US2940266A - Method of constructing an offshore well drilling island - Google Patents

Method of constructing an offshore well drilling island Download PDF

Info

Publication number
US2940266A
US2940266A US600906A US60090656A US2940266A US 2940266 A US2940266 A US 2940266A US 600906 A US600906 A US 600906A US 60090656 A US60090656 A US 60090656A US 2940266 A US2940266 A US 2940266A
Authority
US
United States
Prior art keywords
island
constructing
piling
drilling
well drilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US600906A
Inventor
Smith Verne
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHAMROCK DRILLING CO
Original Assignee
SHAMROCK DRILLING CO
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHAMROCK DRILLING CO filed Critical SHAMROCK DRILLING CO
Priority to US600906A priority Critical patent/US2940266A/en
Application granted granted Critical
Publication of US2940266A publication Critical patent/US2940266A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/02Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto
    • E02B17/027Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto steel structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0039Methods for placing the offshore structure

Definitions

  • This invention relates to a method and apparatus for the connection joint 13. Rubber pads 35 may be provided at the joint if desired.
  • Support structure 36 carried on the upper member 11 is provided with a circular track having conventional rails 37.
  • a carriage 38 is provided with wheels which roll on this track and with a bearing 39 which is positioned on the vertical axis of the island 10.
  • This invention finds particular usefulness in connection with a drilling and production island structure which is portable to the extent that it can be floated to the desired site, rested on the bottom and used as a supporting structure for drilling and producing oil Wells, the entire device being movable to float to a new location if desired.
  • Another object is to provide method and apparatus for constructing a support for a well drilling rig in a marine location and for producing oil or gas from wells drilled from such island. Another object is to provide method and apparatus for constructing a removable island of this type and wherein parts thereof may be separately floated to the drilling site. Another object is to provide a drilling island which is relatively inexpensive to manufacture and erect, which is inherently stable in resisting wind, wave and tide action and which may be used to drill a number of directional holes from the single location. advantages will appear hereinafter.
  • Figure 1 is a side elevation showing a preferred embodiment of my invention.
  • Figure 2 is a fragmentary top plan view thereof, certain parts being omitted for clarity of illustration.
  • Figures 3, 4, 5, 6 and 7 show steps in the method'of erection of the device.
  • Figure 8 is a sectional elevation showing a modification.
  • Figure 9 is a sectional plan view taken substantially on lines 9-9 as shown in Figure 8.
  • a drilling island generally designated 10 includes an upper member 11 and a bottom member 12 connected at the joint 13 by a plurality of removable fastener elements 14.
  • the bottom member 12 comprises concentric frusto conical walls 15 and 16 connected by partitions 17 forming buoyant chambers 18.
  • the lower ends 19 and 29 of the walls may be cylindrical and these cylindrical portions are joined by an annular bottom wall 21.
  • the upper ends of the walls 15 and- 16 likewise may be cylindrical as indicated at 2 2 and 23 and the connecting annular top wall 24 forms one side of the joint COD: nection 13. v a
  • a central vertical guide tube 25 is mounted within the lower member 12 and is connected to the wall '16 by-rneans of suitable beams..26.and 27 and by angle braces 28.. These .beamsand braces preferably extend radially with respect to the central tube 25.
  • the upper member 11 is preferably formed of concentric walls 30 and 31 defining an annular space 32 between them. This annular space is divided by partitions 33 to form buoyant chambers. At the lower ends of the walls 30 and 31 there is provided an annular floor 34 which is shaped to cooperate with the wall 24 to form Other related objects and drill rig assembly generally designated 40 is mounted on this carriage 38.
  • the drill rig assembly 40 includes a mast 41, drilling and hoisting machinery 42 and engines 43.
  • the carriage 38 may be moved to bring the mast 40 and drilling machinery into position for drilling a hole through any one of the vertical conductor pipes 44 provided in the upper member 11.
