KR960009269B1 - Form-less style working method for underground constructions - Google Patents
Form-less style working method for underground constructions Download PDFInfo
- Publication number
- KR960009269B1 KR960009269B1 KR1019920014526A KR920014526A KR960009269B1 KR 960009269 B1 KR960009269 B1 KR 960009269B1 KR 1019920014526 A KR1019920014526 A KR 1019920014526A KR 920014526 A KR920014526 A KR 920014526A KR 960009269 B1 KR960009269 B1 KR 960009269B1
- Authority
- KR
- South Korea
- Prior art keywords
- basement
- layer
- building
- ground
- floor
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/30—Miscellaneous comprising anchoring details
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
제1도의 a-g는 본 발명에 의한 지하층의 구축과정을 순차적으로 예시한 공정 순서도.A-g of FIG. 1 is a process flowchart sequentially illustrating a process of constructing a basement layer according to the present invention.
제2도의 a-d는 본 발명에 있어서, 구축되는 지하층 구조물의 괘지수단으로 이용되는 도르래 설치구조를 예시한 개략도.A-d of FIG. 2 is a schematic diagram illustrating a pulley installation structure used as a holding means of a basement structure to be constructed in the present invention.
제3도의 a는 최초로 시공되는 지하층 하부구조물의 바닥면에 개공을 관통형성시켜준 실시예를, b는 개공이 없는 폐쇄형태로 형성시켜준 실시예를 각각 나타낸 개략평면도.3 is a schematic plan view showing an embodiment in which openings are formed through the bottom surface of the first basement substructure to be constructed, and b is an embodiment in which the openings are formed in a closed shape without openings.
제4도는 본 발명에 있어서, 최초로 시공되는 지하층 구조물에서 양생 판넬 제거하고 지하층 구조물에 직접 와이어 로우프롤 연결하여 괘지시켜준후 지하층을 구축하는 상태를 예시한 실시예시도.FIG. 4 is an exemplary view illustrating a state in which a curing panel is removed from a basement structure to be constructed first, and a basement layer is constructed after the wire layer is directly connected to the basement structure.
제5도는 본 발명에 있어서, 지하층 구조물의 바닥면을 폐쇄형으로 형성시켜준 상태에서 지하층을 구축하는 제3공정의 변형실시예시도.5 is a modified embodiment of the third step of constructing the basement in the state in which the bottom surface of the basement structure is formed closed in the present invention.
제6도 a,b,c는 본 발명의 제1-제3변형실시예시도Figure 6 a, b, c is a first to third modified embodiment of the present invention
* 도면의 주요부분에 대한 부호의 설명* Explanation of symbols for main parts of the drawings
1 : 지표층 2 : 기반암층1: surface layer 2: bedrock layer
3 : 지지파일 4 : 가이드월3: support file 4: guide wall
5 : 연약층 7 : 도르레5: soft layer 7: pulley
8 : 와이어 로우프 9 : 양생판넬8: wire rope 9: curing panel
12,20 : 바닥면 13 : 개공12,20: Bottom surface 13: Opening
16,22 : 흡입기 23 : 푸쉬풀쟈키16,22: inhaler 23: push-pull jockey
30 : 크레인 31 : 어스앵커30 crane 31 earth anchor
A : 지하층 A' : 하부구조물A: Basement A ': Substructure
A',A' : 상부층구조물A ', A': upper layer structure
본 발명은 지표와 지하의 기반암층 사이에 해성이토층(뻘)이나 연약토층(진흙등) 등의 연약층이 존재하는 특징부재에의 건축물 구축시 연약층에 위치되게 되는 지하층을 용이하게 구축시공할 수 있도록한 건물자중을 이용한 자연하강식 지하층 구축방법에 관한 것이다.The present invention can easily construct a basement layer that is located in a soft layer when building a feature member in which a soft layer such as a marine soil layer or a soft soil layer (mud, etc.) exists between the surface and the underground bedrock layer. The present invention relates to a method of constructing a naturally descending underground floor using the weight of the building.
현재 시공되고 있는 대부분의 건축물은 지하에 소정구조의 지하층을 구축하고 있으며, 이러한 지하층은 시공대상의 건축물이 높으면 높을수록 지하 깊숙이 시공되는 것이 통례이다.Most of the buildings currently being constructed have a basement of a predetermined structure in the basement, and it is customary that such a basement is constructed deeper the higher the construction of the object to be constructed.
이와 같이 지하 깊숙이 지하층을 구축에 있어서, 비교적 단단한 지층이 존재하게 되는 부지에서는 지반층을 파내고 지하층을 간단히 시공구축할 수 있으나 비교적 단단한 지반층이 지표로부터 2-3m 두께에 불과하고 그 하부로부터 20-50m 정도의 연약층이 곳곳에 존재하는 해안지방(* 국내에서는 부산, 인천, 울산지역이 특히 심함) 등의 부지에서는 건물 지하층의 구축에 많은 어려움이 따르고 있었다. 그 어려움을 상세하게 설명하면, 지하층 구축을 위해 지반을 파내려가는 과정에서 해성이토층이나 연약토층으로 이루어지는 연약층에 도달하게 되면, 겔상태의 연약층이 횡방향으로부터 계속 밀려들어오게 되면서 더 이상의 굴착작업이 거의 불가능하게 됨에 따라 야기되고 있었다. 이와 같은 요인으로 인해 지반의 굴착이 불가능하게 됨에 따라 그 대응방편으로서 실시되고 있던 종래의 지하층 구축방법을 살펴보기로 한다.As such, when building a basement deep into the basement, it is possible to excavate the ground layer and construct a simple underground construction at the site where a relatively hard layer exists, but the relatively hard ground layer is only 2-3m thick from the surface and 20 from the bottom. There were many difficulties in building the basement of the building at sites such as coastal areas (* Busan, Incheon, Ulsan, especially in Korea) where soft layers of about -50m exist everywhere. Explaining the difficulties in detail, when the soil reaches a soft layer composed of a marine soil layer or a soft soil layer in the process of digging the ground for the construction of the basement layer, the soft layer in the gel state is continuously pushed from the transverse direction and further excavation work is performed. It was caused by almost impossible. Due to such factors, the excavation of the ground becomes impossible, and therefore, the conventional underground construction method, which has been implemented as a countermeasure, will be described.
