KR20110123453A - A bridge post strengthen structure and construction methode there of - Google Patents

A bridge post strengthen structure and construction methode there of Download PDF

Info

Publication number
KR20110123453A
KR20110123453A KR1020100042948A KR20100042948A KR20110123453A KR 20110123453 A KR20110123453 A KR 20110123453A KR 1020100042948 A KR1020100042948 A KR 1020100042948A KR 20100042948 A KR20100042948 A KR 20100042948A KR 20110123453 A KR20110123453 A KR 20110123453A
Authority
KR
South Korea
Prior art keywords
steel pile
fixing
pier
pile
concrete
Prior art date
Application number
KR1020100042948A
Other languages
Korean (ko)
Other versions
KR101211101B1 (en
Inventor
배석동
배형진
Original Assignee
(주) 선암기술연구소
배형진
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주) 선암기술연구소, 배형진 filed Critical (주) 선암기술연구소
Priority to KR1020100042948A priority Critical patent/KR101211101B1/en
Publication of KR20110123453A publication Critical patent/KR20110123453A/en
Application granted granted Critical
Publication of KR101211101B1 publication Critical patent/KR101211101B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D37/00Repair of damaged foundations or foundation structures

Abstract

PURPOSE: A structure for reinforcing pier and a method of constructing the same are provided to reduce a construction period and costs when pier is repaired and reinforced, since the circumferential surface of pier is covered with a steel pile. CONSTITUTION: A structure(100) for reinforcing pier comprises a steel pile(120), a horizontal reinforcing member(130), a back-filling member(140), a fixing unit(150), a blocking form(160), and cap concrete. The steel pile covers pier by being driven to an underwater bearing layer so that at least one short column pile is horizontally connected between the water surface around pier(P) and bridge by a connecting unit(110). The horizontal reinforcing member is horizontally fixed to the inner surface of the steel pile. The back-filling member is filled between the steel pile fixed by the horizontal reinforcing member and pier.

Description

교각 보강구조물 및 이의 시공방법{A bridge post strengthen structure and construction methode there of}A bridge post strengthen structure and construction methode there of}

본 발명은, 교각 보강구조물에 관한 것으로, 보다 상세하게는 교량의 수중 교각 주변을 감싸도록 단주의 강재파일을 연결부로 고정하면서 수중의 지지층에 설치한 상태에서 교각의 주변을 건조시켜 치핑한 후, 강재파일과 교각 사이를 뒷채움재로 채우고, 강재파일 둘레에 차수거푸집을 설치한 상태에서 강재파일 둘레를 건조시켜 보강콘크리트를 타설하며, 이의 상부에 캡콘크리트를 타설하여 교각의 내구력 보존 및 부식을 방지할 수 있는 교각 보강구조물 및 이의 시공방법에 관한 것이다.
The present invention relates to a pier reinforcement structure, and more particularly, after drying and chipping around the pier in a state in which the steel pile is installed on the support layer while fixing the steel pile with the connection portion to surround the pier around the pier, Fill the gap between the steel pile and the pier with backfill, dry the steel pile around the steel pile and install the reinforcement concrete. It relates to a bridge reinforcement structure and its construction method that can be.

일반적으로 교각(橋脚)이라 함은, 다리의 상부구조의 하중을 기초에 안전하게 전달하는 교량의 ‘발’ 또는 ‘기둥’에 해당되는 것으로, 이는 중력식 교각, 반중력식 교각, 라멘식 교각, 원통형 교각, 중공 교각, 문형 교각 등이 있다.Generally, bridge piers are the 'foots' or 'pillars' of bridges that safely transfer the loads of the upper structure of the bridge to the foundations, which are gravity piers, antigravity piers, ramen piers, cylindrical piers , Hollow piers, portal piers, etc.

또한, 상기 교각은 또한 유수(流水)에 대하여 교량의 안전을 확보할 수 있도록 상부구조로부터 전달되는 하중 뿐만 아니라 교각 자체의 하중과 유수에 의한 유압과 바람에 의한 풍압 및 지진에 견딜 수 있게 설계되고 있다.In addition, the pier is also designed to withstand the load transmitted from the superstructure to ensure the safety of the bridge against the flow of water, as well as the load of the pier itself, the hydraulic pressure by the flow and the wind pressure and earthquake caused by the wind and have.

상기 교량을 지지하는 교각이 동결 융해로 피복 콘크리트의 강도가 저하되거나 재료분리와 피복부족으로 인해 철근이 노출되어 부식되는 현상 및 유송물질과의 충돌과 와류현상으로 침식되면 즉시, 교각을 보수 보강하여야 하며, 이의 방법으로 본 건 출원인 특허 제440092호로 등록받은 교각의 보수 보강용 패널 및 이를 이용한 보수 보강 공법을 등록받은 바 있다.If the bridge supporting the bridge is freeze-thawed and the strength of the coated concrete is reduced or the steel is exposed due to material separation and lack of coating, corrosion of the reinforcement, collision with the transport material and erosion are required. As a method of this, the repair reinforcement panel of the piers registered under the applicant's patent No. 440092 and the repair reinforcement method using the same have been registered.

