SU1116183A1 - Method of filling worked-out space with hardening mixture - Google Patents

Method of filling worked-out space with hardening mixture Download PDF

Info

Publication number
SU1116183A1
SU1116183A1 SU823409392A SU3409392A SU1116183A1 SU 1116183 A1 SU1116183 A1 SU 1116183A1 SU 823409392 A SU823409392 A SU 823409392A SU 3409392 A SU3409392 A SU 3409392A SU 1116183 A1 SU1116183 A1 SU 1116183A1
Authority
SU
USSR - Soviet Union
Prior art keywords
laying
filling
pipeline
application
mixture
Prior art date
Application number
SU823409392A
Other languages
Russian (ru)
Inventor
Израил Шмульевич Коган
Марат Жакупович Битимбаев
Кямал Шогаибович Акбаев
Александр Викторович Корн
Валерий Николаевич Габченко
Юрий Арсентьевич Антонинов
Израил-Гирш Ильич Дольник
Телибек Байдрахманович Акатаев
Original Assignee
Kogan Izrail S
Bitimbaev Marat Z
Akbaev Kyamal Sh
Korn Aleksandr V
Gabchenko Valerij N
Antoninov Yurij A
Dolnik Izrail Girsh
Akataev Telibek B
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kogan Izrail S, Bitimbaev Marat Z, Akbaev Kyamal Sh, Korn Aleksandr V, Gabchenko Valerij N, Antoninov Yurij A, Dolnik Izrail Girsh, Akataev Telibek B filed Critical Kogan Izrail S
Priority to SU823409392A priority Critical patent/SU1116183A1/en
Application granted granted Critical
Publication of SU1116183A1 publication Critical patent/SU1116183A1/en

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

СПОСОБ ЗАКЛАДКИ ВЫРАБОТАННОГО ПРОСТРАНСТВА ТВЕРДЕЮЩЕЙ СМЕСШ, включающий прокладку магистрального закладочного трубопровода с отводами в подготовительной вьфаботке, образование закладочных щелей в камерах, 1 годключение щелей к магистральному зaкл.aдoчнo fy трубопроводу и подачу закладочной смеси в камеры пр закладочному трубопроводу, отличающийс  тем, что, с целью снижени  трудоемкости закладочных работ и повышени  интенсивности очистной выемки , закладочные щели образуют в целиках на всю их высоту, отводы в магистральном трубопроводе размещают напротив каждой щели, а в кровле камер укрепл ют отрезки труб, торцы которых герметизируют и снабжают поисковыми элементами, концы последних располагают в щел х, закладочную смесь подают через отводы в щели до полного заполнени  их и камеры, вынимают целики, при этом по мере их ,отработки обнажают поисковые элементы , разгерметизируют отрезки труб, i (Л соедин ют их между собой и с отводами магистрального трубопровода, по образованному трубопроводу подают . закладочную смесь в пространство, образовавшеес  от выемки целиков, начина  с нижнего, затем поочередно отсоедин ют трубы в соседнем с заполненной камерой пространстве. 00 &0METHOD OF BOOTMARKING OF A DEVELOPED SPACE OF A SOLIDING MIXTURE, which includes laying a lay-in laying pipeline with taps in the preparatory process, forming filling holes, in the application, laying the laying of the laying of the backfill pipeline and sending the filling mix to the application, and laying a laying of the laying of the cracks in the main track for fy pipeline and feeding the filling mix to the application laying the laying of the cracks to the backfill pipeline and putting the filling mix into the application laying window and putting the filling mix into the appli- ance laying to the main track for fy pipeline and feeding the filling mix to the laying of the laying application for the backfill pipeline and sending the filling mix to the application. in order to reduce the labor intensity of the backfilling work and increase the intensity of the clearing recess, the backfill slots form in the pillars to their entire height, bends in the main pipelines the gadfly is placed opposite each slit, and in the roof of the chambers sections of pipes are fixed, the ends of which are sealed and supplied with search elements, the ends of the latter are placed in the gaps, the filling mixture is fed through the branches into the slits until they are completely filled and the chambers as they are tested, they strip the search elements, depressurize the pipe sections, i (L, connect them to each other and to the branches of the main pipeline, they serve it through the pipeline formed. the filling mixture into the space formed from the recess of the pillars, starting at the bottom, then alternately disconnecting the pipes in the space adjacent to the filled chamber. 00 & 0

