KR20240079056A KR1020220161974A KR20220161974A KR20240079056A KR 20240079056 A KR20240079056 A KR 20240079056A KR 1020220161974 A KR1020220161974 A KR 1020220161974A KR 20220161974 A KR20220161974 A KR 20220161974A KR 20240079056 A KR20240079056 A KR 20240079056A
Authority
KR
South Korea
Prior art keywords
slab
bathroom
toilet
construction
plate
Prior art date
Application number
KR1020220161974A
Other languages
Korean (ko)
Inventor
권종규
송형민
전병갑
박교훈
Original Assignee
삼성물산 주식회사
주식회사 근하기공
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 삼성물산 주식회사, 주식회사 근하기공 filed Critical 삼성물산 주식회사
Priority to KR1020220161974A priority Critical patent/KR20240079056A/en
Publication of KR20240079056A publication Critical patent/KR20240079056A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/348Structures composed of units comprising at least considerable parts of two sides of a room, e.g. box-like or cell-like units closed or in skeleton form
    • E04B1/34807Elements integrated in a skeleton
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/43Floor structures of extraordinary design; Features relating to the elastic stability; Floor structures specially designed for resting on columns only, e.g. mushroom floors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/162Connectors or means for connecting parts for reinforcements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Residential Or Office Buildings (AREA)

Abstract

본 발명은 시공층의 슬래브 양생 후에 시공층의 슬래브와 다른 높이의 화장실 슬래브 구성이 용이하고, 제작된 화장실 모듈 투입이 용이하게 되는 화장실 슬래브 구조 및 공법을 개시한다.
본 발명에 의한 화장실 슬래브 구조는 건축물의 슬래브에 직접 고정되는 프레임 플레이트와; 상기 프레임 플레이트에 의해 슬래브 중 화장실 시공 위치에 형성되는 투입공간부와; 상층의 투입공간부를 통해 직접 투입되어 화장실 시공층의 프레임 플레이트에 고정되는 화장실용 PC플레이트가; 구성된 것이다.
이에 따라 본 발명은 슬래브의 화장실 시공 위치에 투입공간부를 형성하면서 슬래브를 포함한 골조 공사를 계획대로 진행하고, 슬래브 양생이 완료된 층이면 언제든 슬래브의 투입공간부를 통해 화장실 시공 층까지 화장실용 PC플레이트와 화장실 모듈을 투입하여 설치시공 할 수 있게 되므로 화장실 모듈을 시공 층에 보관할 필요도 없이 화장실 시공과 골조 공사를 독립적으로 진행하여 공기를 감축시킬 수 있는 유용한 효과가 있다.
The present invention discloses a bathroom slab structure and construction method that makes it easy to construct a bathroom slab with a height different from that of the slab in the construction layer after curing the slab in the construction layer, and makes it easy to insert the manufactured bathroom module.
The bathroom slab structure according to the present invention includes a frame plate directly fixed to the slab of the building; an input space formed at a toilet construction location among the slabs by the frame plate; A PC plate for the bathroom is directly inserted through the input space on the upper floor and fixed to the frame plate of the bathroom construction floor; It is composed.
Accordingly, the present invention proceeds as planned with frame construction including the slab while forming an input space at the toilet construction location of the slab, and provides a PC plate for the toilet and a toilet to the toilet construction floor through the input space of the slab at any time on the floor where slab curing is completed. Since installation and construction can be done by inserting modules, there is a useful effect of reducing construction air by carrying out toilet construction and frame work independently without the need to store the toilet module on the construction floor.

Description

화장실 슬래브 구조 및 공법{Toilet slab structure and construction method}Toilet slab structure and construction method

본 발명은 화장실 슬래브 구조 및 공법에 관한 것으로 특히 시공층의 슬래브 양생 후에 시공층의 슬래브와 다른 높이의 화장실 슬래브 구성이 용이하고, 제작된 화장실 모듈 투입이 용이하게 되는 화장실 슬래브 구조 및 공법에 관한 것이다.The present invention relates to a bathroom slab structure and construction method, and in particular, to a bathroom slab structure and construction method that facilitates the construction of a bathroom slab with a height different from that of the slab of the construction layer after curing the slab of the construction layer, and facilitates the insertion of the manufactured bathroom module. .

주지하는 바와 같이, 종래에도 공장에서 생산된 모듈형 화장실을 건축 중인 건물의 시공층에 이송하여 설치하는 방법으로 시공하는 기술이 제안된 바 있으며, 그 대표적인 예로 대한민국 등록특허공보 제10-2271151호(발명의 명칭 : 건축물의 바닥 타설 직후 공장제작 화장실 모듈을 인양하고 설치 시기를 선택하여 설치하는 시공방법 ; 이하 '인용발명'이라 함)가 있다. 이러한 인용발명은 도1로 나타낸 바와 같이, (a) 이음 철근에 이어 벽체 철근을 설치하는 단계;As is well known, a construction technology has been proposed in the past by transporting and installing modular toilets produced in a factory to the construction floor of a building under construction, a representative example of which is Republic of Korea Patent Publication No. 10-2271151 ( Title of invention: Construction method of lifting a factory-made toilet module immediately after pouring the floor of a building and installing it by selecting the installation time; hereinafter referred to as the 'cited invention'). As shown in Figure 1, this cited invention includes the steps of (a) installing wall reinforcement following joint reinforcement;

(b) 상기 (a)단계에서 설치된 벽체 철근에 외벽 거푸집을 설치하는 단계;(b) installing an exterior wall form on the wall reinforcement installed in step (a);

(c) 화장실 모듈을 즉시 설치하는 경우 또는 설치 공간에 보관 후 설치 위치로 이동하여 추후에 설치하는 경우 중 시공 현장 상황에 맞게 어느 하나의 설치 시기에 따른 화장실 모듈을 인양하는 위치를 선택하는 단계;(c) selecting a location to lift the toilet module according to the installation time according to the construction site conditions, either immediately installing the toilet module or storing it in the installation space and moving it to the installation location and installing it later;

(d) 상기 화장실 모듈을 인양하는 위치를 선택하는 단계에서 화장실 모듈을 추후에 설치하는 경우, (b)단계에서 설치된 외벽 거푸집 사이의 화장실 모듈 설치 공간인 N층 슬래브에 화장실 모듈을 인양하는 단계;(d) If the toilet module is later installed in the step of selecting a location for lifting the toilet module, lifting the toilet module to the N-floor slab, which is the toilet module installation space between the outer wall forms installed in step (b);

(e) 상기 외벽 거푸집에 대응하여, 내벽 거푸집을 설치하는 단계;(e) installing an inner wall formwork in response to the outer wall formwork;

(f) 상기 내벽 거푸집 설치 후 슬래브 철근을 설치하는 단계;(f) installing slab reinforcement after installing the inner wall formwork;

