KR20210000234A - Method for Alternate Basement Vertical Structure Construction Method in Top Down Construction Project - Google Patents

Method for Alternate Basement Vertical Structure Construction Method in Top Down Construction Project Download PDF

Info

Publication number
KR20210000234A
KR20210000234A KR1020190075320A KR20190075320A KR20210000234A KR 20210000234 A KR20210000234 A KR 20210000234A KR 1020190075320 A KR1020190075320 A KR 1020190075320A KR 20190075320 A KR20190075320 A KR 20190075320A KR 20210000234 A KR20210000234 A KR 20210000234A
Authority
KR
South Korea
Prior art keywords
basement
floor
construction
constructed
constructing
Prior art date
Application number
KR1020190075320A
Other languages
Korean (ko)
Inventor
양경옥
Original Assignee
양경옥
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 양경옥 filed Critical 양경옥
Priority to KR1020190075320A priority Critical patent/KR20210000234A/en
Publication of KR20210000234A publication Critical patent/KR20210000234A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

According to the present invention, in order to shorten a period for basement framework construction in a basement top-down method for construction, provided is a construction method wherein basement vertical members (core parts, pillars) are alternately constructed to a lower floor and then remaining vertical members are constructed at the same, thereby shortening a construction period. According to the present invention, the top-down construction method performing alternate connection includes: a first step of installing a retaining wall and constructing a basement pillar post, and then, excavating a bed for a first basement floor and constructing a first ground floor; a second step of first constructing a core part of the first basement floor to support a core part of the ground floor constructed upward while constructing a basement floor slab to a lower floor; a third step of constructing basement vertical members downward on an alternate basis floor by floor by using a bottom-up method; and a step of constructing the lowermost mat or foundation, and then, constructing basement vertical members for remaining floors at the same time or step by step by using the bottom-up method. Therefore, since a period for the construction of basement vertical members is shortened, subsequent ground framework and finishing construction can be started at an early stage, which can lead to a reduction in the entire construction period.

Description

하나 걸러 번갈아 시공되는 역타공법의 지하 수직부재 공사방법{Method for Alternate Basement Vertical Structure Construction Method in Top Down Construction Project}[Method for Alternate Basement Vertical Structure Construction Method in Top Down Construction Project}

본 발명은 건설공사 역타공법 탑다운에서의 지하 골조공사 기간을 단축하기 위한 것으로, 더욱 상세하게는 지하 수직부재를 하나 걸러 번갈아 가면서 아래로 순타로 1개층씩 시공하고 이후 매트, 동기초 시공 후에는 하나걸러 남은층의 수직부재를 동시에 또는 순차적으로 순타로 일괄 시공하는 공사방법을 제공하여 지하 수직부재 및 전체 공사기간을 단축할 수 있도록 한다.The present invention is to shorten the period of the basement framework work in the top-down of the construction work reverse punching method, and more specifically, one by one after the construction of the basement vertical member alternately down and one layer down in a suntaro, and then one after the mat and It is possible to shorten the underground vertical member and the entire construction period by providing a construction method in which vertical members of the remaining layers are simultaneously or sequentially constructed collectively.

역타공법(탑다운, Top-down)은 지하층으로 골조공사를 형성해 내려가면서 동시에 지상층 골조공사를 시공하여 공사기간을 단축하는 공법이다.The reverse drilling method (top-down, top-down) is a construction method that shortens the construction period by constructing a frame work on the ground floor while forming a frame work to the basement floor.

일반적인 지하층 역타공법의 시공순서는 흙막이와 기둥을 설치하고 각 층 터파기를 한 후 슬라브를 시공해 내려가면서, 마지막으로 최하층 기초 또는 매트(mat)를 시공하며 지하 4층 내지 8층 깊이를 갖는다.The order of construction of the general basement back-throwing method is to install soil barriers and pillars, digging each floor, and constructing slabs, and finally, constructing the lowermost foundation or mat, and having a depth of 4 to 8 floors below the ground.

지하 수직부재 중 말뚝 기둥은 공사초기에 시공되고 지상층 골조공사를 위하여 지하 1층 코어부가 시공되고 나머지 수직부재(코어월, 기둥)는 매트 타설 후 순타(아래층부터 위층으로)로 시공된다.Among the vertical members of the basement, the pile pillars are constructed at the beginning of the construction, the core of the first basement level is constructed for the construction of the ground floor, and the remaining vertical members (core walls, pillars) are constructed in a sunta (from the bottom to the top) after the mat is placed.

지하 코어월과 기둥을 아래층으로 내려가면서 시공하지 못하는 것은 위에서 아래로 코어월을 시공하는 것은 비용이 많이 들고 품질확보가 어렵기 때문이다. 또한 매트 타설전에 코어월을 많이 시공하면 PRD, RCD 파일(말뚝)에 하중이 많이 실려 다수 지상층을 시공할 수 없어 탑다운의 의미가 없어지기 때문이다.The reason why underground core walls and pillars cannot be constructed while going downstairs is that installing core walls from top to bottom is expensive and quality is difficult to secure. In addition, if a large number of core walls are installed before the mat is placed, a lot of load is placed on the PRD and RCD piles (pile), making it impossible to construct multiple ground floors, and the meaning of top-down disappears.

지상층 골조공사는 지하층과 동시에 시공되지만 기초, 매트 시공전까지 올라가는 층수와 이후 지하 수직부재의 완료시까지 올라가는 층수가 구조적으로 제한이 되어 있다. 예를 들면 기초, 매트 타설전까지는 지상 8층까지만 가능하고 지하 수직부재가 완료되기 전까지는 지상 15층까지만 가능하고 지하 수직부재가 완료된 이후에는 제한없이 옥상층까지 올라갈 수 있는 공사 제약 조건이 부여된다. The ground floor framing work is constructed at the same time as the basement floor, but the number of floors that go up before the foundation and mat construction and the number of floors that go up until the completion of the underground vertical member is structurally limited. For example, it is possible to only up to 8 floors above the ground until foundation and mats are placed, and up to 15 floors above the ground until the underground vertical member is completed, and after the underground vertical member is completed, a construction constraint is imposed that allows you to climb to the rooftop without restrictions. .

