US11434617B2 - Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like - Google Patents

Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like Download PDF

Info

Publication number
US11434617B2
US11434617B2 US16/775,369 US202016775369A US11434617B2 US 11434617 B2 US11434617 B2 US 11434617B2 US 202016775369 A US202016775369 A US 202016775369A US 11434617 B2 US11434617 B2 US 11434617B2
Authority
US
United States
Prior art keywords
foundation
collar
spread
pedestal
bolts
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active, expires
Application number
US16/775,369
Other versions
US20200165792A1 (en
Inventor
Allan P. Henderson
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Terraconn Consultants Inc
Terracon Consultants Inc
Original Assignee
Terraconn Consultants Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Terraconn Consultants Inc filed Critical Terraconn Consultants Inc
Priority to US16/775,369 priority Critical patent/US11434617B2/en
Assigned to TERRACON CONSULTANTS, INC. reassignment TERRACON CONSULTANTS, INC. ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: HENDERSON, ALLAN P.
Publication of US20200165792A1 publication Critical patent/US20200165792A1/en
Priority to US17/874,395 priority patent/US11814808B2/en
Application granted granted Critical
Publication of US11434617B2 publication Critical patent/US11434617B2/en
Active legal-status Critical Current
Adjusted expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • E02D27/425Foundations for poles, masts or chimneys specially adapted for wind motors masts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • E02D27/08Reinforcements for flat foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D37/00Repair of damaged foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/80Ground anchors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/08Members specially adapted to be used in prestressed constructions
    • E04C5/12Anchoring devices
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/20Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
    • F03D13/22Foundations specially adapted for wind motors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/12Geometrical or physical properties corrugated
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F05INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
    • F05BINDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
    • F05B2230/00Manufacture
    • F05B2230/80Repairing, retrofitting or upgrading methods
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/728Onshore wind turbines
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P70/00Climate change mitigation technologies in the production process for final industrial or consumer products
    • Y02P70/50Manufacturing or production processes characterised by the final manufactured product

