NO141445B - PROCEDURES FOR CONSTRUCTING AN UNDERWATER CONSTRUCTION - Google Patents

PROCEDURES FOR CONSTRUCTING AN UNDERWATER CONSTRUCTION Download PDF

Info

Publication number
NO141445B
NO141445B NO751737A NO751737A NO141445B NO 141445 B NO141445 B NO 141445B NO 751737 A NO751737 A NO 751737A NO 751737 A NO751737 A NO 751737A NO 141445 B NO141445 B NO 141445B
Authority
NO
Norway
Prior art keywords
membrane
water
granular material
construction
filling
Prior art date
Application number
NO751737A
Other languages
Norwegian (no)
Other versions
NO141445C (en
NO751737L (en
Inventor
Brian Edward Welsley Dowse
Original Assignee
Golder Hoek & Associates Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Golder Hoek & Associates Ltd filed Critical Golder Hoek & Associates Ltd
Publication of NO751737L publication Critical patent/NO751737L/no
Publication of NO141445B publication Critical patent/NO141445B/en
Publication of NO141445C publication Critical patent/NO141445C/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/02Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/06Constructions, or methods of constructing, in water

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Revetment (AREA)
  • Earth Drilling (AREA)
  • Underground Or Underwater Handling Of Building Materials (AREA)

Description

Oppfinnelsen vedrører en fremgangsmåte for oppbygging av en undervannskonstruksjon, hvor en tett membran festes til periferien av en flytende konstruksjon, og membranen, når den flytende konstruksjonen er plassert på oppbyggingsstedet, fylles og bringes til kontakt med elvebunnen eller havbunnen med en bunndel. The invention relates to a method for the construction of an underwater structure, where a tight membrane is attached to the periphery of a floating structure, and the membrane, when the floating structure is placed at the construction site, is filled and brought into contact with the riverbed or the seabed with a bottom part.

Med foreliggende oppfinnelse tar man særlig sikte på å tilveiebringe en undervannskonstruksjon som egner seg som bruk som oljeborerigg. Konvensjonelle oljeborerigger er vanligvis i form av store prefabrikerte metallkonstruksjoner. Disse er dyre, krever lang byggetid, og det er også forbundet med store problemer å taue dem ut til oppstillingsstedet. With the present invention, the particular aim is to provide an underwater structure that is suitable for use as an oil drilling rig. Conventional oil drilling rigs are usually in the form of large prefabricated metal structures. These are expensive, require a long construction time, and towing them out to the installation site is also associated with major problems.

En hensikt med foreliggende oppfinnelse er A purpose of the present invention is

å tilveiebringe en undervannskonstruksjon som er billigere enn de foran nevnte vanlige stålkonstruksjoner, kan bygges opp på relativt kort tid og lett kan slepes på plass. to provide an underwater structure which is cheaper than the usual steel structures mentioned above, can be built up in a relatively short time and can be easily towed into place.

Ifølge oppfinnelsen går man frem på den måten ved oppbyggingen av en undervannskonstruksjon som inn-ledningsvis nevnt, at membranen fylles med ikke-avbindbart kornformet materiale, og at det kornformede materialet dreneres slik at det ytre vanntrykk kan utøve et trykk for å gjøre materialet koherent slik at det kornformede materialet kan bære konstruksjonen. According to the invention, the construction of an underwater structure, as mentioned at the outset, proceeds in such a way that the membrane is filled with non-bondable granular material, and that the granular material is drained so that the external water pressure can exert a pressure to make the material coherent so that the granular material can support the construction.

Det som er det vesentlige med foreliggende oppfinnelse er således at det benyttes et stort legeme av kornformet materiale (eksempelvis sand) som holdes på plass i en tett membran og holdes i en hovedsaklig tørr tilstand ved at det er sørget for dreneringsmulighet. Dreneringen betyr en sterk øking av skjærstyrken og man får derfor den nødvendige What is essential about the present invention is thus that a large body of granular material (for example sand) is used which is held in place in a tight membrane and is kept in an essentially dry state by providing for the possibility of drainage. The drainage means a strong increase in shear strength and you therefore get the required strength

styrke med hensyn på bæring. strength with regard to bearing.