따라서 지하층 골조공사 기간이 증가하면 지상층 골조는 8층 또는 15층 까지만 시공하고 중단한 후 대기하여야 한다. 반대로 지하층 골조공사가 빨라지면 지상층 골조공사도 빨라져 전체 공사기간은 지하층 공사 속도에 크게 영향을 크게 받는다.Therefore, if the period of the basement frame construction increases, the above-ground frame construction should be constructed only up to the 8th or 15th floor and should be stopped and waited. On the contrary, if the basement floor frame work is accelerated, the ground floor frame work is also accelerated, and the entire construction period is greatly affected by the basement floor construction speed.

특히 지상층 골조는 기준층 1개층 시공에 6일 내지 7일 정도 소요되어 1개월에 4개층 이상을 시공하지만 지하층은 한 개층에 1개월 또는 그 이상이 소요되어 지하층의 공사속도가 상대적으로 느리다.In particular, the ground floor frame construction takes 6 to 7 days to construct one base layer, and four or more floors are constructed per month, but the basement layer takes one month or more for one floor, so the construction speed of the basement floor is relatively slow.

이러한 종래의 역타공법 탑다운에서의 문제점은 다음과 같다.The problems in the conventional reverse punching method top-down are as follows.

종래의 지하 시공순서는 흙막이, 말뚝, 각층 하향 터파기 및 슬라브 시공, 최하층 매트 시공, 지하 수직부재의 상향의 순타시공으로 진행된다.The conventional underground construction sequence is progressed by soil barriers, piles, digging and slab construction down each floor, mat construction at the bottom floor, and sequential construction of the underground vertical members upward.

여기서 지하 수직부재는 매트 타설 후 순타(아래층에서 위층으로 시공)로 진행되는 특징을 가진다. 지하 수직부재의 공사기간은 1개층 시공에 25일 내지 30일이 소요되고 지하 6층인 경우 5개월 내지 6개월이 소요된다.Here, the underground vertical member has a characteristic that it proceeds as a sunta (construction from the lower floor to the upper floor) after the mat is placed. The construction period of the basement vertical member takes 25 to 30 days for the construction of one floor, and 5 to 6 months for the basement 6 floor.

코어월과 기둥인 지하 수직부재는 매트 타설 후 순타(아래에서 위로)로 시공한다. 지하 수직부재가 완성된 이후 지상층이 계속 올라갈 수 있으므로 지하 수직부재는 공사기간을 결정하는 크리티컬 패스(주공정선, critical path)이다.The core wall and the underground vertical member, which is a pillar, are installed with a sunta (from bottom to top) after mat is placed. Since the ground level can continue to rise after the underground vertical member is completed, the underground vertical member is a critical path that determines the construction period.

한편 지상층 골조는 층당 싸이클이 7일 정도로 공사속도가 빠른 반면 지하층 매트 타설 시점(예들 들어 지상 8층)과 지하 수직부재 완성 시점(지상 15층)까지 올라갈 수 있는 층수가 제한되어 있어 지상 8층과 지상 15층의 변곡점에서 공사중단 및 공사대기가 발생하게 된다.On the other hand, while the construction speed of the ground floor frame is 7 days per floor, the number of floors that can be ascended to the time of placing the basement mat (for example, 8 floors above ground) and the completion of the underground vertical member (15 floors above ground) is limited. Construction suspension and construction waiting occur at the inflection point on the 15th floor above the ground.

지하 수직부재 공사 기간중에는 각 층 공사가 여유없이 연속적으로 원활하게 이루어져야 한다는 조건을 달성해야 한다. 만약 한개 층이라도 지연이 발생하는 경우, 지상층 공사는 그만큼 지연되게 된다. 따라서 지하 수직부재를 연속적으로 단기간에 원활하게 시공해야 하는 기존의 공법은 공기지연 리스크가 매우 크다.During the underground vertical member construction period, the condition that the construction of each floor should be performed continuously and smoothly with no margin should be achieved. If there is a delay in even one floor, the ground floor construction will be delayed that much. Therefore, the existing construction method in which the underground vertical member must be continuously and smoothly constructed in a short period has a very high risk of delay.

역타공법은 지하층을 시공하면서 동시에 지상층을 시공하여 공사기간을 단축하는 장점이 있다. 그러나 지하층 공사속도에 따라 지상층이 일정 층수 이상 올라갈 수 없는 구조적인 제약 조건에 따라 공기가 지하 골조공사에 크게 영향을 받고 있는 실정이다.The reverse punching method has the advantage of shortening the construction period by constructing the ground floor while constructing the basement layer. However, according to the structural constraints that the above-ground floor cannot rise more than a certain number of floors depending on the construction speed of the basement floor, the air is greatly affected by the underground frame construction.

출원번호/일자 1020110024619 (2011.03.18), 출원인 주식회사 한빛구조엔지니어링, 등록번호/일자 1012420170000 (2013.03.05), 발명의 명칭 코어내부 격자형 인방보와 우선시공되는 지상층 코어부를 이용한 지상 및 지하구조물 병행Application No./Date 1020110024619 (2011.03.18), Applicant Hanbit Structural Engineering Co., Ltd., Registration No./Date 1012420170000 (2013.03.05), Name of the invention In parallel with ground and subterranean structures using the core of the above-ground layer and the core part of the above-ground layer to be constructed first 구축공법,Construction Method, 출원번호 특1995-0003110, 출원일자 1995년02월18일, 건축구조물의 지상층 및 지하층 골조의 병행 시공방법Application No. Special 1995-0003110, filing date February 18, 1995, parallel construction method of the ground floor and basement frame of a building structure 출원번호 10-2003-0037296, 출원일자 2003년06월10일, 철근콘크리트구조와 철골철근콘크리트구조의 혼합구조를갖는 건축구조물 및 그의 동시시공방법Application No. 10-2003-0037296, Application date June 10, 2003, A building structure having a mixed structure of a reinforced concrete structure and a steel frame reinforced concrete structure, and its simultaneous construction method 출원번호 10-2011-0087835, 출원일자 2011년08월31일, 등록번호 10-1101182, 등록일자 2011년12월26일, 지하구조물의 역타공법Application number 10-2011-0087835, application date August 31, 2011, registration number 10-1101182, registration date December 26, 2011, reverse drilling method of underground structures 출원번호 10-2013-0004918, 출원일자 2013년01월16일, 등록번호 10-1426511, 등록일자 2014년07월29일, 건물의 지하구조물 축조 시 사용되는 가설 골조시스템과 이를 이용한 역타공법Application number 10-2013-0004918, application date January 16, 2013, registration number 10-1426511, registration date July 29, 2014, temporary frame system used when constructing underground structures of buildings and reverse punching method using the same

본 발명은 상기와 같은 종래 기술에 따른 문제점을 해결하기 위하여 창안된 것으로서, 역타공법에서 시간이 많이 소요되는 지하 수직부재의 공사기간을 단축하여 지상층 골조공사를 조기에 진행할 수 있도록 한다. 이에 따라 전체 공사기간을 단축하도록 한다.The present invention has been invented to solve the problems of the prior art as described above, and shortens the construction period of the underground vertical member, which takes a lot of time in the reverse punching method, so that the ground floor frame construction can be carried out early. Accordingly, the entire construction period is shortened.

