CN109837894A - Anti-float anchor rod end multilayer flashing material mating steel plate for sealing water composite water-proof construction technology - Google Patents

Anti-float anchor rod end multilayer flashing material mating steel plate for sealing water composite water-proof construction technology Download PDF

Info

Publication number
CN109837894A
CN109837894A CN201910158146.1A CN201910158146A CN109837894A CN 109837894 A CN109837894 A CN 109837894A CN 201910158146 A CN201910158146 A CN 201910158146A CN 109837894 A CN109837894 A CN 109837894A
Authority
CN
China
Prior art keywords
anchor rod
float anchor
construction
thickness
cement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910158146.1A
Other languages
Chinese (zh)
Inventor
吴攀
黄伟
马志骁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Haichuan Construction Group Co Ltd
Original Assignee
Qingdao Haichuan Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Haichuan Construction Group Co Ltd filed Critical Qingdao Haichuan Construction Group Co Ltd
Priority to CN201910158146.1A priority Critical patent/CN109837894A/en
Publication of CN109837894A publication Critical patent/CN109837894A/en
Pending legal-status Critical Current

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The invention discloses a kind of anti-float anchor rod end multilayer flashing material mating steel plate for sealing water composite water-proof construction technologies, including the following steps: (one) steel plate for sealing water and anti-float anchor rod weld;(2) construction concrete cushion;(3) construction anti-float anchor rod;(4) 20 thickness 1:2.5 cement mortar screedings, bolthole saliva cement mortar press polish;(5) 1.5 solid cement base waterproof coatings, 20 thickness 1:2.5 cement mortar protective courses are brushed;(6) brushing base treatment agent, 4 thickness SBS waterproof coiled material constructions;(7) pitch ointment filleting, concrete cover are constructed in 300 ranges around anchor pole.This engineering method operates conveniently, construction is simple, and SBS waterproof roll anchor pole aperture only paving to aperture root, it is not upper anti-, it avoids the problem that connection is difficult caused by coiled material is walked between anchor pole reinforcing bar, heating is difficult, cutting difficulty etc. is difficult to construct, can construct within a short period of time and finish and guarantee yields;For this engineering method using conventional waterproof material, economy is convenient, prevents to avoid increasing extra cost because leak is repaired repeatedly after building is delivered.The working skill is advanced, easy construction, and social benefit is very significant.