  • the vertical axes of these conductor pipes are spaced topass between the beams 26 and 27 and inclined braces 28 on the lower member 12.
  • the drill site 50 on the ocean floor may be levelled or smoothed, if desired, as shown in Figure 5.
  • a vertical cluster of piles 51 is then driven into the ocean fioor at the center of the Well site by conventional means suchas, for example, by pile driving apparatus mounted 'on a floating barge (not shown).
  • the lower member 12 is then floated to the drill site, the compartments 18 being filled with compressed air.
  • a vertical tubular guide or bar 52 is telescoped over the upper end of the pile cluster 51 after the tubular guide 52 has been inserted into the central tube 25 on the member 12.
  • Pull down cables 53 are attached to the member 12 and pass under pulleys 54 connected to the weight blocks 55 resting on the ocean floor.
  • Each of the cables is connected to one or more buoyant tanks 49 so that the tension applied to the cables by the buoyant tanks serves to apply downward force to the member 12.
  • Additional guy wires 56 are used to maintain the member 12 against lateral movement. The parts are then in the position shown in Figure 4.
  • buoyancy tanks 18 are then flooded to cause the member 12 to descend and rest on the ocean floor. The descent is accomplished with the tubular guide 52 and cluster of piles 51 serving to prevent any sub-.
  • the upper member then extends substantially above the waterlevel '58 so that the machinery on the decks 59 and 60 are positioned above the maximum height of the waves.
  • Thedrill rig assembly 40 maybe in position on the upper member when it is floated out to'sea and as soon as the membels 11 and 12 have been connected solidly together, *the drilling operations may commence.
  • the mud pits, mud pumps and associated equipment may be located on the deck 59.
  • the carriage 38 is moved on the rails 37 to a position to bring the drill string (not shown) into alignment with one of the conductor pipes 44 and the well is directionally drilled through the conductor pipe in the conventional manner. Additional wells may be directionally drilled at each of the other conductor pipes so thata large number of wells may be drilled from the single island.
  • the well may be completed and produced in conventional manners. Pumpingjacks (not shown) may be mounted on the upper deck Stitor each of the wells. If the island is to be used for production, it is desirable to fill the chambers 18 with concrete so that the island becomes a Y permanent installation.
  • the island may be'refloated and moved to a new site. I'his is accomplished'by removing the rocks and rip-rap 57am by pumping'out the sand within the inner wall16, The entire island may then be refloated as a unit after 'the' piles 51 and 56 have been cut by divers.
  • the island '10 also may be Iefloated andmoved to 'a new location in two'sections' 'In this case,'the remov level.
  • the joint 13 is omitted. In all other respects the construction and operation are the same as that previously described.
  • the member 10a isiloated to the drill site and installed on bottom using the same series ofsteps as described above in connection with the lower member 12. 7
  • a method of constructing a well drilling or production island in a marine location comprising the steps of: installingcentral vertical piling on the ocean floor terminating below the water level, floating a member into position over the piling so that a guide elementon the 'member' is aligned with the piling, placing a guide bar having a tubular portion through the guide element and over thetop' of the piling to form an extension thereof,
  • a method oiconstructinga well drilling or production island in a marine location comprising the steps of: installing vertical piling on ;the ocean floor terminating below the water level, floating a lower member into position over the piling so that a guide element on the member is aligned with the piling, placing a guide bar having a tubular portion through the guide element and over the top of the piling to form an extension thereof, lowering said lowermemberso that the guide element thereof telescopes over said guide bar anclpiling until the lower end of said member rests on the ocean floor, removing the guide bar, floating an I'upper member into posin'on above the lower membenrandflowering said upper member to rest on said lower member so that the upper portion-of said upper member extends above the water level.
  • a method of constructing awell drilling or produc' tion island in a marine. location comprising thesteps of:

