PL122905B2 - Method of mending the masonry lining of a mine excavation in particular of a retention tank - Google Patents

Method of mending the masonry lining of a mine excavation in particular of a retention tank Download PDF

Info

Publication number
PL122905B2
PL122905B2 PL22496980A PL22496980A PL122905B2 PL 122905 B2 PL122905 B2 PL 122905B2 PL 22496980 A PL22496980 A PL 22496980A PL 22496980 A PL22496980 A PL 22496980A PL 122905 B2 PL122905 B2 PL 122905B2
Authority
PL
Poland
Prior art keywords
casing
tank
reservoir
metal
partitions
Prior art date
Application number
PL22496980A
Other languages
Polish (pl)
Other versions
PL224969A2 (en
Inventor
Zenon Nowak
Emil Slota
Original Assignee
Przed Robot Gorniczych
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Przed Robot Gorniczych filed Critical Przed Robot Gorniczych
Priority to PL22496980A priority Critical patent/PL122905B2/en
Publication of PL224969A2 publication Critical patent/PL224969A2/xx
Publication of PL122905B2 publication Critical patent/PL122905B2/en

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

Przedmiotem wynalazku jest sposób zniszczonego obmurza górniczego zbiornika retencyj¬ nego stosowanego w podziemiach kopaln zarówno w polach wybierkowych jak i przy szybach wydobywczych.Prawidlowy przebieg procesu produkcyjnego w kopalni wymaga uzyskania mozliwie stalego natezenia strugi urobku doplywajacego do urzadzen przewozowych i wydobywczych. Ze wzgledu na nierównomiernosc urabiania wegla przez kombajny w czasie zmiany wydobywczej wystepuja okresy o duzym natezeniu strugi urobku i strugi o malym natezeniu. W zwiazku z czym w kopalniach powszechnie stosuje sie zbiorniki retencyjne typu szybowego i skarpowego, z których urobek wypuszcza sie struga równomierna przez caly czas zmiany wydobywczej.W czasie pracy tych zbiorników ich obudowa narazona jest na dzialanie dynamiczne. Kesy urobku o róznej wielkosci spadajac z pewnej wysokosci uderzaja o sciany zbiornika powodujac z biegiem czasu wyrwy w obudowie lub odspajania tej obudowy od górotworu. Dotychczas zbiornik ze zniszczona obudowa wylaczano z eksploatacji na czas od dwóch do trzech miesiecy i poddawano go remontowi generalnemu. W praktyce górniczej nie zawsze jednak mozna zatrzymac zbiornik retencyjny na dlugi okres czasu.Znany jest sposób wzmacniania obudowy podziemnych zbiorników wyrównawczych polega¬ jacy na tym, ze na calej powierzchni obudowy zbiornika wierci sie otwory rozmieszczone w regularnych odstepach, najkorzystniej na rogach siatki kwadratowej o boku równym 1 m. Nastep¬ nie w tych otworach osadza sie kotwie wklejane tak, aby ich konce nie wystawaly poza plaszczyzne obudowy. Na koniec zas pustki i wyrwy powstale w obudowie zbiornika wypelnia sie betonem az do uzyskania jednolitej plaszczyzny obudowy.Istota sposobu wedlug wynalazku polega na tym, ze na czas remontu u wylotu zbiornika zabudowuje sie lej zsypowy z oslona kierujaca urobek wpadajacy do tego zbiornika pionowo w dól.Natomiast w samym zbiorniku umieszcza sie ruchomy pomost roboczy. W miejscach ubytków i wyrw w obudowie zbiornika zabudowuje sie metalowe przegrody dostosowane ksztaltem do ksztaltu obudowy zbiornika. Przegrody te sa wykonane z metalowych ksztaltowników wzmocnio¬ nych dodatkowo pierscieniami. Na koniec w pustych przestrzeniach zabudowuje sie siec lin2 122 905 stalowych których wstepny naciag uzyskuje sie poprzez kotwy stalowe o kierunkach kazdorazowo dostosowanych do ksztaltu ubytku w obmurzu lub skale poza obudowa zbiornika, a nastepnie siec lin stalowych z cala przestrzenia wypelnia sie stopniowo (etapami) betonem tworzac w ten sposób strunobetonowe wypelnienie ubytku odporne na dzialanie sil dynamicznych. Ponadto strunobeton laczy w jedna calosc obudowe zbiornika calizne górotworu i metalowa przegrode/Taki sposób naprawy obmurza górniczego zbiornika retencyjnego nie wymaga przerywania jego pracy.Przedmiot wynalazku jest dokladniej wyjasniony na zalaczonym rysunku, na którym fig. 1 przedstawia zbiornik retencyjny bedacy w remoncie w pionowym przekroju osiowym, a fig. 2 — ten sam zbiornik w przekroju poprzecznym wzdluz linii A-A zaznaczonej na fig. 1.Jak uwidoczniono na rysunku naprawe wyrw lub ubytków 1 w obudowie 2 zbiornika retencyj¬ nego wykonuje sie bez przerywania pracy tego zbiornika. W tym celu najpierw w zbiorniku zabudowuje sie ruchomy pomost roboczy 3 oraz lej zsypowy z oslona 4. Nastepnie w miejscach wyrw lub ubytków 1 w obudowie 2 umieszcza sie metalowe przegrody 5 wykonane z ksztaltowni¬ ków wzmocnionych dodatkowo pierscieniami 6, o ksztalcie dostosowanym do ksztaltu obudowy 2 zbiornika. W wyrwach lub ubytkach 1 zabudowuje sie siec lin stalowych 7, których konce kotwi sie znanymi kotwami 8 do skaly lub obmurza ubytku. Na koniec wszystkie pustki za tymi przegrodami wraz z napietymi linami 7 wypelnia sie betonem tworzac strunobeton tak, aby polaczyl on obudowe zbiornika, calizne górotworu i metalowa przegrode wjedna calosc. Wszystkie te prace wykonuje sie z ruchomego pomostu roboczego 3, który w czasie napelniania zbiornika urobkiem ustawia sie przy zrebie tego zbiornika.Zastrzezenie patentowe Sposób naprawy obmurza pionowego wyrobiska górniczego zwlaszcza zbiornika