SU831992A1 SU792780866A SU2780866A SU831992A1 SU 831992 A1 SU831992 A1 SU 831992A1 SU 792780866 A SU792780866 A SU 792780866A SU 2780866 A SU2780866 A SU 2780866A SU 831992 A1 SU831992 A1 SU 831992A1
Authority
SU
USSR - Soviet Union
Prior art keywords
strip
formwork
hardening material
mixer
space
Prior art date
Application number
SU792780866A
Other languages
Russian (ru)
Inventor
Михаил Федорович Малюга
Николай Филиппович Рысев
Игнатий Иванович Жихарев
Алексей Иванович Карлов
Николай Афанасьевич Шаповал
Original Assignee
Malyuga Mikhail F
Rysev Nikolaj F
Zhikharev Ignatij
Karlov Aleksej
Shapoval Nikolaj A
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Malyuga Mikhail F, Rysev Nikolaj F, Zhikharev Ignatij, Karlov Aleksej, Shapoval Nikolaj A filed Critical Malyuga Mikhail F
Priority to SU792780866A priority Critical patent/SU831992A1/en
Application granted granted Critical
Publication of SU831992A1 publication Critical patent/SU831992A1/en

Links

Description

(54) СПОСОБ ОГРАЖДЕНИЯ ВЫРАБОТКИ(54) METHOD FOR PROTECTING DEVELOPMENT

ОТ ВЫРАБОТАННОГО ПРОСТРАНСТВАFROM DEVELOPED SPACE

Claims (2)

