KR20160095739A - Vertical pit construction method using VIR method - Google Patents
Vertical pit construction method using VIR method Download PDFInfo
- Publication number
- KR20160095739A KR20160095739A KR1020150017082A KR20150017082A KR20160095739A KR 20160095739 A KR20160095739 A KR 20160095739A KR 1020150017082 A KR1020150017082 A KR 1020150017082A KR 20150017082 A KR20150017082 A KR 20150017082A KR 20160095739 A KR20160095739 A KR 20160095739A
- Authority
- KR
- South Korea
- Prior art keywords
- htr
- pipe
- reaction force
- pit excavation
- pit
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
- E02D29/05—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/003—Injection of material
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
The present invention relates to a method for effectively excavating vertical pits by a VTR method in a construction site such as a subway construction site in a city where a large-sized equipment is difficult to carry.
The present invention relates to a method of drilling a vertical pit at a construction site, such as a subway construction site in a city center, by applying a pushing-in method by a leading pipe during a vertical pit excavation and a proper finishing method according to various ground conditions, By implementing the VTR (Vertical Tubular Retaining) method, it is possible to shorten the construction period and the construction cost by simplifying the process, and furthermore, it is possible to reduce the construction cost by using the VTR method, which can be effectively applied in a narrow construction site, Provides excavation methods.
Description
The present invention relates to a vertical pit excavation method using a VTR method, and more particularly, to a method of effectively excavating vertical pits by a VTR method in a place where a construction site is narrow, such as a subway construction site in an urban area, .
In general, various types of vertical pits are being constructed, such as vertical pits for venting or unloading of materials when entering underground structures such as subway construction, vertical pits for venting workers, and vertical pits for ventilation.
Various excavation equipment and excavation methods have been applied to construct this kind of vertical pit.
For example, the method for excavating various vertical pits is divided into two types: a bottom-up excavation method and a bottom-up excavation method. The bottom-up excavation method includes the D & B method, the Raise Climber Method, And RBM (Raise Boring Machine Method).
Here, the Drill & Blasting Method is a conventional blasting method using gunpowder, which is performed in the order of punching, blasting, ventilation, buffing, and reinforcement.
Such a method has a disadvantage in that it requires high cost such as a winch, high cost of processing bushing, high risk of safety accident due to high blasting and vibration noise, and excessive labor input due to excavation of workforce, .
In the case of the RC method (Raise Climber Method), the pilot excavation is drilled using a rock drill, and a rail for moving the work foot plate is installed on the excavation surface and drilled in order of drilling, charging, blasting, It proceeds.
This method is difficult to apply in weak ground conditions, and it has a high risk of safety accidents due to large blasting and vibration noise, and it is difficult to cope with a fallout or collapse accident. In a place where precision of construction is required, uncertainty of construction is a problem do.
In the RBM method, the machine room is installed on the upper part of the vertical pit to be excavated and the reaming room is formed on the lower part. Then, the drilling machine is operated in the upper machine room, It is a method to extend a vertical pit by pulling up a reamer through an excavated guide hole by excavating an inducer while connecting and connecting pipes.
Such a method has recently been widely used because it has the advantage that excavation speed is fast, safety accident can be excluded, ventilation is unnecessary, and construction is precise. However, currently, in Korea, Facilities are not presented and almost all of them depend on foreign equipment.
However, these methods have difficulty in applying to the urban subway construction such as the subway construction site in the urban area because of the difficulty in bringing large equipment when the construction site is narrow.
And, when constructing a subway, it is usually necessary to install a vertical pit in an open-cut manner. However, it is not a problem in a place other than the city center, Traffic congestion occurs, and civil complaints are generated, and there are many difficulties in construction.
In consideration of this point, Korean Patent Registration No. 10-1292671 discloses a method of excavating an elevator pit using a VTR method.
However, although the above-mentioned excavation method is a useful excavation method for the construction environment, condition, and construction scale such as elevator pit excavation at the remodeling work of a building, there is a need for various improvements to be applied to large-scale construction and construction conditions such as the construction of a subway do.