(g) 상기 외벽 거푸집과 내벽 거푸집이 설치된 위치에 콘크리트를 타설하는 단계;(g) pouring concrete at the location where the outer wall form and the inner wall form are installed;

(h) 상기 (g)단계에서 타설된 콘크리트를 양생하고 거푸집을 해제하는 단계;(h) curing the concrete poured in step (g) and releasing the form;

(i) 상기 화장실 모듈 설치 공간에서 화장실 모듈 설치 위치로 화장실 모듈을 이동 및 설치하는 단계를 포함하며;(i) including moving and installing the toilet module from the toilet module installation space to the toilet module installation location;

상기 (h)단계 이후에 (a)단계 내지 (h) 단계를 반복적으로 진행되도록 하여, N+1 층 슬래브에 화장실 모듈을 인양하고, 복수의 층에 적층 한 후 (i)단계로 진행되도록 하여, 화장실 모듈을 이동 및 설치하는 시기를 선택할 수 있는 것을 특징으로 하는 공장제작 화장실 모듈을 인양 및 설치하는 시공방법이다.After step (h), steps (a) to (h) are repeatedly performed to lift the toilet module to the N+1 floor slab, stacked on multiple layers, and then proceed to step (i). , a construction method for lifting and installing a factory-made toilet module, characterized in that the timing of moving and installing the toilet module can be selected.

이에 따라 인용발명은 건축물의 바닥(슬래브;Slab) 타설 후 화장실 모듈을 인양하여 즉시 설치하거나, 인양하여 설치 공간에 보관 후 설치 위치로 이동하여 설치할 수 있어, 건축물의 공사 현장 상황에 맞게 선택적으로 설치 시기를 조절할 수 있게 되는 효과가 있으나 층고와 높이가 같으면서 부피가 매우 큰 고 중량체인 화장실 모듈을 설치 공간에 보관하는 것은 해당 층의 내부 공사에 지장을 초래할 뿐만 아니라 기둥과 내벽 등의 간섭이 있을 수 있어서 골조가 완성된 해당 층에서 화장실 모듈을 설치 위치로 수평 이동시키기는 것은 많은 문제점이 있다.Accordingly, the cited invention can lift the toilet module and install it immediately after pouring the floor (slab) of the building, or lift it and store it in the installation space and then move it to the installation location and install it selectively according to the construction site conditions of the building. Although it has the effect of being able to control the timing, storing the toilet module, which is a very heavy and bulky toilet module with the same height as the floor height, in the installation space not only interferes with the internal construction of the floor, but can also cause interference with pillars and internal walls. Therefore, there are many problems in horizontally moving the toilet module to the installation location on the floor where the frame is completed.

더욱이 화장실 모듈을 인양하여 즉시 설치하는 경우는 화장실 모듈의 설치가 완료되어야 다음 층의 슬래브 시공을 시작할 수 있게 되는 것이어서 골조 공사 스케줄에 부관하게 화장실 시공을 할 수 있는 모듈형 화장실 시공의 장점이 없게 되는 것이며, 결과적으로 인용발명이 주장하는 화장실 모듈의 설치 시기 조절은 온전한 실시가 불가능하게 되는 문제점이 있다.Moreover, in the case where the toilet module is lifted and installed immediately, the installation of the toilet module must be completed before the slab construction of the next floor can begin, so there is no advantage of modular toilet construction, which allows toilet construction to be performed in accordance with the frame construction schedule. As a result, there is a problem in that it is impossible to fully implement the control of the installation time of the toilet module claimed by the cited invention.

대한민국 등록특허공보 제10-2271151호Republic of Korea Patent Publication No. 10-2271151

본 발명의 목적은 이러한 문제점을 해결하기 위하여 건축 중인 건축물의 골조 공사 계획과 독립적으로 화장실 시공이 가능하게 되는 화장실 슬래브 구조 및 공법을 제공함에 있다.The purpose of the present invention is to provide a toilet slab structure and construction method that enables toilet construction independent of the structural construction plan of the building under construction in order to solve these problems.

또한 본 발명은 건축물의 슬래브 양생 후에 화장실 시공층의 슬래브와 다른 높이의 화장실 슬래브 구성이 용이하게 되는 화장실 슬래브 구조 및 공법을 제공함에 있다.In addition, the present invention provides a bathroom slab structure and construction method that facilitates the construction of a bathroom slab with a height different from that of the slab on the bathroom construction floor after curing the slab of the building.

이러한 목적을 달성하기 위하여 본 발명에 의한 화장실 슬래브 공법은 건축물의 슬래브 골조 공정 중 루프형의 프레임 플레이트가 설치되어 화장실 시공 위치에 투입공간부가 형성되는 투입공간부 형성 단계와,In order to achieve this purpose, the bathroom slab construction method according to the present invention includes an input space forming step in which a loop-type frame plate is installed during the slab framing process of a building and an input space is formed at the toilet construction location;

상기 건출물의 골조 공정이 진행되면서 상기 투입공간부 형성 단계가 반복되어 층마다 화장실 시공 위치에 투입공간부가 형성되며,As the framing process of the building progresses, the input space forming step is repeated to form an input space at the toilet construction location for each floor,

슬래브 양생 후 상층의 투입공간부를 통해 화장실 시공층까지 화장실용 PC플레이트가 투입되어 화장실 시공층의 투입공간부에 상기 화장실용 PC플레이트가 설치되는 화장실 슬래브 설치 단계와,After curing the slab, the toilet slab installation step is injected into the toilet construction layer through the input space of the upper floor, and the toilet PC plate is installed in the input space of the toilet construction layer;

상기 화장실 슬래브 설치 단계에서 설치된 화장실용 PC플레이트에 상층의 투입공간부를 통과하여 투입된 화장실 모듈이 설치되는 화장실 모듈 설치 단계가 구성될 수 있고,A toilet module installation step may be configured in which a toilet module inserted through the upper input space part is installed on the toilet PC plate installed in the toilet slab installation step,

건축물의 슬래브에 직접 고정되는 프레임 플레이트와; 상기 프레임 플레이트에 의해 슬래브 중 화장실 시공 위치에 형성되는 투입공간부와; 상층의 투입공간부를 통해 직접 투입되어 화장실 시공층의 프레임 플레이트에 고정되는 화장실용 PC플레이트가; 구성된 화장실 슬래브 구조를 제공하여서 된 것이다.A frame plate that is directly fixed to the slab of the building; an input space formed at a toilet construction location among the slabs by the frame plate; A PC plate for the bathroom is directly inserted through the input space on the upper floor and fixed to the frame plate of the bathroom construction floor; This was achieved by providing a structured toilet slab structure.