Definitions

  • the present invention is related to the field of foundations for the support of tall, heavy and/or large towers and, more particularly, to a retrofit structure addition and method for reinforcing existing concrete gravity spread foundations currently used to support wind turbines and similar structures, especially those foundations which have failed or are failing due to long term dynamic fatigue.
  • the present invention is directed to a retrofit spread foundation reinforcing structure and method for restoring the integrity of existing gravity spread foundations and extending the useful life thereof.
  • the retrofit spread foundation reinforcing structure includes a generally cylindrical shape sustaining member forming an annular cementitious reinforcing collar addition positioned around the central pedestal and above the expanded base or horizontal spread section of an original gravity spread foundation.
  • the shape sustaining member forming the annular collar addition may be embodied as a corrugated metal pipe (CMP) having a diameter greater than the diameter of the pedestal.
  • CMP corrugated metal pipe
  • the collar addition thus fully encircles and confines the central pedestal with the base of the collar pressing against the upper surface of the horizontal spread section of the already existing spread foundation adjacent to the engaging interface between the bottom of the pedestal and the top of the spread foundation below the pedestal.
  • a plurality of radially extending bolts extend horizontally through the CMP and cementitious ring of the collar and into the pedestal of the original foundation.
  • Soil and/or rock anchor bolts are placed to extend vertically from the top of the cementitious ring of the collar addition down through the horizontal spread section and into the underlying soil and/or rock substrate beneath the spread section.
  • anchor bolts are used herein for ease of description and are understood by those skilled in the art to include tensioning and/or connecting anchors embodied as bolts as well as anchors having tensioning and/or connecting components other than bolts.
  • the radial bolts and soil and/or rock anchor bolts are post-tensioned in the manner described in my earlier patents, U.S. Pat. Nos. 7,533,505, 5,826,387, 6,672,023, and 7,155,875, all of which are hereby incorporated by reference in their entirety as if fully set forth herein and sometimes are referred to herein as “my prior patents”, to place the entire foundation under high unit compression loading in both the horizontal and vertical directions which strengthens the cold joint interface between the pedestal and the spread section.
  • the soil and/or rock anchor bolts are tightened so as to exceed the maximum uplift expected from overturning forces of the wind turbine structure on the foundation.
  • the entire foundation with the reinforcing collar addition is able to withstand the various loads with the concrete thereof always remaining in compression and the bolts always in static tension.
  • Another object of the present invention is to provide a retrofit spread foundation reinforcing structure addition in accordance with the preceding object that includes a reinforcing collar positioned around the central pedestal and above the expanded base or horizontal spread section of a gravity spread foundation.
  • a further object of the present invention is to provide a retrofit spread foundation reinforcing structure addition in accordance with the preceding objects in which the collar includes a CMP having a diameter greater than an outer diameter of the pedestal to encircle the pedestal, an area between the CMP and the pedestal being filled with cementitious material to define an annular ring bounded on an outer perimeter by the CMP, the base of the collar resting on, or pressing against, the upper surface of the horizontal spread section of the foundation.
  • Yet a further object of the present invention is to provide a retrofit spread foundation reinforcing structure addition in accordance with the preceding objects that includes post-tensioned soil and/or rock anchor bolts extending vertically from the top of the cementitious annular ring of the collar down through the horizontal spread section of the foundation and into the underlying soil and/or rock substrate.
  • Still a further object of the present invention is to provide a retrofit spread foundation reinforcing structure addition in accordance with the preceding objects that includes post-tensioned radially extending bolts that extend horizontally through the CMP and annular cementitious collar and into the pedestal of the foundation.
  • Another object of the present invention is to provide a retrofit spread foundation reinforcing structure addition in accordance with the preceding objects that, when installed on an existing gravity spread foundation, places the retrofit portion of the foundation under high unit compression loading through tightening of the anchor bolts so as to exceed the maximum internal tension expected from overturning forces of the wind turbine structure on the foundation.
  • Yet another object of the present invention is to provide a retrofit spread foundation reinforcing structure addition in accordance with the preceding objects that may be efficiently installed in support of gravity spread foundations of various configurations.
  • Still another object of the present invention is to provide a method of installing a retrofit spread foundation reinforcing structure addition in accordance with the preceding objects that includes placement of a CMP around the base of the pedestal of a spread foundation structure and filling the annular area between the CMP and the pedestal with cementitious material to form a collar that encircles and supports the spread foundation pedestal.
  • Yet a further object of the present invention is to provide a method of installing a retrofit spread foundation reinforcing structure addition in accordance with the preceding objects in which soil and/or rock anchor bolts are installed vertically through the collar and horizontal spread section of the original foundation and into the underlying soil and/or rock substrate either before or after the cementitious material is poured into the annular ring between the CMP and the pedestal to reinforce the cold joint engaging interface between the bottom of the pedestal and the upper surface of the central part of the spread section below the pedestal.
  • Another object of the present invention is to provide a method of installing a retrofit spread foundation reinforcing structure addition in accordance with the preceding objects in which the anchor bolts are post-tensioned in a specified sequence to place uniform tension on the foundation.
  • FIG. 1 is a front view of a wind turbine supported on a conventional gravity spread foundation with the retrofit spread foundation reinforcing structure addition installed thereon in accordance with the present invention.
  • FIG. 2 is a sectional side view of one type of conventional concrete gravity spread foundation.
  • FIG. 3 is a top view of the conventional spread foundation shown in FIG. 2 .
  • FIG. 4 is a sectional side view of the conventional spread foundation shown in FIG. 2 with the retrofit spread foundation reinforcing structure addition installed thereon in accordance with the present invention.
  • FIG. 5 is a top view of the conventional spread foundation reinforced with the retrofit spread foundation reinforcing structure addition shown in FIG. 4 .
  • FIG. 5A is a side cutaway view of the collar showing the radial bolts and strand hoops.
  • FIGS. 6A-6C are top cutaway views of each of three respective layers of radial bolts as installed according to the retrofit structure and method of the present invention.
  • FIG. 6D is an isolated top view of the existing spread foundation tower base flange as shown in relationship to the radial bolts in FIGS. 6A-6C .
  • FIGS. 7A and 7B are side views of the three radial bolt layers shown in FIGS. 6A-6C showing the vertical spacing in their layered configuration as when installed.
  • FIG. 7C is an enlarged view of a radial bolt like those shown in FIGS. 7A and 7B .
  • FIG. 7D is an enlarged view of the coupler for the radial bolts shown in FIGS. 7A-7C .
  • FIG. 8 shows a soil and/or rock anchor bolt in a partial cutaway view of one side of the original foundation as retrofitted with the reinforcing structure addition of the present invention.
  • FIG. 8A is an enlarged view of the drill hole sleeve and foam fill used when the reinforcing collar is constructed before the anchor bolts are in place.
  • FIG. 9 is an enlarged view of Detail 9 shown in FIG. 5 , without the radial bolts inserted in the radial bolt holes, depicting the manner in which the drill holes for the anchor bolts are spaced from the three radial bolt layers shown in FIGS. 6A-6C, 7A and 7B and staggered radially with respect to each other.
  • FIG. 10 is a top view of the circumference of the retrofit collar showing the soil and/or rock anchor bolt locations and a preferred sequence order for tensioning the soil and/or rock anchor bolts when installing the collar.
  • the present invention is directed to a foundation collar reinforcing structure addition, generally designated by reference numeral 10 , for a conventional existing gravity spread foundation generally designated by reference numeral 12 .
  • the gravity spread foundation 12 includes an expanded base or horizontal spread section 14 and a central pedestal 16 upon which a tall and/or heavy tower such as a wind turbine, generally designated by reference numeral 18 , is supported.
  • the reinforcing structure addition 10 according to the present invention includes an annular collar 20 , positioned around the central pedestal 16 and above the expanded base or horizontal spread section 14 of the gravity spread foundation 12 to confine the pedestal.
  • the reinforcing structure addition 10 also exerts compressive force to strengthen the engaging interface 17 which is a cold joint between the bottom of the pedestal and the top of the central part of the spread section under the pedestal 16 .
  • the horizontal spread section 14 of the existing gravity spread foundation 12 extends outwardly on all sides of the pedestal 16 and may be octagonal as shown in FIG. 3 , or other shapes such as circular, square and the like.
  • the tower 18 is secured to the pedestal 16 with a plurality of tower anchor bolts 19 that are secured at their lower ends to an embedment ring 21 as is known in the art and described in my prior patents.
  • the collar 20 as positioned around the central pedestal 16 and above the expanded base or horizontal spread section 14 of the gravity spread foundation 12 , includes a shape sustaining member, generally designated by reference numeral 15 , around its outer perimeter and a ring of cementitious material 24 .
  • the shape sustaining outer member 15 is preferably embodied as a corrugated metal pipe (CMP) 22 and will be referred to as such hereinafter.
  • CMP corrugated metal pipe
  • other perimeter forming structures could be used as long as such alternate structures properly define the periphery of the ring of cementitious material and provide for post tensioning of the radial bolts and the soil and/or anchor bolts as discussed herein.
  • the CMP 22 is generally constructed of a plurality of sections that are bolted together to form a circle or a generally circular ring.
  • the diameter of the CMP 22 is greater than the diameter of the foundation pedestal 16 and defines the outer perimeter of the ring of cementitious material 24 which is poured into and fills the annular area, generally designated by reference numeral 26 , between the outer side of the pedestal 16 and the CMP 22 .
  • the collar 20 thus fully encircles the central pedestal 16 with the base 28 of the collar 20 resting on the upper surface 30 of the horizontal spread section 14 of the foundation 12 (see FIG. 4 ).
  • the width or thickness of the cementitious annular collar when completed is preferably about 3.5′.
  • the collar 20 does not have to rest directly on the upper surface 30 of the spread section 14 of the foundation since a layer of material could be interposed between the collar and the top of the spread section. However, the collar must press against the spread section 14 in accordance with the present invention.
  • the upper surface 81 of the collar bounded by the CMP 22 is preferably about level with the upper surface 83 of the foundation pedestal 16 .
  • the top and bottom of the CMP are preferably cut to form a plane that varies no more than about +/ ⁇ 2′′ from level.
  • the diameter of the CMP is generally between about 19′ and about 25′, with a CMP pipe tolerance for out of roundness of about 3′′.
  • a plurality of radially extending bolts generally designated by reference numeral 40 with strand hoops 44 extend horizontally through the CMP 22 and the cementitious material 24 of the annular ring 26 of the collar 20 and into the pedestal 16 of the foundation 12 as can be seen in FIGS. 4, 5 and 5A .
  • the upper and lower bolt layers are circumferentially reinforced by the wire tied strand hoops 44 at about 6′′ intervals.
  • the innermost ends generally designated by reference numeral 42 of the radial bolts 40 are received into holes 58 drilled into the side of the pedestal 16 while the length of the radial bolts that extends through the cementitious ring 26 is preferably enclosed within a sleeve 68 (see FIGS.
  • the radial bolts 40 which anchor the collar 20 to the pedestal 16 of the foundation 12 , are post-tensioned once the cementitious material has hardened, preferably to about 40% of their ultimate strength.
  • washers fitting into the corrugation of the CMP and having a flat outer surface to contact the tensioning nuts are placed against the outer side of the CMP for proper tensioning of the radial bolts, as is known in the art.
  • tension plates may be placed on the inside or the outside of the CMP for the same purpose.
  • FIGS. 6A, 6B and 6C there are preferably three layers of radial bolts 40 including a top layer 50 , a middle layer 52 and a bottom layer 54 .
  • the radially extending bolts 40 in each layer are on substantially the same plane and equidistantly spaced from one another like the spokes of a wheel.
  • the bolts in each layer are offset with respect to the bolts in the other layers so that, if the three layers were placed directly on top of one another, none of the bolts of one layer would be in vertical alignment with the bolts in the adjacent layers.
  • the radial bolts are positioned so as not to interfere with the tower anchor bolts 19 in the existing tower base flange 56 shown in isolation in FIG. 6D .
  • the radial bolt layers 50 , 52 , 54 are vertically spaced from one another with the area between and around the layers being filled with the cementitious material 24 of the annular collar 20 .
  • the vertical spacing between the layers is preferably about between about 12′′ and about 18′′, and more preferably about 18′′.
  • the diameter of the radial bolts 40 is preferably between about 1′′ and about 2′′.
  • the radial bolts 40 are preferably inserted into core holes 58 that are drilled into the side of the central pedestal of the existing gravity spread foundation to a depth of between about 36′′ to about 60′′, and preferably about 54′′.
  • the diameter of the radial bolt core holes 58 descends in increments as the drilling approaches the center of the pedestal.
  • the core hole at the CMP and inward for about 3′′ has a diameter of about 2.5′′.
  • the core hole has a diameter of about 2′′.
  • the final 30′′ or so of the hole has a diameter of about 1.75′′.
  • the innermost ends 42 of the radial bolts 40 are preferably secured within the drilled foundation core holes 58 with an adhesive such as epoxy 41 that is inserted into the holes during installation of the radial bolts.
  • an adhesive such as epoxy 41 that is inserted into the holes during installation of the radial bolts.
  • the part 62 of the radial bolts that extends through the collar is covered with a sleeve 68 having a length of between about 15′′ and about 26′′, and preferably about 21′′.
  • the radial bolts include two parts.
  • the collar embedded part 62 of the radial bolts 40 is preferably joined with the foundation embedded sleeved part 60 of the radial bolts 40 by a coupler 64 .
  • the coupler 64 is preferably enclosed within a sleeve 66 having a diameter of about 2.5′′ and a length of about 4′′.
  • the collar portion 62 of the radial bolts is preferably between about 4′ and about 5′ in length, and more preferably about 4.5′, and preferably is also encased within a sleeve 68 to prevent engagement of the radial bolt with the cementitious material.
  • the outer ends 70 of the radial bolts extend approximately 12′′ beyond the outer perimeter of the collar CMP 22 , although the length of the projecting ends 70 may be greater or lesser as needed for the particular foundation being reinforced.
  • a plurality of soil and/or rock anchor bolts 80 are placed to extend vertically from the upper surface 81 of the cementitious annular ring 26 of the collar 20 down through the horizontal spread section 14 of the gravity spread foundation and into the underlying soil and/or rock substrate 90 .
  • the soil and/or rock anchor bolts 80 , or anchors are between about 25′ and about 40′ in length, and preferably are about 30′ in length.
  • the upper end of the anchor bolts is preferably enclosed within a sleeve 82 to prevent engagement of the bolt with the cementitious material in a “no bond” area 97 (see FIG. 8 ).
  • the extent of the “no bond” area 97 is defined by the sleeve 82 that is preferably at least 10′ in length.
  • the sleeve 82 extends substantially through the height of the collar 20 , through the spread section 14 of the foundation and about two to three feet into the underlying soil and/or rock substrate 90 .
  • the distance from the upper surface 81 of the collar to the bottom 101 of the spread section is approximately 7.5′, with the 10′ sleeve extending about an additional 2.5′ into the underlying substrate.
  • the lower bonded area 85 of the anchor bolts, below the horizontal spread section 14 and extending into the underlying soil and/or rock substrate 90 is generally between about 14′ and about 30′ in length, and is preferably about 19′ in length.
  • the total embedment length of the soil and/or rock anchor bolts 80 is generally on the order of between about 24′ and about 39′, and preferably is about 29′. Following construction of the collar, the soil and/or rock anchor bolts are post-tensioned in the “no bond” area to about 60% of their ultimate strength.
  • tubular PVC sleeves 88 about 6′′ in diameter are placed vertically in the excavated region for the anchor bolts (see FIGS. 8 and 8A ) and secured for the concrete pour. Once the cementitious material is set, the soil and/or rock anchor bolts are drilled down through the hollow center of the PVC sleeves 88 and, to prevent water entry, the upper 3′′ of the drill hole sleeve 88 is filled with foam 91 as shown in FIG. 8A .
  • the anchor bolts are drilled in holes 100 in between adjoining radial bolt holes 58 in each radial bolt layer as shown in FIG. 9 such that the anchor bolts 80 and the radial bolts 40 inserted in the holes 58 do not interfere with one another.
  • the diameter of the drill hole 100 for the rock anchor bolts is between about 4′′ and about 6′′, and is preferably about 5.5′′.
  • grout is poured into the annular space 71 around the lower end of the anchor bolts in the bonded area 85 and in the annular space 73 between the outer surface of the sleeves 82 and the inner surface of the PVC tubes 88 in the “no-bond” area 97 .
  • the anchor bolts 80 are post-tensioned in the manner described in my prior patents to place the entire collar 20 and spread foundation 12 under high unit compression loading.
  • FIG. 10 A preferred sequence for tensioning of the anchor bolts is shown in FIG. 10 .
  • the first and second bolts to be tensioned are on opposite sides of the collar, and the third and fourth bolts to be tensioned are on opposite sides that are 90° out from the first and second bolts.
  • the soil and/or rock anchor bolts 80 are tensioned in opposing pairs as set forth in FIG. 10 to ensure even and uniform tension on the collar.
  • the soil and/or rock anchor bolts may be part of rock anchors, soil anchors, helical anchors and the like, depending upon the makeup of the underlying support substrate.
  • the soil and/or rock anchor bolts in conjunction with the collar that supports and contains the pedestal, serve to reinforce and strengthen the cold joint engaging interface 17 between the bottom of the pedestal and the top of the spread section under the pedestal.
  • the reinforcing addition of the present invention effectively provides compressive force on the engaging interface 17 to increase the strength, stiffness and load bearing capacity of the spread foundation.
  • a preferred construction sequence for constructing the reinforcing collar according to the present invention is as follows:
  • the reinforcing structure addition according to the present invention can extend the life of an original gravity spread foundation that would otherwise have failed or is failing by at least an additional 20-25 years.
  • the present invention is also directed to a method of modifying an existing gravity spread reinforced concrete foundation, increasing the foundation stiffness and the rotational stiffness of the entire wind turbine structure. Modifying the existing gravity spread foundation also increases the turbine resistance to overturn and extends the foundation life by at least an additional 25 years, which is the expected turbine life.
  • the present invention also includes a method of modifying an existing shallow gravity spread foundation to a deep foundation, alleviating a number of potential failures found in connection with shallow foundations. These failures can include overturn, frost heave, erosion and scour, differential settlement, tilting, foundation/soil gapping, flooding, vertical seismic acceleration, horizontal seismic acceleration, liquefaction, collapsible soils and expansive soils.
  • the present invention provides a method of restoring integrity and continued use to a failed or failing concrete gravity spread foundation.
  • the retrofit reinforcement structure addition including the collar with radial bolts and soil and/or rock anchor bolts extending horizontally and vertically through the collar, respectively, serves to reinforce, strengthen and provide compressive force upon the engaging interface between the bottom of the pedestal and the top of the spread section under the pedestal.
  • the useful life of an otherwise failed or failing gravity foundation is extended for at least an additional 25 years which is the expected turbine life period.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Sustainable Development (AREA)
  • Sustainable Energy (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Foundations (AREA)

Abstract

A retrofit reinforcing structure addition and method for an existing gravity spread foundation for a wind turbine or the like having a central pedestal and a spread section is provided. The retrofit structure addition includes a collar formed around the pedestal of the spread foundation. The collar is formed by a shape sustaining member, such as a CMP, placed around the pedestal to define an annular ring between the CMP and the pedestal that is filled with cementitious material. Radial bolts extend horizontally through the collar and into the side of the pedestal. Soil and/or rock anchor bolts extend vertically through the collar, the spread portion of the foundation and into the underlying soil and/or rock substrate. The radial and anchor bolts are post-tensioned to ensure that the cementitious material of the collar remains in compression and the bolts are always in static tension, strengthening the original gravity spread foundation and extending the fatigue life thereof.