먼저 신축 예정건물 외곡선밖에 흙막이벽(* 연속된 일체의 벽이나 현장 타설말뚝을 겹친벽 또는 H빔사이에 판넬을 끼워 만든 벽 등)을 설치해 주고, 이 흙막이벽 안쪽(* 건물 지하층을 구축할 자리)을 굴착해낸다.First, install a wall of mud walls (* continuous wall, wall with piled on-site piles, or a panel made by sandwiching panels between H beams) outside the planned construction of the new building. Excavate the seat).
그리고 이 굴착과정에서 흙막이벽이 받는 횡토압에 대응토록 하기 위해 어스앵커(EARTH ANCHOR)나 가시설을 흙막이벽에 내설한다. 이와 같은 작업 과정이 끝나면 건물 지하층 맨 밑바닥부터 신축을 시작하게 되는바 이러한 지하층 시공방법은 다음과 같은 문제점이 있다.And in order to cope with the transverse pressure of the wall in the excavation process, earth anchors or temporary facilities are installed on the wall. When the work process is completed, the construction starts from the bottom of the basement floor of the building. The construction method of the basement floor has the following problems.
· 흙막이벽을 지하의 기반암층까지 도달시키지 않으면 굴착시 흙막이벽 바깥과 안쪽의 압력차에 의한 연약층의 유동현상, 즉 솟음(HEAVING) 현상으로 인하여 굴착작업이 어려워진다.Excavation becomes difficult due to the phenomenon of weakening of the weak layer due to the pressure difference between the outside and the inside of the wall when the excavation does not reach the basement rock layer in the underground.
· 가시설을 설치하는 경우 건물 지하층 골조 위치를 피해서 설치해 주어야만 함은 물론 설치된 가시설로 인하여 지하층 골조 신축 작업성이 많이 떨어진다.· In case of installing temporary facilities, it is necessary to avoid the location of the basement frame of the building, as well as the workability of the new construction of basement frames due to the installed facility.
· 지하층 신축 작업을 지상에서 상당히 떨어진 지하부분에서 진행해야 하게 되므로 작업이 번잡하게 되고 안전사고의 위험이 매우 높았다.· Since the construction of the basement floor was to be carried out in the basement part far from the ground, the work was complicated and the risk of safety accidents was very high.
이상의 문제점으로 인하여 작업기일과 경비가 과도하게 소요됨은 물론 인접 건물이나 지반의 피해를 야기하는 사태가 자주 발생된다.Due to the above problems, excessive work dates and expenses are required, as well as situations that cause damage to adjacent buildings or ground.
이러한 제반 문제점을 해소하고자 국내공개특허공보(공개번호 88-10200호)에는 하향식 지하층의 건축방법이 제안되고 있다.In order to solve such problems, a domestic top-down patent publication (Publication No. 88-10200) proposes a top-down basement building method.
이를 간략히 설명하면 목적하는 지하층의 깊이로 웅벽지주와 건물의 각 지주의 H 형강을 설계 위치대로 부지의 지하에 수직으로 매설하고 각층 단위로 옹벽지주와 건물 지주간에 각각 버팀대와 가로빔을 연접시공하고 가로빔을 따라 먼저 골조와 함께 슬라브를 시공한 후 각층 단위로 땅을 굴착하면서 순차적으로 슬라브공사를 하향으로 진행하여서 목적하는 지하층의 공간의 굴착과 슬라브를 시공한 다음 건물과 옹벽 사이의 공간을 매립하여서 지하층을 건축하는 것이다.To explain this briefly, the H-beams of the arch walls and each strut of the building are laid vertically in the basement of the site according to the design depth, and the braces and the horizontal beams are connected between the retaining wall struts and the struts of each floor. After the slab is constructed along with the horizontal beams and the slab is first excavated, the slab construction is carried out downwards, and the excavation of the target basement space and the slab are constructed, and then the space between the building and the retaining wall It is to build a basement by reclamation.
그러나 이와 같은 공법은 해당층 건물을 그 해당층 위치에서 제작하게 됨에 따라 먼저 건축된 해당층의 아래로 또 다른 해당층을 건축하기가 매우 까다롭게 되는 단점이 있었다.However, such a construction method has a disadvantage in that it is very difficult to construct another relevant floor below the first floor, as the corresponding floor is manufactured at the location of the corresponding floor.
즉, 다음 층을 건축시키기 위해서는 양측 옹벽 사이를 통하여 굴착 및 굴삭토의 토출 또는 자재의 운반등이 매우 번거롭고 까다로와 시공기간이 길게 되며, 많은 인력이 요구되는 등의 문제점이 따르게 되는 것이다.That is, in order to build the next floor, excavation and discharge of excavated soil or transportation of materials through both retaining walls are very cumbersome, difficult and construction period is long, and a lot of manpower is required.
이러한 각층 단위로 땅을 굴착하면서 순차적으로 슬라브공사를 하향 진행하게 되는데서 따르게 되는 제반 문제점을 감안하여 일본국 특허공보 소 45-10898호에는 정해진 위치에서 그 아래층의 건물들을 제작하여 하강시키는 지하건조물의 구축공법이 제안되고 있다. 그러나, 이러한 공법 역시 다음과 같은 문제점을 안게 된다.In view of all the problems caused by the sequential construction of the slab, the excavation of the ground by each floor unit, Japanese Patent Publication No. 45-10898 discloses the construction of the underground building that lowers and builds the buildings on the lower floor at the designated location. Construction methods have been proposed. However, this method also has the following problems.
