KR20120078217A - Block out construction method for apparatus base - Google Patents

Block out construction method for apparatus base Download PDF

Info

Publication number
KR20120078217A
KR20120078217A KR1020100140447A KR20100140447A KR20120078217A KR 20120078217 A KR20120078217 A KR 20120078217A KR 1020100140447 A KR1020100140447 A KR 1020100140447A KR 20100140447 A KR20100140447 A KR 20100140447A KR 20120078217 A KR20120078217 A KR 20120078217A
Authority
KR
South Korea
Prior art keywords
concrete
block
foundation
embedded
formwork
Prior art date
Application number
KR1020100140447A
Other languages
Korean (ko)
Inventor
박길석
Original Assignee
(주)정토지오텍
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)정토지오텍 filed Critical (주)정토지오텍
Priority to KR1020100140447A priority Critical patent/KR20120078217A/en
Publication of KR20120078217A publication Critical patent/KR20120078217A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/28Stressing the soil or the foundation structure while forming foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Foundations (AREA)

Abstract

PURPOSE: A method for constructing a machinery foundation is provided to prevent economical losses caused by the delay of operating machinery while a poison of a fixing bolt is exactly fitted into the coupling hole. CONSTITUTION: A method for constructing a machinery foundation is as follows. An embedded plate(121) is installed inside forms for foundation concrete. The embedded plate is installed on the foundation concrete in order that one side of the foundation concrete is exposed. The foundation concrete is placed to fix the embedded plate by placing concrete into the form for the foundation concrete. A fixing bolt(123) is fixed to the exposed surface of the embedded plate to mach the fixing bolt with a coupling hole. A form for a block is installed around the embedded plate and the fixing bolt. A foundation block(126) is built to extend a part of the fixing bolt by placing the concrete for the block into the form for the block.

Description

Block out construction method for apparatus base

The present invention relates to a device-based construction method, and more particularly to a device-based construction method that can be fixed to the foundation block fixing bolts fastened to the base block more accurately and precisely.

In general, in order to install a device (device) in a specific place such as slab, wall, ceiling, etc., the foundation concrete and anchor bolts should be installed at the position where the device is to be fixed, and then the fastening formed at the fastening end of the device. The anchor bolt is inserted into the hole (or the fastening hole of the fastening mechanism) to be fixed.

Anchor bolts are commonly used in the construction and civil engineering sectors to connect structures such as steel structures or wooden pillars or steel girder bridges to the foundation of concrete or reinforced concrete.

These anchor bolts are also widely used to fix various devices (such as the main body of the device or peripheral parts of the device such as pipes), and by fastening the fastening ends of the device with anchor bolts at a plurality of fastening points, Prevent the device from moving.

At this time, the anchor bolt alone is difficult to obtain a sufficient rigidity, so the anchor bolt (hereinafter referred to as fixing bolt) is fixed to the concrete foundation block embedded with reinforcing bars and then fastened with the device.

In addition, since the position of the fastening hole is predetermined at the fastening end (or fastening mechanism) of the device, what should be done by exactly matching the position of each bolt with the corresponding fastening hole position of the device when pre-installing the fixing bolt before installation of the device. More important.

In the conventional case, when installing the foundation concrete in the place where the equipment, such as slab, wall, ceiling, will be installed together with the fixing bolt and the foundation block, the reinforcement of the cast iron reinforcement embedded in the foundation block, the formwork for forming the foundation block This will involve a block out construction process that requires installation and concrete placement.

Fig. 1 is a plan view showing a typical construction state of a block base for a device foundation having a fixing bolt fixed thereto, and Fig. 2 is a typical construction sectional view of a block out for a device foundation with a fixing bolt fixed thereto, which is the line of Fig. 1. A cross section taken along 'A-A'.

Here, reference numeral 10 denotes the foundation concrete, reference numeral 11 denotes the concrete reinforcement embedded in the foundation concrete 10, reference numeral 21 is a connection construction to be embedded in the concrete and the foundation concrete 10 of the foundation block 22 Indicates a cast iron.

As shown in the figure, while constructing the foundation concrete 10 in the place where the equipment, such as slab, wall, ceiling, and the like to construct the concrete foundation block 22 of the protruding structure together, grooves (the upper surface of the foundation block 22) After the fixing bolt 25 is inserted into the 23, the non-shrink concrete is poured into the groove 23 to fix the fixing bolt 25.

Since the fixing bolt 25 fixed as described above has a structure that protrudes and extends from the base block 22, the fixing bolt 25 is inserted into the corresponding fastening hole of the device, and then the nut is fastened to the fixing bolt. It will be completely fixed so that the device does not move.

