Method for building an elevator system, and elevator system suitable for carrying out the method Download PDF

Info

Publication number
US12012305B2
US12012305B2 US18/002,278 US202118002278A US12012305B2 US 12012305 B2 US12012305 B2 US 12012305B2 US 202118002278 A US202118002278 A US 202118002278A US 12012305 B2 US12012305 B2 US 12012305B2
Authority
US
United States
Prior art keywords
cable
lifting platform
lifting
platform
pulley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
US18/002,278
Other languages
English (en)
Other versions
US20230339727A1 (en
Inventor
Gabriele Bizzozero
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Inventio AG
Original Assignee
Inventio AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Inventio AG filed Critical Inventio AG
Assigned to INVENTIO AG reassignment INVENTIO AG ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: BIZZOZERO, Gabriele
Publication of US20230339727A1 publication Critical patent/US20230339727A1/en
Application granted granted Critical
Publication of US12012305B2 publication Critical patent/US12012305B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B19/00Mining-hoist operation
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B19/00Mining-hoist operation
    • B66B19/04Installing or removing mining-hoist cars, cages, or skips
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B19/00Mining-hoist operation
    • B66B19/02Installing or exchanging ropes or cables

Definitions

  • a lifting platform that can also be raised and temporarily fixed in the elevator shaft is installed above the machine platform.
  • a group of deflection pulleys is attached to both the lifting platform and the machine platform, wherein a multiply reeved lifting cable is arranged between the group of deflection pulleys of the lifting platform and the group of deflection pulleys of the machine platform in such a way that the machine platform may be raised with the aid of two cable pull devices installed on the machine platform.
  • the lifting platform Before each raising of the machine platform, the lifting platform must be brought to a higher level in the elevator shaft. This is done with the help of a hoist, which is attached to another supporting structure that can be moved and fixed in the elevator shaft and can raise the lifting platform via a lifting cable.
  • the requirement for minimizing the risk of the lifting platform falling can be met with relatively little effort, even if the lifting platform must be positioned in the uppermost region of the elevator shaft that does not yet have any guide rails.
  • This measure ensures that, when a lifting platform that is moving downwards at an impermissibly high speed is stopped by the cable catch device, a lifting platform that is not guided on guide rails does not tip over, but rather maintains its horizontal position. Injuries to assembly personnel and damage to the lifting platform and the walls of the elevator shaft can thus be avoided.
  • a further aspect of the invention relates to an elevator system in an elevator shaft of a building that is in its construction phase, in which elevator system a usable lifting height of the elevator system can be adapted to an increasing height of the building.
  • This elevator system is preferably designed in such a way that it is suitable for carrying out the method described above.
  • the elevator system comprises a machine platform installed in the elevator shaft, which can be raised and temporarily locked along car guide rails, wherein an elevator drive machine having a traction sheave is arranged on the machine platform.
  • the elevator system also comprises an elevator car and a counterweight, which are suspended from the machine platform via suspension means, wherein the suspension means are guided at least over the traction sheave of the elevator drive machine, so that the elevator car and the counterweight can be moved up and down in opposite directions to one another along guide rails in the elevator shaft by the traction sheave via the suspension means.
  • a construction crane 40 is indicated above the protective platform 20 or above the currently upper end of the elevator shaft 2 , with the help of which construction crane the lifting platform 17 can be raised with less effort than with the lifting device 35 , if the construction crane is available when the lifting platform is to be raised.
  • An adaptation of the elevator system 1 to a newly available greater height of the elevator shaft 2 is essentially achieved in that—if necessary—first the protective platform 20 is raised to a higher level. This is usually carried out using a construction crane 40 or a hoist suspended from, for example, a temporarily installed cross member. The lifting platform 17 is then raised with the construction crane or the lifting device 35 and fixed at a height in the elevator shaft 2 which makes it possible to transport the machine platform 10 to the planned new level with the hoist 18 of the lifting platform and to lock the machine platform there.
