SU1097799A1 - Monolithic concrete support for mine workings - Google Patents

Monolithic concrete support for mine workings Download PDF

Info

Publication number
SU1097799A1
SU1097799A1 SU823419141A SU3419141A SU1097799A1 SU 1097799 A1 SU1097799 A1 SU 1097799A1 SU 823419141 A SU823419141 A SU 823419141A SU 3419141 A SU3419141 A SU 3419141A SU 1097799 A1 SU1097799 A1 SU 1097799A1
Authority
SU
USSR - Soviet Union
Prior art keywords
concrete
rocks
layer
temporary metal
frame
Prior art date
Application number
SU823419141A
Other languages
Russian (ru)
Inventor
Анатолий Васильевич Кирпикин
Виктор Васильевич Кирпикин
Original Assignee
Научно-Исследовательский Горнорудный Институт
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Научно-Исследовательский Горнорудный Институт filed Critical Научно-Исследовательский Горнорудный Институт
Priority to SU823419141A priority Critical patent/SU1097799A1/en
Application granted granted Critical
Publication of SU1097799A1 publication Critical patent/SU1097799A1/en

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

1. МОНОЛИТНАЯ БЕТОННАЯ КРЕПЬ ДЛЯ ГОРНЫХ ВЫРАБОТОК, включающа  временные металлические рамы, железобетонные зат жки и слой набрызтбетона , отличающа с  тем, что, с целью упрощени  монтажа и ///////////// демонтажа временных мет;аллических рам, улучшени  св зи набрызгбетона с закрепными породами и уменьшени  потерь бетонной смеси на отскок,зат жка выполнена в виде крестовины, состо щей из двух плит, причем одна плита зат жки установлена перпендикул рно к поверхности закрепных пород и выполнена в виде односкосного клина с пазом в своей средней части дл  установки в него второй плиты крестовины. 2. Крепь по П.1, о т л и ч ающ а   с   тем, что слой набрызгбетона помещен в промежутках между зат жками и имеет толщину, равную зазору между.временной металличес (Л кой рамой и закрепными породами. т.1. MONOLITHIC CONCRETE FASTENER FOR MINING WORKS, including temporary metal frames, reinforced concrete fasteners and a layer of concrete, characterized in that, in order to simplify the installation and ////////// frame, improving the bond of sprayed concrete with fixed rocks and reducing the loss of concrete mix for rebound, the pulling is made in the form of a cross, consisting of two plates, one puff plate installed perpendicular to the surface of the fixed rocks and made in the form of a single-slit wedge with a groove in his wednesday days of the part for installing the second cross plate into it. 2. The support according to Clause 1, about tl and h ayusha with the fact that the layer of sprayed concrete is placed in the spaces between the puffs and has a thickness equal to the gap between the temporary metal (L frame and fixed rocks. T.