Description

Изобретение относитс  к горной промьшшенности и может быть использовано при разработке наклонных залежей полезных ископаемых камера ш по простиранию в две очереди с закладкой выработанного пространств Известен способ закладки выработанного пространства твердеющей смесью, заключающийс  в ограждении перемычками выработанного пространс ва, подаче твердеющей смеси за пер мычки по закладочному трубопроводу , проложенному по восстающему и выработанному пространству в горизонтальном слое, дозакладке выработанного пространства пластичной смесью и демонтаже закладочного трубопровода в горизонтальном слое ив нижней части вертикального закладочного восстающего после перво стадии закладки ft. Недостатком способа  вл етс  бол ша  трудоемкость закладочных работ. Известен также способ заполнени  выработанного пространства закладочным материалом, включающий прокладку магистрального закладочного трубопровода в подготовительной выработке , образование закладочных щелей в камерах, расположенных р дами , подключение магистрального трубопровода к закладочным транспор ным щел м и подаче по ним твердеющей закладочной смесиJ23. Однако известный способ имеет высокую трудоемкость закладочньш абот и низкую интенсивность очистной выемки. Цель изобретени  - сн1 жение труд емкости закладочных работ и повышен интенсивности очистной выемки. Поставленна , цель достигаетс  тем, tfTo согласно способу, включающему прокладку магистрального за кладочного трубопровода с отводами в подготовительной выработке, образование закладочных щелей в камера подключение щелей к магистральному закладочному трубопроводу и подачу закладочной смеси в камеры, закладочные щели образуют в целиках на всю их высоту отводы в магистрально трубопроводе размещают напротив каж дой щели, а в кровле камер укрепл ю отрезки труб, торцы которых гермети зируют и снабжают поисковыми элемен , концы последних располагают в щел х, закладочную смесь подают через отводы в щели и камеры до полного их заполнени , затем вынимают целики, при этом по мере их отработки обнажают поисковые элементы , разгерметизируют отрезки труб, соедин ют их между собой и с отводами магистрального трубопровода, по образованному таким образом трубопроводу подают закладочную смесь в пространство, образовавшеес  от выемки целиков до его заполнени , начина  с нижнего, затем поочередно отсоедин ют трубы в соседнем с заполненной камерой пространстве. - На фиг.1 показано расположение магистрального закладочного трубопровода , щелей и камер после закладки , вид в плане на фиг.2 - схема образовани  закладочного трубопровода и последовательность закладки пространства, образовавшегос  от выемки целиков. Способ осуществл етс  следующим образом. В горизонтальной выработке прокладывают магистральный закладочный трубопровод 2 с отводами 3. По мереотработки камер 4 на всю высоту целиков выполн ют щели 5, а в кровле камер 4 в створе с соседними по падению щел ми 5 и отводами 3 укрепл ют отрезки труб 6, торцы которых герметизируют и снабжают поисковыми элементами 7, например проволокой, концы последних располагают в щел х 5, по магистральному закладочному трубопроводу 2 через отводы 3 в камеры 4 и щели 5 подают закладочную смесь до полного их заполнени , затем вынимают целики 8, при этом по мере их отработки обнажают поисковые элементы 7, разгерметизиру7от отрезки труб 6, соедин ют их меткду собой и с отводами 3 магистрального трубопровода 2 по образованному таким образом трубопроводу 9 подают закладочную смесь в пространство, образовавшеес  от выемки целиков, начина  с нижнего 10. После заполнени  пространства закладочной смесью поочередно отсоедин ют трубы 11 в соседнем с заполненной камерой пространстве. Предлагаемый способ закладки выработанного пространства твердеющей смесью позвол ет снизить трудоемкость закладочных работ и повысить интенсивность