SU877013A1 - Method of mining thick sloping coal beds - Google Patents

Method of mining thick sloping coal beds Download PDF

Info

Publication number
SU877013A1
SU877013A1 SU792835945A SU2835945A SU877013A1 SU 877013 A1 SU877013 A1 SU 877013A1 SU 792835945 A SU792835945 A SU 792835945A SU 2835945 A SU2835945 A SU 2835945A SU 877013 A1 SU877013 A1 SU 877013A1
Authority
SU
USSR - Soviet Union
Prior art keywords
strip
soil
laid
mining
strips
Prior art date
Application number
SU792835945A
Other languages
Russian (ru)
Inventor
Людвиг Павлович Томашевский
Original Assignee
Всесоюзный Научно-Исследовательский И Проектно-Конструкторский Угольный Институт (Кузниуи)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Всесоюзный Научно-Исследовательский И Проектно-Конструкторский Угольный Институт (Кузниуи) filed Critical Всесоюзный Научно-Исследовательский И Проектно-Конструкторский Угольный Институт (Кузниуи)
Priority to SU792835945A priority Critical patent/SU877013A1/en
Application granted granted Critical
Publication of SU877013A1 publication Critical patent/SU877013A1/en

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

(54) СПОСОБ РАЗРАБОТКИ МОЩНЫХ КРУПНЫХ УГОЛЬНЫХ ПЛАСТОВ(54) METHOD FOR DEVELOPING POWERFUL LARGE COAL STRAYS

Claims (2)

