KR20110126493A - Marine section prefabricated bathroom of construction - Google Patents

Marine section prefabricated bathroom of construction Download PDF

Info

Publication number
KR20110126493A
KR20110126493A KR1020100046185A KR20100046185A KR20110126493A KR 20110126493 A KR20110126493 A KR 20110126493A KR 1020100046185 A KR1020100046185 A KR 1020100046185A KR 20100046185 A KR20100046185 A KR 20100046185A KR 20110126493 A KR20110126493 A KR 20110126493A
Authority
KR
South Korea
Prior art keywords
factory
plate
wall plate
semi
bathroom
Prior art date
Application number
KR1020100046185A
Other languages
Korean (ko)
Inventor
이동형
Original Assignee
이동형
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이동형 filed Critical 이동형
Priority to KR1020100046185A priority Critical patent/KR20110126493A/en
Publication of KR20110126493A publication Critical patent/KR20110126493A/en

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B29/00Accommodation for crew or passengers not otherwise provided for
    • B63B29/02Cabins or other living spaces; Construction or arrangement thereof
    • B63B29/14Closet or like flushing arrangements; Washing or bathing facilities peculiar to ships
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H1/00Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
    • E04H1/12Small buildings or other erections for limited occupation, erected in the open air or arranged in buildings, e.g. kiosks, waiting shelters for bus stops or for filling stations, roofs for railway platforms, watchmen's huts or dressing cubicles
    • E04H1/125Small buildings, arranged in other buildings
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B29/00Accommodation for crew or passengers not otherwise provided for
    • B63B29/02Cabins or other living spaces; Construction or arrangement thereof
    • B63B2029/022Bathing platforms
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65DCONTAINERS FOR STORAGE OR TRANSPORT OF ARTICLES OR MATERIALS, e.g. BAGS, BARRELS, BOTTLES, BOXES, CANS, CARTONS, CRATES, DRUMS, JARS, TANKS, HOPPERS, FORWARDING CONTAINERS; ACCESSORIES, CLOSURES, OR FITTINGS THEREFOR; PACKAGING ELEMENTS; PACKAGES
    • B65D2585/00Containers, packaging elements or packages specially adapted for particular articles or materials
    • B65D2585/64Containers, packaging elements or packages specially adapted for particular articles or materials for bulky articles
    • B65D2585/641Containers, packaging elements or packages specially adapted for particular articles or materials for bulky articles specific articles
    • B65D2585/642Containers, packaging elements or packages specially adapted for particular articles or materials for bulky articles specific articles bathroom and toilet devices
    • Y02T70/14

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Residential Or Office Buildings (AREA)

Abstract

PURPOSE: A construction method for a prefabricated bathroom of a ship is provided to reduce the area required for manufacture of a bathroom of a ship in a production place because a body, a door unit, and a bottom plate are semi-finished in the production place and assembled in the site. CONSTITUTION: A construction method for a prefabricated bathroom of a ship is as follows. A body(10) in which a wall plate(11) and a ceiling plate(12) are integrated is manufactured as a semi product in a factory. A door unit(20) which is hinged on an inlet(13) of the wall plate to open and close the inlet is manufactured as a semi product in the factory. A bottom plate(30) composed of a bottom surface(31) and a support surface(32) is manufactured in the factory. The semi-finished body and door unit are transported and assembled in the construction site.

Description

Marine section Prefabricated Bathroom of construction}

The present invention relates to a method of constructing a prefabricated bathroom for ships, and more particularly, to produce a finished product in a factory and not to deliver it to a shipyard, to deliver it to a shipyard as a semi-finished product and to assemble it at a construction work site to complete a bathroom of a finished product. Therefore, by supplying the finished bathrooms in the form of semi-finished products and assembling the finished products at the site of use, solving the lack of space in the production plant, prompt response to the delivery date of customers, improving the efficiency of required labor, and careless handling of finished products The present invention relates to a ship's prefabricated bathroom structure that increases efficiency of eliminating maintenance work and preventing leakage between wall and floor plates.

In general, the bathroom installed inside the ship during the construction work is installed by two methods.

Firstly, there is a site assembly method for constructing bathrooms with prefabricated panels and installing toilets, washbasins, and metal fittings that make up floors and toilets. There is a prefabricated bathroom method that connects piping and electricity by assembling the equipment such as toilet bowl, wash basin, and metal fittings in one piece and moving it on the ship construction site.

By the way, the bathroom is manufactured as a finished product in the factory and moved to the construction site after installation, if there is damage to a part of the product during the movement, must be replaced as a whole, and due to careless handling of the silicon leak due to bathroom leakage problems Problems that increase the manufacturing cost and installation time occurs.

SUMMARY OF THE INVENTION Accordingly, the present invention has been made keeping in mind the above problems occurring in the prior art,

The main body, door part, and floor plate are manufactured in semi-finished form at the factory, delivered, and assembled at the work site, so that the semi-finished product can be inspected and assembled so that customer damage can be grasped in advance. And, thereby it is an object to provide a prefabricated bathroom construction method for removing the customer complaints of the appearance quality.

In addition, since the semi-finished products of the main body, the door, and the bottom plate are fixed with screws at the construction site, silicon work is performed, and thus, a prefabricated vessel for preventing the leakage of the bathroom due to silicon breakage caused by careless handling in the past. Another purpose is to provide a bathroom construction method.

In order to achieve the above object, the present invention is the wall plate and the outer wall is formed according to the bathroom installation space of the vessel and the inlet is formed in one end surface so that the user can enter and the bottom end is formed in the cross-section "b" shape, and the wall plate Producing a main body made of a semi-finished product at the factory consisting of a ceiling plate formed in the same shape as the outer cross-sectional shape of the wall plate to be fixed to the upper surface of the factory (S100);

Hinged to the inlet of the wall plate, the door unit for opening and closing the inlet is manufactured as a semi-finished product in the factory (S200);

The bottom end of the main body is provided in the bathroom installation space of the ship and the upper end is formed protruding upward along the outer surface of the bottom surface is formed in the cross-section "" in the shape of the end so that the lower end of the wall plate and the shower Producing a bottom plate integrally formed in the factory with a support surface through which the discharge port is formed at one end so that the water introduced into the interior is discharged to outside (S300);

Carrying a main body, a door part, and a bottom plate manufactured as a semi-finished product in the factory and assembling the finished product to a construction work site (S400);

It relates to a ship assembly bathroom construction method characterized in that it comprises a.

As described above, the ship assembly bathroom construction method of the present invention by manufacturing the main body, the door portion, and the bottom plate in the form of semi-finished products in the factory and delivered to the workplace, to solve the lack of space in the production plant, customers Prompt response to delivery time, improvement of efficiency of manpower, elimination of repair work due to breakage between wall plate and floor plate due to vibration generated during transportation of finished product, and assembly of finished product after transportation at the site of use There is an effect of increasing the efficiency, such as preventing leakage between the joints.

1 is an exploded perspective view showing a prefabricated bathroom for a ship according to an embodiment of the present invention,
Figure 2 is a perspective view showing a combined bathroom for a ship according to an embodiment of the present invention.

The present invention has the following features to achieve the above object.

According to the present invention, the outer surface is bent according to the bathroom installation space of the ship and the inlet is formed at one end so that the user can enter, and the lower end is formed in the form of a cross-section "b" and fixed to the upper surface of the wall plate Manufacturing a main body of a ceiling plate which is formed in the same shape as the external cross section of the wall plate so as to be a semi-finished product in a factory (S100);

Hinged to the inlet of the wall plate, the door unit for opening and closing the inlet is manufactured as a semi-finished product in the factory (S200);

The upper end portion is provided in the lower end of the main body is installed in the bathroom installation space of the ship, and protrudes upwards according to the outer surface of the bottom surface and the upper end portion is formed in the shape of "A" in cross-section so that the lower end of the wall plate is supported, Producing a bottom plate integrally formed in the factory with a support surface through which the outlet is formed at one end so that the water introduced into the interior is discharged to the outside (S300);

And a step (S400) of assembling the finished product to a construction work site by carrying a main body, a door part, and a bottom plate manufactured as a semi-finished product in the factory.

Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings. Prior to this, terms or words used in the specification and claims should not be construed as having a conventional or dictionary meaning, and the inventors should properly explain the concept of terms in order to best explain their own invention. Based on the principle that can be defined, it should be interpreted as meaning and concept corresponding to the technical idea of the present invention.

Therefore, the embodiments described in the specification and the drawings shown in the drawings are only the most preferred embodiment of the present invention and do not represent all of the technical idea of the present invention, various modifications that can be replaced at the time of the present application It should be understood that there may be equivalents and variations.

1 is an exploded perspective view showing a prefabricated bathroom for a ship according to an embodiment of the present invention, Figure 2 is a combined perspective view showing a prefabricated bathroom for a ship according to an embodiment of the present invention.