Description

June 14, 1960 V. SMITH METHOD OF CONSTRUCTING AN OFFSHORE WELL DRILLING ISLAND Filed July 30, 1956 3 SheetsSheet 1 INVENTOR. VfzeA/f SM/T/V BY $0M? V. SMITH METHOD OF CONSTRUCTING AN OFFSHORE WELL DRILLING ISLAND Filed July 30, 1956 3 Sheets-Sheet 2 a 0. W M M M m W "H MW .1 -M 5w 0 m. Y B
June 14, 1960 v. SMITH 2,940,266
METHOD OF CONSTRUCTING AN OFFSHORE WELL DRILLING ISLAND Filed July 30, 1956 3 Sheets-Sheet 3 BY fa/r4 United States l atent O METHOD OF CONSTRUCTING AN OFFSHORE WELL DRILLING ISLAND Verne Smith, Corona Del Mar, Ca1if., assignor to Shamrock Drilling Co., Los Angeles, Calif.
Filed July 30, 1956, Ser. No. 600,906
5 Claims. (Cl. 61-465) This invention relates to a method and apparatus for the connection joint 13. Rubber pads 35 may be provided at the joint if desired.
Support structure 36 carried on the upper member 11 is provided with a circular track having conventional rails 37. A carriage 38 is provided with wheels which roll on this track and with a bearing 39 which is positioned on the vertical axis of the island 10. A
drilling and producing oil, gas or other wells in an ofi shore marine location. This invention finds particular usefulness in connection with a drilling and production island structure which is portable to the extent that it can be floated to the desired site, rested on the bottom and used as a supporting structure for drilling and producing oil Wells, the entire device being movable to float to a new location if desired. i i
Among the objects of the present invention are to provide method and apparatus for constructing a support for a well drilling rig in a marine location and for producing oil or gas from wells drilled from such island. Another object is to provide method and apparatus for constructing a removable island of this type and wherein parts thereof may be separately floated to the drilling site. Another object is to provide a drilling island which is relatively inexpensive to manufacture and erect, which is inherently stable in resisting wind, wave and tide action and which may be used to drill a number of directional holes from the single location. advantages will appear hereinafter.
In the drawings:
Figure 1 is a side elevation showing a preferred embodiment of my invention.
Figure 2 is a fragmentary top plan view thereof, certain parts being omitted for clarity of illustration.
Figures 3, 4, 5, 6 and 7 show steps in the method'of erection of the device.
Figure 8 is a sectional elevation showing a modification.
Figure 9 is a sectional plan view taken substantially on lines 9-9 as shown in Figure 8.
Referring to Figures 1-7 of the drawings, a drilling island generally designated 10 includes an upper member 11 and a bottom member 12 connected at the joint 13 by a plurality of removable fastener elements 14. The bottom member 12 comprises concentric frusto conical walls 15 and 16 connected by partitions 17 forming buoyant chambers 18. The lower ends 19 and 29 of the walls may be cylindrical and these cylindrical portions are joined by an annular bottom wall 21. The upper ends of the walls 15 and- 16 likewise may be cylindrical as indicated at 2 2 and 23 and the connecting annular top wall 24 forms one side of the joint COD: nection 13. v a
A central vertical guide tube 25 is mounted within the lower member 12 and is connected to the wall '16 by-rneans of suitable beams..26.and 27 and by angle braces 28.. These .beamsand braces preferably extend radially with respect to the central tube 25.
The upper member 11 is preferably formed of concentric walls 30 and 31 defining an annular space 32 between them. This annular space is divided by partitions 33 to form buoyant chambers. At the lower ends of the walls 30 and 31 there is provided an annular floor 34 which is shaped to cooperate with the wall 24 to form Other related objects and drill rig assembly generally designated 40 is mounted on this carriage 38.
The drill rig assembly 40 includes a mast 41, drilling and hoisting machinery 42 and engines 43. The carriage 38 may be moved to bring the mast 40 and drilling machinery into position for drilling a hole through any one of the vertical conductor pipes 44 provided in the upper member 11. The vertical axes of these conductor pipes are spaced topass between the beams 26 and 27 and inclined braces 28 on the lower member 12.
In constructing the drilling island in accordance with my method, the drill site 50 on the ocean floor may be levelled or smoothed, if desired, as shown in Figure 5. A vertical cluster of piles 51 is then driven into the ocean fioor at the center of the Well site by conventional means suchas, for example, by pile driving apparatus mounted 'on a floating barge (not shown). The lower member 12 is then floated to the drill site, the compartments 18 being filled with compressed air. A vertical tubular guide or bar 52 is telescoped over the upper end of the pile cluster 51 after the tubular guide 52 has been inserted into the central tube 25 on the member 12.
Pull down cables 53 are attached to the member 12 and pass under pulleys 54 connected to the weight blocks 55 resting on the ocean floor. Each of the cables is connected to one or more buoyant tanks 49 so that the tension applied to the cables by the buoyant tanks serves to apply downward force to the member 12. Additional guy wires 56 are used to maintain the member 12 against lateral movement. The parts are then in the position shown in Figure 4.
The buoyancy tanks 18 are then flooded to cause the member 12 to descend and rest on the ocean floor. The descent is accomplished with the tubular guide 52 and cluster of piles 51 serving to prevent any sub-.
stantial tilting of the lower member 12 as it descends toward the ocean floor. The member comes torest with the annular floor surface 21 resting on the ocean floor...
The device is then in the position shown inFigure 5;
Sand or other material heavier than sea water is then.
pumped into the interior of the lower member 12 to fill the entire space within the inner Wall 16. Piles 48.'
are then driven through vertical openings 57 provided around the periphery of the member 12. The cables 53 and 56 are then removed. The device is then in the. position shown in Figure 6. Rock and rip-rap 57- maythenv be placed around the outer periphery of the lowerv end of the member 12 as shown in Figure 7. The lower member 12 is then firmly anchored inplace-with its upper end substantially below the water line 58. -I't will be understood that although I have referred to the .f body of water as the ocean, it is intended that the device. may be usedin any body of water and not necessarily the open sea.