선 등록된 특허는, 교각의 둘레에 수밀성 케이슨을 설치하고, 수밀성 케이슨 내부의 물을 제거하여 교각의 둘레를 건조시킨 상태에서 수밀성 케이슨과 교각 사이에 패널을 설치한 후, 상기 패널과 교각 사이에 콘크리트를 타설 및 양생하여 교각을 보수.보강하는 공법이다.The pre-registered patent installs a watertight caisson around the pier, removes water inside the watertight caisson, and installs a panel between the watertight caisson and the pier while drying the circumference of the pier. The method of repairing and reinforcing bridge piers by placing and curing concrete.

그러나 선 등록된 특허는, 교각의 내구성을 향상시키는 효과는 우수하나, 수밀성 케이슨의 설치 및 해체에 많은 시간과 공사비용이 소요되는 문제점이 있었다.
However, the pre-registered patent, although the effect of improving the durability of the bridge is excellent, there was a problem that takes a lot of time and construction cost to install and dismantle the watertight caisson.

그러나 강재파일이 물과 접하는 비말대는 외부에 노출되어 있으므로 부식속도가 가장 빨라 조기에 부식되어 강도를 떨어뜨림과 아울러 강재파일의 녹물로 인한 수질을 오염시킬 뿐만 아니라 외관이 산화되어 미관이 미려하지 않는 문제점이 있었다.However, since the steel pile is exposed to the water, the splash zone is exposed to the outside, so the corrosion rate is the fastest, which leads to premature corrosion, reducing the strength and polluting the water quality due to the rust of the steel pile. There was a problem.

또한, 강재파일의 비말대 부식 또는 외부로 노출된 철근콘크리트 부식과 중성화에 따라 구조물의 내구력이 떨어짐과 아울러 내구력을 보존할 수 없어 보수.보강이 요구되므로 강재파일의 부식을 방지하는 재료구입과 작업수행 및 강재파일의 지속적인 관리에 따른 비용이 많이 소요되므로 유지보수에 많은 어려운 문제점이 있었다.
In addition, due to the corrosion of steel piles or the corrosion and neutralization of reinforced concrete exposed to the outside, the durability of the structure falls and the durability cannot be preserved, so repair and reinforcement are required. There are many difficult problems in maintenance because of the high cost of performance and continuous management of steel piles.

이에 상술한 바와 같은 종래의 제반 결함을 감안하여 이루어진 것으로, 본 발명의 목적은, 적어도 1개 이상의 단주 파일을 연결부로 고정하는 강재파일로 교각의 둘레를 감싸므로 교각의 보수.보강시, 공사기간의 단축 및 비용을 절감할 수 있는 교각 보강구조물 및 이의 시공방법을 제공함에 있다.In view of the above-described conventional defects, the object of the present invention is to wrap the circumference of the piers with steel pilings for fixing at least one or more single column piles as a connection part. It is to provide a bridge reinforcement structure and its construction method that can reduce the cost and reduce the cost.

또한, 본 발명의 다른 목적은, 교각의 둘레를 감싼 강재파일에 차수거푸집을 설치하고, 차수거푸집 내부의 강재파일을 건조시킨 상태에서 보강콘크리트를 형성하므로 강재파일의 부식 방지 및 캡콘크리트로 고정시켜 내구력을 향상시킬 수 있도록 하는 교각 보강구조물 및 이의 시공방법을 제공함에 있다.
In addition, another object of the present invention, by installing the order form on the steel pile wrapped around the piers, and forming the reinforcement concrete in the dried state of the steel pile inside the formwork to prevent corrosion of the steel pile and fixed with cap concrete It is to provide a bridge reinforcement structure and its construction method to improve the durability.

본 발명 교각 보강구조물은,The pier reinforcement structure of the present invention,

교각이 설치된 수면과 교량 사이에서 적어도 1개 이상의 단주 파일을 연결부로 고정시키면서 수평으로 연결되도록 수중의 지지층에 항타하여 교각을 감싸도록 하는 강재파일과;A steel pile for piercing the pier by striking the support layer in the water so as to be connected horizontally while fixing at least one or more filed columns between the water surface and the bridge where the pier is installed;

상기 강재파일 내면에 수평으로 고정되어 보강하는 수평보강부재와;A horizontal reinforcing member fixed to and reinforced horizontally on an inner surface of the steel pile;

상기 수평보강부재로 고정된 강재파일과 교각 사이를 충진하는 뒷채움재와;A back filling material filling between the steel pile and the piers fixed by the horizontal reinforcing member;

상기 강재파일 전면에 차수거푸집을 고정하도록 하는 고정부와;A fixing part to fix the order formwork to the front of the steel pile;

상기 강재파일 전면에 차수재가 밀착되면서 물의 유입을 차단하도록 고정부로 고정되어 보강콘크리트가 형성되도록 하는 차수거푸집과;Ordering formwork is fixed to the fixed portion to block the inflow of water while the orderer is in close contact with the front of the steel pile to form a reinforcement concrete;

상기 교각과 뒷채움재 및 강재파일과 보강콘크리트 상부에 콘크리트를 타설.양생하여 보호하는 캡콘크리트를 포함하여 구성되는 것을 특징으로 하는 것이다.
The pier and backfill and steel piles and reinforcement concrete, the concrete is characterized in that it comprises a cap concrete to protect by placing.