The base block 22 and the fixing bolt 25 of the block-out for the device base is installed in accordance with the number of fastening holes of the device, by fastening at the same time in a plurality of block-out position can be more securely fixed to the device. Will be.

3 is a process diagram showing the basic construction process of the device according to the prior art, a device foundation, that is, a fixing bolt 25 for fixing the device, a concrete foundation block 22 to which the fixing bolt 25 is fixed, and The construction process of the block out including the cast reinforcing bar 21 to be built into the foundation block 22 is shown divided into three stages.

That is, the construction of the main reinforcing bar 21 and the concrete foundation block 22, the insertion of the fixing bolt 25, can be proceeded to the process of placing the non-contraction concrete 24. Is the same as

First, to install the concrete foundation block 22 to be fastened to the end (or fastening mechanism) of the device, when the foundation concrete 10 where the device is to be installed in the base cast iron 21 for the block base concrete 10 After reinforcement so as to be embedded in the formwork (not shown) around the cast iron reinforcing block 21 for block, and then cast concrete in the formwork to construct the foundation block 22.

At this time, the upper surface of the foundation block 22 to form a groove 23 into which the end of the fixing bolt 25 can be inserted, the formwork is dismantled after the concrete of the foundation block 22 is cured.

Then, the end of the fixing bolt 25 is inserted into the recess 23 of the foundation block 22 constructed, and the non-contraction concrete 24 is poured into the recess 23 into which the end of the fixing bolt 25 is inserted. When the fixing bolt 25 is fixed to the bar, when the non-contraction concrete 24 is cured, the position of the fixing bolt 25 is completely fixed.

On the other hand, in general, a plurality of fastening holes are formed in the device is formed slightly larger than the diameter of the fixing bolt so as to have a little play in the state that the fixing bolt 25 is inserted, respectively, the fixing bolt 25 is fixed If the bolt position does not coincide with the clamping hole position of the device and cannot be inserted, the bolt position must be readjusted.

If the fastening hole position exactly matches the designed position, and the position of the fixing bolt 25 actually constructed also exactly matches the designed fastening hole position, since the fastening hole position and the bolt position do not deviate and coincide with each other, Can be fixed to the foundation.

However, when the fastening hole position does not match the designed position or the actual construction position of the fastening bolt 25 does not match the designed position, it is impossible for each fixing bolt 25 to be inserted into the corresponding fastening hole. It cannot be fixed.

In addition, in the process of pouring the non-concrete concrete 24, the fixing bolt 25 is moved to change the position may cause a problem that the bolt position does not exactly match the position of the fastening hole.

That is, even if you know the exact position of the fastening hole, it is difficult to accurately install the fixing bolt 25 in the correct position, and in order to fix the position of the fixing bolt 25 in the process of pouring non-concrete concrete 24, Need utensils.

If the bolt position and the fastening hole match do not match, it is possible to adjust the bolt position by breaking and re-installing the concrete foundation block 22, but it is not easy to rebuild the concrete foundation block 22 when the machine has already arrived on site. In addition, the process causes a lot of problems.

If it is inevitable to rebuild, it will inevitably increase the time required for fixing the device, and additional time and manpower and costs, as well as delays in the use of the device will result in huge economic losses.

Therefore, the present invention has been invented to solve the above problems, it is possible to precisely construct the fixing bolt fastened to the fastening hole of the device in the correct position in the base block, the position of the fastening bolt is the position of the fastening hole The purpose is to provide a method for basic construction of equipment that can prevent economic losses due to air delays, additional manpower and cost, and delays in equipment operation that may occur due to mismatch.

In order to achieve the above object, the present invention, in the process of constructing the foundation concrete in the place where the device is installed, while installing the embedded plate in the formwork for the foundation concrete, the embedded so that the surface of one side in the foundation concrete can be exposed Installing the plate at a surface location of the foundation concrete; Placing the concrete in the formwork for the foundation concrete to construct the foundation concrete so that the embedded plate is fixed; Fixing the fixing bolt to the exposed surface of the embedded plate to match the position of the fastening hole of the device; Installing a formwork for the block around the embedded plate and the fixing bolt; Provides a device foundation construction method comprising the step of laying the block concrete in the block formwork to construct a foundation block so that a portion of the fixing bolt protrudes outward.

In a preferred embodiment, the embedded plate is fixed to the binding member to be inserted into the base concrete to the surface is embedded in the concrete.

In addition, as a binding member, a stud is welded to and fixed to an embedded surface of an embedded plate.

In addition, after the concrete poured in the formwork for the foundation concrete is cured, the step of drilling a reinforcing rod insertion hole to be inserted into the cast steel reinforcement for the foundation concrete; And inserting the main cast steel for the block into the reinforcing hole, and then installing the formwork for the block, and then placing the concrete for the block so that the main cast steel for the block is constructed by constructing the basic block.