Изобретение относитс  к угольной промышленности и может быть использовано дл  ограничени  вентил ционных (углеспускных) печей от выработанного пространства при отработке участка щитовыми агрегатами на пластах крутого падени . Известен способ ограждени  выработки от выработанного пространства , включающий возведение из твердею щего материала боковых стенок в виде устанавливаемых с интервалом опор между породами кровли и. прчвы пласта 1. Недостаток такого способа заключаетс  в том, что опоры из твердеюще го материала не образуют сплошной стенки и не в состо нии сразу воспри н ть нагрузку. Известен также другой способ огра дени  выработки от выработанного пространства, включающий возведение; в ней за проходом очистного забо  полосы из твердеющего материала, укладываемого в опалубочное пространство , которое оконтуривают внешним и внутренним параллельными р дами стоек с обшивкой, и подачу твердеющего материала по трубопроводу, подк.точен ному к смесителю 2. Однако такой способ рассчитан на ограждение выработок от выработанного пространства при разработке только пологих пластов. Цель изобретени  - обеспечение возможности использовани  полосы из твердеющих материалов дл  ограждени  вентил ционной печи при выемке по падению крупного пласта с помощью щитового агрегата. Поставленна  цель достигаетс  тем, что полосу возвод т участками, каждый, из которых отдел ют от последующего посредством устройства торцового откоса в сторону выработанного пространства из однородной органки с внутренней обшивкой, при этом твердеющии материал подают через окна в опалубке, оставл емые в верхней части каждого участка, внешний параллельный р д стоек выполн ют из однор дной органки, а внутренний - из двухр дной , при возведении полосы смеситель подк.лючают к трубопроводу на вводе его в опалубку. На фиг. 1 изображена схема ограждени  вентил ционной печи от выработанного пространства, вид в плане; на фиг. 2 - разрез А-А на фиг. 1, Ограждение вентил ционной (углеспускной ) печи производ т по мере спускани  щитового агрегата 1, период чески укладыва  бетонную полосу участками 2 в заранее установленную опалубку- щик, оконтуренный по паще ВИЮ пласта со стороны завала и лест|ничного отделени  однор дной органч ой 3 с внутренней обшивкой 4 и пере крытием 5 По кровле и почве пласта, а с торца - опорной однор дной орган кой б с внутренней обшивкой в виде откоса 7, После установки посто нной крепи печи с укладкой по почве и кровле пласта по простиранию шпальных брусьев 8 и установки по их концам дерев нных стоек 9, а посредине двухр дной оргакки 10, раздел ющей печь на лестнично- и грузовое отделени , производ т подачу бетона через окна, оставл емые в верхней части каждого участка 2, в опалубку- щик по трубопроводу , в конце которого на вводе е в опалубку заранее устанавливают сме ситель 13 и емкость 14 с ускорителем схватывани  бетона.Из смесител  13 бе тонна  смесь по патрубку 15 поступает в опалубку- щик,причем верхний конец торцового фартука 16 щитового аг регата равный 1/4 части его длины по то нно располагают на ранее возведен ные участки бетонной полосы. Формула изобретени  1, Способ ограждени  выработки от выработанного пространства, включающий возведение вслед за проходом очистного забо  полосы из твердею щего материала, укладываемого в опалубочное пространство, которое оконтуривают внешним и внутренними параллельными р дами стоек с обшивкой, и подачу твердеющего материала по трубопроводу , подключенному к смесителю , о. тличающийс  тем, что, с обеспечени  возможности использовани  полосы из твердеющих материсшов дл  ограждени  вентил ционной печи при выемке по падению круп кого пласта с помощью щитового агрегата , полосу возвод т участками, каждый из которых отдел ют от- после- . дующего посредством устройства торцового откоса в сторону выработанного пространства из однор дной органки с внутренней обшивкой, при этом твердеющий материал подают через окна в опалубке, оставл емые в верхней части каждого участка. 2,Способ по п. 1, отличающийс  тем, что внешний парашлельный р д стоек выполн ют из однор дной органки, а внутренний - из двухр дной. 3.Способ по п. 1, отличаю щ и и с   тем/ что при возведении полосы смеситель -подключают к трубопроводу на вводе его в опалубку. Источники информации, прин тые во внимание при экспертизе 1.Авторское свидетельство СССР по за вке № 2553474, кл. Е 21 D 11/08, 1977. The invention relates to the coal industry and can be used to limit the ventilation (coal-fired) furnaces from the mined-out space when mining a site with shield panels on steep dip seams. There is a known method of protecting the excavation from a developed space, including the erection of side walls from hardening material in the form of supports installed with an interval between roof rocks and. Structures of the reservoir 1. The disadvantage of this method is that the supports made of hardening material do not form a solid wall and are not able to immediately absorb the load. There is also known another way to restrict the generation from the goaf, which includes erection; there is a strip of hardening material laid in the shuttering space, which is contoured by external and internal parallel rows of racks with cladding, and the supply of hardening material through a conduit piping to the mixer 2. from the developed space in the development of only flat seams. The purpose of the invention is to make it possible to use a strip of hardening materials to enclose a ventilation furnace when a large reservoir is being excavated by means of a panel board. This goal is achieved in that the strip is erected in sections, each of which is separated from the subsequent one by means of an end slope device in the direction of a hollowed out space from a homogeneous organka with inner lining, while hardening material is fed through the windows in the formwork left at the top of each The site, the outer parallel row of pillars, is made of a single-ply organ, and the inner one, of a two-pillar, when the strip is erected, the mixer is connected to the pipeline at its entrance to the formwork. FIG. 1 shows a diagram of the fence of the ventilation furnace from the goaf, a plan view; in fig. 2 shows section A-A in FIG. 1, The fencing of the ventilation (coal-fired) furnace is made as the switchboard unit is lowered 1, periodically placing the concrete strip in sections 2 into a pre-installed formwork, contoured in the VIS formation layer from the dam side and the ladder compartment with a single organ 3 with inner lining 4 and overlapping 5 On the roof and soil of the reservoir, and from the end - supporting single-sided organ b with the inner lining in the form of a slope 7, After installing the permanent lining of the furnace with laying on the soil and roof of the reservoir along the strike of the sleeper bars 8 and mouth Arrangements at their ends of wooden poles 9, and in the middle of a two-pillar organ 10 dividing the kiln into a staircase and a cargo compartment, concrete is supplied through windows left in the upper part of each section 2 into the formwork through the pipeline, the end of which, on entering the formwork, preliminarily install the mixer 13 and the tank 14 with the accelerator for setting the concrete. From the mixer, 13 concrete mixture passes through the branch pipe 15 to the formwork, and the upper end of the face apron 16 of the panel assembly is equal to 1/4 of its The lengths of this are placed on anee nye elevated portions of the concrete strip. Claim 1, A method of protecting a mine from an exhausted space, including the construction of a strip of hardening material following the passage of a cleaning slab, which is laid in the shuttering space, which is contoured by external and internal parallel rows of racks with cladding, and the supply of hardening material through a pipeline connected to to the mixer, oh. Advantageously, since it is possible to use a strip of hardening materials for fencing a ventilation oven when excavating a large stratum using a switchboard unit, the strip is erected in sections, each of which is separated from one another. blowing through the device of the face slope in the direction of the worked-out space from single-paneed organka with inner lining, at the same time hardening material is fed through the windows in the formwork left at the top of each section. 2, a method according to claim 1, characterized in that the outer parachneal row of pillars is made of one-ply organ, and the inner one is made of two-pillar. 3. The method according to claim 1, distinguishing between u and with the fact / that during the construction of the strip, the mixer is connected to the pipeline at its entry into the formwork. Sources of information taken into account in the examination 1. USSR author's certificate in application number 2553474, cl. E 21 D 11/08, 1977. 2.Колчин A.M. и др. Охрана выработки полосок из бетона.- Уголь Украины , 1978, № 2, с. 16-17 (прототип ) .2. Kolchin A.M. and others. Protection of the development of strips of concrete. - Coal of Ukraine, 1978, No. 2, p. 16-17 (prototype).
SU792780866A 1979-06-13 1979-06-13 Method of fencing a mine working from excavated space SU831992A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU792780866A SU831992A1 (en) 1979-06-13 1979-06-13 Method of fencing a mine working from excavated space