Fra det britiske patentskrift nr. 1 136 178 er det kjent en utførelse hvor man som fyllmateriale benytter våtsand. Den anvendte membran er nemlig vanngjennomtrengelig og i realiteten fyller man altså membranen med en blanding av vann og sand. Denne kjente konstruksjon er dessuten bare egnet for mindre konstruksjoner. From the British patent document no. 1 136 178, an embodiment is known where wet sand is used as filling material. The membrane used is indeed water permeable and in reality the membrane is therefore filled with a mixture of water and sand. This known construction is also only suitable for smaller constructions.

Fra US patentskrift nr. 3 798 912 er det kjent et konsept som avskiller seg fra det her foreslåtte, fordi man i US patentskriftet tar sikte på å benytte en blanding som fryser og danner et bæregrunnlag. From US patent no. 3 798 912 a concept is known which differs from that proposed here, because in the US patent the aim is to use a mixture which freezes and forms a support base.

Fra det tyske offentliggjøringsskrift nr. From the German publication no.

2 036 470 er det kjent å foreta en nivellering av en massiv prefabrikert konstruksjon ved hjelp av en indre ringmembran ved bunnen. Denne ringmembran benyttes imidlertid bare til å omgi en betongblanding til. denne er herdet. Det dreier seg således ikke om å benytte et drenert samlegeme for bæring. 2 036 470 it is known to carry out a leveling of a massive prefabricated construction by means of an inner ring membrane at the bottom. However, this ring membrane is only used to surround a concrete mixture. this one is hardened. It is therefore not a matter of using a drained joint for bearing.

Oppfinnelsen skal beskrives nærmere under henvisning til tegningene hvor: fig. 1-3 viser forskjellige trinn under oppbyggingen av en undervannskonstruksjon, og The invention shall be described in more detail with reference to the drawings where: fig. 1-3 show various steps during the construction of an underwater structure, and

fig. 4 viser et forstørret riss av en fig. 4 shows an enlarged view of one

detalj i fig. 2. detail in fig. 2.

Fig. 1 viser et første trinn som består i Fig. 1 shows a first step which consists of

at en konstruksjonsenhet 10 med tilhørende tett membran 12 fløtes ut til byggestedet. Membranen er festet vanntett til enhetens nedre periferi og er sammenfoldet under transporten. På byggestedet holdes konstruksjonen på plass ved hjelp av ankere, og vann pumpes så inn i membranen slik at den blåses opp og beveger seg med sin bunndel ned mot sjøbunnen 14 som undervannskonstruksjonen skal bygges opp på. Tre konsentriske rør 16,18, 20 (se fig. 2) føres så ned gjennom en boring 22 i enheten 10, helt til deres nedre ender befinner seg nær membranens bunn. Det innerste rør 16 er perforert og de to ytre rør 18 og 20 er tette. Mellom røret 18 og røret 16 er det anordnet en pakning 24 som er festet til røret 18. En blanding av grov sand og vann pumpes så ned i ringrommet mellom rørene 18 og 20, slik at membranbunnen tilføres et drenerings-lag 28 bestående av grov sand. Såsnart dette lag 28 har fått that a construction unit 10 with associated tight membrane 12 is floated out to the construction site. The membrane is attached watertight to the unit's lower periphery and is folded during transport. At the construction site, the structure is held in place by means of anchors, and water is then pumped into the membrane so that it is inflated and moves with its bottom part down towards the seabed 14 on which the underwater structure is to be built. Three concentric tubes 16, 18, 20 (see Fig. 2) are then passed down through a bore 22 in the unit 10, until their lower ends are near the bottom of the membrane. The innermost tube 16 is perforated and the two outer tubes 18 and 20 are sealed. Between the pipe 18 and the pipe 16, a gasket 24 is arranged which is attached to the pipe 18. A mixture of coarse sand and water is then pumped down into the annulus between the pipes 18 and 20, so that the membrane bottom is supplied with a drainage layer 28 consisting of coarse sand . As soon as this team 28 has got