상기 프레임 플레이트는 슬래브의 슬래브철근에 직접 고정되는 슬래브부와 벽체에 설치되는 벽체부 중 적어도 어느 하나로 루프를 형성하는 것이고, 상기 화장실용 PC플레이트는 프레임 플레이트의 슬래브부에 고정되는 슬래브연결부와, 프레임 플레이트의 벽체부 구성 시 상기 벽체부에 고정되는 벽체연결부가 구성된 것이다.The frame plate forms a loop with at least one of a slab part directly fixed to the slab reinforcement of the slab and a wall part installed on the wall, and the toilet PC plate includes a slab connection part fixed to the slab part of the frame plate, and a frame When constructing the wall portion of the plate, a wall connection portion is formed that is fixed to the wall portion.

이와 같이 하여 본 발명은 슬래브의 화장실 시공 위치에 투입공간부를 형성하면서 슬래브를 포함한 골조 공사를 계획대로 진행하고, 슬래브 양생이 완료된 층이면 언제든 상층들에 형성된 슬래브의 투입공간부들을 통해 화장실의 시공 층까지 화장실용 PC플레이트와 화장실 모듈을 투입하여 설치시공 할 수 있게 되므로 화장실 모듈을 시공 층에 보관할 필요도 없이 화장실 시공과 골조 공사를 독립적으로 진행하여 공기를 감축시킬 수 있는 유용한 효과가 있다.In this way, the present invention proceeds as planned with the construction of the frame including the slab while forming an input space at the toilet construction location of the slab, and whenever the slab curing is completed, the construction layer of the toilet is formed through the input space of the slab formed on the upper floors. Since installation and construction can be done by inserting the PC plate and toilet module for the toilet, there is a useful effect of reducing construction air by carrying out toilet construction and frame work independently without the need to store the toilet module on the construction floor.

또한 본 발명은 건축물의 슬래브 양생 이후 화장실 시공 시에 미리 생산된 화장실용 PC플레이트를 상층의 투입공간부를 통해 투입하여 화장실 시공층의 투입공간부에 설치하므로 건축물의 슬래브 공사를 위한 거푸집 설계 및 시공할 때 화장실 단차를 고려할 필요가 없게 되어 건축물의 슬래브 시공이 간소화될 수 있으며, 다양한 단차가 적용되어 생산되는 화장실용 PC플레이트의 사용이 가능하게 되고, 화장실용 PC플레이트의 위치 미세 조정이 가능하게 됨에 따라 건축물의 슬래브 양생 후에 화장실 시공층의 슬래브와 다른 높이의 화장실 슬래브 구성이 용이하게 되는 유용한 효과가 있다.In addition, in the present invention, when constructing a toilet after curing the slab of a building, the pre-produced PC plate for the toilet is inserted through the input space of the upper floor and installed in the input space of the toilet construction layer, so that it is possible to design and construct the form for the slab construction of the building. As there is no need to consider the toilet level difference, the slab construction of the building can be simplified, and it becomes possible to use PC plates for toilets produced with various level differences, and fine adjustment of the position of the PC plate for toilets becomes possible. After curing the slab of a building, there is a useful effect of making it easier to construct a bathroom slab of a different height from the slab on the bathroom construction floor.

도1은 인용발명의 구성을 나타내는 공장제작 화장실 모듈을 인양 및 설치하는 시공방법의 흐름도.
도2는 본 발명에 의한 화장실 슬래브 구조 및 공법의 구체적인 실시예의 프레임 플레이트 구성을 나타낸 사시도.
도3은 본 발명에 의한 화장실 슬래브 구조 및 공법의 구체적인 실시예의 화장실용 PC플레이트 구성을 나타낸 사시도.
도4는 본 발명에 의한 화장실 슬래브 구조 및 공법의 구체적인 실시예의 전체적인 구성을 나타내는 측단면도.
도5는 본 발명에 의한 화장실 슬래브 구조 및 공법의 구체적인 실시예의 전체적인 구성을 나타내도록 프레임 플레이트와 PC플레이트가 조립된 사시도.
도6은 본 발명에 의한 화장실 슬래브 구조 및 공법의 구체적인 실시예가 적용된 화장실 바닥의 정면 투영도.
도7은 본 발명에 의한 화장실 슬래브 구조 및 공법의 구체적인 실시예를 설명하는 설명도.
Figure 1 is a flow chart of a construction method for lifting and installing a factory-made toilet module showing the configuration of the cited invention.
Figure 2 is a perspective view showing the frame plate configuration of a specific embodiment of the bathroom slab structure and construction method according to the present invention.
Figure 3 is a perspective view showing the configuration of a PC plate for a bathroom in a specific embodiment of the bathroom slab structure and construction method according to the present invention.
Figure 4 is a side cross-sectional view showing the overall configuration of a specific embodiment of the bathroom slab structure and construction method according to the present invention.
Figure 5 is a perspective view of a frame plate and a PC plate assembled to show the overall configuration of a specific embodiment of the bathroom slab structure and construction method according to the present invention.
Figure 6 is a front projection of a bathroom floor to which a specific embodiment of the bathroom slab structure and construction method according to the present invention is applied.
Figure 7 is an explanatory diagram illustrating a specific embodiment of the bathroom slab structure and construction method according to the present invention.

이러한 본 발명을 첨부된 도면을 참조하여 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 상세히 설명하면 다음과 같다.With reference to the accompanying drawings, embodiments of the present invention will be described in detail so that those skilled in the art can easily carry out the present invention.

본 발명에 의한 화장실 슬래브 구조 및 공법의 구체적인 실시예의 전체적인 구성을 도 2 내지 도 5로 도시하였다.The overall configuration of a specific example of the bathroom slab structure and construction method according to the present invention is shown in Figures 2 to 5.

이에서 볼 수 있는 바와 같이, 본 발명에 의한 화장실 슬래브(110) 구조는 건축물의 슬래브(110) 형성 시 슬래브(110)에 직접 고정되는 프레임 플레이트(200)와,As can be seen from this, the structure of the bathroom slab 110 according to the present invention includes a frame plate 200 directly fixed to the slab 110 when forming the slab 110 of a building,

상기 프레임 플레이트(200)에 의해 슬래브(110) 중 화장실 시공 위치에 형성되는 투입공간부(112)와,An input space 112 formed at the toilet construction location among the slabs 110 by the frame plate 200,

상층의 투입공간부(112)를 통해 직접 투입되어 화장실 시공층의 프레임 플레이트(200)에 고정되는 공장에서 미리 제작된 프리캐스트콘크리트(PC:Precast Concrete) 플레이트로 된 화장실용 PC플레이트(300)가 구성될 수 있다.The PC plate (300) for the bathroom is made of precast concrete (PC) plate manufactured in advance at the factory, which is directly inserted through the input space (112) on the upper floor and fixed to the frame plate (200) of the bathroom construction floor. It can be configured.