본 발명 교각 보강구조물의 시공방법은,Construction method of the pier reinforcement structure of the present invention,

교각이 설치된 수면과 교량 사이에서 적어도 1개 이상의 단주 파일을 연결부로 고정시키면서 수평으로 연결되도록 수중의 지지층에 강재파일을 항타하여 교각을 감싸도록 하는 단계와;Driving the steel pile on the support layer in the water so as to be connected horizontally while fixing the at least one pillar file between the water and the bridge on which the bridge is installed;

상기 강재파일 내면에 수평으로 수평보강부재를 고정하여 보강하는 단계와;Fixing and reinforcing horizontal reinforcing members horizontally to an inner surface of the steel pile;

상기 강재파일과 교각 사이의 물을 제거하여 건조시킨 후, 치핑한 교각과 강재파일 사이를 뒷채움재로 충진하는 단계와;Removing water between the steel piers and the piers and drying them, and filling the backfill between the chipped piers and the piers;

상기 강재파일 전면에 차수거푸집을 고정시키는 고정부를 고정하는 단계와;Fixing a fixing part to fix the order formwork on the front of the steel pile;

상기 강재파일 전면에 차수거푸집의 차수재가 밀착되면서 물의 유입을 차단하도록 고정부에 고정하는 단계와;Fixing to the fixing unit to block the inflow of water while the order of the order form is in close contact with the front of the steel pile;

상기 고정부로 고정된 차수거푸집 내부에 콘크리트를 타설.양생하여 보강콘크리트를 형성하는 단계와;Placing concrete in the order form secured by the fixing part to form reinforcement concrete;

상기 교각과 뒷채움재 및 강재파일과 보강콘크리트 상부에 캡콘크리트를 형성하여 보호하는 단계와;Forming a cap concrete on the pier and the backfill and the steel pile and the reinforcement concrete to protect the pier;

상기 차수거푸집을 분리하는 단계를 포함하여 이루어지는 것을 특징으로 하는 것이다.
It characterized in that it comprises a step of separating the order formwork.

본 발명 교각 보강구조물 및 이의 시공방법에 의하면, 적어도 1개 이상의 단주 파일을 연결부로 고정하는 강재파일로 교각의 둘레를 감싸고, 강재파일과 교각 사이의 물을 제거하여 건조시킨 후, 치핑한 교각과 강재파일 사이에 뒷채움재를 충진하여 보강하는 교각의 보수,보강시, 별도의 거푸집이 필요 없으므로 공사기간의 단축 및 비용을 절감할 수 있는 이점을 가질 수 있는 것이다.According to the pier reinforcement structure of the present invention and a construction method thereof, the steel piling to secure at least one or more columnar piles as a connecting portion, wrap the circumference of the piers, remove the water between the steel pilings and piers to dry, and then chipped piers and When repairing or reinforcing the piers to fill and reinforce the backfill between steel piles, no additional formwork is required, which can reduce the construction period and reduce costs.

또한, 본 발명 교각 보강구조물 및 이의 시공방법에 의하면, 교각의 둘레를 감싼 강재파일에 차수거푸집을 설치하고, 차수거푸집 내부의 강재파일을 건조시킨 상태에서 보강콘크리트를 형성하므로 강재파일의 부식 방지 및 캡콘크리트로 고정시켜 교각의 내구력을 향상시킴과 아울러 유지관리를 용이하게 할 수 있는 이점을 가질 수 있는 것이다.
In addition, according to the present invention pier reinforcement structure and its construction method, by installing the order form on the steel piles wrapped around the pier, and forming the reinforcement concrete in the state of drying the steel piles inside the order form to prevent corrosion of the steel piles and Fixing with cap concrete can have the advantage of improving the durability of the piers and facilitate maintenance.

도 1은 본 발명의 단주파일에 연결부를 고정하여 강재파일을 형성한 사시도
도 2는 도 1의 평단면도
도 3은 본 발명 교각 보강구조물의 정단면도
도 4 내지 도 9는 본 발명의 설치를 위한 과정도
Figure 1 is a perspective view of the steel pile formed by fixing the connection to the monofiling file of the present invention
Figure 2 is a cross-sectional view of Figure 1
3 is a front sectional view of the present invention pier reinforcement structure
4 to 9 is a process diagram for the installation of the present invention

이하, 첨부된 도면에 의거하여 본 발명의 일 실시예를 상세히 설명한다. 도 1은 본 발명의 단주파일에 연결부를 고정하여 강재파일을 형성한 사시도이고, 도 2는 도 1의 평단면도이며, 도 3은 본 발명의 교각 보강구조물의 정단면도이다.Hereinafter, an embodiment of the present invention will be described in detail with reference to the accompanying drawings. 1 is a perspective view of a steel pile formed by fixing a connection portion to the stern pile of the present invention, Figure 2 is a cross-sectional view of Figure 1, Figure 3 is a front sectional view of the pier reinforcement structure of the present invention.