Accordingly, it is an object of the present invention to provide a method and apparatus for pushing a leading pipe during vertical pit drilling at a construction site, such as a subway construction site in an urban area, and an appropriate finishing method according to various ground conditions (Vertical Tubular Retaining) method, which can excavate vertical pits efficiently, it is possible to reduce the construction period and construction cost by simplifying the process, and to reduce the construction cost, especially in a narrow construction site such as a subway construction site in the urban area And it is an object of the present invention to provide a vertical pit excavation method using a VTR method that can be effectively applied.
In order to achieve the above object, the vertical pit excavation method using the VTR method of the present invention has the following features.
The vertical pit excavation method using the VTR method includes the steps of installing a reaction force anchor on the ground in the vertical pit excavation area and providing a reaction force mechanism, installing a first pipe and a first HTR pipe inside the reaction force mechanism, A hydraulic jack is installed between the observation and the HTR observation, and then the hydraulic jack is operated to propel the leading pipe vertically downward; and a second HTR pipe is connected to the first HTR pipe in the space secured by the driving of the leading pipe, A step of performing a finishing process between the HTR pipe and the excavation surface of the pit, a step of propelling the leading pipe, a step of installing and connecting the HTR pipe and a finishing process, And securing a drilling hole having a predetermined depth in which the pipe is stacked up, and then placing the concrete in the HTR pipe to construct the internal structure.
Therefore, the vertical pit excavation method using the VTR method is advantageous in a narrow construction site where it is difficult to bring large equipment such as a subway construction site in a city center.
Here, in the step of embedding the reaction force anchor and installing the reaction force mechanism, the reaction force anchors are disposed in at least two to four places of the box-type reaction force mechanism woven in a square or a round shape, And a method of installing a reaction force mechanism can be applied.
In addition, in the step of installing the HTR tube, at least one HTR frame-connecting steel member and a plurality of soil plates are connected and arranged between the upper and lower H-beams after the H- beams woven in a square or round shape are arranged up and down, The HTR tube can be completed in such a manner that the HTR tube is arranged along the circumference of the mold.
In addition, in the step of propelling the leading pipe, a space of a depth to which one HTR pipe is inserted is secured several times by pushing the leading pipe, while the leading pipe is installed with a hydraulic jack at a depth that is once driven by the hydraulic jack The propulsion can be performed while still supporting the link between the HTR tubes.
When the finishing process is performed between the HTR pipe and the pit excavation surface, the waterproof sheet and the pad may be stacked in order from the outer circumference of the HTR pipe to the pit excavation surface in the case of the soft ground, A waterproof sheet can be placed between the outer circumference of the HTR tube and the excavation surface of the pit, and a waterproof sheet and a grouting layer can be sequentially laminated on the outer surface of the HTR pipe. And pressing the waterproof sheet against the pit excavation surface by applying pressure grouting to the waterproof sheet from the HTR observation.
The vertical pit excavation method using the VTR method provided by the present invention has the following advantages.
First, it is possible to construct excavation efficiently and economically at narrow construction sites such as subway construction sites in urban areas by securing enough space to install a leading pipe.
Second, since the leading pipe is used as a soil plate during excavation, the risk of collapse of the pneumatic wall can be reduced and structural stability can be secured.
Third, proper finishing work is performed according to the ground conditions such as soft ground, watery soil, rock mass, etc. Therefore, it is possible to shorten the construction time and air safety as well as reduce the construction cost due to the ground stabilization.
1 is a schematic view showing a vertical pit excavation method using a VTR method according to an embodiment of the present invention.
2 is a schematic view showing a method of finishing an excavation surface in a vertical pit excavation method using a VTR method according to an embodiment of the present invention.
3 is a perspective view showing a reaction force mechanism used in the vertical pit excavation method using the VTR method according to an embodiment of the present invention.
4 is a perspective view illustrating a leading pipe and an HTR pipe used in the vertical pit excavation method using the VTR method according to an embodiment of the present invention.
Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.
1A and 1B are schematic views showing a vertical pit excavation method using a VTR method according to an embodiment of the present invention.