이를 각 구성요소별로 더욱 상세하게 설명하면, 상기 투입공간부(112)는 도2와 도7로 예시한 바와 같이, 슬래브(110) 중 화장실 시공 위치에 형성되는 것이며, 대부분 매 층에 화장실이 설치되므로 이러한 투입공간부(112)는 매 층에 반복적으로 형성될 수 있고, 상층의 투입공간부(112)는 화장실모듈(400)이 인양되는 통로가 될 수 있다.To explain this in more detail for each component, the input space 112 is formed at the toilet construction location in the slab 110, as illustrated in Figures 2 and 7, and in most cases, a toilet is installed on every floor. Therefore, this input space 112 can be formed repeatedly on every floor, and the input space 112 on the upper floor can be a passage through which the toilet module 400 is lifted.

또한 상기 프레임 플레이트(200)는 도2에서 보인 바와 같이, 슬래브(110)에 투입공간부(112)를 형성할 수 있도록 슬래브(110)의 슬래브철근(111)에 직접 고정되는 슬래브부(210) 다수개가 서로 이어져 루프를 형성하는 것일 수 있고, 하나의 슬래브부(210)가 루프형태로 형성된 것일 수 있으며, 상기 슬래브부(210)는 슬래브(110)와 일체화되도록 슬래브(110)방향으로 돌출된 매립부(211)와, 화장실용 PC플레이트(300)가 지지(支持)되면서 결합될 수 있는 투입공간부(112) 방향으로 돌출된 슬래브커플러(212)가 구성될 수 있다.In addition, as shown in Figure 2, the frame plate 200 is a slab portion 210 that is directly fixed to the slab reinforcement 111 of the slab 110 so as to form an input space 112 in the slab 110. A plurality of them may be connected to each other to form a loop, and one slab part 210 may be formed in a loop shape, and the slab part 210 protrudes in the direction of the slab 110 so as to be integrated with the slab 110. A slab coupler 212 protruding in the direction of the input space 112, which can be coupled while supporting the embedded part 211 and the toilet PC plate 300, may be configured.

여기에서 상기 매립부(211)는 슬래브철근(111)에 연결될 수 있고, 건축물의 슬래브(110) 형성 시 슬래브(110)에 내장되어 슬래브(110)와 프레임 플레이트(200)를 일체화시키며, 추후 설치되는 화장실용 PC플레이트(300)와 화장실 모듈(400)의 중량을 슬래브(110)에 고르게 분산하여 지지하도록 하는 것이다.Here, the embedded portion 211 may be connected to the slab reinforcing bar 111, and is embedded in the slab 110 when forming the slab 110 of a building to integrate the slab 110 and the frame plate 200 and be installed later. The weight of the toilet PC plate 300 and the toilet module 400 is evenly distributed and supported on the slab 110.

또한 이러한 프레임 플레이트(200)는 화장실의 설치 위치에 따라 구성이 달리 될 수 있어서, 벽체(120)가 있는 슬래브(110)의 가장자리 부분에 화장실 설치 위치가 된다면 벽체(120)에 인접되는 프레임 플레이트(200)의 부분은 슬래브부(210) 대신 벽체커플러(222)와 함께 벽체(120)에 매립되는 벽체부(220)가 구성되어 루프를 형성할 수 있으며, 이러한 루프는 다각형 루프 또는 곡선 루프일 수 있다.In addition, this frame plate 200 may have a different configuration depending on the installation location of the toilet, so if the toilet is installed at the edge of the slab 110 where the wall 120 is located, the frame plate adjacent to the wall 120 ( The portion of 200) may be composed of a wall portion 220 embedded in the wall 120 together with a wall coupler 222 instead of the slab portion 210 to form a loop, and this loop may be a polygonal loop or a curved loop. there is.

여기에서 상기 벽체부(220)는 일측이 벽체(120)에 매립될 수 있도록 벽체(120) 형성을 위한 내부폼 설치 시 내부폼이 지지 및 고정되는 폼거치부(221)가 구성될 수 있으며, 상기 폼거치부(221)는 벽체부(220)의 매립을 위해 투입공간부(112) 측에서 내부폼을 설치할 수 있도록 벽체부(220)에서 투입공간부(112) 방향으로 돌출된 것일 수 있다.Here, the wall portion 220 may be configured with a foam holder 221 that supports and fixes the inner foam when installing the inner foam to form the wall 120 so that one side can be embedded in the wall 120, The foam mounting portion 221 may be protruding from the wall portion 220 toward the input space 112 so that the inner foam can be installed from the input space 112 side for embedding in the wall portion 220. .

또한 상기 화장실용 PC플레이트(300)는 도3에서 예시한 바와 같이, 건축물 슬래브(110)의 상면보다 낮은 높이의 단차가 형성되도록 하며, 프레임 플레이트(200)의 슬래브부(210)에 고정되는 슬래브연결부(310)와, 상기 벽체부(220)의 벽체커플러(222)에 지지(支持)되어 결합되는 지지결합부(322)를 구비한 벽체연결부(320)가 구성될 수 있다. 이러한 화장실용 PC플레이트(300) 역시 화장실 설치 위치가 슬래브(110)의 중간이면 슬래브연결부(310)만으로 구성될 수 있고, 슬래브(110)의 가장자리나, 모퉁이 부분과 같이 벽체(120)가 인접된 부분에 결합되는 화장실용 PC플레이트(300)의 부분에는 슬래브연결부(310) 대신에 벽체연결부(320)가 구성될 수 있는 것이다.In addition, as illustrated in FIG. 3, the toilet PC plate 300 forms a height difference lower than the upper surface of the building slab 110, and is a slab fixed to the slab portion 210 of the frame plate 200. The wall connection part 320 may be configured to include a connection part 310 and a support coupling part 322 that is supported and coupled to the wall coupler 222 of the wall part 220. This PC plate 300 for a toilet can also be composed of only the slab connection part 310 if the toilet installation location is in the middle of the slab 110, and the wall 120 is adjacent to the edge or corner of the slab 110. The portion of the bathroom PC plate 300 that is coupled to the portion may be provided with a wall connection portion 320 instead of the slab connection portion 310.