  • the definition of the installation position refers to the position of the cable pulley level.
  • the cable pulley support 26 with the cable pulleys is fixed to the protective platform 20 , which has been positioned in or on the currently uppermost region of the elevator shaft at the latest when the usable lifting height of the elevator system 1 begins to be adapted to a currently existing height of the building or elevator shaft 2 .
  • the cable catch device 25 . 1 comprises the safety cable fixed point 29 attached to the lifting platform 17 , a load-bearing pulley arrangement 32 coupled to the lifting platform, the cable stop device 30 and the four load-bearing cable portions 31 . 1 - 31 . 4 comprising the safety cable 31 .
  • the safety cable is arranged between the lifting platform 17 and the cable pulley support 26 fixed above the lifting platform in the elevator shaft according to the principle of a block and tackle having the four load-bearing cable portions 31 . 1 - 31 . 4 , wherein a first load-bearing cable portion 31 . 1 of the safety cable 31 is fixed to the safety cable fixed point 29 attached to the lifting platform 17 , and wherein a last load-bearing cable portion 31 . 4 is guided through a cable stop device 30 attached to the lifting platform.
  • the cable catch device 25 . 1 for the lifting platform 17 shown in FIG. 2 solves the problem of ensuring that, on the one hand, the catching force resulting from a catching process passes through the center of gravity S of the lifting platform and, on the other hand, that a free space extending upwards from the center of gravity S space can be realized.
  • this object is achieved by the safety cable 31 —with reference to an imaginary reference plane extending vertically through the center of gravity S of the lifting platform 17 —is guided from a safety cable fixed point 29 on the lifting platform vertically upwards to a vertical first deflection pulley 27 .
  • the lifting platform 17 is shown without the lifting device 35 shown in FIG. 1 , either because the lifting device has been dismantled to enable a crane cable to be coupled to the lifting platform for raising the lifting platform 17 , or because there is no lifting device at all, since it is intended to raise the lifting platform exclusively with the construction crane 40 .
  • FIG. 3 shows a side view of a part of the elevator system 1 according to FIG. 1 in the currently topmost region of the elevator shaft 2 on the left-hand side, and a section A-A through this region on the right-hand side.
  • the lifting platform 17 is equipped with the cable catch device 25 . 1 according to the first embodiment shown in FIG. 2 .
  • FIG. 3 shows the elevator system with the lifting device 35 indicated in FIG. 1 , which is used to raise the lifting platform 17 , because no construction crane is present, or if the construction crane is not available within a reasonable time at the time of the adaptation of the usable lifting height of elevator system.
  • the elevator system 1 according to FIG. 3 which is equipped with the lifting device 35 , additionally has a lifting cable deflection device 36 , a cable pull device 37 , a lifting cable 38 and a lifting cable holder 39 .
  • the lifting cable deflection device which comprises at least one lifting cable deflection pulley 36 . 1 , is advantageously fixed to the protective platform 20 described in connection with FIG. 1 in the region of the passage opening 21 present therein.
  • a first load-bearing portion of the lifting cable 38 is fixed to the lifting platform 17 by means of the lifting cable holder 39 . From this lifting cable holder, the lifting cable is guided vertically upwards to the at least one lifting cable deflection pulley 36 .
  • FIG. 4 shows a side view of a part of the elevator system 1 according to FIG. 1 in the currently topmost region of the elevator shaft 2 on the left-hand side, and a section A-A through this region on the right-hand side.
  • the lifting platform 17 is equipped with a lifting device 35 —as already described in connection with FIG. 3 .
  • the elevator system according to FIG. 4 is equipped with a cable catch device 25 . 2 according to a second embodiment.
  • the cable pulley support 26 of the cable catch device 25 . 2 is equipped with only four vertically arranged deflection pulleys 28 . 1 - 28 .

Landscapes

  • Types And Forms Of Lifts (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
US18/002,278 2020-06-26 2021-06-23 Method for building an elevator system, and elevator system suitable for carrying out the method Active US12012305B2 (en)

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
EP20182623 2020-06-26
EP20182623 2020-06-26
EP20182623.7 2020-06-26
PCT/EP2021/067070 WO2021259969A1 (de) 2020-06-26 2021-06-23 Verfahren zum errichten einer aufzugsanlage sowie zur durchführung des verfahrens geeignete aufzugsanlage

Publications (2)

Publication Number Publication Date
US20230339727A1 US20230339727A1 (en) 2023-10-26
US12012305B2 true US12012305B2 (en) 2024-06-18

Family

ID=71266342

Family Applications (1)