Description

The construction of anti-float anchor rod end multilayer flashing material mating steel plate for sealing water composite water-proof Technique
Technical field
The present invention relates to a kind of anti-float anchor rod end multilayer flashing material mating steel plate for sealing water composite water-proof construction technology, Belong to technical field of building construction.
Background technique
Many regional geology complicated conditions, and level of ground water is higher, when more architectural design foundation can be using anti- The form of drogue bar.Since anti-float anchor rod is more reinforcing bar compositions, so the waterproof construction at this position is difficult point, various waterproof materials Material effect in this position single use is very undesirable, when being used in combination again since material property is different, material construction is wanted It asks and is difficult to the problems such as operating in different, anti-float anchor rod aperture and causes waterproof performance bad, so the easily leak of anti-float anchor rod position, Waterproof performance is not can guarantee, later period maintenance process is again extremely complex, it is difficult to guarantee maintenance effect.
Summary of the invention
The technical problems to be solved by the present invention are: providing a kind of anti-float anchor rod end multilayer flashing material mating water-stopping steel Plate composite water-proof construction technology.
In order to solve the above technical problems, the technical solution adopted by the present invention is that:
Anti-float anchor rod end multilayer flashing material mating steel plate for sealing water composite water-proof construction technology provided by the invention, including under Column step:
(1) steel plate for sealing water and anti-float anchor rod weld
1 according to construction drawing, positioning and resisting flotation anchor pole reinforcement location and aperture on steel plate for sealing water, to the accurate aperture of steel plate for sealing water, Port size deviation should not exceed 0.5%;
Answered when 2 steel plate for sealing water are with anti-float anchor rod reinforcement welding it is two-sided be fully welded, must not have sand holes, solder skip, if any should repair welding immediately.
(2) construction concrete cushion
1 concrete cushion answers vibration compacting when constructing;
2 ensure concrete cushion thickness, guarantee that mat surface is smooth.
(3) construction anti-float anchor rod
1 anti-float anchor rod should be noted that finished product protection when constructing, the construction machinery of anti-float anchor rod drilling on concrete cushion when driving Boarding is answered, prevents concrete cushion from being destroyed by construction machinery;
2 anti-float anchor rods should clean out the earthing on concrete cushion after drilling immediately;
3 ensure the verticality of anti-float anchor rod.
(4) 20 thickness 1:2.5 cement mortar screedings, bolthole saliva cement mortar press polish
1 levelling cement mortar will ensure thickness, guarantee that waterproof material base is smooth, smooth, if discovery cement mortar can not be levelling When should polish in time concrete cushion.
2 anchor pole aperture cement mortar press polish, must not have situations such as out-of-flatness, hole.
(5) 1.5 solid cement base waterproof coatings, 20 thickness 1:2.5 cement mortar protective courses are brushed
1 by polymer modified cement based waterproofing coating and cement in 1:1.5(weight ratio) ratio cement is slowly added into liquid material container, And stirred with electric mixer, mixing time is 5 minutes, and uniform and smooth is wanted in stirring, must not contain pellet shape mixture;
2 brush first of film: checking base's screed-coat, if base is smooth can to brush the first coating film, when brushing can use modeling Material or squeegee are uniformly brushed, and consistency of thickness is made every effort to, and single layer controls between 0.5-0.6mm;
3 brushing second films: after first of curing of coating (tack-free), can uniformly brush the second coating film on it, apply Brushing direction should be vertical with first of brushing direction, and thickness control is between 0.5-0.6mm;
4 brushing third road films: the same second of method, brushing direction should be vertical with second brushing direction, and thickness control exists Between 0.5-0.6mm;
In 5 painting process, inside anti-float anchor rod aperture of constructing emphatically, it is necessary to assure the cement base inside anti-float anchor rod aperture is anti- Water coating thickness, and cement-based waterproof film coated surface is smooth;
The 1:2.5 cement mortar protective course thickness of 6 cement-based waterproof films needs strict control, guarantees thickness in 20mm and less In 22mm.
(6) brushing base treatment agent, 4 thickness SBS waterproof coiled material constructions