Description

This application is a divisional of prior application Ser. No. 15/585,775 filed May 3, 2017, which is a divisional of application Ser. No. 14/870,955 filed Sep. 30, 2015, which issued as U.S. Pat. No. 9,783,950 on Oct. 10, 2017, which claimed priority from U.S. provisional application, Ser. No. 62/060,743 filed Oct. 7, 2014, and also claims the priority of U.S. provisional application, Ser. No. 62/211,158 filed Aug. 28, 2015, and hereby claims the priority thereof to which it is entitled.
BACKGROUND OF THE INVENTION Field of the Invention
The present invention is related to the field of foundations for the support of tall, heavy and/or large towers and, more particularly, to a retrofit structure addition and method for reinforcing existing concrete gravity spread foundations currently used to support wind turbines and similar structures, especially those foundations which have failed or are failing due to long term dynamic fatigue.
Description of the Related Art
Concrete gravity spread foundations are often used to support turbines in the 1.5 megawatt (MW) range of which there are several thousand in the U.S. Conventional gravity spread foundation construction relies on reinforced concrete theory and designs which is inappropriate for very dynamic structures like a wind turbine. As a result, these gravity spread foundations are susceptible to long term fatigue failures which can result in collapse of the foundation. Such collapses have been known to occur after as few as 8 to 13 years, well before the expiration of turbine life which is on the order of 20-25 years or more. Therefore, there is a need for a structure and method by which gravity spread foundations may be reinforced to extend their fatigue life well beyond the turbine life.
SUMMARY OF THE INVENTION
In view of the foregoing, the present invention is directed to a retrofit spread foundation reinforcing structure and method for restoring the integrity of existing gravity spread foundations and extending the useful life thereof. The retrofit spread foundation reinforcing structure includes a generally cylindrical shape sustaining member forming an annular cementitious reinforcing collar addition positioned around the central pedestal and above the expanded base or horizontal spread section of an original gravity spread foundation. The shape sustaining member forming the annular collar addition may be embodied as a corrugated metal pipe (CMP) having a diameter greater than the diameter of the pedestal. A ring of cementitious material is poured into and fills the annular area between the outer side of the central pedestal and the surrounding shape sustaining member or CMP. The collar addition thus fully encircles and confines the central pedestal with the base of the collar pressing against the upper surface of the horizontal spread section of the already existing spread foundation adjacent to the engaging interface between the bottom of the pedestal and the top of the spread foundation below the pedestal. A plurality of radially extending bolts extend horizontally through the CMP and cementitious ring of the collar and into the pedestal of the original foundation. Soil and/or rock anchor bolts are placed to extend vertically from the top of the cementitious ring of the collar addition down through the horizontal spread section and into the underlying soil and/or rock substrate beneath the spread section. The terms “soil and/or rock anchor bolts” or “anchor bolts” are used herein for ease of description and are understood by those skilled in the art to include tensioning and/or connecting anchors embodied as bolts as well as anchors having tensioning and/or connecting components other than bolts.
The radial bolts and soil and/or rock anchor bolts are post-tensioned in the manner described in my earlier patents, U.S. Pat. Nos. 7,533,505, 5,826,387, 6,672,023, and 7,155,875, all of which are hereby incorporated by reference in their entirety as if fully set forth herein and sometimes are referred to herein as “my prior patents”, to place the entire foundation under high unit compression loading in both the horizontal and vertical directions which strengthens the cold joint interface between the pedestal and the spread section. The soil and/or rock anchor bolts are tightened so as to exceed the maximum uplift expected from overturning forces of the wind turbine structure on the foundation. As a result, the entire foundation with the reinforcing collar addition is able to withstand the various loads with the concrete thereof always remaining in compression and the bolts always in static tension.
Accordingly, it is an object of the present invention to provide a retrofit spread foundation reinforcing structure addition and method that restores the integrity of existing gravity spread foundations and extends the useful life thereof for many additional years.
Another object of the present invention is to provide a retrofit spread foundation reinforcing structure addition in accordance with the preceding object that includes a reinforcing collar positioned around the central pedestal and above the expanded base or horizontal spread section of a gravity spread foundation.
A further object of the present invention is to provide a retrofit spread foundation reinforcing structure addition in accordance with the preceding objects in which the collar includes a CMP having a diameter greater than an outer diameter of the pedestal to encircle the pedestal, an area between the CMP and the pedestal being filled with cementitious material to define an annular ring bounded on an outer perimeter by the CMP, the base of the collar resting on, or pressing against, the upper surface of the horizontal spread section of the foundation.
Yet a further object of the present invention is to provide a retrofit spread foundation reinforcing structure addition in accordance with the preceding objects that includes post-tensioned soil and/or rock anchor bolts extending vertically from the top of the cementitious annular ring of the collar down through the horizontal spread section of the foundation and into the underlying soil and/or rock substrate.
Still a further object of the present invention is to provide a retrofit spread foundation reinforcing structure addition in accordance with the preceding objects that includes post-tensioned radially extending bolts that extend horizontally through the CMP and annular cementitious collar and into the pedestal of the foundation.
Another object of the present invention is to provide a retrofit spread foundation reinforcing structure addition in accordance with the preceding objects that, when installed on an existing gravity spread foundation, places the retrofit portion of the foundation under high unit compression loading through tightening of the anchor bolts so as to exceed the maximum internal tension expected from overturning forces of the wind turbine structure on the foundation.
Yet another object of the present invention is to provide a retrofit spread foundation reinforcing structure addition in accordance with the preceding objects that may be efficiently installed in support of gravity spread foundations of various configurations.
Still another object of the present invention is to provide a method of installing a retrofit spread foundation reinforcing structure addition in accordance with the preceding objects that includes placement of a CMP around the base of the pedestal of a spread foundation structure and filling the annular area between the CMP and the pedestal with cementitious material to form a collar that encircles and supports the spread foundation pedestal.
Yet a further object of the present invention is to provide a method of installing a retrofit spread foundation reinforcing structure addition in accordance with the preceding objects in which soil and/or rock anchor bolts are installed vertically through the collar and horizontal spread section of the original foundation and into the underlying soil and/or rock substrate either before or after the cementitious material is poured into the annular ring between the CMP and the pedestal to reinforce the cold joint engaging interface between the bottom of the pedestal and the upper surface of the central part of the spread section below the pedestal.
Another object of the present invention is to provide a method of installing a retrofit spread foundation reinforcing structure addition in accordance with the preceding objects in which the anchor bolts are post-tensioned in a specified sequence to place uniform tension on the foundation.
These together with other objects and advantages which will become subsequently apparent reside in the details of construction and operation as more fully hereinafter described and claimed, reference being had to the accompanying drawings forming a part hereof, wherein like numerals refer to like parts throughout.
BRIEF DESCRIPTION OF THE DRAWINGS
FIG. 1 is a front view of a wind turbine supported on a conventional gravity spread foundation with the retrofit spread foundation reinforcing structure addition installed thereon in accordance with the present invention.
FIG. 2 is a sectional side view of one type of conventional concrete gravity spread foundation.
FIG. 3 is a top view of the conventional spread foundation shown in FIG. 2.
FIG. 4 is a sectional side view of the conventional spread foundation shown in FIG. 2 with the retrofit spread foundation reinforcing structure addition installed thereon in accordance with the present invention.
FIG. 5 is a top view of the conventional spread foundation reinforced with the retrofit spread foundation reinforcing structure addition shown in FIG. 4.
FIG. 5A is a side cutaway view of the collar showing the radial bolts and strand hoops.
FIGS. 6A-6C are top cutaway views of each of three respective layers of radial bolts as installed according to the retrofit structure and method of the present invention. FIG. 6D is an isolated top view of the existing spread foundation tower base flange as shown in relationship to the radial bolts in FIGS. 6A-6C.
FIGS. 7A and 7B are side views of the three radial bolt layers shown in FIGS. 6A-6C showing the vertical spacing in their layered configuration as when installed.
FIG. 7C is an enlarged view of a radial bolt like those shown in FIGS. 7A and 7B.
FIG. 7D is an enlarged view of the coupler for the radial bolts shown in FIGS. 7A-7C.
FIG. 8 shows a soil and/or rock anchor bolt in a partial cutaway view of one side of the original foundation as retrofitted with the reinforcing structure addition of the present invention.
FIG. 8A is an enlarged view of the drill hole sleeve and foam fill used when the reinforcing collar is constructed before the anchor bolts are in place.
FIG. 9 is an enlarged view of Detail 9 shown in FIG. 5, without the radial bolts inserted in the radial bolt holes, depicting the manner in which the drill holes for the anchor bolts are spaced from the three radial bolt layers shown in FIGS. 6A-6C, 7A and 7B and staggered radially with respect to each other.
FIG. 10 is a top view of the circumference of the retrofit collar showing the soil and/or rock anchor bolt locations and a preferred sequence order for tensioning the soil and/or rock anchor bolts when installing the collar.
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
Although only one preferred embodiment of the invention is explained in detail, it is to be understood that the embodiment is given by way of illustration only. It is not intended that the invention be limited in its scope to the details of construction and arrangement of components set forth in the following description or illustrated in the drawings. Also, in describing the preferred embodiments, specific terminology will be resorted to for the sake of clarity. It is to be understood that each specific term includes all technical equivalents which operate in a similar manner to accomplish a similar purpose.
As shown in FIG. 1, the present invention is directed to a foundation collar reinforcing structure addition, generally designated by reference numeral 10, for a conventional existing gravity spread foundation generally designated by reference numeral 12. The gravity spread foundation 12 includes an expanded base or horizontal spread section 14 and a central pedestal 16 upon which a tall and/or heavy tower such as a wind turbine, generally designated by reference numeral 18, is supported. The reinforcing structure addition 10 according to the present invention includes an annular collar 20, positioned around the central pedestal 16 and above the expanded base or horizontal spread section 14 of the gravity spread foundation 12 to confine the pedestal. The reinforcing structure addition 10 also exerts compressive force to strengthen the engaging interface 17 which is a cold joint between the bottom of the pedestal and the top of the central part of the spread section under the pedestal 16.
As shown in isolation in FIGS. 2 and 3, the horizontal spread section 14 of the existing gravity spread foundation 12 extends outwardly on all sides of the pedestal 16 and may be octagonal as shown in FIG. 3, or other shapes such as circular, square and the like. The tower 18 is secured to the pedestal 16 with a plurality of tower anchor bolts 19 that are secured at their lower ends to an embedment ring 21 as is known in the art and described in my prior patents.
As best shown in FIG. 4, the collar 20 as positioned around the central pedestal 16 and above the expanded base or horizontal spread section 14 of the gravity spread foundation 12, includes a shape sustaining member, generally designated by reference numeral 15, around its outer perimeter and a ring of cementitious material 24. The shape sustaining outer member 15 is preferably embodied as a corrugated metal pipe (CMP) 22 and will be referred to as such hereinafter. However, other perimeter forming structures could be used as long as such alternate structures properly define the periphery of the ring of cementitious material and provide for post tensioning of the radial bolts and the soil and/or anchor bolts as discussed herein.
The CMP 22 is generally constructed of a plurality of sections that are bolted together to form a circle or a generally circular ring. The diameter of the CMP 22 is greater than the diameter of the foundation pedestal 16 and defines the outer perimeter of the ring of cementitious material 24 which is poured into and fills the annular area, generally designated by reference numeral 26, between the outer side of the pedestal 16 and the CMP 22. The collar 20 thus fully encircles the central pedestal 16 with the base 28 of the collar 20 resting on the upper surface 30 of the horizontal spread section 14 of the foundation 12 (see FIG. 4). As measured from the outer side surface of the pedestal to the CMP, the width or thickness of the cementitious annular collar when completed is preferably about 3.5′.
Alternatively, the collar 20 does not have to rest directly on the upper surface 30 of the spread section 14 of the foundation since a layer of material could be interposed between the collar and the top of the spread section. However, the collar must press against the spread section 14 in accordance with the present invention.
The upper surface 81 of the collar bounded by the CMP 22 is preferably about level with the upper surface 83 of the foundation pedestal 16. The top and bottom of the CMP are preferably cut to form a plane that varies no more than about +/−2″ from level. The diameter of the CMP is generally between about 19′ and about 25′, with a CMP pipe tolerance for out of roundness of about 3″.