- 1 Изобретение относитс  к горной про мьшшенности и предназначено дл  разработки мощных крутых угольных пластов . Известен способ разработки мощных рудных тел сло ми сверху вниз камерно-столбовой системой с закладкой выработанного пространства l. . Однако данный способ недостаточно эффективен. Известен также способ разработки мощных крупных угольных пластов, вклю чак дий отработку пласта короткими полосами в нисход щем пор дке с закладкой выработанного пространства из трубопровода, оставление угольньис целиков , выемку угольных целиков непосредственно перед закладкой выработанного пространства Г2. Однако указанный способ недостато но эффективен из-за значительной тру доемкости горных работ. Цель изобретени  - повышение эффективности разработки за счет снижени  трудоемкостд горных работ. Поставленна  цель достигаетс ,-тем что короткие полосы отрабатывают в шахтном пор дке, угольные целики вынимают из отработанных полос, .а тру- бопровод укладывают в почве каждой полосы. На фиг. 1 изображена схема отработки полос и вынимаемых целиков; на фиг. 2 - схема.расположени  заложенных закладкой камер по мощности и падению пласта на фиг. 3 - разрез А-А на фиг. 1. Способ осуществл етс  следуквдим образом. Предохранительный межгоризонтальный целик отрабатывают горизонтальными сло ми сверху вниз с твердеющей закладкой. На границе между этажами укладываетс  гибкое перекрытие 1,.которое анкерами 2 прикрепл етс  к кровле и почве пласта. Первый слой под гибким перекрытием 1 отрабатываетс  короткими полосами 3 (например 3 х 3 м) от кровли к почве пласта и закладываетс  твердеющей закладкой. В почве каждой полосы вкладываетс  закладочный трубопровод 4, который с помощью хомутов и канатиков 5 подвешиваетс  к закладочному массиву Кажда  полоса 3 вынимаетс  проходческб-очистным или проходческим комбайном б,. например типа ГПК, и крепитс -инвев-у тарной крепью. После выемки каждой полосы она закладЫЬаетс  в отступающем пор дке твердеющей смесью. При не достаточно прочном закладочном массиве на почве полосы настилаетс  металлическа  сетка 7. Выемка полос в сло х производитс  в шахматномпор дке. Например, вынимаетс  полоса 8 посередине пласта, в следующем слое полосы 9 и 10 в кровли и почвы пласти , зачтем полоса 11 - посередина пласта и т.д. После выемки и з.акладки полос 3 у кровли и почвы пласта происходит выемка полосы 8 во втором слое также на всю длину блока. В обратном пор дке от границы блока с помощью -комбайна б или буровзрывных работ производитс  .выемка временно оставленного целика 12 (onYCKaHHe потолочины полосы), извлечение инвертарной штрековой крепи и превращение полосы в камеру 13 котора  затем закладываетс  твердеюще смесью из трубопровода 4, ранее уложенного под гибким перекрытием 1. По мере закладки камеры, трубопровод, подвешенный к почве вышележащей камеры с помощью хомутов или канатиков 5, в закладке демонтируетс  и уклады ваетс  в канавку на почве закладываемой камеры. После закладки камеры 13 производитс  выемка и закладка камеры 14 из полосы 9, а затем -камеры. 15 из полосы 10 и т.д. Таким образом, предохранительный целик (межгоризонтальный)отрабатнваетс  узкими (шириной 3-3,5 м) , но . высокими камерами (5-6 м), располагаемшли в шахматном пор дке в пласте аналогично кирпичной кладке и закладываемыми из трубопроводов трердеющей смесью. Предлагаемый способ и пор док.отработки пласта повышает эффективность разработки и снижает трудоемкость горных работ. Формула изобретени  Способ разработки мощных крупных угольных пластов , включающий отработку пласта короткими полосами в нисход щем пор дке с закладкой выработанного пространства из трубопровода , оставление угольных целиков, выемку угольных целиков непосредственно перед закладкой выработанного пространства, отличающий.с   тем, что, с целью повышени  эффективности разра ботки за счет снижени  трудоемкости горных работ/ короткие полосы отрабатывают, в шахматном пор дке, угольные целики вынимают из отработанных полос, расположенных под целиками, а трубопровод укладывают в почве каждой полосы. . Источники информации, прин тые во внимание при экспертизе 1.Авторское свидетельство СССР №605969, кл. Е 21 С 41/06, 1976.  - 1 The invention relates to the mining industry and is intended for the development of thick steep coal seams. There is a known method of developing powerful ore bodies with layers from top to bottom of the chamber-and-pillar system with laying the mined-out space l. . However, this method is not effective enough. There is also a known method of developing powerful large coal seams, including mining the strip in short strips in a descending order with the laying of the exhausted space out of the pipeline, leaving the coal pillars, and excavating the coal pillars just before laying the worked-out G2 space. However, this method is not sufficiently effective due to the considerable labor consumption of mining operations. The purpose of the invention is to increase the development efficiency by reducing the labor-intensive mining activities. The goal is achieved, because the short strips are worked out in the mine order, the coal pillars are removed from the spent strips, and the pipeline is laid in the soil of each strip. FIG. 1 shows a diagram of the mining bands and removable pillars; in fig. 2 is a schematic diagram of the location of the camera’s inlaid chambers in terms of thickness and dip in FIG. 3 shows section A-A in FIG. 1. The method is carried out in the following manner. The safety inter-horizontal rear sight is worked out in horizontal layers from top to bottom with a hardening tab. At the boundary between the floors there is a flexible overlap 1, which is attached by anchors 2 to the roof and the soil of the formation. The first layer under the flexible overlap 1 is worked out with short strips 3 (for example, 3 x 3 m) from the roof to the soil of the formation and is laid with a hardening tab. In the soil of each strip, a backfill pipe 4 is inserted, which with the help of clamps and ropes 5 is suspended from the backfill array. Each lane 3 is pulled out of a passage-clearing or tunneling machine b ,. for example, of the type of GPC, and is fastened to the belayed-tare lining. After each strip has been removed, it lays back in retreating order with a hardening mixture. If the backfill array is not strong enough, a metal mesh 7 is laid on the soil of the strip. The strips in the layers are dredged in a staggered manner. For example, strip 8 is removed in the middle of the seam, in the next layer strip 9 and 10 in the roofs and soil of the seam, after strip 11 is in the middle of the seam, etc. After excavation and backfilling of the strips 3 near the roof and the soil of the reservoir, the strips 8 in the second layer are also excavated for the entire length of the block. In the reverse order from the block boundary, a temporarily abandoned rear pillar 12 (onYCKaHHe ceiling slabs) is removed by a combination of b or a blasting, removal of the invertar liner and transformation of the strip into chamber 13 which is then laid hardening with a mixture from pipeline 4 previously laid flexible overlap 1. As the chamber is laid down, the pipeline suspended from the soil of the overlying chamber using clamps or cables 5 in the tab is dismantled and laid into the groove on the soil of the laying chamber. After the camera 13 has been laid down, the camera 14 is dredged and laid out from the strip 9 and then the camera. 15 of lane 10, etc. Thus, the safety sight (inter-horizontal) is worked out narrow (3-3.5 m wide), but. high chambers (5-6 m), are placed in a staggered order in the formation similar to the brickwork and laid with pipelines with a purging mixture. The proposed method and the order of the reservoir processing improves the development efficiency and reduces the labor intensity of mining operations. The invention The method of developing powerful large coal seams, including mining the strip in short strips in a descending order with the laying of the open space of the pipeline, leaving the coal pillars, excavation of the coal pillars just before the laying of the open space, characterized by the fact that in order to increase efficiency development by reducing the labor intensity of mining operations / short strips work, in a checkerboard pattern, coal pillars are removed from the waste bands, located x under the pillars, and the pipeline is placed in the soil of each strip. . Sources of information taken into account during the examination 1. USSR author's certificate No. 605969, cl. E 21 C 41/06, 1976. 2.Авторское свидетельство СССР по за вке № 2427444,кл.Е 21 С 41/04, 1976 (прототип).2. USSR author's certificate for application number 2427444, class E 21 C 41/04, 1976 (prototype).
SU792835945A 1979-11-11 1979-11-11 Method of mining thick sloping coal beds SU877013A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU792835945A SU877013A1 (en) 1979-11-11 1979-11-11 Method of mining thick sloping coal beds