It will be observed that'the rocks and riprap lie against the inclined outer wall 15 and thereby et fectivelymember 12 and the two members are connected together by the fastener elements 14 to function as a single integral unit. The upper member then extends substantially above the waterlevel '58 so that the machinery on the decks 59 and 60 are positioned above the maximum height of the waves. Thedrill rig assembly 40 maybe in position on the upper member when it is floated out to'sea and as soon as the membels 11 and 12 have been connected solidly together, *the drilling operations may commence. The mud pits, mud pumps and associated equipment may be located on the deck 59. The carriage 38 is moved on the rails 37 to a position to bring the drill string (not shown) into alignment with one of the conductor pipes 44 and the well is directionally drilled through the conductor pipe in the conventional manner. Additional wells may be directionally drilled at each of the other conductor pipes so thata large number of wells may be drilled from the single island. The well: may be completed and produced in conventional manners. Pumpingjacks (not shown) may be mounted on the upper deck Stitor each of the wells. If the island is to be used for production, it is desirable to fill the chambers 18 with concrete so that the island becomes a Y permanent installation.
If oil is not found in commercial quantities, the island 'may be'refloated and moved to a new site. I'his is accomplished'by removing the rocks and rip-rap 57am by pumping'out the sand within the inner wall16, The entire island may then be refloated as a unit after 'the' piles 51 and 56 have been cut by divers. V
The island '10 also may be Iefloated andmoved to 'a new location in two'sections' 'In this case,'the remov level. The joint 13 is omitted. In all other respects the construction and operation are the same as that previously described. The member 10a isiloated to the drill site and installed on bottom using the same series ofsteps as described above in connection with the lower member 12. 7
Having fully described my invention, it is to be understood that I do not wish to be limited to the details herein set forth, but my invention is of the full scope of the appended claims.
Iclaim:
l. A method of constructing a well drilling or production island in a marine location comprising the steps of: installingcentral vertical piling on the ocean floor terminating below the water level, floating a member into position over the piling so that a guide elementon the 'member' is aligned with the piling, placing a guide bar having a tubular portion through the guide element and over thetop' of the piling to form an extension thereof,
and loweringsaid member so that the guide element thereof telescopes over said guide bar and piling until the lower end, of said member rests on the ocean floor.
a 2 'A inethod of constructing a well drillingor production island in a marine location comprising the steps of;
I installing central vertical piling on the ocean floor terminating below the water level, floating a member into position over the piling so that-a single central guide element on the member is aligned with the piling, extending a guide bar having a tubular portion through the guide element and over the top of the piling to form an extension thereof, and lowering said member so that the guide element thereof telescopes over said guide bar and piling until the lower' end of said me'mber rests on the ocean floor. I H
3. A method oiconstructinga well drilling or production island in a marine location comprising the steps of: installing vertical piling on ;the ocean floor terminating below the water level, floating a lower member into position over the piling so that a guide element on the member is aligned with the piling, placing a guide bar having a tubular portion through the guide element and over the top of the piling to form an extension thereof, lowering said lowermemberso that the guide element thereof telescopes over said guide bar anclpiling until the lower end of said member rests on the ocean floor, removing the guide bar, floating an I'upper member into posin'on above the lower membenrandflowering said upper member to rest on said lower member so that the upper portion-of said upper member extends above the water level.
" 4; A method'of constructing a well drilling or production island in a marine location" comprising the steps of:
installing centralverticalpiling on the ocean floor terminating below'the water level, .floating a-lower member an extension .thereofl lowering said lower member so that the guide element thereof telescopes over said guide bar and piling 'until the lower end of. said member rests on the ocean floor, removing the guide bar, floating an upper member into position above the lower member,
and lowering said upper member to rest on said lower member so that the upper portion of said upper member extends above the water level.
'5. A method of constructing awell drilling or produc' tion island in a marine. location comprising thesteps of:
' installing central verticalpiling on the ocean floor terminating below the water level, floating a memberinto position over the piling so that aguide element on the member is aligned with the piling, extending aguide bar having a tubular portion through the guide element and over the top of the piling to form an extension thereof, lowering said member so that the guide element thereof telescopes over the guidebar and piling until the lower end of said member rests on the ocean floor, filling the interior .of the member with material heavier than water, and driving piles into the ocean floor at intervals around the periphery of the member.
References Cited in the file of thiszpatent UNITED STATES PATENTS.
US600906A 1956-07-30 1956-07-30 Method of constructing an offshore well drilling island Expired - Lifetime US2940266A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US600906A US2940266A (en) 1956-07-30 1956-07-30 Method of constructing an offshore well drilling island