en tilstrekkelig tykkelse erstattes den grove sand i sand-vann-blandingen av finere sand og det bygges opp et sandlag 30 på toppen av laget 28. Man veksler så med ifylling av lag bestående av grov sand og fin sand, helt til membranen er fylt til ønsket høyde. Under pumpingen dreneres vann fra sandlagene gjennom røret 16, dvs. gjennom dettes perforerte vegger, og vannet suges opp gjennom røret og ut gjennom en pumpeledning 32. Ettersom fyllingsnivået øker trekkes de to ytre rørene 18 og 20 opp slik at deres nedre ender stadig ligger nær fyllingens øvre nivå. a sufficient thickness, the coarse sand in the sand-water mixture is replaced by finer sand and a sand layer 30 is built up on top of the layer 28. You then alternate filling in layers consisting of coarse sand and fine sand, until the membrane is filled to capacity desired height. During pumping, water is drained from the sand layers through the pipe 16, i.e. through its perforated walls, and the water is sucked up through the pipe and out through a pump line 32. As the filling level increases, the two outer pipes 18 and 20 are pulled up so that their lower ends are constantly close the filling's upper level.

Når membranen er fylt til ønsket nivå senkes enheten 10 ned på toppen av sandfyllingen•(se fig. 3) og ytter-rørene 18 og 20 fjernes. Innerrøret blir igjen for fortsatt utsuging av vann som dreneres inn i røret. Dreneringen lettes ved anordningen av dreneringslagene 28. When the membrane is filled to the desired level, the unit 10 is lowered onto the top of the sand filling• (see fig. 3) and the outer tubes 18 and 20 are removed. The inner pipe remains for continued extraction of water that is drained into the pipe. The drainage is facilitated by the arrangement of the drainage layers 28.

Ved at vann trekkes ut av sandfyllingen vil As water is drawn out of the sand filling will

en oppbygging av porevanntrykk i sanden reduseres og på den måten kan man holde den indre skjærstyrke i den delvist drenerte sand-fylling på et egnet nivå, idet det naturlige hydrostatiske vanntrykk hele tiden virker på utsiden av membranen. Undervanns-konstruks j onen blir på denne måten i stand til å bære enheten 10. Enheten 10 gir en temporær eller permanent arbeidsplass over vannflaten. Oppfinnelsen kan naturligvis også benyttes til å tilveiebringe en molo eller en kunstig øy. a build-up of pore water pressure in the sand is reduced and in this way the internal shear strength in the partially drained sand filling can be kept at a suitable level, as the natural hydrostatic water pressure is constantly acting on the outside of the membrane. In this way, the underwater construction is able to carry the unit 10. The unit 10 provides a temporary or permanent workplace above the water surface. The invention can of course also be used to provide a breakwater or an artificial island.

Istedet for sand kan det benyttes ethvert annet egnet kornformet materiale og det kan benyttes et eller flere perforerte rør for drenering. Instead of sand, any other suitable granular material can be used and one or more perforated pipes can be used for drainage.

I utførelseseksemplet er membranen konisk, men man kan naturligvis også benytte andre utførelsesformer, f.eks. sylindriske og hyperboliske utførelser. In the design example, the membrane is conical, but you can of course also use other designs, e.g. cylindrical and hyperbolic designs.