retencyj¬ nego, znamienny tym, ze najpierw u wylotu zbiornika zabudowuje sie lej zsypowy z oslona (4) kierujaca urobek pionowo w dól oraz ruchomy pomost roboczy (3), po czym w miejscach wyrw lub ubytków (1) w obudowie (2) umieszcza sie metalowe przegrody (5) wykonane z metalowych ksztaltowników wzmocnionych dodatkowo pierscieniami (6), dostosowane swoim ksztaltem do ksztaltu obudowy (2) zbiornika, a na koniec puste przestrzenie poza tymi przegrodami wypelnia sie szczelnie betonem laczacym obudowe zbiornika (2), calizne górotworu i metalowa przegrode (5) w jedna calosc.122 905 Fig. 2 PLThe subject of the invention is a method of damaged lining of a mining retention reservoir used in mine undergrounds, both in extraction fields and at mining shafts. The correct course of the production process in a mine requires a constant stream of excavated material flowing to the transport and mining equipment. Due to the unevenness of the coal mining by the shearers, during the mining shift, there are periods of high intensity of the output stream and low intensity stream. Therefore, in mines, shaft and slope-type retention reservoirs are commonly used, from which the spoil flows out uniformly throughout the entire mining shift. During their operation, their casing is exposed to dynamic action. Tosses of spoil of various sizes falling from a certain height hit the walls of the tank, causing in the course of time tears in the casing or detachment of this casing from the rock mass. So far, the tank with the damaged housing was taken out of service for two to three months and underwent a general overhaul. In mining practice, however, it is not always possible to stop the storage reservoir for a long period of time. It is known to strengthen the lining of underground expansion tanks by drilling holes at regular intervals on the entire surface of the reservoir housing, preferably at the corners of a square mesh with a side equal to 1 m. Then, glued-in anchors are placed in these holes so that their ends do not protrude beyond the plane of the casing. Finally, the voids and holes formed in the tank housing are filled with concrete until a uniform surface of the housing is obtained. The essence of the method according to the invention consists in the fact that during the renovation at the outlet of the tank, a chute is built with a cover directing the material falling into this tank vertically downwards. On the other hand, a movable working platform is placed in the tank itself. In the places of losses and holes in the casing of the tank, metal partitions are installed, adapted in shape to the shape of the casing of the tank. These partitions are made of metal shapes additionally reinforced with rings. Finally, a network of steel ropes is built in the voids, the initial tension of which is obtained by steel anchors with directions each time adapted to the shape of the defect in the brickwork or rock outside the tank housing, and then the network of steel ropes from the entire space is gradually filled with concrete (in stages) thus creating a prestressed concrete filling of the cavity resistant to dynamic forces. Moreover, pre-stressed concrete joins the entire structure of the reservoir and the metal partition into one whole / This method of repairing the brickwork of the mining storage reservoir does not require interrupting its operation. axially, and in Fig. 2, the same reservoir in a cross section along the line AA marked in Fig. 1. As shown in the drawing, repairing the tears or cavities 1 in the retention reservoir housing 2 is performed without interrupting the operation of the reservoir. For this purpose, a movable working platform 3 and a chute with a cover 4 are installed in the tank first. Then, in the places of tears or holes 1 in the casing 2, metal partitions 5 made of shapes additionally reinforced with rings 6 are placed, with a shape adapted to the shape of the casing 2 tank. A network of steel ropes 7 is built into the holes or cavities 1, the ends of which are anchored with known anchors 8 to the rock or wall of the defect. Finally, all the voids behind these partitions, together with the tensioned lines 7, are filled with concrete, forming pre-stressed concrete so that it joins the casing of the tank, the entire rock mass and the metal partition together. All these works are carried out on the movable working platform 3, which is positioned at the bottom of the reservoir during the filling of the reservoir. Patent claim Method of repairing the vertical brickwork of a mining excavation, especially a retention reservoir, characterized by the fact that a chute is built at the reservoir outlet first with a cover (4) directing the excavated material vertically downwards and a movable working platform (3), then in the casing (2) there are metal partitions (5) made of metal shapes additionally reinforced with rings (6) in the housing (2) , adapted to the shape of the casing (2) of the tank, and finally the voids outside these partitions are tightly filled with concrete joining the casing of the tank (2), the complete rock mass and the metal partition (5) into one whole. 122 905 Fig. 2 EN