본 발명 교각 보강구조물(100)은, 교각(P)이 설치된 수면과 교량 사이에서 적어도 1개 이상의 단주 파일(121)(121')을 연결부(110)로 고정시키면서 수평으로 연결되도록 수중의 지지층에 항타하여 교각(P)을 감싸도록 하는 강재파일(120)이 구성되고, 상기 강재파일(120) 내면에 수평으로 고정되어 보강하는 수평보강부재(130)가 구성되며, 상기 수평보강부재(130)로 고정된 강재파일(120)과 교각(P) 사이를 충진하는 뒷채움재(140)가 구성되고, 상기 강재파일(120) 전면에 차수거푸집(160)을 고정하도록 하는 고정부(150)가 구성되며, 상기 강재파일(120) 전면에 차수재(161)가 밀착되면서 물의 유입을 차단하도록 고정부(150)로 고정되어 보강콘크리트(162)가 형성되도록 하는 차수거푸집(160)이 구성되고, 상기 교각(P)과 뒷채움재(140) 및 강재파일(120)과 보강콘크리트(162) 상부에 콘크리트를 타설.양생하여 보호하는 캡콘크리트(170)를 포함하여 구성되는 것으로, 이를 좀더 구체적으로 설명하면 다음과 같다.The pier reinforcement structure 100 of the present invention is connected to the support layer in the water so as to be connected horizontally while fixing at least one or more of the columnar files 121, 121 'between the water surface and the bridge is installed bridge pier (P). A steel pile 120 is formed to cover the piers P by driving, and a horizontal reinforcing member 130 is fixed to the inner surface of the steel pile 120 to be reinforced horizontally, and the horizontal reinforcing member 130 is formed. The back filling material 140 is filled between the steel pile 120 and the pier (P) is fixed to the fixed portion 150 to fix the order form 160 to the front of the steel pile (120). The order form 160 is fixed to the fixing part 150 to block the inflow of water while the order material 161 is in close contact with the front of the steel pile 120 to form a reinforcement concrete 162. On the pier (P) and backfill material 140 and steel pile 120 and reinforcement concrete 162 To be configured to include the concrete cap 170 to protect the casting. Curing the concrete, it will be described in more detail.

상기 연결부(110)는, 상기 단주 파일(121)(121') 양단부에 각각 형성된 파일연결공(111)(111')이 구비되고, 상기 파일연결공(111)(111')과 판연결공(112')이 동일 선상을 유지하도록 적어도 1개 이상의 단주 파일(121)(121')에 밀착되는 연결판(112)이 구비되며, 상기 연결판(112)의 판연결공(112')과 파일(121)의 파일연결공(111)을 고정시키는 연결볼트(113) 및 연결너트(113')를 포함하여 구비된다.The connection part 110 is provided with file connection holes 111 and 111 'respectively formed at both ends of the column-like file 121 and 121', and the file connection hole 111 and 111 'and the plate connection hole. The connection plate 112 is provided to be in close contact with at least one of the pillar file (121, 121 ') so that the (112') to keep the same line, and the plate connection hole (112 ') of the connecting plate 112 The connection bolt 113 and the connection nut 113 'for fixing the file connection hole 111 of the file 121 are provided.

상기 연결판(112)은 파일(121)(121')의 내면에 밀착되거나 감쌀 수 있도록 파일과 동일한 모양으로 형성되는 것이 바람직하다.The connecting plate 112 is preferably formed in the same shape as the pile so as to be in close contact with or wrapped around the inner surface of the pile (121, 121 ').

상기 고정부(150)는, 상기 강재파일(120)의 전면에 일정간격으로 고정되면서 연결너트(151a)로 연결되는 고정볼트(151)가 구비되고, 상기 고정볼트(151)에 장착되는 차수거푸집(160)을 고정하도록 고정볼트(151)에 체결되는 고정너트(152)를 포함하여 구비된다.
The fixing part 150 is provided with a fixing bolt 151 connected to the connecting nut 151a while being fixed at a predetermined interval on the front of the steel pile 120, and the order form mounted on the fixing bolt 151. And a fixing nut 152 fastened to the fixing bolt 151 to fix the 160.

다음은 상기와 같이 구성된 본 발명의 설치과정을 설명한다.The following describes the installation process of the present invention configured as described above.

먼저, 도 4에 도시된 바와 같이, 교각(P)이 설치된 수면과 교량 사이에서 단주 파일(121)을 교각(P)으로부터 일정한 거리로 이격된 위치에서 항타장비로 항타하는데, 상기 단주 파일(121)은 단주 파일(121')과 연결부(110)로 연결하면서 항타장비로 항타된다.First, as shown in FIG. 4, between the water surface and the bridge on which the bridge P is installed, the pillar file 121 is driven by driving equipment at a position spaced apart from the bridge P by a predetermined distance. ) Is driven by the driving device while being connected to the single file (121 ') and the connecting portion (110).

여기서 상기 연결부(110)의 연결판(112)은 'U'자형 및 파일과 동일한 모양으로 형성되어 적어도 1개 이상의 단주 파일(121)(121')의 양단부를 감싸거나 밀착될 수 있으며, 적어도 1개 이상의 단주 파일(121)(121')에 밀착되는 연결판(112)의 판연결공(112')이 적어도 1개 이상의 단주 파일(121)(121')에 각각 관통된 파일연결공(111)(111')과 동일 선상을 유지하게 된다.Here, the connecting plate 112 of the connecting portion 110 is formed in the same shape as the 'U' shape and the file can be wrapped or adhered to both ends of at least one or more single column files (121, 121 '), at least one File connection holes 111 through which the plate connecting hole 112 'of the connecting plate 112 in close contact with the at least one file length (121, 121') through each of the at least one file length file (121, 121 ') It is maintained on the same line as 111).

