect and supplement especially where the panels are physically damaged in use destroying a portion of the powder coating.
- the prior art also includes roll-on and spray on liners for application to the interior walls of a vessel.
- These “after market” liners do not adhere well to the substrate due to contamination and corrosion on the surface of the metal.
- These “after market” liners are more expensive to apply because of surface preparations and labor required for installation.
- these prior art liners use cleaners, primer coatings, and/or mechanical surface preparation such as sanding, sand blasting or the like to clean and prepare the surface.
- Sealants used to seal the seams are butyl tape and/or caulk and may react chemically with the liner and may create a loose attachment of the liner to the substrate causing a compromised installation.
- the present invention is a factory-installed liner for use in evaporative cooling, condensing and similar systems holding and circulating hot and cold liquids for heat transfer and storage.
- the liner includes a coated metal such as galvanized steel as a structural substrate having a powdered polymer coating electrostatically applied and baked on the clean galvanized surface.
- the organic powder polymer bonds chemically and mechanically to the galvanized metal substrate and provides a clean, dry and possibly warm surface for the elastomeric barrier coating to mechanically and chemically adhere to. Additional support is provided for the barrier coating by holes formed in the substrate panels of the structure, forms placed in the corners, liner edges isolated from contact with flowing or standing water and seams attached without caulks and sealants.
- the holes are formed prior to application of the organic powder.
- the organic powder is applied to flow through sealing the hole and the surrounding galvanized material on the inside and outside surfaces.
- the forms provide better drainage to prevent standing water when the vessel is not in use.
- the forms are for allowing draining along the vessel edges where dirt, debris, and corrosive elements may become trapped and stand degrading the barrier coating.
- the panels are attached using mechanical fasteners in the standard manner of connecting panels to form a contiguous vessel wall. Fasteners are used in assembling the panels.
- the caulk or tape used in the prior art for sealing all sides with a homogenous application or sealing the seams are not used in the present invention.
- the present invention describes and claims a liner and method of application for sealing the seams and lining the panels with a homogenous application of an elastomeric material requiring fewer fasteners used and fewer holes in assembling the panels.
- the present invention is directed to a liner for use on the inner surface of a vessel or basin comprising a first coating of zinc applied to the steel panels to galvanize them.
- a second coating comprises an organic powder coating on the galvanized coating and a third layer of a material such as polyurethane, polyurea, a polyurethane/polyurea blend, or similar.
- the organic powder is applied electrostatically to provide a uniform and even coating even in blind spots to a clean galvanized steel surface and baked to cure resulting in a sealing coat having good adhesion and providing a bonding surface for the third polyurethane barrier coating layer.
- the organic powder coating may be an epoxy-like material such as deposited by the Baltibond Corrosion Protection System available from Baltimore Air Coil and described and claimed in the aforementioned U.S. '637 patent.
- the organic coating is applied to the interior and exterior surfaces in the manufacture of the structure by a multi-step cleaning and drying process to maximize adhesion between the coating and the metal.
- the coated panels are assembled using threaded fasteners or rivets as is known in the art of mechanical assembly of a large metal vessel or structure.
- the method of the present invention does not require a separate sealing tape or sealant before application of the third barrier coating layer.
- the method includes applying the elastomeric material in liquid form over the seams and any portion of the fasteners exposed to the inside of the vessel.
- the seams are covered by liquid barrier coating material first to provide a preseal.
- the method can also further comprise placing of corner forms in the corners and/or at the angled areas where the panels meet or bend to promote drainage and cleaning of the vessel, forming an inner surface with smooth transitions.
- the barrier coating is sprayed over the entire vessel interior up to and over the maximum standing water level.
- the barrier coating extends past the junction point for an adjoining panel to provide for the adjoining section to be connected having the seam isolated from the standing water. Often this seam can be further secured by compressing the barrier coating between the flanges or use of a flange ring wherever possible.
- the present invention is directed to a liner mechanically coupled to the key areas of the vessel such as sidewalls, high flowage areas and areas of high traffic.
- the mechanical coupling to the panels is achieved by punching link holes in the panels to allow the powder coating to coat in around and through each hole without closing the opening in the panel.
- the link holes allow the elastomeric barrier material to flow out of the link hole and form a button-like globule on the outside of the vessel tied to the barrier coating.
- the elastomeric barrier coating extends from the inside of the vessel to the outside of the panel through the link hole to mechanically attach the barrier coating to the sidewall.
- the clean dry surface of the organic powder second sealing layer allows the atomized spray of the elastomeric third layer to penetrate the pores and mechanically and chemically attach to the substrate.
- the organic coating over the galvanized steel provides a second protective layer as well as a bonding layer, and the sealing barrier coating provides a triple level of protection for the metal structure.
- the barrier coating is an inert material that resists corrosive water conditions and chemicals in the water better than stainless steel, especially in high chloride environments.
- the present invention is directed to a process for assembling and sealing a cooling tower, water basin or the like for holding water for cooling, evaporative or condensing systems.
- the process comprises the steps of forming panels in preconfigured shapes and sizes.
- the operator punches holes in the panels in a predetermined pattern, the holes spaced from the edges of the panel for further attachment of the barrier coating.
- the panels are galvanized steel of a type G-235 to provide a first corrosion resistant coating.
- the number following the G designation refers to the total coating weight on both sides of the sheet in hundredths of an ounce per square foot (oz/ft 2 ) of sheet. Thus, G235 would have a minimum total 02.350 oz/ft 2 of coating.
- the panels comprise a pre-adapted collection of steel panels for assembly into a holding basin.
- the panels are cleaned by an acid type cleaning solution such as phosphoric acid to remove contaminates followed by a rinse with water to remove the cleaner.
- the next step is to rinse again to insure the acid solution is removed.
- the operator dries the panels using air and heat to thoroughly dry the metal and immediately thereafter coat the panels with an organic powder coating such as, for example epoxy, polyester, acrylics or hybrids that are homogenous and designed for application to metals.
- the powder is applied by electrostatic spray on both sides of the panel especially around the link holes and edges to a typical thickness of 0.004 inches.
- the coated metal panels are baked usually at around 250-600 degrees for 1 to 20 minutes to thermoset the powder coating 56 .
- the time and temperature are predetermined values depending on the coating and thickness of the steel to cure the coating.
- the panels are cooled after curing and the clean and coated panels are assembled into subassemblies for application of the barrier coating.
- the elastomeric barrier coating application steps comprise, first applying in a liquid state, directly over the seams to form a preseal for the seams and prevent the elastomeric material from leaking through the seams during application. Next, the forms, if desired, are placed in the corners and where adjoining panels meet; next spraying the elastomeric material onto the basin including double spraying the seams and any exposed fasteners.
- the barrier coating coats the interior of the vessel and extends out of the basin and over the basin flange such that the barrier coating extends above the maximum standing liquid level and beyond the attachment to the upper structural section.
- the present invention is directed to an elastomeric barrier coating that is double applied over seams and fasteners and extends from in the liquid holding area to outside the liquid holding area by application to the basin and extension along the mounting flange of the basin to a point separated from the inside of the basin by the attachment of the adjacently upper panel attaching to the basin with the liner edge between the respective mounting flanges where possible.
- Additional attributes of the elastomeric barrier coating include extension of the barrier coating outside the basin, link holes punched in the panels forming a mechanical link to the panel by a button-like knob of barrier coating material formed on the outside of the basin by the liquid elastomeric material flowing out of the link hole and hardening. The link seals the adjacent link hole.
- the elastomeric barrier coating may be selected from elastomeric coatings and appropriate additives having acid resistance, fast cure times, inert properties, high durability, fire retardancy, and/or ablative properties.
- FIG. 1 is a side elevation section view of a prior art seam sealed with tape and caulk over the fasteners and seams;
- FIG. 2 is a side elevation section view of a basin seam sealed in accordance with the present invention
- FIG. 3 is a side elevation section view of a pre-sealed and lined basin subassembly in accordance with the present invention
- FIG. 4 is a section view of a mechanical link between the barrier coating and the basin panel in accordance with the present invention.
- FIG. 5 is a side elevation section view of a connection pipe in the basin in accordance with the present invention.
- FIG. 6 is a side elevation section view of the mechanical lock on the barrier coating edge between the basin and the upper section in accordance with the present invention.
- FIG. 7 is a section view of a panel coated and lined in accordance with the present invention.
- FIG. 8 is a flow chart demonstrating one method of lining a liquid holding basin in accordance with the present invention.
- FIG. 9 is a side section view of an assembled structure showing the lined basin and the lined upper section with the respective barrier coating edges captured between the adjoining flanges.
- the prior art basin of FIG. 1 shows a basin 10 made of panels 12 fastened together at the edges 14 of the panel 12 .
- the panels 12 are configured to form a water holding basin 10 having a bottom 30 with an outer edge attached to panels 12 adapted to form a side wall 32 .
- the basin 10 has a bottom 30 , a side wall 32 .
- Fasteners 16 extend through the flanges 42 to hold the panels 12 together to form a structure such as a basin 10 .
- the fasteners 16 may be self-tapping sheet metal screws or nut and bolt assemblies depending on individual basin requirements. The number of fasteners 16 is calculated to hold the panels 12 together structurally and for sealing purposes.
- the fasteners 16 extend through mating fastener holes 18 in adjacent flanges 40 as is well known in the art of assembling panels together into a basin 10 or the like.
- a sealing tape 20 may be used to seal the seam 24 between panels 12 and a caulk 22 may be used over the seal tape as a secondary sealing measure.
- the panels 12 are joined together at flanges 40 having a fastener portion 42 directed away from the basin 10 .
- the break flanges 40 have the fasteners 16 outside the basin 10 through the flanges 40 , also called break flanges 40 , to hold the panels 12 together.
- the elastomeric barrier coating 26 is applied in liquid form to the seams 24 between the panels 12 to form a pre-seal 25 .
- the elastomeric barrier layer 26 materials flows into the seam 24 between the adjacent panels 12 to fill and seal the seam 24 and form a pre-seal 25 over and in each panel seam 40 .
- the basin 10 is lined with an elastomeric barrier layer 26 applied in a continuous coat over the fasteners 16 and the seams 24 .