1 sprays one layer of neoprene modified pitch adhesive in processed base.With long handle round brush or sprayer by base Layer inorganic agent brushing will brush uniformly in substrate surface, must not leak brush or show-through.Base treatment agent brushing finishes, it is necessary to pass through Waterproof construction can be carried out by reaching within 12 hours or more degree of drying;
2 paving coiled materials: when using Hot-melt construction, the heating of coiled material bottom surface uniformly should avoid excessive heat from burning coiled material;Paving When should flatten compacting, must firm pasting between coiled material and basal plane;Paving coiled material should be rolled immediately after coiled material surface hot melt, exclude coiled material Following air, and spreading firm pasting, must not there is hollowing, gauffer;Seam areas must overflow pitch hot melt when rolling paving coiled material Glue, scraping envelope interface at any time makes to be firmly bonded;Coiled material after paving answer it is smooth, straight, overlap joint size it is correct, must not have distortion;
3 coiled materials are handled at anti-float anchor rod aperture position: when installation of membrane to anti-float anchor rod aperture position, with wallpaper knife to coiled material It is cut, cuts out the circular hole of anti-float anchor rod aperture size, and ensure the paving of coiled material energy to anti-float anchor rod aperture root.
(7) pitch ointment filleting, concrete cover are constructed in 300 ranges around anchor pole
1 pitch ointment belongs to heat construction waterproof material, by pitch ointment solid except being placed in iron pan after unlap, rises slowly Temperature, the side Bian Jiare is stirred continuously, careful burn-out-proof coked agglomerate becomes waste product;
2 when being warming up to 100 DEG C -110 DEG C, when pitch ointment surface black is bright, sufficiently fusing when, constant temperature can construct;
3 by the pitch ointment flow coat of fusing to anti-float anchor rod aperture position, first ensure that and be covered with pitch ointment in aperture, then Again by 300mm range around the uniform flow coat anti-float anchor rod of pitch ointment;
4 (are jammed on foot and expendable deformation do not occur) when pitch ointment is re-condensed into solid, can carry out concrete Protective layer construction.
One, engineering method feature:
1. anti-float anchor rod end water-proofing treatment is the universal difficult point of construction, due to the complexity of anti-float anchor rod end, this position pole Easy to leak.This engineering method is blocked using three kinds of waterproof material confrontation drogue boom ends, is coupled hardness with softness, is effectively formed composite water-proof Layer, while the infiltration that may be present of anti-float anchor rod aperture is obstructed using steel plate for sealing water, it is ensured that building waterproof performance;
2. an engineering method operates conveniently, construction is simple, and SBS waterproof roll anchor pole orifice part position only paving to aperture root, no Upper anti-, what difficult, cutting difficulty of connection difficulty, heating caused by avoiding coiled material from walking between anchor pole reinforcing bar etc. was difficult to construct asks Topic, can construct within a short period of time and finish and guarantee yields;
3. engineering method can effectively solve the problems, such as anchor rod foundation later period easy to leak and maintenance effect is undesirable;
4. engineering method is using conventional waterproof material, economy is convenient, prevents to avoid increasing because leak is repaired repeatedly after building is delivered Extra cost.
Two, engineering method principle
The engineering method uses three layers of waterproof material, first layer brushing cement-based waterproof film, second layer paving in anti-float anchor rod end SBS waterproof roll, third layer flow coat pitch ointment.Using hot melt paving when because of SBS waterproof roll paving, so anti-in cement base Use cement mortar covering as protective layer after water coating construction on it again, effectively isolation SBS waterproof coiled material construction when Heat prevents cement-based waterproof film to be destroyed.The closure of pitch ointment is reused after SBS waterproof coiled material construction, is effectively solved Certainly SBS waterproof roll is difficult to the problem of constructing in anti-float anchor rod end.
Beneficial effects of the present invention:
Economic benefit: this engineering method easy construction and more time saving, all waterproof rolls in aperture position of anti-float anchor rod end not on Instead, Master Cost is saved compared to other construction methods, every anti-float anchor rod saves 10 yuan of Master Cost;Waterproof roll is in anti-floating Labour cost has been saved without interting paving, only paving to anti-float anchor rod reinforcing bar aperture root in anchor pole orifice part position, and every anti- Drogue bar solves 12 yuan of labour cost;This engineering method effectively prevents the problem of anti-float anchor rod position is easy leakage, has saved later period dimension Expense is repaired, every anti-float anchor rod saves 35 yuan;It is 57 yuan that every anti-float anchor rod of this engineering method, which amounts to saving expense,.