이때, 동일 선상을 유지하는 판연결공(112')과 파일연결공(111)에 연결볼트(113)를 판연결공(112')으로 결합하여 파일연결공(111)으로 돌출시킨 후, 파일연결공(111)으로 돌출되는 연결볼트(113)에 연결너트(113')를 체결하여 고정시키는데, 상기 연결볼트(113)를 파일연결공(111)으로 결합하여 판연결공(112')으로 돌출시킨 상태에서 연결너트(113')로 체결하여 고정시킬 수도 있는 것이다.At this time, the connection bolt 113 is connected to the plate connection hole 112 'and the file connection hole 111 to maintain the same line by the plate connection hole 112' to protrude into the file connection hole 111, and then the file The connection nut 113 'is fixed to the connection bolt 113 protruding to the connection hole 111, and the connection bolt 113 is coupled to the file connection hole 111 to the plate connection hole 112'. It can also be fixed by fastening with a connection nut 113 'in the protruding state.

상기 연결부(110)로 고정된 단주 파일(121)(121')은 수중의 지지층에 항타되며, 이와 같은 방법으로 적어도 1개 이상의 단주 파일(121)(121')에 연결부로 고정되는 적어도 1개 이상의 단주 파일이 수평으로 서로 연결되면서 교각(P)을 감싸는 강재파일(120)을 형성하게 되는 것이다.The monopole files 121 and 121 'fixed by the connection unit 110 are driven by the support layer in the water, and at least one monolithic file 121 and 121' is fixed to the connection layer in this manner. The above-described column file is connected to each other horizontally to form a steel pile 120 surrounding the pi (P).

또한, 도 5에 도시된 바와 같이, 상기 강재파일(120)이 교각(P)으로부터 일정거리 이격된 상태에서 교각(P)을 감싸면, 상기 교각(P)과 강재파일(120) 사이에 물을 양수기(미도시)의 작동으로 배수시킨 후, 교각(P)을 건조시킨 상태에서 상기 강재파일(120) 내면에 수평으로 일정간격 이격되게 다수의 수평보강부재(130)를 고정하는데, 상기 수평보강부재(130)는 강재파일(120)과 용접으로 고정하는 것이 바람직하며, 도 6에 도시된 바와 같이, 건조된 강재파일(120)과 교각(P) 사이 공간을 형상이 양호한 골재나 콘크리트 채움을 하고 다짐을 하는데, 지지층에 공극이 많은 경우에는 공극을 채워 안정화할 수 있는 그라우팅을 실시할 수 있으며, 상기 골재, 콘크리트 및 그라우팅 등이 뒤채움재(140)에 속한다.In addition, as shown in FIG. 5, when the steel pile 120 surrounds the pier P in a state spaced apart from the pier P by a predetermined distance, water is stored between the pier P and the steel pile 120. After draining by the operation of a water pump (not shown), while fixing the plurality of horizontal reinforcing members 130 horizontally spaced horizontally on the inner surface of the steel pile (120), the horizontal reinforcement The member 130 is preferably fixed to the steel pile 120 by welding. As shown in FIG. 6, the space between the dried steel pile 120 and the piers P is formed to have good shape aggregate or concrete filling. And the compaction, if there are a lot of voids in the support layer can be carried out grouting can be stabilized by filling the voids, the aggregate, concrete and grouting, etc. belong to the backfill material 140.

상기 뒷채움재(140)의 채움이 완료되면, 도 7에 도시된 바와 같이, 상기 강재파일(120)의 다수의 단주 파일(121)(121') 표면에 고정볼트(151)를 고정시키는데, 이는 수중의 지지층에 항타된 단주 파일(121)(121')에 수중용접으로 고정시킬 수 있으나, 항타장비에 의해 항타되기 전의 단주 파일(121)(121')에 고정하는 것도 한 방법임을 밝혀둔다.When the filling of the back filling material 140 is completed, as shown in FIG. 7, the fixing bolts 151 are fixed to the surface of the plurality of monofiling files 121 and 121 ′ of the steel pile 120. Although it can be fixed by underwater welding to the pillar file (121, 121 ') driven on the support layer in the water, it is clear that it is also a method of fixing to the pillar file (121, 121') before being driven by the navigation equipment.

여기서 상기 고정볼트(151)에 연결너트(151a)의 일단부를 체결한 후, 상기 연결너트(151a)의 타단부에 다른 고정볼트(151')를 체결하여 고정볼트의 길이를 늘릴 수 있는 것이다.Here, after fastening one end of the connection nut 151a to the fixing bolt 151, the other fixing bolt 151 'may be fastened to the other end of the connection nut 151a to increase the length of the fixing bolt.