- Corner molds 28 are positioned to smooth the transition at corners such as where the bottom panel 30 meets the lower most side panel 32 . These corner molds 28 have a bottom wall 34 , a sidewall 36 and an outward wall 38 . The bottom wall 34 and sidewall 36 are positioned against adjoining panels 12 . The outward wall 38 smoothes the transition between the adjacent panels having a shape that is straight, convex or concave.
- the corner mold 28 may be a ring shaped, triangular cross-sectioned body for mounting in a circular basin between the sidewalls 32 and the bottom 30 .
- the corner mold 28 may be a plurality of forms having a triangular or other shape to provide a smooth transition between adjoining panels.
- the corner mold 28 comprising straight sections adapted for mounting in a polygon-sided basin between the sidewalls 32 and the bottom 30 or between the adjoining sidewalls 32 .
- the corner mold 28 can be made of foam, wood, metal, plastic or any material compatible with the elastomeric barrier coating material and substrate.
- the corner molds are placed in a desired position and sprayed with the third elastomer barrier layer 26 to hold the mold in place as a part of the substrate and intermediate the barrier coating 26 and the basin 10 .
- the base 30 and the sidewalls 32 join at approximately a right angle.
- the side panels 32 and bottom panels 30 are joined at a break flange 40 formed at the edge 14 of each panel.
- the corner molds 28 are disposed between the adjoining panels and are pre-sealed 25 by an application of barrier coating material.
- the bottom wall 34 of the corner mold 28 is on the bottom 30 of the basin 10 and the outside wall 38 faces into the basin 10 .
- Inside wall 44 extending along the bottom 30 and sides 32 of the basin 10 defines the water holding area with an open top 33 .
- the corner molds 28 provide a rounded edge for the bottom 30 of the basin 10 reducing the sharp corners and for sloping from the walls 32 to the drain 74 .
- the elastomeric barrier 26 is applied to the inside wall 44 , along the top flange 46 into each pipe stub 47 and along the sides 32 and bottom 30 .
- the elastomeric barrier 26 is applied to the basin 10 along the interior wall 44 of the sides 32 and the bottom 30 panels 12 .
- the elastomeric barrier liner 26 is sprayed or otherwise applied over the preferably still warm preseal 25 applied to the seams 24 to form a multilayer homogenous third barrier layer 26 .
- the outside elastomeric barrier 26 is extended up along the sidewalls 32 and onto the mounting surface 45 of the top flange 46 to liner edge 48 .
- Liner edge 48 is disposed outside the interior wall 44 of the basin 10 along the top flange 46 preferably outside the fastener holes 18 on top flange 46 .
- Link holes 50 are punched or drilled through the panels 12 from the inside 44 to the outside 54 . It should be understood, the link hole 50 may alternatively be formed as a dent 84 ( FIG. 9 ) or indent on the panel 12 . The dent 84 ( FIG. 9 ) creating a contour on the inner surface 44 of the basin 10 to provide a mechanical link between the barrier coating 26 and the panel 12 .
- the link 52 is formed through the link hole 50 ending in a button head shaped like a knob 62 on the outside 54 of the basin 10 .
- the link hole 50 has a tie diameter d 1 and extends from the inside 44 to the outside 54 .
- the link hole 50 is coated with the second layer organic powder 56 , along the inner surface 58 of the hole.
- the barrier layer 26 flows through the link hole 50 on application to the basin 10 .
- the barrier layer 26 forms a tie 60 in the hole 50 and accumulates on the outside 54 of the basin 10 in a knob 62 .
- the knob 62 has a knob diameter d2 that is larger than the link hole 50 to resist being pulled through the link hole 50 .
- the link hole 50 is coated with the second layer organic powder 56 , along the inner surface 58 of the hole.
- the link hole 50 is sealed with the elastomeric barrier coating 26 on the inside 44 and by the knob 62 on the outside 54 .
- the connector pipe stub 47 is shown as attached to the panel 12 .
- the pipe stub 47 provides an attaching location for source and drain piping 67 at the installation site.
- the pipe stub 47 is attached to the panel 12 before application of the organic coating 56 .
- the second layer organic powder coating is applied to the panel including around and on the pipe stub 47 to seal the ends, exterior and a portion of the interior of the stub 47 and the weld 49 .
- the pipe stub 47 has an inside end 51 and an outside end 53 .
- the outside diameter 63 and inside diameter 65 of the pipe stub 47 are chosen based on the application, flow rates and customer preference.
- the pipe stub 47 has an inside wall 55 and an outside wall 59 .
- the pipe hole 61 in the panel 12 is sized slightly larger than the outside diameter 63 to allow the pipe stub 47 to be inserted into the pipe hole 61 to a position having the inside end 51 aligned with the inside surface 44 of the basin 10 .
- the pipe hole 61 in the panel is sized to allow the pipe stub 47 to concentrically fit in the hole 61 for attachment.
- a weld 49 attaches the pipe stub 47 to the panel 12 .
- the powder coating 56 is electrostatically applied to evenly coat the entire panel pipe stub assembly including the weld 49 and provide a bonding surface for the elastomeric barrier coating 26 .
- the elastomeric barrier 26 is applied to the inside 44 of the panel 12 and extended onto a portion of the inside wall 55 a predetermined distance 57 usually about 2 inches from the inside end 51 .
- the liner edge 48 in the pipe stub 47 is spaced a predetermined distance from the outside end 53 to protect against over heating the barrier coating 26 when the pipe stub 47 is attached to facility piping 67 such as by welding.
- the panels of the sidewall 32 are lined 15 with the first galvanizing layer 70 , the second organic powder coating layer 56 , and the third elastomeric barrier coating layer 26 .
- the barrier coating 26 extends up to the wall flange 46 and past the fastener 16 and fastener hole 18 to a position spaced from the basin 10 interior.
- Upper section 64 may be a casing for housing heat transfer coils (not shown) having a sidewall 66 and bottom flange 148 for mateingly attaching to basin sidewall 32 .
- Upper section 64 is attached to basin 10 by aligning the flanges 46 , 146 and driving fasteners 16 there through.
- the fastener 16 may penetrate the barrier coat 26 on the top flange 46 .
- the barrier coating 26 extends intermediate the upper section 64 and the side wall 32 .
- the fastener 16 bears against the flange 46 and flange 68 to compress barrier coating 26 there between. Sealer or a preseal 25 as described above may also be used in this flange joint 24 to help seal the joint.
- Fastener 16 is intermediate liner edge 46 and the interior of basin 10 .
- the barrier coating 26 is applied along the interior 44 of the sidewall 32 .
- Link holes 50 are positioned along the panel 12 especially at high action areas such as close to flow interfaces, high traffic areas or where liquid is moving due to a pump or circulating action.
- the link hole 50 extends through the wall 32 , 30 of the panel 12 to allow the elastomeric barrier coating 26 to flow through during application and form a button head 62 on the outside surface 54 .
- the button head 62 is larger than link hole 50 to prevent the button head 62 from being pulled through the hole 50
- the button head provides a mechanical link to the panel 12 to promote the connection to the underlying substrate 70 and to hold the barrier coating 26 in place and preserve the integrity of the barrier coating 26 in the basin 10 in the event that the bond between the barrier coating 26 and the powder coating 56 is broken.
- the outside third layer of an elastomeric material is a barrier coating 26 when properly applied and cured becomes an integral inner surface of the basin 10 .
- the barrier coating 26 having its liner edge 46 is mechanically bound by the attached flanges 46 , 146 and is isolated from the basin contents.
- the pre-seal 25 over the seams 24 is separately cured and bonded to the barrier coating 26 to become homogenously part of the elastomeric inner barrier coating 26 .
- the pre-seal 25 may also be applied over the corner mold 28 .
- Corner mold 28 is adapted to fit snugly in corner spaces or where two adjoining walls 30 , 32 meet.
- the corner mold 28 has an outer surface 38 adapted to provide a smooth transition between the two adjoining walls 30 , 32 .
- the corner mold 28 may have a flat, convex or concave outer surface 38 depending on the angle of intersection of the adjacent walls.
- the corner mold 28 is placed in the structure before the third layer elastomeric barrier coating 26 is applied to become an integral part of the basin 10 .
- the molds 28 become part of the substrate when covered by the last barrier coating coat 26 .
- the barrier coating 26 on the bottom wall 30 is allowed to gravity cure so the resulting basin bottom 72 is flat or properly sloped to a drain 74 ( FIG. 5 ).
- the panel 12 comprises a steel plate 12 having a first layer to resist corrosion of zinc 70 thus galvanizing the steel plate 12 .
- the panels 12 are coated with a thermoset second layer 56 comprising a powdered polymer coating electrostatically applied to both sides 44 , 54 and to the inner surfaces of the holes 18 , 50 ( FIG. 3 ), 61 ( FIG. 5 ).
- a third barrier layer 26 is applied onto the thermoset layer 56 forming an elastomeric barrier coating 26 .
- the elastomeric barrier coating 26 is formed from a material such as polyurethane, polyurea, a mixture of the two or similar sprayable material on the inside wall 44 .
- the galvanized coating may be of a type well known in the art of coated metals.
- the organic powder coating 56 protects the inside surface 44 and outside surface 54 of the panel 12 from contaminates and corrosive elements and to provide a clean surface to bond to the elastomeric barrier coating 26 .
- a G235 type galvanizing on the panel works well.
- the powder coating 56 is an organic type of coating applied to the galvanized steel after it has been cleaned, rinsed and dried preferably using heat.
- the organic coating 56 is favorably applied using an electrostatic spraying process to evenly coat and hold the powder coating to the galvanized metal 70 .
- a thermoset cure is used to bond the organic coating to the galvanized substrate 12 by baking at a predefined time and temperature predetermined by the requirements of the coating material.
- the second layer comprising an organic powder coating electrostatically sprayed on the galvanized substrate and baked to cure may be a material such as Coating Powder available from Rohm and Haas Canada, 2 Manse Road, West Hill, Ontario, M1E 3T9, Canada.
- the Rohm and Haas product is comprised of Calcium metasilicate having a weight percentage between 40 and 50%, an epoxy resin having a weight percentage of between 40 and 50% and titanium dioxide having a weight percentage between 5 and 10%.
- the third layer elastomer barrier coating 26 is an elastomeric coating such as a polyurethane, polyurea, or mixture of polyurethane and polyurea or other similar material applied in a liquid form.