Social benefit: this engineering method is blocked using three kinds of waterproof material confrontation drogue boom ends, is coupled hardness with softness, effective shape The infiltration that may be present of anti-float anchor rod aperture is obstructed at complex waterproof layer, while using steel plate for sealing water, it is ensured that building waterproof Energy;This engineering method operates conveniently, construction is simple, and SBS waterproof roll anchor pole aperture only paving to aperture root, it is not upper anti-, keep away Exempt from difficult connection caused by coiled material is walked between anchor pole reinforcing bar, heating difficulty, cutting difficulty etc. and is difficult to the problem of constructing, Ke Yi Construction finishes and guarantees yields in short period;For this engineering method using conventional waterproof material, economy is convenient, prevents building delivery Afterwards because leak is repaired repeatedly, avoid increasing extra cost.The working skill is advanced, easy construction, and social benefit is very significant.
Specific embodiment
Embodiment 1
Anti-float anchor rod end multilayer flashing material mating steel plate for sealing water composite water-proof construction technology provided in this embodiment, including The following steps:
Anti-float anchor rod end multilayer flashing material mating steel plate for sealing water composite water-proof construction technology, including the following steps:
(1) steel plate for sealing water and anti-float anchor rod weld
1 according to construction drawing, positioning and resisting flotation anchor pole reinforcement location and aperture on steel plate for sealing water, to the accurate aperture of steel plate for sealing water, Port size deviation should not exceed 0.5%;
Answered when 2 steel plate for sealing water are with anti-float anchor rod reinforcement welding it is two-sided be fully welded, must not have sand holes, solder skip, if any should repair welding immediately.
(2) construction concrete cushion
1 concrete cushion answers vibration compacting when constructing;
2 ensure concrete cushion thickness, guarantee that mat surface is smooth.
(3) construction anti-float anchor rod
1 anti-float anchor rod should be noted that finished product protection when constructing, the construction machinery of anti-float anchor rod drilling on concrete cushion when driving Boarding is answered, prevents concrete cushion from being destroyed by construction machinery;
2 anti-float anchor rods should clean out the earthing on concrete cushion after drilling immediately;
3 ensure the verticality of anti-float anchor rod.
(4) 20 thickness 1:2.5 cement mortar screedings, bolthole saliva cement mortar press polish
1 levelling cement mortar will ensure thickness, guarantee that waterproof material base is smooth, smooth, if discovery cement mortar can not be levelling When should polish in time concrete cushion.
2 anchor pole aperture cement mortar press polish, must not have situations such as out-of-flatness, hole.
(5) 1.5 solid cement base waterproof coatings, 20 thickness 1:2.5 cement mortar protective courses are brushed
1 by polymer modified cement based waterproofing coating and cement in 1:1.5(weight ratio) ratio cement is slowly added into liquid material container, And stirred with electric mixer, mixing time is 5 minutes, and uniform and smooth is wanted in stirring, must not contain pellet shape mixture;
2 brush first of film: checking base's screed-coat, if base is smooth can to brush the first coating film, when brushing can use modeling Material or squeegee are uniformly brushed, and consistency of thickness is made every effort to, and single layer controls between 0.5-0.6mm;
3 brushing second films: after first of curing of coating (tack-free), can uniformly brush the second coating film on it, apply Brushing direction should be vertical with first of brushing direction, and thickness control is between 0.5-0.6mm;
4 brushing third road films: the same second of method, brushing direction should be vertical with second brushing direction, and thickness control exists Between 0.5-0.6mm;
In 5 painting process, inside anti-float anchor rod aperture of constructing emphatically, it is necessary to assure the cement base inside anti-float anchor rod aperture is anti- Water coating thickness, and cement-based waterproof film coated surface is smooth;
The 1:2.5 cement mortar protective course thickness of 6 cement-based waterproof films needs strict control, guarantees thickness in 20mm and less In 22mm.
(6) brushing base treatment agent, 4 thickness SBS waterproof coiled material constructions
1 sprays one layer of neoprene modified pitch adhesive in processed base.With long handle round brush or sprayer by base Layer inorganic agent brushing will brush uniformly in substrate surface, must not leak brush or show-through.Base treatment agent brushing finishes, it is necessary to pass through Waterproof construction can be carried out by reaching within 12 hours or more degree of drying;
2 paving coiled materials: when using Hot-melt construction, the heating of coiled material bottom surface uniformly should avoid excessive heat from burning coiled material;Paving When should flatten compacting, must firm pasting between coiled material and basal plane;Paving coiled material should be rolled immediately after coiled material surface hot melt, exclude coiled material Following air, and spreading firm pasting, must not there is hollowing, gauffer;Seam areas must overflow pitch hot melt when rolling paving coiled material Glue, scraping envelope interface at any time makes to be firmly bonded;Coiled material after paving answer it is smooth, straight, overlap joint size it is correct, must not have distortion;
3 coiled materials are handled at anti-float anchor rod aperture position: when installation of membrane to anti-float anchor rod aperture position, with wallpaper knife to coiled material It is cut, cuts out the circular hole of anti-float anchor rod aperture size, and ensure the paving of coiled material energy to anti-float anchor rod aperture root.
(7) pitch ointment filleting, concrete cover are constructed in 300 ranges around anchor pole
1 pitch ointment belongs to heat construction waterproof material, by pitch ointment solid except being placed in iron pan after unlap, rises slowly Temperature, the side Bian Jiare is stirred continuously, careful burn-out-proof coked agglomerate becomes waste product;
2 when being warming up to 100 DEG C -110 DEG C, when pitch ointment surface black is bright, sufficiently fusing when, constant temperature can construct;
3 by the pitch ointment flow coat of fusing to anti-float anchor rod aperture position, first ensure that and be covered with pitch ointment in aperture, then Again by 300mm range around the uniform flow coat anti-float anchor rod of pitch ointment;
4 (are jammed on foot and expendable deformation do not occur) when pitch ointment is re-condensed into solid, can carry out concrete Protective layer construction.
Embodiment 2
(1) the city ease product the second stage of the project of Qingdao Taizhou road 15,17,19
Project profile
The city ease product second phase project of Qingdao Taizhou road 15,17,19 is located at city, Qingdao City, Taizhou road, South 15,17,19, engineering 72203.16 ㎡ of overall floorage.The engineering level of ground water is higher, basis use anti-float anchor rod form, and anti-float anchor rod quantity compared with More, according to conventional construction mode, the bigger meeting of anti-float anchor rod quantity is so that the increase of leak probability, later period maintenance higher cost.
Condition of construction
This engineering amounts to 1210 anti-float anchor rods, and all anti-float anchor rod end waterproof measures of the project are all made of anti-float anchor rod end Cement-based waterproof film, SBS waterproof roll, pitch ointment and the construction of steel plate for sealing water composite water-proof, and in strict accordance with the engineering method skill Art regulation is constructed.
Application effect
This Anti-Floating Anchor Bar end cement-based waterproof film, SBS waterproof roll, pitch ointment and steel plate for sealing water composite water-proof are applied It is checked and accepted jointly during work by design, supervision, management, construction, unit in charge of construction, meets code requirement, and in subsequent construction mistake Anti-float anchor rod position maintains good waterproof performance in journey.
(2) Qingdao International Exhibition Center conference centre, southern side, the shop project 3# extension project
Project profile
The Qingdao International Exhibition Center conference centre shop project 3# southern side extension project is located at the Qingdao City road Miao Ling 9, and engineering is always built Build 12763.74 ㎡ of area.The engineering height above sea level is lower, and level of ground water is very high, and basis carries out anti-floating using anti-float anchor rod, resists Drogue bar quantity is more, and waterproof construction is difficult, according to conventional construction mode, waterproof construction effect is undesirable, the later period easily Leakage.
Condition of construction
This engineering amounts to 993 anti-float anchor rods, and all anti-float anchor rod end waterproof measures of the project are all made of anti-float anchor rod end Cement-based waterproof film, SBS waterproof roll, pitch ointment and the construction of steel plate for sealing water composite water-proof, and in strict accordance with the engineering method skill Art regulation is constructed.
Application effect
This Anti-Floating Anchor Bar end cement-based waterproof film, SBS waterproof roll, pitch ointment and steel plate for sealing water composite water-proof are applied It is checked and accepted jointly during work by design, supervision, management, construction, unit in charge of construction, meets code requirement, and after being completed delivery Anti-float anchor rod position maintains good waterproof performance.