또한 상기 화장실용 PC플레이트(300)는 필요에 따라 다양한 단차 또는 화장실 바닥 레벨을 가질 수 있도록 미리 생산공장 등에서 설계된 크기와 규격으로 생산될 수 있고, 타워크레인 등을 통해 인양될 수 있도록 인양구(340)를 구비할 수 있으며, 이러한 화장실용 PC플레이트(300)가 타워크레인 등과 인양구(340)를 통해 연결되어 최상층의 투입공간부(112)를 통해 화장실이 설치되는 화장실 시공층의 투입공간부(112)까지 상층의 투입공간부(112)들을 모두 통과하면서 인양되어 화장실 시공층의 투입공간부(112)를 막도록 설치되는 것이고, 도4 내지 도6으로 나타낸 바와 같이, 슬래브연결부(310)의 커플링결합부(311)는 화장실용 PC플레이트(300) 내부의 플레이트철근(330)에 고정되며, 벽체연결부(320)의 지지결합부(322)도 화장실용 PC플레이트(300) 내부의 플레이트철근(330)에 고정되는 것이 바람직하다.In addition, the PC plate 300 for the bathroom can be produced in a size and standard designed in advance at a production factory so that it can have various steps or bathroom floor levels as needed, and has a lifting port (340) so that it can be lifted through a tower crane, etc. ) can be provided, and the toilet PC plate 300 is connected to a tower crane, etc. through the lifting port 340, and the input space part of the toilet construction floor where the toilet is installed through the input space part 112 on the top floor ( It is lifted while passing through all the input spaces 112 of the upper floor up to 112) and is installed to block the input space 112 of the toilet construction floor. As shown in Figures 4 to 6, the slab connection part 310 The coupling joint 311 is fixed to the plate reinforcing bar 330 inside the PC plate 300 for the bathroom, and the support coupling portion 322 of the wall connection portion 320 is also fixed to the plate reinforcing bar inside the PC plate 300 for the restroom. It is preferable to be fixed at (330).

여기에서 벽체연결부(320)의 지지결합부(322)는 벽체(120)에 매립된 프레임 플레이트(200)의 벽체부(220)에 구성되어 투입공간부(112)로 돌출된 벽체커플러(222)가 삽입될 수 있는 것이며, 이러한 벽체커플러(222)에 지지결합부(322)가 연결된 상태로 고정시킬 수 있는 볼트 등의 고정구의 삽입을 위해 화장실용 PC플레이트(300)는 지지결합부(322)의 내측과 연결되는 컵홀(321)이 형성될 수 있으며, 이러한 컵홀(321)을 통해 삽입된 고정구가 지지결합부(322)와 벽체커플러(222)를 고정시킬 수 있고, 지지결합부(322)에 삽입된 벽체커플러(222)와 화장실용 PC플레이트(300) 사이 또는 커플링결합부(311)에 삽입된 슬래브커플러(212)와 화장실용 PC플레이트(300) 사이에는 미세조정부가 설치될 수 있어서 화장실용 PC플레이트(300)의 높이를 미세조정할 수 있게 됨에 따라 건축물의 슬래브(110) 양생 후에 화장실 시공층의 슬래브(110)와 다른 높이의 화장실 슬래브(110) 구성이 용이하게 되는 것이다.Here, the support coupling portion 322 of the wall connection portion 320 is formed on the wall portion 220 of the frame plate 200 embedded in the wall 120 and is a wall coupler 222 protruding into the input space 112. can be inserted, and for the insertion of fixtures such as bolts that can be fixed to the wall coupler 222 with the support coupler 322 connected, the toilet PC plate 300 has a support coupler 322. A cup hole 321 connected to the inside may be formed, and a fixture inserted through this cup hole 321 can secure the support coupling portion 322 and the wall coupler 222, and the support coupling portion 322 A fine adjustment unit can be installed between the wall coupler 222 inserted into the wall coupler 222 and the bathroom PC plate 300 or between the slab coupler 212 inserted into the coupling joint 311 and the bathroom PC plate 300. As the height of the PC plate 300 for the bathroom can be finely adjusted, it becomes easier to construct a bathroom slab 110 of a different height from the slab 110 of the bathroom construction floor after curing the slab 110 of the building.

또한 상기 지지결합부(322)는 단면도인 도 4로 나타낸 바와 같이, 삽입된 벽체커플러(222)에 지지되는 지지력을 화장실용 PC플레이트에 분산할 수 있도록 단면이 역유자형 끝에 옆으로 돌출된 분산판이 구비된 "

Figure pat00001
"형의 통형상으로 형성될 수 있고, 이러한 지지결합부(322)와 연결된 컵홀(321)은 화장실용 PC플레이트(300)의 플레이트철근(330)과 연결되어 견고하게 프레임 플레이트(200)와 화장실용 PC플레이트(300)를 일체화 시킬 수 있게 되는 것이다.In addition, as shown in FIG. 4, which is a cross-sectional view, the support coupling portion 322 has a distribution plate protruding sideways at the end of an inverted U-shaped cross section to distribute the support force supported by the inserted wall coupler 222 to the PC plate for the bathroom. "Equipped"
Figure pat00001
It can be formed in a cylindrical shape, and the cup hole 321 connected to this support coupling portion 322 is connected to the plate reinforcing bar 330 of the PC plate 300 for the bathroom to firmly connect the frame plate 200 and the bathroom. It is possible to integrate the PC plate 300 for use.

이러한 화장실 슬래브(110) 구조를 갖는 본 발명의 화장실 슬래브(110) 공법은 건축물의 슬래브(110) 골조 공정 중 루프형의 프레임 플레이트(200)가 설치되어 화장실 시공 위치에 투입공간부(112)가 형성되는 투입공간부(112) 형성 단계와,The toilet slab (110) construction method of the present invention having such a toilet slab (110) structure is such that a loop-shaped frame plate (200) is installed during the slab (110) framing process of a building, and an input space portion (112) is provided at the toilet construction location. A step of forming the input space 112,

상기 건출물의 골조 공정이 진행되면서 상기 투입공간부(112) 형성 단계가 반복되어 층마다 화장실 시공 위치에 투입공간부(112)가 형성되며,As the framing process of the building progresses, the step of forming the input space 112 is repeated, so that the input space 112 is formed at the toilet construction location for each floor,

슬래브(110) 양생 후 상층의 투입공간부(112)를 통해 화장실 시공층까지 화장실용 PC플레이트(300)가 투입되어 화장실 시공층의 투입공간부(112)에 상기 화장실용 PC플레이트(300)가 설치되는 화장실 슬래브(110) 설치 단계와,After curing the slab (110), the toilet PC plate (300) is inserted into the toilet construction layer through the upper input space (112), and the toilet PC plate (300) is inserted into the toilet construction layer's input space (112). The installation step of the installed toilet slab (110),

상기 화장실 슬래브(110) 설치 단계에서 설치된 화장실용 PC플레이트(300)에 상층의 투입공간부(112)를 통과하여 투입된 화장실 모듈(400)이 설치되는 화장실 모듈(400) 설치 단계가 구성될 수 있다.The toilet module 400 installation step may be configured in which the toilet module 400 inserted through the upper input space 112 is installed on the toilet PC plate 300 installed in the toilet slab 110 installation step. .