- the barrier coating 26 materials are pumped from separate containers into a two-component spray gun where the components are mixed, atomized and discharged from the gun (not shown).
- the barrier coating 26 may be a material such as TUFF STUFF or Durabond Polyurethane both available from Rhino Linings, USA, 9151 Rehco Road, San Diego, Calif. 92121.
- the Rhino Lining TUFF STUFF has two components comprising an A component, isocyanate, part no. 60012 and B component resin, part no. 60021.
- the barrier coating 26 is applied by liquid form on the seams 24 to pre-seal the joints between panels 12 .
- the present invention is directed to a process for assembling and sealing a cooling tower, water basin or the like for holding water for cooling, evaporative or condensing processes.
- the process comprises the steps of:
- an upper section 64 having a sidewall 76 with a bottom 78 and a bottom flange 146 may be pre assembled and mounted to the basin 10 at the customer site.
- the upper section 64 may be a casing, which mount on the basins and typically have heat transfer coils and/or cooling tower fill therein.
- the upper section 64 may have an elastomeric upper section barrier 126 on the inside surface 80 .
- the elastomeric barrier 126 may extend outside the interior 82 of the structure 64 along a bottom flange 146 .
- the basin 10 has a single piece three layer liner 26 along the inside wall 32 of the basin.
- the liner edges 48 are on the respective mounting flanges 46 , 146 .
- Fasteners 16 extend through fastener holes 18 in the top and bottom flanges 46 , 146 and through the elastomeric barrier 26 to attach the basin 10 to the upper section 64 .
- the fasteners are preferably intermediate the liner edge 48 and the interior of the basin 10 .
- the edges 48 , 148 respective barrier coatings 26 of the upper section 64 and the basin 10 are sealingly compressed along the junction of the mounting flanges 46 , 146 . In this way, the elastomeric barrier 26 is clamped between the assembled sub assemblies 10 , 64 to prevent the barrier coating edge 48 from exposure to the water in the basin 10 .
- the upper section can be lined with the elastomeric barrier 26 or not.
- the barrier coating of the basin 10 is captured by the upper section 64 and the basin 10 joined vertically having the liner edge 48 extending out onto the top flange 46 and captured between the mating flanges 46 146 .
- a flange ring 71 or sealer may be used on top of the mounting flange 46 to sealingly isolate the liner edge 48 .
- the basin is formed from prepared steel panels 12 made of galvanized steel with a zinc coating 70 thereon.
- the first protective layer is zinc applied during the galvanizing process.
- the second protective layer 56 is an organic powder electrostatically applied and cured on top of the zinc 70 . Applying the organic powder coating 56 provides a clean dry surface and enhance the adhesion of the barrier coating 26 to the basin 10 also seals and protects the galvanized steel panels.
- the panels 12 are assembled into a basin 10 or other sub structure for holding water or liquid and other subassemblies are also assembled.
- the third protective layer comprising an elastomer material is sprayed on the basin 10 .
- the elastomer barrier coating 26 material is applied first in liquid form to the seams 24 , and joints and areas around the connecting pipes 47 to preseal 25 those areas.
- the third layer elastomeric barrier coating 26 is then applied by spraying the same or different multi-part elastomer material evenly over the entire inner surface 44 of the basin 10 to form a contiguous coating 26 over the entire interior surface of the basin 10 having the barrier coating 26 extending up to and out of the top of the basin along the mounting flange 46 .
- the barrier coating 26 should preferably be sprayed to a minimum thickness such that the pre-seal layers are covered, and the liner 15 is a uniform thickness forming a smooth interior surface across the entire basin.
- the third elastomeric layer 26 is applied to a minimum is 1/16′′ up to a preferred maximum of 1 ⁇ 8′′.
- the third layer barrier coating 26 can be thicker to 1′′ if the environment and liquid conditions require this thickness of protection.
- the barrier coating 26 is preferably extended above the maximum standing water level in the basin 10 to isolate the liner edge 48 from the water.
- the organic powder coating 56 is applied to both sides of each panel, on the inside surface of the link holes 50 and over and inside the pipe stubs 47 and their welded connection to the panel 12 .
- the organic coating 56 provides a fresh surface where the elastomeric barrier coating 26 adheres to the organic coating 56 better than adhering to the galvanized 70 ( FIG. 7 ) surface to secure the barrier coating 26 in place in the basin 10 .
- the galvanized layer 70 ( FIG. 7 ) and the organic coating 56 provide a two coat bonding layer for the third coat elastomer barrier coating 26 .
- the zinc of the galvanizing 70 FIG.
- the organic powder coating 56 may be a coating like Baltibond® available from Baltimore Air Coil.
- Other organic powder coatings include powder coating such as, for example, epoxy, polyester, acrylics or hybrids that are homogenous and designed for application to metals.
- An organic coating 56 having a microscopically porous outer surface provides a mechanically bonding site for the barrier coating material along with a chemical bonding mechanism.
- the barrier coating is applied in liquid form from the mixing gun (not shown) where the components are mixed, atomized allowing the liquid barrier coating to flow into the pores of the organic coating and mechanically and chemically bond the barrier coating 26 to the organic coating 56 .
- the elastomer barrier coating 26 is preferably a two part polyurethane mixture.
- the multiple parts are mixed during the application process.
- a spray gun is provided having inputs for each of the individual barrier coating components wherein the parts are mixed at a predetermined ratio while being atomized and propelled out of the gun at the nozzle to be applied to the surface of the vessel 10 .
- the elastomeric barrier coating 26 materials may also be polyurea or a mixture of polyurea and polyurethane. It should also be understood the barrier coating material may have additives to adjust the cure time, improve UV resistance, change impact, slip and chemical resistance, add color to the barrier coating, and improve fire retardancy, and increase durability and traction among other attributes.
- Additional chemicals or accelerants can be mixed with the barrier coating mixture to accelerate cure time.
- the partial cure time or setup time is calculated to be less than one minute to allow ongoing work on the vessel 10 shortly after application of the elastomer barrier coating 26 , to reduce uneven application due to dripping, and allow multiple spray layers as in the pre-sealing of the seams of the basin.
- Additives with solvent properties to the organic bonding layer 56 may be added to the elastomer barrier coating 12 materials to provide an additional chemical bonding to the organic powder coating.
- the elastomer barrier coating material 12 Upon application the elastomer barrier coating material 12 would soften the outside surface of the organic coating causing a chemical mixture with the liquid barrier coating material.
- organic coating and barrier coating would be chemically bonded as well.
- the elastomer third layer barrier coating 26 is applied to the inside wall 44 from the top flange 46 into each pipe stub 47 and along the sides 32 and bottom 30 and over the top flange 46 on the other side.
- the elastomer barrier coating 26 is applied to the basin 10 along the interior wall 44 of the sides 32 and the bottom 30 panels 12 .
- the barrier coating 26 flows over the first coat preseal 25 , applied to the seams 24 and fasteners 16 , to form a multilayer homogenous barrier coating 26 sealing the seams 24 and protecting the substrate.
- the elastomer barrier coating 26 is preferably applied before the pre-seal 25 is fully set up to allow the maximum bonding between the barrier coating layer 26 and the preseal 25 .
- the barrier coating 26 should preferably be sprayed to a thickness such that the pre-seal layers are covered, and the liner is a uniform thickness across the entire basin.
- the elastomer barrier coating is extended up along the sidewalls 32 and over mounting wall flange 46 to a point outside the basin where possible.
- the liner edge 48 is captured and compressed between the top flange 46 of the basin sub assembly and the bottom flange 148 of the mating panel to prevent any chance of water attacking the edge bond to the panel 12 .
- Liner edge 48 is disposed outside the interior wall 44 of the basin 10 along the wall flange 46 between the fastener holes 18 and the panel edge 14 but may extend out to the edge of the flange 46 .
- Link holes 50 are formed to extend through the panels 12 from the inside 44 to the outside 54 .
- the elastomer barrier coating 26 material flows out through the link holes 50 and forms a retaining knob 62 adjacent the exterior wall 54 of the basin 10 creating a mechanical button like link between the outer layer 54 and the inner layer 44 wherein the button 62 cannot pull through the link hole 50 and thereby holds the barrier coating to the panel 12 , filling the hole and forming a mechanical link to the panel and the elastomer barrier coating 26 , while simultaneously increasing the bonding surface area for greater adhesion compared to a flat surface only.
- the tie 60 and the knob 62 are formed of the elastomeric material of the barrier layer 26 which flows through the link hole 50 upon application of the barrier coating 26 .
- the vessel is filled with water usually treated with chemicals to control water chemistry and to prevent biological growth and circulated in the system for cooling or heat transfer, etc.
- the barrier coating protects the metal structure and seals the seams and link holes to contain the water and protect the steel panels.
- the seams 25 and link holes 50 provide a tattletale status of a leak or water seeping behind the barrier coating and next to the panel 12 . If a rip or fault in the barrier coating 26 allows water between the barrier coating and the basin substrate, the water will seep out of the seam or link hole to indicate a problem with the barrier coating. This early indicator may allow repair of the barrier coating before corrosive damage happens to the underlying structural panel.
Abstract
Description
- The present invention relates to liners bonded to liquid containing metal structures and the method of applying and bonding the liner.
- Liquid holding structures such as cooling towers, evaporative condensers, and other evaporative systems for cooling or condensing and holding evaporative liquid are subjected to great mechanical stresses and exposure to corrosive environments. Chemicals used in the water to control water chemistries and to prevent biological growth can also work against the metal structure sections to promote corrosion unless carefully monitored. Such structures are usually made of treated steel, stainless steel, or plastic to protect the basin from corrosion. Plastic or polymer structures may be made from FRP or Polypropylene or similar materials. Fasteners are used to attach the panels together. The seams between the panels are usually sealed separately to give added protection to these areas. These metal structures are more likely to leak at or around the seams. Seams are sealed with a butyl rubber tape and/or a caulk. Prior art systems involved the use of galvanized, plastic or stainless materials to hold the liquid and prevent corrosion. Galvanized basins and structures provide limited resistance to corrosion. Prolonged exposure, especially to treated water having high chlorides and the like, can break down the galvanized coating. The loss of the galvanized coating exposes the panels to the corrosive liquid resulting in a need to repair or replace the structure or sections. Stainless tanks and basins are expensive and may be susceptible to corrosion from certain water chemistries such as high chlorides. Vessels formed from galvanized panels use many more fasteners than are needed to structurally assemble the panels. The fasteners are positioned and inserted to seal the seams as well as hold the panels together. The fasteners may need a fastener hole formed in the aligned flanges. Stainless steel panels can be fastened together with to form the basin or vessel having good corrosion protection to some chemicals. Furthermore, most metal vessels also have square corners and joints making vessel cleaning difficult and drainage an issue as water can pool in a corner or at an angle joint.