Application Number Title Priority Date Filing Date
US18/002,278 Active US12012305B2 (en) 2020-06-26 2021-06-23 Method for building an elevator system, and elevator system suitable for carrying out the method

Country Status (4)

Country Link
US (1) US12012305B2 (de)
EP (1) EP4172096A1 (de)
CN (1) CN115720568A (de)
WO (1) WO2021259969A1 (de)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US12043519B2 (en) * 2020-10-01 2024-07-23 Inventio Ag Elevator system
WO2022194391A1 (en) * 2021-03-19 2022-09-22 Kone Corporation Method of constructing elevator and construction-time elevator arrangement
DE102023102305A1 (de) 2023-01-31 2024-04-11 Tk Elevator Innovation And Operations Gmbh Hebeanordnung und Verfahren zum Bewegen einer Maschinenplattform oder einer Aufzuganlagen-Maschinenraumeinheit

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2694279A1 (fr) * 1992-08-03 1994-02-04 Otis Elevator Co Ascenseur ou monte-charges, suivant l'avancement du gros-Óoeuvre de la construction de bâtiments.
WO2010100319A1 (en) 2009-03-06 2010-09-10 Kone Corporation Elevator arrangement and method
WO2015003965A1 (de) * 2013-07-10 2015-01-15 Inventio Ag Erweiterung eines schachtbereiches
WO2015003964A1 (de) 2013-07-10 2015-01-15 Inventio Ag Absturzsicherung für eine plattform
CN105073621A (zh) * 2013-03-20 2015-11-18 通力股份公司 电梯的安装装置
WO2017102684A1 (de) 2015-12-14 2017-06-22 Inventio Ag Verfahren zum errichten einer aufzugsanlage und an zunehmende gebäudehöhe anpassbare aufzugsanlage
US9809424B2 (en) * 2012-03-06 2017-11-07 Kone Corporation Method and an elevator arrangement
WO2019068469A1 (de) * 2017-10-06 2019-04-11 Inventio Ag Verfahren zum errichten einer aufzugsanlage mit zunehmender nutzbarer hubhöhe
WO2020088979A1 (de) * 2018-10-30 2020-05-07 Inventio Ag Verfahren zum installieren einer aufzugsanlage
WO2020193119A1 (de) * 2019-03-27 2020-10-01 Inventio Ag Montagevorrichtung und verfahren zur durchführung eines installationsvorgangs in einem aufzugschacht eines aufzugsystems
WO2022069316A1 (de) * 2020-10-01 2022-04-07 Inventio Ag Aufzugsanlage
WO2022135689A1 (en) * 2020-12-22 2022-06-30 Kone Corporation Construction arrangement of an elevator and method
CN115038660A (zh) * 2020-03-16 2022-09-09 株式会社日立制作所 施工用升降机装置
CN115190862A (zh) * 2020-02-28 2022-10-14 通力股份公司 电梯布置和用于建造电梯的方法

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2694279A1 (fr) * 1992-08-03 1994-02-04 Otis Elevator Co Ascenseur ou monte-charges, suivant l'avancement du gros-Óoeuvre de la construction de bâtiments.
WO2010100319A1 (en) 2009-03-06 2010-09-10 Kone Corporation Elevator arrangement and method
US8881872B2 (en) * 2009-03-06 2014-11-11 Kone Corporation Method of installing an elevator
US9809424B2 (en) * 2012-03-06 2017-11-07 Kone Corporation Method and an elevator arrangement
CN105073621A (zh) * 2013-03-20 2015-11-18 通力股份公司 电梯的安装装置
WO2015003965A1 (de) * 2013-07-10 2015-01-15 Inventio Ag Erweiterung eines schachtbereiches
WO2015003964A1 (de) 2013-07-10 2015-01-15 Inventio Ag Absturzsicherung für eine plattform
WO2017102684A1 (de) 2015-12-14 2017-06-22 Inventio Ag Verfahren zum errichten einer aufzugsanlage und an zunehmende gebäudehöhe anpassbare aufzugsanlage
WO2019068469A1 (de) * 2017-10-06 2019-04-11 Inventio Ag Verfahren zum errichten einer aufzugsanlage mit zunehmender nutzbarer hubhöhe
WO2020088979A1 (de) * 2018-10-30 2020-05-07 Inventio Ag Verfahren zum installieren einer aufzugsanlage
WO2020193119A1 (de) * 2019-03-27 2020-10-01 Inventio Ag Montagevorrichtung und verfahren zur durchführung eines installationsvorgangs in einem aufzugschacht eines aufzugsystems
CN115190862A (zh) * 2020-02-28 2022-10-14 通力股份公司 电梯布置和用于建造电梯的方法
CN115038660A (zh) * 2020-03-16 2022-09-09 株式会社日立制作所 施工用升降机装置
WO2022069316A1 (de) * 2020-10-01 2022-04-07 Inventio Ag Aufzugsanlage
WO2022135689A1 (en) * 2020-12-22 2022-06-30 Kone Corporation Construction arrangement of an elevator and method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Machine Translation of WO 2015/003965. *