즉, 지반굴착 및 건물하강에 있어서 맨 바닥층 하부에서 지반이 별도로 굴착되어야 하며, 굴착후 건물을 제작하여 하강시키게 되는 다시 말하면 미리 여러층의 지하건조물을 동시에 건조하여 하강시키게 됨에 따라 큰 하중을 동작시키는 기술이 매우 까다롭게 되었다.That is, in the ground excavation and building descent, the ground must be excavated separately from the bottom of the bottom floor, and after the excavation, the building is lowered. In other words, the underground buildings of several floors are dried and lowered in advance to operate a large load. Technology is very demanding.
또한, 건물하강시 수평유지에 있어서 제작된 건물측면에 롤라를 달아 수직기 등에 의지시켜 전체 건물의 수평을 유지하면서 하강시키게 됨에 따라 정밀한 수평유지 기술이 요구되는 것이다.In addition, a precise horizontal maintenance technique is required as the rollers are attached to the side of the building produced in the horizontal maintenance during the descent of the building and descended while maintaining the horizontal level of the entire building.
또한, 맨 바닥층 개폐 여부에 있어서는 맨 바닥층이 항상 밀폐된 상태를 유지되는 까닭에 맨 바닥층 하부에서 별도의 공사가 요구되는 경우 밀폐된 바닥층을 오픈시키게 하던지 하여 이중의 필요없는 작업이 행해져야만 하였다.In addition, when opening or closing the bottom floor, the bottom floor is always kept in a closed state, so if a separate construction is required under the bottom floor floor, the closed floor should be opened or not, so that unnecessary work had to be performed.
또한, 지하층 이벽 형성 필요 여부에 있어서 상기 공법은 슬러리월(Slurry Wall) 등의 지하층 외벽 형성이 필요하게 됨에 따라 공사비 증대는 물론 공사 기간이 연장되는 등의 여러 문제점이 야기되는 것이었다.In addition, whether or not the basement layer needs to be formed, the above method requires the formation of an outer layer of the basement layer such as a slurry wall, which causes various problems such as an increase in construction cost and an extension of the construction period.
본 발명은 이와 같은 현실정을 감안하여 연구개발된 것으로, 설정되는 건축부지의 지표층을 관통하여 지상으로부터 지하의 기반암층까지 다수의 지지파일을 신축 예정건물 외곽부위에 박아 고정시켜준 다음 상기 지지파일을 연결하는 ''가이드 월'' 지표층 내벽부에 설치하여 횡방향으로부터 가해지는 압력에 대응토록 하는 선 작업과정을 실시한 후, 지상으로 노출된 상태의 지지파일 상부측에 도르레 등의 괘지 수단을 설치하고 상기 괘지수단에 감겨지는 와이어 로우프에 콘크리트 양생판넬을 괘지 설치해준 상태에서 임의 설계된대로 콘크리트를 타설 양생시켜 지하층의 하부측 구조물을 선구축해 준다음 수평유지장치에 의하여 구조물의 수평을 유지시킨 상태에서 도르레를 풀어주면서 구축된 지하층 구조물의 자체하중에 의해 연약층 내로 침강되도록 하되, 지하층 구조물의 상측 일부는 연약층 위에 노출되어 있도록 하고, 그 노출부위에 연결되는 상태로서 콘크리트를 타설 양생시켜 주는 과정을 반복 시행하면서 지하층 구조물을 완성 구축토록 하는 새로운 공법의 지하층 구축방법을 제공하므로서, 지표층과 기반암층 사이에 해성이토층이나 연약토층 등의 연약층이 존재하는 부지에서도 건축물을 신속 용이하게 구축할 수 있도록 하면서 그 시공 경비는 시공기간의 최소화 효과를 얻도록 함은 물론 시공과정의 단순화로 시공작업상의 편리성 증대효과를 기대할 수 있도록 하는데 주목적이 있는 것으로 그 공정과정과 실시예 및 그에 따른 작용효과를 첨부도면에 의거하여 상세히 설명하면 다음과 같다.The present invention has been researched and developed in view of such a reality, and through the ground layer of the building site to be set, a plurality of support piles from the ground to the basement rock layer to be fixed to the outer portion of the new projected building and then the support pile `` Guidewall '' is installed on the inner wall of the ground layer to connect the wires, and the line work process to cope with the pressure applied from the transverse direction is carried out, and then, a ruling means such as a pulley is installed on the upper side of the supporting pile exposed to the ground. In the state where the concrete curing panel is installed on the wire rope wound on the hanging means, the concrete is laid as it is designed to cure concrete and pre-construct the lower side structure of the basement floor. Settle into the soft layer by the self-load of the basement structure constructed by releasing the pulley The base part of the basement structure should be exposed on the soft layer, and the base layer construction method of the new construction method to complete the basement structure is repeated while repeating the process of pouring concrete as it is connected to the exposed part. Therefore, the construction cost can be quickly and easily constructed even on the site where the soft soil such as the marine soil layer or soft soil layer exists between the surface layer and the bedrock layer. The main purpose is to simplify the convenience of the construction work can be expected by the simplification. The process and the embodiment and the effects thereof according to the accompanying drawings will be described in detail as follows.
(제1공정)(Step 1)
제1도의 a,b,c에 도시된 바와 같이, 고강도를 갖는 다수의 앵커파일이나 스크류파일(3)을(이하 지지파일이라 칭함) 선정되는 건축부지의 지표층(1)으로부터 지하의 기반암층(2)까지 적정간격으로 견고히 박아 고정설치해 주면서 각각의 지지파일(3)이 그리게 되는 사방외곽선 내에 구축 예정이 지하층 설치 면적이 확보되도록 하고, 지표층(1)의 내면부에는 각각의 지지파일(3)에 지지되는 상태로 가이드월(GUIDEWALL)(4)을 설치하여 지표층(1)의 횡압에 대응토록 한 상태에서 각각의 지지파일 내측부에 해당되는 지표층(1)을 굴착하면서 걷어내 그 하부층에 위치되는 해성이토층이나 연약토층 등으로 이루어진 연약층(5)이 노출되도록 하여, 각각의 지지파일(3) 상단에는 도르레(7) 등의 괘지수단을 고정 설치해 주는 선행작업 공정과정이다.As shown in a, b, and c of FIG. 1, a plurality of anchor piles or screw piles 3 (hereinafter referred to as support piles) having high strength are selected from the ground layer 1 from the ground layer 1 of the building site to be selected. 2) To be firmly fixed at proper intervals until the installation, the construction plan is to be secured within the four-sided outline where each supporting pile 3 is drawn, and each supporting pile 3 is provided on the inner surface of the ground layer 1. The guide wall (GUIDEWALL) (4) is installed in a state supported on the ground layer (1) to cope with the transverse pressure of the ground layer (1) to excavate the ground layer (1) corresponding to the inner side of each support pile, and is located in the lower layer By exposing the soft layer (5) consisting of a marine soil layer, a soft soil layer, etc., each support pile (3) is a preliminary work process to fix the fixing means such as the pulley (7) on the top.