- Single or multi piece plastic or polymer basins are susceptible to cracking, and may not be structurally sound when containing large volumes. The plastic structures may be flammable, expensive, and damaged by heat or thermal shifts due to climates that have wide temperature range swings. Coatings such as epoxy and polymer coatings on metal have weaknesses especially when the coating is below the water line and exposed to chemicals and the water continuously. Such exposure can results in blistering, cracking, and peeling of the coating and thus exposing the metal substrate to the water and chemicals. Lining the basins with materials such as polyurethane may be difficult because of long cure times and expensive surface preparation. The lined basins are still susceptible to compatibility with sealer material like tape, caulk, and other sealants used which may react with the barrier coating after installation. Furthermore, the polyurethane liners are known to flow through cracks and seams in their liquid state before curing causing uneven coating especially where the liner is needed most, at the seams. Adhesion of the liner to the substrate can also be a problem especially on the bottom and walls below the water level. Water and chemicals attacking the edge interface between the liner and the substrate can penetrate between the liner and the substrate causing corrosion behind the liner. This corrosive damage can be very hard to repair and may damage the integrity of surrounding areas.
- Steel structures have been used extensively in the prior art to build structures for holding liquid such as water and treated water for cooling and evaporative functions. A steel structure provides a cost/strength-valued construction, but must be insulated from the liquid. Those skilled in the art would recognize that the prior art teaches that corrosion protection is accomplished with a polymer coating the structure or an organic powder coating. Each coating requires several steps be satisfied. First, the surface must be thoroughly cleaned of all dirt, oil, oxidation products, and any other foreign matter. Second, sites to which the liner can bond must be available on the surface. Third, the coatings must be specially formulated to impart specific wear, adhesion, sealing, and corrosion resistant properties to the steel when applied in layered sequential coatings. Liner joints or seams below the water line can allow penetration of the liquid through the seam and behind the liner promoting corrosion and eventually causing a leak.
- The U.S. Pat. No. 4,540,637 to Geary et al. for a PROCESS FOR THE APPLICATION OF ORGANIC MATERIAL TO GALVANIZED METAL is assigned to the assignee of the present invention and the disclosure is by this reference incorporated in its entirety in the present application. The liner protects the surface of the panels from chemical attack and corrosion caused by the water, treated water or other liquid contained in the vessel.
- The '637 patent discloses and claims a process for the application of an organic powder coating to galvanized steel comprising a four step process. The panels are acid cleaned to remove contaminates and thoroughly rinsed and dried to prepare the metal galvanized surface for adhesion of the powder coating. The powder coating uses the galvanized layer as a back up corrosion resistant layer to protect and supplement especially where the panels are physically damaged in use destroying a portion of the powder coating.
- The prior art also includes roll-on and spray on liners for application to the interior walls of a vessel. These “after market” liners do not adhere well to the substrate due to contamination and corrosion on the surface of the metal. These “after market” liners are more expensive to apply because of surface preparations and labor required for installation. In addition, these prior art liners use cleaners, primer coatings, and/or mechanical surface preparation such as sanding, sand blasting or the like to clean and prepare the surface. Sealants used to seal the seams are butyl tape and/or caulk and may react chemically with the liner and may create a loose attachment of the liner to the substrate causing a compromised installation.
- The present invention is a factory-installed liner for use in evaporative cooling, condensing and similar systems holding and circulating hot and cold liquids for heat transfer and storage. The liner includes a coated metal such as galvanized steel as a structural substrate having a powdered polymer coating electrostatically applied and baked on the clean galvanized surface. The organic powder polymer bonds chemically and mechanically to the galvanized metal substrate and provides a clean, dry and possibly warm surface for the elastomeric barrier coating to mechanically and chemically adhere to. Additional support is provided for the barrier coating by holes formed in the substrate panels of the structure, forms placed in the corners, liner edges isolated from contact with flowing or standing water and seams attached without caulks and sealants. The holes are formed prior to application of the organic powder. The organic powder is applied to flow through sealing the hole and the surrounding galvanized material on the inside and outside surfaces. The forms provide better drainage to prevent standing water when the vessel is not in use. The forms are for allowing draining along the vessel edges where dirt, debris, and corrosive elements may become trapped and stand degrading the barrier coating. The panels are attached using mechanical fasteners in the standard manner of connecting panels to form a contiguous vessel wall. Fasteners are used in assembling the panels. The caulk or tape used in the prior art for sealing all sides with a homogenous application or sealing the seams are not used in the present invention. The present invention describes and claims a liner and method of application for sealing the seams and lining the panels with a homogenous application of an elastomeric material requiring fewer fasteners used and fewer holes in assembling the panels.
- The present invention is directed to a liner for use on the inner surface of a vessel or basin comprising a first coating of zinc applied to the steel panels to galvanize them. A second coating comprises an organic powder coating on the galvanized coating and a third layer of a material such as polyurethane, polyurea, a polyurethane/polyurea blend, or similar. The organic powder is applied electrostatically to provide a uniform and even coating even in blind spots to a clean galvanized steel surface and baked to cure resulting in a sealing coat having good adhesion and providing a bonding surface for the third polyurethane barrier coating layer. The organic powder coating may be an epoxy-like material such as deposited by the Baltibond Corrosion Protection System available from Baltimore Air Coil and described and claimed in the aforementioned U.S. '637 patent. The organic coating is applied to the interior and exterior surfaces in the manufacture of the structure by a multi-step cleaning and drying process to maximize adhesion between the coating and the metal. The coated panels are assembled using threaded fasteners or rivets as is known in the art of mechanical assembly of a large metal vessel or structure. The method of the present invention does not require a separate sealing tape or sealant before application of the third barrier coating layer. The method includes applying the elastomeric material in liquid form over the seams and any portion of the fasteners exposed to the inside of the vessel. In the double break flange assembly of the vessel; all fasteners are typically outside the basin as shown in
FIG. 2 . In all cases in the present invention, the seams are covered by liquid barrier coating material first to provide a preseal. The method can also further comprise placing of corner forms in the corners and/or at the angled areas where the panels meet or bend to promote drainage and cleaning of the vessel, forming an inner surface with smooth transitions. The barrier coating is sprayed over the entire vessel interior up to and over the maximum standing water level. The barrier coating extends past the junction point for an adjoining panel to provide for the adjoining section to be connected having the seam isolated from the standing water. Often this seam can be further secured by compressing the barrier coating between the flanges or use of a flange ring wherever possible. - The present invention is directed to a liner mechanically coupled to the key areas of the vessel such as sidewalls, high flowage areas and areas of high traffic. The mechanical coupling to the panels is achieved by punching link holes in the panels to allow the powder coating to coat in around and through each hole without closing the opening in the panel. The link holes allow the elastomeric barrier material to flow out of the link hole and form a button-like globule on the outside of the vessel tied to the barrier coating. The elastomeric barrier coating extends from the inside of the vessel to the outside of the panel through the link hole to mechanically attach the barrier coating to the sidewall. The clean dry surface of the organic powder second sealing layer allows the atomized spray of the elastomeric third layer to penetrate the pores and mechanically and chemically attach to the substrate. The organic coating over the galvanized steel provides a second protective layer as well as a bonding layer, and the sealing barrier coating provides a triple level of protection for the metal structure. The barrier coating is an inert material that resists corrosive water conditions and chemicals in the water better than stainless steel, especially in high chloride environments.
- The present invention is directed to a process for assembling and sealing a cooling tower, water basin or the like for holding water for cooling, evaporative or condensing systems. The process comprises the steps of forming panels in preconfigured shapes and sizes. The operator punches holes in the panels in a predetermined pattern, the holes spaced from the edges of the panel for further attachment of the barrier coating. The panels are galvanized steel of a type G-235 to provide a first corrosion resistant coating. The number following the G designation refers to the total coating weight on both sides of the sheet in hundredths of an ounce per square foot (oz/ft2) of sheet. Thus, G235 would have a minimum total 02.350 oz/ft2 of coating. The panels comprise a pre-adapted collection of steel panels for assembly into a holding basin. The panels are cleaned by an acid type cleaning solution such as phosphoric acid to remove contaminates followed by a rinse with water to remove the cleaner. The next step is to rinse again to insure the acid solution is removed. Next, the operator dries the panels using air and heat to thoroughly dry the metal and immediately thereafter coat the panels with an organic powder coating such as, for example epoxy, polyester, acrylics or hybrids that are homogenous and designed for application to metals. The powder is applied by electrostatic spray on both sides of the panel especially around the link holes and edges to a typical thickness of 0.004 inches. The coated metal panels are baked usually at around 250-600 degrees for 1 to 20 minutes to thermoset the
powder coating 56. The time and temperature are predetermined values depending on the coating and thickness of the steel to cure the coating. The panels are cooled after curing and the clean and coated panels are assembled into subassemblies for application of the barrier coating. The elastomeric barrier coating application steps comprise, first applying in a liquid state, directly over the seams to form a preseal for the seams and prevent the elastomeric material from leaking through the seams during application. Next, the forms, if desired, are placed in the corners and where adjoining panels meet; next spraying the elastomeric material onto the basin including double spraying the seams and any exposed fasteners. The barrier coating coats the interior of the vessel and extends out of the basin and over the basin flange such that the barrier coating extends above the maximum standing liquid level and beyond the attachment to the upper structural section. - The present invention is directed to an elastomeric barrier coating that is double applied over seams and fasteners and extends from in the liquid holding area to outside the liquid holding area by application to the basin and extension along the mounting flange of the basin to a point separated from the inside of the basin by the attachment of the adjacently upper panel attaching to the basin with the liner edge between the respective mounting flanges where possible. Additional attributes of the elastomeric barrier coating include extension of the barrier coating outside the basin, link holes punched in the panels forming a mechanical link to the panel by a button-like knob of barrier coating material formed on the outside of the basin by the liquid elastomeric material flowing out of the link hole and hardening. The link seals the adjacent link hole. The elastomeric barrier coating may be selected from elastomeric coatings and appropriate additives having acid resistance, fast cure times, inert properties, high durability, fire retardancy, and/or ablative properties.