이러한 본 발명의 화장실 슬래브(110) 공법은 건축물의 슬래브(110) 골조 공정 중에 프레임 플레이트(200) 설치로 복잡한 화장실 단차 구조 시공 없이 건축물의 슬래브(110) 골조 공정이 진행될 수 있어서 간소화 및 공기를 줄일 수 있게 되는 것이며, 화장실 시공 또는 설치와 상관없이 건축물의 슬래브(110) 골조 공정을 진행할 수 있게 되는 것일 뿐 아니라 이에 따라 화장실모듈(400)을 상층 슬래브(110) 시공 전에 해당층에 미리 인양하여 보관할 필요가 없이 화장실모듈(400) 설치 때에 인양하여 설치할 수 있기 때문에 다른 공정에 간섭이나 지장을 주지 않고 별도의 보관 공간을 마련하지 않아도 되는 것이며, 화장실모듈(400)에도 이동을 위한 구성들이 불필요하게 되므로 화장실모듈(400)이 간소화될 수 있는 것이다.This bathroom slab (110) construction method of the present invention allows the slab (110) framing process of a building to proceed without constructing a complex toilet step structure by installing a frame plate (200) during the slab (110) framing process of a building, thereby simplifying and reducing construction time. This not only makes it possible to proceed with the slab (110) framing process of the building regardless of toilet construction or installation, but also allows the toilet module (400) to be lifted and stored in advance on the relevant floor before constructing the upper slab (110). Since the toilet module 400 can be lifted and installed without the need for installation, there is no need to provide a separate storage space without interfering with or disrupting other processes, and the toilet module 400 also does not need any components for movement. The toilet module 400 can be simplified.

여기에서 투입공간부(112)의 사방이 모두 슬래브(110)로 되어 있는 경우 상기 화장실 슬래브(110) 설치 단계는 화장실 시공층의 슬래브(110)에 고정되는 프레임 플레이트(200)의 슬래브커플러(212)가 상기 화장실 시공층의 슬래브철근(111)에 고정되도록 설치되는 슬래브커플러(212) 설치단계와,Here, when all four sides of the input space 112 are made of slabs 110, the toilet slab 110 installation step is performed by installing the slab coupler 212 of the frame plate 200 fixed to the slab 110 of the toilet construction floor. ) is installed so that it is fixed to the slab reinforcing bar 111 of the bathroom construction layer; a slab coupler 212 installation step;

화장실용 PC플레이트(300)의 슬래브연결부(310)에 형성된 커플링결합부(311)가 상기 슬래브커플러(212) 설치단계에서 설치된 슬래브커플러(212)에 지지(支持)되는 상태로 고정되는 슬래브(110) 연결 단계와,A slab ( 110) connection step,

상기 슬래브(110) 연결 단계 후 화장실용 PC플레이트(300)와 화장실 시공층의 슬래브(110) 사이 및 고정부위가 마감되는 되메우기 단계가 구성될 수 있다.After the step of connecting the slab 110, a backfilling step may be performed in which the fixing portion and between the PC plate 300 for the bathroom and the slab 110 of the bathroom construction layer are completed.

또한 투입공간부(112)의 둘레 중 적어도 어느 하나 이상에 벽체(120)가 있는 경우 상기 화장실 슬래브(110) 설치 단계는 화장실 시공층의 슬래브(110)에 고정되는 프레임 플레이트(200)의 슬래브부(210)에 구비되는 슬래브커플러(212)가 상기 화장실 시공층의 슬래브철근(111)에 고정되도록 설치되고, 프레임 플레이트(200)의 벽체부(220)에 형성되는 벽체커플러(222)가 화장실 시공층의 시공 위치에 있는 벽체(120)의 철근에 고정되도록 설치되는 커플러 설치단계와,In addition, if there is a wall 120 on at least one of the perimeters of the input space 112, the toilet slab 110 installation step is performed by installing the slab portion of the frame plate 200 fixed to the slab 110 of the toilet construction layer. The slab coupler 212 provided at (210) is installed to be fixed to the slab reinforcement 111 of the toilet construction layer, and the wall coupler 222 formed on the wall portion 220 of the frame plate 200 is used for toilet construction. A coupler installation step that is installed to be fixed to the reinforcing bar of the wall 120 at the construction location of the floor,

화장실용 PC플레이트(300)의 슬래브연결부(310)에 형성된 커플링결합부(311)가 상기 슬래브커플러(212) 설치단계에서 설치된 슬래브커플러(212)에 지지되고, 상기 화장실용 PC플레이트(300)의 벽체연결부(320)에 구성된 지지결합부(322)가 상기 벽체부(220)의 벽체커플러(222)에 지지되는 벽체(120) 연결 단계와,The coupling coupling portion 311 formed on the slab connection portion 310 of the PC plate 300 for a bathroom is supported on the slab coupler 212 installed in the installation step of the slab coupler 212, and the PC plate 300 for a bathroom is supported. A wall 120 connecting step in which the support coupling portion 322 formed in the wall connecting portion 320 is supported by the wall coupler 222 of the wall portion 220,

상기 커플링결합부(311)와 지지결합부(322)에 각각 내장되는 미세조정부가 슬래브커플러(212)와 커플링결합부(311) 사이 및 벽체커플러(222)와 지지결합부(322) 사이를 각각 이격시키면서 화장실용 PC플레이트(300)의 바닥 레벨을 조정하고, 화장실용 PC플레이트(300)가 화장실 시공층의 슬래브(110) 및 벽체(120)에 고정되는 레벨 조정단계와,The fine adjustment unit built into each of the coupling coupler 311 and the support coupler 322 is between the slab coupler 212 and the coupling coupler 311 and between the wall coupler 222 and the support coupler 322. A level adjustment step in which the floor level of the toilet PC plate 300 is adjusted while spaced apart from each other, and the toilet PC plate 300 is fixed to the slab 110 and the wall 120 of the toilet construction floor,

상기 벽체(120) 연결 단계 후 화장실용 PC플레이트(300)와 화장실 시공층의 슬래브(110) 사이, 화장실용 PC플레이트(300)와 벽체(120) 사이 및 고정부위가 마감되는 되메우기 단계가 구성될 수 있다.After the wall 120 connection step, a backfilling step will be performed in which the restroom PC plate 300 and the slab 110 of the restroom construction floor, the restroom PC plate 300 and the wall 120, and the fixing portion are finished. You can.

이러한 본 발명은 슬래브(110)의 화장실 시공 위치에 투입공간부(112)를 형성하면서 슬래브(110)를 포함한 골조 공사를 계획대로 진행하고, 슬래브(110) 양생이 완료된 층이면 언제든 슬래브(110)의 투입공간부(112)를 통해 화장실의 시공 층까지 화장실용 PC플레이트(300)와 화장실모듈(400)을 수직으로 직접 투입하여 설치시공 할 수 있게 되므로 화장실모듈(400)을 시공 층에 보관할 필요도 없이 화장실 시공과 골조 공사를 독립적으로 진행하여 공기를 감축시킬 수 있게 되는 것이며,In this invention, the construction of the frame including the slab 110 proceeds as planned while forming the input space 112 at the toilet construction location of the slab 110, and the slab 110 can be installed at any time on the floor where curing of the slab 110 is completed. Installation and construction can be done by directly inserting the toilet PC plate 300 and the toilet module 400 vertically into the construction floor of the toilet through the input space 112 of the toilet, so it is necessary to store the toilet module 400 on the construction floor. By carrying out toilet construction and framing work independently, it is possible to reduce air emissions.