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US600906A US2940266A (en) 1956-07-30 1956-07-30 Method of constructing an offshore well drilling island

Publications (1)

Publication Number Publication Date
US2940266A true US2940266A (en) 1960-06-14

Family

ID=24405545

Family Applications (1)

Application Number Title Priority Date Filing Date
US600906A Expired - Lifetime US2940266A (en) 1956-07-30 1956-07-30 Method of constructing an offshore well drilling island

Country Status (1)

Country Link
US (1) US2940266A (en)

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3117423A (en) * 1959-02-09 1964-01-14 Gasaccumulator Svenska Ab Method for the production of underwater foundations
US3165898A (en) * 1962-06-11 1965-01-19 Continental Oil Co Off-shore oil drilling apparatus
US3315473A (en) * 1965-08-27 1967-04-25 Brown & Root Offshore platform
US3383869A (en) * 1965-01-18 1968-05-21 Canadian Patents Dev Marine piers
US3412564A (en) * 1967-02-21 1968-11-26 Pike Corp Of America Sub-sea working and drilling apparatus
US3429133A (en) * 1967-04-19 1969-02-25 Brown & Root Offshore tower
US3453830A (en) * 1968-03-13 1969-07-08 Mobil Oil Corp Method and apparatus for alleviating scouring about legs of a marine structure
US3474629A (en) * 1967-12-08 1969-10-28 Shell Oil Co Rotatable drilling platform
US3528254A (en) * 1968-12-03 1970-09-15 Global Marine Inc Offshore platform structure and construction method
US3529427A (en) * 1968-11-05 1970-09-22 Delta Diving Ltd Device for preventing or reducing scours at the lower ends of members supporting marine structures
US3624702A (en) * 1969-10-20 1971-11-30 Homayoun J Meheen Offshore platform support
US3675430A (en) * 1970-02-05 1972-07-11 Atlantic Richfield Co Arctic construction and drilling
US3698198A (en) * 1971-02-12 1972-10-17 Warren Petroleum Corp Deep-water drilling, production and storage system
US3738114A (en) * 1971-11-01 1973-06-12 G Bishop Method and apparatus for forming ice island for drilling or the like
US3824943A (en) * 1971-03-16 1974-07-23 Mo Och Domsjoe Ab Drilling platform
US3824795A (en) * 1971-03-16 1974-07-23 Mo Och Domsjoe Ab Platform structure
US3846991A (en) * 1971-07-16 1974-11-12 Orb Inc Pile driving method and apparatus
US3981154A (en) * 1969-11-25 1976-09-21 Arcadia Refining Company System for recovering petroleum fluids from underwater fissures
US4242011A (en) * 1978-04-03 1980-12-30 Brown & Root, Inc. Method and apparatus for forming integrated deck sub-structure assembly including arch-vessel passage means
US4325656A (en) * 1979-10-15 1982-04-20 Bishop Gilbert H Apparatus and method for forming off-shore ice island structure
US4360291A (en) * 1980-01-07 1982-11-23 Cranberg Alexis M Subsea foundation
DE3137967A1 (en) * 1981-09-24 1983-04-14 Hochtief Ag Vorm. Gebr. Helfmann, 4300 Essen Method of founding a drilling and production platform of a drilling rig in a stretch of water
US4504172A (en) * 1983-07-11 1985-03-12 Mobil Oil Corporation Caisson shield for arctic offshore production platform
US5049004A (en) * 1989-01-20 1991-09-17 Masateru Niimura Underwater building and constructing method thereof
DE102007043268A1 (en) * 2007-09-11 2009-03-12 Jähnig GmbH Felssicherung und Zaunbau Metal skeleton for the construction of submarine foundations