A plurality of radially extending bolts generally designated by reference numeral 40 with strand hoops 44 extend horizontally through the CMP 22 and the cementitious material 24 of the annular ring 26 of the collar 20 and into the pedestal 16 of the foundation 12 as can be seen in FIGS. 4, 5 and 5A. The upper and lower bolt layers are circumferentially reinforced by the wire tied strand hoops 44 at about 6″ intervals. The innermost ends generally designated by reference numeral 42 of the radial bolts 40 are received into holes 58 drilled into the side of the pedestal 16 while the length of the radial bolts that extends through the cementitious ring 26 is preferably enclosed within a sleeve 68 (see FIGS. 7A-7D) to prevent the bolts from bonding with or adhering to the cementitious material 24 when poured and cured. The radial bolts 40, which anchor the collar 20 to the pedestal 16 of the foundation 12, are post-tensioned once the cementitious material has hardened, preferably to about 40% of their ultimate strength. Preferably, washers fitting into the corrugation of the CMP and having a flat outer surface to contact the tensioning nuts are placed against the outer side of the CMP for proper tensioning of the radial bolts, as is known in the art. Alternatively or additionally, tension plates may be placed on the inside or the outside of the CMP for the same purpose.
As shown in FIGS. 6A, 6B and 6C, there are preferably three layers of radial bolts 40 including a top layer 50, a middle layer 52 and a bottom layer 54. The radially extending bolts 40 in each layer are on substantially the same plane and equidistantly spaced from one another like the spokes of a wheel. As between layers, the bolts in each layer are offset with respect to the bolts in the other layers so that, if the three layers were placed directly on top of one another, none of the bolts of one layer would be in vertical alignment with the bolts in the adjacent layers. In addition, the radial bolts are positioned so as not to interfere with the tower anchor bolts 19 in the existing tower base flange 56 shown in isolation in FIG. 6D.
As shown in FIGS. 7A and 7B, the radial bolt layers 50, 52, 54 are vertically spaced from one another with the area between and around the layers being filled with the cementitious material 24 of the annular collar 20. The vertical spacing between the layers is preferably about between about 12″ and about 18″, and more preferably about 18″. The diameter of the radial bolts 40 is preferably between about 1″ and about 2″.
The radial bolts 40 are preferably inserted into core holes 58 that are drilled into the side of the central pedestal of the existing gravity spread foundation to a depth of between about 36″ to about 60″, and preferably about 54″. The diameter of the radial bolt core holes 58 descends in increments as the drilling approaches the center of the pedestal. The core hole at the CMP and inward for about 3″ has a diameter of about 2.5″. For the next approximately 21″, the core hole has a diameter of about 2″. The final 30″ or so of the hole has a diameter of about 1.75″. The innermost ends 42 of the radial bolts 40 are preferably secured within the drilled foundation core holes 58 with an adhesive such as epoxy 41 that is inserted into the holes during installation of the radial bolts. Preferably the part 62 of the radial bolts that extends through the collar is covered with a sleeve 68 having a length of between about 15″ and about 26″, and preferably about 21″.
As shown in the embodiment of FIGS. 7C and 7D, the radial bolts include two parts. The collar embedded part 62 of the radial bolts 40 is preferably joined with the foundation embedded sleeved part 60 of the radial bolts 40 by a coupler 64. The coupler 64 is preferably enclosed within a sleeve 66 having a diameter of about 2.5″ and a length of about 4″. The collar portion 62 of the radial bolts is preferably between about 4′ and about 5′ in length, and more preferably about 4.5′, and preferably is also encased within a sleeve 68 to prevent engagement of the radial bolt with the cementitious material. After tensioning, the outer ends 70 of the radial bolts extend approximately 12″ beyond the outer perimeter of the collar CMP 22, although the length of the projecting ends 70 may be greater or lesser as needed for the particular foundation being reinforced.
As shown in FIGS. 4, 5 and 8, a plurality of soil and/or rock anchor bolts 80 are placed to extend vertically from the upper surface 81 of the cementitious annular ring 26 of the collar 20 down through the horizontal spread section 14 of the gravity spread foundation and into the underlying soil and/or rock substrate 90. The soil and/or rock anchor bolts 80, or anchors, are between about 25′ and about 40′ in length, and preferably are about 30′ in length. The upper end of the anchor bolts is preferably enclosed within a sleeve 82 to prevent engagement of the bolt with the cementitious material in a “no bond” area 97 (see FIG. 8). The extent of the “no bond” area 97 is defined by the sleeve 82 that is preferably at least 10′ in length. The sleeve 82 extends substantially through the height of the collar 20, through the spread section 14 of the foundation and about two to three feet into the underlying soil and/or rock substrate 90. In the embodiment shown, the distance from the upper surface 81 of the collar to the bottom 101 of the spread section is approximately 7.5′, with the 10′ sleeve extending about an additional 2.5′ into the underlying substrate. The lower bonded area 85 of the anchor bolts, below the horizontal spread section 14 and extending into the underlying soil and/or rock substrate 90, is generally between about 14′ and about 30′ in length, and is preferably about 19′ in length. The total embedment length of the soil and/or rock anchor bolts 80, including the bonded 85 and “no bond” 97 areas, is generally on the order of between about 24′ and about 39′, and preferably is about 29′. Following construction of the collar, the soil and/or rock anchor bolts are post-tensioned in the “no bond” area to about 60% of their ultimate strength.
If the cementitious material of the retrofit collar addition is to be poured before the soil and/or rock anchor bolts are drilled, tubular PVC sleeves 88 about 6″ in diameter are placed vertically in the excavated region for the anchor bolts (see FIGS. 8 and 8A) and secured for the concrete pour. Once the cementitious material is set, the soil and/or rock anchor bolts are drilled down through the hollow center of the PVC sleeves 88 and, to prevent water entry, the upper 3″ of the drill hole sleeve 88 is filled with foam 91 as shown in FIG. 8A.
The anchor bolts are drilled in holes 100 in between adjoining radial bolt holes 58 in each radial bolt layer as shown in FIG. 9 such that the anchor bolts 80 and the radial bolts 40 inserted in the holes 58 do not interfere with one another. The diameter of the drill hole 100 for the rock anchor bolts is between about 4″ and about 6″, and is preferably about 5.5″. When the anchor bolts are in place in the drill holes 100, grout is poured into the annular space 71 around the lower end of the anchor bolts in the bonded area 85 and in the annular space 73 between the outer surface of the sleeves 82 and the inner surface of the PVC tubes 88 in the “no-bond” area 97. The anchor bolts 80 are post-tensioned in the manner described in my prior patents to place the entire collar 20 and spread foundation 12 under high unit compression loading.
A preferred sequence for tensioning of the anchor bolts is shown in FIG. 10. As shown, the first and second bolts to be tensioned are on opposite sides of the collar, and the third and fourth bolts to be tensioned are on opposite sides that are 90° out from the first and second bolts. The soil and/or rock anchor bolts 80 are tensioned in opposing pairs as set forth in FIG. 10 to ensure even and uniform tension on the collar. The soil and/or rock anchor bolts may be part of rock anchors, soil anchors, helical anchors and the like, depending upon the makeup of the underlying support substrate.
The soil and/or rock anchor bolts, in conjunction with the collar that supports and contains the pedestal, serve to reinforce and strengthen the cold joint engaging interface 17 between the bottom of the pedestal and the top of the spread section under the pedestal. With the radial bolts horizontally securing the collar to the pedestal, and the anchor bolts providing a vertical connection of the collar to the spread section, the reinforcing addition of the present invention effectively provides compressive force on the engaging interface 17 to increase the strength, stiffness and load bearing capacity of the spread foundation.
A preferred construction sequence for constructing the reinforcing collar according to the present invention is as follows:
    • 1) construct temporary turbine supports (temporary guys or brackets);
    • 2) excavate soil from atop the spread foundation for construction of retrofit collar; pile soil adjacent to the retrofit excavation;
    • 3) expose rebar at radial bolt and rock anchor locations;
    • 4) core two 2″ diameter holes 24″ long into foundation pedestal for each bolt;
    • 5) expand the 2″ core to 2.5″ for the first 3″ of the core;
    • 6) drill 1.75″ hole with percussion drill beyond the 2″ cored hole to within about 30″ of the center of the pedestal for each radial bolt; radial bolt holes extend about 1″ beyond the end of the 0.5″ radial bolt;
    • 7) inject approximately 30 cubic inches of epoxy into the back of the holes drilled for the radial bolts;
    • 8) insert into each radial bolt hole the 1.5″ grade 75 all thread radial bolt with PVC sleeve sealed at the end of the PVC to the bolt with epoxy;
    • 9) turn the couplers onto the bolt;
    • 10) turn into the coupler the sleeved outer 4.5′ of 1.5″ grade 75 all thread bolt with wire tied strand hoops on the upper and lower radial bolt circles;
    • 11) insert multi-plate CMP sections over radial bolts and bolt CMP sections together;
    • 12) place half oval washers over radial bolts into the CMP depressions; turn nuts onto the radial bolts and snug against the washers;
    • 13) place 6″ PVC tubes vertical for rock anchors to be drilled through and secure for concrete pour;
    • 14) pour concrete retrofit;
    • 15) drill and install rock anchors, centralized, and grouted in place in the bond and “no bond” areas, upper ends of said rock anchors being enclosed within a sleeve in the “no bond” area;
    • 16) post-tension radial bolts;
    • 17) install rock anchor plates grouted in place; and
    • 18) post-tension rock anchors.
The steps to be undertaken with respect to a wind turbine installed on an existing gravity spread foundation before and after installing the reinforcing collar according to the present invention are as follows:
    • 1) coordinate retrofit foundation work with electrical work;
    • 2) verify turbine de-energized before any work is begun;
    • 3) provide backup power generator to allow for control of the wind turbine in an idling condition;
    • 4) disconnect cables from transformers;
    • 5) temporarily remove and store the transformer for reinstallation;
    • 6) demolish the transformer concrete pad, if necessary to remove the pad;
    • 7) temporarily remove the existing stairs and store for reinstallation;
    • 8) demolish the existing stair landing concrete slab, if necessary;
    • 9) locate grounding wires and protect during excavation; if necessary reroute or disconnect and reinstall grounding wires as needed;
    • 10) control water that enters the excavation and the turbine pad;
    • 11) remove anchor bolt caps and grout from caps and bolt threads;
    • 12) relax the tower anchor bolts and thoroughly clean the threads;
    • 13) maintain tower anchor bolt nuts in a tight and snug condition; tighten with impact wrench to snug condition;
    • 14) repair or reinstall ground wires as required;
    • 15) route or reroute conduit as required;
    • 16) remove the temporary supports after the retrofit foundation has been constructed complete in place and concrete cured;
    • 17) construct new support slab and conduit vault for transformer, if required;
    • 18) restore anchor bolt tension;
    • 19) reinstall tower access stair; and
    • 20) reinstall transformer and connect the electrical cables.
The anchor bolts are tightened so as to exceed the maximum internal tension expected from overturning forces of the wind turbine structure on the foundation. As a result, the entire foundation with the reinforcing collar is able to withstand the various loads with the concrete thereof always remaining in compression and both the radial and the soil and/or rock anchor bolts always in static tension. As a result, the reinforcing structure addition according to the present invention can extend the life of an original gravity spread foundation that would otherwise have failed or is failing by at least an additional 20-25 years.
The present invention is also directed to a method of modifying an existing gravity spread reinforced concrete foundation, increasing the foundation stiffness and the rotational stiffness of the entire wind turbine structure. Modifying the existing gravity spread foundation also increases the turbine resistance to overturn and extends the foundation life by at least an additional 25 years, which is the expected turbine life.
The present invention also includes a method of modifying an existing shallow gravity spread foundation to a deep foundation, alleviating a number of potential failures found in connection with shallow foundations. These failures can include overturn, frost heave, erosion and scour, differential settlement, tilting, foundation/soil gapping, flooding, vertical seismic acceleration, horizontal seismic acceleration, liquefaction, collapsible soils and expansive soils.
Finally, the present invention provides a method of restoring integrity and continued use to a failed or failing concrete gravity spread foundation. As evident from the foregoing description, the retrofit reinforcement structure addition including the collar with radial bolts and soil and/or rock anchor bolts extending horizontally and vertically through the collar, respectively, serves to reinforce, strengthen and provide compressive force upon the engaging interface between the bottom of the pedestal and the top of the spread section under the pedestal. When restored and supported by the retrofit reinforcement structure addition of the present invention, the useful life of an otherwise failed or failing gravity foundation is extended for at least an additional 25 years which is the expected turbine life period.
The foregoing descriptions and drawings should be considered as illustrative only of the principles of the invention. The invention may be configured in a variety of shapes and sizes and is not limited by the dimensions of the preferred embodiment. Numerous applications of the present invention will readily occur to those skilled in the art. Therefore, it is not desired to limit the invention to the specific examples disclosed or the exact construction and operation shown and described. Rather, all suitable modifications and equivalents may be resorted to, falling within the scope of the invention.

