NL1036626C2 - UNDERGROUND SPACE IN CITY WITH CLOSED STREETS. - Google Patents

UNDERGROUND SPACE IN CITY WITH CLOSED STREETS. Download PDF

Info

Publication number
NL1036626C2
NL1036626C2 NL1036626A NL1036626A NL1036626C2 NL 1036626 C2 NL1036626 C2 NL 1036626C2 NL 1036626 A NL1036626 A NL 1036626A NL 1036626 A NL1036626 A NL 1036626A NL 1036626 C2 NL1036626 C2 NL 1036626C2
Authority
NL
Netherlands
Prior art keywords
spaces
underground
concrete
city
water
Prior art date
Application number
NL1036626A
Other languages
Dutch (nl)
Inventor
Bastian Karel Jacques Obladen
Original Assignee
Strukton Groep N V
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Strukton Groep N V filed Critical Strukton Groep N V
Priority to NL1036626A priority Critical patent/NL1036626C2/en
Application granted granted Critical
Publication of NL1036626C2 publication Critical patent/NL1036626C2/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H6/00Buildings for parking cars, rolling-stock, aircraft, vessels or like vehicles, e.g. garages
    • E04H6/08Garages for many vehicles
    • E04H6/10Garages for many vehicles without mechanical means for shifting or lifting vehicles, e.g. with helically-arranged fixed ramps, with movable ramps

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

Ondergrondse ruimte in stad met nauwe stratenUnderground space in city with narrow streets

In veel dichtbevolkte steden met nauwe straten, zoals Amsterdam, is het autoverkeer een toenemend probleem 5 geworden. Dergelijke steden zijn veelal niet ingericht of ontworpen om de automobielen ruime toegang tot het centrum te verlenen, terwijl het in veel gevallen onmogelijk is toe-en afritten te maken voor ondergrondse parkeerruimte. De straten worden ontsierd door grote hoeveelheden geparkeerde 10 auto's, welke ruimte wordt onttrokken aan wandel- en zitruimte voor het publiek. Het gebrek aan (parkeer)ruimte beperkt het zakelijke gebruik van de gebouwen, alsmede het privégebruik van woningen en appartementen daar voor meerdere bewoners te weinig toegangsruimte voor hun 15 automobiel beschikbaar is.In many densely populated cities with narrow streets, such as Amsterdam, car traffic has become an increasing problem 5. Such cities are often not arranged or designed to give the cars ample access to the center, while in many cases it is impossible to make entrances and exits for underground parking space. The streets are marred by large quantities of 10 cars parked, which space is withdrawn from walking and sitting areas for the public. The lack of (parking) space limits the business use of the buildings, as well as the private use of homes and apartments, as there is not enough access space for their residents for their cars.

In het verleden zijn reeds voorstellen gedaan de ondergrondse ruimte te gebruiken voor parkeerdoeleinden. De kosten voor het maken van toe- en afritten zijn echter prohibitief, waardoor dergelijke plannen op de tekentafel 20 zijn blijven steken.In the past, proposals have already been made to use the underground space for parking purposes. However, the costs for making entrances and exits are prohibitive, as a result of which such plans have remained on the drawing board 20.

De onderhavige uitvinding verschaft een werkwijze voor het in slappe of drassige bodem aanbrengen van ondergrondse parkeerplaatsen en/of een rijbaan en/of een betonnen vloer daarvoor en/of andere doeleinden, waarbij 25 zonodig oppervlaktewater wordt weggepompt, diepwanden in de drassige bodem tot op een zandlaag worden geplaatst, een betonnen bovenwand tussen de diepwanden wordt aangebracht, en vervolgens de drassige bodem onder de bovenste betonnen plaat wordt verwijderd, bijvoorbeeld wordt weggegraven en/of 30 weggepompt, waarbij de ondergrondse parkeerplaatsen en/of de rijbaan en/of de betonnen vloer in een bestaande gracht wordt aangebracht nadat deze met zand is gedempt.The present invention provides a method for providing underground parking spaces and / or a roadway and / or a concrete floor for this and / or other purposes in slack or marshy soil, wherein surface water is pumped away if necessary, deep walls in the marshy soil up to a sand layer, a concrete top wall is placed between the deep walls, and then the soggy bottom under the upper concrete plate is removed, for example, being excavated and / or pumped away, whereby the underground parking places and / or the roadway and / or the concrete floor is installed in an existing canal after it has been filled in with sand.