Enheten 10 kan benyttes som oljeborings-plattform og i slike og lignende tilfeller forsynes enheten med mannskapsbekvemmeligheter, verksteder, oljeboringsutstyr, etc, herunder også lagringsmuligheter for ferskvann og eventuelt også for olje. The unit 10 can be used as an oil drilling platform and in such and similar cases the unit is provided with crew amenities, workshops, oil drilling equipment, etc., including storage options for fresh water and possibly also for oil.

Undervannskonstruksjonen egner seg for vanndybder på opptil 300 m. The underwater construction is suitable for water depths of up to 300 m.

Claims (6)

1. Fremgangsmåte ved oppbygging av en undervanns-konstruks jon hvor en tett membran (12) festes til periferien av en flytende konstruksjon (10), og membranen, når den flytende konstruksjon er plassert på oppbyggingsstedet, fylles og bringes til kontakt med elvebunnen eller havbunnen med en bunndel, karakterisert ved at membranen fylles med et ikke-avbindbart kornformet materiale (28, 30) og at det kornformede materiale dreneres slik at det ytre vanntrykk kan utøve et trykk for å gjøre materialet koherent, slik at det kornformede materialet kan bære konstruksjonen.1. Procedure for the construction of an underwater structure where a tight membrane (12) is attached to the periphery of a floating structure (10), and the membrane, when the floating structure is placed at the construction site, is filled and brought into contact with the riverbed or the seabed with a bottom part, characterized in that the membrane is filled with a non-detachable granular material (28, 30) and that the granular material is drained so that the external water pressure can exert a pressure to make the material coherent, so that the granular material can support the structure . 2. Fremgangsmåte ifølge krav 1, karakterisert ved at materialfyllingen bygges opp med vek-slende lag av finere (30) og grovere (28) kornformet materiale, idet lagene med grovere kornformet materiale anordnes for å understøtte dreneringen.2. Method according to claim 1, characterized in that the material filling is built up with alternating layers of finer (30) and coarser (28) granular material, the layers of coarser granular material being arranged to support the drainage. 3. Fremgangsmåte ifølge krav 1 eller 2, karakterisert ved at membranen strekkes ut ved innpumping av vann.3. Method according to claim 1 or 2, characterized in that the membrane is stretched by pumping in water. 4. Fremgangsmåte ifølge krav 1, 2 eller 3, karakterisert ved at materialfyllingen opp-bygges ved å pumpe en blanding av kornformet materiale og vann inn i membranen, idet vann trekkes ut fra fyllingen.4. Method according to claim 1, 2 or 3, characterized in that the material filling is built up by pumping a mixture of granular material and water into the membrane, water being extracted from the filling. 5. Fremgangsmåte ifølge krav 4, karakterisert ved at blandingen føres inn gjennom det ytre (20)av to konsentriske rør som er senket ned i membranen, og at vannet trekkes ut gjennom det indre rør, idet dette er perforert, samt ved at det ytre rør løftes under fyllingen slik at rørets nedre ende holdes i nærheten av fyllingens øvre nivå.5. Method according to claim 4, characterized in that the mixture is introduced through the outer (20) of two concentric tubes which are sunk into the membrane, and that the water is drawn out through the inner tube, as this is perforated, and in that the outer pipe is lifted under the fill so that the lower end of the pipe is kept close to the upper level of the fill. 6. Fremgangsmåte ifølge krav 1, 2, 3, 4 eller 5,karakterisert„ved at den flytende konstruksjon føres ut til oppbyggingsstedet med membranen sammenfoldet.6. Method according to claim 1, 2, 3, 4 or 5, characterized in that the floating construction is carried out to the construction site with the membrane folded.
NO751737A 1974-05-22 1975-05-15 PROCEDURE FOR BUILDING AN UNDERWATER CONSTRUCTION NO141445C (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
GB2281774A GB1460529A (en) 1974-05-22 1974-05-22 Underwater structure

Publications (3)

Publication Number Publication Date
NO751737L NO751737L (en) 1975-11-25
NO141445B true NO141445B (en) 1979-12-03
NO141445C NO141445C (en) 1980-03-12