Claims (2)

1. Zastrzezenie patentowe Sposób naprawy obmurza pionowego wyrobiska górniczego zwlaszcza zbiornika retencyj¬ nego, znamienny tym, ze najpierw u wylotu zbiornika zabudowuje sie lej zsypowy z oslona (4) kierujaca urobek pionowo w dól oraz ruchomy pomost roboczy (3), po czym w miejscach wyrw lub ubytków (1) w obudowie (2) umieszcza sie metalowe przegrody (5) wykonane z metalowych ksztaltowników wzmocnionych dodatkowo pierscieniami (6), dostosowane swoim ksztaltem do ksztaltu obudowy (2) zbiornika, a na koniec puste przestrzenie poza tymi przegrodami wypelnia sie szczelnie betonem laczacym obudowe zbiornika (2), calizne górotworu i metalowa przegrode (5) w jedna calosc.122 905 Fig. 1. Patent claim A method of repairing the vertical brickwork of a mining excavation, especially a retention reservoir, characterized in that a chute with a cover (4) directing the excavated material vertically downwards is installed at the mouth of the reservoir, and a movable working platform (3), then in places holes or cavities (1) in the casing (2), metal partitions (5) made of metal shapes additionally reinforced with rings (6) are placed, adjusted to the shape of the tank casing (2), and finally the empty spaces outside these partitions are filled tightly with concrete joining the tank casing (2), the entire rock mass and the metal partition (5) into one whole. 122 905 Fig. 2 PL2 PL
PL22496980A 1980-06-12 1980-06-12 Method of mending the masonry lining of a mine excavation in particular of a retention tank PL122905B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
PL22496980A PL122905B2 (en) 1980-06-12 1980-06-12 Method of mending the masonry lining of a mine excavation in particular of a retention tank

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PL22496980A PL122905B2 (en) 1980-06-12 1980-06-12 Method of mending the masonry lining of a mine excavation in particular of a retention tank

Publications (2)

Publication Number Publication Date
PL224969A2 PL224969A2 (en) 1981-04-24
PL122905B2 true PL122905B2 (en) 1982-09-30

Family

ID=20003667

Family Applications (1)

Application Number Title Priority Date Filing Date
PL22496980A PL122905B2 (en) 1980-06-12 1980-06-12 Method of mending the masonry lining of a mine excavation in particular of a retention tank

Country Status (1)

Country Link
PL (1) PL122905B2 (en)

Also Published As

Publication number Publication date
PL224969A2 (en) 1981-04-24

Similar Documents

Publication Publication Date Title
EP1162345B1 (en) R. b. yun's method for the exploitation of open-air mining fields
IL45242A (en) Method of blasting and reinforcing rock cavities
CN114837667B (en) Construction method for crushing stratum large-diameter vertical shaft by adopting vertical shaft heading machine
CA1171675A (en) Elongated underground construction having a uniform section and method of building this construction
CN112943260A (en) Tunnel middle partition wall step excavation method
Marlow et al. Shotcrete ribs and cemented rock fill ground control methods for stoping in weak squeezing rock at Wattle Dam Gold Mine
RU2128773C1 (en) Method for supporting mining workings with loose roof rock by anchor support
PL122905B2 (en) Method of mending the masonry lining of a mine excavation in particular of a retention tank
RU2132950C1 (en) Method for combination development of deposits
RU2289694C1 (en) Method for reclamation of limestone quarries during construction of industrial structures
CN115773113B (en) Mining method for steeply inclined, broken, thick and large ore bodies
McKOWN Perimeter control blasting for underground excavations in fractured and weathered rock
RU2166631C2 (en) Method of opening of mine horizons from deep openpits in mining of kimberlite deposits
SU1266988A1 (en) Method of working pillars
SU989083A1 (en) Method of driving large-section workings
Gustafsson Wire cutting as a complement to drill and blast in vibration sensitive environments
SU1717833A1 (en) Method of maintaining workings with heaving floors
SU711297A1 (en) Mine roof support
RU2152473C1 (en) Method for erection of vehicular traffic tunnel of urban ring highway of megapolis
SU1647203A1 (en) Underground construction technique
Bonniga A case study on Tunneling using NATM.
SU1705582A1 (en) Method of making large-volume cavity in rocks
SU1608345A1 (en) Method of mining mineral deposits
SU1113465A1 (en) Underground structure finishing
SU1700237A1 (en) Method of dumping overburden rock in flooded conditions