상기에서와 같이 강재파일(120)에 고정볼트(151)의 고정이 완료되면, 상기 강재파일(120) 주변에 일정한 간격으로 보강철근망(163)을 배근하여 고정볼트(151)에 결속시킬 수 있다.As described above, when the fixing of the fixing bolt 151 to the steel pile 120 is completed, the reinforcing steel reinforcement net 163 at a predetermined interval around the steel pile 120 can be bound to the fixing bolt 151. have.

상기 고정볼트(151')에 차수거푸집(160)을 결합하여 강재파일(120) 전면에 밀착시키는데, 상기 차수거푸집(160)의 홈(160')에 장착된 차수재(161)가 강재파일(120) 전면에 밀착됨과 동시에 상기 차수거푸집(160)은 연결너트(151a)에 밀착되면서 강재파일(120)과 차수거푸집(160)이 일정간격을 유지하게 되고, 상기 연결너트(151a)와 연결된 타단부의 다른 고정볼트(151')에 차수거푸집(160)을 끼우고 고정너트(152)를 체결하여 고정시킨다. 설치한 차수거푸집(160)을 철거시에 고정너트(152)를 풀면 보강콘크리트(162)에 매설된 고정볼트(151)와 체결된 연결너트(151a)에서 다른 고정볼트(151')는 분리하여 철거할 수 있는 것이다.Coupling the order formwork 160 to the fixing bolt 151 'to closely adhere to the front of the steel pile 120, the orderer 161 mounted in the groove 160' of the order form 160 is a steel pile ( 120 is in close contact with the front and at the same time the order form 160 is in close contact with the connection nut (151a) and the steel pile 120 and the order form 160 to maintain a constant interval, the other connected to the connection nut (151a) Insert the order formwork 160 to the other fixing bolt 151 'of the end and fasten the fixing nut 152 to fix. When removing the fixing nut 152 at the time of dismantling the installed order formwork 160, the other fixing bolt 151 'is separated from the fixing bolt 151 and the connection nut 151a fastened to the reinforcement concrete 162. It can be demolished.

상기 고정너트(152)가 연결너트(151a)에 체결되면서 차수거푸집(160)을 가압함에 따라 상기 차수거푸집(160)이 강재파일(120) 전면에 밀착되면서 차수거푸집(160)의 홈(160')에 장착된 차수재(161)가 강재파일(120) 전면에 견고하게 밀착되면서 강재파일(120)과 차수거푸집(160) 사이로 유입되는 물을 차단하게 된다.As the fixing nut 152 is fastened to the connecting nut 151a and presses the order formwork 160, the order form 160 is closely adhered to the front of the steel pile 120 and the groove 160 'of the order form 160 is formed. The order member 161 mounted on the) closes tightly to the front of the steel pile 120 to block water flowing between the steel pile 120 and the order form 160.

또한, 상기 고정부(150)에 고정된 차수거푸집(160)과 강재파일(120) 사이의 물은 양수기(미도시)의 작동으로 배수시킨 후, 도 8에 도시된 바와 같이, 강재파일(120)을 건조시킨 상태에서 차수거푸집(160)과 강재파일(120) 사이의 공간에 콘크리트를 타설.양생하여 보강콘크리트(162)를 형성할 수 있으며, 상기 보강콘크리트(162)가 형성되면, 상기 교각(P)과 뒷채움재(140) 및 강재파일(120)과 보강콘크리트(162) 상부 즉, 차수거푸집(160) 내부로 콘크리트를 타설.양생하는 캡콘크리트(170)를 형성하는데, 상기 캡콘크리트(170)는 교각(P)과 뒷채움재(140) 및 강재파일(120)과 보강콘크리트(162)를 보호하면서 견고하게 고정시키게 된다.In addition, after the water between the order formwork 160 and the steel pile 120 fixed to the fixing part 150 is drained by the operation of a water pump (not shown), as shown in Figure 8, the steel pile 120 Concrete in the space between the order form 160 and the steel pile 120 in the dried state. The reinforcement concrete 162 can be formed by curing, and when the reinforcement concrete 162 is formed, the piers (P) and the back filling material 140 and the steel pile 120 and the reinforcement concrete 162, that is, to form the concrete into the top of the formwork 160. Curing concrete to form the cap concrete (170) 170 is firmly fixed while protecting the pier (P) and backfill material 140 and steel pile 120 and reinforcement concrete 162.

상기 캡콘크리트(170) 형성이 완료되어 차수거푸집(160)을 분리하고자 할 경우, 도 9에 도시된 바와 같이, 고정볼트(151')에 체결된 고정너트(152)를 풀어 차수거푸집(160)을 분리한 후, 연결너트(151a)에서 다른 고정볼트(151')를 분리하여 철거하면, 교각을 보강한 교각 보강구조물(100)의 설치가 완료되는 것이다.When the cap concrete 170 is formed to remove the order formwork 160, as shown in FIG. 9, the order form 160 is released by releasing the fixing nut 152 fastened to the fixing bolt 151 ′. After the separation, when the other fixing bolt 151 'is removed and removed from the connection nut (151a), the installation of the pier reinforcement structure 100 is reinforced.

여기서, 상기 보강콘크리트(162)와 캡콘크리트(170)를 타설되는 콘크리트에 의해 동시에 형성할 수도 있는 것이다.Here, the reinforcement concrete 162 and the cap concrete 170 may be formed at the same time by pouring concrete.