이러한 공정과정에 있어서는, 기반암층(2)에 박혀지는 지지파일(3)이 정확하게 수직 상태를 유지토록 하고, 각각의 지지파일(3) 간격은 구축대상의 건축물에 의해 가해지게 될 예상하중과 기반암층(2)의 지질을 감안하여 적절히 조절설정해 주도록 하며, 건축여건상 지지파일(3)이 강한 인발력을 발휘토록 하고자 할 때는 선단에 스크류가 형성된 스크류파일을 지지파일로 선택 설치하는 것이 바람직하다.In this process, the supporting piles 3 embedded in the bedrock layer 2 are kept vertically precisely, and the interval between each supporting pile 3 is expected to be applied by the building to be built and the bedrock. In consideration of the geology of the layer (2), it is appropriately adjusted and set, and in order to make the support pile (3) exhibit strong pulling force due to the construction condition, it is preferable to select and install a screw pile having a screw formed at the tip as a support pile.
상기 지지파일(3)과 가이드월(4)은 경우에 따라서 가이드월(4)의 설치작업을 선행한 후 지지파일(3)을 설치하는 방안도 가능한 실시예이며, 이때 가이드월(4)의 설치 깊이는 지표층(1)의 하단부까지 다다르도록 하되, 지표층(1)의 층 두께가 2-3m 이내에 불과할 경우에는 연약층(5)까지 약간 연장 설치해 주는 것이 바람직하며, 괘지수단으로 사용되게 되는 도르레(7)의 설치구조는 도면 제2도에 도시된 바와 같이, 다양한 형식으로 변형실시할 수 있는바, 구축여건에 따라 가장 알맞는 형식을 선택하도록 한다.The support pile (3) and the guide wall (4) is an embodiment in which a method for installing the support pile (3) prior to the installation work of the guide wall (4) in some cases, the guide wall (4) The installation depth is to reach the lower end of the ground layer (1), but if the layer thickness of the ground layer (1) is only within 2-3m, it is preferable to extend slightly to the soft layer (5), the pulley to be used as a ruling means As shown in Fig. 2, the installation structure of (7) can be modified in various forms, so that the most suitable form is selected according to the construction conditions.
(제2공정)(2nd step)
상기 제1공정과정을 완료한 후, 제1도의 라에 도시된 바와 같이, 괘지수단으로 지지파일(3) 상부에 설치되는 도르레(7)에 고강도의 와이어 로우프(8)를 감아 주고, 상기 와이어 로우프(8)에 일정 형태로 짜여진 콘크리트 양생판넬(9)을 걸어 설치해준 상태에서 콘크리트를 타설 양생하여 소정구조를 갖는 지하층(A)의 최하부측에 해당되는 하부구조물(A')을 선 구축하는 공정과정이다.After completing the first process, as shown in the la of FIG. 1, the high-strength wire rope (8) is wound around the pulley (7) installed on the support pile (3) by the locking means, the wire Pre-constructing the substructure A 'corresponding to the lowermost side of the basement layer A having a predetermined structure by placing concrete in the state where the concrete curing panel 9 woven in a certain shape is installed on the rope 8 It is a process.
이러한 공정과정을 실시함에 있어서는 지하층의 설계구조에 따라 하부층 구조물을 구축하게 되며, 콘크리트 타설작업을 양생판넬(9)이 도르레(7)를 통해 지상에 괘지되도록한 상태에서 실시하게 됨으로서 타설작업의 편리성 증대효과를 얻게 된다.In carrying out such a process, the lower layer structure is constructed according to the design structure of the basement layer, and the concrete placing work is carried out in a state where the curing panel 9 is suspended on the ground through the pulley 7, thereby making it convenient to place the work. You will gain sex.
한편, 구축되는 지하층(A)의 하부구조물(A') 바닥은 제3도의 가에 도시된 바와 같이 바닥면(12)상에 다수의 개공(13)이 관통 형성되거나 바닥골조 그대로인 개방형태로 형성해 주는 방법과(이하 바닥 개방형이라 칭함) 나에 도시된 바와 같은 폐쇄형으로 구축하는 방법(이하 바닥 폐쇄형이라 칭함)이 있다.On the other hand, the bottom of the lower structure (A ') of the basement layer (A) to be constructed is formed in an open form in which a plurality of openings 13 are formed through the bottom surface 12 or as the bottom frame as shown in FIG. There is a method of giving (hereinafter referred to as a bottom open type) and a method of building as a closed type (hereinafter referred to as a bottom closed type).