상기한 목적을 달성하고 상술한 종래기술의 문제점을 해결하기 위하여, 본 발명에 따른 하나 걸러 번갈아 시공되는 지하 수직부재 공사방법은In order to achieve the above object and to solve the problems of the prior art described above, the underground vertical member construction method alternately constructed every other according to the present invention

지하 수직부재를 하나 걸러 번갈아 하향으로 1개층을 순타로 시공하고, 이후에는 잔여 수직부재를 상기 앞서 시공된 수직부재 사이로 분산하여 동시에 끼워서 시공 또는 순차로 시공한다.One floor is sequentially constructed downward by alternating every other vertical member in the basement, and after that, the remaining vertical members are distributed among the previously constructed vertical members and simultaneously sandwiched and constructed or sequentially constructed.

본 발명에 따르면 다음과 같은 효과를 기대할 수 있다.According to the present invention, the following effects can be expected.

전체 공정표상에서 다수의 지하 수직부재를 선시공하여 공사기간을 결정하는 주공정선(크리티컬 패스, Criticla path)상에서 배제하므로써 공사기간이 단축된다.The construction period is shortened by pre-installing a number of underground vertical members in the overall process schedule and excluding them from the main line (Criticla path) that determines the construction period.

지하 수직부재를 하나 걸러 시공하므로 기둥의 좌굴길이가 짧아져 보다 많은 지상층을 시공할 수 있어 전체 공사기간이 단축된다.Since every other underground vertical member is constructed, the buckling length of the column is shortened, allowing more ground floors to be constructed, reducing the overall construction period.

지하 수직부재를 하나 걸러 시공하면, 상향으로 시공되는 잔여분을 동시에 각각 시공할 수 있어 전체 공사기간이 단축된다.If every other underground vertical member is constructed, the remaining parts to be constructed upward can be simultaneously constructed, reducing the overall construction period.

각층 코어월과 기둥은 하나걸러 시공하므로 각층을 순타로 시공할 수 있다. 매트 타설전에 하나걸러 시공하는 층(지하 1,3,5층)은 위층(지하 2,4층)이 비어 있으므로 순타로 시공된다. 매트 타설 이후 하나걸러 남아 있는 층(지하 2, 4, 6층)은 이미 시공되어 있으므로 철근을 연결하기 용이하고 알폼 형틀을 붙여 쉽게 시공할 수 있다.Each floor core wall and pillars are constructed one by one, so each floor can be constructed in succession. Before the mat is placed, every other layer (1st, 3rd, 5th basement floor) is installed in a row because the upper floors (2nd and 4th basement) are empty. Since every other layer (2nd, 4th, 6th basement floor) remaining after the mat is placed is already constructed, it is easy to connect reinforcing bars and can be easily constructed by attaching an alform frame.

지하 수직부재를 해당층 슬라브 시공 후 조기에 시공할 수 있어 공사지연이 발생할 여지가 적어 전체 공사기간을 지연시키지 않게 된다.Since the underground vertical member can be constructed early after the slab construction of the corresponding floor, there is little room for delay in construction, so the entire construction period is not delayed.

철근조립만을 먼저 시공하고 콘크리트는 동시에 일괄 타설하여 공사기간을 더욱 단축할 수 있다.Construction period can be further shortened by constructing only rebar assembly first and placing concrete at the same time.

종래에는 매트 타설후 지하 6층을 수직부재를 시공한 후 지하 5층, 지하 4층, 지하 3층, 지하 2층의 순서로 순타로 시공하였다. 이에 따라 종래에는 순타로 5개층을 시공하는데 층당 30일인 경우 총 150일이 소요되었으나 본 발명에 따르면 홀수층은 매트 타설전에 이미 완료하였으며 매트 타설 후에는 짝수층인 지하 6층, 지하 4층, 지하 2층을 동시에 시공 또는 순타로 시공하여 30일 내지 50일만 소요된다. 그 결과 종래에는 매트 타설 후 지하층 완료까지 150일 소요되었으나 본 발명에 따르면 30 내지 50일이 소요되므로 결과적으로 100내지 120일이 단축된다. 이에 따라 전체 공사기간도 약 120일 (3내지 4개월)이 단축된다.Conventionally, after the mat was poured, vertical members were installed on the 6th basement level, followed by sequential construction of 5 basement levels, 4 basement levels, 3 basement levels, and 2 basement levels. Accordingly, conventionally, it took a total of 150 days to construct 5 floors in Suntaro for 30 days per floor, but according to the present invention, the odd-numbered layers were already completed before the mat was placed, and after the mat was placed, the even-numbered floors were 6 basement levels, 4 basement levels, and 2 basement levels. It takes only 30 to 50 days to construct the floors simultaneously or in a pure manner. As a result, conventionally, it took 150 days to complete the basement layer after placing the mat, but according to the present invention, it took 30 to 50 days, resulting in a reduction of 100 to 120 days. Accordingly, the entire construction period is also reduced by about 120 days (3 to 4 months).

본 발명에 따르면 지하 6층, 지상 39층 오피스 빌딩에서 39개월 대비 35내지 36개월로 약 3개월 내지 4개월(전체공기의 8%~10% 정도)의 공기단축 효과를 나타낸다.According to the present invention, in an office building with 6 floors below ground and 39 floors above the ground, it is 35 to 36 months compared to 39 months, showing an effect of shortening the construction period of about 3 to 4 months (about 8% to 10% of the total air).

오피스, 오피스텔 등에서의 전체 공사 기간의 단축은 건설사 측면에서의 공사관리비, 현장경비 등의 공사비 절감과 함께 건물주 측면에서의 조기 분양, 임대료 수입, 매출 추가 발생(년 매출의 25%) 등 높은 경제적 효과를 갖는다. Shortening the entire construction period in offices and officetels has high economic effects, such as early pre-sale, rental income, and additional sales (25% of annual sales), along with reduction of construction costs such as construction management and field expenses from the perspective of the construction company. Has.