22

Berekeningen hebben aangetoond dat door het aanbrengen van één of meer betonnen vloeren in de drassige bodem, bijvoorbeeld onder een gracht, de kosten per parkeerplaats, en voor andere oppervlakten grosso modo 5 beperkt blijven tot de huidige kosten voor het aanleggen van parkeerplaatsen. Dit is onder meer te danken aan het systeem dat de toeritten reeds aan het begin van het centrum van de stad worden aangelegd, waardoor een ondergronds net van parkeerplaatsen en ruimtes ontstaat.Calculations have shown that by installing one or more concrete floors in the marshy soil, for example under a canal, the costs per parking space, and for other surfaces, are roughly limited to the current costs for constructing parking spaces. This is partly due to the system that the tours are already laid at the beginning of the center of the city, creating an underground network of parking spaces and spaces.

10 Bij voorkeur bedraagt het aantal betonnen vloeren twee, bij meer voorkeur meer dan vier en nog meer bij voorkeur zes, opdat de kosten verder beperkt blijven. In de onderste ruimte kunnen dan bovendien de diverse utiliteitvoorzieningen, zoals gas, water, licht, 15 (glasvezel)kabels voor telecommunicatie e.d. worden gelegd.The number of concrete floors is preferably two, more preferably more than four and even more preferably six, so that the costs are further limited. In addition, the various utility facilities, such as gas, water, light, (fiber optic) cables for telecommunications and the like can then be laid in the lower space.

Bij voorkeur zijn de ondergrondse ruimtes in verticaal scheidbare compartimenten opgedeeld die in brandsituaties kunnen worden afgesloten door middel van brandwerende deuren opdat het risico daarvan beperkt blijft 20 tot een dergelijk compartiment.The underground spaces are preferably divided into vertically separable compartments which in fire situations can be closed by means of fire doors so that the risk thereof is limited to such a compartment.

In een verdere voorkeursuitvoeringsvorm is sprake van gebruik van aardwarmte voor het verwarmen en/of koelen van de luchtstromen in ten minste de bovenste ruimtes teneinde de klimaatbeheersing zonder gebruik te maken van 25 fossiele brandstoffen te laten plaatsvinden.In a further preferred embodiment, use is made of geothermal heat for heating and / or cooling the air streams in at least the upper spaces in order to allow climate control to take place without using fossil fuels.

In een verdere voorkeursuitvoeringsvorm wordt na het aanbrengen van ten minste twee vloeren, water in de gracht gelaten en worden werkzaamheden voor het aanbrengen van dieperliggende lagen hieronder, dat wil zeggen in de 30 ruimte tussen de reeds aangebrachte vloeren, voortgezet. Het verdere verloop van de werkzaamheden wordt hiermee aan het zicht van de bewoners onttrokken, waardoor overlast voor de omgeving tot een minimum wordt beperkt.In a further preferred embodiment, after the installation of at least two floors, water is left in the canal and work for the installation of deeper layers is continued below, that is to say in the space between the floors already applied. The further course of the work is thus hidden from the view of the residents, so that nuisance for the environment is kept to a minimum.

33

Verdere voordelen, kenmerken en details van de onderhavige uitvinding zullen worden verduidelijkt aan de hand van de navolgende beschrijving van de voorkeursuitvoeringsvorm daarvan, met verwijzing naar de 5 bijgevoegde tekening, waarin tonen:Further advantages, features and details of the present invention will be elucidated on the basis of the following description of the preferred embodiment thereof, with reference to the accompanying drawing, in which:

Figuur 1 een gedeeltelijk schematisch aanzicht van een ondergrondse ruimte volgens de onderhavige uitvinding;Figure 1 is a partial schematic view of an underground space according to the present invention;

Figuur 2-6 achtereenvolgende werkwijze stappen voor het realiseren van de in Figuur 1 getoonde ruimte; en 10 Figuur 7 een aanzicht in doorsnede van een klimaatbeheersingssysteem voor de voorkeursuitvoeringsvorm zoals die getoond is in Figuur 1.Figure 2-6 consecutive method steps for realizing the space shown in Figure 1; and Figure 7 shows a cross-sectional view of a climate control system for the preferred embodiment as shown in Figure 1.

Onder een gracht C, waarbij aan de oevers aan weerszijden pakeerplaatsen O zijn gesitueerd wordt onder de 15 bodem 10 van de gracht C een aantal vloeren 11, 12, 13, 14, 15, 16 aangebracht met een overspanning van 28 tot 30 meter tussen zogenoemde diepwanden 20, 21 die waterdicht zijn en die zich benedenwaarts kunnen uitstrekken tot aan een diepte van 60 meter in de bodem, bij voorkeur tot op een zandlaag 20 onder de slappe, klei-achtige bodem.Underneath a moat C, on which banks on either side parking places O are situated, below the bottom 10 of the moat C a number of floors 11, 12, 13, 14, 15, 16 are provided with a span of 28 to 30 meters between so-called deep walls 20, 21 that are watertight and that can extend downwards to a depth of 60 meters in the bottom, preferably up to a layer of sand 20 below the limp, clay-like bottom.

Op niet-getoonde wijze kunnen de ondergrondse ruimtes tussen de bodem 10 van de gracht C en ten minste een aantal van de ruimtes tussen de vloeren verticaal worden gescheiden met afsluitbare branddeuren.In a manner not shown, the underground spaces between the bottom 10 of the canal C and at least a number of the spaces between the floors can be vertically separated with lockable fire doors.

25 In een stad als Amsterdam kan een net van dergelijke vloeren onder de grachten worden aangelegd, zodat de toegang bijvoorbeeld vanaf de ondergrond van de Amstel tot in de meeste locaties in Amsterdam bereikbaar is, alsmede vanuit de Weesperzijde, de Hobbemakade, de 30 Sloterkade en de Haarlemmerweg. Er behoeven derhalve in de oude binnenstad bij de grachten geen toe- en afvoerwegen te worden gemaakt.25 In a city such as Amsterdam, a network of such floors can be installed under the canals, so that access can be achieved from, for example, the subsurface of the Amstel to most locations in Amsterdam, as well as from Weesperzijde, Hobbemakade, Sloterkade 30 and the Haarlemmerweg. Therefore, there is no need to make supply and discharge roads near the canals in the old city center.

44

De voertuigen kunnen zijn voorzien van voertuigidentificatie, opdat slechts bepaalde geïdentificeerde voertuigen toegang hebben tot de ondergrondse ruimte. Op de zijwanden van de ruimte kunnen de 5 gevels van de grachten worden geprojecteerd, zodat de bewoner of zakelijke gebruiker gemakkelijk kan zien waar hij zich bevindt en waar hij zijn automobiel kan parkeren. Er kan voldoende ruimte worden gecreëerd voor ondergrondse winkels, squashhallen, fitnessruimtes e.d. teneinde de 10 beperkte ruimte in een dichtbevolkte stad als Amsterdam optimaal te gebruiken.The vehicles can be provided with vehicle identification, so that only certain identified vehicles have access to the underground space. The facades of the canals can be projected onto the side walls of the room, so that the resident or business user can easily see where he is and where he can park his automobile. Sufficient space can be created for underground shops, squash halls, fitness rooms and the like in order to optimally use the limited space in a densely populated city such as Amsterdam.

Bij de werkwijze volgens de onderhavige uitvinding wordt allereerst een woonboot W verwijderd, waarna een gracht C met zand wordt gedempt. Na het verwijderen van 15 afval, zoals een oude fiets B, worden de diepwanden 20, 21 tot de genoemde diepte of minder de grond in gegraven of anderszins daarin aangebracht (Figuur 3). Daarna wordt een betonnen bodem 10 tussen die diepwanden 20, 21 aangebracht. Tussen damwanden 42, 43 kan dan een graafmachine E de veen-20 of klei-achtige onderlaag S tot op de gewenste diepte afgraven. Het materiaal uit onderlaag S is bij voorkeur per pijpleiding af te voeren, bij voorkeur per een in de grachten drijvende pijpleiding. In sommige gevallen behoeft er wellicht nauwelijks graafwerk te worden verricht indien 25 voldoende water wordt toegevoegd.In the method according to the present invention, first a houseboat W is removed, after which a canal C with sand is filled in. After removing waste, such as an old bicycle B, the deep walls 20, 21 are dug to the said depth or less into the ground or otherwise installed therein (Figure 3). A concrete bottom 10 is then provided between said deep walls 20, 21. Between sheet pile walls 42, 43, an excavator E can then dig the peat-20 or clay-like bottom layer S to the desired depth. The material from bottom layer S can preferably be discharged per pipeline, preferably per a pipeline floating in the canals. In some cases, digging may hardly be necessary if sufficient water is added.

Het moge duidelijk zijn dat het water in de gracht C boven de betonnen vloer 41 veel schoner blijft dan in de huidige omstandigheden, daar de gracht C is voorzien van een betonnen bodem, waardoor geen verontreinigingen vanuit de 30 bodem het water kunnen vervuilen.It will be clear that the water in the moat C above the concrete floor 41 remains much cleaner than in the current circumstances, since the moat C is provided with a concrete bottom, so that no contamination from the bottom can contaminate the water.

Nadat een volgende betonnen vloer 11 is aangebracht, kan met de graafmachine E een volgende onderlaag worden weggegraven (Figuur 5), waarna een verdere 5 ondervloer 12 daaronder kan worden aangebracht. Het moge duidelijk zijn dat na het aanbrengen van de eerste betonnen vloer 10 alle werkzaamheden kunnen worden uitgevoerd zonder dat de stad en haar stedelingen daar overlast van 5 ondervinden.After a further concrete floor 11 has been applied, a further underlayer can be dug away with the excavator E (Figure 5), whereafter a further underfloor 12 can be provided underneath. It will be clear that after the installation of the first concrete floor 10, all work can be carried out without the city and its city dwellers being inconvenienced by this.

Zoals getoond in Figuur 7 kan in de zomer overtollige warmte H in bodemschachten 71, 72 naar beneden worden gepompt, terwijl bijvoorbeeld in de winter via warmtewisselaar 72, 73 en een warmtepomp 74 verwarmde lucht 10 via warmtewisselaars 75, 76 in ten minste de bodemcompartimenten kan worden gepompt.As shown in Figure 7, excess heat H can be pumped down into soil shafts 71, 72 in the summer, while, for example, heated air 10 can be heated via heat exchangers 72, 73 and a heat pump 74 through heat exchangers 75, 76 into at least the bottom compartments. be pumped.

Op bijvoorbeeld 60 m diepte is de aardwarmte vrij constant, en in de ordegrootte van 10°C-12°C. In de zomer, bij een buitentemperatuur van bijvoorbeeld 25°C, kan de 15 aardtemperatuur van 10°C-12°C worden gebruikt voor koeling. In de winter, wanneer de buitentemperatuur wel kan zakken tot bijvoorbeeld -10°C, is de aardtemperatuur van 10°C-12°C daarentegen juist toepasbaar voor verwarming.For example, at a depth of 60 m, the geothermal heat is fairly constant, and in the order of magnitude of 10 ° C-12 ° C. In the summer, at an outside temperature of, for example, 25 ° C, the earth temperature of 10 ° C-12 ° C can be used for cooling. On the other hand, in winter, when the outside temperature can drop to -10 ° C, the earth temperature of 10 ° C-12 ° C can be used for heating.

Opslag van koude en/of warmte reduceert de 20 behoefte aan alternatieve energiebronnen voor het koelen, respectievelijk verwarmen van de onder de grond aangebrachte ruimtes. Desgewenst kunnen wel aanvullende installaties zijn voorzien voor het tot een gewenste temperatuur bijkoelen en/of bijverwarmen van de ondergrondse ruimtes.Storage of cold and / or heat reduces the need for alternative energy sources for cooling and / or heating the spaces installed underground. If desired, additional installations can be provided for cooling and / or reheating the underground spaces to a desired temperature.

25 De onderhavige uitvinding is niet beperkt tot de hierboven beschreven voorkeursuitvoeringsvorm. De beschreven rechten worden bepaald door de navolgende conclusies in de strekking waarvan vele modificaties denkbaar zijn.The present invention is not limited to the preferred embodiment described above. The rights described are defined by the following claims in the scope of which many modifications are conceivable.

Claims (7)

1. Werkwijze voor het in slappe bodem aanbrengen van ondergrondse parkeerplaatsen en/of een 5 rijbaan en/of een betonnen vloer daarvoor en/of andere doeleinden, waarbij zonodig oppervlaktewater wordt weggepompt, diepwanden in de drassige bodem tot op een zandlaag worden geplaatst, een betonnen bovenwand tussen de diepwanden wordt aangebracht, en vervolgens de drassige 10 bodem onder de bovenste betonnen plaat wordt verwijderd, bijvoorbeeld wordt weggegraven en/of weggepompt, waarbij de ondergrondse parkeerplaatsen en/of de rijbaan en/of de betonnen vloer in een bestaande gracht wordt aangebracht nadat deze met zand is gedempt. 151. Method for providing underground parking places and / or a roadway and / or a concrete floor for this and / or other purposes in slack soil, whereby surface water is pumped away if necessary, deep walls are placed in the marshy soil up to a sand layer, concrete top wall is arranged between the deep walls, and then the marshy bottom under the upper concrete slab is removed, for example, is excavated and / or pumped away, whereby the underground parking places and / or the roadway and / or the concrete floor are placed in an existing canal applied after it has been filled in with sand. 15 2. Werkwijze volgens conclusie 1, waarbij één of meer toeritten aan het begin van het centrum van een stad worden aangelegd, waardoor een ondergronds net van parkeerplaatsen en ruimtes ontstaat. 20Method as claimed in claim 1, wherein one or more rounds are laid at the beginning of the center of a city, whereby an underground network of parking spaces and spaces is created. 20 3. Werkwijze volgens conclusie 1, waarbij bij voorkeur twee, meer bij voorkeur meer dan vier, en nog meer bij voorkeur zes betonnen vloeren worden aangebracht.A method according to claim 1, wherein preferably two, more preferably more than four, and even more preferably six concrete floors are applied. 4. Werkwijze volgens één van de voorgaande conclusies, waarbij ten minste in de onderste ruimte één of meer utiliteitvoorzieningen, zoals gas, water, licht, (glasvezel)kabels voor telecommunicatie e.d. worden gelegd.Method according to one of the preceding claims, wherein at least one or more utility facilities, such as gas, water, light, (fiber optic) cables for telecommunications and the like are laid in the lower space. 5. Werkwijze volgens één van de voorgaande conclusies, waarbij de ondergrondse ruimtes in verticaal scheidbare compartimenten worden opgedeeld die in brandsituaties kunnen worden afgesloten door middel van brandwerende deuren.A method according to any one of the preceding claims, wherein the underground spaces are divided into vertically separable compartments which can be closed in fire situations by means of fire doors. 6. Werkwijze volgens één van de voorgaande 5 conclusies, waarbij aardwarmte wordt gebruikt voor het verwarmen en/of koelen van de luchtstromen in ten minste de bovenste ruimtes.A method according to any one of the preceding claims, wherein geothermal heat is used for heating and / or cooling the air flows in at least the upper spaces. 7. Werkwijze volgens één van de voorgaande 10 conclusies, waarbij na het aanbrengen van ten minste twee vloeren, water in de gracht wordt gelaten en werkzaamheden voor het aanbrengen van dieperliggende lagen hieronder wordt voortgezet.7. Method as claimed in any of the foregoing claims, wherein after the application of at least two floors, water is allowed into the canal and work for applying deeper layers is continued below.
NL1036626A 2009-02-24 2009-02-24 UNDERGROUND SPACE IN CITY WITH CLOSED STREETS. NL1036626C2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
NL1036626A NL1036626C2 (en) 2009-02-24 2009-02-24 UNDERGROUND SPACE IN CITY WITH CLOSED STREETS.

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
NL1036626 2009-02-24
NL1036626A NL1036626C2 (en) 2009-02-24 2009-02-24 UNDERGROUND SPACE IN CITY WITH CLOSED STREETS.

Publications (1)

Publication Number Publication Date
NL1036626C2 true NL1036626C2 (en) 2010-08-25

Family

ID=41132829

Family Applications (1)

Application Number Title Priority Date Filing Date
NL1036626A NL1036626C2 (en) 2009-02-24 2009-02-24 UNDERGROUND SPACE IN CITY WITH CLOSED STREETS.

Country Status (1)

Country Link
NL (1) NL1036626C2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105863330A (en) * 2016-05-25 2016-08-17 上海建工建集团有限公司 Sequential construction method for car ramps in reverse construction method

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB511373A (en) * 1938-03-11 1939-08-17 Campbell Murray Hunter Improvements relating to the construction of underground chambers
FR1263735A (en) * 1960-08-02 1961-06-09 Process for the construction of underground garages or other underground premises
GB940500A (en) * 1959-12-02 1963-10-30 Noel Ebenezer Morris Brydon Improvements relating to the construction of underground buildings
GB1156848A (en) * 1966-10-12 1969-07-02 Helical Parks Ltd Improvements relating to Garages for the Multiple Parking of Vehicles.
GB2211877A (en) * 1987-11-03 1989-07-12 Christiani & Nielsen Ltd Road vehicle storage structures
NL1005826C1 (en) * 1997-04-17 1998-05-19 Dlp Inc Designer & Licensee Of Construction and method for installation of parking provisions under municipal canal zones, canals and parks - involves construction formed by concrete and or steel closed trough with several entrances and exits which issue onto traffic section crossways to canal or park
NL1008220C2 (en) * 1997-10-15 1999-03-01 Bovon Construction method for road or rail tunnel or cutting
NL1013267C2 (en) * 1998-11-25 2000-05-30 Leonardus Karel Van Tol H O D Tunnel construction method for waterlogged urban area provides tunnel for underground railway and surface roadway
BE1015517A3 (en) * 2003-05-15 2005-05-03 Denys Nv METHOD FOR THE CONSTRUCTION OF A TUNNEL UNDER A ROADWAY AND APPLIED THEREBY vault.
EP1548208A1 (en) * 2003-12-16 2005-06-29 Edera S.R.L. Underground garage including an improved ventilating system

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB511373A (en) * 1938-03-11 1939-08-17 Campbell Murray Hunter Improvements relating to the construction of underground chambers
GB940500A (en) * 1959-12-02 1963-10-30 Noel Ebenezer Morris Brydon Improvements relating to the construction of underground buildings
FR1263735A (en) * 1960-08-02 1961-06-09 Process for the construction of underground garages or other underground premises
GB1156848A (en) * 1966-10-12 1969-07-02 Helical Parks Ltd Improvements relating to Garages for the Multiple Parking of Vehicles.
GB2211877A (en) * 1987-11-03 1989-07-12 Christiani & Nielsen Ltd Road vehicle storage structures
NL1005826C1 (en) * 1997-04-17 1998-05-19 Dlp Inc Designer & Licensee Of Construction and method for installation of parking provisions under municipal canal zones, canals and parks - involves construction formed by concrete and or steel closed trough with several entrances and exits which issue onto traffic section crossways to canal or park
NL1008220C2 (en) * 1997-10-15 1999-03-01 Bovon Construction method for road or rail tunnel or cutting
NL1013267C2 (en) * 1998-11-25 2000-05-30 Leonardus Karel Van Tol H O D Tunnel construction method for waterlogged urban area provides tunnel for underground railway and surface roadway
BE1015517A3 (en) * 2003-05-15 2005-05-03 Denys Nv METHOD FOR THE CONSTRUCTION OF A TUNNEL UNDER A ROADWAY AND APPLIED THEREBY vault.
EP1548208A1 (en) * 2003-12-16 2005-06-29 Edera S.R.L. Underground garage including an improved ventilating system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105863330A (en) * 2016-05-25 2016-08-17 上海建工建集团有限公司 Sequential construction method for car ramps in reverse construction method

Similar Documents

Publication Publication Date Title
US20170321397A1 (en) Honeycomb module and underground storage system
WO2013147652A2 (en) Metro station and method for constructing same
US11891793B2 (en) Resilient building and site construction system and method
NL1036626C2 (en) UNDERGROUND SPACE IN CITY WITH CLOSED STREETS.
GB2371584A (en) Sectioned flood defence barrier
RU2511067C1 (en) Multi-functional structure
Ramírez Chasco et al. Lezkairu Utilities Tunnel
El-Habash et al. GROUNDWATER MANAGEMENT FOR THE ENHANCEMENT OF THE URBAN FABRIC IN HISTORIC CAIRO.
RU2304670C1 (en) All-purpose skeleton-type building or building structure
Guillette et al. Achieving Sustainable Site Design through Low Impact Development Practices
Halilaj Zero Energy Office Building Design and Management
Brambila et al. Design of Multistory Historical LEED Building
Reyes et al. Design Report: Stormwater Improvements
Kril Influence of engineering-geological conditions on safety working of a transport network at the traffic intensification
Musilli Clean Venice: Infrastructure & Place-Making in Venice, Italy
Sedrak et al. Solution Model for Infrastructure Planning and Design for Urban Slums: Egyptian Case Study
Suemori et al. Current Stormwater Practices and Future Implementation at Portland State University with the Uncertainty of Climate Change
Garg Construction Works Outside the Main Building
CALL et al. Town of Groton, Connecticut
Bapla et al. Stadium Neighborhood Underground Parkade and Water Storage
Pace Low-Impact Infrastructure: Development and Design Potential for Surface Application Alternatives for Subsurface Infrastructure in Yellowstone National Park's Upper Geyser Basin
Arcot et al. Multiple Use Stormwater Detention Adjacent to UBC Centre for Comparative Medicine: Final Design Report
Arcot et al. UBC Stormwater Detention: Multiple Use Stormwater Detention Adjacent to UBC Centre for Comparative Medicine
KR101475031B1 (en) Auto snow-removing block
Sarchenko The economic essence of underground development

Legal Events

Date Code Title Description
RC Pledge established

Free format text: DETAILS LICENCE OR PLEDGE: PANDRECHT, GEVESTIGD, INDIENING PANDAKTE OP 9 OKTOBER 2015 DOOR NLO TE DEN HAAG. PANDGEVER IS STRUKTON GROEP N.V. TE UTRECHT PANDHOUDER IS COOEPERATIEVE CENTRALE RAIFFEISEN-BOERENLEENBANK B.A. TE UTRECHT ZIE VERDER DE AKTE.

Name of requester: COOEPERATIEVE CENTRALE RAIFFEISEN-BOERENLEENBANK B

Effective date: 20151009

RF Pledge or confiscation terminated

Free format text: RIGHT OF PLEDGE, REMOVED

Effective date: 20180725

MM Lapsed because of non-payment of the annual fee

Effective date: 20200301