As shown in Figure 1 and 2, the construction method of the prefabricated bathroom for ships of the present invention is unique in that the construction method, first, produced and produced as a semi-finished product in the factory, and delivers the semi-finished product to the construction site, that is, shipyard to deliver the finished product from the ship It is the construction method to assemble and install.

Here, the semi-finished product is composed of a main body 10, a door portion 20 and a bottom plate 30, the main body 10 is composed of a wall plate 11 and a ceiling plate (12).

1 and 2, the wall plate 11 of the main body 10 is formed in a form in which the outer surface is bent in accordance with the bathroom installation space of the vessel, one end surface of the wall plate 11 An inlet 13 is formed to enter, and a mechanism (not shown) such as a shower or a sink to be installed in the main body 10 is connected by a pipe, and the pipe is provided inside or outside the main body 10. A plurality of through holes (not shown) are formed at one end surface of the wall plate 11 so as to be possible.

Here, the upper and lower portions of the wall plate 11 penetrate the ceiling plate 12 at the upper portion, and the bottom plate 30 is installed at the lower portion to block the upper and lower portions of the wall plate 11. At this time, the lower end of the wall plate 11 is formed in the cross-section "b" shape to be combined with the bottom plate 30, the bottom plate 30 is also cross-sectional "a" to be joined to the lower end of the wall plate (11) "Formed in contact with each other, fixed by a coupling member such as bolts, nuts, screws, nails, and the like, to prevent leakage between the bottom surface of the wall plate 11 and the top surface of the bottom plate 30. Seal with a leakproof material such as rubber gasket or silicone.

In addition, the cross-sectional shape of the wall plate 11 may be a protruding portion formed in the shower is installed on one side, a shower booth (not shown) may be installed on the protruding portion.

In addition, the ceiling plate 12 of the main body 10 is fixed to the upper surface of the wall plate 11, as shown in Figs. 1 and 2, in the same shape as the outer cross-sectional shape of the wall plate 11 After being formed and fixed with screws, the gap between the ceiling plate 12 and the wall plate 11 is sealed by silicon work to prevent leakage.

As such, the wall plate 11 and the ceiling plate 12 is manufactured as one semi-finished product is delivered to the site, where there is assembled another door portion 20 and the bottom plate 30 to form a finished product.

As shown in FIGS. 1 and 2, the door part 20 is hinged to the inlet 13 of the wall plate 11 to open and close the inlet 13, and is a general door in which a separate handle is installed. No further description is given. However, the door part 20 is made of a semi-finished product, that is, a single product, and is installed at the inlet 13 of the wall plate 11 at the site.

As shown in FIG. 1, the bottom plate 30 includes a bottom surface 31 and a support surface 32 to be provided at the lower end of the main body 10, wherein the bottom surface 31 is a bathroom of a ship. Installed in the installation space, the upper surface is attached to the tiles (not shown) used in the bathroom.

Here, the bottom surface 31 is formed in the same manner as the outer cross-sectional shape of the wall plate 11, it is formed larger than the width of the wall plate (11).

In addition, the support surface 32 is formed to protrude upward along the outer surface of the bottom surface 31, the upper end portion of the support surface 32 is formed in the form of "b" in cross-section as described above, the wall plate The lower end of the bottom 11 is supported, and water introduced into the bottom plate 30 is discharged to the outside through the pipe 34 under the bottom plate through a shower installed in the wall plate 11.

10: body 11: wallboard
12: ceiling plate 13: inlet
20: door part 30: bottom plate
31: bottom surface 32: support surface
33: outlet

Claims (1)

According to the bathroom installation space of the vessel and the outer surface is bent and the inlet 13 is formed on one end so that the user can enter and the bottom plate end 11 is formed in the cross-section "b" shape, and the wall plate 11 Manufacturing a main body (10) made of a semi-finished product in a factory in which the ceiling plate (12) formed in the same shape as the outer cross-sectional shape of the wall plate (11) is fixed at the upper surface of the factory (S100);
Step S200 is hinged to the inlet 13 of the wall plate 11 is manufactured as a semi-finished product in the factory to open and close the door portion 20 to open and close the inlet 13 (S200);
The bottom surface 31 is provided at the lower end of the main body 10 and protrudes upwardly according to the outer surface of the bottom surface 31 so as to support the lower end of the wall plate 11. The bottom end is formed of a support surface 32 formed in the shape of the cross-section "a" in the cross-section and the outlet 33 penetrates at one end so that water introduced into the interior through the shower is discharged to the outside through the pipe at the bottom of the bottom plate. Manufacturing the plate 30 integrally at the factory (S300);
Carrying the main body 10, the door part 20, and the bottom plate 30, which are manufactured as semi-finished products in the factory, to be assembled as a finished product on a construction work site (S400);
Prefabricated bathroom construction method for ships, characterized in that comprising a.
KR1020100046185A 2010-05-17 2010-05-17 Marine section prefabricated bathroom of construction KR20110126493A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100046185A KR20110126493A (en) 2010-05-17 2010-05-17 Marine section prefabricated bathroom of construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100046185A KR20110126493A (en) 2010-05-17 2010-05-17 Marine section prefabricated bathroom of construction

Publications (1)

Publication Number Publication Date
KR20110126493A true KR20110126493A (en) 2011-11-23

Family

ID=45395603

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100046185A KR20110126493A (en) 2010-05-17 2010-05-17 Marine section prefabricated bathroom of construction

Country Status (1)

Country Link
KR (1) KR20110126493A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101564934B1 (en) * 2013-10-31 2015-11-02 삼성중공업 주식회사 Companion for deck and manufacturing method thereof
CN108622311A (en) * 2018-07-26 2018-10-09 上海外高桥造船有限公司 Modularization accommodation and ship with it
CN109159852A (en) * 2018-08-17 2019-01-08 上海外高桥造船有限公司 The installation method of modularization accommodation
CN110588902A (en) * 2019-09-12 2019-12-20 华南建材(深圳)有限公司 Light sanitary unit chassis structure

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101564934B1 (en) * 2013-10-31 2015-11-02 삼성중공업 주식회사 Companion for deck and manufacturing method thereof
CN108622311A (en) * 2018-07-26 2018-10-09 上海外高桥造船有限公司 Modularization accommodation and ship with it
CN108622311B (en) * 2018-07-26 2023-06-27 上海外高桥造船有限公司 Modularized living cabin and ship with same
CN109159852A (en) * 2018-08-17 2019-01-08 上海外高桥造船有限公司 The installation method of modularization accommodation
CN109159852B (en) * 2018-08-17 2020-03-17 上海外高桥造船有限公司 Installation method of modular living cabin
CN110588902A (en) * 2019-09-12 2019-12-20 华南建材(深圳)有限公司 Light sanitary unit chassis structure

Similar Documents

Publication Publication Date Title
KR100559161B1 (en) Wall water open panel
EP1682730B1 (en) Construction industry pods
KR20110126493A (en) Marine section prefabricated bathroom of construction
RU2679717C2 (en) Mounting cover for wall-mounted fixtures, consisting of thermoplastic layer and reinforcing layers, as well as device with mounting cover for wall-mounted fixtures
US5438713A (en) Seamless bathroom module for a marine vessel
JP6780999B2 (en) Sanitary equipment unit
CN211007806U (en) Prefabricated type integral bathroom structure made of ultra-high performance concrete
ITPI20100059A1 (en) HYDRAULIC SYSTEM OF DISCHARGE OF GRAY WATERS FROM A USER
CN204627039U (en) A kind of integral vacuum toilet
KR101064614B1 (en) Structure of prefabricated bathroom
JP5496537B2 (en) Assembled sanitary unit
US20230087534A1 (en) Reinforced floors for modular bathrooms
JP5106071B2 (en) Bathroom and bathroom unit
CN209780343U (en) Integral bathroom chassis
KR101053213B1 (en) Marine prefabricated toilet
WO2015146474A1 (en) Bathroom unit and method for construction thereof
GB2592176A (en) Prebuilt module for installing water-related fittings
US7350246B1 (en) Bathroom leak damage prevention apparatus
EP3399113A1 (en) Plumbing unit
CN210976055U (en) Water stop structure for water combined room
KR101488639B1 (en) unit bathroom with recessed waterproof board
WO2021157570A1 (en) Structure having room equipped with apparatus using water
JP2011132676A (en) Structure for laying floor pan
KR20240114067A (en) Modular prefabricated bathroom pod with integral assembly structure of horizontal sewage pipe for floor level that can be horizontally infilled in building space and its manufacturing method
JP2689804B2 (en) Bathroom unit construction method

Legal Events

Date Code Title Description
A201 Request for examination
E601 Decision to refuse application