이상과 같이 본 발명은, 비록 한정된 실시예와 도면에 의해 설명되었으나, 본 명세서 및 청구범위에 사용된 용어나 단어는 통상적이거나 사전적인 의미로 한정되어 해석되어서는 아니되며, 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다. 따라서, 본 명세서에 기재된 실시예와 도면에 도시된 구성은 본 발명의 일실시예에 불과할 뿐이고, 본 발명의 기술적 사상을 모두 대변하는 것은 아니므로, 본 발명의 청구범위를 벗어나지 않는 한도 내에서 다양한 균등물과 변형예들이 있을 수 있음을 이해하여야 한다.
As described above, the present invention, although described by the limited embodiments and drawings, terms or words used in the present specification and claims are not limited to the ordinary or dictionary meanings and should not be interpreted, the technical spirit of the present invention It must be interpreted to mean meanings and concepts. Therefore, the configuration shown in the embodiments and drawings described herein are only one embodiment of the present invention, and do not represent all of the technical spirit of the present invention, various changes within the scope of the claims of the present invention It should be understood that there may be equivalents and variations.

100: 교각 보강구조물 110: 연결부
120: 강재파일 130: 수평보강부재
140: 뒷채움재 150: 고정부
160: 차수거푸집 170: 캡콘크리트
100: bridge reinforcement structure 110: connection portion
120: steel pile 130: horizontal reinforcing member
140: back filling material 150: fixed part
160: order form 170: cap concrete

Claims (5)

교각이 설치된 수면과 교량 사이에서 적어도 1개 이상의 단주 파일을 연결부로 고정시키면서 수평으로 연결되도록 수중의 지지층에 항타하여 교각을 감싸도록 하는 강재파일과;
상기 강재파일 내면에 수평으로 고정되어 보강하는 수평보강부재와;
상기 수평보강부재로 고정된 강재파일과 교각 사이를 충진하는 뒷채움재와;
상기 강재파일 전면에 차수거푸집을 고정하도록 하는 고정부와;
상기 강재파일 전면에 차수재가 밀착되면서 물의 유입을 차단하도록 고정부로 고정되어 보강콘크리트가 형성되도록 하는 차수거푸집과;
상기 교각과 뒷채움재 및 강재파일과 보강콘크리트 상부에 콘크리트를 타설.양생하여 보호하는 캡콘크리트를 포함하여 구성되는 것을 특징으로 하는 교각 보강구조물.
A steel pile for piercing the pier by striking the support layer in the water so as to be connected horizontally while fixing the at least one pillar file between the water surface and the bridge where the pier is installed;
A horizontal reinforcing member fixed to and reinforced horizontally on an inner surface of the steel pile;
A back filling material filling between the steel pile and the piers fixed by the horizontal reinforcing member;
A fixing part to fix the order formwork to the front of the steel pile;
Ordering formwork is fixed to the fixed portion to block the inflow of water while the orderer is in close contact with the front of the steel pile to form a reinforcement concrete;
The bridge piers reinforcement structure, characterized in that it comprises a cap concrete to protect and cure concrete in the upper portion of the bridge and backfill and steel pile and reinforcement concrete.
청구항 1에 있어서, 연결부는,
상기 단주 파일 양단부에 각각 형성된 파일연결공과;
상기 파일연결공과 판연결공이 동일 선상을 유지하도록 적어도 1개 이상의 단주 파일에 밀착되는 연결판과;
상기 연결판의 판연결공과 파일의 파일연결공을 고정시키는 연결볼트 및 연결너트를 포함하여 구비되는 것을 특징으로 하는 교각 보강구조물.
The method according to claim 1, The connecting portion,
A pile connection hole respectively formed at both ends of the single column pile;
A connection plate in close contact with at least one or more single file piles such that the pile connection hole and the plate connection hole maintain the same line;
Pier reinforcement structure characterized in that it comprises a connection bolt and a connection nut for fixing the plate connection hole of the connection plate and the file connection hole of the file.
청구항 2에 있어서,
상기 연결판은 파일의 내면에 밀착되거나 감쌀 수 있도록 파일과 동일한 모양으로 형성되는 것을 특징으로 하는 교각 보강구조물.
The method according to claim 2,
The connecting plate is a piling reinforcement structure, characterized in that formed in the same shape as the pile to be in close contact with or wrapped around the inner surface of the pile.
청구항 1에 있어서, 고정부는,
상기 강재파일의 전면에 일정간격으로 고정되면서 연결너트로 연결되는 고정볼트와;
상기 고정볼트에 장착되는 차수거푸집을 고정하도록 고정볼트에 체결되는 고정너트를 포함하여 구비되는 것을 특징으로 하는 강재파일에 패널이 부착된 강구조물.
The method of claim 1, wherein the fixing unit,
A fixing bolt connected to the connection nut while being fixed at a predetermined interval on the front side of the steel pile;
Steel structure with a panel attached to the steel pile, characterized in that it comprises a fixing nut fastened to the fixing bolt to fix the order formwork mounted on the fixing bolt.
교각이 설치된 수면과 교량 사이에서 적어도 1개 이상의 단주 파일을 연결부로 고정시키면서 수평으로 연결되도록 수중의 지지층에 강재파일을 항타하여 교각을 감싸도록 하는 단계와;
상기 강재파일 내면에 수평으로 수평보강부재를 고정하여 보강하는 단계와;
상기 강재파일과 교각 사이의 물을 제거하여 건조시킨 후, 치핑한 교각과 강재파일 사이를 뒷채움재로 충진하는 단계와;
상기 강재파일 전면에 차수거푸집을 고정시키는 고정부를 고정하는 단계와;
상기 강재파일 전면에 차수거푸집의 차수재가 밀착되면서 물의 유입을 차단하도록 고정부에 고정하는 단계와;
상기 고정부로 고정된 차수거푸집 내부에 콘크리트를 타설.양생하여 보강콘크리트를 형성하는 단계와;
상기 교각과 뒷채움재 및 강재파일과 보강콘크리트 상부에 캡콘크리트를 형성하여 보호하는 단계와;
상기 차수거푸집을 분리하는 단계를 포함하여 이루어지는 것을 특징으로 하는 교각 보강구조물의 시공방법.
Driving the steel pile on the support layer in the water so as to be connected horizontally while fixing the at least one pillar file between the water and the bridge on which the bridge is installed;
Fixing and reinforcing horizontal reinforcing members horizontally to an inner surface of the steel pile;
Removing water between the steel piers and the piers and drying them, and filling the backfill between the chipped piers and the piers;
Fixing a fixing part to fix the order formwork on the front of the steel pile;
Fixing to the fixing unit to block the inflow of water while the order of the order form is in close contact with the front of the steel pile;
Placing concrete in the order form secured by the fixing part to form reinforcement concrete;
Forming a cap concrete on the pier and the backfill and the steel pile and the reinforcement concrete to protect the pier;
Construction method of a piers reinforcement structure, characterized in that comprising the step of separating the order formwork.
KR1020100042948A 2010-05-07 2010-05-07 A bridge post strengthen structure and construction methode there of KR101211101B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100042948A KR101211101B1 (en) 2010-05-07 2010-05-07 A bridge post strengthen structure and construction methode there of

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100042948A KR101211101B1 (en) 2010-05-07 2010-05-07 A bridge post strengthen structure and construction methode there of

Publications (2)

Publication Number Publication Date
KR20110123453A true KR20110123453A (en) 2011-11-15
KR101211101B1 KR101211101B1 (en) 2012-12-11

Family

ID=45393615

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100042948A KR101211101B1 (en) 2010-05-07 2010-05-07 A bridge post strengthen structure and construction methode there of

Country Status (1)

Country Link
KR (1) KR101211101B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20220161584A (en) 2021-05-27 2022-12-07 박석암 A repairing method for column type underwater structures

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101596352B1 (en) 2015-02-26 2016-02-22 주식회사 다인건설 Piers Reinforced Construction Equipment And Construction Methods

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20220161584A (en) 2021-05-27 2022-12-07 박석암 A repairing method for column type underwater structures

Also Published As

Publication number Publication date
KR101211101B1 (en) 2012-12-11

Similar Documents

Publication Publication Date Title
CA3013854C (en) Foundation for a wind mill
CA3013852C (en) Foundation for a wind mill
KR100837608B1 (en) J.K Bracket Method
CN101813069A (en) Foundation for enabling anchoring of a wind turbine tower thereto by means of replaceable through-bolts
JP5012355B2 (en) Underwater structure reinforcement method, underwater structure
KR101025892B1 (en) Concrete steel house
KR100946879B1 (en) Connection for Steel Pile Head, Connection Structure and Method of Pile and Precast Concrete Pier Structure
KR101173029B1 (en) Under Water Structure Building and Maintenance and Reinforce Method Using Water Tightened Caisson
KR100949597B1 (en) Method for enhancing bearing power of existing bridges using the a pile
CN107165056B (en) Anti-overturning steel bar bracket for cantilever bent cap concrete pouring and mounting method thereof
KR20120029625A (en) Construction method of steel composite girder bridge applying precast deck
US7351013B2 (en) Unitary pile jacking sleeve for installing and compressively loading piling without overhead access and without disrupting a super-structure
KR20100073881A (en) Dummy bearing for bridge using sand and upper structure of bridge supporting method thterewith
KR101211101B1 (en) A bridge post strengthen structure and construction methode there of
KR20120100052A (en) Bridge leg correcting method using oil compressure jack and broken parts compensation structure
CN215165508U (en) Dado stake
JP5534861B2 (en) PC well and bridge construction method
CN114293564A (en) Construction method for foundation pit slope pile foundation of building engineering on site
KR100609825B1 (en) Preflexed rigid- frame bridge installed using prestressed upper structure and constructing method thereof
CN202577324U (en) Reinforced-concrete combined hanging box
KR20110050032A (en) A structure and method of bridge pier mould construction repair
KR20060017433A (en) Foundation well bucket and bridge new construction method of large bridge
KR100949868B1 (en) The enlargement construction method for base of bridge with guides and molds in the shape of pipes
JP7431142B2 (en) Construction method of underground structure and scaffolding structure
JP7051058B2 (en) Repair method for existing irrigation canals

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20160302

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20161128

Year of fee payment: 5

LAPS Lapse due to unpaid annual fee