도 1은 본 발명에 따른 하나 걸러 시공되는 지하 수직부재 시공방법의 전체 흐름도.
도 2내지 도7은 본 발명에 따른 하나 걸러 시공되는 지하 8층인 경우의 규모의 수직부재 시공방법.
도 8내지 도12는 본 발명에 따른 하나 걸러 시공되는 지하 7층인 경우의 수직부재 시공방법.
도 13내지 도17은 본 발명에 따른 하나 걸러 시공되는 지하 6층인 경우의 수직부재 시공방법.
도 18내지 도20은 본 발명에 따른 하나 걸러 시공되는 지하 5층인 경우의 수직부재 시공방법.
도 21은 본 발명에 따른 하나 걸러 시공되는 지하 4층인 경우의 수직부재 시공방법.
1 is an overall flowchart of a method for constructing an underground vertical member that is constructed every other time according to the present invention.
2 to 7 is a vertical member construction method of the scale in the case of eight basement floors constructed every other according to the present invention.
Figures 8 to 12 are vertical member construction method in the case of the seventh basement level constructed every other according to the present invention.
13 to 17 is a vertical member construction method in the case of the sixth basement level constructed every other according to the present invention.
18 to 20 is a vertical member construction method in the case of a fifth basement level constructed every other according to the present invention.
Figure 21 is a vertical member construction method in the case of four basement levels that are constructed every other time according to the present invention.

이하, 본 발명에 따른 하나 걸러 번갈아 시공되는 역타공법의 지하층 수직부재 시공방법을 상세히 설명한다.Hereinafter, a method of constructing a vertical member of the basement layer of the reverse punching method alternately constructed every other according to the present invention will be described in detail.

도 1은 본 발명의 일실시예에 따른 하나 걸러 시공되는 역타공법의 지하 수직부재 시공방법의 전체 흐름도이다. 실시 대상 프로젝트는 지하 6층, 지상 39층의 SRC 오피스 빌딩이다.1 is an overall flowchart of a method of constructing an underground vertical member of the reverse punching method that is constructed every other time according to an embodiment of the present invention. The project to be implemented is an SRC office building with 6 stories below ground and 39 stories above ground.

도 1을 참조하면, 본 실시예에 따른 지하 수직부재의 시공방법은 흙막이 시공단계(S10)에서는 건물 지하층 외벽을 기준으로 지하에 흙막이를 시공하며 슬러리 월, CIP, H-Pile 및 토류판 등이 시공된다.Referring to FIG. 1, in the construction method of the underground vertical member according to the present embodiment, in the soil barrier construction step (S10), a soil barrier is constructed in the basement based on the outer wall of the basement layer of the building, and a slurry wall, CIP, H-Pile, and earth plate are constructed. do.

지하 말뚝 시공단계(S20)에서는 역타공법에서 지하층 슬라브를 지지하기 위하여 1층 바닥에서 장비를 이용하여 기초와 매트 깊이까지 PRD, RCD ACT등의 기둥이 시공된다.In the underground pile construction step (S20), columns such as PRD and RCD ACT are constructed to the depth of the foundation and mat by using equipment from the first floor in order to support the basement slab in the reverse punching method.

1층 슬라브 시공단계(S30)에서는 지하 1층을 터파기하고 상기 (S20)단계에서 시공한 기둥을 이용하여 철골보, 데크플레이트 및 콘크리트를 타설하여 1층 슬라브를 완성한다.In the first-floor slab construction step (S30), the first basement floor is excavated, and the first-floor slab is completed by pouring steel beams, deck plates, and concrete using the columns constructed in step (S20).

지하 1층 슬라브 시공단계(S40)에서는 지하 2층을 터파기하고 1층과 마찬가지로 지하 1층 슬라브를 완성한다.In the first basement level slab construction step (S40), the second basement level is excavated, and the first basement level slab is completed like the first level.

지하 1층 수직부재(코어부, 기둥) 시공단계(S50)에서는 상기(S40) 단계에서 시공한 지하 1층 슬라브로부터 지하 1층 코어부를 완성하여 지상층으로 코어부 골조가 상향 시공될 수 있도록 한다.In the first basement level vertical member (core part, column) construction step (S50), the first basement level core part is completed from the first basement level slab constructed in the step (S40) so that the core part frame can be constructed upward to the ground level.

지상층 골조(1차) 시공단계(S60)에서는 상기 (S50)단계에서 시공한 지하 1층 코어부, 기둥으로 부터 지상층 코어부와 기둥을 완성한다. 예를 들어 PRD 파일의 구조조건상 매트 시공전까지 지상 8층까지만 골조를 시공할 수 있다면, 상기 지상층 골조(1차) 단계에서는 지상 8층까지 골조를 시공한다.In the ground-floor frame (1st) construction step (S60), the ground-floor core portion and pillars are completed from the first basement core portion and pillars constructed in the step (S50). For example, if the structural condition of the PRD pile allows only 8 floors above the ground to be constructed before mat construction, the above ground floor frame (1st) is constructed up to 8 floors above the ground.

지하 2층 슬라브 시공단계(S70)에서는 상기 (S40)단계에 이어 하향으로 지하 3층 터파기를 한 후 지하 2층 슬라브를 시공한다.In the second basement slab construction step (S70), after the step (S40), the third basement level is dug downward, and then the second basement level slab is constructed.

지하 3층 슬라브 시공단계(S80)에서는 상기 (S70)단계에 이어 하향으로 지하 4층 터파기를 한 후 지하 3층 슬라브를 시공한다.In the slab construction step (S80) of the 3rd basement level, after the step (S70), the 4th basement level is dug downward, and the slab of the 3rd basement is constructed.

본 발명의 특징에 따른 지하 3층 수직부재 시공단계(S90)에서는 상기(S80) 단계에서 시공한 지하 3층 슬라브로부터 지하 3층 코어부를 완성한다. 상기 (S50)단계에서 지하 1층 코어부를 시공한 후 지하 2층 코어부 시공을 생략하고 한 층 걸러 지하 3층 코어부를 시공하면 순타로 시공할 수 있어 시공이 용이하다. In the basement three-story vertical member construction step (S90) according to a feature of the present invention, the basement three-story core part is completed from the basement three-story slab constructed in the step (S80). In the step (S50), after constructing the first basement core part, if the construction of the second basement core part is omitted and the third basement core part is installed every other floor, the construction can be performed in a straightforward manner.