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU792780866A SU831992A1 (en) 1979-06-13 1979-06-13 Method of fencing a mine working from excavated space

Publications (1)

Publication Number Publication Date
SU831992A1 true SU831992A1 (en) 1981-05-23

Family

ID=20834086

Family Applications (1)

Application Number Title Priority Date Filing Date
SU792780866A SU831992A1 (en) 1979-06-13 1979-06-13 Method of fencing a mine working from excavated space

Country Status (1)

Country Link
SU (1) SU831992A1 (en)

Similar Documents

Publication Publication Date Title
CN104131829A (en) Method for removing hydraulic supports for solid filling coal mining
CN115182737A (en) Vertical orthogonal ejection type air duct structure of deep-buried subway station and construction method
CN108978673A (en) A kind of foundation pit supporting construction and construction method of viaduct pile foundation underpinning
SU831992A1 (en) Method of fencing a mine working from excavated space
US3751929A (en) Method of supporting exposed ground or rock
RU2565314C2 (en) Subway station erection method (yurkevich(s method)
RU2509893C1 (en) Erection method of earthquake resistant concrete support
RU2444624C1 (en) Method of full development of gently sloping coal beds with power-driven systems without any preparatory mine workings
SU1266988A1 (en) Method of working pillars
RU2785300C1 (en) Single-vault deep underground station with supporting tunnels, constructed by a closed method for work
SU771347A1 (en) Method of filling-up excavated area at shield system of mining
FR2000075A1 (en)
SU1745940A1 (en) Method of erecting supporting pillar
RU2065038C1 (en) Method for increasing stability of roof rock
SU1465584A1 (en) Method of constructing a tunnel under existing structure
SU1795100A1 (en) Method for mining thick steeply dipping coal seams
SU574535A1 (en) Method of developing thick unstable ore body
SU1249164A1 (en) Ferroconcrete lining of underground structure walls
SU669061A1 (en) Method of supporting mine working with monolithic concrete
SU947296A1 (en) Method of protection of foundation of structures erected on undermined territory
SU991059A1 (en) Method of constructing roofs of vertical mine working
DE50010662D1 (en) Load-bearing sealing vault for sealing underground tunnels
SU97031A1 (en) The method of construction of the overlap of wire mesh in the development of powerful, oblique coal seams
RU2013547C1 (en) Method for steep coal seams mining
SU943401A1 (en) Method of consolidating mine working with monolithic concrete