Claims (16)

What is claimed is:
1. A retrofit reinforcing structure addition for an existing spread foundation that has a central pedestal and a horizontal spread section, the retrofit reinforcing structure addition comprising:
a collar surrounding the central pedestal of the existing spread foundation, a base of the collar pressing on an upper surface of the horizontal spread section of the existing spread foundation;
a plurality of radial bolts each having an outermost, tensioning-nut carrying end and an innermost, nut-free end, the radial bolts extending in a generally horizontal orientation from an outer perimeter of the collar, and through the collar, such that the innermost nut-free ends extend into a plurality of adhesive-filled holes in the central pedestal, respectively, whereby the adhesive-filled holes secure the innermost nut-free ends of the radial bolts into the central pedestal; and
a plurality of soil and/or rock anchor bolts extending in a generally vertical orientation through the collar and the horizontal spread section and into an underlying soil and/or rock substrate below the horizontal spread section.
2. The retrofit reinforcing structure addition as set forth in claim 1, wherein said soil and/or rock anchor bolts and said radial bolts are post tensioned.
3. The retrofit reinforcing structure addition as set forth in claim 1, wherein said existing spread foundation has a tower already supported thereon when the retrofit reinforcing structure addition is added.
4. The retrofit reinforcing structure addition as set forth in claim 1, wherein said collar includes a shape sustaining outer member having a perimeter greater than an outer diameter of the pedestal to define a region between the shape sustaining outer member and the central pedestal, said region having cementitious material poured therein which hardens to form a body of cementitious material surrounding the pedestal and contained within the shape sustaining outer member.
5. The retrofit reinforcing structure addition as set forth in claim 4, wherein the perimeter of said shape sustaining outer member is generally circular.
6. The retrofit reinforcing structure addition as set forth in claim 5, wherein said shape sustaining outer member is a corrugated metal pipe (CMP), against which CMP the tensioning nuts carried by the radial bolts are tensioned.
7. The retrofit reinforcing structure addition as set forth in claim 4, wherein said radial bolts include a plurality of layers of extending radial bolts vertically spaced from one another.
8. A retrofitted reinforced gravity spread foundation supporting a tower or a wind turbine comprising:
a concrete gravity spread foundation having a central pedestal and a horizontal spread section, the tower or the wind turbine being mounted on the central pedestal;
a reinforcing structure addition added to the concrete gravity spread foundation and including a supporting member surrounding the central pedestal of the concrete gravity spread foundation, a base of the supporting member pressing on an upper surface of the horizontal spread section of the concrete gravity spread foundation;
a plurality of post-tensioned radial bolts extending in substantially horizontal orientation through the supporting member and into a plurality of adhesive-filled holes, respectively, formed in the central pedestal securing the radial bolts therein; and
a plurality of post-tensioned anchor bolts extending in a substantially vertical orientation through the supporting member and the horizontal spread section and into an underlying soil and/or rock substrate.
9. The retrofitted reinforced gravity spread foundation as set forth in claim 8, wherein said post-tensioned radial bolts are arranged to be in an upper layer, a middle layer and a lower layer, said layers being spaced vertically from one another.
10. The retrofitted reinforced gravity spread foundation as set forth in claim 9, wherein the post-tensioned radial bolts in each layer are offset with respect to the post-tensioned radial bolts in other layers such that, if the three layers were placed directly on top of one another, the post-tensioned radial bolts in one layer would not be in vertical alignment with the post-tensioned radial bolts in the adjacent layers.
11. The retrofitted reinforced gravity spread foundation as set forth in claim 8, wherein said supporting member is a collar.
12. The retrofitted reinforced gravity spread foundation as set forth in claim 11, wherein said collar includes a shape sustaining member having a perimeter greater than an outer diameter of the central pedestal to define a region between the shape sustaining member and the central pedestal, a cementitious material being poured into said region and hardened to form a body of cementitious material surrounding the central pedestal and contained within the shape sustaining member.
13. The retrofitted reinforced gravity spread foundation as set forth in claim 12, wherein the perimeter of said shape sustaining member is generally circular.
14. The retrofitted reinforced gravity spread foundation as set forth in claim 13, wherein said shape sustaining member includes a corrugated metal pipe (CMP).
15. The retrofitted reinforced gravity spread foundation as set forth in claim 14, wherein said post-tensioned radial bolts extend through said CMP and said body of cementitious material.
16. The retrofitted reinforced gravity spread foundation as set forth in claim 8, wherein a lower portion of said central pedestal engages a central upper portion of said horizontal spread section at an engagement interface, said plurality of post tensioned anchor bolts reinforcing the engagement interface between the lower portion of the central pedestal and the central upper portion of the horizontal spread section.
US16/775,369 2014-10-07 2020-01-29 Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like Active 2035-11-22 US11434617B2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
US16/775,369 US11434617B2 (en) 2014-10-07 2020-01-29 Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like
US17/874,395 US11814808B2 (en) 2014-10-07 2022-07-27 Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like

Applications Claiming Priority (5)

Application Number Priority Date Filing Date Title
US201462060743P 2014-10-07 2014-10-07
US201562211158P 2015-08-28 2015-08-28
US14/870,955 US9783950B2 (en) 2014-10-07 2015-09-30 Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like
US15/585,775 US10648150B2 (en) 2014-10-07 2017-05-03 Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like
US16/775,369 US11434617B2 (en) 2014-10-07 2020-01-29 Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
US15/585,775 Division US10648150B2 (en) 2014-10-07 2017-05-03 Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like

Related Child Applications (1)

Application Number Title Priority Date Filing Date
US17/874,395 Continuation US11814808B2 (en) 2014-10-07 2022-07-27 Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like

Publications (2)

Publication Number Publication Date
US20200165792A1 US20200165792A1 (en) 2020-05-28
US11434617B2 true US11434617B2 (en) 2022-09-06

Family

ID=55632428

Family Applications (4)

Application Number Title Priority Date Filing Date
US14/870,955 Active US9783950B2 (en) 2014-10-07 2015-09-30 Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like
US15/585,775 Active US10648150B2 (en) 2014-10-07 2017-05-03 Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like
US16/775,369 Active 2035-11-22 US11434617B2 (en) 2014-10-07 2020-01-29 Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like
US17/874,395 Active US11814808B2 (en) 2014-10-07 2022-07-27 Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like

Family Applications Before (2)

Application Number Title Priority Date Filing Date
US14/870,955 Active US9783950B2 (en) 2014-10-07 2015-09-30 Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like
US15/585,775 Active US10648150B2 (en) 2014-10-07 2017-05-03 Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like

Family Applications After (1)

Application Number Title Priority Date Filing Date
US17/874,395 Active US11814808B2 (en) 2014-10-07 2022-07-27 Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like

Country Status (2)

Country Link
US (4) US9783950B2 (en)
CA (2) CA3019073C (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20240026631A1 (en) * 2021-04-12 2024-01-25 Rwe Renewables Europe & Australia Gmbh Retrofit for existing wind turbine foundations, retrofitted wind turbine foundation and method for retrofitting a wind turbine foundation

Families Citing this family (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102011087022A1 (en) * 2011-11-24 2013-05-29 Wobben Properties Gmbh Device and method for anchoring a wind energy plant
US9783950B2 (en) 2014-10-07 2017-10-10 Allan P. Henderson Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like
US10544559B2 (en) 2016-11-02 2020-01-28 Inventus Holdings, Llc Pier and mat foundation fortification and monitoring system
CN107091005A (en) * 2017-05-24 2017-08-25 常熟风范电力设备股份有限公司 A kind of reinforcement type electric force pole tower
CN107100192B (en) * 2017-06-19 2022-06-07 湖南科技大学 Local reinforcing device and method for foundation ring of wind generating set
CN107237266B (en) * 2017-06-27 2023-02-28 中铁第四勘察设计院集团有限公司 Open cut rock anchor combined foundation and reverse operation construction method thereof
CN107859050B (en) * 2017-09-29 2019-12-13 新疆金风科技股份有限公司 Wind driven generator foundation and construction method thereof
CN108360549A (en) * 2018-01-09 2018-08-03 上海斯耐迪工程咨询有限公司 Anchor pole bar planting foundation construction method of the mountainous region photovoltaic gradient more than 25 degree of angles
US11085165B2 (en) * 2018-04-19 2021-08-10 RRC Power & Energy, LLC Post-tension tube foundation and method of assembling same
US10662605B2 (en) * 2018-04-19 2020-05-26 RRC Power & Energy, LLC Post-tension tube foundation and method of assembling same
CN108797633B (en) * 2018-06-12 2020-04-21 国网四川省电力公司技能培训中心 Island type high-voltage line tower footing protection structure and construction method thereof
US11661718B2 (en) * 2018-07-25 2023-05-30 Terracon Consultants, Inc. Concrete pier foundation with lateral shear reinforcing loops and methods of constructing the same
US11365523B2 (en) 2018-11-13 2022-06-21 Terracon Consultants, Inc. Methods for constructing tensionless concrete pier foundations and foundations constructed thereby
KR102160628B1 (en) * 2018-11-19 2020-09-29 한국건설기술연구원 Wind turbine structure for retrofitting spread footing in partial repowering , and construction method for the same
US11274412B2 (en) * 2019-01-31 2022-03-15 Terracon Consultants, Inc. Reinforcement structures for tensionless concrete pier foundations and methods of constructing the same
US11885092B2 (en) 2019-01-31 2024-01-30 Terracon Consultants, Inc. Reinforcement structures for tensionless concrete pier foundations and methods of constructing the same
CN110700334B (en) * 2019-09-25 2021-04-27 江苏筑岩建设有限公司 Rapid repairing method for fan foundation
CN111155571A (en) * 2019-12-25 2020-05-15 湖北瑞宏新能源设备有限公司 Foundation anchor bolt reinforcing structure of wind driven generator and foundation anchor bolt fracture reinforcing method
JP7536396B2 (en) 2020-06-24 2024-08-20 鹿島建設株式会社 Methods for reinforcing the foundation footing of existing bridge piers
CN112112201A (en) * 2020-09-03 2020-12-22 中天钢铁集团有限公司 Rapid treatment method for rolling mill foundation
CN112064664A (en) * 2020-09-17 2020-12-11 武大巨成结构股份有限公司 Improved structure and improved method for fan foundation
CN113338365B (en) * 2021-06-25 2022-11-15 中国华能集团清洁能源技术研究院有限公司 Reinforced structure of onshore fan expanded foundation pipe pile and construction method
CN113700614A (en) * 2021-09-16 2021-11-26 华能(浙江)能源开发有限公司清洁能源分公司 Gravity type foundation for offshore wind power
CN114592536A (en) * 2022-03-23 2022-06-07 山东建筑大学 Fan foundation transformation structure and construction method
EP4431679A1 (en) * 2023-03-17 2024-09-18 Nordex Energy Spain, S.A.U. Reinforcement system for a tower of a wind turbine, tower of a wind turbine and method of reinforcing a tower of a wind turbine