종래에는 지하 3층 코어부는 매트 타설 후 지하 6층부터 순타로 시공하였으나, 본 발명에 따라 지하 3층 수직부재는 지하 1층 코어부 시공 후 한 층 걸로 먼저 시공하므로써 공사기간을 단축하는 효과를 갖는다.Conventionally, the core part of the basement 3rd floor was constructed sequentially from the 6th floor of the basement after the mat was placed, but according to the present invention, the vertical member of the basement 3rd floor has the effect of shortening the construction period by constructing one floor after the core part of the 1st basement is constructed.

지하 4층 슬라브 시공단계(S100)에서는 상기(S80) 단계에 이어 하향으로 지하 5층 터파기를 한 후 지하 4층 슬라브를 시공한다.In the slab construction step (S100) of the fourth basement level, after the step (S80), the 5th basement level is dug downward, and then the slab of the fourth basement level is constructed.

지하 5층 슬라브 시공단계(S110)에서는 상기(S100) 단계에 이어 하향으로 지하 6층 터파기를 한 후 지하 5층 슬라브를 시공한다.In the step of constructing a slab with a 5th basement level (S110), after the step (S100), after digging the 6th basement level downward, a slab with a 5th basement level is constructed.

본 발명에 특징에 따른 지하 5층 수직부재 시공단계(S120)에서는 상기(S110) 단계에서 시공한 지하 5층 슬라브로부터 지하 5층 코어부를 완성한다. 상기 (S90)단계에서 지하 3층 코어부를 시공한 후 지하 4층 코어부 시공을 생략하고 한 층 걸러 지하 5층 코어부를 시공하면 순타로 시공할 수 있다. In the step of constructing a vertical member of the fifth basement level according to the present invention (S120), a core part of the fifth basement level is completed from the slab of the fifth basement level constructed in the step (S110). In the step (S90), after constructing the core of the third basement level, if the construction of the core of the fourth basement is omitted and the core of the 5th basement is constructed every other floor, it can be constructed in a straightforward manner.

종래에는 지하 5층 코어부는 매트 타설 후 지하 6층부터 순타로 시공하였으나, 본 발명에 따라 지하 5층 수직부재는 지하 3층 코어부 시공 후 한 층 걸로 먼저 시공하므로써 공사기간이 단축되는 특징을 갖는다.Conventionally, the core part of the basement 5th floor was constructed sequentially from the 6th floor of the basement after the mat was placed, but according to the present invention, the vertical member of the basement 5th floor is constructed one floor after the core part of the 3rd basement level is constructed, thereby shortening the construction period.

지하 3층 수직부재 시공단계(S90)와 지하 5층 수직부재 시공단계(S120)는 본 발명의 특징에 따라 매트 타설전에 순타로 한층 걸러 미리 시공하는 방법으로서 공사기간을 단축한다.The three basement vertical member construction step (S90) and the fifth basement vertical member construction step (S120) are a method of pre-installing one layer before placing the mat in accordance with the features of the present invention to shorten the construction period.

이후 기초 또는 매트(Mat) 시공단계(S130)에서는 상기 (S110)단계에 이어 하향으로 최종 터파기를 한 후 기초, 매트를 시공한다. 매트가 시공되면, 이제 유턴하여 상향으로 지하층 수직부재와 지상층 골조를 동시에 시공한다. 예를 들어 매트 시공전까지는 지상 골조는 8층까지 올릴 수 있고, 지하 수직부재 완성시까지는 15층까지 시공할 수 있으며 지하 수직부재 완료 후에는 최상층인 지붕층까지 시공할 수 있다.Thereafter, in the foundation or mat construction step (S130), after the final digging downwards following the step (S110), the foundation and mat are constructed. When the mat is installed, now make a U-turn and construct the basement level vertical member and the ground level frame at the same time upward. For example, the ground frame can be raised up to 8 floors before mat construction, up to 15 floors can be constructed until the basement vertical member is completed, and the top floor, the roof layer, can be constructed after the basement vertical member is completed.

기초, 매트가 완성되면(S140), 이제 지하 수직부재(코어부, 기둥)를 시공한다.When the foundation and mat are completed (S140), now construct the underground vertical member (core part, pillar).

지하 수직부재중 지하 1층(S50), 지하 3층(S90), 지하 5층(S120)는 본 발명에 따라 하나 걸러 미리 시공하였으므로 남은 수직부재는 지하 6층, 지하 4층, 지하 2층이다. 본 발명에서는 상기 잔여 수직부재(지하 6층, 지하 4층, 지하 2층)를 시공하는데 있어 해당층의 상하로 코어부가 이미 시공되어 있으므로 동시에 일시에 시공할 수 있는 장점과 특징을 갖는다(S150, S160, S170). Among the vertical basement members, the first basement level (S50), the basement level 3 (S90), and the basement level 5 (S120) were constructed in advance according to the present invention, so the remaining vertical members are 6 basement levels, 4 basement levels, and 2 basement levels. In the present invention, in the construction of the remaining vertical members (6 basement levels, 4 basement levels, 2 basement levels), since the core part is already constructed above and below the corresponding floor, it has the advantage and characteristic that it can be constructed at the same time (S150, S160, S170).

종래에는 지하 6층 코어부를 시공한 후, 지하 5층을 시공하고 이어서 지하 4층, 지하 3층, 지하 2층 순으로 순서대로 시공해야 했다. 그러나 본 발명에 따르면, 잔여 수직부재(지하 6층, 지하 4층, 지하 2층)를 동시에 시공할 수 있으므로 1개층을 시공하는 기간만 소요된다.Conventionally, after constructing the core of the 6th basement level, the 5th basement level was constructed, followed by 4 basement levels, 3 basement levels, and 2 basement levels in order. However, according to the present invention, since the remaining vertical members (6 basement levels, 4 basement levels, and 2 basement levels) can be constructed at the same time, only a period of construction of one floor is required.

이에 따라 매트 타설전에는 지하 3층, 지하 5층의 2개 층의 코어부를 먼저 시공하고, 매트 타설후에는 잔여 수직부재(지하6, 4, 2층)를 동시에 시공하므로 종합적으로 4개층을 미리 시공하는 효과를 갖는다. 따라서 1개층 수직부재에 통상 30일이 소요되므로, 종래에는 150일이 소요되었으나, 본 발명에 따르면 30일이 소요되어 120일(4개월)의 전체 공사기간 단축효과를 갖는다. Accordingly, the core part of the two floors of the 3rd basement and 5th basement is first constructed before the mat is placed, and the remaining vertical members (6th, 4th, and 2nd floors) are simultaneously constructed after the mat is placed. Has the effect of Therefore, since it usually takes 30 days for one floor vertical member, it took 150 days in the past, but according to the present invention, it took 30 days to reduce the overall construction period of 120 days (4 months).