(제3공정)(3rd step)
상기 제2공정과정을 통해 최하부층에 해당되는 하부구조물(A')이 구축되게 되면, 제1도의 마에 도시된 바와 같이, 도르레(7)를 풀어주면서 자중에 의해 구조물(A')이 연약층(5) 내부로 침강되도록 하고, 이와 같은 상태로 구조물(A')의 침강작용이 계속되면서 상단 일부만이 지상에 남아 있게 되며 도르레(7)를 멈춰 구조물(A')이 더 이상 침강하지 못하도록 한 상태에서 지상에 노출되어 있는 구조물(A')의 상측에 소정구조의 상부층 구조물(A'')을 연결 구축한 후, 전술과 같은 과정을 통해 구조물이 연약층(5)내로 침강되도록하고, 침강작용이 계속되면서 신축된 상부층 구조물(A)의 상측 일부만이 지상에 위치되게 되면 도르레(7)를 멈추고 상부층 구조물(A) 상측에 또 다른 상부층 구조물(A')을 연결 구축해 주는 과정을 반복 실시하면서 제1도의 마에 도시된 바와 같이 소정구조의 지하층 구축을 완성하는 공정과정이다.When the lower structure (A ') corresponding to the lowermost layer is constructed through the second process, the structure (A') is a soft layer due to its own weight while releasing the pulley (7), as shown in FIG. 5) It is settled to the inside, and in this state, the sedimentation of the structure A 'continues and only the upper part remains on the ground, and the pulley 7 is stopped to prevent the structure A' from sinking anymore. After connecting and establishing the upper layer structure (A '') of the predetermined structure on the upper side of the structure (A ') exposed to the ground in the above, the structure is settled into the weak layer (5) through the same process as described above, If only a portion of the upper portion of the stretched upper layer structure A is positioned on the ground, the first step is repeated while stopping the pulley 7 and connecting another upper layer structure A 'to the upper layer structure A. Bar shown in town Likewise, it is a process of completing basement construction of a predetermined structure.
이러한 공정과정에서는 소정구조로 구축되는 지하층(A)의 내부 공간(* 방, 부엌, 화장실 등의 실내구조)에 물이나 비중이 높은 벤트 나이트 등의 액체류를 적정량씩 채워넣어 건물자중을 증대시켜 줌으로서, 구조물의 침강작용 촉진효과를 기대할 수 있도록 함과 동시에 각각의 내부공간에 채워지는 액체류의 양을 적절히 이동조절해 주면서 침강되는 구조물의 수평균형 유지수단으로 이용토록 하고, 이때 침강상태인 구조물의 수평 유지 여부는 구조물 적정부위에 수준기나 센서 등을 설치하여 외부에서 검측할 수 있도록 한다.In this process, by filling the appropriate amount of liquid such as water or bent knight with high specific gravity into the internal space (* room, kitchen, bathroom, etc.) of the underground floor (A), which has a predetermined structure, the weight of the building is increased. By zooming, it is possible to expect the effect of promoting the sedimentation of the structure and to use it as a means for maintaining the number average type of the sedimented structure while properly controlling the amount of liquids filled in each internal space. Leveling of the structure is to be installed at the appropriate part of the structure so that the level can be detected from the outside.
한편, 제4도에 도시된 것은, 상기 제3공정의 변형실시예를 나타낸 것인바, 지하층(A)을 이루는 하부구조물(A')이 양생 구축되면 콘크리트 양생판넬(9)을 분리시키고 와이어 로우프(8)를 하부구조물(A')에 직접 연결해 주면서 도르레(7)에 괘지되도록한 상태에서 잔여 공정과정을 진행토록 한 것인바, 이러한 실시예는 지하층(A)을 완전히 구축한 상태에서 하부구조물(A')의 바닥과 기반암층(3) 사이에 존재하게 되는 틈을 메워주기 위해 그라우팅 작업을 실시할 때(후술될 제5공정과정에서 실시하게 됨) 작업의 편리성을 얻게 되며, 하부구조물의 바닥면과 기반암층(2) 사이에 양생판넬이 존재하지 않도록 하면서 구조물의 안착상태를 더욱 견고히 하는 효과를 기대할 수 있다.On the other hand, it is shown in Figure 4, which shows a modified embodiment of the third process, when the substructure (A ') constituting the basement layer (A) is cured to build the concrete curing panel (9) and wire rope Directly connecting (8) to the undercarriage (A ') while the rest of the process to proceed to the state to be suspended in the pulley (7), this embodiment is a substructure in the state of fully built basement layer (A) When grouting is performed to fill the gap existing between the bottom of (A ') and the bedrock layer 3 (in the fifth process described later), the convenience of the work is obtained, and the substructure While the curing panel does not exist between the bottom surface and the bedrock layer (2) of the structure can be expected to further strengthen the seating state.
(제4공정)(4th step)
상기 공정과정의 순차적 실시로 소정구조의 지하층(A) 구축이 완료된 상태에서 지하층(A) 내부를 깨끗이 세척하고 바닥의 개공(13)을 메워주는 씰링작업을 실시한 후 각 지하층에의 슬래브(SLAB) 설치작업 등을 실행하는 내부 마무리 작업공정과정이다.Slabs to each basement floor after performing the sealing operation to clean the inside of the basement layer (A) and fill the opening 13 of the floor in the state that the construction of the basement layer (A) of the predetermined structure is completed by the sequential implementation of the process process. This is the internal finishing work process that performs the installation work.
이때의 공정과정에서는 최종적으로 설치하였뎐 흡입교반기를 제거토록 한다.In this process, the suction stirrer is finally removed.
이와 같은 공정과정은 바닥 개방형에 주로 적용되게 되는 것인바, 지하층의 바닥이 소정의 위치까지 침강하면 지하층 바닥(12)을 임시로 막아주어야 하는데 이때 기존에 설치된 차단막을 끌어당기는 시스템을 이용하거나 콘크리트 양생판넬을 변형하는 방법을 사용토록 한다.This process is to be mainly applied to the open floor type, when the basement floor is settled to a predetermined position to temporarily block the basement floor 12, at this time using a system that pulls the existing barrier screen or curing concrete Use a panel modification method.