Citations (79)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US732485A (en) 1903-01-30 1903-06-30 William N Wight Composite column and beam.
US969039A (en) 1909-03-20 1910-08-30 John Wunder Reinforced concrete structure.
US1139384A (en) 1913-05-22 1915-05-11 Harrison S Taft Apparatus for constructing concrete columns.
US1189459A (en) 1915-04-10 1916-07-04 Emil O Lundin Electrical pole and pole-base.
US1529895A (en) 1924-07-21 1925-03-17 Chance John H La Sectional foundation for mounting signal poles and the like
US1647925A (en) 1925-04-25 1927-11-01 May John Walter Anchor footing for steel towers
US2377055A (en) 1944-05-31 1945-05-29 Joseph H Thornley Pile cap
US2625815A (en) 1943-10-23 1953-01-20 Eric A Black Adjustable anchorage
US2971295A (en) 1955-03-21 1961-02-14 Phillips Petroleum Co Prestressed concrete units and structures
US3646748A (en) 1970-03-24 1972-03-07 Frederic A Lang Tendons for prestressed concrete and process for making such tendons
USRE27732E (en) 1971-02-22 1973-08-14 Reinforcement of concrete structures
US3798868A (en) 1972-04-07 1974-03-26 D Loranger Method of building construction
US3927497A (en) 1972-11-15 1975-12-23 Hitachi Ltd Supporting structure of pressure vessel
US4043133A (en) 1976-07-21 1977-08-23 Yegge Lawrence R Structure and method of constructing and test-loading pile anchored foundations
US4051661A (en) 1976-09-15 1977-10-04 Bethlehem Steel Corporation Wire strand and rope
US4068445A (en) 1975-02-18 1978-01-17 A. B. Chance Company Lightweight, screw anchor supported foundation and method of installing same
US4092811A (en) 1977-02-14 1978-06-06 T. Y. Lin International Cooling tower, construction method therefor and precast prestressed concrete building units
US4094222A (en) * 1975-06-09 1978-06-13 Hilti Aktiengesellschaft Adhesively secured anchor bolt
DE2754577A1 (en) 1977-12-08 1979-06-13 Bateman Ltd E Conveyor installation method - by excavating for foundations, then casting in whilst support members are held up in position
US4197695A (en) 1977-11-08 1980-04-15 Bethlehem Steel Corporation Method of making sealed wire rope
US4247225A (en) 1979-09-06 1981-01-27 Kamak Corporation Alignment device
WO1984003531A1 (en) 1983-03-03 1984-09-13 Bakvis Beheer Bv Device for securing an upstanding elongated element at its lower end to the upper surface of a pedestal
JPS6092518A (en) 1983-10-26 1985-05-24 Taisei Corp Connection of pile heads under water
EP0160135A1 (en) 1982-11-29 1985-11-06 Raymond E. Hutchinson Tendon for post-tensioning prestressed concrete and process for making the tendon
JPS61109826A (en) 1984-11-02 1986-05-28 Nikken Sekkei:Kk Reinforcing metal fitting for pile-foundation connection
JPS6471987A (en) 1987-09-04 1989-03-16 Gen Motors Corp Cable drive type window regulator
US4866903A (en) 1987-01-06 1989-09-19 Ferstay William G Positioning device
US4887691A (en) 1988-11-04 1989-12-19 Rotondo/Penn-Cast Modular wall construction using posts and panels
JPH04353117A (en) 1991-05-29 1992-12-08 Zenitakagumi:Kk Wire anchor body and anchoring method
US5218805A (en) 1991-08-19 1993-06-15 Superior Precast, Inc. Post assembly and noise barrier wall
JPH05311678A (en) 1992-05-12 1993-11-22 Chiyoda Corp Foundation combined with pile
US5505033A (en) 1988-12-06 1996-04-09 501 Hitachi Metals Ltd. Column base structure and connection arrangement
JPH08338034A (en) 1995-06-14 1996-12-24 Hitachi Ltd Fixed construction of crane, fixing method thereof and withdrawal method of fixed construction
US5586417A (en) 1994-11-23 1996-12-24 Henderson; Allan P. Tensionless pier foundation
US5623792A (en) 1996-05-24 1997-04-29 Crumpacker; William H. Grave marker leveling
JPH09256390A (en) 1996-03-18 1997-09-30 Geotop Corp Vibration-isolation pile foundation
JPH1113150A (en) * 1997-06-23 1999-01-19 Nakamura:Kk Bond anchor method
JPH11181797A (en) 1997-12-18 1999-07-06 Modern Material:Kk Method for fixing support for retaining-wall block and foundation member for use therein
US5966882A (en) 1994-12-19 1999-10-19 Naito; Kingo Structure of base of column and construction method for base of column
US6102118A (en) 1998-12-30 2000-08-15 Moore; Curt A. Multi-purpose adjustable centralizer system with tool
KR20010057453A (en) 1999-12-23 2001-07-04 이구택 Steel pier anchorage system using large deformed bar
JP2001200582A (en) 2000-01-17 2001-07-27 Ps Corp Prestress introduction method for concrete disk structure
JP2002061201A (en) 2000-08-16 2002-02-28 Kinya Miura Foundation structure and its construction method
WO2002027105A1 (en) 2000-09-27 2002-04-04 Allan P Henderson Perimeter weighted foundation for wind turbines and the like
US20020050110A1 (en) 2001-10-26 2002-05-02 Ytterberg Carl N. Reinforced shrinkage compensating concrete slab structure
US20020095878A1 (en) 2000-12-05 2002-07-25 Henderson Allan P. Tilt-up and telescopic support tower for large structures
DE10105472A1 (en) 2001-02-05 2002-08-22 Straeb Gmbh & Co Geb Height-adjustable foundation for posts for traffic signs etc. has tubular holder with hollow crumple zone filled and enclosed by soft mortar encasing material
WO2002099204A1 (en) 2001-06-06 2002-12-12 Corus Uk Ltd Ground anchorage apparatus
JP2003013442A (en) 2001-07-03 2003-01-15 Ashimori Ind Co Ltd Cast-in-place pile construction method and its structure
FR2833029A1 (en) 2001-11-30 2003-06-06 Pierre Louis Glacon Box for making cavity for upright beam in concrete foundation is made from expanded metal with two opposite holes for transverse bar
JP2003232046A (en) 2002-02-07 2003-08-19 Ohbayashi Corp Steel pipe damper and locking foundation structure using the same
US6659691B1 (en) 2002-07-08 2003-12-09 Richard M. Berry Pile array assembly system for reduced soil liquefaction
US6665990B1 (en) 2000-03-06 2003-12-23 Barr Engineering Co. High-tension high-compression foundation for tower structures
US6705058B1 (en) 1999-02-12 2004-03-16 Newmark International Inc. Multiple-part pole
US20040261340A1 (en) 2003-06-27 2004-12-30 Thomas Behlinger Fastening arrangement of a machine base and method of fastening the same
EP1526278A1 (en) 2003-10-21 2005-04-27 GMB Beton- en industriebouw noord west B.V. Wind turbine foundation
JP2005220554A (en) 2004-02-04 2005-08-18 Railway Technical Res Inst Construction method of concrete structure of axial prestressed construction making use of spiral hoop and its concrete structure
CA2551712A1 (en) 2006-07-05 2008-01-05 Con-Tech Systems Ltd. Void form for constructing post-tensioned foundation piles
US7533505B2 (en) 2003-01-06 2009-05-19 Henderson Allan P Pile anchor foundation
US7618217B2 (en) 2003-12-15 2009-11-17 Henderson Allan P Post-tension pile anchor foundation and method therefor
JP2010065454A (en) 2008-09-11 2010-03-25 Mitsui Eng & Shipbuild Co Ltd Foundation structure of tower-like structure
US7905069B1 (en) 2005-12-30 2011-03-15 Aero Solutions, Llc Reinforcing systems to strengthen monopole towers
WO2011029994A1 (en) 2009-09-11 2011-03-17 Peikko Group Oy Connecting element and radial reinforcement structure
US20110173897A1 (en) 2010-01-20 2011-07-21 Stacey Schneider Apparatus and method for protecting a downspout of a gutter
US20120047830A1 (en) 2006-09-21 2012-03-01 Ahmed Phuly Fatigue resistant foundation
WO2012037450A1 (en) 2010-09-17 2012-03-22 Ensoft, Inc. Foundation for wind turbine generator
WO2012062425A2 (en) 2010-11-09 2012-05-18 Rehau Ag + Co System for reinforcing and setting up a supporting post for the passage of a heat transfer medium, and method for producing the supporting post
US20120151860A1 (en) 2010-12-15 2012-06-21 Yeou-Fong Li Ductile shear reinforced bar layout applied to reinforced concrete shear wall structures
US20120266447A1 (en) 2011-04-21 2012-10-25 Francisco Diaz-Vallellanes Anti-theft devices for electrical wires
DE202012006606U1 (en) 2012-07-07 2012-11-12 Alexander Nikulin module
US20120314540A1 (en) 2011-06-07 2012-12-13 Alter Josef K Hollow rebar for crosshole sonic logging access tubes and longitudinal concrete reinforcing in drilled shafts
US20130129474A1 (en) 2010-04-21 2013-05-23 Wobben Properties Gmbh Wind power plant foundation and wind power plant
US20130255169A1 (en) * 2012-03-30 2013-10-03 Allan P. Henderson Cementitious foundation cap with post-tensioned helical anchors
US20140260223A1 (en) 2013-03-14 2014-09-18 Allison Transmission Inc. System And Method For Controlling Pump Performance In A Transmission
US20150075099A1 (en) * 2013-08-08 2015-03-19 University Of Utah Research Foundation Elongate member reinforcement
US20150376859A1 (en) 2006-09-21 2015-12-31 Ahmed Phuly Fatigue Resistant Foundation
US9783950B2 (en) 2014-10-07 2017-10-10 Allan P. Henderson Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like
US20180264680A1 (en) 2006-09-21 2018-09-20 Ahmed Phuly Foundation with pedestal and ribs for towers
US20200032478A1 (en) 2016-06-06 2020-01-30 Robert Carl Rajewski Hydrovac