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US360273A (en) * 1887-03-29 Composite pier for bridges
US1489428A (en) * 1921-01-29 1924-04-08 John F Cushing Breakwater
US2317016A (en) * 1939-10-20 1943-04-20 Herschel H Allen Bridge foundation and method of making same
US2472869A (en) * 1947-02-24 1949-06-14 Richfield Oil Corp Island for well drilling
US2574140A (en) * 1947-07-18 1951-11-06 Raymond Concrete Pile Co Marine oil well derrick foundation
US2579703A (en) * 1949-10-03 1951-12-25 Ingalls Shipbuilding Corp Submersible tank for supporting offshore structures
US2628818A (en) * 1949-05-16 1953-02-17 Phillips Petroleum Co Well drilling rig
US2736172A (en) * 1956-02-28 mcchesney
US2771747A (en) * 1950-07-19 1956-11-27 Bethlehem Steel Corp Offshore drilling barge

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US360273A (en) * 1887-03-29 Composite pier for bridges
US2736172A (en) * 1956-02-28 mcchesney
US1489428A (en) * 1921-01-29 1924-04-08 John F Cushing Breakwater
US2317016A (en) * 1939-10-20 1943-04-20 Herschel H Allen Bridge foundation and method of making same
US2472869A (en) * 1947-02-24 1949-06-14 Richfield Oil Corp Island for well drilling
US2574140A (en) * 1947-07-18 1951-11-06 Raymond Concrete Pile Co Marine oil well derrick foundation
US2628818A (en) * 1949-05-16 1953-02-17 Phillips Petroleum Co Well drilling rig
US2579703A (en) * 1949-10-03 1951-12-25 Ingalls Shipbuilding Corp Submersible tank for supporting offshore structures
US2771747A (en) * 1950-07-19 1956-11-27 Bethlehem Steel Corp Offshore drilling barge