очистной выемки.The invention relates to the mining industry and can be used in the development of inclined deposits of minerals chamber w in two turns with laying the developed space. The known method of laying the developed space with hardening mixture consisting in protecting the developed space by bridges, feeding hardening mixture of permafrost pipeline, laid on an ascending and developed space in the horizontal layer; ary mixture and disassembly of the packing pipe in a horizontal layer ive bottom of the vertical stowing rebelling after the first step ft bookmarks. The disadvantage of this method is the greater laboriousness of backfilling. There is also known a method of filling the developed space with filling material, including laying a main filling pipeline in the preparatory development, forming filling cavities in chambers arranged in rows, connecting the main pipeline to filling filling slots and feeding hardening filling material through them J23. However, the known method has a high labor intensity of backfill and low intensity of the clearing recess. The purpose of the invention is to reduce the labor capacity of the filling operations and increase the intensity of the clearing recess. The goal is achieved by tfTo according to the method, including laying the trunk gasket pipeline with taps in the preparatory development, the formation of filling cracks in the chamber connecting the slots to the trunk filling pipe and feeding the filling mixture into the chambers, filling the slots in the pillars for their entire height in the main pipeline, they are placed opposite each slot, and in the roof of the chambers fortified pipe sections, the ends of which seal and supply search elements, the ends of the last they are placed in the slots, the filling mixture is fed through the taps into the gaps and chambers until they are completely filled, then the pillars are removed, and as they are worked out, the search elements are exposed, they depressurize the pipe sections, connect them to each other and to the branches of the main pipeline, according to Thus, the pipeline is fed with a filling mixture into the space formed from the excavation of the pillars before it is filled, starting from the bottom, then the pipes are alternately disconnected in the space adjacent to the filled chamber. - Figure 1 shows the location of the main filling pipeline, slots and chambers after laying, a plan view of figure 2 is a diagram of the formation of a filling pipeline and the sequence of laying the space formed from the excavation of the pillars. The method is carried out as follows. In horizontal development, a main filling pipeline 2 with taps 3 is laid. As the chambers 4 are worked out, the slots 5 are made to the entire height of the pillars, and in the roof of the chambers 4 in the alignment with the gaps 5 and taps 3 adjacent to the drop, the pipe sections 6 are reinforced they seal and supply the search elements 7, for example with wire, the ends of the latter are located in slots 5, through the main backfill pipe 2 through taps 3 into chambers 4 and slots 5 feed the filling mixture until they are completely filled, then the pillars 8 are removed, As they are mined, the search elements 7 are exposed, depressurized from sections of pipes 6, connected to each other and with branches 3 of the main pipeline 2 through the pipeline 9 formed in this way, the filling mixture is fed into the space formed from the excavation of the pillars, starting from the bottom 10. After filling the space filling pipes alternately disconnect the pipes 11 in the space adjacent to the filled chamber. The proposed method of laying the worked-out space with a hardening mixture allows reducing the laboriousness of backfilling and increasing the intensity of the clearing recess.