As shown in FIGS. 1A and 1B, the vertical pit excavation method using the VTR method is a method for efficiently excavating vertical pits in a narrow site condition, such as a subway construction site in an urban area.
To this end, a reaction force anchor (12) is first placed on the ground in the vertical pit excavation area and a reaction force mechanism (13) is installed.
That is, four
At this time, the
Here, the reaction mechanism (13) has a structure to be coupled to the reaction force anchors (12) while being placed on the ground in the excavation area.
For example, as shown in Fig. 3, the
As a result, the
The
Here, the
Next, the leading
At this time, it is preferable that the reaction mechanism (13) and the first HTR tube (11a) are bound together by welding or the like.
With respect to the installation work of the
In other words, it is also possible to install a preliminarily formed circular tube or a rectangular pipe-like leading
In the installation step of the
For example, as shown in Fig. 4, H-
Here, the
Subsequently, a
Four
The
In the step of propelling the
That is, it is possible to propel the leading
For example, the
In this way, the third propulsion, the fourth propulsion, and the like are repeatedly promoted, and a plurality of connecting
Of course, the soil in the excavation space thus secured is discharged to the outside in an appropriate manner and removed.
Next, a
That is, the
The
Particularly, between the
Next, by repeating the step of propelling the leading
In other words, by repeating the step of advancing the leading
Subsequently, a mold (not shown) is installed in parallel with the
2 is a schematic view illustrating a method of finishing an excavation surface in a vertical pit excavation method using a VTR method according to an embodiment of the present invention.
As shown in Fig. 2, the present embodiment shows a ground reinforcement method optimized for various types of ground such as soft ground, heavy water, and rock.
First, when a vertical pit is excavated from a soft ground, a
That is, by stacking the
It is preferable that the
Next, when the vertical pit is excavated from the ground where a lot of water is discharged, a laminated construction of the
That is, after securing the excavating hole, the
Next, when the vertical pit is excavated in the rocky zone, the
That is, after securing the excavating hole, the
Therefore, it is possible to reinforce the ground as a whole as well as to waterproof the
At this time, the
In the case of the pressurizing method for forming the
That is, pressure grouting can be performed on the waterproof sheet portion that is out of the leading pipe.
Thus, the present invention has been shown and described with reference to certain preferred embodiments thereof. It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the spirit or scope of the invention as defined in the appended claims. Change will be possible.
10: Leading Hall
11, 11a, 11b, 11c, 11d, 11e, 11f: HTR tube
12: reaction force anchor
13: reaction force mechanism
14: reaction force transmitting steel
15: Anchor head
16:
17: H-beam
18: HTR frame connection steel
19: Hydraulic Jack
20: Links
21: Stand
22: Pit excavation surface
23: Pad
24: Waterproof sheet
25: Grouting layer
26: tube
Claims (7)
Installing a first pipe and a first HTR pipe inside the reaction force mechanism, and operating a hydraulic jack after a hydraulic jack is installed between a leading pipe and an HTR pipe to propel the leading pipe vertically downward;
Connecting a first HTR pipe with a second HTR pipe in a space secured by the driving of the leading pipe, and performing a finishing process between the HTR pipe and the pit excavation surface;
The HTR pipe is installed and connected and the finishing process is repeated to secure a drilling hole having a predetermined depth in which a plurality of HTR pipes are vertically stacked along the inner wall of the pit Placing the concrete in the HTR tube to construct an internal structure;
The method of claim 1,
In the step of embedding the reaction force anchor and installing the reaction force mechanism, a reaction force anchor is installed in at least two to four places of the box-type reaction force mechanism woven in a square or oval shape so that the reaction force mechanism is supported in a balanced manner And a reaction force mechanism is installed in the vertical pit excavation method.
In the step of installing the HTR tube, at least one HTR frame-connecting steel and a plurality of dust plates are connected between the upper and lower H-beams after the H-beams woven in a square or a round shape are arranged up and down, And the HTR pipe is completed in a manner that the HTR pipe is connected to the HTR pipe.
In the step of propelling the lead pipe, the depth of the space to which one HTR pipe is inserted is secured while propelling the lead pipe several times. The HTR pipe having the hydraulic jack and the pre- Wherein the pushing of the vertical pits is performed while the pushing member is continuously supported.
Wherein the step of applying a finishing treatment between the HTR tube and the pit excavation surface comprises sequentially stacking the waterproof sheet and the pads in order from the outer circumference of the HTR pipe to the pit excavation surface in the case of the soft ground Vertical pit excavation method.
And the step of applying a finishing treatment between the HTR tube and the pit excavation surface includes the step of sequentially stacking the waterproof sheet and the grouting layer from the outer circumference of the HTR pipe to the pit excavation surface in the case of a lot of water, Vertical pit excavation method using VTR method.
In the step of performing finishing treatment between the HTR tube and the pit excavation surface, a waterproof sheet is disposed between the outer circumference of the HTR tube and the excavation surface of the pit in the rocky area, and then the waterproof sheet 24 is subjected to pressure grouting And pressing the sheet (24) against the pit excavation surface.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020150017082A KR20160095739A (en) | 2015-02-04 | 2015-02-04 | Vertical pit construction method using VIR method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020150017082A KR20160095739A (en) | 2015-02-04 | 2015-02-04 | Vertical pit construction method using VIR method |
Publications (1)
Publication Number | Publication Date |
---|---|
KR20160095739A true KR20160095739A (en) | 2016-08-12 |
Family
ID=56714706
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020150017082A KR20160095739A (en) | 2015-02-04 | 2015-02-04 | Vertical pit construction method using VIR method |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR20160095739A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114991479A (en) * | 2022-07-04 | 2022-09-02 | 孔德奎 | Intelligent construction method for building decoration |
-
2015
- 2015-02-04 KR KR1020150017082A patent/KR20160095739A/en not_active Application Discontinuation
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114991479A (en) * | 2022-07-04 | 2022-09-02 | 孔德奎 | Intelligent construction method for building decoration |
CN114991479B (en) * | 2022-07-04 | 2023-10-13 | 新疆富昌建设工程有限公司 | Intelligent construction method for building decoration |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101014796B1 (en) | Top-down underground construction method using prefabricated concrete column member as temporary bridge column | |
KR100713787B1 (en) | The underground structure assembly and the underground structure building method which it uses | |
CN104947681B (en) | Super large super deep basement ground pit construction method | |
KR100967497B1 (en) | Method for constructing an underground structure | |
JP6274406B2 (en) | Construction method of new underground structure with dismantling of existing underground structure | |
KR20140055639A (en) | A execution method of architecture beam | |
JP2017166139A (en) | Construction method of underground structure | |
JP2012107479A (en) | Method for constructing underground and aboveground structure | |
CN108316670B (en) | Steel pipe underpinning construction method under existing building foundation | |
CN114215090A (en) | Construction method of raft and compression pile in closed space | |
JP6422084B2 (en) | Underground space construction method | |
KR101358471B1 (en) | architecture using a complex steel pile | |
JP5189946B2 (en) | Pile hole drilling method | |
CN111042104A (en) | Method for constructing diaphragm wall at existing underground structure | |
KR20160095739A (en) | Vertical pit construction method using VIR method | |
JP6993293B2 (en) | How to reinforce existing structures in the ground | |
KR20090011442A (en) | Tunnel boring method using sheet pile and tunnel structure therof | |
JP2006299660A (en) | Temporary receiving construction method and temporary receiving structure | |
KR100967496B1 (en) | Device for constructing an underground structure | |
CN214657227U (en) | Top-down shaft channel for constructing ultra-deep shaft by reverse construction method | |
JP6220659B2 (en) | Position adjustment method of reaction force receiving member and top of column | |
JP2008274746A (en) | Method of demolishing and removing underground structure | |
JP2007308951A (en) | Method of constructing outer peripheral column by inverted construction method | |
JP6362863B2 (en) | Forming method and structure of onboard platform pile | |
JP2762133B2 (en) | How to build a large architectural space underground |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E601 | Decision to refuse application |