In addition, the block reinforcing bar is inserted into the reinforcing hole, characterized in that it is fixed by the injection of non-contraction concrete in the reinforcing hole to block the main reinforcing bars.

In addition, in the process of constructing the foundation concrete, the block cast iron reinforcement is installed in the formwork for the foundation concrete, and then cast concrete in the formwork for the foundation concrete, the fixed cast iron reinforcement together with the embedded plate when installing the foundation concrete, Then, after installing the formwork for the block is characterized by constructing the foundation block by pouring the concrete for the block so that the cast steel reinforcement for the block.

In addition, by installing a band reinforcing bar reinforcing bar cast steel reinforcement with the cast steel reinforcement for the block concrete is characterized in that the construction of the foundation block.

Accordingly, according to the device foundation construction method according to the present invention, it is possible to precisely install the fixing bolt fastened to the fastening hole of the device in the correct position in the base block, the position of the fastening bolt does not match the position of the fastening hole Economic losses due to air delays, additional manpower and costs, and delays in equipment operation can be avoided.

In particular, after the embedded plate is fixed and installed in the construction of the foundation concrete, after the device is brought into the site, the fixing bolt can be accurately measured to accurately fix the position of the fixing bolt to match the position of the fastening hole. The device can be secured without any additional work that requires repositioning.

In addition, in the method of using the extension beam, even if the embedded plate is installed in the wrong position, the position of the fastening point (position of the fixing bolt) with the device can be precisely adjusted at any time, and it can be installed in accordance with the position of the actual device. The position of the machine foundation structure can be changed more accurately and easily.

In particular, by changing the installation of the fixing bolt to the correct position without any concrete crushing work it is possible to easily change the position of the machine foundation structure and the fastening point position to be final construction.

1 is a plan view showing a typical construction state of the block-out for the foundation of the device fixed to the fixing bolt.
Fig. 2 is a typical construction cross sectional view of a block-out for an instrument foundation having a fixing bolt fixed thereto.
3 is a process chart showing a device-based construction process according to the prior art.
4 is a plan view illustrating a device-based construction state according to the first embodiment of the present invention.
5 is a cross-sectional view showing the basic construction state of the device according to the first embodiment of the present invention.
6 is a process chart showing a device-based construction process according to a first embodiment of the present invention.
7 is a plan view showing a device-based construction state according to a second embodiment of the present invention.
8 is a cross-sectional view showing a device-based construction state according to a second embodiment of the present invention.
9 is a process chart showing a device-based construction process according to a second embodiment of the present invention.
10 is a view illustrating a state in which a pipe of the device is fixed by using a blockout constructed in accordance with the present invention.
11 is a plan view illustrating a device-based construction state according to a third embodiment of the present invention.
12 is a cross-sectional view showing the basic construction state of the device according to the third embodiment of the present invention.
13 is a process chart showing a device-based construction process according to a third embodiment of the present invention.
14 is a plan view showing a device-based construction state according to a fourth embodiment of the present invention.
Fig. 15 is a cross-sectional view showing the basic construction state of the device according to the fourth embodiment of the present invention.
16 is a process chart showing a device-based construction process according to a fourth embodiment of the present invention.

Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those skilled in the art may easily implement the present invention.

FIG. 4 is a plan view showing a device-based construction state according to the first embodiment of the present invention, and FIG. 5 is a cross-sectional view showing a device-based construction state according to the first embodiment of the present invention, and the line 'B-B' of FIG. It is a cross-sectional view taken along. 6 is a process chart showing a device-based construction process according to a first embodiment of the present invention.

In FIG. 5 or FIG. 6, reference numeral 111 denotes a concrete reinforcing bar embedded in the foundation concrete 110. In addition, reference numeral 124 denotes a cast reinforcing bar connected to be embedded in the concrete and the foundation concrete 110 of the foundation block 126, reference numeral 120 denotes an embedded plate 121, fixing bolts 123, cast reinforcing bars 124 and The block-out for the device foundation including the band reinforcement 125, the foundation block 126, and the like is shown.

4 and 5, there are shown an embodiment in which four foundation blocks 126 and four fixing bolts 123 are constructed, one fixing bolt 123 for each foundation block 126. Shows an example where) is installed.

The fixing bolt 123 is installed so as to protrude outwardly from the base block 126 is the same as the conventional, and the block concrete after installing the formwork (not shown) the cast reinforcing bar 124 The process of pouring is no difference.