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2948995A (en) * 1953-02-24 1960-08-16 Shell Oil Co Connections between reinforced, precast concrete structures and method of making same
US5761875A (en) * 1996-08-27 1998-06-09 Newmark International, Inc. Reinforced concrete pole with attachment mechanism
US6513291B2 (en) * 2001-04-23 2003-02-04 David R. Gilsdorf Concrete slab construction for building columns
US7166876B2 (en) 2004-04-28 2007-01-23 Taiwan Semiconductor Manufacturing Company, Ltd. MOSFET with electrostatic discharge protection structure and method of fabrication
JP4046741B2 (en) * 2004-09-06 2008-02-13 リサーチ インスティチュート オブ インダストリアル サイエンス アンド テクノロジー Grout reinforcement
EP1866484A1 (en) * 2005-03-16 2007-12-19 Densit A/S Tower foundation system and method for providing such system
US20110061321A1 (en) * 2006-09-21 2011-03-17 Ahmed Phuly Fatigue reistant foundation system
US8555518B2 (en) * 2011-05-18 2013-10-15 Norman Tooman Grout template for wind turbine foundations
DE102011087022A1 (en) * 2011-11-24 2013-05-29 Wobben Properties Gmbh Device and method for anchoring a wind energy plant
US9340947B2 (en) 2013-03-07 2016-05-17 Allan P. Henderson Perimeter pile anchor foundation
US20140260023A1 (en) * 2013-03-15 2014-09-18 Allan Henderson Continuous strand hoop reinforcement for concrete foundations

Patent Citations (88)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US732485A (en) 1903-01-30 1903-06-30 William N Wight Composite column and beam.
US969039A (en) 1909-03-20 1910-08-30 John Wunder Reinforced concrete structure.
US1139384A (en) 1913-05-22 1915-05-11 Harrison S Taft Apparatus for constructing concrete columns.
US1189459A (en) 1915-04-10 1916-07-04 Emil O Lundin Electrical pole and pole-base.
US1529895A (en) 1924-07-21 1925-03-17 Chance John H La Sectional foundation for mounting signal poles and the like
US1647925A (en) 1925-04-25 1927-11-01 May John Walter Anchor footing for steel towers
US2625815A (en) 1943-10-23 1953-01-20 Eric A Black Adjustable anchorage
US2377055A (en) 1944-05-31 1945-05-29 Joseph H Thornley Pile cap
US2971295A (en) 1955-03-21 1961-02-14 Phillips Petroleum Co Prestressed concrete units and structures
US3646748A (en) 1970-03-24 1972-03-07 Frederic A Lang Tendons for prestressed concrete and process for making such tendons
USRE27732E (en) 1971-02-22 1973-08-14 Reinforcement of concrete structures
US3798868A (en) 1972-04-07 1974-03-26 D Loranger Method of building construction
US3927497A (en) 1972-11-15 1975-12-23 Hitachi Ltd Supporting structure of pressure vessel
US4068445A (en) 1975-02-18 1978-01-17 A. B. Chance Company Lightweight, screw anchor supported foundation and method of installing same
US4094222A (en) * 1975-06-09 1978-06-13 Hilti Aktiengesellschaft Adhesively secured anchor bolt
US4043133A (en) 1976-07-21 1977-08-23 Yegge Lawrence R Structure and method of constructing and test-loading pile anchored foundations
US4051661A (en) 1976-09-15 1977-10-04 Bethlehem Steel Corporation Wire strand and rope
US4092811A (en) 1977-02-14 1978-06-06 T. Y. Lin International Cooling tower, construction method therefor and precast prestressed concrete building units
US4197695A (en) 1977-11-08 1980-04-15 Bethlehem Steel Corporation Method of making sealed wire rope
DE2754577A1 (en) 1977-12-08 1979-06-13 Bateman Ltd E Conveyor installation method - by excavating for foundations, then casting in whilst support members are held up in position
US4247225A (en) 1979-09-06 1981-01-27 Kamak Corporation Alignment device
EP0160135A1 (en) 1982-11-29 1985-11-06 Raymond E. Hutchinson Tendon for post-tensioning prestressed concrete and process for making the tendon
WO1984003531A1 (en) 1983-03-03 1984-09-13 Bakvis Beheer Bv Device for securing an upstanding elongated element at its lower end to the upper surface of a pedestal
JPS6092518A (en) 1983-10-26 1985-05-24 Taisei Corp Connection of pile heads under water
JPS61109826A (en) 1984-11-02 1986-05-28 Nikken Sekkei:Kk Reinforcing metal fitting for pile-foundation connection
US4866903A (en) 1987-01-06 1989-09-19 Ferstay William G Positioning device
JPS6471987A (en) 1987-09-04 1989-03-16 Gen Motors Corp Cable drive type window regulator
US4887691A (en) 1988-11-04 1989-12-19 Rotondo/Penn-Cast Modular wall construction using posts and panels
US5505033A (en) 1988-12-06 1996-04-09 501 Hitachi Metals Ltd. Column base structure and connection arrangement
JPH04353117A (en) 1991-05-29 1992-12-08 Zenitakagumi:Kk Wire anchor body and anchoring method
US5218805A (en) 1991-08-19 1993-06-15 Superior Precast, Inc. Post assembly and noise barrier wall
JPH05311678A (en) 1992-05-12 1993-11-22 Chiyoda Corp Foundation combined with pile
US5826387A (en) 1994-11-23 1998-10-27 Henderson; Allan P. Pier foundation under high unit compression
US5586417A (en) 1994-11-23 1996-12-24 Henderson; Allan P. Tensionless pier foundation
US5966882A (en) 1994-12-19 1999-10-19 Naito; Kingo Structure of base of column and construction method for base of column
JPH08338034A (en) 1995-06-14 1996-12-24 Hitachi Ltd Fixed construction of crane, fixing method thereof and withdrawal method of fixed construction
JPH09256390A (en) 1996-03-18 1997-09-30 Geotop Corp Vibration-isolation pile foundation
US5623792A (en) 1996-05-24 1997-04-29 Crumpacker; William H. Grave marker leveling
JPH1113150A (en) * 1997-06-23 1999-01-19 Nakamura:Kk Bond anchor method
JPH11181797A (en) 1997-12-18 1999-07-06 Modern Material:Kk Method for fixing support for retaining-wall block and foundation member for use therein
US6102118A (en) 1998-12-30 2000-08-15 Moore; Curt A. Multi-purpose adjustable centralizer system with tool
US6705058B1 (en) 1999-02-12 2004-03-16 Newmark International Inc. Multiple-part pole
KR20010057453A (en) 1999-12-23 2001-07-04 이구택 Steel pier anchorage system using large deformed bar
JP2001200582A (en) 2000-01-17 2001-07-27 Ps Corp Prestress introduction method for concrete disk structure
US6665990B1 (en) 2000-03-06 2003-12-23 Barr Engineering Co. High-tension high-compression foundation for tower structures
JP2002061201A (en) 2000-08-16 2002-02-28 Kinya Miura Foundation structure and its construction method
WO2002027105A1 (en) 2000-09-27 2002-04-04 Allan P Henderson Perimeter weighted foundation for wind turbines and the like
US6672023B2 (en) 2000-09-27 2004-01-06 Allan P. Henderson Perimeter weighted foundation for wind turbines and the like
US20020124502A1 (en) 2000-09-27 2002-09-12 Henderson Allan P. Perimeter weighted foundation for wind turbines and the like
US7155875B2 (en) 2000-09-27 2007-01-02 Henderson Allan P Method of forming a perimeter weighted foundation for wind turbines and the like
US20050005562A1 (en) 2000-12-05 2005-01-13 Henderson Allan P. Telescopic support tower
US20020095878A1 (en) 2000-12-05 2002-07-25 Henderson Allan P. Tilt-up and telescopic support tower for large structures
US6782667B2 (en) 2000-12-05 2004-08-31 Z-Tek, Llc Tilt-up and telescopic support tower for large structures
DE10105472A1 (en) 2001-02-05 2002-08-22 Straeb Gmbh & Co Geb Height-adjustable foundation for posts for traffic signs etc. has tubular holder with hollow crumple zone filled and enclosed by soft mortar encasing material
WO2002099204A1 (en) 2001-06-06 2002-12-12 Corus Uk Ltd Ground anchorage apparatus
JP2003013442A (en) 2001-07-03 2003-01-15 Ashimori Ind Co Ltd Cast-in-place pile construction method and its structure
US20020050110A1 (en) 2001-10-26 2002-05-02 Ytterberg Carl N. Reinforced shrinkage compensating concrete slab structure
FR2833029A1 (en) 2001-11-30 2003-06-06 Pierre Louis Glacon Box for making cavity for upright beam in concrete foundation is made from expanded metal with two opposite holes for transverse bar
JP2003232046A (en) 2002-02-07 2003-08-19 Ohbayashi Corp Steel pipe damper and locking foundation structure using the same
US6659691B1 (en) 2002-07-08 2003-12-09 Richard M. Berry Pile array assembly system for reduced soil liquefaction
US7533505B2 (en) 2003-01-06 2009-05-19 Henderson Allan P Pile anchor foundation
US20040261340A1 (en) 2003-06-27 2004-12-30 Thomas Behlinger Fastening arrangement of a machine base and method of fastening the same
EP1526278A1 (en) 2003-10-21 2005-04-27 GMB Beton- en industriebouw noord west B.V. Wind turbine foundation
US7707797B2 (en) 2003-12-15 2010-05-04 Henderson Allan P Pile anchor foundation
US7618217B2 (en) 2003-12-15 2009-11-17 Henderson Allan P Post-tension pile anchor foundation and method therefor
JP2005220554A (en) 2004-02-04 2005-08-18 Railway Technical Res Inst Construction method of concrete structure of axial prestressed construction making use of spiral hoop and its concrete structure
US7905069B1 (en) 2005-12-30 2011-03-15 Aero Solutions, Llc Reinforcing systems to strengthen monopole towers
CA2551712A1 (en) 2006-07-05 2008-01-05 Con-Tech Systems Ltd. Void form for constructing post-tensioned foundation piles
US20120047830A1 (en) 2006-09-21 2012-03-01 Ahmed Phuly Fatigue resistant foundation
US20150376859A1 (en) 2006-09-21 2015-12-31 Ahmed Phuly Fatigue Resistant Foundation
US10640995B2 (en) 2006-09-21 2020-05-05 Ahmed M. Phuly Method of constructing a wind tower foundation with pedestal and ribs
US20180264680A1 (en) 2006-09-21 2018-09-20 Ahmed Phuly Foundation with pedestal and ribs for towers
JP2010065454A (en) 2008-09-11 2010-03-25 Mitsui Eng & Shipbuild Co Ltd Foundation structure of tower-like structure
WO2011029994A1 (en) 2009-09-11 2011-03-17 Peikko Group Oy Connecting element and radial reinforcement structure
US20110173897A1 (en) 2010-01-20 2011-07-21 Stacey Schneider Apparatus and method for protecting a downspout of a gutter
US20130129474A1 (en) 2010-04-21 2013-05-23 Wobben Properties Gmbh Wind power plant foundation and wind power plant
WO2012037450A1 (en) 2010-09-17 2012-03-22 Ensoft, Inc. Foundation for wind turbine generator
US20120070233A1 (en) 2010-09-17 2012-03-22 Ensoft, Inc. Foundation for wind turbine generator
WO2012062425A2 (en) 2010-11-09 2012-05-18 Rehau Ag + Co System for reinforcing and setting up a supporting post for the passage of a heat transfer medium, and method for producing the supporting post
US20120151860A1 (en) 2010-12-15 2012-06-21 Yeou-Fong Li Ductile shear reinforced bar layout applied to reinforced concrete shear wall structures
US20120266447A1 (en) 2011-04-21 2012-10-25 Francisco Diaz-Vallellanes Anti-theft devices for electrical wires
US20120314540A1 (en) 2011-06-07 2012-12-13 Alter Josef K Hollow rebar for crosshole sonic logging access tubes and longitudinal concrete reinforcing in drilled shafts
US20130255169A1 (en) * 2012-03-30 2013-10-03 Allan P. Henderson Cementitious foundation cap with post-tensioned helical anchors
DE202012006606U1 (en) 2012-07-07 2012-11-12 Alexander Nikulin module
US20140260223A1 (en) 2013-03-14 2014-09-18 Allison Transmission Inc. System And Method For Controlling Pump Performance In A Transmission
US20150075099A1 (en) * 2013-08-08 2015-03-19 University Of Utah Research Foundation Elongate member reinforcement
US9783950B2 (en) 2014-10-07 2017-10-10 Allan P. Henderson Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like
US20200032478A1 (en) 2016-06-06 2020-01-30 Robert Carl Rajewski Hydrovac