Description

Изобретение относитс  к горному делу, а именно к креплени м горных вьфаботок при ведении подземных работ. Известна монолитна  бетонна  крепь, включающа  металлическую крепь с зат жками, по которым затем образуют бетонную оболочку опалубным бетонированием.или безопалубным набрызгбетониров нием tП. Недостатком  вл етс  трудоемкость работ, большой расход металла и бетона. Известна монолитна  бетонна  крепь дл  горных выработок, включаю ща  временные металлические рамы, железобетонные зат жки и слой набры бетона С2, Недостатком крепи  вл етс  трудо емкость работ по расклинке рам, забутовке и удалению металлических рам, большие потери набрызгбетона на отскок. Цель изобретени  - упрощение мон тажа и демонтажа временных металлических рам, улучшение св зи набрызг бетона с закрепленными породами и уменьшение потерь бетонной смеси на отскок. Поставленна  цель достигаетс  тем, что в монолитной бетонной крепи дл  горных выработок, включающей временные металлические рамы, железобетонные зат жки и слой набрызгбе тона, зат жка выполнена в виде крес товины, состо щей из двух, плит, при чем одна плита зат жки установлена перпендикул рно к поверхности закре ленных пород и вьтолнена в виде одн скосного клина с пазом в своей сред ней части дл  установки в него второй плиты крестовины. Кроме того, слой назбрызгбетона: помещен в промежутках между зат жка ми и имеет толщину,равную зазору ме ду временной металлической рамой и закрепными породами.; На фиг.1 показана выработка, зак репл ема  набрызгбетоном, продольный разрез, на фиг.2-4 - сечени  А-А, Б-Б и В-В на фиг.1 соответственно , на фиг.5-7 - соединение и конструкции железобетонных зат жек. Монолитна  бетонна  крепь устанавливаетс  следующим образом. После проведени  горной выработки 1 на величину шага установки крепи монтируют временную металлическую раму 2, несущие элементы которой вьшолнены из спецпрофил . Между рамой 2 и закрепленными породами 3 оставл ют зазор, равный толщине сло  возводимой впоследствии бетонной крепи 4 и соответствующий ширине железобетонных зат жек 5. Собранную раму 2 соедин ют ст жками 6 со смежной, ранее установленной рамой. Кровлю и бока выработки зат гивают железобетонными зат жками 5, которые укладывают вразбежку, размещают радиапьно по отношению к раме 2 и перпендикул рно к поверхности породного контура выработки 1 (фиг.1 и 2). При весьма слабых, неустойчивых закрепных породах 3 межд.у зат жкой 5 и породой 3 помещают металлическую сетку 7. Затем с помощью пневмобетрномашины производ т набрызгбетонирование , заполн   бетонной смесью промежутки между зат жками 5 и между металлическими рамами 2. При этом.в первую очередь закупоривают набрызгбетонной смесью трещины и углублени  на стенках и в кровле горной выработки, после чего равномерно заполн ют пространство между рамами 2 и породами 3, чем достигают необходимой толщины бетонной крепи 4 (фиг.З). После схватывани  и затвердевани  до требуемой прочности набрызгбетонной крепи 4 удал ют временные металлические рамы 2 (фиг.4) и используют их повторно, например дл  креплени  зтой же выработки 1. Зат жки 5 выполн ютс  в виде плиты, имеющей форму односкатного клина. Така  форма зат жки позвол ет совместить во времени выполнение операций по укладке зат жек 5, их фиксации и расклинк-е временных металлических рам 2. Дл  повышени  устойчивости зат жек 5 их устанавливают попарно с зат жкой-перегородкой 8, размеща  их перекрестно относительно друг друга. С помощью пазов 9 и to, вьшолненных в средней части одной из сторон соответственно зат жки 5 и перегородки 8,последние сочлен ют, образовыва  крестовину . Применение монолитной бетонной крепи горных выработок позвол ет упростить установку и извлечение временных металлических рам, исключить процесс забутовки закрепного пространства, уменьшить расход 3 набрызгбетона за счет использовани  железобетонных зат жек в качестве арматуры монолитной бетонной крепи и за счет снижени  потерь бетона на отскок, повысить коэффициент 799 повторного использовани  металлических рам, улучшить сцепление набрызгбетона с породным контуром выработки и взаимодействие бетонной крепи с закрепными породами.FIELD OF THE INVENTION The invention relates to mining, in particular to fastenings of mining operations during underground operations. Monolithic concrete lining is known, including metal lining with clamps, on which the concrete shell is then formed by form-based concreting, or without decking, and concrete tP. The disadvantage is the complexity of work, high consumption of metal and concrete. Known monolithic concrete lining for mine workings, including temporary metal frames, reinforced concrete fasteners and a layer of concrete C2. A disadvantage of lining is the difficulty of splitting the frames, filling and removing metal frames, and there is a large loss of concrete bounce. The purpose of the invention is to simplify the mounting and dismantling of temporary metal frames, improving the bond of sprayed concrete with fixed rocks and reducing the loss of concrete mix to rebound. The goal is achieved by the fact that in monolithic concrete lining for mine workings, including temporary metal frames, reinforced concrete taps and a layer of sprayed tone, the taper is made in the form of a chair consisting of two plates, with one talted slab installed perpendicular straight to the surface of the enlarged rocks and is made in the form of a single bevel wedge with a groove in its middle part for installing a second cross plate into it. In addition, a layer of concrete spatter: placed in the gaps between the puffs and has a thickness equal to the gap between the temporary metal frame and the fixed rocks .; Figure 1 shows the production, the fastening of the sprayed concrete, a longitudinal section; in Figures 2-4, sections A-A, B-B and B-B in Fig. 1, respectively, in Figures 5-7 - the connection and structures reinforced concrete pads. Monolithic concrete lining is installed as follows. After the mine workings out 1, the temporary metal frame 2 is mounted on the size of the installation step, the bearing elements of which are made of special profile. Between the frame 2 and the fixed rocks 3 there is left a gap equal to the thickness of the layer of subsequently erected concrete lining 4 and corresponding to the width of reinforced concrete tacks 5. The assembled frame 2 is connected by straps 6 to an adjacent, previously installed frame. The roof and sides of the excavation are tightened with reinforced concrete fasteners 5, which are placed in a razbezhku, placed radically with respect to the frame 2 and perpendicular to the surface of the rock contour of the generation 1 (Figures 1 and 2). With very weak, unstable fixed rocks 3 between the puff 5 and the rock 3, the metal mesh 7 is placed. Then, using a pneumatic concrete machine, the concrete is sprayed and filled with the concrete mixture between the puffs 5 and between the metal frames 2. At the same time, first of all blocking the concrete mix with cracks and depressions on the walls and in the roof of the mine workings, then uniformly fill the space between the frames 2 and the rocks 3, thus reaching the required thickness of the concrete lining 4 (Fig. 3). After setting and hardening to the required strength of the sprayed concrete lining 4, temporary metal frames 2 are removed (Fig. 4) and are reused, for example, to fasten the same production 1. The shafts 5 are made in the form of a single wedge-shaped plate. This form of tightening makes it possible to combine in time the execution of operations for placing the plugs 5, fixing them and unfolding the temporary metal frames 2. To increase the stability of the plugs 5, they are installed in pairs with the partition-clamp 8, placing them crosswise with respect to each other . Using the slots 9 and to, made in the middle part of one of the sides, respectively, of the puff 5 and the partition 8, the latter are joined to form a crosspiece. The use of monolithic concrete lining of mine workings allows to simplify the installation and removal of temporary metal frames, eliminate the filling-in process of the fixed space, reduce the consumption of 3 concrete by using reinforced concrete shafts as reinforcement of monolithic concrete lining and by reducing the loss of concrete for rebound, increase the coefficient 799 reuse metal frames, improve the adhesion of sprayed concrete to the rock contour of the excavation and the interaction of concrete lining with fixed rocks.