Family

ID=10185530

Family Applications (1)

Application Number Title Priority Date Filing Date
NO751737A NO141445C (en) 1974-05-22 1975-05-15 PROCEDURE FOR BUILDING AN UNDERWATER CONSTRUCTION

Country Status (7)

Country Link
CA (1) CA1010667A (en)
DE (1) DE2522534C3 (en)
FR (1) FR2272229B1 (en)
GB (1) GB1460529A (en)
NL (1) NL7505974A (en)
NO (1) NO141445C (en)
SE (1) SE422092B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0060578A1 (en) * 1981-03-13 1982-09-22 Akzo N.V. Method of forming an elevation partially or entirely under water, an elevation formed by this method and a boundary means to be used for the formation of the elevation
GB8328404D0 (en) * 1983-10-24 1983-11-23 Dixon R K Concrete construction
CA1245468A (en) * 1984-03-15 1988-11-29 William E. Hodge Method and apparatus for constructing an underwater fill
DE3739045A1 (en) * 1986-11-27 1988-06-09 Hollandsche Betongroep Nv METHOD FOR PRODUCING AN ACCUMULATION OF GRAINY MATERIALS, IN PARTICULAR A DAM OR A DYE
DE4431081C1 (en) * 1994-09-01 1996-04-25 Awu Consult Ingenieurgesellsch Buoyant, anchored breakwater element
RU2239025C1 (en) * 2003-04-04 2004-10-27 Соломоник Илья Борисович Method of tunnel building under seabed
DE102014213760B4 (en) * 2014-07-15 2016-09-22 Sinn Power Gmbh Muringsteinschalungsform

Also Published As

Publication number Publication date
DE2522534B2 (en) 1980-05-08
NL7505974A (en) 1975-11-25
FR2272229B1 (en) 1980-07-04
SE422092B (en) 1982-02-15
CA1010667A (en) 1977-05-24
DE2522534A1 (en) 1975-12-04
NO141445C (en) 1980-03-12
NO751737L (en) 1975-11-25
FR2272229A1 (en) 1975-12-19
SE7505775L (en) 1975-11-24
AU8119475A (en) 1976-11-18
DE2522534C3 (en) 1981-01-15
GB1460529A (en) 1977-01-06

Similar Documents

Publication Publication Date Title
US2589146A (en) Submersible deepwater drilling apparatus
US3896628A (en) Marine structures
US4425055A (en) Two-section arctic drilling structure
US2940266A (en) Method of constructing an offshore well drilling island
US4063426A (en) Three column tower
NO871255L (en) PROCEDURE FOR THE DEVELOPMENT OF OIL AND / OR GAS FIELDS FOR THE SEA, AND THE FOUNDATION FOR A DRILL AND / OR PRODUCTION PLATFORM FOR THE SEA.
US3528254A (en) Offshore platform structure and construction method
US3380256A (en) Underwater drilling installation and method of construction
NO136650B (en)
NO136683B (en)
US2580911A (en) Foundation structure for derricks
NO141445B (en) PROCEDURES FOR CONSTRUCTING AN UNDERWATER CONSTRUCTION
US2678540A (en) Process for the production and sinking of caissons of any desired shape
US2865179A (en) Offshore drilling structure
US4069681A (en) Offshore structure for deltaic substrates
US2475888A (en) Pier for offshore drilling rigs
CN104762942B (en) Fixed platform soft soil foundation seabed, aquatic building ocean fixed installation construction method
US4009580A (en) Underwater structure
US3186180A (en) Offshore well drilling and oil storage platform
US3091937A (en) Underwater foundation structure and method therefor
US1811761A (en) Submarine oil well derrick
US2661600A (en) Underwater drilling derrick
US3961489A (en) Method for placing a floating structure on the sea bed
US3556210A (en) Deep sea well drilling structure
NO742938L (en)