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU792835945A SU877013A1 (en) 1979-11-11 1979-11-11 Method of mining thick sloping coal beds

Publications (1)

Publication Number Publication Date
SU877013A1 true SU877013A1 (en) 1981-10-30

Family

ID=20857647

Family Applications (1)

Application Number Title Priority Date Filing Date
SU792835945A SU877013A1 (en) 1979-11-11 1979-11-11 Method of mining thick sloping coal beds

Country Status (1)

Country Link
SU (1) SU877013A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2475647C2 (en) * 2011-05-20 2013-02-20 Юрий Абрамович Дик Mining method of thick steep ore bodies
RU2486340C2 (en) * 2011-08-01 2013-06-27 АКЦИОНЕРНАЯ КОМПАНИЯ "АЛРОСА" (открытое акционерное общество) Layered room-and-pillar system with complete stowing
CN109162713A (en) * 2018-09-03 2019-01-08 中国矿业大学(北京) A kind of double resource pit mining modes of coal water not changing overlying strata hydrogeologic condition

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2475647C2 (en) * 2011-05-20 2013-02-20 Юрий Абрамович Дик Mining method of thick steep ore bodies
RU2486340C2 (en) * 2011-08-01 2013-06-27 АКЦИОНЕРНАЯ КОМПАНИЯ "АЛРОСА" (открытое акционерное общество) Layered room-and-pillar system with complete stowing
CN109162713A (en) * 2018-09-03 2019-01-08 中国矿业大学(北京) A kind of double resource pit mining modes of coal water not changing overlying strata hydrogeologic condition
CN109162713B (en) * 2018-09-03 2020-08-11 中国矿业大学(北京) Coal-water dual-resource mine mining method without changing overlying strata hydrogeological conditions

Similar Documents

Publication Publication Date Title
SU877013A1 (en) Method of mining thick sloping coal beds
SU898067A1 (en) Method of working thick coal beds
SU1434108A1 (en) Method of exploiting thick steep coal seams
SU825964A1 (en) Method of working thick steeply-inclined ore bodies
RU2093678C1 (en) Method for mining thick steep ore bodies
SU905467A1 (en) Method of working unstable ores
SU95492A1 (en) Development system of high-grade steeply dipping seams with horizontal layers
SU1004639A1 (en) Method of mining thick gently-sloping beds
SU1661424A1 (en) Method for working out closely contiguous disrupted coal seams
SU768984A1 (en) Method of working thick steep coal seams
SU962617A1 (en) Method of mining gently-sloping ore deposits
SU912934A1 (en) Method of strip mining of mineral deposits
SU1710750A1 (en) Method of mining thick coal seams with filling
SU1461942A1 (en) Method of mining thick ore deposits
SU1035221A1 (en) Method of working gently-sloping coal seams with coal and gas outburst hazard present
SU1745935A1 (en) Method of protecting and supporting development drift on its pitching portion
SU827789A1 (en) Method of working thick sloping coal seams
SU1281671A1 (en) Method of working thick steep seams and mechanized unit for performing same
SU934006A1 (en) Method of working gently-sloping mineral beds
SU679729A1 (en) Method of mining thick steep and gently sloping coal beds
SU1665039A1 (en) Method of roof adjustment for driving steep bed
SU905468A1 (en) Method of working pillars
SU939752A1 (en) Method of working thick gently-sloping beds
RU2083833C1 (en) Method for development of steep coal seams with backing worked-out area
SU949179A1 (en) Method for underground working of seam deposits