또한 건축물의 슬래브(110) 양생 이후 화장실 시공 시에 화장실용 PC플레이트(300)를 투입공간부(112)에 설치하므로 건축물의 슬래브(110) 공사를 위한 거푸집 설계 및 설치할 때 화장실의 단차를 고려할 필요가 없게 되어 건축물의 슬래브(110) 시공이 간소화 될 수 있으며, 다양한 단차가 적용된 화장실용 PC플레이트(300)의 사용이 가능하게 되고, 화장실용 PC플레이트(300)의 위치 미세 조정이 가능하게 됨에 따라 건축물의 슬래브(110) 양생 후에 화장실 시공층의 슬래브(110)와 다른 높이의 화장실 슬래브(110) 구성이 용이하게 되는 것이다.In addition, when constructing a toilet after curing the slab (110) of the building, the PC plate (300) for the toilet is installed in the input space (112), so it is necessary to consider the level difference in the toilet when designing and installing the form for constructing the slab (110) of the building. As there is no more, construction of the slab 110 of the building can be simplified, the use of the PC plate 300 for the bathroom with various steps is possible, and fine adjustment of the position of the PC plate 300 for the bathroom becomes possible. After curing the slab 110 of the building, it becomes easy to construct a bathroom slab 110 of a different height from the slab 110 of the bathroom construction floor.

이상에서, 본 발명에 대한 기술사상을 첨부도면과 함께 서술하였지만, 이는 본 발명의 가장 양호한 실시예를 예시적으로 설명한 것이지 본 발명을 한정하는 것이 아니고, 이 기술분야의 통상의 지식을 가진 자이면 누구나 본 발명의 기술사상의 범위를 이탈하지 않는 범위 내에서 치수 및 모양 그리고 구조 등의 다양한 변형 및 모방할 수 있음은 명백한 사실이며 이러한 변형 및 모방은 본 발명의 기술 사상의 범위에 포함된다.In the above, the technical idea of the present invention has been described along with the accompanying drawings, but this is an illustrative description of the best embodiment of the present invention and does not limit the present invention, and any person skilled in the art will It is a clear fact that anyone can make various modifications and imitations of dimensions, shapes, and structures without departing from the scope of the technical idea of the present invention, and such modifications and imitations are included in the scope of the technical idea of the present invention.

110: 슬래브 111: 슬래브철근 112: 투입공간부
120: 벽체 200: 프레임 플레이트 210: 슬래브부
211: 매립부 212: 슬래브커플러 220: 벽체부
221: 폼거치부 222: 벽체커플러 300: PC플레이트
310: 슬래브연결부 311: 커플링결합부 320: 벽체연결부
321: 컵홀 322: 지지결합부 330: 플레이트철근
340: 인양구 400: 화장실 모듈
110: Slab 111: Slab rebar 112: Input space part
120: Wall 200: Frame plate 210: Slab part
211: buried part 212: slab coupler 220: wall part
221: Foam holder 222: Wall coupler 300: PC plate
310: Slab connection part 311: Coupling connection part 320: Wall connection part
321: Cup hole 322: Support joint 330: Plate rebar
340: Salvage area 400: Toilet module

Claims (6)