88 .88

/////////////А/////А//////////////////////////Л//////////// A ///// A ////////////////////////// Л

//. ///. /

//фаг . 2// phage. 2

Claims (1)

СПОСОБ ЗАКЛАДКИ ВЫРАБОТАННОГО ПРОСТРАНСТВА ТВЕРДЕЮЩЕЙ СМЕСЬЮ, включающий прокладку магистрального закладочного трубопровода с отводами в подготовительной выработке, образование закладочных щелей в камерах, подключение щелей к магистральному закладочному трубопроводу и подачу закладочной смеси в камеры по закладочному трубопроводу, отличающийся тем, что, с целью снижения трудоемкости закладочных работ и повышения интенсивности очистной выемки, закладочные щели образуют в целиках на всю их высоту, отводы в магистральном трубопроводе размещают напротив каждой щели, а в кровле камер укрепляют отрезки труб, торцы которых герметизируют и снабжают поисковыми элементами, концы последних располагают в щелях, закладочную смесь подают через отводы в щели до полного заполнения их и камеры, вынимают целики, при этом по мере их отработки обнажают поисковые элементы, разгерметизируют отрезки труб, соединяют их между собой и с отводами магистрального трубопровода, по образованному трубопроводу подают . закладочную смесь в пространство, образовавшееся от выемки целиков, начиная с нижнего, затем поочередно отсоединяют трубы в соседнем с заполненной камерой пространстве.METHOD FOR LAYING THE EQUIPPED SPACE OF A SOLID MIXTURE, including laying the main filling pipeline with taps in the preparatory excavation, forming filling slots in the chambers, connecting the cracks to the main filling pipe and feeding the filling mixture into the chambers through the filling pipe, characterized in that work and increase the intensity of the cleaning recess, filling slots form in the pillars to their entire height, bends in the main pipeline e is placed opposite each slot, and pipe sections are strengthened in the roof of the chambers, the ends of which are sealed and provided with search elements, the ends of the pipes are placed in the slots, the filling mixture is fed through the taps into the slots until they and the chamber are completely filled, the pillars are taken out, and as they are mining exposes the search elements, depressurizes the pipe segments, connect them together and with the bends of the main pipeline, they are fed through the formed pipeline. filling mixture into the space formed from the excavation of the pillars, starting from the bottom, then the pipes are alternately disconnected in the space adjacent to the chamber filled. SU,». 1116183SU, ". 1116183 1 . 111611 . 11161
SU823409392A 1982-03-12 1982-03-12 Method of filling worked-out space with hardening mixture SU1116183A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU823409392A SU1116183A1 (en) 1982-03-12 1982-03-12 Method of filling worked-out space with hardening mixture

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU823409392A SU1116183A1 (en) 1982-03-12 1982-03-12 Method of filling worked-out space with hardening mixture

Publications (1)

Publication Number Publication Date
SU1116183A1 true SU1116183A1 (en) 1984-09-30

Family

ID=21001851

Family Applications (1)

Application Number Title Priority Date Filing Date
SU823409392A SU1116183A1 (en) 1982-03-12 1982-03-12 Method of filling worked-out space with hardening mixture

Country Status (1)

Country Link
SU (1) SU1116183A1 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
1. Авторское свидетельство СССР 756043, кл. Е 21 F 15/00, 1978. 2. Авторское свидетельство СССР 769030, кл. Е 21 F 15/00, 1978. *

Similar Documents

Publication Publication Date Title
RU2283431C1 (en) Method for thick steep mineral seam mining along with goaf filling
SU1116183A1 (en) Method of filling worked-out space with hardening mixture
SU1668667A1 (en) Method for combination mining of gently sloping seams
SU1745935A1 (en) Method of protecting and supporting development drift on its pitching portion
SU756044A1 (en) Method of hydraulic filling-up of underground working at mining vertical seams on the strike
SU1239336A1 (en) Method of mining thick mineral deposits
SU1257240A1 (en) Method of erecting support strips of setting composition
SU1203241A1 (en) Method of mining mineral deposits with filling-up of excavated space
RU2101498C1 (en) Method of underground mineral mining
SU625059A1 (en) Method of conducting filling-up work
SU1209901A1 (en) Method of filling=up the bottom of chamber with setting composition
SU1149035A1 (en) Method of erecting filling strips in shield system of mining mineral deposits
SU1146478A1 (en) Method of conducting filling work
SU1710750A1 (en) Method of mining thick coal seams with filling
RU2069766C1 (en) Method for construction of isolation connection
US4440524A (en) Process for bringing a body of water into communication with a tunnel
SU1642003A1 (en) Method of mining mineral deposits
SU941631A1 (en) Method of filling-up excavated space
SU1661424A1 (en) Method for working out closely contiguous disrupted coal seams
SU1038679A2 (en) Method of laying underground pipeline
SU1645517A1 (en) Method of mining ore bodies in slices
SU1366640A1 (en) Method of producing artificial roof in working adjacent seams in permafrost environment
SU769030A1 (en) Method of filling worked area with hardenable filling in materials
SU1180536A2 (en) Method of forming workings in setting fill-up body
SU1282947A1 (en) Method of establishing artificial pillars