Cited By (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3117423A (en) * 1959-02-09 1964-01-14 Gasaccumulator Svenska Ab Method for the production of underwater foundations
US3165898A (en) * 1962-06-11 1965-01-19 Continental Oil Co Off-shore oil drilling apparatus
US3383869A (en) * 1965-01-18 1968-05-21 Canadian Patents Dev Marine piers
US3315473A (en) * 1965-08-27 1967-04-25 Brown & Root Offshore platform
US3412564A (en) * 1967-02-21 1968-11-26 Pike Corp Of America Sub-sea working and drilling apparatus
US3429133A (en) * 1967-04-19 1969-02-25 Brown & Root Offshore tower
US3474629A (en) * 1967-12-08 1969-10-28 Shell Oil Co Rotatable drilling platform
US3453830A (en) * 1968-03-13 1969-07-08 Mobil Oil Corp Method and apparatus for alleviating scouring about legs of a marine structure
US3529427A (en) * 1968-11-05 1970-09-22 Delta Diving Ltd Device for preventing or reducing scours at the lower ends of members supporting marine structures
US3528254A (en) * 1968-12-03 1970-09-15 Global Marine Inc Offshore platform structure and construction method
US3624702A (en) * 1969-10-20 1971-11-30 Homayoun J Meheen Offshore platform support
US3981154A (en) * 1969-11-25 1976-09-21 Arcadia Refining Company System for recovering petroleum fluids from underwater fissures
US3675430A (en) * 1970-02-05 1972-07-11 Atlantic Richfield Co Arctic construction and drilling
US3698198A (en) * 1971-02-12 1972-10-17 Warren Petroleum Corp Deep-water drilling, production and storage system
US3824943A (en) * 1971-03-16 1974-07-23 Mo Och Domsjoe Ab Drilling platform
US3824795A (en) * 1971-03-16 1974-07-23 Mo Och Domsjoe Ab Platform structure
US3846991A (en) * 1971-07-16 1974-11-12 Orb Inc Pile driving method and apparatus
US3738114A (en) * 1971-11-01 1973-06-12 G Bishop Method and apparatus for forming ice island for drilling or the like
US4252468A (en) * 1978-04-03 1981-02-24 Brown & Root, Inc. Method and apparatus for installing deck structures entailing composite shock absorbing and alignment aspects
US4252469A (en) * 1978-04-03 1981-02-24 Brown & Root, Inc. Method and apparatus for installing integrated deck structure and rapidly separating same from supporting barge means
US4242011A (en) * 1978-04-03 1980-12-30 Brown & Root, Inc. Method and apparatus for forming integrated deck sub-structure assembly including arch-vessel passage means
US4325656A (en) * 1979-10-15 1982-04-20 Bishop Gilbert H Apparatus and method for forming off-shore ice island structure
US4360291A (en) * 1980-01-07 1982-11-23 Cranberg Alexis M Subsea foundation
DE3137967A1 (en) * 1981-09-24 1983-04-14 Hochtief Ag Vorm. Gebr. Helfmann, 4300 Essen Method of founding a drilling and production platform of a drilling rig in a stretch of water
US4504172A (en) * 1983-07-11 1985-03-12 Mobil Oil Corporation Caisson shield for arctic offshore production platform
US5049004A (en) * 1989-01-20 1991-09-17 Masateru Niimura Underwater building and constructing method thereof
DE102007043268A1 (en) * 2007-09-11 2009-03-12 Jähnig GmbH Felssicherung und Zaunbau Metal skeleton for the construction of submarine foundations

Similar Documents

Publication Publication Date Title
US2940266A (en) Method of constructing an offshore well drilling island
US2589146A (en) Submersible deepwater drilling apparatus
US3896628A (en) Marine structures
US2691272A (en) Submersible oil well drilling rig
US3209544A (en) Marine structure
US2777669A (en) Marine well drilling apparatus
JP6912490B2 (en) Submarine support units and methods for providing shallow water drilling terminals
US3191388A (en) Slender column support for offshore platforms
US2429952A (en) Underwater foundation and method of erecting the same
US3736756A (en) Method and apparatus for assembling an offshore structure
US4063426A (en) Three column tower
US2775095A (en) Method of erecting structures in water
US3852969A (en) Offshore platform structures
US3528254A (en) Offshore platform structure and construction method
US3094847A (en) Offshore platform structure
US4266887A (en) Self-elevating fixed platform
US2946566A (en) Subaqueous drilling apparatus
US2515540A (en) Marine drilling method and means
US3380256A (en) Underwater drilling installation and method of construction
US4170266A (en) Apparatus and method for offshore drilling at great depths
US3624702A (en) Offshore platform support
US2580911A (en) Foundation structure for derricks
US2865179A (en) Offshore drilling structure
US3665721A (en) Submerged well platform
US4069681A (en) Offshore structure for deltaic substrates