5five

V////////////////7777V //////////////// 7777

/I/f/ I / f

PU2.2PU2.2

Claims (2)

1. МОНОЛИТНАЯ БЕТОННАЯ КРЕПЬ ДЛЯ ГОРНЫХ ВЫРАБОТОК, включающая временные металлические рамы, железобетонные затяжки и слой набрызг— бетона, отличающая с я тем, что, ‘с целью упрощения монтажа и пород и выполнена в виде односкосного клина с пазом в своей средней части для установки в него второй плиты крестовины.1. MONOLITHIC CONCRETE FASTENER FOR MINING, including temporary metal frames, reinforced concrete puffs and a spray-concrete layer, characterized in that, in order to simplify installation and rocks, it is made in the form of a single-axis wedge with a groove in its middle part for installation into it the second plate of the cross. 2. Крепь поп.1, отличающаяся тем, что слой набрызгбе· тона помещен в промежутках между затяжками и имеет толщину, равную зазору между.временной металлической рамой и закрепными породами.2. Lining pop. 1, characterized in that the spray layer is placed between the puffs and has a thickness equal to the gap between the temporary metal frame and the fixing rocks. j η г с h \ ч (¾¾ ТУ АО УМ ......ОШ-j η g with h \ h (¾¾ TU AO UM ...... OSH- W2J л лзей) (¾¾¾ уц стал ун, casu—o_(M«bsai—О—ssaJ—шь,---, J//W2J л lzейi) (¾¾¾ uc became un, casu — o_ (M «bsai – О – ssaJ – ш, ---, J // -J г -J g АA 1Θ977991Θ97799
SU823419141A 1982-04-07 1982-04-07 Monolithic concrete support for mine workings SU1097799A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU823419141A SU1097799A1 (en) 1982-04-07 1982-04-07 Monolithic concrete support for mine workings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU823419141A SU1097799A1 (en) 1982-04-07 1982-04-07 Monolithic concrete support for mine workings

Publications (1)

Publication Number Publication Date
SU1097799A1 true SU1097799A1 (en) 1984-06-15

Family

ID=21005267

Family Applications (1)

Application Number Title Priority Date Filing Date
SU823419141A SU1097799A1 (en) 1982-04-07 1982-04-07 Monolithic concrete support for mine workings

Country Status (1)

Country Link
SU (1) SU1097799A1 (en)

Similar Documents

Publication Publication Date Title
DE59310069D1 (en) Method of erecting a concrete wall using braced formwork
US3788023A (en) Assembly method for beam structures
SU1097799A1 (en) Monolithic concrete support for mine workings
JPH0941666A (en) Concrete formwork construction method
RU2101501C1 (en) Method of preservation of mine working
US3436892A (en) Method of producing concrete panel assemblies
RU2087720C1 (en) Method of support of mine workings and device for its embodiment
RU2043505C1 (en) Method for support of mine workings
SU718528A1 (en) Method of constructing the lining of underground structures
JPH1144188A (en) Constructing method for bulkhead inside shielded tunnel
JPH0485461A (en) Reinforcing structure of building
FR2439848A1 (en) Prefabricated building construction - has precast wall panels fixed by vertical tie bars in joint grooves and which also fix cleats for roof frames
JPH10266794A (en) Tunnel lining reinforcing method using mortar composit carbon fiber sheet
GB1402259A (en) Building method and structure using prefabricated elements
JPH11181809A (en) Construction of large scale prestressed concrete culvert
SU1055879A1 (en) Method of roof control in mine workings
RU2004811C1 (en) Method for tunnel lining with monolithic concrete
GB1436849A (en) Method of making a rigid joint for constructing precast reinforced concrete and prestressed concrete structures
ES2122819A1 (en) Structure for forming recoverable formwork (shuttering)
JPH0313643A (en) Construction method for long and large structure with expansion joint section
SU1315568A1 (en) Method of constructing a tunnel
RU2069759C1 (en) Method for support of mine workings
SU1420167A1 (en) Prefabricated tunnel lining
RU96101124A (en) METHOD FOR CONSTRUCTING DEEP LOAD TUNNELS IN Slow-resilient soils
JPS58204228A (en) Construction of concrete retaining wall