However, in the present invention, the embedded plate (121) to be installed by adjusting the position of the fixing bolt 123 accurately and precisely according to the position of the fastening hole formed in the fastening end (or fastening mechanism) of the device There is a main feature to using.

Referring to the device foundation construction process according to the present invention in detail, as shown in Figure 6 to install the foundation concrete 110 in the place where the equipment, such as slab, wall, ceiling, etc., the foundation concrete 110 The embedded plate 121 is fixedly installed so that the surface of one side may be exposed in the process.

Here, in order to increase the binding force between the embedded plate 121 and the base concrete 110, a fixing member 122 is inserted into the base concrete 110 and fixed to the embedded surface of the embedded plate 121 to be used. do.

A stud may be used as the binding member 122, which may be fixed by welding to an embedded surface of the embedded plate 121.

In this way, the embedded plate 121, to which the binding member 122 is fixed, is positioned at the surface position of the foundation concrete 110, and the formwork for the foundation concrete so that the binding member 122 can be completely embedded in the foundation concrete 110 (not shown). Not embedded) and the foundation concrete 110 is poured after fixing the embedded plate 121.

When fixing the embedded plate 121 to the surface position of the foundation concrete 110 may be used to bind the fixing member 122 by binding with a concrete reinforcement 111 and the like wires in the formwork for the foundation concrete.

Subsequently, the reinforcement insertion hole 112 is drilled using the drill equipment on the completed basic concrete 110, and the plurality of reinforcement insertion holes 112 are drilled up and down in the periphery of the embedded plate 121.

Subsequently, the fixing bolt 123 is fixed to the exposed surface of the exposed embedded plate 121 by welding. At this time, the fixing bolt 123 is accurately positioned and welded to match the position of the fastening hole for fastening the device.

When the embedded plate 121 is installed and the fixing bolt 123 is fixed in this manner, the fixing bolt 123 is fixed to the fastening hole position in a state where the fastening hole for fastening the device is exactly known. It can be fixed at the correct position to match, and since the position of the fixing bolt 123 does not change even if the concrete of the foundation block 126 is poured, it is possible to precise construction.

After the fixing bolt 123 is installed as described above, the main reinforcing bars 124 and the band reinforcing bars 125 that are embedded in the base block 126 around the fixing bolts 123 are disposed, and the main reinforcing bars 124 are provided. Insert the end of the reinforcing bar 124 into the reinforcing hole 112 so as to be fixed in a standing state on the base concrete 110, and to fix the main reinforcing bar 124 does not move inside the reinforcing hole 112 Non-contraction concrete 113 is injected.

Subsequently, a block formwork is formed to form the foundation block 126 so that the main reinforcing bars 124 and the band reinforcing bars 125 may be embedded around the embedded plate and the fixing bolt, and then concrete is placed inside the block formwork. (Instrument foundation secondary concrete pouring) to form the foundation block 126. After the concrete of the foundation block 126 is cured, the formwork for the block is dismantled.

As a result, as shown in FIGS. 5 and 6, the main reinforcing bar 124 connected between the base concrete 110 and the band reinforcing bar 125 installed in the main reinforcing bar 124 are embedded in the base block 126. In the state in which a part of the fixing bolt 123 welded to the embedded plate 121 that is pre-buried in the foundation concrete 110 is embedded in the foundation block 126, the remaining portion of the fixing bolt is installed to fasten the device. The block out 120 of the structure exposed to the outside of the block 126 is completed.

In each blockout 120, the fixing bolt 123 exposed to the outside of the basic block 126 is inserted into a fastening hole formed at a corresponding fastening end (or fastening mechanism) of the device, and then fixed by fastening a nut. The method is the same as before.

In the first embodiment, the process of drilling the reinforcing hole 112 into the basic concrete 110 and the process of welding the fixing bolt 123 to the embedded plate 121 may be performed in reverse order.

Next, FIG. 7 is a plan view illustrating a device-based construction state according to a second embodiment of the present invention, and FIG. 8 is a cross-sectional view illustrating a device-based construction state according to a second embodiment of the present invention. Sectional view taken along line C-C '. 9 is a process chart showing a device-based construction process according to a second embodiment of the present invention.

In the first embodiment, the embedded plate 121 was purchased during the construction of the foundation concrete 110 and then the reinforcing hole 112 was drilled. However, in the second embodiment, the foundation without additional drilling of the reinforcing hole was performed. In addition to embedding the embedded plate 121 at the time of construction of the concrete 110, the cast reinforcing bars 124 together and installed.

That is, after installing the base concrete formwork (not shown) during the construction of the foundation concrete 10, the main reinforcing bars 124 and the embedded plate 121 is fixed and concrete is poured, and the main reinforcing bars together with the embedded plate 121 ( 124) is embedded and fixed in the foundation concrete.

To this end, the main reinforcing bars 124 to be fixed up and down in the formwork for the foundation concrete, at this time, to fix the main reinforcing bars 124 is used to bind with a concrete reinforcement 111 and the wire reinforcement in the formwork for the foundation concrete is used. Can be.

In this way, by using the method of embedding the main reinforcing bar 124, the drill equipment and the non-concrete concrete is unnecessary, the work using them, that is, the drill operation (rebar insertion hole drilling work) and the non-concrete concrete pouring work can be omitted. .

After the construction of the foundation concrete 110 by embedding the embedded plate 121 and the cast reinforcing bars 124 as described above, by welding the fixing bolt 123 to the embedded plate 121, and then installed After laying the reinforcing bars 125 and install the formwork for blocks (not shown).

After the block formwork is installed, concrete is placed inside the block formwork (equipment foundation secondary concrete placing) to form the foundation block 126, and after the concrete of the foundation block 126 is cured, the block formwork is dismantled. do.

As described above, in the present invention, instead of the method of constructing the foundation block and inserting the fixing bolt into the groove of the foundation block and then placing and fixing the non-concrete concrete, the embedded plate at the time of construction of the foundation concrete 110 ( The construction of 121 and the method of welding and fixing the fixing bolt 123 to the embedded plate 121 are applied, so that the position of the fixing bolt 123 can be accurately and precisely adjusted according to the position of the fastening hole of the device. It becomes possible.

FIG. 10 is a view illustrating a state in which an accessory part of a device is fixed by using a blockout 120 constructed in accordance with the present invention. The foundation block 126, the fixing bolt 123, and the fastening mechanism 132 are constructed. Shows an example of fixing the pipe 131 of the device or equipment using.

As shown, it can be installed by fixing the two fixing bolts 123 to the embedded plate 121, the number of fixing bolts 123 in the present invention is to be fixed to the device (device body or pipe shown) It can be variously changed according to various conditions such as type, shape, size, arrangement state, etc.).

That is, the plurality of fixing bolts 123 may be welded to the embedded plate 121 to be fixed, and the foundation block 126 may be constructed. As illustrated, the fixing bolts 123 may be fixed to the fastening holes of the fastening mechanism 132. ), The pipe 131 may be fixed by fastening the nut 127 to the fixing bolt 123.

At this time, in consideration of the moment (force) acting from the device (pipe) 131 can adjust the position and number of the fastening hole and the fixing bolt 123 of the fastening mechanism 132, the height and lateral position of the fastening point By adjusting the height of the base block 126 and the fixing bolt 123 and precisely adjusting the position of the fixing bolt 123 according to the above, providing a more stable support and fixing state without any problems in construction Can construct a device foundation structure.

FIG. 11 is a plan view illustrating a device-based construction state according to a third embodiment of the present invention, and FIG. 12 is a cross-sectional view illustrating a device-based construction state according to a third embodiment of the present invention. Sectional view taken along line D '. 13 is a process chart showing a device-based construction process according to a third embodiment of the present invention.

According to the third embodiment of the present invention, the embedded plate 121 is first fixedly installed on the foundation concrete 110, and then an extension beam 128 is fixedly installed on the embedded plate 121. 128) proceeds in a manner of fixing the fixing bolt 123 for fastening with the device in the correct position above.

In this manner, since the extension beam 128 is installed on the embedded plate 121 embedded in the foundation concrete 110, the fixing bolt 123 is fixed to the extension beam 128, and thus the foundation concrete 110 is installed. Even if the embedded plate 121 is installed in the wrong position, the position of the fastening point (position of the fixing bolt) with the device can be precisely adjusted at any time, and the device foundation to be constructed in accordance with the actual fastening position with the device It is possible to change the position of the structure more accurately and easily.

In particular, since the method of fixing the position of the fixing bolt 123 on the extension beam 128 after the construction of the foundation concrete 110, before the concrete for block construction, fixing bolt 123 without any concrete crushing work By changing and installing the position of the device to the correct position, it is possible to easily change the position and the fastening point position of the machine foundation structure to be finally constructed.

The extension beam 128 is a rigid body structurally connecting the foundation block 126 and the fixing bolt 123 with the embedded plate 121, it is possible to use H-shaped steel, c-shaped steel, L-shaped steel, basic concrete ( 110 is fixed by welding on the surface of the embedded plate 121 exposed above.

In addition, the fixing bolt 123 is fixed by welding vertically on the extension beam (128).

Hereinafter, the device foundation construction process according to the third embodiment of the present invention will be described in detail, as shown in Figure 13, the construction of the foundation concrete 110 in the place where the equipment, such as slabs, walls, ceilings will be installed, In the process of pouring the concrete 110, the embedded plate 121 is fixedly installed so that one surface thereof is exposed.

The installation process of the embedded plate 121 is performed in the same process as in the first and second embodiments.

As such, when the installation of the embedded plate 121 is completed, when the fixing bolt 123 is fixedly installed on the embedded plate 121 as it is, the position of the fastening hole of the device that arrives at the site and is actually installed is the fixing bolt ( If the position of the fastening point with the device is located outside the embedded plate 121 while not coinciding with the position of 123, the position of the fixing bolt 123 (fastening point position) is reset to a position outside the embedded plate 121. In order to install the extension beam 128.

In this case, the extension beam 128 is welded to be extended to one side on the exposed surface of the embedded plate 121 embedded in the foundation concrete 110, and a plurality of extension beams 128 are provided as shown in FIG. 11. It is also possible to install side by side on the embedded plate 121.

Subsequently, the reinforcing hole 112 is drilled in the foundation concrete 110 in accordance with the construction position of the foundation block 126 in the section in which the extension beam 128 is installed. Perforate 112) up and down long.

Subsequently, the main reinforcing bars 124 and the band reinforcing bars 125 that are embedded in the base block 126 are disposed around the fixing bolt 123, so that the main reinforcing bars 124 may be fixed in a standing state on the base concrete 110. After inserting the end of the reinforcing bar 124 into the reinforcing hole 112 and inject the non-contracted concrete 113 to fix the main reinforcing bar 124 does not move into the reinforcing hole (112).

When the reinforcement work of the reinforcing bar for the block is completed as described above, by fixing the fixing bolt 123 on the extension beam 128 to be fixed, the fixing bolt 123 to match the position of the fastening hole for fastening the device Place the weld correctly.

Subsequently, a block formwork is formed for forming the foundation block 126 so that the main reinforcing bars 124 and the band reinforcing bars 125 may be embedded around the embedded plate 121 and the fixing bolt 123. Placing concrete in the formwork (apparatus foundation secondary concrete casting) to form the foundation block 126. After the concrete of the foundation block 126 is cured, the formwork for the block is dismantled.

As a result, as shown in Figs. 11 and 12, the main reinforcing bar 124 connected between the base concrete 110 and the band reinforcing bar 125 provided in the main reinforcing bar 124 is embedded in the base block 126, In a state in which a part of the fixing bolt 123 welded to the extension beam 128 is embedded in the base block 126, the other part of the fixing bolt 123 is moved to the outside of the base block 126 for fastening the device. The blockout 120 of the exposed structure is completed.

In the blockout 120 thus completed, the basic block 126 supporting the device and the fixing bolt 123 fastened to the device are provided through the extension beam 128, the embedded plate 121, and the main reinforcing bar 124. It can be structurally firmly connected to the foundation concrete (110).

In each blockout 120, the fixing bolt 123 exposed to the outside of the basic block 126 is inserted into a fastening hole formed at a corresponding fastening end (or fastening mechanism) of the device, and then fixed by fastening a nut. The method is the same as before.

In the third embodiment, the reinforcement work of the reinforcing bars for reinforcing the main reinforcing bars 124 and the band reinforcing bars 125 and the process of welding the fixing bolts 123 on the extension beam 128 are performed in reverse order. It does not matter.

That is, the fixing bolt 123 may be welded on the extension beam 128 first, and then the reinforcement work of the reinforcing bar may be performed.

FIG. 14 is a plan view illustrating a device-based construction state according to a fourth embodiment of the present invention, and FIG. 15 is a cross-sectional view illustrating a device-based construction state according to a fourth embodiment of the present invention. It is a cross-sectional view taken along. 16 is a process chart showing a device-based construction process according to a fourth embodiment of the present invention.

The fourth embodiment of the present invention is different from the installation method of the main reinforcing bars 124 of the reinforcing bar compared to the third embodiment, the main reinforcing bars 124 embedded in the base block 126 to the extension beam 128 There is a difference in the way of welding and fixing.

That is, the embedded plate 121 is first fixed to the foundation concrete 110, and then the extension beam 128 is fixedly installed on the embedded plate 121. Then, the main reinforcing bar 124 is perpendicular to the extension beam 128. After the installation by welding and then reinforcing the band reinforcing bars 125, and then proceeds to the installation of the fixing bolt 123, the formwork for the block, the concrete pouring for the block in order to complete the basic structure of the device.

As described above, all processes may be performed in the same manner as in the third embodiment except that the main reinforcing bar 124 is welded to the extension beam 128.

When the main reinforcing bar 124 is fixedly installed in the extension beam 128 as described above, the drilling process for forming the reinforcing hole is omitted, which eliminates the need for drilling equipment and non-concrete concrete, and thus uses the drill. Work (rebar insertion hole drilling work) and non-concrete concrete pouring work can be omitted.

In this way, the embodiment using the extension beam has been described in detail, and it is possible to construct the device foundation in parallel with the third and fourth embodiments of the first and second embodiments.

That is, as shown in Figure 4 and 7, in the construction of a plurality of block out 120 in the base concrete 110, some of the method of the first embodiment and the second embodiment, some of the third embodiment and It is to be constructed by the method of the fourth embodiment.

At this time, after embedding the embedded plate in the foundation concrete, the extension beam 128 as shown in Figs. The method of use may be applied.

While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is to be understood that the scope of the present invention is not limited to the disclosed exemplary embodiments. Modified forms are also included within the scope of the present invention.

110: foundation concrete 111: concrete reinforcement
112: reinforcement hole 113: non-contraction concrete
120: blockout 121: embedded plate
122: binding member 123: fixing bolt
124: cast iron 125: band steel
126: foundation block 127: nut
128: extension beam 131: pipe
132: Fastening Mechanism

Claims (13)

In the process of constructing the foundation concrete 110 at the place where the device is to be installed, the embedded plate 121 is installed in the formwork for the foundation concrete, but the embedded plate 121 is exposed so that one surface of the foundation concrete 110 is exposed. ) At the surface position of the foundation concrete (110);
Placing the concrete in the formwork for the foundation concrete to construct the foundation concrete 110 so that the embedded plate 121 is fixed;
Fixing a fixing bolt 123 to an exposed surface of the embedded plate 121 so as to match a position of a fastening hole of the device;
Installing a formwork for the block around the embedded plate 121 and the fixing bolt 123;
Placing a block concrete in the block formwork to construct a foundation block 126 so that a part of the fixing bolt 123 protrudes outward;
Device-based construction method comprising a.
The method according to claim 1,
Device embedded construction method, characterized in that for fixing the binding member 122 is inserted into the base concrete 110, the surface is embedded in the embedded concrete plate (121).
The method according to claim 2,
Method of mounting the base member, characterized in that the stud is welded and fixed to the embedded surface of the embedded plate 121 as the binding member (122).
The method according to claim 1,
Drilling the reinforcing hole 112 into which the main cast steel 124 for the block is inserted into the foundation concrete 110 after the concrete poured in the formwork for the foundation concrete is cured;
Inserting the block reinforcing bar reinforcement 124 into the reinforcing rod insertion hole 112;
Proceed to, and then install the formwork for the block after the installation of the block concrete so that the main cast reinforcing block (124) is embedded, the basic block 126 construction method, characterized in that the construction of the foundation block.
The method of claim 4,
After inserting the main cast iron 124 for the block into the reinforcement hole 112, the non-concrete concrete 113 is injected into the reinforcing hole 112 to fix the main cast iron 124 for the block foundation Way.
The method according to claim 1,
In the process of constructing the foundation concrete 110, the block cast iron reinforcing bars 124 in the formwork for the foundation concrete is installed and then cast concrete in the formwork for the foundation concrete, embedded plate 121 during the construction of the foundation concrete (110) And fixed with the main cast reinforcing bar 124 together, and then install the formwork for the block and then cast the concrete for the block so that the cast main reinforcing bars 124 is built, characterized in that the construction of the foundation block 126 Instrument foundation construction method.
The method according to claim 4 or 6,
Instrument base, characterized in that the installation of the base block 126 by installing a concrete for the block so that the band reinforcing bars 125 are embedded with the main reinforcing bars 124 to install the band reinforcing bars (124) Construction method.
In the process of constructing the foundation concrete 110 at the place where the device is to be installed, the embedded plate 121 is installed in the formwork for the foundation concrete, but the embedded plate 121 is exposed so that one surface of the foundation concrete 110 is exposed. ) At the surface position of the foundation concrete (110);
Placing the concrete in the formwork for the foundation concrete to construct the foundation concrete 110 so that the embedded plate 121 is fixed;
Fixing an extension beam (128) extending to one side on an exposed surface of the embedded plate (121);
Fixing a fixing bolt (123) to the extension beam (128) so as to match the position of the fastening hole of the device;
Installing a formwork for block around the fixing bolt (123);
Placing a block concrete in the block formwork to construct a foundation block 126 so that a part of the fixing bolt 123 protrudes outward;
Device-based construction method comprising a.
The method according to claim 8,
Device embedded construction method, characterized in that for fixing the binding member 122 is inserted into the base concrete 110, the surface is embedded in the embedded concrete plate (121).
The method according to claim 8,
Drilling the reinforcing hole 112 into which the main cast iron 124 for the block is inserted into the basic concrete 110 after the concrete cast in the formwork for the basic concrete is cured;
Inserting the block reinforcing bar reinforcement 124 into the reinforcing rod insertion hole 112;
Proceed to install the formwork for the block, and then install the block concrete so that the main cast reinforcing bar (124) is embedded, the device foundation construction method, characterized in that for constructing the foundation block (126).
The method according to claim 10,
After inserting the main cast iron 124 for the block into the reinforcement hole 112, the non-concrete concrete 113 is injected into the reinforcing hole 112 to fix the main cast iron 124 for the block foundation Way.
The method according to claim 8,
After the fixed installation of the extension beam 128, the block cast reinforcing bars 124 are installed upright on the extension beam 128, and after installing the formwork for the block cast concrete for the block so that the cast reinforcing bar 124 is embedded Instrument foundation construction method characterized in that the construction of the foundation block (126).
The method according to claim 10 or 12,
Instrument base, characterized in that the installation of the base block 126 by installing a concrete for the block so that the band reinforcing bars 125 are embedded with the main reinforcing bars 124 to install the band reinforcing bars (124) Construction method.






KR1020100140447A 2010-12-31 2010-12-31 Block out construction method for apparatus base KR20120078217A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100140447A KR20120078217A (en) 2010-12-31 2010-12-31 Block out construction method for apparatus base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100140447A KR20120078217A (en) 2010-12-31 2010-12-31 Block out construction method for apparatus base

Publications (1)

Publication Number Publication Date
KR20120078217A true KR20120078217A (en) 2012-07-10

Family

ID=46711600

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100140447A KR20120078217A (en) 2010-12-31 2010-12-31 Block out construction method for apparatus base

Country Status (1)

Country Link
KR (1) KR20120078217A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101708760B1 (en) * 2016-08-26 2017-02-21 동서 피, 씨, 씨 주식회사 Construction method for precast concrete wall
CN106917413A (en) * 2017-02-21 2017-07-04 东莞市鹏翼自动化科技有限公司 A kind of solid wood base beam fixture construction
KR20210149305A (en) 2020-06-02 2021-12-09 김종섭 Anchor bolt for use of a constructing building

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101708760B1 (en) * 2016-08-26 2017-02-21 동서 피, 씨, 씨 주식회사 Construction method for precast concrete wall
CN106917413A (en) * 2017-02-21 2017-07-04 东莞市鹏翼自动化科技有限公司 A kind of solid wood base beam fixture construction
KR20210149305A (en) 2020-06-02 2021-12-09 김종섭 Anchor bolt for use of a constructing building

Similar Documents

Publication Publication Date Title
KR101860512B1 (en) Method for reinforcing cross section installation of ground and underwater structure using integral mold module
KR20180072968A (en) Permanent form for pier and construction method using the same
KR20110128396A (en) Pre-embedded anchor frame equipped with coupler and anchoring method of steel column thereof
KR100895881B1 (en) Underground tunnel formation infrastructure establishment method
KR100622935B1 (en) Horizontal extension joint structuer and joint method using thereof
JP2011001717A (en) Method for connecting precast column and foundation, and temporary receiving frame
JP6543077B2 (en) Construction method of structure
KR20120078217A (en) Block out construction method for apparatus base
KR200407092Y1 (en) Support Structure for PC Panel of Cantilever Part
KR100653283B1 (en) Method for connecting reinforced concrete structures
KR20130087137A (en) Noise barrier basis and construction method thereof
KR102269141B1 (en) Deck plate wall installation method using underground pavement
KR100626326B1 (en) concrete structure
KR200422931Y1 (en) A pile head reinforcement structure of steel pile
KR101482523B1 (en) Nodular Box Girder, and Nodular Box Girder Bridge and Constructing Method thereof
KR101947418B1 (en) Continuous construction method for precast reinforced concrete structure and steel-framed structure and precast reinforced concrete column for using the method
JP2018178588A (en) Bridge construction method
KR100456192B1 (en) Composition of precast concrete wall and precast concrete column for outdoor to sustain external force
JPH1077607A (en) Method of executing viaduct by using pca concrete member
JP5056534B2 (en) Structure installation method for water gradient floor
JP7288390B2 (en) Foundation construction method and foundation
JP6710064B2 (en) Seismic isolation retrofit construction method and building construction
JP2864906B2 (en) Precast wall joining method
JP4511080B2 (en) Construction method of underground structure
KR200362827Y1 (en) concrete structure

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E902 Notification of reason for refusal
E601 Decision to refuse application