-
FIG. 1 is a side elevation section view of a prior art seam sealed with tape and caulk over the fasteners and seams; -
FIG. 2 is a side elevation section view of a basin seam sealed in accordance with the present invention; -
FIG. 3 is a side elevation section view of a pre-sealed and lined basin subassembly in accordance with the present invention; -
FIG. 4 is a section view of a mechanical link between the barrier coating and the basin panel in accordance with the present invention; -
FIG. 5 is a side elevation section view of a connection pipe in the basin in accordance with the present invention; -
FIG. 6 is a side elevation section view of the mechanical lock on the barrier coating edge between the basin and the upper section in accordance with the present invention; -
FIG. 7 is a section view of a panel coated and lined in accordance with the present invention; -
FIG. 8 is a flow chart demonstrating one method of lining a liquid holding basin in accordance with the present invention; -
FIG. 9 is a side section view of an assembled structure showing the lined basin and the lined upper section with the respective barrier coating edges captured between the adjoining flanges. - The prior art basin of
FIG. 1 shows abasin 10 made ofpanels 12 fastened together at theedges 14 of thepanel 12. Thepanels 12 are configured to form awater holding basin 10 having a bottom 30 with an outer edge attached topanels 12 adapted to form aside wall 32. Thebasin 10 has a bottom 30, aside wall 32.Fasteners 16 extend through theflanges 42 to hold thepanels 12 together to form a structure such as abasin 10. Thefasteners 16 may be self-tapping sheet metal screws or nut and bolt assemblies depending on individual basin requirements. The number offasteners 16 is calculated to hold thepanels 12 together structurally and for sealing purposes. Thefasteners 16 extend through mating fastener holes 18 inadjacent flanges 40 as is well known in the art of assembling panels together into abasin 10 or the like. In the prior art vessels, a sealingtape 20 may be used to seal theseam 24 betweenpanels 12 and acaulk 22 may be used over the seal tape as a secondary sealing measure. - Referring to
FIG. 2 , thepanels 12 are joined together atflanges 40 having afastener portion 42 directed away from thebasin 10. The break flanges 40 have thefasteners 16 outside thebasin 10 through theflanges 40, also calledbreak flanges 40, to hold thepanels 12 together. In accordance with the present invention, theelastomeric barrier coating 26 is applied in liquid form to theseams 24 between thepanels 12 to form a pre-seal 25. Theelastomeric barrier layer 26 materials flows into theseam 24 between theadjacent panels 12 to fill and seal theseam 24 and form a pre-seal 25 over and in eachpanel seam 40. - Continuing to refer to
FIG. 2 , thebasin 10 is lined with anelastomeric barrier layer 26 applied in a continuous coat over thefasteners 16 and theseams 24.Corner molds 28 are positioned to smooth the transition at corners such as where thebottom panel 30 meets the lowermost side panel 32. Thesecorner molds 28 have abottom wall 34, asidewall 36 and anoutward wall 38. Thebottom wall 34 andsidewall 36 are positioned against adjoiningpanels 12. Theoutward wall 38 smoothes the transition between the adjacent panels having a shape that is straight, convex or concave. Thecorner mold 28 may be a ring shaped, triangular cross-sectioned body for mounting in a circular basin between the sidewalls 32 and the bottom 30. Alternatively, thecorner mold 28 may be a plurality of forms having a triangular or other shape to provide a smooth transition between adjoining panels. Thecorner mold 28 comprising straight sections adapted for mounting in a polygon-sided basin between the sidewalls 32 and the bottom 30 or between the adjoiningsidewalls 32. Thecorner mold 28 can be made of foam, wood, metal, plastic or any material compatible with the elastomeric barrier coating material and substrate. The corner molds are placed in a desired position and sprayed with the thirdelastomer barrier layer 26 to hold the mold in place as a part of the substrate and intermediate thebarrier coating 26 and thebasin 10. - Referring to
FIG. 3 , thebase 30 and thesidewalls 32 join at approximately a right angle. Theside panels 32 andbottom panels 30 are joined at abreak flange 40 formed at theedge 14 of each panel. Thecorner molds 28 are disposed between the adjoining panels and are pre-sealed 25 by an application of barrier coating material. Thebottom wall 34 of thecorner mold 28 is on the bottom 30 of thebasin 10 and theoutside wall 38 faces into thebasin 10. Insidewall 44 extending along the bottom 30 andsides 32 of thebasin 10 defines the water holding area with an open top 33. Thecorner molds 28 provide a rounded edge for the bottom 30 of thebasin 10 reducing the sharp corners and for sloping from thewalls 32 to thedrain 74. Theelastomeric barrier 26 is applied to theinside wall 44, along thetop flange 46 into eachpipe stub 47 and along thesides 32 and bottom 30. Theelastomeric barrier 26 is applied to thebasin 10 along theinterior wall 44 of thesides 32 and the bottom 30panels 12. Theelastomeric barrier liner 26 is sprayed or otherwise applied over the preferably stillwarm preseal 25 applied to theseams 24 to form a multilayer homogenousthird barrier layer 26. The outsideelastomeric barrier 26 is extended up along thesidewalls 32 and onto the mountingsurface 45 of thetop flange 46 toliner edge 48.Liner edge 48 is disposed outside theinterior wall 44 of thebasin 10 along thetop flange 46 preferably outside the fastener holes 18 ontop flange 46. Link holes 50 are punched or drilled through thepanels 12 from the inside 44 to the outside 54. It should be understood, thelink hole 50 may alternatively be formed as a dent 84 (FIG. 9 ) or indent on thepanel 12. The dent 84 (FIG. 9 ) creating a contour on theinner surface 44 of thebasin 10 to provide a mechanical link between thebarrier coating 26 and thepanel 12. - Continuing to refer to
FIG. 3 , and referring toFIG. 4 , thelink 52 is formed through thelink hole 50 ending in a button head shaped like aknob 62 on the outside 54 of thebasin 10. Thelink hole 50 has a tie diameter d1 and extends from the inside 44 to the outside 54. Thelink hole 50 is coated with the second layerorganic powder 56, along theinner surface 58 of the hole. Thebarrier layer 26 flows through thelink hole 50 on application to thebasin 10. Thebarrier layer 26 forms atie 60 in thehole 50 and accumulates on the outside 54 of thebasin 10 in aknob 62. Theknob 62 has a knob diameter d2 that is larger than thelink hole 50 to resist being pulled through thelink hole 50. Thelink hole 50 is coated with the second layerorganic powder 56, along theinner surface 58 of the hole. Thelink hole 50 is sealed with theelastomeric barrier coating 26 on the inside 44 and by theknob 62 on the outside 54. - Referring to
FIG. 5 , theconnector pipe stub 47 is shown as attached to thepanel 12. Thepipe stub 47 provides an attaching location for source and drain piping 67 at the installation site. Thepipe stub 47 is attached to thepanel 12 before application of theorganic coating 56. The second layer organic powder coating is applied to the panel including around and on thepipe stub 47 to seal the ends, exterior and a portion of the interior of thestub 47 and theweld 49. Thepipe stub 47 has aninside end 51 and anoutside end 53. The outside diameter 63 and insidediameter 65 of thepipe stub 47 are chosen based on the application, flow rates and customer preference. Thepipe stub 47 has aninside wall 55 and an outside wall 59. Thepipe hole 61 in thepanel 12 is sized slightly larger than the outside diameter 63 to allow thepipe stub 47 to be inserted into thepipe hole 61 to a position having theinside end 51 aligned with theinside surface 44 of thebasin 10. Thepipe hole 61 in the panel is sized to allow thepipe stub 47 to concentrically fit in thehole 61 for attachment. Aweld 49 attaches thepipe stub 47 to thepanel 12. Thepowder coating 56 is electrostatically applied to evenly coat the entire panel pipe stub assembly including theweld 49 and provide a bonding surface for theelastomeric barrier coating 26. Theelastomeric barrier 26 is applied to the inside 44 of thepanel 12 and extended onto a portion of the inside wall 55 apredetermined distance 57 usually about 2 inches from theinside end 51. Theliner edge 48 in thepipe stub 47 is spaced a predetermined distance from theoutside end 53 to protect against over heating thebarrier coating 26 when thepipe stub 47 is attached to facility piping 67 such as by welding. - Referring to
FIG. 6 , the panels of thesidewall 32 are lined 15 with the first galvanizinglayer 70, the second organicpowder coating layer 56, and the third elastomericbarrier coating layer 26. Thebarrier coating 26 extends up to thewall flange 46 and past thefastener 16 andfastener hole 18 to a position spaced from thebasin 10 interior. Upper section 64 may be a casing for housing heat transfer coils (not shown) having a sidewall 66 andbottom flange 148 for mateingly attaching tobasin sidewall 32. Upper section 64 is attached tobasin 10 by aligning theflanges fasteners 16 there through. Thefastener 16 may penetrate thebarrier coat 26 on thetop flange 46. Thebarrier coating 26 extends intermediate the upper section 64 and theside wall 32. Thefastener 16 bears against theflange 46 and flange 68 to compressbarrier coating 26 there between. Sealer or a preseal 25 as described above may also be used in this flange joint 24 to help seal the joint.Fastener 16 isintermediate liner edge 46 and the interior ofbasin 10. - Continuing to refer to
FIG. 6 , thebarrier coating 26 is applied along the interior 44 of thesidewall 32. Link holes 50 are positioned along thepanel 12 especially at high action areas such as close to flow interfaces, high traffic areas or where liquid is moving due to a pump or circulating action. Thelink hole 50 extends through thewall panel 12 to allow theelastomeric barrier coating 26 to flow through during application and form abutton head 62 on theoutside surface 54. Thebutton head 62 is larger thanlink hole 50 to prevent thebutton head 62 from being pulled through thehole 50 The button head provides a mechanical link to thepanel 12 to promote the connection to theunderlying substrate 70 and to hold thebarrier coating 26 in place and preserve the integrity of thebarrier coating 26 in thebasin 10 in the event that the bond between thebarrier coating 26 and thepowder coating 56 is broken. It should be understood, the outside third layer of an elastomeric material is abarrier coating 26 when properly applied and cured becomes an integral inner surface of thebasin 10. Thebarrier coating 26 having itsliner edge 46 is mechanically bound by the attachedflanges - Continuing to refer to
FIG. 6 , the pre-seal 25 over theseams 24 is separately cured and bonded to thebarrier coating 26 to become homogenously part of the elastomericinner barrier coating 26. The pre-seal 25 may also be applied over thecorner mold 28.Corner mold 28 is adapted to fit snugly in corner spaces or where two adjoiningwalls corner mold 28 has anouter surface 38 adapted to provide a smooth transition between the two adjoiningwalls corner mold 28 may have a flat, convex or concaveouter surface 38 depending on the angle of intersection of the adjacent walls. Thecorner mold 28 is placed in the structure before the third layerelastomeric barrier coating 26 is applied to become an integral part of thebasin 10. Themolds 28 become part of the substrate when covered by the lastbarrier coating coat 26. Thebarrier coating 26 on thebottom wall 30 is allowed to gravity cure so the resulting basin bottom 72 is flat or properly sloped to a drain 74 (FIG. 5 ). - Referring to
FIG. 7 , thepanel 12 comprises asteel plate 12 having a first layer to resist corrosion ofzinc 70 thus galvanizing thesteel plate 12. Thepanels 12 are coated with a thermosetsecond layer 56 comprising a powdered polymer coating electrostatically applied to bothsides holes 18, 50 (FIG. 3 ), 61(FIG. 5 ). Athird barrier layer 26 is applied onto thethermoset layer 56 forming anelastomeric barrier coating 26. Theelastomeric barrier coating 26 is formed from a material such as polyurethane, polyurea, a mixture of the two or similar sprayable material on theinside wall 44. The galvanized coating may be of a type well known in the art of coated metals. Theorganic powder coating 56 protects theinside surface 44 and outsidesurface 54 of thepanel 12 from contaminates and corrosive elements and to provide a clean surface to bond to theelastomeric barrier coating 26. In the preferred embodiment a G235 type galvanizing on the panel works well. Thepowder coating 56 is an organic type of coating applied to the galvanized steel after it has been cleaned, rinsed and dried preferably using heat. Theorganic coating 56 is favorably applied using an electrostatic spraying process to evenly coat and hold the powder coating to the galvanizedmetal 70. A thermoset cure is used to bond the organic coating to the galvanizedsubstrate 12 by baking at a predefined time and temperature predetermined by the requirements of the coating material. The second layer comprising an organic powder coating electrostatically sprayed on the galvanized substrate and baked to cure may be a material such as Coating Powder available from Rohm and Haas Canada, 2 Manse Road, West Hill, Ontario, M1E 3T9, Canada. The Rohm and Haas product is comprised of Calcium metasilicate having a weight percentage between 40 and 50%, an epoxy resin having a weight percentage of between 40 and 50% and titanium dioxide having a weight percentage between 5 and 10%. - Continuing to refer to
FIG. 7 , the third layerelastomer barrier coating 26 is an elastomeric coating such as a polyurethane, polyurea, or mixture of polyurethane and polyurea or other similar material applied in a liquid form. Thebarrier coating 26 materials are pumped from separate containers into a two-component spray gun where the components are mixed, atomized and discharged from the gun (not shown). Thebarrier coating 26 may be a material such as TUFF STUFF or Durabond Polyurethane both available from Rhino Linings, USA, 9151 Rehco Road, San Diego, Calif. 92121. The Rhino Lining TUFF STUFF has two components comprising an A component, isocyanate, part no. 60012 and B component resin, part no. 60021. Thebarrier coating 26 is applied by liquid form on theseams 24 to pre-seal the joints betweenpanels 12. - Referring to
FIG. 8 , the present invention is directed to a process for assembling and sealing a cooling tower, water basin or the like for holding water for cooling, evaporative or condensing processes. The process comprises the steps of: -
- 1. Forming
panels 12 in reconfigured shapes and sizes from galvanized steel panels having a type G-235 galvanized coating to provide a first corrosion resistant layer and substrate forsubsequent coatings 70. - 2. Modifying the
panels 12 by bendingflanges 46 and punching fastener holes 18 in the flanges for interconnecting thepanels 12. The fastener holes 18 formed in a predetermined pattern spaced, from the edges of the panel. - 3. Cutting link holes 50 by punching, drilling or other means in the
panel 12 to providemechanical link 52 between thebarrier coating 26 and thepanel 12. - 4. Cutting source and drain holes in the panels at predetermined locations. The holes are sized to receive the outside diameter of the pipe stub therein.
- 5. Attaching source or drain pipe stubs concentrically into the respective source and drain holes by inserting the pipe stub in the respective hole having the inside end of the stub flush with the
inside surface 44 of thebasin 10 and welding the stub in place to sealingly attach the stub to thebasin 10. - 6. Cleaning the
panels 12 by an acid type cleaning solution such as phosphoric acid to remove contaminates. - 7. Rinsing the
panels 12 with water to remove the acid type cleaner. - 8. Rinsing the panels a second time to remove as much of the acid solution as possible from the
panels 12. - 9. Drying the panels using heat to thoroughly dry the metal and immediately thereafter,
- 10. Coating the panels including the inside and outside surface, including any attached pipe stubs with an organic powder coating such as, for example epoxy, polyester, acrylics or hybrids that are homogenous and designed for application to metals, by electrostatic spray on both sides of the panel especially around the binding holes and edges to a typical thickness of 0.004 inches.
- 11. Baking the coated metal panels to cure or thermoset the organic coating. The baking process performed in the preferred embodiment at around 250-600 degrees Fahrenheit for 1 to 20 minutes depending on the coating and thickness of the steel.
- 12. Cooling the panels after curing.
- 13. Assembling the coated panels into sub assemblies as required for shipping to the installation site.
- 14. Mixing any selected additives into the barrier coating components for desired mechanical or chemical properties of the barrier coating.
- 15. Sealing the seams between the
panels 12 by application of a liquid state barrier coating material directly over the seams. The liquid barrier coating material pre-seals the seams and prevents the barrier coating material from leaking through the seams during the barrier coating application - 16. Placing the forms, if desired, in the corners, between adjacent panels and where sides meet to provide a smooth transition between adjacent panels.
- 17. Spraying the elastomer barrier coating onto the inside of the
basin 10 to form aseamless barrier coating 26 on the interior of thebasin 10, including double spraying the seams and any exposed fasteners and spraying into each pipe stub a predetermined distance and along thevertical walls 32 of the basin and along the mountingflange 46. - 18. Curing the barrier coating by time, heat or other method.
- 19. Shipping the subassemblies to the assembly site for further assembly of the unit structure.
- 20. Assembling the subassemblies together in a manner that minimizes the exposure of the edge of the barrier coating to water in the basin by capturing the
liner 15 between adjacent subassemblies.
- 1. Forming
- Referring to
FIG. 9 , an upper section 64 having asidewall 76 with a bottom 78 and abottom flange 146 may be pre assembled and mounted to thebasin 10 at the customer site. The upper section 64 may be a casing, which mount on the basins and typically have heat transfer coils and/or cooling tower fill therein. The upper section 64 may have an elastomericupper section barrier 126 on theinside surface 80. Theelastomeric barrier 126 may extend outside the interior 82 of the structure 64 along abottom flange 146. As described above, thebasin 10 has a single piece threelayer liner 26 along theinside wall 32 of the basin. The liner edges 48 are on the respective mountingflanges Fasteners 16 extend through fastener holes 18 in the top andbottom flanges elastomeric barrier 26 to attach thebasin 10 to the upper section 64. The fasteners are preferably intermediate theliner edge 48 and the interior of thebasin 10. Theedges respective barrier coatings 26 of the upper section 64 and thebasin 10 are sealingly compressed along the junction of the mountingflanges elastomeric barrier 26 is clamped between the assembledsub assemblies 10, 64 to prevent thebarrier coating edge 48 from exposure to the water in thebasin 10. It should be understood, the upper section can be lined with theelastomeric barrier 26 or not. In the case that the upper section is not lined, the barrier coating of thebasin 10 is captured by the upper section 64 and thebasin 10 joined vertically having theliner edge 48 extending out onto thetop flange 46 and captured between themating flanges 46 146. Alternatively, aflange ring 71 or sealer may be used on top of the mountingflange 46 to sealingly isolate theliner edge 48. - In use, the basin is formed from
prepared steel panels 12 made of galvanized steel with azinc coating 70 thereon. The first protective layer is zinc applied during the galvanizing process. The secondprotective layer 56 is an organic powder electrostatically applied and cured on top of thezinc 70. Applying theorganic powder coating 56 provides a clean dry surface and enhance the adhesion of thebarrier coating 26 to thebasin 10 also seals and protects the galvanized steel panels. Thepanels 12 are assembled into abasin 10 or other sub structure for holding water or liquid and other subassemblies are also assembled. The third protective layer comprising an elastomer material is sprayed on thebasin 10. Theelastomer barrier coating 26 material is applied first in liquid form to theseams 24, and joints and areas around the connectingpipes 47 to preseal 25 those areas. The third layerelastomeric barrier coating 26 is then applied by spraying the same or different multi-part elastomer material evenly over the entireinner surface 44 of thebasin 10 to form acontiguous coating 26 over the entire interior surface of thebasin 10 having thebarrier coating 26 extending up to and out of the top of the basin along the mountingflange 46. Thebarrier coating 26 should preferably be sprayed to a minimum thickness such that the pre-seal layers are covered, and theliner 15 is a uniform thickness forming a smooth interior surface across the entire basin. The thirdelastomeric layer 26 is applied to a minimum is 1/16″ up to a preferred maximum of ⅛″. The thirdlayer barrier coating 26 can be thicker to 1″ if the environment and liquid conditions require this thickness of protection. Thebarrier coating 26 is preferably extended above the maximum standing water level in thebasin 10 to isolate theliner edge 48 from the water. - After preparing the