Also Published As

Publication number Publication date
EP4172096A1 (de) 2023-05-03
CN115720568A (zh) 2023-02-28
US20230339727A1 (en) 2023-10-26
WO2021259969A1 (de) 2021-12-30

Similar Documents

Publication Publication Date Title
US12012305B2 (en) Method for building an elevator system, and elevator system suitable for carrying out the method
US11208296B2 (en) Method for constructing an elevator system having increasing usable lifting height
RU2196096C2 (ru) Способ и устройство для монтажа лифта
US9617121B2 (en) Installation method for an elevator
CA2544881C (en) Method and device for installation of guide rails in a lift shaft
EP2016015B1 (de) Verfahren zur installation des hubseils für einen aufzug
US9890019B2 (en) Arrangement and a method for parallel transport and installation of elevator components
EP2993153A1 (de) Führungsschieneninstallationseinrichtung und Verfahren zur Installation von Führungsschienen
CA2969603A1 (en) Elevator having a movable machine room
US20080308362A1 (en) Cable management assembly and method for construction elevator systems
US12043519B2 (en) Elevator system
WO2020142001A1 (en) A moveable platform
US20160332852A1 (en) Arrangement and a method for transporting material in an elevator shaft
CN205346757U (zh) 一种双动力施工平台
CN112110317A (zh) 一种建筑工程施工用物料提升机
CN213923658U (zh) 用于超高层建筑楼层内吊运材料的运输装置
KR101976724B1 (ko) 엘리베이터 승강로 가이드 레일의 설치방법
TW201722833A (zh) 具有牽引介質用儲存器的升降系統
US20240253950A1 (en) Arrangement and method for installing guide rails of an elevator
CN217478801U (zh) 一种电梯安全系统
US20230042428A1 (en) Lifting device for lifting a payload within an elevator shaft in a controllable manner
FI104813B (fi) Hissin asennusmenetelmä ja asennuslaitteisto
CN210366573U (zh) 在电梯井中安装电梯的设备

Legal Events

Date Code Title Description
AS Assignment

Owner name: INVENTIO AG, SWITZERLAND

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:BIZZOZERO, GABRIELE;REEL/FRAME:062163/0555

Effective date: 20221116

FEPP Fee payment procedure

Free format text: ENTITY STATUS SET TO UNDISCOUNTED (ORIGINAL EVENT CODE: BIG.); ENTITY STATUS OF PATENT OWNER: LARGE ENTITY

STPP Information on status: patent application and granting procedure in general

Free format text: DOCKETED NEW CASE - READY FOR EXAMINATION

STPP Information on status: patent application and granting procedure in general

Free format text: NON FINAL ACTION MAILED

STPP Information on status: patent application and granting procedure in general

Free format text: RESPONSE TO NON-FINAL OFFICE ACTION ENTERED AND FORWARDED TO EXAMINER

STPP Information on status: patent application and granting procedure in general

Free format text: AWAITING TC RESP., ISSUE FEE NOT PAID

STPP Information on status: patent application and granting procedure in general

Free format text: NOTICE OF ALLOWANCE MAILED -- APPLICATION RECEIVED IN OFFICE OF PUBLICATIONS

STPP Information on status: patent application and granting procedure in general

Free format text: PUBLICATIONS -- ISSUE FEE PAYMENT RECEIVED

STCF Information on status: patent grant

Free format text: PATENTED CASE