Claims (1)

1. anti-float anchor rod end multilayer flashing material mating steel plate for sealing water composite water-proof construction technology, which is characterized in that including The following steps:
(1) steel plate for sealing water and anti-float anchor rod weld
1 according to construction drawing, positioning and resisting flotation anchor pole reinforcement location and aperture on steel plate for sealing water, to the accurate aperture of steel plate for sealing water, Port size deviation should not exceed 0.5%;
Answered when 2 steel plate for sealing water are with anti-float anchor rod reinforcement welding it is two-sided be fully welded, must not have sand holes, solder skip, if any should repair welding immediately;
(2) construction concrete cushion
1 concrete cushion answers vibration compacting when constructing;
2 ensure concrete cushion thickness, guarantee that mat surface is smooth;
(3) construction anti-float anchor rod
1 anti-float anchor rod should be noted that finished product protection when constructing, the construction machinery of anti-float anchor rod drilling on concrete cushion when driving Boarding is answered, prevents concrete cushion from being destroyed by construction machinery;
2 anti-float anchor rods should clean out the earthing on concrete cushion after drilling immediately;
3 ensure the verticality of anti-float anchor rod;
(4) 20 thickness 1:2.5 cement mortar screedings, bolthole saliva cement mortar press polish
1 levelling cement mortar will ensure thickness, guarantee that waterproof material base is smooth, smooth, if discovery cement mortar can not be levelling When should polish in time concrete cushion;
2 anchor pole aperture cement mortar press polish, must not have situations such as out-of-flatness, hole;
(5) 1.5 solid cement base waterproof coatings, 20 thickness 1:2.5 cement mortar protective courses are brushed
1 by polymer modified cement based waterproofing coating and cement in 1:1.5(weight ratio) ratio cement is slowly added into liquid material container, And stirred with electric mixer, mixing time is 5 minutes, and uniform and smooth is wanted in stirring, must not contain pellet shape mixture;
2 brush first of film: checking base's screed-coat, if base is smooth can to brush the first coating film, when brushing can use modeling Material or squeegee are uniformly brushed, and consistency of thickness is made every effort to, and single layer controls between 0.5-0.6mm;
3 brushing second films: after first of curing of coating (tack-free), can uniformly brush the second coating film on it, apply Brushing direction should be vertical with first of brushing direction, and thickness control is between 0.5-0.6mm;
4 brushing third road films: the same second of method, brushing direction should be vertical with second brushing direction, and thickness control exists Between 0.5-0.6mm;
In 5 painting process, inside anti-float anchor rod aperture of constructing emphatically, it is necessary to assure the cement base inside anti-float anchor rod aperture is anti- Water coating thickness, and cement-based waterproof film coated surface is smooth;
The 1:2.5 cement mortar protective course thickness of 6 cement-based waterproof films needs strict control, guarantees thickness in 20mm and less In 22mm;
(6) brushing base treatment agent, 4 thickness SBS waterproof coiled material constructions
1 sprays one layer of neoprene modified pitch adhesive in processed base;With long handle round brush or sprayer by base Layer inorganic agent brushing will brush uniformly in substrate surface, must not leak brush or show-through;Base treatment agent brushing finishes, it is necessary to pass through Waterproof construction can be carried out by reaching within 12 hours or more degree of drying;
2 paving coiled materials: when using Hot-melt construction, the heating of coiled material bottom surface uniformly should avoid excessive heat from burning coiled material;Paving When should flatten compacting, must firm pasting between coiled material and basal plane;Paving coiled material should be rolled immediately after coiled material surface hot melt, exclude coiled material Following air, and spreading firm pasting, must not there is hollowing, gauffer;Seam areas must overflow pitch hot melt when rolling paving coiled material Glue, scraping envelope interface at any time makes to be firmly bonded;Coiled material after paving answer it is smooth, straight, overlap joint size it is correct, must not have distortion;
3 coiled materials are handled at anti-float anchor rod aperture position: when installation of membrane to anti-float anchor rod aperture position, with wallpaper knife to coiled material It is cut, cuts out the circular hole of anti-float anchor rod aperture size, and ensure the paving of coiled material energy to anti-float anchor rod aperture root;
(7) pitch ointment filleting, concrete cover are constructed in 300 ranges around anchor pole
1 pitch ointment belongs to heat construction waterproof material, by pitch ointment solid except being placed in iron pan after unlap, rises slowly Temperature, the side Bian Jiare is stirred continuously, careful burn-out-proof coked agglomerate becomes waste product;
2 when being warming up to 100 DEG C -110 DEG C, when pitch ointment surface black is bright, sufficiently fusing when, constant temperature can construct;
3 by the pitch ointment flow coat of fusing to anti-float anchor rod aperture position, first ensure that and be covered with pitch ointment in aperture, then Again by 300mm range around the uniform flow coat anti-float anchor rod of pitch ointment;
4 (are jammed on foot and expendable deformation do not occur) when pitch ointment is re-condensed into solid, can carry out concrete Protective layer construction.
CN201910158146.1A 2019-03-03 2019-03-03 Anti-float anchor rod end multilayer flashing material mating steel plate for sealing water composite water-proof construction technology Pending CN109837894A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910158146.1A CN109837894A (en) 2019-03-03 2019-03-03 Anti-float anchor rod end multilayer flashing material mating steel plate for sealing water composite water-proof construction technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910158146.1A CN109837894A (en) 2019-03-03 2019-03-03 Anti-float anchor rod end multilayer flashing material mating steel plate for sealing water composite water-proof construction technology