건축물의 슬래브 골조 공정 중 프레임 플레이트가 설치되어 화장실 시공 위치에 투입공간부가 형성되는 투입공간부 형성 단계와,
상기 건출물의 골조 공정이 진행되면서 상기 투입공간부 형성 단계가 반복되어 층마다 화장실 시공 위치에 투입공간부가 형성되며,
슬래브 양생 후 상층의 투입공간부를 통해 화장실 시공층까지 화장실용 PC플레이트가 투입되어 화장실 시공층의 투입공간부에 상기 화장실용 PC플레이트가 설치되는 화장실 슬래브 설치 단계와,
상기 화장실 슬래브 설치 단계에서 설치된 화장실용 PC플레이트에 상층의 투입공간부를 통과하여 투입된 화장실 모듈이 설치되는 화장실 모듈 설치 단계가 구성됨을 특징으로 하는 화장실 슬래브 공법.
During the slab framing process of a building, a frame plate is installed and an input space is formed at the toilet construction location;
As the framing process of the building progresses, the input space forming step is repeated to form an input space at the toilet construction location for each floor,
After curing the slab, the toilet slab installation step is injected into the toilet construction layer through the input space of the upper floor, and the toilet PC plate is installed in the input space of the toilet construction layer;
A toilet slab construction method comprising a toilet module installation step in which a toilet module inserted through the upper input space part is installed on the toilet PC plate installed in the toilet slab installation step.
제 1 항에 있어서,
상기 화장실 슬래브 설치 단계는 화장실 시공층의 슬래브에 고정되는 프레임 플레이트의 슬래브커플러가 상기 화장실 시공층의 슬래브철근에 고정되도록 설치되는 슬래브커플러 설치단계와,
화장실용 PC플레이트의 슬래브연결부에 형성된 커플링결합부가 상기 슬래브커플러 설치단계에서 설치된 슬래브커플러에 지지되는 상태로 고정되는 슬래브 연결 단계와,
상기 슬래브 연결 단계 후 화장실용 PC플레이트와 화장실 시공층의 슬래브 사이 및 고정부위가 마감되는 되메우기 단계가 구성됨을 특징으로 하는 화장실 슬래브 공법.
According to claim 1,
The bathroom slab installation step includes a slab coupler installation step in which the slab coupler of the frame plate fixed to the slab of the bathroom construction layer is installed so that it is fixed to the slab rebar of the bathroom construction layer,
A slab connection step in which the coupling joint formed at the slab connection portion of the PC plate for a bathroom is fixed in a supported state by the slab coupler installed in the slab coupler installation step,
A bathroom slab construction method, characterized in that after the slab connection step, a backfilling step is performed in which the fixing portion and between the PC plate for the bathroom and the slab of the bathroom construction layer are finished.
제 1 항에 있어서,
상기 화장실 슬래브 설치 단계는 화장실 시공층의 슬래브에 고정되는 프레임 플레이트의 슬래브부에 구비되는 슬래브커플러가 상기 화장실 시공층의 슬래브철근에 고정되도록 설치되고, 프레임 플레이트의 벽체부에 형성되는 벽체커플러가 화장실 시공층의 시공위치에 있는 벽체의 철근에 고정되도록 설치되는 커플러 설치단계와,
화장실용 PC플레이트의 슬래브연결부에 형성된 커플링결합부가 상기 슬래브커플러 설치단계에서 설치된 슬래브커플러에 지지되고, 상기 화장실용 PC플레이트의 벽체연결부에 구성된 지지결합부가 상기 벽체부의 벽체커플러에 지지되는 벽체 연결 단계와,
상기 커플링결합부와 지지결합부에 각각 내장되는 미세조정부가 슬래브커플러와 커플링결합부 사이 및 벽체커플러와 지지결합부 사이를 각각 이격시키면서 화장실용 PC플레이트의 바닥 레벨을 조정하고, 화장실용 PC플레이트가 화장실 시공층의 슬래브 및 벽체에 고정되는 레벨 조정단계와,
상기 벽체 연결 단계 후 화장실용 PC플레이트와 화장실 시공층의 슬래브 사이, 화장실용 PC플레이트와 벽체 사이 및 고정부위가 마감되는 되메우기 단계가 구성됨을 특징으로 하는 화장실 슬래브 공법.
According to claim 1,
In the bathroom slab installation step, the slab coupler provided on the slab portion of the frame plate fixed to the slab of the bathroom construction layer is installed so that it is fixed to the slab rebar of the bathroom construction layer, and the wall coupler formed on the wall portion of the frame plate is installed in the bathroom. A coupler installation step that is installed to be fixed to the reinforcing bar of the wall at the construction location of the construction floor,
A wall connection step in which the coupling joint formed in the slab connection portion of the PC plate for a bathroom is supported by the slab coupler installed in the slab coupler installation step, and the support joint formed in the wall connection portion of the PC plate for a bathroom is supported by the wall coupler of the wall portion. and,
The fine adjustment unit, which is built into the coupling joint and the support joint, respectively, adjusts the floor level of the PC plate for the bathroom while spaced apart between the slab coupler and the coupling joint and between the wall coupler and the support joint, respectively. A level adjustment step in which the plate is fixed to the slab and wall of the bathroom construction floor,
A bathroom slab construction method, characterized in that after the wall connection step, a backfilling step is completed between the PC plate for the bathroom and the slab of the bathroom construction floor, between the PC plate for the bathroom and the wall, and the fixing portion.
건축물의 슬래브에 직접 고정되는 프레임 플레이트와,
상기 프레임 플레이트에 의해 슬래브 중 화장실 시공 위치에 형성되는 투입공간부와,
상층의 투입공간부를 통해 직접 투입되어 화장실 시공층의 프레임 플레이트에 고정되는 화장실용 PC플레이트가 구성됨을 특징으로 하는 화장실 슬래브 구조.
A frame plate that is directly fixed to the slab of the building,
An input space formed at the toilet construction location in the slab by the frame plate,
A bathroom slab structure characterized in that it consists of a PC plate for a bathroom that is directly inserted through the input space on the upper floor and fixed to the frame plate of the bathroom construction layer.
제 4 항에 있어서,
상기 프레임 플레이트는 슬래브의 슬래브철근에 직접 고정되는 슬래브부와, 벽체에 설치되는 벽체부 중 적어도 어느 하나로 루프를 형성하는 것임을 특징으로 하는 화장실 슬래브 구조.
According to claim 4,
A bathroom slab structure, characterized in that the frame plate forms a loop with at least one of a slab portion directly fixed to the slab reinforcement of the slab and a wall portion installed on the wall.
제 4 항에 있어서,
상기 화장실용 PC플레이트는 슬래브보다 높이가 낮은 단차가 형성되도록 하며, 프레임 플레이트의 슬래브부에 고정되는 슬래브연결부와, 프레임 플레이트의 벽체부 구성 시 상기 벽체부에 고정되는 벽체연결부가 구성된 것임을 특징으로 하는 화장실 슬래브 구조.
According to claim 4,
The PC plate for the bathroom is configured to form a step lower in height than the slab, and is composed of a slab connection part fixed to the slab part of the frame plate, and a wall connection part fixed to the wall part when constructing the wall part of the frame plate. Toilet slab structure.
KR1020220161974A 2022-11-28 2022-11-28 Toilet slab structure and construction method KR20240079056A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020220161974A KR20240079056A (en) 2022-11-28 2022-11-28 Toilet slab structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020220161974A KR20240079056A (en) 2022-11-28 2022-11-28 Toilet slab structure and construction method

Publications (1)

Publication Number Publication Date
KR20240079056A true KR20240079056A (en) 2024-06-04

Family

ID=91466063

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020220161974A KR20240079056A (en) 2022-11-28 2022-11-28 Toilet slab structure and construction method

Country Status (1)

Country Link
KR (1) KR20240079056A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102271151B1 (en) 2020-11-13 2021-07-01 금강공업 주식회사 A Construction Method In Which A Factory Manufactured Toilet Module Is Lifted And The Installation Time Is Selected And Installed

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102271151B1 (en) 2020-11-13 2021-07-01 금강공업 주식회사 A Construction Method In Which A Factory Manufactured Toilet Module Is Lifted And The Installation Time Is Selected And Installed

Similar Documents

Publication Publication Date Title
AU727062B2 (en) Pre-cast concrete panels for construction of a building
US9371648B1 (en) Concrete building structure and method for modular construction of same
CA2741405A1 (en) Modular construction system and components and method
KR101903628B1 (en) Precast Double Wall Structure with Enhanced Seismic Performance and Construction method thereof
WO2012088588A1 (en) Modular construction system and components and method
KR102197689B1 (en) Vertical core structure horizontally assembled and construction method therewith
KR20200012263A (en) Under ground structure using column wall and construction method thereof
KR102319792B1 (en) 2-way precast pannel and structure construction method using the same
JP7411749B2 (en) How to construct a concrete building
KR20240079056A (en) Toilet slab structure and construction method
KR101908943B1 (en) RC WALL STRUCTURE FOR TOP-DOWN AND METHOD FOR CONSTRUCTING THE STRUCTUREa
JP2005016078A (en) Cast-in-place hollow concrete slab, its construction method and spacer-cum-support used therefor
KR101827381B1 (en) Multi-layer construction structure of the structure using double-wall PC and construction method thereof
JP7160357B2 (en) Method for manufacturing a structure with wall modules
KR20130022656A (en) Hybrid building construction method combining dry type and wet type
JPH08302808A (en) Connecting method of large pc wall board
KR100669198B1 (en) Wall structure unified the finish material
JP2002038641A (en) Floor slab structure
KR102297420B1 (en) Manufacturing method of a facing block using retaining wall facing block and construction method of retaining wall using the facing block
CN220928305U (en) External wallboard connection structure
KR102412128B1 (en) Precast slab using 2-way grid reinforcing member and structure construction method using the same
IL101814A (en) Method for the manufacture of building structures and buildings and prefabricated modular units for carrying out the method
KR102658475B1 (en) Precast pannel and structure construction method using the same
KR102411003B1 (en) Constructing method using assembled room-assembly and wall
KR0153719B1 (en) A precast post structure and working method of underground structure using precast post