이상과 같이 지하 수직부재가 완성되면(S170), 다음으로 지상층 골조(2차)(S180)이 시작될 수 있다. 예를 들면 지상층 골조(1차)는 지하 수직부재가 완성되기 전까지는 지상 15층까지 시공할 수 있고, 지하 부직부재 완성 이후에는 지상층 골조(2차)(S180)로서 지상 16층부터 최상층(지붕)까지 제약없이 시공할 수 있다.When the underground vertical member is completed as described above (S170), the ground floor frame (secondary) (S180) may be started next. For example, the ground floor frame (primary) can be constructed up to 15 floors above the ground until the basement vertical member is completed, and after the basement nonwoven member is completed, it is a ground floor frame (secondary) (S180) from the 16th floor to the top (roof). ) Can be constructed without restrictions.

도 2 내지 도 7은 본 발명의 일실시예에 따른 하나 걸러 번갈아 시공되는 역타공법의 지하 8층인 경우의 수직부재 시공방법의 순서이다.2 to 7 is a sequence of a vertical member construction method in the case of the eighth basement level of the reverse punching method alternately constructed according to an embodiment of the present invention.

시공순서는 다음과 같다.The construction sequence is as follows.

흙막이Dirt barrier

지하기둥(PRD, RDC, ACT column)Prd, RDC, ACT column

지하1층 및 지하2층 터파기Excavating the 1st basement level and 2nd basement level

지하1층 철골 데크 철근 콘크리트 타설(슬라브 타설)Basement 1st floor steel deck reinforced concrete pouring (slab pouring)

지하3층 터파기Excavating the 3rd basement floor

지하2층 슬라브 타설, 지하1층 코어월 기둥 타설2nd basement slab casting, Core wall pillar placement on the first basement floor

지하4층 터파기Excavating the 4th basement floor

지하3층 슬라브 타설Slab placement on the 3rd basement floor

지하5층 터파기Excavating the 5th basement floor

지하4층 슬라브 타설, 지하3층 코어월 기둥 타설4 basement level slab casting, Core wall pillar placement on the 3rd basement floor

지하6층 터파기Excavating the 6th basement floor

지하5층 슬라브 타설Slab placement on the 5th basement floor

지하7층 터파기Excavating the 7th basement floor

지하6층 슬라브 타설, 지하5층 코어월 기둥 타설6 basement level slab casting, Core wall pillar placement on the 5th basement floor

지하8층 터파기 및 매트 터파기Excavating the 8th basement floor and excavating the mat

지하7층 슬라브 타설, 지하7층 코어월 기둥 타설 7th basement slab casting, 7th basement level core wall pillar placement

지하8층 바닥 매트 타설Floor mats on the 8th basement floor

잔여층인 지하8층, 지하6층, 지하4층, 지하4층 코어월 기둥 타설 (4개층 동시시공)The remaining floors, 8 basement levels, 6 basement levels, 4 basement levels, and 4 basement levels, core wall pillar placement (simultaneous construction of 4 floors)

또는 지하8층 및 한개층 추가하여 2개층 1차 시공 후 남은 2개층 2차 코어월 기둥 시공(2개층 2회 시공)Or, add 8 basement levels and one level, and build the second core wall pillars on the remaining two levels after the first construction of two floors (two floors, two times)

또는 지하8층 및 한개층 추가하여 2개층 1차 시공 후 남은 2개층을 한개층씩 2차 3차로 코어월 기둥 시공(2개층 1회, 1개층 2회 총 3회 시공)Or add 8 basement levels and one floor, and after the first construction of two floors, the remaining two floors are constructed as core wall pillars in the second and third lanes one by one (2 floors 1 time, 1 floor 2 times total 3 times)

또는 지하8층 코어월 기둥 시공 후 남은 3개층을 한개층씩 시공 (4개층을 총4회 시공)Or, after constructing the core wall pillar on the 8th basement level, the remaining 3 floors are constructed one by one (4 floors are constructed 4 times in total)

매트 타설이후에는 남은 층은 4개층이며 1회, 2회, 3회, 4회에 분할하여 타설한다.After the mat is poured, there are 4 remaining layers, and it is divided into 1, 2, 3, and 4 times.

도 8 내지 도 12는본 발명의 일실시예에 따른 하나 걸러 번갈아 시공되는 역타공법의 지하 7층인 경우의 수직부재 시공방법의 순서이다.8 to 12 is a sequence of a vertical member construction method in the case of the seventh basement level of the reverse punching method alternately constructed every other according to an embodiment of the present invention.

시공순서는 다음과 같다.The construction sequence is as follows.

흙막이Dirt barrier

지하기둥(PRD, RDC, ACT column)Prd, RDC, ACT column

지하1층 및 지하2층 터파기Excavating the 1st basement level and 2nd basement level

지하1층 철골 데크 철근 콘크리트 타설(슬라브 타설)Basement 1st floor steel deck reinforced concrete pouring (slab pouring)

지하3층 터파기Excavating the 3rd basement floor

지하2층 슬라브 타설, 지하1층 코어월 기둥 타설2nd basement slab casting, Core wall pillar placement on the first basement floor

지하4층 터파기Excavating the 4th basement floor

지하3층 슬라브 타설Slab placement on the 3rd basement floor

지하5층 터파기Excavating the 5th basement floor

지하4층 슬라브 타설, 지하3층 코어월 기둥 타설4 basement level slab casting, Core wall pillar placement on the 3rd basement floor

지하6층 터파기Excavating the 6th basement floor

지하5층 슬라브 타설Slab placement on the 5th basement floor

지하7층 터파기 및 매트 터파기Excavating the 7th basement floor and excavating the mat

지하6층 슬라브 타설, 지하5층 코어월 기둥 타설6 basement level slab casting, Core wall pillar placement on the 5th basement floor

지하7층 바닥 매트 타설Floor mats on the 7th basement floor

잔여층인 지하 7층, 지하6층, 지하4층, 지하2층에서The remaining floors are 7 basement levels, 6 basement levels, 4 basement levels, and 2 basement levels.