이와 같은 방법으로 지하바닥을 외부로부터 차단시킨 상태에서 지상으로부터 교반스크류(17) 등을 투입하여 지항층내부의 뻘을 교반한 후 흡입기(16)로 빨아낸 다음 지하층 내부를 세척해 주도록 하고, 이와같은 과정을 통해 지하층 바닥면(임시 차단막 포함)이 나타나면 지하층 바닥면을 다시 측조하거나 임시 차단막을 잘 폐쇄시켜 영구 지하층 바닥을 형성시킨다.In this way, while the basement floor is blocked from the outside, a stirring screw (17), etc. is introduced from the ground to stir the tank inside the sea zone layer, sucked by the inhaler (16), and the inside of the basement layer is washed. If the basement floor surface (including temporary barriers) appears through the same process, the basement floor surface is re-measured or the temporary barrier is well closed to form a permanent basement floor.
한편, 바닥 폐쇄형에 있어서는, 바닥이 막힌 영구 지하층 바닥(20)을 최초 시공시 측조하고 전술한 바와같은 건물 침강방법으로 하강시킨다. 단, 이 방법은 건물하강에 따르는 하강 저항이 커지거나 하강한 부피만큼의 연약층이 인접 지반을 교란시킬 가능성이 우려되게 되며, 그 대응책으로 지하층 바닥면(20) 하부측에 교반스크류(17)를 설치하여 연약층(5)을 교반시져 주면서 기 설치된 흡입기(22)를 통해 입여 연약층을 지상으로 배출시켜 주도록 한다. 이때 지하층 바닥면이 예정된 위치에 다다르게 되면 다음 공사시 재사용할 수 있도록 교반스크류(17)를 회수하는 방법도 세워볼 수 있다. 이러한 방법은 연약층이 아닌 단단한 지층에서 사용될 수 있을 것이며 교반스크류(17)와 흡입기(16)의 기능만 강화되면 거의 모든 지반의 지하층 설치에 사용될 수 있을 것이다.(* 후술될 제5공정과정에서 상세히 설명될 것임).On the other hand, in the floor-closed type, the basement floor 20 with the floor blocked is surveyed at the time of initial construction and lowered by the building sedimentation method as described above. However, in this method, there is a concern that the lowering resistance due to the lowering of the building is increased or that the soft layer corresponding to the lowered volume may disturb the adjacent ground, and as a countermeasure, the stirring screw 17 is placed on the lower side of the basement floor 20. It is installed through the inhaler 22 installed while stirring the soft layer (5) to discharge the soft layer to the ground. At this time, when the basement floor reaches the predetermined position, it is possible to build a method for recovering the stirring screw 17 to be reused in the next construction. This method can be used in the hard bed, not the soft bed, and can be used for the installation of almost all the basements of the ground if only the functions of the stirring screw 17 and the inhaler 16 are enhanced. Will be explained).
(제5공정)(5th process)
상기 공정과정으로 지하층(A)의 내부를 마무리한 후 제1도의 사에 도시된 바와 같이 침강 완료된 지하층(A)이, 상부측에 연결 구축되는 상부구조물을 완벽하게 지지해 주는 기초 구조물로서의 기능을 보유토록 하기 위한 보강 공정과정인바, 가이드월(4)과 건물본체(주로 지하 1층 외벽부위)를 체결키(40)나 쐐기(41) 또는 앵커 볼트 등으로 연결해 주거나 접착제(42)로 접착하여 상호 일체화하면서 건물 하중이 가이드 월(4) 및 지지파일(3)을 통해 기반암층(2)에 전달되도록, 기반암층(2)과 지하층(A)의 바닥면 사이에 그라우팅 작업을 실시하여 마감 처리하거나 최하층의 기둥에서 연장되는 개념의 스틸말뚝(18)을 다수 설치하여 지하층(A)을 견고히 안착 설치시켜 주는 공정이다.After finishing the inside of the basement layer (A) by the above process process, as shown in Fig. 1, the sedimentary basement layer (A) functions as a basic structure that perfectly supports the upper structure connected to the upper side. It is a reinforcing process for retaining, connecting the guide wall (4) and the building body (mainly the basement floor of the first floor) with a fastening key (40), a wedge (41) or an anchor bolt, or by adhering with adhesive (42). A grouting operation is performed between the base rock layer 2 and the basement floor A so that building loads are transferred to the bedrock layer 2 through the guide wall 4 and the support pile 3 while integrating with each other. Or by installing a number of steel piles (18) having a concept extending from the lowermost pillars is a process to firmly install the basement layer (A).
이와 같은 공정을 시행함에 있어서는, 기반암층(2)의 상태에 따라시 상술된 3가지의 처리과정을 동시에 실시할 수도 있고, 전혀 실시하지 않을 수 있는바, 기반암층(2)이 일측으로 경사지거나 불규칙할 경우에는 전부 실시해 주는 것이 바람직하다.In implementing such a process, depending on the state of the bedrock layer (2) may be carried out at the same time three treatment processes described above, may not be carried out at all, barbed rock layer (2) is inclined to one side or If it is irregular, it is preferable to carry out all.
한편, 제5도에 도시된 바와 같은 전기한 제2공정과정을 통해 지하층(A)의 하부구조물(A')을 구축함에 있어서, 바닥면을 폐쇄형태로 구축하여 순차적으로 침강되도록 하는 하나의 실시예를 나타낸 것인바, 폐쇄된 영구 지하층 바닥면(20) 하부측에 교반스크류(21)를 측설함과 동시에 다수의 흡입기(22)를 투입 설치하여 연약층(5)으로의 지하층(A)에 침강을 위한 뻘의 교반 및 흡출 제거수단을 이루도록 하고 바닥면이 폐쇄형태로 형성되어 있음에 따라 구조물의 원할한 침강작용을 기대할 수 없게 되는바, 그 대응책으로서 외벽체 상측부와 지지파일(3) 사이에 푸쉬풀 쟈키(23)을 장착하여 강제 침강 수단을 이루도록 하며, 이때 연약층 내로의 구조물 침강작용시 구조물 외벽과 지표층(1) 내벽의 가이드월(4) 사이에 존재하게 되는 틈을 통해 겔 상태의 뻘이 밀려 올라가게 되면서 기본적인 구조물 침강조건은 조성되게 되고, 건물 내부층과 층 사이에 미폐쇄 상태로 형성되는 계단실을 통해 유입되는 뻘은 전기 제3공정에서와 같이 흡입기를 투입 제거해 주도록 한다.Meanwhile, in constructing the substructure A 'of the basement layer A through the above-described second process as shown in FIG. For example, it is settled in the basement layer (A) to the soft layer (5) by the installation of a plurality of inhalers 22 while at the same time staked out the stirring screw 21 on the lower side of the closed permanent basement floor 20. As the bottom surface is formed in a closed form, it is impossible to expect a smooth settling action of the structure, as a countermeasure between the upper side of the outer wall and the support pile (3). Push-pull jockey 23 is installed to form a forced sedimentation means, and at this time, during the sedimentation of the structure into the soft layer, the gel is formed through the gap between the outer wall of the structure and the guide wall 4 of the inner wall of the ground layer 1. Pushed As the basic structure store la settling condition is presented the composition, mud flowing through a staircase formed of a non-closed construction between the inner layer and the layer is removed to give input to the inhaler as in electric third step.