Publications (1)

Publication Number Publication Date
CN109837894A true CN109837894A (en) 2019-06-04

Family

ID=66885157

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910158146.1A Pending CN109837894A (en) 2019-03-03 2019-03-03 Anti-float anchor rod end multilayer flashing material mating steel plate for sealing water composite water-proof construction technology

Country Status (1)

Country Link
CN (1) CN109837894A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112854211A (en) * 2021-03-17 2021-05-28 上海宝冶集团有限公司 Waterproof plugging construction method for drilling hole of anchoring end of anti-floating anchor rod
CN113863393A (en) * 2021-10-22 2021-12-31 上海宝冶建筑装饰有限公司 Construction method for waterproofing end of anti-floating anchor rod

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6414428A (en) * 1987-07-08 1989-01-18 Tokyu Kensetsu Kk Water stopping work for opening of underground structure of building and metal therefor
CN204919629U (en) * 2015-02-02 2015-12-30 成都建筑工程集团总公司 Anti sea anchor pole waterproof construction
CN108331031A (en) * 2018-02-08 2018-07-27 中建六局土木工程有限公司 A kind of anti-float anchor rod waterproof construction method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6414428A (en) * 1987-07-08 1989-01-18 Tokyu Kensetsu Kk Water stopping work for opening of underground structure of building and metal therefor
CN204919629U (en) * 2015-02-02 2015-12-30 成都建筑工程集团总公司 Anti sea anchor pole waterproof construction
CN108331031A (en) * 2018-02-08 2018-07-27 中建六局土木工程有限公司 A kind of anti-float anchor rod waterproof construction method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张燕等: "抗浮锚杆在某工程中的应用", 《青岛理工大学学报》 *
李勇等: "浅谈抗浮锚杆的实际工程应用", 《建筑工人》 *
靳艳军等: "滨海工程抗浮锚杆根部防水处理技术", 《建筑技术》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112854211A (en) * 2021-03-17 2021-05-28 上海宝冶集团有限公司 Waterproof plugging construction method for drilling hole of anchoring end of anti-floating anchor rod
CN113863393A (en) * 2021-10-22 2021-12-31 上海宝冶建筑装饰有限公司 Construction method for waterproofing end of anti-floating anchor rod

Similar Documents

Publication Publication Date Title
CN101852031B (en) Construction method of soil covering tank
CN108755983B (en) Waterproof process
CN111042348A (en) Waterproof construction process for base layer in various complex forms
CN105797939A (en) Pipeline rehabilitation method based on iron resin spray-coating
CN109837894A (en) Anti-float anchor rod end multilayer flashing material mating steel plate for sealing water composite water-proof construction technology
CN110206074A (en) A kind of underground waterproof engineering construction technology
CN101787742A (en) Planted roof soil lower deformation joint construction structure and construction method thereof
KR101075723B1 (en) Coating material, use thereof and method for applying said coating material
CN113047459A (en) Construction process for laying HDPE (high-density polyethylene) high-molecular self-adhesive film waterproof coiled material
CN108086684B (en) Construction method for building waterproofing by using non-cured rubber asphalt and application thereof
CN110629893B (en) Construction method of toilet waterproof engineering
CN105133855A (en) Energy-saving and environment-friendly waterproof warming construction method for existing roof surface
WO2003055828A1 (en) Method for coating a cement-containing molding piece
CN113550451A (en) Waterproof construction method for building outer wall
CN114960978B (en) Waterproof method for concrete joint without reserved embedded structure in reconstruction and expansion structure
CN107859142A (en) Anti-corrosion leak-proof layer and preparation method thereof
CN209722876U (en) A kind of structure of interior canal storing facilities of water waterproof layer
CN116537473A (en) Construction method for plastering inner wall of building
CN105178518A (en) Energy-saving environment-friendly waterproof heat-insulating construction method for existing roof
CN204418011U (en) The bridge asphalt pavement structure of the triple water-proof system of a kind of rubber asphalt double sum
CN110820921B (en) Waterscape waterproof structure and construction method thereof
CN104452813B (en) A kind of underground power house gate shaft protected against the effects of immersion method
CN109826158A (en) The production method and structure of a kind of interior canal storing facilities of water waterproof layer
CN110424641A (en) A kind of waterproof and insulation integrated system wet-laying construction technology of modified-high polymer
CN218029283U (en) Arc stand polyurea spraying structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190604

RJ01 Rejection of invention patent application after publication