지하7층 및 한개층 추가(지하 4층 또는 지하 2층 중에서 택1)하여 2개층 1차 시공 후 남은 2개층 2차 코어월 기둥 시공(2개층 2회 시공)Add 7 basement levels and 1 level (choose 1 from 4 basement levels or 2 basement levels) and install 2 floors remaining after the 1st construction of 2 floors and 2nd core wall pillar construction (2 floors 2 times construction)

또는 지하7층, 잔여 3개층에서 2개층 2차 시공, 나머지 잔여 1개층 시공 (총 3회 분할 시공)Alternatively, 2nd floor construction from the 7th basement level and the remaining 3 floors, the remaining 1 floor construction (a total of 3 divisions)

또는 한개층씩 시공하여 총 4회 시공한다.Alternatively, each layer is constructed and constructed four times.

도 13 내지 도 17은 본 발명의 일실시예에 따른 하나 걸러 번갈아 시공되는 역타공법의 지하 6층인 경우의 수직부재 시공방법의 순서이다.13 to 17 are a sequence of a vertical member construction method in the case of the sixth basement level of the reverse punching method alternately constructed every other according to an embodiment of the present invention.

시공순서는 다음과 같다.The construction sequence is as follows.

흙막이Dirt barrier

지하기둥(PRD, RDC, ACT column)Prd, RDC, ACT column

지하1층 및 지하2층 터파기Excavating the 1st basement level and 2nd basement level

지하1층 철골 데크 철근 콘크리트 타설(슬라브 타설)Basement 1st floor steel deck reinforced concrete pouring (slab pouring)

지하3층 터파기Excavating the 3rd basement floor

지하2층 슬라브 타설, 지하1층 코어월 기둥 타설2nd basement slab casting, Core wall pillar placement on the first basement floor

지하4층 터파기Excavating the 4th basement floor

지하3층 슬라브 타설Slab placement on the 3rd basement floor

지하5층 터파기Excavating the 5th basement floor

지하4층 슬라브 타설, 지하3층 코어월 기둥 타설4 basement level slab casting, Core wall pillar placement on the 3rd basement floor

지하6층 터파기 및 매트 터파기Excavating the 6th basement floor and excavating the mat

지하5층 슬라브 타설 Slab placement on the 5th basement floor

지하6층 바닥 매트 타설, 지하5층 코어월 기둥 타설 Floor mat placement on the 6th basement floor, Core wall pillar placement on the 5th basement floor

잔여층인 지하6층, 지하4층, 지하2층에서In the remaining floors, 6 basement levels, 4 basement levels, and 2 basement levels

잔여 3개층으로 동시에 시공(총1회)Simultaneous construction with the remaining 3 floors (total 1 time)

또는 지하6층 시공 후 지하4층과 지하2층을 동시시공 (총2회)Or, after constructing the 6th basement level, simultaneously construct the 4th basement level and the 2nd basement level (2 times in total)

또는 지하6층과 지하4층을 동시 시공 후 지하2층을 시공 (총2회)Or, construct the 6th basement level and 4th basement level at the same time and then build 2 basement levels (total of 2 times)

한개층씩 시공하여 총 3회 시공(총3회 분할시공)한다.Each floor is constructed and constructed three times (a total of three divided constructions).

도 18 내지 도 20은 본 발명의 일실시예에 따른 하나 걸러 번갈아 시공되는 역타공법의 지하 5층인 경우의 수직부재 시공방법의 순서이다.18 to 20 are a sequence of a vertical member construction method in the case of the fifth basement level of the reverse punching method alternately constructed every other according to an embodiment of the present invention.

시공순서는 다음과 같다.The construction sequence is as follows.

흙막이Dirt barrier

지하기둥(PRD, RDC, ACT column)Prd, RDC, ACT column

지하1층 및 지하2층 터파기Excavating the 1st basement level and 2nd basement level

지하1층 철골 데크 철근 콘크리트 타설(슬라브 타설)Basement 1st floor steel deck reinforced concrete pouring (slab pouring)

지하3층 터파기Excavating the 3rd basement floor

지하2층 슬라브 타설, 지하1층 코어월 기둥 타설2nd basement slab casting, Core wall pillar placement on the first basement floor

지하4층 터파기Excavating the 4th basement floor

지하3층 슬라브 타설Slab placement on the 3rd basement floor

지하5층 터파기 및 매트 터파기Excavating the 5th basement floor and excavating the mat

지하4층 슬라브 타설, 지하3층 코어월 기둥 타설4 basement level slab casting, Core wall pillar placement on the 3rd basement floor

지하5층 바닥 매트 타설Floor mat placement on the 5th basement floor

잔여층인 지하5층, 지하4층, 지하2층에서In the remaining floors, 5 basement levels, 4 basement levels, and 2 basement levels

지하 5층 시공후 지하 4층과 지하2층을 동시시공(총2회)After construction of 5 basement levels, simultaneous construction of 4 basement levels and 2 basement levels (2 times in total)

또는 지하 5층과 지하2층 동시시공후 지하 4층을 시공(총2회)Or, after simultaneous construction of 5 basement levels and 2 basement levels, construct 4 basement levels (2 times in total)

잔여 3개층으로 한개층씩 시공(총3회)한다.Construct one layer at a time with the remaining 3 layers (a total of 3 times).

도 21은 본 발명의 일실시예에 따른 하나 걸러 번갈아 시공되는 역타공법의 지하 4층인 경우의 수직부재 시공방법의 순서이다.21 is a sequence of a vertical member construction method in the case of a fourth basement level of the reverse punching method alternately constructed every other according to an embodiment of the present invention.

시공순서는 다음과 같다.The construction sequence is as follows.

흙막이Dirt barrier

지하기둥(PRD, RDC, ACT column)Prd, RDC, ACT column

지하1층 및 지하2층 터파기Excavating the 1st basement level and 2nd basement level

지하1층 철골 데크 철근 콘크리트 타설(슬라브 타설)Basement 1st floor steel deck reinforced concrete pouring (slab pouring)

지하3층 터파기Excavating the 3rd basement floor

지하2층 슬라브 타설, 지하1층 코어월 기둥 타설2nd basement slab casting, Core wall pillar placement on the first basement floor

지하4층 터파기 및 매트 터파기Excavating the 4th basement floor and excavating the mat

지하3층 슬라브 타설, 지하3층 코어월 기둥 타설3 basement level slab casting, Core wall pillar placement on the 3rd basement floor

지하4층 바닥 매트 타설Floor mats on the 4th basement floor

잔여층인 지하4층, 지하2층에서In the remaining floors, the 4th basement level and the 2nd basement level

지하 4층과 지하2층을 동시시공(총1회)Simultaneous construction of 4 basement levels and 2 basement levels (1 time in total)

잔여 2개층을 한개층씩 시공(총2회)한다.The remaining 2 floors are constructed one by one (2 times in total).

Claims (1)

건축 지하 역타공사의 골조시공에 있어서,
지하 파일을 시공하는 단계 ;
지하 터파기를 하면서 내려가는 단계 ;
지하 수평재(슬라브 철골 및 데크, 철근, 콘크리트)를 시공해 내려가는 단계 ;
지하 한 개층(N층)의 수직재(코어월, 기둥)을 시공하는 단계 ;
상기 한 개층(N층)의 하나 걸러 다른 층(N-2층)의 코어월, 기둥을 시공하는 단계 ;
상기 한 개층(N-2층)의 하나 걸러 다른 층(N-4층)의 코어월, 기둥을 시공하는 단계 ;
상기 하나 걸러 과정을 반복하는 단계 ;
지하 기초, 매트(Mat)를 시공하는 단계 ;
상기 과정에서 시공되고 남은 층의 코어월, 기둥을 시공하는 단계 ;
를 포함하여 시공되는 것을 특징으로 하는
하나 걸러 역타공사의 수직재 공사방법.
In the frame construction of the construction basement construction,
Step of constructing an underground pile;
Step of going down while excavating underground;
Step of constructing underground horizontal materials (slab steel frame and deck, reinforcing bar, concrete);
Constructing vertical materials (core walls, pillars) of one basement level (N level);
Constructing a core wall and a pillar of the other layer (N-2 layer) for every other layer (N layer);
Constructing a core wall and a pillar of the other layer (N-4 layer) for every other layer (N-2 layer);
Repeating the process every other time;
The step of constructing the basement foundation and mat;
Constructing the core wall and pillars of the remaining layers constructed in the above process;
Characterized in that it is constructed, including
Vertical material construction method of every other work.
KR1020190075320A 2019-06-24 2019-06-24 Method for Alternate Basement Vertical Structure Construction Method in Top Down Construction Project KR20210000234A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190075320A KR20210000234A (en) 2019-06-24 2019-06-24 Method for Alternate Basement Vertical Structure Construction Method in Top Down Construction Project

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190075320A KR20210000234A (en) 2019-06-24 2019-06-24 Method for Alternate Basement Vertical Structure Construction Method in Top Down Construction Project

Publications (1)

Publication Number Publication Date
KR20210000234A true KR20210000234A (en) 2021-01-04

Family

ID=74127555

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190075320A KR20210000234A (en) 2019-06-24 2019-06-24 Method for Alternate Basement Vertical Structure Construction Method in Top Down Construction Project

Country Status (1)

Country Link
KR (1) KR20210000234A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR950003110A (en) 1993-07-29 1995-02-16 정몽원 Steering Control Method of Vehicle
KR20030037296A (en) 2001-11-01 2003-05-14 천명철 Business method for e-commerce by p2p of equality and computer readable medium having stored thereon computer executable instruction for performing the method
KR20110024619A (en) 2009-09-02 2011-03-09 한국건설기술연구원 Apparatus for installing a grouting mortar supply pipe in tunnel
KR20110087835A (en) 2010-01-27 2011-08-03 엘지디스플레이 주식회사 Liquid crystal display of mobile terminal
KR20130004918A (en) 2010-03-05 2013-01-14 콘티넨탈 테베스 아게 운트 코. 오하게 Operating method for a motor vehicle comprising in particular an electronically controlled parking brake system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR950003110A (en) 1993-07-29 1995-02-16 정몽원 Steering Control Method of Vehicle
KR20030037296A (en) 2001-11-01 2003-05-14 천명철 Business method for e-commerce by p2p of equality and computer readable medium having stored thereon computer executable instruction for performing the method
KR20110024619A (en) 2009-09-02 2011-03-09 한국건설기술연구원 Apparatus for installing a grouting mortar supply pipe in tunnel
KR20110087835A (en) 2010-01-27 2011-08-03 엘지디스플레이 주식회사 Liquid crystal display of mobile terminal
KR20130004918A (en) 2010-03-05 2013-01-14 콘티넨탈 테베스 아게 운트 코. 오하게 Operating method for a motor vehicle comprising in particular an electronically controlled parking brake system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
구축공법,

Similar Documents

Publication Publication Date Title
US3354593A (en) Concrete beamless building construction
KR102588684B1 (en) Method for constructing basement vertical member of top-down method constructed alternately
CN106703197B (en) A kind of large span multilayer anti-seismic frame structure system and its construction method
KR102301605B1 (en) A Method of Bottom-up Removal of Underground Structures
CN114134931B (en) Reverse construction method for developing basement structure of existing building
CN209855277U (en) Conversion layer structure for underground added layer of existing building
CN114737573A (en) Deep foundation pit engineering main building area rear-dismantling support structure and construction method
CN113718753B (en) Anchor underground continuous wall foundation assembled type intermediate wall and construction method
KR20090044195A (en) Core and construction method thereof for extension of elevator operation floor and elevation of seismic resistant performance in remodeling of structure
KR102396786B1 (en) Underground expansion and top-down method of new building using reinforcement of existing underground outer wall
RU2220258C1 (en) Process of erection of multilevel underground structure ( variants )
KR101310677B1 (en) Top down method using precast composite retaining wall and raker in slope
US20230068973A1 (en) Construction of a building
KR20210000234A (en) Method for Alternate Basement Vertical Structure Construction Method in Top Down Construction Project
KR20220024070A (en) The underground vertical member construction method of the reverse perforation method, which is constructed alternately every other time
KR101242017B1 (en) The simultaneous construction method of ground and underground structure using ground core pre-construction and latticed lintel beam in core
WO2021031860A1 (en) Beam lowering construction method of subsurface structure in top-down method
KR100877596B1 (en) Building repairing method using column reinforcing member
US20240229451A9 (en) Top-down construction method for multi-storey basement with full steel structure
US20240133175A1 (en) Top-down construction method for multi-storey basement with full steel structure
KR20240068954A (en) Continuous construction method of the superstructure by adding spare piles to the lowest basement floor in the top-down construction project
KR100593203B1 (en) a deck supportframe and a construction methed
KR101026112B1 (en) The construction method of underground structure using mega-structure
CN109736589B (en) Construction method of lattice column force transmission component
Narafu et al. Experimental study on confined brick masonry in Indonesia

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application