한편, 지하층(A)을 구성하는 각각의 실내공간에는 상기 제3공정에서와 같이 물 등의 액체류를 담아 자중증대 효과를 얻도록 함과 동시에 구획된 각 실내공간에 채워지는 액체류의 양을 적절히 조절해 주면서 지하층의 전체 수평균형을 유지시켜 주도록 하는 한편, 수평균형의 유지 여부 및 침강속도의 완급여부는 센서 등의 감지수단을 이용하여 검측할 수 있도록 하고 이러한 검측수단을 제어는 상황에 따라 개발된 프로그램이 내장된 컴퓨터를 통해 자동으로 실시되도록 하는 것이 바람직하다.On the other hand, in each indoor space constituting the basement layer (A) as in the third step to contain the liquids, such as water to obtain a self-weighting effect and at the same time the amount of liquids to be filled in each of the partitioned indoor spaces While maintaining the overall number average form of the basement while appropriately adjusting, the maintenance of the number average form and the settling rate of sedimentation rate can be detected by using a sensing means such as a sensor. It is desirable for the developed program to be executed automatically through the embedded computer.
한편, 지하층의 구축작업이 완료된 후에 바닥저부에 위치되는 흡입기 및 교반스크류를 제거 또는 회수할 필요가 있을 경우 흡입기 및 교반기의 상측에 위치되는 바닥판의 슬래브를 회동 가능한 상태로 가설해 주는 간단한 방안을 채택함으로서, 슬래브를 회동시켜 소정 공간이 마련되도록 한 후, 상기 공간을 통해 흡입기를 빼내 제거하고 슬래브를 원위치 시킨 상태에서 상기 제4공정 및 제5공정과정을 순차적으로 진행하여 지하층을 완성 구축하게 된다.On the other hand, if it is necessary to remove or recover the inhaler and the stirring screw located at the bottom after completion of the construction of the basement floor, a simple method of hypothesizing the slab of the bottom plate located at the upper side of the inhaler and the agitator in a rotatable state is provided. By adopting, the slab is rotated so that a predetermined space is provided, and then the inhaler is removed and removed through the space, and the fourth and fifth process steps are sequentially performed in the state where the slab is in the original position to complete the basement layer. .
도면 제6도의 a,b,c에 도시된 것은 전술한 본 발명의 제1공정과정을 생략하고 가이드월 또는 지지파일을 설치하지 않는 상태에서 지하층을 간단히 구축하도록 한 본 발명의 변형 실시예를 나타낸 것인바 가에 도시된 제1실시예는, 건축부지 면적이 다소 넓거나 인접부지에 타건축물이 없는 경우 지표층(1) 일부를 상광하협 형태로 경사지게 굴착해 준 상태에서 그 굴착부위에 콘크리트 양생판넬(9)을 설치하고 콘크리트 타설양생시켜 지하층(A)을 선 구축하되, 하부구조물의 바닥면에는 개공이 관통형성된 상태로 구축하여 지상에 설치되는 크레인(30)을 통해 개공 부위를 계속 굴착해 주면서 지하층(A)이 연약층 내로 자연 침강되도록 하면서 연약층에 지하층을 구축 설치토록 한 것이며 그 외의 마무리 공정과정은 본 발명과 같다. 이와 같은 실시예에 있어서는, 전술의 본 발명과 같이, 건물(지하층, 지상층)을 이루는 각각의 실내공간에 액체류를 담고 그 액체류의 량을 유동 조절하면서 건물 전체의 수평 균형을 유지시켜 주도록 하고 이때의 수평균형 유지여부 및 침강속도의 완급여부는 센서 등의 감지수단을 이용토록 하며 상기 감지수단의 제어는 컴퓨터를 통해 자동으로 제어되도록 하는 지상건물 침강발란스 유지방안을 적용하는 것이 바람직하다.6, a, b, and c of FIG. 6 illustrate a modified embodiment of the present invention, in which the basement layer is simply constructed without omitting the first process of the present invention and without installing the guide wall or the supporting pile. According to the first embodiment of the present invention, when the construction site area is a little wide or there are no other buildings on the adjacent site, the concrete curing panel is disposed on the excavation site in a state in which a part of the surface layer 1 is inclined in the form of a light subsoil. (9) install and pour concrete to build the basement layer (A) in advance, while the bottom surface of the lower structure through the opening formed through the construction of the ground through the crane 30 installed on the ground while continuously excavating the opening site The basement layer (A) is to be settled in the soft layer while the natural sedimentation into the soft layer, and the other finishing process is the same as the present invention. In such an embodiment, as in the present invention described above, liquids are contained in each indoor space constituting the building (basement and ground floors), and the flow of the liquids is controlled to maintain horizontal balance of the entire building. At this time, whether or not the number average type maintenance and settlement of the sedimentation speed is to use a sensing means such as a sensor, and the control of the sensing means is preferably applied to maintain the ground building sedimentation balance to be controlled automatically through a computer.