panels 12 by cutting, punching, bending and welding, theorganic powder coating 56 is applied to both sides of each panel, on the inside surface of the link holes 50 and over and inside the pipe stubs 47 and their welded connection to thepanel 12. Theorganic coating 56 provides a fresh surface where theelastomeric barrier coating 26 adheres to theorganic coating 56 better than adhering to the galvanized 70 (FIG. 7 ) surface to secure thebarrier coating 26 in place in thebasin 10. The galvanized layer 70 (FIG. 7 ) and theorganic coating 56 provide a two coat bonding layer for the third coatelastomer barrier coating 26. The zinc of the galvanizing 70 (FIG. 7 ) adheres very well to theunderlying steel panel 12, theorganic powder coating 56 is tightly bonded to the zinc coating 70 (FIG. 7 ) and theelastomer barrier coating 26 tightly bonds to theorganic coating 56. Theorganic powder coating 56 may be a coating like Baltibond® available from Baltimore Air Coil. Other organic powder coatings include powder coating such as, for example, epoxy, polyester, acrylics or hybrids that are homogenous and designed for application to metals. Anorganic coating 56 having a microscopically porous outer surface provides a mechanically bonding site for the barrier coating material along with a chemical bonding mechanism. The barrier coating is applied in liquid form from the mixing gun (not shown) where the components are mixed, atomized allowing the liquid barrier coating to flow into the pores of the organic coating and mechanically and chemically bond thebarrier coating 26 to theorganic coating 56. - The
elastomer barrier coating 26 is preferably a two part polyurethane mixture. The multiple parts are mixed during the application process. In the present invention a spray gun is provided having inputs for each of the individual barrier coating components wherein the parts are mixed at a predetermined ratio while being atomized and propelled out of the gun at the nozzle to be applied to the surface of thevessel 10. Theelastomeric barrier coating 26 materials may also be polyurea or a mixture of polyurea and polyurethane. It should also be understood the barrier coating material may have additives to adjust the cure time, improve UV resistance, change impact, slip and chemical resistance, add color to the barrier coating, and improve fire retardancy, and increase durability and traction among other attributes. Additional chemicals or accelerants can be mixed with the barrier coating mixture to accelerate cure time. In the preferred environment the partial cure time or setup time is calculated to be less than one minute to allow ongoing work on thevessel 10 shortly after application of theelastomer barrier coating 26, to reduce uneven application due to dripping, and allow multiple spray layers as in the pre-sealing of the seams of the basin. Additives with solvent properties to theorganic bonding layer 56 may be added to theelastomer barrier coating 12 materials to provide an additional chemical bonding to the organic powder coating. Upon application the elastomerbarrier coating material 12 would soften the outside surface of the organic coating causing a chemical mixture with the liquid barrier coating material. Upon curing the two layers, organic coating and barrier coating would be chemically bonded as well. - The elastomer third
layer barrier coating 26 is applied to theinside wall 44 from thetop flange 46 into eachpipe stub 47 and along thesides 32 and bottom 30 and over thetop flange 46 on the other side. Theelastomer barrier coating 26 is applied to thebasin 10 along theinterior wall 44 of thesides 32 and the bottom 30panels 12. Thebarrier coating 26 flows over thefirst coat preseal 25, applied to theseams 24 andfasteners 16, to form a multilayerhomogenous barrier coating 26 sealing theseams 24 and protecting the substrate. Theelastomer barrier coating 26 is preferably applied before the pre-seal 25 is fully set up to allow the maximum bonding between thebarrier coating layer 26 and thepreseal 25. Thebarrier coating 26 should preferably be sprayed to a thickness such that the pre-seal layers are covered, and the liner is a uniform thickness across the entire basin. The elastomer barrier coating is extended up along thesidewalls 32 and over mountingwall flange 46 to a point outside the basin where possible. Theliner edge 48 is captured and compressed between thetop flange 46 of the basin sub assembly and thebottom flange 148 of the mating panel to prevent any chance of water attacking the edge bond to thepanel 12.Liner edge 48 is disposed outside theinterior wall 44 of thebasin 10 along thewall flange 46 between the fastener holes 18 and thepanel edge 14 but may extend out to the edge of theflange 46. Link holes 50 are formed to extend through thepanels 12 from the inside 44 to the outside 54. During application, theelastomer barrier coating 26 material flows out through the link holes 50 and forms a retainingknob 62 adjacent theexterior wall 54 of thebasin 10 creating a mechanical button like link between theouter layer 54 and theinner layer 44 wherein thebutton 62 cannot pull through thelink hole 50 and thereby holds the barrier coating to thepanel 12, filling the hole and forming a mechanical link to the panel and theelastomer barrier coating 26, while simultaneously increasing the bonding surface area for greater adhesion compared to a flat surface only. Thetie 60 and theknob 62 are formed of the elastomeric material of thebarrier layer 26 which flows through thelink hole 50 upon application of thebarrier coating 26. - The vessel is filled with water usually treated with chemicals to control water chemistry and to prevent biological growth and circulated in the system for cooling or heat transfer, etc. The barrier coating protects the metal structure and seals the seams and link holes to contain the water and protect the steel panels. The
seams 25 and link holes 50 provide a tattletale status of a leak or water seeping behind the barrier coating and next to thepanel 12. If a rip or fault in thebarrier coating 26 allows water between the barrier coating and the basin substrate, the water will seep out of the seam or link hole to indicate a problem with the barrier coating. This early indicator may allow repair of the barrier coating before corrosive damage happens to the underlying structural panel. - Although the invention has been described above in connection with particular embodiments and examples, it will be appreciated by those skilled in the art that the invention is not necessarily so limited, and that numerous other embodiments, examples, uses, modifications and departures from the embodiments, examples and uses are intended to be encompassed by the claims attached hereto. The entire disclosure of each patent and publication cited herein is incorporated by reference, as if each such patent or publication were individually incorporated by reference herein.
Claims (22)
Priority Applications (9)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US11/454,648 US20070289966A1 (en) | 2006-06-16 | 2006-06-16 | Liquid vessel liner and method of application |
MYPI20070162A MY148397A (en) | 2006-06-16 | 2007-02-02 | Liquid vessel liner and method of application |
CN2007100885700A CN101089542B (en) | 2006-06-16 | 2007-03-16 | Liquid vessel liner and method of layout |
EP07251215.5A EP1867400B1 (en) | 2006-06-16 | 2007-03-22 | Method of lining of a vessel for liquids |
ES07251215T ES2421186T3 (en) | 2006-06-16 | 2007-03-22 | Method of coating a liquid tank |
BRPI0702324-3A BRPI0702324B1 (en) | 2006-06-16 | 2007-04-30 | METHOD FOR APPLYING A LINER TO A BASIN |
MX2007006983A MX2007006983A (en) | 2006-06-16 | 2007-06-11 | Liquid vessel liner and method of application. |
KR1020070058675A KR100912864B1 (en) | 2006-06-16 | 2007-06-15 | Liquid Vessel Liner and Method of Application |
US12/931,107 US8931158B2 (en) | 2006-06-16 | 2011-01-25 | Liquid vessel liner and method of application |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US11/454,648 US20070289966A1 (en) | 2006-06-16 | 2006-06-16 | Liquid vessel liner and method of application |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US12/931,107 Division US8931158B2 (en) | 2006-06-16 | 2011-01-25 | Liquid vessel liner and method of application |
Publications (1)
Publication Number | Publication Date |
---|---|
US20070289966A1 true US20070289966A1 (en) | 2007-12-20 |
Family
ID=38515393
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US11/454,648 Abandoned US20070289966A1 (en) | 2006-06-16 | 2006-06-16 | Liquid vessel liner and method of application |
US12/931,107 Active 2029-03-06 US8931158B2 (en) | 2006-06-16 | 2011-01-25 | Liquid vessel liner and method of application |
Family Applications After (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US12/931,107 Active 2029-03-06 US8931158B2 (en) | 2006-06-16 | 2011-01-25 | Liquid vessel liner and method of application |
Country Status (7)
Country | Link |
---|---|
US (2) | US20070289966A1 (en) |
EP (1) | EP1867400B1 (en) |
KR (1) | KR100912864B1 (en) |
CN (1) | CN101089542B (en) |
ES (1) | ES2421186T3 (en) |
MX (1) | MX2007006983A (en) |
MY (1) | MY148397A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20120213590A1 (en) * | 2010-02-04 | 2012-08-23 | Sanders Darrell J | Mine shaft liner plate system and method |
US20150048097A1 (en) * | 2013-08-16 | 2015-02-19 | Industrial Solutions USA, LLC | Storage container lining and insulation system |
US20170107733A1 (en) * | 2014-03-28 | 2017-04-20 | Oil Transporting Joint Stock Company "Transneft" | Method for thermally insulating reservoirs |
US20220074037A1 (en) * | 2018-12-21 | 2022-03-10 | Aquacare Europe B.V. | Method for patinating zinc surfaces and system therefor |