Non-Patent Citations (47)

* Cited by examiner, † Cited by third party
Title
A unique turnkey solution for wind turbine tower foundations. https://web.archive.org/...b/20120403071116/http://www.peikko.com/solutions-category/solutions/s=A+unique+turnkey+solution+for+wind+turbine+tower+foundations/sid=24072976.
Affidavit of Josef Alter in U.S. Appl. No. 11/428,778, executed on Jun. 2, 2009.
Allam et al. Crack width evaluation for flexural RC members. Alexandria Engineering Journal, (2012) 51, 211-220.
Aschenbroich, Horst Dipl.Ing. Reinforcement of dams in Canada and the USA. Www.contechsystems.com.
Aschenbroich, Horst, Dipl. Ing. Micro Pile Reinforcement Systems and Corrosion Protection, 2001.
Aschenbroich, Horst. Dipl. Ing. A Post Tensioned Micropile Foundation System with Groutable Void Forms (GVF).
Benefits for wind energy specialist. https://web.archive/org/web/20121030175316/http://www.peikko.com/group/t=Wind+Energy+Specialist.
Bruce et al. Foundation Rehabilitation of the Pocomoke River Bridge, Maryland, Using High Capacity Preloaded Pinpiles, The Conference on Bridges official proceedings. Jun. 4-6, 1984.
Clemence, Samuel P., Uplift Behavior of Anchor Foundations in Soil. Proceedings of a session sponsored by the Geotechnical Engineering Division of the American Society of Civil Engineers in conjunction with the ASCE Convention in Detroit, Michigan. Oct. 24, 1985.
Crabtree et al. The Strengthening of Transmission Tower Foundations Using Grouted Anchor Bars.
Dams—Innovations for Sustainable Water Resources, 22nd Annual USSD Conference San Diego, California, Jun. 24-28, 2002.
Declaration of Dr. John T. Bryant in Support of Petition for Inter Partes U.S. Pat. No. 7,533,505 (filed Sep. 9, 2021).
Declaration of Dr. John T. Bryant in Support of Petition for Inter Partes U.S. Pat. No. 7,618,217 (filed Sep. 9, 2021).
Declaration of Dr. John T. Bryant in Support of Petition for Inter Partes U.S. Pat. No. 7,707,797 (filed Sep. 9, 2021).
Deformation of Reinforced Concrete Anchor Foundations in the Far Norht, Plenum Publishing Corporation, 1991.
Design Examples: Attachment 8.
Eurooppalainetekninen hyväksyntä. ETA-10/02; European Technical Approval. VTT Expert Services Oy. Issued Apr. 21, 2011.
Federal Highway Administration Transportation. Geotechnical Engineering Circular N. 4, Ground Anchors and Anchored Systems, Jun. 1999.
Hevosselkä Wind Park, Tervola, Finland, https://www.peikko.com/reference/hevosselka-wind-park.
https://web.archive.org/web/20121003065612/http://www.peikko.com:80/news/year=2012.
https://web.arcive.org/web/20121003064830/http://www.peikko.com/news/year=2012/month=05.
Kelley. A. Short History of Unbounded Post—Tensioning Specifications, Concrete Repair Bullentine, Jul./Aug. 2001.
Kim, Nak-Kyung. Performance of Tension and Compression Anchors in Weathered Soil. Journal of Geotechnical and Geoenvironmental Engineering, Dec. 2003.
Loflin, Bryan J. Bond and Material Properties of Grade 270 and Grade 300 Prestressing Strands. Jun. 10, 2008.
Mäkelänkangas Wind Park, Hamina, Finland, https://www.peikko.com/reference/makelankangas-wind-park/.
Muukko Wind Park, Lappeenranta, Finland. https://www.peikko.com/reference/muukko-wind-park/.
Newman, Morton. Structural Details for Concrete Construction. McGraw Hill Book Company, 1998.
Nigels, McLeod C. Prestressed Conrete Tension Piles and Their Connections, PCI Journal, Jul.-Aug. 1988.
Peck et al. Foundation Engineering, Sec ond Edition, John Wiley & Sons, 1953.
Peikko and Enercon to Expand Their Cooperation. Press Release Apr. 5, 2011. https://web.archive/org/web/20110814012119/http://www.peikko.com/news/n=Peikko+and+Enecon+to+expand+their+cooperation.
Peikko Group: Product Catalogue. Jul. 2, 2012.
Peikko to supply the wind turbine tower foundation solution to Finnish Muukko wind park. https://www.peikko.cz/novinky/peikko-to-supply-the-wind-turbine-tower-foundation-solution-to-finnish-muukko-wind-park-2/.
Peikko to supply the wind turbine tower foundation solution to Finnish Muukko wing park. https://web.archive/org/web/20121001214327/http://www.peikko.com/news/n=Peikko+to+supply+the+wing+turbine+tower+foundation+solution+to+Finnish+Muukko+wing+park.
Peikko's Foundation Solution Chosen for Wing for Wing Park to be Built in Hamina, Finland. https://web.archive.org/web/20111228043258/http://www.peikko.com/news/n=Peikko%27s+Foundation+Solution+choses+for+Wind+Park+to+be+builtin+in+Hamina%2c+Finland.
Petition for Inter Partes Review of U.S. Pat. No. 7,533,505 filed Sep. 10, 2021.
Petition for Inter Partes Review of U.S. Pat. No. 7,618,217 filed Sep. 10, 2021.
Petition for Inter Partes Review of U.S. Pat. No. 7,707,797 filed Sep. 10, 2021.
Post-Tensioning Manueal, Fifth Edition, Post-Tensioning Institute, 1990.
Prestressed Concrete Bridges.
Prestressed Concrete, PCA America's Cement Manufacturers, 1916.
Reflections on the Beginnings of Prestressed Concrete in America, The Prestressed Concrete Institute, 1981.
Standard Specification for Steel Strand, Uncoated Seven-Wire for Prestressed Concrete, ASTM International.
Svensson, Henrick. Design of Foundations for Wind Turbines, 2010.
U.S. Department of Transportation Federal Highway Administration. Post-Tensioning Tendon Installation and Grouting Manuarl, Version 2.0, May 2013.
Video by Peiiko Group uploaded to YouTube on Apr. 13, 2012. https://urldefense.com/v3/_https://youtu.be/j7k-ayGWfh4_;lUrcuqBw_IQl3puXZHuFb4eyZpuDPdTKr3XTjcljoqtpuEEdpwCGStoa9L6X9-0D1V2Ngk3NmsUcbQ51S.
Wind Turbine Anchoring Solutions, Peikko Group, Concrete Connections.
Wind Turbines Uljabuouda, Sweden, Project Story in PeikkoNews Feb. 2009. https://web.archive.org/web/20120320121335/http:www.peikko.com/reference-main/references/rg=Power+Plants+and+LInes/r=Wind+Turbines+Ulkabuouda+%2C+Sweden.

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20240026631A1 (en) * 2021-04-12 2024-01-25 Rwe Renewables Europe & Australia Gmbh Retrofit for existing wind turbine foundations, retrofitted wind turbine foundation and method for retrofitting a wind turbine foundation
US12018449B2 (en) * 2021-04-12 2024-06-25 Rwe Renewables Europe & Australia Gmbh Retrofit for existing wind turbine foundations, retrofitted wind turbine foundation and method for retrofitting a wind turbine foundation

Also Published As

Publication number Publication date
CA3019073C (en) 2020-09-08
US11814808B2 (en) 2023-11-14
CA2908093A1 (en) 2016-04-07
US20200165792A1 (en) 2020-05-28
US9783950B2 (en) 2017-10-10
US20220356669A1 (en) 2022-11-10
CA2908093C (en) 2018-11-13
CA3019073A1 (en) 2016-04-07
US20160097179A1 (en) 2016-04-07
US10648150B2 (en) 2020-05-12
US20170233975A1 (en) 2017-08-17

Similar Documents

Publication Publication Date Title
US11434617B2 (en) Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like
US9739027B2 (en) Perimeter pile anchor foundation
US9745712B2 (en) Cementitious foundation cap with post-tensioned helical anchors and method of making the same
US7416367B2 (en) Lateral force resistance device
US20160201350A1 (en) Tower and method for assembling tower
US10851763B2 (en) Wind turbine foundation and method of constructing a wind turbine foundation
JP6638141B2 (en) Basic structure of tower structure
US10738436B1 (en) Tubular foundation for onshore wind turbine generators
WO2006030893A1 (en) Foundation structure of tower
ES2652466T3 (en) Foundation placement method
US20210348597A1 (en) Pile foundation and construction method of pile foundation
JP2008223303A (en) Foundation structure of tower-like structure
JP5860662B2 (en) Structural members for steel tower foundation, steel tower foundation, and construction method of steel tower foundation
JP6703466B2 (en) Jig for preventing leakage of filler and method for manufacturing composite pile using the jig
KR101613844B1 (en) Transition pieces of offshore wind turbines and whole structure of wind turbines having it
US20200208612A1 (en) Bionic Root Foundation for Onshore Wind Turbine Generators
JP5301721B1 (en) PC artificial ground in the active fault area and buildings on the PC artificial ground
EP3247848A1 (en) Tower and method for constructing a tower
CN104278691A (en) Pile foundation for high-voltage transmission line iron tower

Legal Events

Date Code Title Description
AS Assignment

Owner name: TERRACON CONSULTANTS, INC., KANSAS

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:HENDERSON, ALLAN P.;REEL/FRAME:051653/0004

Effective date: 20190311

FEPP Fee payment procedure

Free format text: ENTITY STATUS SET TO UNDISCOUNTED (ORIGINAL EVENT CODE: BIG.); ENTITY STATUS OF PATENT OWNER: LARGE ENTITY

STPP Information on status: patent application and granting procedure in general

Free format text: NON FINAL ACTION MAILED

STPP Information on status: patent application and granting procedure in general

Free format text: RESPONSE TO NON-FINAL OFFICE ACTION ENTERED AND FORWARDED TO EXAMINER

STPP Information on status: patent application and granting procedure in general

Free format text: FINAL REJECTION MAILED

STPP Information on status: patent application and granting procedure in general

Free format text: DOCKETED NEW CASE - READY FOR EXAMINATION

STPP Information on status: patent application and granting procedure in general

Free format text: NON FINAL ACTION MAILED

STPP Information on status: patent application and granting procedure in general

Free format text: RESPONSE TO NON-FINAL OFFICE ACTION ENTERED AND FORWARDED TO EXAMINER

STPP Information on status: patent application and granting procedure in general

Free format text: NOTICE OF ALLOWANCE MAILED -- APPLICATION RECEIVED IN OFFICE OF PUBLICATIONS

STPP Information on status: patent application and granting procedure in general

Free format text: PUBLICATIONS -- ISSUE FEE PAYMENT VERIFIED

STCF Information on status: patent grant

Free format text: PATENTED CASE