나도는 건축물의 부지면적이 다소 넓거나 인접부지에 타건축물이 없는 경우 실시할 수 있도록한 상기 제1실시예와 거의 유사한 본 발명의 제2실시예를 나타낸 것으로, 상광하협 형태로 경사지게 지표층(l)을 굴착하여 그 내측에 소정구조의 지하층(A)을 구축 설치하되, 지상에는 도르레(7) 등의 괘지수단을 설치하여 양생판넬(9)을 괘지해준 상태에서 지하층의 구축을 연속 반복하여 연약층(5) 내로 침강시켜 주면서 완성 구축하도록 한 것이고, 그외 침강과정에서의 발란스 유지방법 및 마무리 공정과정은 본 발명과 동일하게 이루어진다.Figure 2 shows a second embodiment of the present invention which is almost similar to the first embodiment, which can be carried out when the site area of a building is rather large or when there is no other building in an adjacent site. ) Excavate and install the basement layer (A) of a predetermined structure inside, but on the ground by installing the means of the pulley (7) and the rubbing means of the curing panel (9) in the state of repeating the construction of the basement layer continuously and soft layer (5) The sedimentation process is completed and completed, and the balance maintaining method and the finishing process in the sedimentation process are made in the same manner as the present invention.
이러한 본 발명의 제2실시예에는 지하층의 바닥면에 개공이 없는 폐쇄형으로 형성할 때도 공히 적용할 수있다.The second embodiment of the present invention can also be applied when forming a closed type without openings in the bottom surface of the basement layer.
다도는 지표층(1)을 수직상태로 굴착해 준 상태에서 가이드월(4)을 다수의 어스앵커(31)로 지표층(1)의 내면에 고정설치하고, 상기 가이드월(4) 상단에는 도르레(7) 등의 괘지수단을 설치해준 상태에서 전술의 본 발명과 동일한 공정과정을 순차적으로 실시하여 소정 구조의 지하층을 구축토록한 본 발명의 제3실시예를 나타낸 것으로, 이러한 본 발명의 제3실시예를 진행함에 있어서는, 가이드월(4)이 과도한 수직력을 받게되면 붕괴될 위험이 있으므로 수평 및 수직 발란스를 정교하게 유지시켜 주면서 각각의 공정과정을 실시하는 것이 바람직하다.The tea ceremony is fixed to the inner surface of the ground layer (1) with a plurality of earth anchors 31, the guide wall (4) in a state in which the ground layer (1) is excavated in a vertical state, the upper side of the guide wall (4) 7) shows a third embodiment of the present invention to build a basement layer of a predetermined structure by sequentially performing the same process as the above-described present invention in the state in which the rubbing means such as, the third embodiment of the present invention In carrying out the example, since the guide wall 4 is subject to excessive vertical force, there is a risk of collapse, and therefore it is preferable to carry out the respective process steps while maintaining the horizontal and vertical balance precisely.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1019920014526A KR960009269B1 (en) | 1992-08-12 | 1992-08-12 | Form-less style working method for underground constructions |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1019920014526A KR960009269B1 (en) | 1992-08-12 | 1992-08-12 | Form-less style working method for underground constructions |
Publications (2)
Publication Number | Publication Date |
---|---|
KR940004156A KR940004156A (en) | 1994-03-14 |
KR960009269B1 true KR960009269B1 (en) | 1996-07-16 |
Family
ID=19337898
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1019920014526A KR960009269B1 (en) | 1992-08-12 | 1992-08-12 | Form-less style working method for underground constructions |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR960009269B1 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20010067680A (en) * | 2001-03-07 | 2001-07-13 | 권이현 | Clamp-off aufban method for the facilities using earth-anchor |
-
1992
- 1992-08-12 KR KR1019920014526A patent/KR960009269B1/en not_active IP Right Cessation
Also Published As
Publication number | Publication date |
---|---|
KR940004156A (en) | 1994-03-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107542108B (en) | A kind of reverse construction method of building basement structure | |
US3184893A (en) | Contact foundation method | |
CN106013053B (en) | A kind of steel sheet pile construction method for supporting for being used to build underground garage open caisson | |
CN100473790C (en) | Tower crane foundation for construction and manufacturing method thereof | |
CN105804089A (en) | Locally-deepened supporting and protecting system used after original deep foundation pit is constructed and construction method of system | |
CN102430277B (en) | Coarse grid sunk well for physically processing waste water and construction method thereof | |
CN103912009A (en) | Quicksand high-rise residence foundation sump construction method | |
CN107964976A (en) | Steel pipe-conversion steel platform tower crane top-down construction method | |
CN112211199A (en) | Large deep foundation pit supporting construction structure and method thereof | |
CN114108649A (en) | Foundation pit reinforcing construction method for mucky soil layer | |
CN216194901U (en) | Unloading plate type retaining wall structure for large-span underground garage | |
CN107165173A (en) | A kind of foundation pit supporting system and its construction method | |
WO2004033843A2 (en) | Subterranean structures and methods for constructing subterranean structures | |
KR960009269B1 (en) | Form-less style working method for underground constructions | |
CN109024657B (en) | Construction method of super high-rise core tube deep pit edge tower crane foundation under complex conditions | |
CN113898007B (en) | Semi-inverse construction method for long-span corridor structure along street | |
AU2020100004A4 (en) | A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method | |
JP2002121754A (en) | Method for constructing underwater foundation | |
JP2588075B2 (en) | Underground building construction method | |
CN109469087A (en) | Cesspool strengthening of foundation system and its construction method in a kind of industrial premises room | |
CN114232638B (en) | Anchor supporting structure | |
CN217298946U (en) | Anchorage supporting construction | |
JPH0886117A (en) | Building installation method | |
KR102279832B1 (en) | Underground Bracket Type Aseismic Reinforcement Structure and Method | |
JP3614587B2 (en) | How to install a shaft in the groundwater under pressure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
G160 | Decision to publish patent application | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20000704 Year of fee payment: 6 |
|
LAPS | Lapse due to unpaid annual fee |