Families Citing this family (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
MX2010009130A (en) | 2008-02-20 | 2010-12-02 | Aos Holding Co | Organic polymer coatings for water containers. |
KR101584559B1 (en) | 2010-05-17 | 2016-01-12 | 대우조선해양 주식회사 | Piping structure of liquefied fuel gas storage tank of floating structure |
NL2006309C2 (en) * | 2011-02-28 | 2012-08-29 | Inventum Holding B V | DEVICE FOR HEATING AND DELIVERING HOT AND / OR COOKING WATER AND A RESERVOIR FOR SUCH DEVICE. |
GB2543370B (en) * | 2016-03-17 | 2019-04-10 | Galvgard U K Ltd | A gasket arrangement |
US10302198B2 (en) * | 2016-11-08 | 2019-05-28 | Gm Global Technology Operations Llc. | Sealing interface for corrosion protection |
US10362698B2 (en) * | 2017-01-20 | 2019-07-23 | Yaskawa America, Inc. | Method and system for environmental sealing of electrical enclosures |
US11054173B2 (en) * | 2017-12-06 | 2021-07-06 | A. O. Smith Corporation | Water heater with organic polymer coating |
DE102018113977A1 (en) * | 2018-06-12 | 2019-12-12 | ECO Holding 1 GmbH | Camshaft unit and method for producing a camshaft unit |
US10487570B1 (en) * | 2018-07-05 | 2019-11-26 | Schlage Lock Company Llc | Door with interior protective coating |
DE102019121639A1 (en) * | 2019-08-12 | 2021-02-18 | Adolf Kühner Ag | Water bath for moistening an interior of an incubator |
CN110625535A (en) * | 2019-10-25 | 2019-12-31 | 立丰家庭用品(南京)有限公司 | Enamel container manufacturing process and enamel container |
CN111545436A (en) * | 2020-05-15 | 2020-08-18 | 太仓鑫祥金属制品有限公司 | Surface treatment process of high-strength steel part for large bending machine |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US1232419A (en) * | 1917-06-01 | 1917-07-03 | William S Bacon | Washbasin. |
US2541768A (en) * | 1948-07-03 | 1951-02-13 | Kenneth M Keller | Flexible molding strip |
US3952338A (en) * | 1975-04-21 | 1976-04-27 | Troxclair Robert S | Therapy basin |
US4540637A (en) * | 1980-12-29 | 1985-09-10 | Baltimore Aircoil Company, Inc. | Process for the application of organic materials to galvanized metal |
US5431295A (en) * | 1989-03-31 | 1995-07-11 | Westinghouse Electric Corporation | Storage module for nuclear waste with improved liner |
US5644873A (en) * | 1995-05-05 | 1997-07-08 | Bourgault; Jean | Stairs for swimming-pool |
US20010005911A1 (en) * | 1999-12-01 | 2001-07-05 | Fritz Pieper | Sanitary tub |
US20030019741A1 (en) * | 2001-07-24 | 2003-01-30 | Applied Materials, Inc. | Method and apparatus for sealing a substrate surface during an electrochemical deposition process |
Family Cites Families (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US567667A (en) * | 1896-09-15 | Thirds to john w | ||
US1381877A (en) * | 1919-05-12 | 1921-06-14 | Edward T Neyhard | Knockdown tank |
US1801468A (en) * | 1928-08-27 | 1931-04-21 | Glenn L Martin Co | Fluid tank |
US2592419A (en) * | 1948-01-20 | 1952-04-08 | Sun Oil Co | Lead lined vessel |
US3606958A (en) * | 1968-05-17 | 1971-09-21 | Shell Oil Co | Laminated fluid-barrier container and method of making it |
NL7302527A (en) * | 1973-02-23 | 1974-08-27 | ||
US3896963A (en) * | 1973-05-21 | 1975-07-29 | Goodyear Tire & Rubber | Linings for containers for handling corrosive chemicals and the method of preparing said containers |
US4036390A (en) * | 1975-10-17 | 1977-07-19 | Morse California Co. | Plastic tank panels and joint assembly |
JPS53108171A (en) * | 1977-03-03 | 1978-09-20 | Sekisui Chem Co Ltd | Corrosion-proofing of liquid bath |
US4620815A (en) * | 1984-03-21 | 1986-11-04 | Preformed Line Products Company | Fastener strips for splice cases |
US5381915A (en) * | 1993-04-16 | 1995-01-17 | Yardley Box Company | Collapsible, reusable container |
US6203928B1 (en) * | 1997-04-24 | 2001-03-20 | Stanley Kotler | Housings for parking meters and other outdoor token handling devices and method of making and refurbishing same |
CN2345504Y (en) * | 1998-12-18 | 1999-10-27 | 崔海龙 | Water tank installed with inner and outer liner |
NL1011315C2 (en) * | 1999-02-16 | 2000-08-17 | Janssens & Dieperink B V | Method for manufacturing a silo. |
US6387524B1 (en) * | 2000-01-19 | 2002-05-14 | Blair Rubber Company | Tank liners and methods for installing same |
US6562467B2 (en) * | 2001-07-18 | 2003-05-13 | Eaton Corporation | Corrosion and UV resistant article and process for electrical equipment |
US20050249872A1 (en) * | 2004-05-04 | 2005-11-10 | Cox Timothy B | Method of sealing a sump |
US7516864B2 (en) * | 2005-06-30 | 2009-04-14 | E-Make Co., Ltd. | Built-up container |
DE102008034659A1 (en) * | 2008-07-25 | 2010-02-04 | Schmidt-Seeger Gmbh | Round container for germination or kilning of grain |
-
2006
- 2006-06-16 US US11/454,648 patent/US20070289966A1/en not_active Abandoned
-
2007
- 2007-02-02 MY MYPI20070162A patent/MY148397A/en unknown
- 2007-03-16 CN CN2007100885700A patent/CN101089542B/en active Active
- 2007-03-22 EP EP07251215.5A patent/EP1867400B1/en active Active
- 2007-03-22 ES ES07251215T patent/ES2421186T3/en active Active
- 2007-06-11 MX MX2007006983A patent/MX2007006983A/en active IP Right Grant
- 2007-06-15 KR KR1020070058675A patent/KR100912864B1/en active IP Right Grant
-
2011
- 2011-01-25 US US12/931,107 patent/US8931158B2/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US1232419A (en) * | 1917-06-01 | 1917-07-03 | William S Bacon | Washbasin. |
US2541768A (en) * | 1948-07-03 | 1951-02-13 | Kenneth M Keller | Flexible molding strip |
US3952338A (en) * | 1975-04-21 | 1976-04-27 | Troxclair Robert S | Therapy basin |
US4540637A (en) * | 1980-12-29 | 1985-09-10 | Baltimore Aircoil Company, Inc. | Process for the application of organic materials to galvanized metal |
US5431295A (en) * | 1989-03-31 | 1995-07-11 | Westinghouse Electric Corporation | Storage module for nuclear waste with improved liner |
US5644873A (en) * | 1995-05-05 | 1997-07-08 | Bourgault; Jean | Stairs for swimming-pool |
US20010005911A1 (en) * | 1999-12-01 | 2001-07-05 | Fritz Pieper | Sanitary tub |
US20030019741A1 (en) * | 2001-07-24 | 2003-01-30 | Applied Materials, Inc. | Method and apparatus for sealing a substrate surface during an electrochemical deposition process |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20120213590A1 (en) * | 2010-02-04 | 2012-08-23 | Sanders Darrell J | Mine shaft liner plate system and method |
US8795777B2 (en) * | 2010-02-04 | 2014-08-05 | Contech Engineered Solutions LLC | Mine shaft liner plate system and method |
US20150048097A1 (en) * | 2013-08-16 | 2015-02-19 | Industrial Solutions USA, LLC | Storage container lining and insulation system |
US20170107733A1 (en) * | 2014-03-28 | 2017-04-20 | Oil Transporting Joint Stock Company "Transneft" | Method for thermally insulating reservoirs |
US10072435B2 (en) * | 2014-03-28 | 2018-09-11 | Public-Joint Stock Company “Transneft” | Method for thermally insulating reservoirs |
US20220074037A1 (en) * | 2018-12-21 | 2022-03-10 | Aquacare Europe B.V. | Method for patinating zinc surfaces and system therefor |
Also Published As
Publication number | Publication date |
---|---|
MX2007006983A (en) | 2008-10-30 |
EP1867400A1 (en) | 2007-12-19 |
CN101089542B (en) | 2010-12-22 |
MY148397A (en) | 2013-04-15 |
US8931158B2 (en) | 2015-01-13 |
CN101089542A (en) | 2007-12-19 |
EP1867400B1 (en) | 2013-07-03 |
ES2421186T3 (en) | 2013-08-29 |
US20110117285A1 (en) | 2011-05-19 |
BRPI0702324A (en) | 2008-02-19 |
KR100912864B1 (en) | 2009-08-19 |
KR20070120043A (en) | 2007-12-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8931158B2 (en) | Liquid vessel liner and method of application | |
US8133345B2 (en) | Method and apparatus for lining process tanks | |
US9278478B2 (en) | Methods and apparatus for lining process tanks | |
JP7150720B2 (en) | Method and system for environmental sealing of electrical enclosures | |
KR101557775B1 (en) | Structures and method for water tank waterproofing concrete of using the panel | |
US5829209A (en) | Method of manufacturing a silo or tank with a lining, and a wall sheet for manufacturing a silo or tank | |
US10138053B2 (en) | Methods and apparatus for lining process tanks | |
JPH07180395A (en) | Constructing method of lined silo or tank, wall board for constructing silo or tank and manufacture of wall board used for silo or tank | |
CA2403702C (en) | Method and apparatus for lining manholes | |
AT501247B1 (en) | FLOOR DRAIN | |
KR101029976B1 (en) | Water tank and method for constructing the same | |
AU2001243675A1 (en) | Method and apparatus for lining manholes | |
BRPI0702324B1 (en) | METHOD FOR APPLYING A LINER TO A BASIN | |
KR100407231B1 (en) | method for manufacture in panel water tank and panel water tank | |
KR101515964B1 (en) | The Sealing Method for bolted structure | |
CN109837894A (en) | Anti-float anchor rod end multilayer flashing material mating steel plate for sealing water composite water-proof construction technology | |
JPH11276949A (en) | Coating of inside/outside surfaces of special shaped tube, and coating apparatus | |
JP6755729B2 (en) | Construction method of waterproof and rust preventive material | |
US5209369A (en) | Application of sealant membrane by spraying and resultant membrane | |
CA1178813A (en) | Sealing system for use on an offshore platform and a method of applying this sealing system | |
KR20200088927A (en) | A method of manufacturing a corrugated steel pipe having excellent durability performance and watertightness and a corrugated steel pipe | |
KR20100029439A (en) | Surface finished structure and constructing method of the structure | |
JP2001020467A (en) | Frp waterproof cover structure for existing roof and method for constructing the same | |
JPH01291931A (en) | Coating material for building and the like | |
HU188866B (en) | Method for renewing the internal covering of fluid storing and/or treating space having space limiting structure made of concrete and/or natural or/and artificial stone particularly food industrial fluid storage tank |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
AS | Assignment |
Owner name: BALTIMORE AIRCOIL COMPANY, INC., MARYLAND Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:MORRISON, FRANK T.;LOWMAN, GREG M.;HAWKINS, JOHN R.;AND OTHERS;REEL/FRAME:018008/0442 Effective date: 20060608 |
|
AS | Assignment |
Owner name: BANK OF AMERICA, N.A., (AS SUCCESSOR TO CITICORP N Free format text: INTELLECTUAL PROPERTY SECURITY AGREEMENT SUPPLEMENT;ASSIGNORS:AMSTED INDUSTRIES INCORPORATED;AMCONSTRUCT CORPORATION;AMRAIL CORPORATION;AND OTHERS;REEL/FRAME:024662/0436 Effective date: 20100317 |
|
STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |