KR101947418B1 - Continuous construction method for precast reinforced concrete structure and steel-framed structure and precast reinforced concrete column for using the method - Google Patents

Continuous construction method for precast reinforced concrete structure and steel-framed structure and precast reinforced concrete column for using the method Download PDF

Info

Publication number
KR101947418B1
KR101947418B1 KR1020180087233A KR20180087233A KR101947418B1 KR 101947418 B1 KR101947418 B1 KR 101947418B1 KR 1020180087233 A KR1020180087233 A KR 1020180087233A KR 20180087233 A KR20180087233 A KR 20180087233A KR 101947418 B1 KR101947418 B1 KR 101947418B1
Authority
KR
South Korea
Prior art keywords
reinforced concrete
precast reinforced
fixing part
steel structure
lower fixing
Prior art date
Application number
KR1020180087233A
Other languages
Korean (ko)
Inventor
나금옥
Original Assignee
동서 피, 씨, 씨 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 동서 피, 씨, 씨 주식회사 filed Critical 동서 피, 씨, 씨 주식회사
Priority to KR1020180087233A priority Critical patent/KR101947418B1/en
Application granted granted Critical
Publication of KR101947418B1 publication Critical patent/KR101947418B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/185Connections not covered by E04B1/21 and E04B1/2403, e.g. connections between structural parts of different material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The present invention relates to a method of continuously constructing a precast reinforced concrete structure and a steel structure, the method including a first step of installing a precast reinforced concrete column having a plurality of main beams exposed at an upper portion thereof; a second step of placing a precast reinforced concrete beam on the precast reinforced concrete column; a third step of installing a lower fixing part on the exposed main beam; a fourth step of placing the upper reinforcing bar in the precast reinforced concrete beam; a fifth step of positioning a fixture of the steel structure on the lower fixing part of the exposed main beam and installing the upper fixing part; a sixth step of placing on-site pouring concrete between the precast reinforced concrete beam and the precast reinforced concrete column; and a seventh step of pouring non-shrinkable mortar into a space between the on-site pouring concrete and the fixture of the steel structure. In the third step, the installation height of the lower fixing part is determined such that the on-site pouring concrete is positioned below the fixture of the steel structure. The fixture of the steel structure is installed on the precast reinforced concrete column before on-site pouring of topping concrete of the precast reinforced concrete beam, and thus the precast reinforced concrete structure and the steel structure can be continuously built by means of the same building process and apparatus.

Description

프리캐스트 철근콘크리트 구조물과 철골 구조물을 연속 시공하는 방법과 이에 사용된 프리캐스트 철근콘크리트 기둥{CONTINUOUS CONSTRUCTION METHOD FOR PRECAST REINFORCED CONCRETE STRUCTURE AND STEEL-FRAMED STRUCTURE AND PRECAST REINFORCED CONCRETE COLUMN FOR USING THE METHOD}TECHNICAL FIELD [0001] The present invention relates to a method of continuously constructing a precast reinforced concrete structure and a steel structure, and a precast reinforced concrete column used for the precast reinforced concrete structure and a precast reinforced concrete column,

본 발명은 철근콘크리트 구조물에 철골 구조물을 연속적으로 시공하는 방법에 관한 것으로, 더욱 자세하게는 하부의 프리캐스트 철근콘크리트 기둥과 보를 시공하면서 상부의 철골 구조물을 함께 연속적으로 시공하는 방법에 관한 것이다.The present invention relates to a method of continuously constructing a steel structure in a reinforced concrete structure, and more particularly, to a method of continuously constructing an upper steel structure together with a lower precast reinforced concrete column and a beam.

일반적으로 다수의 층으로 구성된 건물은 주요 뼈대로서 기둥과 보가 설치되며, 이러한 기둥과 보를 구성하는 재료에 따라서 건축물의 기본 형태가 나뉘며, 대표적으로 기둥과 보가 철근이 매설된 콘크리트로 구성된 철근콘크리트 구조의 건물과 기둥과 보에 철골을 사용하는 철골 구조의 건물이 있다.Generally, a multi-story building has columns and beams as main skeletons, and the basic form of the building is divided according to the materials constituting the columns and beams. Typically, a reinforced concrete structure composed of concrete in which columns and beams are embedded with reinforcing bars There is a steel-framed building with steel columns in the building, pillars and beams.

철근콘크리트 구조와 철골 구조는 각각이 장점과 단점이 있으며, 최근에는 건물의 하부층에 내화와 진동변이에 유리한 철근콘크리트 구조를 적용하고 상부층에는 가벼운 재질로 지진에 유리한 철골 구조를 적용한 복합 구조의 건물도 사용되고 있다.Reinforced concrete structure and steel structure have advantages and disadvantages respectively. Recently, reinforced concrete structure which is favorable for fire resistance and vibration variation is applied to the lower layer of the building, and a composite structure of steel structure with light material for earthquake .

도 10은 철근콘크리트 구조와 철골 구조가 복합 적용된 구성을 도시한 모식도이다.10 is a schematic diagram showing a configuration in which a reinforced concrete structure and a steel frame structure are combined.

철근콘크리트 기둥과 철근콘크리트 보를 포함하는 철근콘크리트 구조물(1000)로 하부층(L)을 구성한 뒤에, 철근콘크리트 구조물(1000)의 위에 철골 기둥과 철골 보를 포함하는 철골 구조물(2000)을 설치하여 상부층(H)을 구성한다.A steel structure 2000 including a steel column and a steel beam is installed on a reinforced concrete structure 1000 after a lower layer L is constructed with a reinforced concrete structure 1000 including a reinforced concrete column and a reinforced concrete beam, ).

이때, 하부층(L)을 구성하는 철근콘크리트 구조물(1000)은 보 철근과 기둥 주근이 X, Y방향으로 촘촘히 엮여있기 때문에, 철골 구조물(2000)의 정착(앵커)철물을 정확한 위치에 설치하는 것은 어려우며, 잘못 시공되는 경우에 보수나 보강도 어려운 단점이 있다. 철근콘크리트 구조물(1000)로서 미리 제작하여 현장에서 시공하는 프리캐스트 철근콘크리트 기둥과 보를 사용하는 경우에, 현장에서 거푸집을 사용하여 제조하는 경우에 비하여 철골 구조물(2000)의 정착(앵커)철물을 정확한 위치에 설치할 수 있다. 다만, 현재는 프리캐스트 철근콘크리트 기둥과 보를 연결하기 위한 콘크리트의 현장 타설까지 끝내서 철근콘크리트 구조물(1000)을 완성한 뒤에 철골 구조물(2000)의 정착(앵커)철물을 설치하기 때문에, 철근콘크리트 부분과 철골부분의 시공이 별도의 장비와 별도의 시공공정으로 이루어지면서 설치 시간이 길어지는 단점이 있다.At this time, since the reinforced concrete structure 1000 constituting the lower layer L is tightly bonded in the X and Y directions with the reinforcement and the column main body, the anchor hardware of the steel structure 2000 is installed at an accurate position And it is difficult to repair or reinforce it if it is erroneously applied. In the case of using precast reinforced concrete columns and beams that are prefabricated as reinforced concrete structures (1000) and constructed in the field, compared to the case where the formworks are used in the field, the anchors of steel structures (2000) Location. However, since the anchor hardware of the steel structure 2000 is installed after completing the reinforced concrete structure 1000 by completing the field installation of the concrete for connecting the precast reinforced concrete column with the beam, The construction of the part is performed by a separate construction process from the separate equipment, and the installation time is lengthened.

대한민국 등록특허 10-0442548Korea Patent No. 10-0442548

본 발명은 전술한 종래 기술의 문제점을 해결하기 위한 것으로서, 하부 프리캐스트 철근콘크리트 기둥과 보를 시공하면서 접합부 및 슬래프의 토핑 콘크리트의 타설 없이, 상부 철골 구조물을 함께 연속적으로 시공하는 방법을 제공하는데 그 목적이 있다.It is an object of the present invention to provide a method of continuously constructing upper steel structures together without installing topping concrete of joints and slabs while constructing lower precast reinforced concrete columns and beams, There is a purpose.

상기 목적을 달성하기 위한 본 발명에 의한 프리캐스트 철근콘크리트 구조물과 철골 구조물을 연속 시공하는 방법은, 상부에 복수의 주근이 노출된 프리캐스트 철근콘크리트 기둥을 설치하는 제1단계; 상기 프리캐스트 철근콘크리트 기둥에 프리캐스트 철근콘크리트 보를 위치시키는 제2단계; 상기 노출된 주근에 하부 고정부를 설치하는 제3단계; 상기 프리캐스트 철근콘크리트 보에 상단철근을 배근하는 제4단계; 상기 노출된 주근의 하부 고정부 위에 철골 구조물의 정착철물을 위치시키고 상부 고정부를 설치하는 제5단계; 상기 프리캐스트 철근콘크리트 보와 상기 프리캐스트 철근콘크리트 기둥의 사이에 현장타설 콘크리트를 타설하는 제6단계; 및 상기 현장타설 콘크리트와 상기 철골 구조물의 정착물의 사이의 공간에 무수축 모르타르를 타설하는 제7단계를 포함하고, 상기 제3단계에서, 현장타설 콘크리트가 상기 철골 구조물의 정착물보다 아래에 위치되도록, 상기 하부 고정부의 설치 높이가 결정되는 것을 특징으로 한다.According to another aspect of the present invention, there is provided a method of continuously constructing a pre-cast reinforced concrete structure and a steel structure, the method comprising: a first step of installing a precast reinforced concrete column having a plurality of main beams exposed at an upper portion thereof; Placing a precast reinforced concrete beam on the precast reinforced concrete column; A third step of installing a lower fixing part on the exposed main frame; A fourth step of placing the upper reinforcing bars in the precast reinforced concrete beams; A fifth step of placing a fixture of a steel frame structure on a lower fixture of the exposed main beam and installing an upper fixture; Placing a spotting concrete between the precast reinforced concrete beam and the precast reinforced concrete column; And a seventh step of pouring non-shrinking mortar into a space between the locally-placed concrete and the fixture of the steel structure, wherein in the third step, the locally-placed concrete is positioned below the fixture of the steel structure, And an installation height of the lower fixing part is determined.

본 발명은 프리캐스트 철근콘크리트 기둥과 보를 설치하는 과정에서, 프리캐스트 철근콘크리트 보의 토핑(toping) 콘크리트를 현장 타설하기 전에, 상부 철골 구조물을 프리캐스트 철근콘크리트 기둥에 설치하는 점에 특징이 있다. 이러한 구성으로부터, 프리캐스트 철근콘크리트 구조물과 철골 구조물을 동일한 시공과정과 장치를 사용하여 연속적으로 시공할 수 있는 장점이 있다.The present invention is characterized in that an upper steel structure is installed on a precast reinforced concrete column prior to casting a toe concrete of a precast reinforced concrete beam in the process of installing precast reinforced concrete columns and beams. From this configuration, there is an advantage that the precast reinforced concrete structure and the steel structure can be continuously constructed using the same construction process and apparatus.

노출된 주근을 감싸는 후프형 철근을 설치하는 단계를 제2단계의 직전 또는 직후에 더 수행하여, 주근이 휘는 것을 방지할 수 있다.The step of installing the hoop-shaped reinforcing bars surrounding the exposed main ropes may be further performed immediately before or after the second step to prevent the main ropes from being bent.

주근을 감싸는 후프형 철근을 프리캐스트 철근콘크리트 기둥을 제작하는 과정에서 설치하여 제공할 수도 있고, 제1단계를 수행하기 전에 후프형 철근을 설치할 수도 있다.The hoop type reinforcing bar surrounding the main frame may be installed in the process of manufacturing the precast reinforced concrete column, or the hoop type reinforcement may be installed before the first step.

노출된 주근의 끝부분 적어도 일부에 나사산이 형성되고, 하부 고정부는 하부 너트를 포함하여 구성되며, 제3단계가 하부 너트를 나사산에 체결하여 수행되는 것이 바람직하다. 하부 너트를 사용하면, 하부 고정부의 설치 높이를 매우 정밀하게 조절하는 것이 가능하다. 이때, 상부 고정부도 상부 너트를 포함하여 구성되며, 제5단계도 상부 너트를 나사산에 체결하여 수행되는 것이 바람직하다.A thread is formed on at least a part of the end of the exposed main body, the lower fixing part includes a lower nut, and the third step is performed by fastening the lower nut to the thread. By using the lower nut, it is possible to adjust the installation height of the lower fixing part with high precision. At this time, the upper fixing part also includes an upper nut, and the fifth step is also performed by fastening the upper nut to the thread.

그리고 하부 고정부들이 수평을 이루며 정확한 위치에 설치될 수 있도록, 주근에 끼워지는 가설판을 하부 고정부의 위에 위치시킨 상태에서 하부 고정부의 설치 높이를 조절하는 방법으로 제3단계를 수행하는 것이 좋다. 가설판을 사용하는 경우, 제4단계에서는 가설판을 제거한 뒤에 상단철근을 배근하는 것이 바람직하다.The third step is to adjust the installation height of the lower fixing part in such a state that the lower fixing parts are horizontally positioned and installed on the lower fixing part, good. In the case where the temporary plate is used, it is preferable to remove the temporary plate and then insert the upper reinforcing bar in the fourth step.

제3단계 이후에, 하부 고정부의 설치 위치를 고정하기 위한 수평가이드철근을 설치하는 단계를 더 수행할 수 있다.After the third step, a step of installing a horizontal guide reinforcing bar for fixing the installation position of the lower fixing part can be further performed.

본 발명의 다른 형태에 의한 프리캐스트 철근콘크리트 기둥은, 프리캐스트 철근콘크리트 구조물과 철골 구조물을 연속 시공하는 방법에 사용되는 프리캐스트 철근콘크리트 기둥으로서, 콘크리트 재질의 기둥 몸체; 및 상기 기둥 몸체에 내에 길이방향으로 삽입되며 기둥 몸체의 상부로 적어도 일부가 노출된 주근을 포함하며, 상기 주근은, 프리캐스트 철근 콘크리트 기둥의 위에 설치되는 철골 구조물의 정착철물 하부판에 형성된 설치공의 위치와 개수에 맞추어져 있고, 상기 노출된 주근의 끝부분 적어도 일부에 나사산이 형성된 것을 특징으로 한다.A precast reinforced concrete column according to another aspect of the present invention is a precast reinforced concrete column used for a continuous construction method of a precast reinforced concrete structure and a steel structure, comprising: a columnar body of a concrete material; And a main body inserted into the column body in the longitudinal direction and exposed at least a part of the upper portion of the column body, the main body of the main body comprising: a mounting hole formed in the lower plate of the fixing steel frame of the steel structure installed on the precast reinforced concrete column; And a screw thread is formed on at least a part of the end of the exposed main shaft.

이때, 주근을 감싸는 후프형 철근을 더 포함할 수 있다. At this time, it is possible to further include a hoop reinforcing bar surrounding the main frame.

상술한 바와 같이 구성된 본 발명은, 프리캐스트 철근콘크리트 구조물의 토핑 콘크리트를 현장 타설하기 전에 상부 철골 구조물의 정착물을 프리캐스트 철근콘크리트 기둥에 설치함으로써, 프리캐스트 철근콘크리트 구조물과 철골 구조물을 동일한 시공과정과 장치를 사용하여 연속적으로 시공할 수 있는 효과가 있다.The present invention having the above-described structure is characterized in that, by installing the fixtures of the upper steel structure on the pre-cast reinforced concrete columns before putting the topping concrete of the precast reinforced concrete structure on the site, the precast reinforced concrete structure and the steel structure are subjected to the same construction process There is an effect that continuous construction can be carried out by using the apparatus.

또한, 현장타설 콘크리트를 타설하기 전에 철골 구조물의 정착철물을 설치함으로써, 이동식장비가 진입하여 한꺼번에 조립하고 나오면서 시공하여 장비의 효율이 높아지고 접합부의 시공간편성도 극대화되며 앵커철근의 정착 길이도 필요 없어지는 뛰어난 효과가 있다.In addition, by installing steel fixture of steel structure before installing cast-in-place concrete, it is possible to increase the efficiency of equipment by maximizing the time-space knitting of the joint and maximizing the length of anchor steel It has excellent effect.

도 1은 본 실시예에 따른 연속시공을 위한 프리캐스트 철근콘크리트 기둥의 상부를 도시한 도면이다.
도 2는 본 실시예에 따른 연속시공을 위한 프리캐스트 철근콘크리트 기둥에 프리캐스트 철근콘크리트 보를 위치시킨 모습을 표시한 도면이다.
도 3은 본 실시예에 따른 연속시공을 위한 프리캐스트 철근콘크리트 기둥의 상부에 노출된 주근에 후프형 철근을 설치한 모습을 도시한 도면이다.
도 4는 본 실시예에 따른 연속시공을 위한 프리캐스트 철근콘크리트 기둥의 상부에 노출된 주근에 하부 고정부를 설치한 모습을 도시한 도면이다.
도 5는 본 실시예에 따른 연속시공을 위한 프리캐스트 철근콘크리트 기둥의 주근에 설치된 하부 고정부의 위치를 가이드하기 위한 수평가이드철근을 설치한 모습을 도시한 도면이다.
도 6은 본 실시예에 따른 연속시공을 위한 프리캐스트 철근콘크리트 기둥의 주근에서 가설판을 제거한 상태로 프리캐스트 철근콘크리트 보에 상단철근을 배근한 모습을 도시한 도면이다.
도 7은 본 실시예에 따른 연속시공을 위한 프리캐스트 철근콘크리트 기둥의 주근에 철골구조물의 정착철물과 상부 고정부를 설치한 모습을 도시한 도면이다.
도 8은 본 실시예에 따른 연속시공을 위한 프리캐스트 철근콘크리트 기둥과 프리캐스트 철근콘크리트 보의 사이에 현장타설 콘크리트를 타설한 모습을 도시한 도면이다.
도 9는 본 실시예에 따른 연속시공을 위한 프리캐스트 철근콘크리트 기둥에 설치된 철골 구조물의 정착철물과 현장타설 콘크리트의 사이에 무수축 모르타르를 타설한 모습을 도시한 도면이다.
1 is a top view of a precast reinforced concrete column for continuous construction according to the present embodiment.
FIG. 2 is a view showing a precast reinforced concrete beam positioned on a precast reinforced concrete column for continuous construction according to the present embodiment. FIG.
3 is a view showing a state in which a hoop type reinforcing bar is installed on a main body exposed on an upper part of a precast reinforced concrete column for continuous construction according to the present embodiment.
4 is a view showing a state in which a lower fixing part is installed on a main beam exposed on an upper part of a precast reinforced concrete column for continuous construction according to the present embodiment.
5 is a view showing a horizontal guide reinforcing bar installed to guide a position of a lower fixing part installed on a main frame of a precast reinforced concrete column for continuous construction according to the present embodiment.
FIG. 6 is a view showing a state in which the upper reinforcing bars are installed in the precast reinforced concrete beams in a state where the temporary plates are removed from the main rods of the precast reinforced concrete columns for continuous construction according to the present embodiment.
FIG. 7 is a view showing a state in which a fixture of a steel structure and an upper fixing part are installed on a main frame of a precast reinforced concrete column for continuous construction according to the present embodiment.
FIG. 8 is a view showing a placement of a spotted concrete between a pre-cast reinforced concrete column and a pre-cast reinforced concrete beam for continuous construction according to the present embodiment.
FIG. 9 is a view showing the installation of non-shrinkable mortar between the fixing hardware of the steel structure installed on the pre-cast reinforced concrete column for continuous construction according to the present embodiment and the cast concrete placed on-site.

첨부된 도면을 참조하여 본 발명에 따른 실시예를 상세히 설명한다. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Referring to the accompanying drawings, embodiments of the present invention will be described in detail.

도 1 내지 도 9는 본 발명의 실시예에 따라서 프리캐스트 철근콘크리트 구조물과 철골 구조물을 연속 시공하는 과정을 도시한 도면이다.FIGS. 1 to 9 are views showing a process of continuously constructing a precast reinforced concrete structure and a steel structure according to an embodiment of the present invention.

도 1은 본 실시예에 따른 연속시공을 위한 프리캐스트 철근콘크리트 기둥의 상부를 도시한 도면이다.1 is a top view of a precast reinforced concrete column for continuous construction according to the present embodiment.

본 실시예의 프리캐스트 철근콘크리트 기둥(100)은 미리 공장에서 제작되어 현장에서 설치되는 프리캐스트 철근콘크리트 시공 방법에 적용되는 기둥이다. 프리캐스트콘크리트 시공 방법은 미리 제작된 기둥과 보를 현장에서 설치 및 결합하는 시공방법이며, 현장에 기둥과 보를 위한 거푸집을 세우지 않으며, 기둥과 보를 결합하는 과정에서 일부의 현장 타설 콘크리트를 타설하여 시공된다. The precast reinforced concrete column 100 of the present embodiment is a column that is applied to a precast reinforced concrete construction method previously installed in a factory and installed in the field. Precast concrete construction method is a construction method in which pre-fabricated columns and beams are installed and combined at the site. In the process of joining columns and beams, concrete is put into place by placing some of the cast concrete .

본 실시예의 프리캐스트 철근콘크리트 기둥(100)은 내부에 주근을 포함하여 제작되는 프리캐스트 철근콘크리트 기둥의 구성이 제한 없이 적용될 수 있으며, 다만 프리캐스트 철근콘크리트 기둥(100)의 상부로 주근(110)의 끝부분이 노출되고, 노출된 주근(110)의 끝부분 적어도 일부에는 나사산(112)이 형성된 점에 특징이 있다. 도 1에 삽입된 도면은 프리캐스트 철근콘크리트 기둥(100)을 위쪽에서 바라본 평면도이다. 이때, 프리캐스트 철근콘크리트 기둥(100)의 주근(110)은 일반적인 프리캐스트 철근콘크리트 기둥과 동일하게 제작될 수도 있으나, 상부에 철골 구조가 연속 시공되는 특징을 감안한 사전 구조검토를 기준으로, 주근의 개수가 추가되거나 위치가 변경될 수도 있다. 본 실시예에서는 철골 구조물의 정착철물 하부판에 형성된 설치공의 위치와 개수에 맞추어 8개의 주근(110)을 사용하여 프리캐스트 철근콘크리트 기둥(100)을 제작하였다. 상기한 특징을 제외한 프리캐스트 철근콘크리트 기둥(100)의 구성은 특별히 제한되지 않으므로 자세한 설명을 생략한다. The precast reinforced concrete column 100 of the present embodiment can be applied without limitation to the structure of the precast reinforced concrete columns manufactured by including the main rods in the interior of the precast reinforced concrete columns 100. However, And a thread 112 is formed on at least a part of the end of the exposed main muscle 110. [ 1 is a plan view of the precast reinforced concrete column 100 as viewed from above. At this time, the main rope 110 of the precast reinforced concrete column 100 may be manufactured in the same manner as a general precast reinforced concrete column, but based on the preliminary structure review considering the feature that the steel structure is continuously installed on the upper part, The number may be added or the location may be changed. In this embodiment, precast reinforced concrete columns 100 are manufactured by using eight main rods 110 in accordance with the positions and the number of installation holes formed in the lower plate of the fixture of the steel structure. The construction of the precast reinforced concrete column 100 except for the above features is not particularly limited, so a detailed description will be omitted.

또한 본 실시예의 프리캐스트 철근콘크리트 기둥(100)은 철근콘크리트 구조 부분의 최상층, 즉 철근 구조물이 연속 시공되는 위치에만 설치되며, 이보다 아래층에 해당하는 부분에는 일반적인 프리캐스트 철근콘크리트 기둥이 설치된다.In addition, the precast reinforced concrete column 100 of the present embodiment is installed only at the uppermost layer of the reinforced concrete structure portion, that is, the position where the reinforced concrete structure is continuously installed, and a general precast reinforced concrete column is installed at a portion corresponding to the lower layer.

도 2는 본 실시예에 따른 연속시공을 위한 프리캐스트 철근콘크리트 기둥에 프리캐스트 철근콘크리트 보를 위치시킨 모습을 표시한 도면이다.FIG. 2 is a view showing a precast reinforced concrete beam positioned on a precast reinforced concrete column for continuous construction according to the present embodiment. FIG.

본 실시예의 프리캐스트 철근콘크리트 보(200)는, 프리캐스트 철근콘크리트 기둥(100)과 같이 미리 공장에서 제작되어 현장에서 설치되는 프리캐스트 철근콘크리트 시공 방법에 적용되는 보로서, 내부에 주근을 포함하여 제작되는 프리캐스트 철근콘크리트 보의 구성이 제한 없이 적용될 수 있다. 특히, 도면에서는 생략되었지만, 서로 이격된 양쪽의 프리캐스트 철근콘크리트 보(200) 각각에서 프리캐스트 철근콘크리트 기둥(100)의 위쪽으로 돌출된 하부주근을 포함하는 것이 일반적이다.The precast reinforced concrete beam 200 of the present embodiment is applied to a precast reinforced concrete construction method which is manufactured in the factory such as a precast reinforced concrete column 100 and installed in the field in advance, The construction of the precast reinforced concrete beams to be manufactured can be applied without limitation. In particular, although omitted in the drawings, it is common to include a lower main body protruding upward from the precast reinforced concrete column 100 in each of the two precast reinforced concrete beams 200 separated from each other.

기존에는 프리캐스트 철근콘크리트 기둥(100)과 철근콘크리트 보(200)를 결합 시공하기 위한 현장타설 콘크리트를 타설하여, 철근콘크리트 기둥(100)과 철근콘크리트 보(200)를 결합 시공하여 설치한 뒤에, 현장타설 콘크리트의 위쪽으로 철골 구조물을 설치하였다. 반면, 본 실시예의 시공 방법에서는 현장타설 콘크리트를 타설하지 않은 상태에서 추가적인 작업을 진행한다.In the prior art, a cast concrete for placing a precast reinforced concrete column 100 and a reinforced concrete beam 200 is installed and a reinforced concrete column 100 and a reinforced concrete beam 200 are jointly installed and installed. The steel structure was installed above the spotted concrete. On the other hand, in the construction method of the present embodiment, additional work is carried out in a state in which no cast concrete is laid.

도 3은 본 실시예에 따른 연속시공을 위한 프리캐스트 철근콘크리트 기둥의 상부에 노출된 주근에 후프형 철근을 설치한 모습을 도시한 도면이다.3 is a view showing a state in which a hoop type reinforcing bar is installed on a main body exposed on an upper part of a precast reinforced concrete column for continuous construction according to the present embodiment.

후프형 철근(300)은 철근을 감아서 가운데가 비어있는 후프모양으로 형성한 철근으로서, 프리캐스트 철근콘크리트 기둥(100)의 상부로 노출된 주근(110)들이 후프모양 내부에 접하도록 배치되어, 후프형 철근(300)이 주근(110)을 감싸는 형태로 설치된다.The hoop-type reinforcing bar 300 is a reinforcing bar formed by winding a reinforcing bar and having an empty center in the shape of a hoop. The main ropes 110 exposed to the upper portion of the precast reinforced concrete column 100 are arranged so as to be in contact with the inside of the hoop- And a hoop-type reinforcing bar 300 is installed to surround the main rope 110.

이러한 후프형 철근(300)은 현장타설 콘크리트로 덮이지 않은 주근(110)을 보강하여, 주근(110)이 서로 벌어지거나 하는 것을 방지한다. 본 실시예에서는 주근(110)을 안전하게 보강하기 위하여, 높이를 달리하여 3개의 후프형 철근(300)을 설치하였으나 이에 한정되는 것은 아니다.The hoop-shaped reinforcing bars 300 reinforce the main ropes 110 that are not covered with the cast-in-place concrete to prevent the main ropes 110 from spreading. In the present embodiment, three hoop-type reinforcing bars 300 are provided at different heights in order to safely reinforce the main ropes 110, but the present invention is not limited thereto.

또한, 본 실시예에서는 후프형 철근(300)을 프리캐스트 철근콘크리트 보(200)를 위치시킨 뒤에 현장에서 설치하였으나, 공장에서 프리캐스트 철근콘크리트 기둥(100)을 제작하는 과정에서 후프형 철근까지 설치하여 제작할 수도 있고, 현장에서 설치하되 프리캐스트 철근콘크리트 보(200)를 위치시키기 전에 설치할 수도 있다.In the present embodiment, the hoop type reinforced concrete bar 300 is installed in the field after the precast reinforced concrete beam 200 is positioned. However, in the process of manufacturing the precast reinforced concrete column 100 at the factory, Alternatively, it may be installed in the field, but it may be installed before placing the precast reinforced concrete beam 200.

도 4는 본 실시예에 따른 연속시공을 위한 프리캐스트 철근콘크리트 기둥의 상부에 노출된 주근에 하부 고정부를 설치한 모습을 도시한 도면이다.4 is a view showing a state in which a lower fixing part is installed on a main beam exposed on an upper part of a precast reinforced concrete column for continuous construction according to the present embodiment.

프리캐스트 콘크리트 기둥(100) 상부에 노출된 주근(110)의 나사산(112)에 하부 고정부(400)를 설치한다. 하부 고정부(400)는 하부 너트(410)와 하부 와셔(420)로 구성되어 높이 조절이 용이하며, 하부 고정부(400)가 수평을 유지할 수 있는 정확한 위치와 높이에 설치하기 위하여 임시로 설치되는 가설판(500)을 위치시킨 상태에서 하부 고정부(400)를 설치하였다. 도 4에 삽입된 도면은 가설판(500)을 위쪽에서 바라본 평면도이며, 가설판(500)에는 철골구조물에 주근(110)이 삽입되는 위치에 홀이 뚫려있고, 프리캐스트 콘크리트 기둥(100)의 X축과 Y축을 확인할 수 있는 X축선(510)과 Y축선(520)이 표시되어 있다. 본 실시예에서는 하부 너트(410)를 나사산(112)에 체결함으로써, 하부 너트(410)의 설치 높이를 정밀하게 조절할 수 있다.The lower fixing part 400 is installed on the thread 112 of the main body 110 exposed on the precast concrete column 100. The lower fixing part 400 is composed of a lower nut 410 and a lower washer 420 so that the height can be easily adjusted and the lower fixing part 400 is temporarily installed The lower fixing part 400 is installed in a state where the temporary fixing plate 500 is positioned. 4 is a plan view of the hypothetical plate 500 viewed from above. Holes are formed in the hypothetical plate 500 at positions where the main ropes 110 are inserted into the steel structure, and the holes of the precast concrete columns 100 An X axis line 510 and a Y axis line 520 for identifying the X axis and the Y axis are displayed. In the present embodiment, the installation height of the lower nut 410 can be precisely controlled by fastening the lower nut 410 to the screw thread 112.

도 5는 본 실시예에 따른 연속시공을 위한 프리캐스트 철근콘크리트 기둥의 주근에 설치된 하부 고정부의 위치를 가이드하기 위한 수평가이드철근을 설치한 모습을 도시한 도면이다.5 is a view showing a horizontal guide reinforcing bar installed to guide a position of a lower fixing part installed on a main frame of a precast reinforced concrete column for continuous construction according to the present embodiment.

수평가이드철근(600)은 주근(110)의 위치와 간격을 정확하게 고정하기 위하여 설치되며, 정확한 위치에 수평가이드철근(600)을 위치시키고 태그용접으로 고정한다. The horizontal guide reinforcing bars 600 are installed to precisely fix the position and the spacing of the main bars 110, and the horizontal guide reinforcing bars 600 are positioned at the correct positions and fixed by tag welding.

프리캐스트 철근콘크리트 보(200)를 완전하게 설치하기 위해서는 이격되어 위치하는 프리캐스트 철근콘크리트 보(200)들에 걸쳐서 위치하는 상단철근을 배근해야하며, 이때 가설판(500)이 있는 경우에는 배근에 어려움이 있다. 따라서 상단철근을 배근할 때에 간섭을 피하기 위해 가설판(500)을 제거하여야 하지만 이때 주근(110)의 위치와 간격이 흐트러지는 문제가 발생할 수 있다. 하지만, 본 실시예에서는 수평가이드철근(600)에 의해서 주근(110)의 위치와 간격이 정확하게 고정되므로, 가설판(500)을 제거하여도 주근(110)의 위치와 간격이 안정적으로 고정된다. In order to completely install the precast reinforced concrete beam 200, it is necessary to dispose the upper reinforcing bars positioned over the precast reinforced concrete beams 200 located apart from each other. In this case, if there is a temporary plate 500, There is a difficulty. Therefore, in order to avoid interference when laying the upper reinforcing bars, the temporary plate 500 should be removed, but the position and spacing of the main ropes 110 may be disturbed. However, in this embodiment, since the position and spacing of the main frame 110 are accurately fixed by the horizontal guide reinforcement 600, the position and spacing of the main frame 110 can be stably fixed even when the temporary plate 500 is removed.

이때, 하부 고정부(400)의 하부 너트(410)가 회전하여 움직이지 않도록 고정하거나, 정확한 위치를 표시하기 위한 부품을 추가로 설치할 수도 있다.At this time, the lower nut 410 of the lower fixing part 400 may be fixed so as not to move by rotating, or a component for indicating an accurate position may be additionally provided.

도 6은 본 실시예에 따른 연속시공을 위한 프리캐스트 철근콘크리트 기둥의 주근에서 가설판을 제거한 상태로 프리캐스트 철근콘크리트 보에 상단철근을 배근한 모습을 도시한 도면이다.FIG. 6 is a view showing a state in which the upper reinforcing bars are installed in the precast reinforced concrete beams in a state where the temporary plates are removed from the main rods of the precast reinforced concrete columns for continuous construction according to the present embodiment.

수평가이드철근(600)에 의해서 주근(110)의 위치와 간격 및 하부 고정부(400)의 위치가 정확하게 고정된 상태에서 가설판을 제거하여 방해받지 않은 상태로 프리캐스트 철근콘크리트 보(200)들에 걸쳐서 위치하는 상단철근(210)을 배근한다.The horizontal guide reinforcing bars 600 remove the temporary plates in a state in which the positions and the spacing of the main ropes 110 and the positions of the lower fixing portions 400 are accurately fixed to prevent the precast reinforcing concrete beams 200 The upper reinforcing bar 210 is positioned at the upper end of the upper reinforcing bar 210.

도 7은 본 실시예에 따른 연속시공을 위한 프리캐스트 철근콘크리트 기둥의 주근에 철골구조물의 정착철물과 상부 고정부를 설치한 모습을 도시한 도면이다.FIG. 7 is a view showing a state in which a fixture of a steel structure and an upper fixing part are installed on a main frame of a precast reinforced concrete column for continuous construction according to the present embodiment.

상단철근(210)을 배근한 뒤에는 철골 구조물(2000)의 정착(앵커)철물을 설치하며, 철골 구조물(2000)의 정착철물 하부판(2100)이 주근(110)에 끼워져 하부 고정부(400)로 아래가 고정된 뒤에, 상부 고정부(700)를 설치한다. 상부 고정부(700)는 프리캐스트 콘크리트 기둥(100) 상부에 노출된 주근(110)의 나사산(112)에 설치된 상부 너트(710)와 상부 와셔(720)로 구성되며, 하부 고정부(400)와 함께 철골 구조물(2000)의 정착철물 하부판(2100)을 상부와 하부에서 각각 고정한다.After the upper reinforcing bars 210 are laid, an anchor steel member of the steel structure 2000 is installed and the lower fixing plate 2100 of the steel structure 2000 is inserted into the main steel bar 110, After the lower portion is fixed, the upper fixing portion 700 is installed. The upper fixing part 700 is composed of an upper nut 710 and an upper washer 720 provided on the thread 112 of the main body 110 exposed on the precast concrete column 100. The lower fixing part 400, The lower metal plate 2100 of the steel structure 2000 is fixed at the upper portion and the lower portion, respectively.

도 8은 본 실시예에 따른 연속시공을 위한 프리캐스트 철근콘크리트 기둥과 프리캐스트 철근콘크리트 보의 사이에 현장타설 콘크리트를 타설한 모습을 도시한 도면이다.FIG. 8 is a view showing a placement of a spotted concrete between a pre-cast reinforced concrete column and a pre-cast reinforced concrete beam for continuous construction according to the present embodiment.

철골 구조물(2000)과 상부 고정부(700)가 설치된 뒤에, 프리캐스트 철근콘크리트 기둥(100)과 프리캐스트 철근콘크리트 보(200)의 사이에 현장타설 콘크리트(800)를 타설하여, 프리캐스트 철근콘크리트 기둥(100)과 프리캐스트 철근콘크리트 보(200)를 결합한다.After the steel structure 2000 and the upper fixing part 700 are installed, a spotted concrete 800 is laid between the precast reinforced concrete column 100 and the precast reinforced concrete beam 200 to form precast reinforced concrete The column 100 and the precast reinforced concrete beam 200 are combined.

이때, 현장타설 콘크리트(800)의 높이는 철골 구조물(2000)의 정착철물 하부판(2100)이 설치된 위치보다 낮아야 하며, 정착철물 하부판(2100)의 설치 높이, 즉 하부 고정부(400)의 설치 높이는 현장타설 콘크리트(800)의 높이를 감안하여 결정되고, 도 4에서 이 높이에 맞추어 하부 고정부(400)가 설치된다. 바람직하게는 현장타설 콘크리트(800)가 하부 고정부(400)의 아래에 위치하는 것이 좋다. At this time, the height of the spotted concrete 800 should be lower than the position where the lower fixture metal plate 2100 of the steel structure 2000 is installed, and the installation height of the lower fixture plate 2100, Is determined in consideration of the height of the poured concrete 800, and the lower fixing part 400 is installed to match the height of the poured concrete 800 in Fig. Preferably, the site-poured concrete 800 is located below the lower fixing part 400.

도 9는 본 실시예에 따른 연속시공을 위한 프리캐스트 철근콘크리트 기둥에 설치된 철골구조물과 현장타설 콘크리트의 사이에 무수축 모르타르를 타설한 모습을 도시한 도면이다.FIG. 9 is a view showing a non-shrinkage mortar installed between a steel frame structure installed on a precast reinforced concrete column for continuous construction according to the present embodiment and an on-site cast concrete.

앞서 살펴본 것과 같이, 현장타설 콘크리트(800)가 하부 고정부(400)의 아래에 위치하여, 철골 구조물(2000)의 정착철물 하부판(2100)과 현장타설 콘크리트(800)의 사이에 형성된 공간은 무수축 모르타르(900)를 타설하여 고정한다.As described above, the site-cast concrete 800 is located below the lower fixture 400, and the space formed between the fixture lower plate 2100 of the steel structure 2000 and the cast concrete 800 is free The shrinkage mortar 900 is placed and fixed.

정착철물 하부판(2100)의 밑 부분을 현장타설 콘크리트(800)로 채우는 경우, 콘크리트의 특성과 시공 상의 어려움으로 인하여, 틈이 발생하거나 불완전한 시공이 발생한다. 본 실시예에서는 철골 구조물(2000)의 정착철물 하부판(2100)과 현장타설 콘크리트(800)가 이격되도록 현장타설 콘크리트(800)를 타설한 뒤에, 정착철물 하부판(2100)과 현장타설 콘크리트(800) 사이의 공간은 무수축 모르타르(900)를 주입 타설함으로써, 철골 구조물(2000)의 정착철물 하부판(2100)과 현장타설 콘크리트(800)의 사이에 빈틈이 생기지 않고 완전히 채워지도록 하였다.If the lower part of the lower fixture plate 2100 is filled with the cast concrete 800, cracks may occur or incomplete construction may occur due to the characteristics of concrete and difficulty in construction. In this embodiment, the spotting concrete 800 is placed so that the lower metal plate 2100 of the steel structure 2000 is spaced apart from the spotting concrete 800 and then the lower metal plate 2100 and the spot- Shrinkage mortar 900 is poured into the space between the lower steel plate 2100 and the cast concrete 800 of the steel structure 2000 so as to be completely filled with no gap.

이상 본 발명을 바람직한 실시예를 통하여 설명하였는데, 상술한 실시예는 본 발명의 기술적 사상을 예시적으로 설명한 것에 불과하며, 본 발명의 기술적 사상을 벗어나지 않는 범위 내에서 다양한 변화가 가능함은 이 분야에서 통상의 지식을 가진 자라면 이해할 수 있을 것이다. 따라서 본 발명의 보호범위는 특정 실시예가 아니라 특허청구범위에 기재된 사항에 의해 해석되어야 하며, 그와 동등한 범위 내에 있는 모든 기술적 사상도 본 발명의 권리범위에 포함되는 것으로 해석되어야 할 것이다.While the present invention has been particularly shown and described with reference to preferred embodiments thereof, it is to be understood that the invention is not limited to the disclosed embodiments, but, on the contrary, is intended to cover various modifications and equivalent arrangements included within the spirit and scope of the appended claims. Those skilled in the art will understand. Therefore, the scope of protection of the present invention should be construed not only in the specific embodiments but also in the scope of claims, and all technical ideas within the scope of the same shall be construed as being included in the scope of the present invention.

100: 프리캐스트 철근콘크리트 기둥 110: 주근
112: 나사산 200: 프리캐스트 철근콘크리트 보
210: 상단철근 300: 후프형 철근
400: 하부 고정부 410: 하부 너트
420: 하부 와셔 500: 가설판
510: X축선 520: Y축선
600: 수평가이드철근 700: 상부 고정부
710: 상부 너트 720: 상부 와셔
800: 현장타설 콘크리트 900: 무수축 모르타르
1000: 철근콘크리트 구조물 2000: 철골 구조물
2100: 하부판
100: Precast reinforced concrete column 110:
112: Thread 200: Precast reinforced concrete beam
210: Upper reinforcing bar 300: Hoop reinforcing bar
400: lower fixing part 410: lower nut
420: lower washer 500:
510: X axis 520: Y axis
600: horizontal guide reinforcing bar 700: upper fixing part
710: upper nut 720: upper washer
800: Cast-in-place concrete 900: Non-shrinkable mortar
1000: Reinforced concrete structure 2000: Steel structure
2100:

Claims (10)

상부에 복수의 주근이 노출된 프리캐스트 철근콘크리트 기둥을 설치하는 제1단계;
상기 프리캐스트 철근콘크리트 기둥에 프리캐스트 철근콘크리트 보를 위치시키는 제2단계;
상기 노출된 주근 각각에 하부 고정부를 설치하는 제3단계;
상기 프리캐스트 철근콘크리트 보에 상단철근을 배근하는 제4단계;
상기 노출된 주근의 하부 고정부 위에 철골 구조물의 정착철물을 위치시키고 상부 고정부를 설치하여 철골 구조물의 정착철물을 설치하는 제5단계;
상기 프리캐스트 철근콘크리트 보와 상기 프리캐스트 철근콘크리트 기둥의 사이에 현장타설 콘크리트를 타설하는 제6단계; 및
상기 현장타설 콘크리트와 상기 철골 구조물의 정착물의 사이의 공간에 무수축 모르타르를 타설하는 제7단계를 포함하고,
상기 제3단계에서, 현장타설 콘크리트가 상기 철골 구조물의 정착철물보다 아래에 위치되도록, 상기 하부 고정부의 설치 높이가 결정되는 것을 특징으로 하는 프리캐스트 철근콘크리트 구조물과 철골 구조물을 연속 시공하는 방법.
A first step of installing precast reinforced concrete columns having a plurality of main beams exposed on the upper part thereof;
Placing a precast reinforced concrete beam on the precast reinforced concrete column;
A third step of installing a lower fixing part on each of the exposed main beams;
A fourth step of placing the upper reinforcing bars in the precast reinforced concrete beams;
A fifth step of locating the fixing hardware of the steel structure on the lower fixing part of the exposed main beam and installing the fixing part of the steel structure by installing the upper fixing part;
Placing a spotting concrete between the precast reinforced concrete beam and the precast reinforced concrete column; And
And a seventh step of placing non-shrinkable mortar in a space between the locally placed concrete and the fixture of the steel structure,
Wherein the installation height of the lower fixing part is determined so that the site-dumped concrete is positioned below the fixing steel of the steel structure in the third step.
청구항 1에 있어서,
상기 주근을 감싸는 후프형 철근을 설치하는 단계를 상기 제2단계의 직전 또는 직후에 더 수행하는 것을 특징으로 하는 프리캐스트 철근콘크리트 구조물과 철골 구조물을 연속 시공하는 방법.
The method according to claim 1,
Wherein the step of installing the Hoop type reinforcing bars surrounding the main reinforcing bars is performed immediately before or after the second step.
청구항 1에 있어서,
상기 주근을 감싸는 후프형 철근이 프리캐스트 철근콘크리트 기둥을 제작하는 과정에서 설치되거나 상기 제1단계 이전에 설치되는 것을 특징으로 하는 프리캐스트 철근콘크리트 구조물과 철골 구조물을 연속 시공하는 방법.
The method according to claim 1,
Wherein the hoop reinforcing bars surrounding the main frame are installed in a process of manufacturing the precast reinforced concrete column or are installed before the first step.
청구항 1에 있어서,
상기 노출된 주근의 끝부분 적어도 일부에 나사산이 형성되고,
상기 하부 고정부는 하부 너트를 포함하여 구성되며,
상기 제3단계는, 하부 너트를 상기 나사산에 체결하여 수행되는 것을 특징으로 하는 프리캐스트 철근콘크리트 구조물과 철골 구조물을 연속 시공하는 방법.
The method according to claim 1,
A thread is formed on at least a part of the end of the exposed main muscle,
The lower fixing part includes a lower nut,
Wherein the third step is carried out by fastening the lower nut to the thread, and wherein the pre-cast reinforced concrete structure and the steel structure are continuously installed.
청구항 1에 있어서,
제3단계에서, 상기 하부 고정부가 수평을 이루며 정확한 위치에 설치될 수 있도록, 주근에 끼워지는 가설판을 상기 하부 고정부의 위에 위치시킨 상태에서 하부 고정부의 위치를 조절하는 것을 특징으로 하는 프리캐스트 철근콘크리트 구조물과 철골 구조물을 연속 시공하는 방법.
The method according to claim 1,
Wherein a position of the lower fixing part is adjusted in a state where the lower fixing part is positioned on the lower fixing part so that the lower fixing part can be installed horizontally and at an accurate position, A method of continuously constructing a cast reinforced concrete structure and a steel structure.
청구항 1에 있어서,
상기 제3단계 이후에, 하부 고정부의 설치 위치를 고정하기 위한 수평가이드철근을 설치하는 단계를 더 수행하는 것을 특징으로 하는 프리캐스트 철근콘크리트 구조물과 철골 구조물을 연속 시공하는 방법.
The method according to claim 1,
Further comprising the step of installing a horizontal guide reinforcing bar for fixing the installation position of the lower fixing part after the third step.
청구항 5에 있어서,
상기 제4단계에서, 상기 가설판을 제거한 뒤에 상단철근을 배근하는 것을 특징으로 하는 프리캐스트 철근콘크리트 구조물과 철골 구조물을 연속 시공하는 방법.
The method of claim 5,
Wherein in the fourth step, the upper reinforcing bars are routed after removing the temporary plate, and a method for continuously constructing the reinforced concrete structure and the steel structure.
청구항 4에 있어서,
상기 상부 고정부는 상부 너트를 포함하여 구성되며,
상기 제5단계는, 상부 너트를 상기 나사산에 체결하여 수행되는 것을 특징으로 하는 프리캐스트 철근콘크리트 구조물과 철골 구조물을 연속 시공하는 방법.
The method of claim 4,
Wherein the upper fixing part includes an upper nut,
Wherein the fifth step is carried out by fastening an upper nut to the thread, and wherein the pre-cast reinforced concrete structure and the steel structure are continuously installed.
삭제delete 삭제delete
KR1020180087233A 2018-07-26 2018-07-26 Continuous construction method for precast reinforced concrete structure and steel-framed structure and precast reinforced concrete column for using the method KR101947418B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020180087233A KR101947418B1 (en) 2018-07-26 2018-07-26 Continuous construction method for precast reinforced concrete structure and steel-framed structure and precast reinforced concrete column for using the method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020180087233A KR101947418B1 (en) 2018-07-26 2018-07-26 Continuous construction method for precast reinforced concrete structure and steel-framed structure and precast reinforced concrete column for using the method

Publications (1)

Publication Number Publication Date
KR101947418B1 true KR101947418B1 (en) 2019-02-13

Family

ID=65366465

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020180087233A KR101947418B1 (en) 2018-07-26 2018-07-26 Continuous construction method for precast reinforced concrete structure and steel-framed structure and precast reinforced concrete column for using the method

Country Status (1)

Country Link
KR (1) KR101947418B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102092257B1 (en) * 2019-11-20 2020-05-26 신병철 Concrete structure and construction metohds
CN112012387A (en) * 2020-09-21 2020-12-01 江苏九如建设有限公司 Construction process for beam slab joint of prefabricated concrete structure and portable stirrup bender

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100965855B1 (en) * 2009-06-12 2010-06-24 (주)이에스연구소 Joint structure and method for combining steel member on concrete member

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100965855B1 (en) * 2009-06-12 2010-06-24 (주)이에스연구소 Joint structure and method for combining steel member on concrete member

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102092257B1 (en) * 2019-11-20 2020-05-26 신병철 Concrete structure and construction metohds
CN112012387A (en) * 2020-09-21 2020-12-01 江苏九如建设有限公司 Construction process for beam slab joint of prefabricated concrete structure and portable stirrup bender

Similar Documents

Publication Publication Date Title
KR101570484B1 (en) Half-PC Column using lightweight Encased Inner Form And Manufacturing Method Thereof, And Construction Method Using The Same
KR100937745B1 (en) Constructing method using precast concrete column
KR100862005B1 (en) Manufacturing method of segmental internally confined hollow concrete filled tube
EA039205B1 (en) System for wall to wall connection for precast shear walls and method thereof
KR101947418B1 (en) Continuous construction method for precast reinforced concrete structure and steel-framed structure and precast reinforced concrete column for using the method
JP5183606B2 (en) Unit structure of anchor bolt used for foundation construction of equipment and foundation construction method of equipment using it
JP5865567B2 (en) Connecting slab and its construction method
JP3342891B2 (en) Construction method of horizontal beam erected on columnar structure
KR20200075600A (en) Method for constructing transfer layer of building using precast concrete slab
JP2001271366A (en) Joint structre between flat slab and concrete filled steel pipe column, and installation method for flat slab
JP2002030672A (en) Structure of joining foundation pile to pier base and method of constructing the structure
KR20120078217A (en) Block out construction method for apparatus base
KR20130022656A (en) Hybrid building construction method combining dry type and wet type
JP2017223055A (en) Form-reinforcement integral structure and reinforced concrete, and form-reinforcement integral construction method
JP3586121B2 (en) Mixed structure of reinforced concrete column and steel beam and its construction method
JP6710064B2 (en) Seismic isolation retrofit construction method and building construction
JP4511080B2 (en) Construction method of underground structure
KR20010095899A (en) Composition of precast concrete wall and precast concrete column for outdoor to sustain external force
JP7462475B2 (en) How to build a building
JPH0777596A (en) Large scale slab in atomic energy facility and construction thereof
JP7321923B2 (en) Structure and its construction method
TWI823797B (en) Precast base, method of manufacturing the precast base and method of mounting architectural structure having the precast base
JP7389634B2 (en) Building construction method
JP2023016370A (en) Construction method of structure
KR102149661B1 (en) Method for constructing overground transfer layer of building using precast concrete

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant