JP7431142B2 - Construction method of underground structure and scaffolding structure - Google Patents

Construction method of underground structure and scaffolding structure Download PDF

Info

Publication number
JP7431142B2
JP7431142B2 JP2020185303A JP2020185303A JP7431142B2 JP 7431142 B2 JP7431142 B2 JP 7431142B2 JP 2020185303 A JP2020185303 A JP 2020185303A JP 2020185303 A JP2020185303 A JP 2020185303A JP 7431142 B2 JP7431142 B2 JP 7431142B2
Authority
JP
Japan
Prior art keywords
shaft
concrete
steel frame
hole
outer periphery
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2020185303A
Other languages
Japanese (ja)
Other versions
JP2022074888A (en
Inventor
正利 戸張
忠宏 佐藤
一正 矢野
慎一郎 柑本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2020185303A priority Critical patent/JP7431142B2/en
Publication of JP2022074888A publication Critical patent/JP2022074888A/en
Application granted granted Critical
Publication of JP7431142B2 publication Critical patent/JP7431142B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、地下構造物の構築方法およびこれに用いる足場構造に関する。 The present invention relates to a method for constructing an underground structure and a scaffolding structure used therein.

従来、深礎基礎は、地盤に立坑を掘削し、立坑の内部に鉄筋篭を組み立ててコンクリートを打設することによって構築されている(例えば、特許文献1、2参照)。 Conventionally, deep foundations are constructed by excavating a shaft in the ground, assembling a reinforcing cage inside the shaft, and pouring concrete (for example, see Patent Documents 1 and 2).

例えば特許文献1では、立坑の中央部のトレミー管を用いてコンクリートを打設することが記載されており、また特許文献2には、足場部材の下面に浮き部材を設けた作業用足場を用い、立坑内にコンクリートを打設する際にこの作業用足場をコンクリート上に浮かせて足場上で締固め作業を行うことが記載されている。 For example, Patent Document 1 describes placing concrete using a tremie pipe in the center of a shaft, and Patent Document 2 describes using a working scaffold with a floating member provided on the lower surface of the scaffold member. , describes that when pouring concrete into a shaft, this work scaffold is floated on top of the concrete and compaction work is performed on the scaffold.

特開平06-306864号公報Japanese Patent Application Publication No. 06-306864 特開平08-120913号公報Japanese Patent Application Publication No. 08-120913

しかしながら、上記のような方法で大規模な深礎基礎を構築すると、コンクリートの打設に大変な手間がかかり、特に配筋の密集した箇所でコンクリートを充填することは難しい。そのため、コンクリートの打設を容易に行い施工作業を効率化できる手法が望まれていた。 However, when constructing a large-scale deep foundation using the method described above, it takes a lot of effort to pour concrete, and it is especially difficult to fill in areas with dense reinforcement. Therefore, there has been a need for a method that can easily place concrete and improve the efficiency of construction work.

本発明は上記の問題点に鑑みてなされたものであり、その目的は、施工作業を効率化できる地下構造物の構築方法等を提供することである。 The present invention has been made in view of the above-mentioned problems, and its purpose is to provide a method of constructing an underground structure, etc., which can improve the efficiency of construction work.

前述した目的を達成するための第1の発明は、地下構造物の構築方法であって、地盤に形成した立坑内の外周部に補強材を配置する工程と、前記立坑内にコンクリートを打設する工程と、を有し、コンクリートを打設する際、前記立坑内の外周部にコンクリートの打設を行うための打設孔を有する足場板を、前記補強材の上端部の高さに設け、圧送されたコンクリートを前記打設孔を介して前記立坑内の外周部で打設することを特徴とする地下構造物の構築方法である。 A first invention to achieve the above-mentioned object is a method for constructing an underground structure, which includes a step of arranging a reinforcing material on the outer periphery of a shaft formed in the ground, and pouring concrete into the shaft. and, when placing concrete, a scaffold board having a casting hole for pouring concrete on the outer periphery of the shaft is provided at a height of the upper end of the reinforcing material. , a method for constructing an underground structure, characterized in that the pumped concrete is placed at the outer periphery of the shaft through the placing hole.

本発明では、大規模な深礎基礎などの地下構造物を構築する際、鉄筋や形鋼などの補強材が配置された立坑の外周部において、補強材の上端部に足場板を設置し、その打設孔を用いてコンクリートの圧送、打設を行う。これにより、立坑の外周部で密に配筋されている場合にも迅速かつ確実にコンクリートを充填でき、コンクリートの打設に係る様々な作業を足場板上の作業員により容易に行うことができる。そのため、地下構造物の施工作業を効率化できる。 In the present invention, when constructing an underground structure such as a large-scale deep foundation, a scaffold board is installed at the upper end of the reinforcing material at the outer periphery of a shaft where reinforcing material such as reinforcing bars and shaped steel is placed, Concrete is pumped and placed using the pouring hole. This allows concrete to be filled quickly and reliably even when reinforcement is densely arranged around the outer circumference of a shaft, and allows workers on scaffolding boards to easily perform various tasks related to concrete placement. . Therefore, construction work for underground structures can be made more efficient.

前記足場板は、前記足場板の貫通孔に配置された固定部により前記補強材に固定されることが望ましい。また前記固定部は、前記貫通孔から上方に突出するように、前記補強材に取り付けられた固定板と、前記固定板の差込孔に差し込まれ、両端が前記足場板上に載置される梁状の差込材と、を有することが望ましい。
足場板は、固定部により補強材に固定し、位置ずれを防止することができる。また固定部は、上記のように固定板と差込材によるかんぬき状の構成とすることで、簡単な機構で足場板を確実に固定することができる。
It is preferable that the scaffold board is fixed to the reinforcing member by a fixing part disposed in a through hole of the scaffold board. Further, the fixing part is inserted into the fixing plate attached to the reinforcing member and the insertion hole of the fixing plate so as to protrude upward from the through hole, and both ends are placed on the scaffold board. It is desirable to have a beam-shaped insertion member.
The scaffold board can be fixed to the reinforcing member by the fixing part to prevent displacement. Moreover, by having the fixing portion have a bolt-like structure including the fixing plate and the insert material as described above, the scaffold board can be securely fixed with a simple mechanism.

前記補強材として、前記立坑内の外周部に鉛直方向の形鋼を配置することが望ましい。
地下構造物の補強材として強度の高い形鋼を用いることで、多量の鉄筋を配置する場合に比べて配筋作業を省力化することができる。
As the reinforcing material, it is desirable to arrange a vertically oriented steel section on the outer periphery of the shaft.
By using high-strength steel sections as reinforcing materials for underground structures, it is possible to save labor in reinforcing work compared to placing a large number of reinforcing bars.

第2の発明は、立坑内でのコンクリートの打設時に用いる足場構造であって、立坑内の外周部に配置された補強材の上端部の高さに設けられ、前記立坑内の外周部にコンクリートの打設を行うための打設孔を有する足場板を具備することを特徴とする足場構造である。 A second invention is a scaffolding structure used when pouring concrete in a shaft, which is provided at the height of the upper end of a reinforcing member placed on the outer periphery of the shaft. This is a scaffold structure characterized by comprising a scaffold board having a pouring hole for pouring concrete.

本発明によれば、施工作業を効率化できる地下構造物の構築方法等を提供できる。 According to the present invention, it is possible to provide a method for constructing an underground structure, etc., which can improve the efficiency of construction work.

深礎基礎10を示す図。A diagram showing a deep foundation 10. ストライプH形鋼を示す図。A diagram showing a striped H-beam. 深礎基礎10の構築方法について説明する図。The figure explaining the construction method of the deep foundation 10. 深礎基礎10の構築方法について説明する図。The figure explaining the construction method of the deep foundation 10. 深礎基礎10の構築方法について説明する図。The figure explaining the construction method of the deep foundation 10. 深礎基礎10の構築方法について説明する図。The figure explaining the construction method of the deep foundation 10. コンクリート打設システム100と足場板200を示す図。FIG. 2 is a diagram showing a concrete placing system 100 and a scaffold board 200. 足場板200と固定部230を示す図。FIG. 3 is a diagram showing a scaffolding board 200 and a fixing part 230. コンクリート9の打設について説明する図。FIG. 3 is a diagram illustrating the placement of concrete 9. コンクリート9の打設について説明する図。FIG. 3 is a diagram illustrating the placement of concrete 9.

以下、図面に基づいて本発明の好適な実施形態について詳細に説明する。 Hereinafter, preferred embodiments of the present invention will be described in detail based on the drawings.

(1.深礎基礎10)
図1は本発明の実施形態に係る構築方法で構築された地下構造物である深礎基礎10を示す図である。
(1. Deep foundation 10)
FIG. 1 is a diagram showing a deep foundation 10, which is an underground structure constructed by a construction method according to an embodiment of the present invention.

深礎基礎10は、径の大きな大口径深礎基礎であり、橋脚等の基礎として用いられる。 The deep foundation 10 is a large-diameter deep foundation, and is used as a foundation for bridge piers and the like.

深礎基礎10は、地盤1に形成された立坑2内にコンクリート9を打設することで構築される。立坑2および深礎基礎10は円形平面を有する。立坑2の壁面には図示しない鋼製リングが設けられ、吹付材が吹付けられる。あるいは、壁面にライナープレートを設ける場合や、壁面に吹付けを行いロックボルトを設ける場合もある。 The deep foundation 10 is constructed by pouring concrete 9 into a shaft 2 formed in the ground 1. The shaft 2 and the deep foundation 10 have a circular plane. A steel ring (not shown) is provided on the wall of the shaft 2, and a spray material is sprayed onto the ring. Alternatively, liner plates may be provided on the wall surface, or rock bolts may be provided by spraying on the wall surface.

深礎基礎10の外周部では、外側帯鉄筋5、外側鉄骨6、内側帯鉄筋7、内側鉄骨8等の補強材がコンクリート9に埋設される。なお外側とは立坑2の壁面に近い側をいい、内側とは立坑2の平面の中心に近い側をいうものとする。 At the outer periphery of the deep foundation 10, reinforcing materials such as outer band reinforcing bars 5, outer steel frames 6, inner band reinforcing bars 7, and inner steel frames 8 are buried in concrete 9. Note that the outside refers to the side closer to the wall surface of the shaft 2, and the inside refers to the side closer to the center of the plane of the shaft 2.

外側帯鉄筋5は、立坑2(深礎基礎10)の最外部に位置し、立坑2の周方向に沿って配置される鉄筋である。外側帯鉄筋5は、立坑2内の平面において円周状に配置される。外側帯鉄筋5は、鉛直方向に所定の間隔を空けて設置される。 The outer band reinforcing bars 5 are reinforcing bars located at the outermost part of the shaft 2 (deep foundation 10) and arranged along the circumferential direction of the shaft 2. The outer band reinforcing bars 5 are arranged circumferentially on a plane within the shaft 2. The outer band reinforcing bars 5 are installed at predetermined intervals in the vertical direction.

外側鉄骨6は、外側帯鉄筋5の内側に配置される鉛直方向の形鋼であり、本実施形態ではストライプH形鋼が用いられる。ストライプH形鋼は、図2に示すようにフランジ幅方向の凸条aをフランジ表面に設けたH形鋼である。 The outer steel frame 6 is a vertical steel section arranged inside the outer band reinforcing bar 5, and in this embodiment, a striped H section steel is used. The striped H-shaped steel is an H-shaped steel in which a protruding strip a extending in the flange width direction is provided on the flange surface, as shown in FIG.

外側鉄骨6は、ウェブの幅方向を立坑2の径方向に合わせ、立坑2の周方向に沿って所定の間隔を空けて複数設置される。また本実施形態では、複数本の外側鉄骨6が添接板63を用いたボルト接合により上下に連結して用いられる。 A plurality of outer steel frames 6 are installed at predetermined intervals along the circumferential direction of the shaft 2, with the width direction of the web aligned with the radial direction of the shaft 2. Further, in this embodiment, a plurality of outer steel frames 6 are used in a vertically connected manner by bolt connection using attachment plates 63.

内側帯鉄筋7は、外側鉄骨6の内側に位置し、立坑2の周方向に沿って配置される鉄筋である。内側帯鉄筋7は、立坑2内の平面において内外二重の同心円状に配置される。内側帯鉄筋7は、鉛直方向に所定の間隔を空けて設置される。 The inner band reinforcing bars 7 are reinforcing bars located inside the outer steel frame 6 and arranged along the circumferential direction of the shaft 2. The inner band reinforcing bars 7 are arranged in a double inner and outer concentric circle on a plane inside the shaft 2. The inner band reinforcing bars 7 are installed at predetermined intervals in the vertical direction.

内側鉄骨8は、内側帯鉄筋7の内側に配置される鉛直方向の形鋼であり、本実施形態ではストライプH形鋼が用いられる。内側鉄骨8は、ウェブの幅方向を立坑2の径方向に合わせ、立坑2の周方向に沿って所定の間隔を空けて複数設置される。また本実施形態では、複数本の内側鉄骨8が添接板83を用いたボルト接合により上下に連結して用いられる。 The inner steel frame 8 is a vertical steel section arranged inside the inner band reinforcing bar 7, and in this embodiment, a striped H section steel is used. A plurality of inner steel frames 8 are installed at predetermined intervals along the circumferential direction of the shaft 2, with the width direction of the web aligned with the radial direction of the shaft 2. Further, in this embodiment, a plurality of inner steel frames 8 are connected vertically by bolt connection using attachment plates 83.

なお、図1の符号3は外側鉄骨6と内側鉄骨8の設置に用いる設置台3であり、深礎基礎10では設置台3もコンクリート9に埋設される。また図1の符号4は設置台3の位置を固定するための底部コンクリートであり、上記のコンクリート9は底部コンクリート4の上に打設される。 Note that reference numeral 3 in FIG. 1 is an installation stand 3 used for installing the outer steel frame 6 and the inner steel frame 8, and in the deep foundation 10, the installation stand 3 is also buried in the concrete 9. Further, reference numeral 4 in FIG. 1 is a bottom concrete for fixing the position of the installation base 3, and the above-mentioned concrete 9 is placed on the bottom concrete 4.

(2.深礎基礎10の構築方法)
次に、図3~図6等を参照して深礎基礎10の構築方法について説明する。
(2. Method of constructing deep foundation 10)
Next, a method for constructing the deep foundation 10 will be explained with reference to FIGS. 3 to 6 and the like.

本実施形態では、地盤1を掘削して立坑2を形成した後、図3に示すように立坑2の底部に設置台3を設ける。設置台3は、H形鋼30と繋ぎ材31を有する。なお、図3において(a)は立坑2を上から見た図、(b)は立坑2の底部の鉛直断面を示す図である。これは以降の図4、5においても同様である。 In this embodiment, after excavating the ground 1 to form a shaft 2, an installation stand 3 is provided at the bottom of the shaft 2, as shown in FIG. The installation stand 3 has an H-shaped steel 30 and a connecting member 31. In addition, in FIG. 3, (a) is a view of the shaft 2 viewed from above, and (b) is a view showing a vertical cross section of the bottom of the shaft 2. This also applies to subsequent FIGS. 4 and 5.

H形鋼30は、ウェブの幅方向を鉛直方向に合わせ、立坑2の径方向に沿って配置される。H形鋼30は、立坑2の周方向に沿って間隔を空けて複数本放射状に設けられる。H形鋼30の上フランジには、後述する外側鉄骨6や内側鉄骨8の固定に用いる孔(不図示)が設けられる。 The H-shaped steel 30 is arranged along the radial direction of the shaft 2 with the width direction of the web aligned with the vertical direction. A plurality of H-beams 30 are provided radially at intervals along the circumferential direction of the shaft 2. The upper flange of the H-shaped steel 30 is provided with holes (not shown) used for fixing an outer steel frame 6 and an inner steel frame 8, which will be described later.

繋ぎ材31は、立坑2の周方向に並んだ複数のH形鋼30を連結し、隣り合うH形鋼30同士の間隔を保持する。繋ぎ材31には例えばアングル材が用いられ、立坑2内の平面において内外二重の同心円状に配置される。繋ぎ材31はH形鋼30の上フランジにボルト等で接合される。 The connecting member 31 connects a plurality of H-beams 30 lined up in the circumferential direction of the shaft 2, and maintains a distance between adjacent H-beams 30. For example, an angle member is used as the connecting member 31, and it is arranged in a double concentric circle shape inside and outside the shaft 2 on a plane inside the shaft 2. The connecting member 31 is joined to the upper flange of the H-beam 30 with bolts or the like.

立坑2の底部では、必要に応じて立坑2の外周部に均しコンクリート33を打設し、不陸を調整する。H形鋼30は均しコンクリート33上に墨出しを行って均しコンクリート33上の所定位置に設置される。H形鋼30は、アンカー34により均しコンクリート33やその下方の地盤1に固定される。 At the bottom of the shaft 2, leveling concrete 33 is poured around the outer periphery of the shaft 2 as necessary to adjust unevenness. The H-beam 30 is marked on the leveled concrete 33 and installed at a predetermined position on the leveled concrete 33. The H-beam 30 is fixed to leveled concrete 33 or the ground 1 below it by anchors 34.

本実施形態では、次に、図4に示すように外側帯鉄筋5と外側鉄骨6を設置する。ここでは、まず立坑2の底部に底部コンクリート4を打設し、設置台3の位置を固定する。底部コンクリート4は、後述する外側鉄骨6や内側鉄骨8の固定作業を考慮して、H形鋼30の上部が露出するように打設する。 In this embodiment, next, as shown in FIG. 4, outer band reinforcing bars 5 and outer steel frames 6 are installed. Here, first, bottom concrete 4 is placed at the bottom of the shaft 2, and the position of the installation stand 3 is fixed. The bottom concrete 4 is cast so that the upper part of the H-beam 30 is exposed, taking into account the work of fixing the outer steel frame 6 and the inner steel frame 8, which will be described later.

底部コンクリート4を打設したら、立坑2の外周部に外側帯鉄筋5と外側鉄骨6を配置する。外側帯鉄筋5は、立坑2の壁面に設置した取付材(不図示)に固定して配置する。外側鉄骨6は外側帯鉄筋5の内側に設置する。 After the bottom concrete 4 is placed, outer band reinforcing bars 5 and outer steel frames 6 are placed around the outer periphery of the shaft 2. The outer band reinforcing bars 5 are fixed to mounting members (not shown) installed on the wall surface of the shaft 2. The outer steel frame 6 is installed inside the outer band reinforcement 5.

図4(b)に示すように、外側鉄骨6の下端にはエンドプレート61が設けられており、外側鉄骨6の設置時には、エンドプレート61の孔(不図示)をH形鋼30の上フランジの孔と連通させ、これらの孔に頭付きボルト64の軸部を下から挿入し、エンドプレート61から突出する軸部の先端にナット65を締め込む。これにより、外側鉄骨6がH形鋼30の上フランジに固定される。 As shown in FIG. 4(b), an end plate 61 is provided at the lower end of the outer steel frame 6, and when installing the outer steel frame 6, a hole (not shown) in the end plate 61 is inserted into the upper flange of the H-beam 30. The shafts of headed bolts 64 are inserted into these holes from below, and nuts 65 are tightened onto the tips of the shafts protruding from the end plate 61. Thereby, the outer steel frame 6 is fixed to the upper flange of the H-section steel 30.

こうして立坑2の周方向に複数の外側鉄骨6が配置される。これらの外側鉄骨6の上端部同士は、立坑2の周方向に沿って配置された繋ぎ材62によって連結される。 In this way, a plurality of outer steel frames 6 are arranged in the circumferential direction of the shaft 2. The upper ends of these outer steel frames 6 are connected to each other by a connecting member 62 arranged along the circumferential direction of the shaft 2.

繋ぎ材62は例えばアングル材であり、内外二重の同心円状に配置される。内外の繋ぎ材62は、立坑2の周方向に並んだ複数の外側鉄骨6の内側フランジと外側フランジにそれぞれボルト等で接合され、これにより複数の外側鉄骨6の上端部同士が繋ぎ材62により連結される。繋ぎ材62により隣り合う外側鉄骨6同士の間隔が保持され、外側鉄骨6の設置精度が高まる。 The connecting members 62 are, for example, angle members, and are arranged in a concentric double inner and outer circle. The inner and outer connecting members 62 are joined to the inner flanges and outer flanges of the plurality of outer steel frames 6 arranged in the circumferential direction of the shaft 2 with bolts, etc., so that the upper ends of the plurality of outer steel frames 6 are connected to each other by the connecting members 62. Concatenated. The spacing between adjacent outer steel frames 6 is maintained by the connecting members 62, and the installation accuracy of the outer steel frames 6 is increased.

次に、図5に示すように、外側鉄骨6から所定の間隔を空けて、外側鉄骨6の内側に内側帯鉄筋7と内側鉄骨8を設置する。内側帯鉄筋7は、外側鉄骨6に設けた取付治具(不図示)に固定することができる。内側鉄骨8は内側帯鉄筋7の内側に設置する。内側鉄骨8の下端にはエンドプレート81が設けられており、当該エンドプレート81を先程と同様に頭付ボルト84とナット85を用いてH形鋼30の上フランジに固定する。 Next, as shown in FIG. 5, the inner band reinforcing bars 7 and the inner steel frame 8 are installed inside the outer steel frame 6 at a predetermined distance from the outer steel frame 6. The inner band reinforcing bars 7 can be fixed to a mounting jig (not shown) provided on the outer steel frame 6. The inner steel frame 8 is installed inside the inner band reinforcing bar 7. An end plate 81 is provided at the lower end of the inner steel frame 8, and the end plate 81 is fixed to the upper flange of the H-section steel 30 using head bolts 84 and nuts 85 in the same manner as before.

内側鉄骨8は、立坑2の周方向に複数配置される。これらの内側鉄骨8の上端部同士は、先程の繋ぎ材62と同様の繋ぎ材82を用いて、外側鉄骨6と同様に連結される。 A plurality of inner steel frames 8 are arranged in the circumferential direction of the shaft 2. The upper ends of these inner steel frames 8 are connected in the same manner as the outer steel frames 6 using a connecting member 82 similar to the connecting member 62 described above.

こうして図6(a)に示すように立坑2内に外側帯鉄筋5、外側鉄骨6、内側帯鉄筋7、内側鉄骨8が設置される。その後、図6(b)に示すように立坑2内にコンクリート9を打設することで、深礎基礎10の一部が構築される。なおコンクリート9は外側鉄骨6や内側鉄骨8の上端部が露出するように打設し、前記の繋ぎ材62、82はコンクリート9の打設後に取り外して後の工程で転用する。 In this way, the outer band reinforcing bars 5, the outer steel frames 6, the inner band reinforcing bars 7, and the inner steel frames 8 are installed in the shaft 2 as shown in FIG. 6(a). Thereafter, a part of the deep foundation 10 is constructed by placing concrete 9 in the shaft 2 as shown in FIG. 6(b). The concrete 9 is cast so that the upper ends of the outer steel frame 6 and the inner steel frame 8 are exposed, and the connecting members 62 and 82 are removed after the concrete 9 is cast and reused in a later process.

その後、図6(c)に示すように、先程設置した外側帯鉄筋5、外側鉄骨6、内側帯鉄筋7、内側鉄骨8の上方に、新たな外側帯鉄筋5、外側鉄骨6、内側帯鉄筋7、内側鉄骨8を先程と同様に設置する。ただし、外側鉄骨6、内側鉄骨8の下端は、設置台3に固定されるのではなく、その下段の外側鉄骨6、内側鉄骨8の上端に添接板63、83を用いて連結される。 After that, as shown in FIG. 6(c), new outer band reinforcing bars 5, outer steel frames 6, and inner band reinforcing bars are placed above the outer band reinforcing bars 5, outer steel frames 6, inner band reinforcing bars 7, and inner steel frames 8 that were installed earlier. 7. Install the inner steel frame 8 in the same way as before. However, the lower ends of the outer steel frame 6 and the inner steel frame 8 are not fixed to the installation stand 3, but are connected to the upper ends of the lower outer steel frame 6 and inner steel frame 8 using attachment plates 63 and 83.

そして、先程打設したコンクリート9の上方に、図6(d)に示すように新たなコンクリート9を打設する。以下図6(c)、(d)の工程を繰り返すことで図1に示す深礎基礎10が構築される。 Then, new concrete 9 is placed above the concrete 9 that was previously placed, as shown in FIG. 6(d). The deep foundation 10 shown in FIG. 1 is constructed by repeating the steps shown in FIGS. 6(c) and 6(d).

(3.コンクリート9の打設)
本実施形態では、図7に示すコンクリート打設システム100を用いてコンクリート9を打設する。図7(a)はコンクリート打設システム100の立面図であり、図7(b)はコンクリート打設システム100を上から見た図である。
(3. Placing concrete 9)
In this embodiment, concrete 9 is placed using a concrete placing system 100 shown in FIG. FIG. 7(a) is an elevation view of the concrete placement system 100, and FIG. 7(b) is a top view of the concrete placement system 100.

コンクリート打設システム100は、架台110、ディストリビュータ(間配り機)120、バケット130、フロート足場140等を有する。 The concrete placement system 100 includes a pedestal 110, a distributor 120, a bucket 130, a float scaffold 140, and the like.

架台110は、立坑2内の中央部で底部コンクリート4上に設置される平面十字状の架台であり、その上端は外側鉄骨6や内側鉄骨8の上端より高い位置にある。 The pedestal 110 is a planar cross-shaped pedestal installed on the bottom concrete 4 at the center of the shaft 2, and its upper end is located at a higher position than the upper ends of the outer steel frame 6 and the inner steel frame 8.

架台110は、鉛直方向の支柱111と、上下複数段の水平材112を組み合わせて形成される。また架台110の内部には作業足場114が配置され、架台110の上部には渡り足場115が平面十字状に配置される。 The pedestal 110 is formed by combining a vertical support 111 and horizontal members 112 in multiple stages above and below. Further, a work scaffold 114 is disposed inside the pedestal 110, and a crossing scaffold 115 is disposed above the pedestal 110 in a planar cross shape.

作業足場114は、架台110の上部のホイストから吊り下げたチェーン(不図示)によって図7(a)の矢印bに示すように架台110内で昇降可能となっており、架台110に設けたブラケット113に載置される。ブラケット113は架台110で上下複数段に設けられる。 The work scaffold 114 can be moved up and down within the pedestal 110 as shown by arrow b in FIG. 113. The brackets 113 are provided in a plurality of upper and lower stages on the pedestal 110.

ディストリビュータ120は、立坑2内の外周部にコンクリート9を圧送、打設するための装置であり、架台110上に設けられる。 The distributor 120 is a device for pumping and pouring the concrete 9 to the outer circumference of the shaft 2, and is provided on the pedestal 110.

ディストリビュータ120は、旋回部121と圧送配管122を有し、台部125によって架台110上に固定される。 The distributor 120 has a rotating part 121 and a pressure-feeding pipe 122, and is fixed on the pedestal 110 by a pedestal part 125.

旋回部121は水平方向に延びる部材である。旋回部121は、先端に取り付けられたロープ(不図示)を引張るなどして、手動により立坑2の平面中心周りに回転させることができる。 The rotating portion 121 is a member extending in the horizontal direction. The rotating portion 121 can be manually rotated around the plane center of the shaft 2 by pulling a rope (not shown) attached to the tip.

圧送配管122はコンクリート9を圧送するための配管であり、旋回部121に沿って取り付けられる。圧送配管122は地上のコンクリートポンプ車(不図示)に接続される。圧送配管122は、旋回部121とともに平面において回転させることができる。 The pressure-feeding pipe 122 is a pipe for pressure-feeding the concrete 9, and is installed along the turning portion 121. The pressure pipe 122 is connected to a concrete pump truck (not shown) on the ground. The pressure feeding pipe 122 can be rotated in a plane together with the turning section 121.

圧送配管122の先端の吐出口は、立坑2の壁面付近に配置される。コンクリート9の圧送、打設時には圧送配管122の吐出口にコンクリート9の流路となるホース124を取り付け、立坑2の外周部に垂下させる。 The discharge port at the tip of the pressure-feeding pipe 122 is arranged near the wall surface of the shaft 2. When the concrete 9 is being pumped and placed, a hose 124 is attached to the discharge port of the pressure pipe 122 to serve as a flow path for the concrete 9, and is suspended from the outer periphery of the shaft 2.

バケット130は、立坑2内の中央部でコンクリート9を打設するためのものであり、コンクリート9を収容した状態でクレーン等の揚重機(不図示)によって立坑2内に吊り込まれる。 The bucket 130 is used to place concrete 9 in the center of the shaft 2, and is suspended into the shaft 2 by a lifting device (not shown) such as a crane while containing the concrete 9.

フロート足場140は、架台110の平面位置を避けて底部コンクリート4上に配置される。 The floating scaffold 140 is placed on the bottom concrete 4, avoiding the planar position of the pedestal 110.

また本実施形態では、立坑2内の外周部において、外側鉄骨6と内側鉄骨8の上端部の高さで足場板200を円周状に設け、この足場板200を用いてコンクリート9の打設に係る作業を行う。なお、足場板200と渡り足場115の間には図示しない階段が設置され、足場板200と架台110の間の往来が可能である。 In addition, in this embodiment, a scaffold board 200 is provided in a circumferential manner at the outer circumference of the shaft 2 at the height of the upper ends of the outer steel frame 6 and the inner steel frame 8, and this scaffold board 200 is used to place the concrete 9. Perform work related to. Note that a staircase (not shown) is installed between the scaffolding board 200 and the crossing scaffolding 115, and it is possible to go back and forth between the scaffolding board 200 and the pedestal 110.

図8(a)は足場板200の平面図であり、図8(b)~(d)はそれぞれ図8(a)の線A-A、線B-B、線C-Cによる鉛直方向の断面を示す図である。 FIG. 8(a) is a plan view of the scaffolding board 200, and FIGS. 8(b) to 8(d) are the vertical directions along lines AA, BB, and CC in FIG. 8(a), respectively. FIG. 3 is a diagram showing a cross section.

足場板200は、内外の辺を立坑2の外周部に沿った曲率の略円弧状とした(上記曲率の円弧を直線近似した)扇形の平面を有し、打設孔210と貫通孔220が設けられる。本実施形態では、複数の足場板200が、図7(b)に示すように立坑2の外周部に沿って円周状に並べて配置される。 The scaffolding board 200 has a fan-shaped plane whose inner and outer sides are approximately arc-shaped with a curvature along the outer periphery of the shaft 2 (the arc of the above-mentioned curvature is approximated by a straight line), and the casting hole 210 and the through hole 220 are formed. provided. In this embodiment, a plurality of scaffolding boards 200 are arranged in a circumferential manner along the outer periphery of the shaft 2, as shown in FIG. 7(b).

打設孔210は、立坑2内の外周部にコンクリート9の打設を行うための孔であり、外側鉄骨6、内側鉄骨8を避けた位置に形成される。打設孔210は立坑2の周方向に間隔を空けて複数設けられる。 The pouring hole 210 is a hole for pouring concrete 9 on the outer periphery of the shaft 2, and is formed at a position avoiding the outer steel frame 6 and the inner steel frame 8. A plurality of driving holes 210 are provided at intervals in the circumferential direction of the shaft 2.

打設孔210は、通常時、蓋211により閉じられており、コンクリート9の打設時に蓋211を外して開放される。図8(c)、(d)に示すように、蓋211の下面には、打設孔210に挿入される挿入部213が設けられる。挿入部213にはアングル材等が用いられ、打設孔210の縁部に沿って配置される。なお図8(c)、(d)の符号212は蓋211の上面に設けた取っ手である。 The pouring hole 210 is normally closed with a lid 211, and is opened by removing the lid 211 when pouring concrete 9. As shown in FIGS. 8(c) and 8(d), an insertion portion 213 inserted into the casting hole 210 is provided on the lower surface of the lid 211. An angle material or the like is used for the insertion portion 213, and it is arranged along the edge of the casting hole 210. Note that reference numeral 212 in FIGS. 8(c) and 8(d) is a handle provided on the top surface of the lid 211.

貫通孔220は、足場板200を外側鉄骨6、内側鉄骨8に固定するための孔であり、外側鉄骨6、内側鉄骨8と対応する位置に形成される。その他、足場板200の上面の内周側には図示しない手摺等も設けられる。 The through holes 220 are holes for fixing the scaffolding board 200 to the outer steel frame 6 and the inner steel frame 8, and are formed at positions corresponding to the outer steel frame 6 and the inner steel frame 8. In addition, a handrail (not shown) is also provided on the inner peripheral side of the upper surface of the scaffold board 200.

図8(b)に示すように、足場板200は、天板201の下面に立坑2の径方向および周方向の骨組材202を設けたものであり、径方向の骨組材202を外側鉄骨6、内側鉄骨8の繋ぎ材62、82に載せて配置する。前記の打設孔210や貫通孔220は天板201に設けられ、足場板200は貫通孔220の内側に配置された固定部230を用いて外側鉄骨6や内側鉄骨8に固定される。 As shown in FIG. 8(b), the scaffold board 200 is provided with frame members 202 in the radial direction and circumferential direction of the vertical shaft 2 on the lower surface of the top plate 201, and the radial frame members 202 are connected to the outer steel frame 6. , placed on the connecting members 62, 82 of the inner steel frame 8. The above-mentioned casting holes 210 and through holes 220 are provided in the top plate 201, and the scaffolding board 200 is fixed to the outer steel frame 6 and the inner steel frame 8 using fixing parts 230 arranged inside the through holes 220.

固定部230は固定板231、差込材232等を有し、足場板200と固定部230は本発明における足場構造を構成する。 The fixing part 230 has a fixing plate 231, an insert member 232, etc., and the scaffold board 200 and the fixing part 230 constitute a scaffold structure in the present invention.

固定板231は、外側鉄骨6、内側鉄骨8の上端部のウェブを両側から挟むように一対配置される。この時、固定板231の孔(不図示)と、添接板63、83のボルト接合に用いるウェブの孔(不図示)が連通し、一方の固定板231側からこれらの孔に頭付ボルトの軸部を通し、他方の固定板231から突出する軸部の先端にナットを締め込む。これにより、頭付ボルトとナット等による締結具233を用いて固定板231がウェブに取付けられる。 A pair of fixing plates 231 are arranged so as to sandwich the upper end webs of the outer steel frame 6 and the inner steel frame 8 from both sides. At this time, the holes (not shown) in the fixing plate 231 communicate with the holes (not shown) in the web used for bolting the attachment plates 63 and 83, and the headed bolts are inserted into these holes from the fixing plate 231 side. 2, and tighten a nut onto the tip of the shaft protruding from the other fixed plate 231. As a result, the fixing plate 231 is attached to the web using fasteners 233 such as headed bolts and nuts.

各固定板231は、貫通孔220から上方に突出するように配置され、この突出部分に差込孔234が設けられる。これらの差込孔234に梁状の差込材232を差し込み、図8(d)に示すように差込材232の両端を足場板200上に載置する。差込材232には角形鋼管が用いられるが、これに限ることはない。 Each fixing plate 231 is arranged so as to protrude upward from the through hole 220, and an insertion hole 234 is provided in this protruding portion. Beam-shaped inserts 232 are inserted into these insertion holes 234, and both ends of the inserts 232 are placed on the scaffold board 200 as shown in FIG. 8(d). Although a square steel pipe is used for the insertion member 232, the present invention is not limited to this.

以上の固定部230により、足場板200が外側鉄骨6と内側鉄骨8から外れないように固定される。なお、差込材232には、頭部と軸部を有する差込棒236が、その頭部が差込材232上に位置し、軸部が差込材232を貫通して貫通孔220の内側に達するように設けられる。また差込材232の上面には、L字状の金具等によるストッパ235も設けられる。 The above fixing portions 230 fix the scaffolding board 200 so that it does not come off the outer steel frame 6 and the inner steel frame 8. The insertion rod 236 has a head and a shaft portion, and the head portion thereof is located on the insertion material 232 and the shaft portion passes through the insertion material 232 and is inserted into the through hole 220. It is installed to reach the inside. Further, a stopper 235 made of an L-shaped metal fitting or the like is also provided on the upper surface of the insertion member 232.

ストッパ235と差込棒236は固定板231を挟むように設けられ、これにより差込材232が固定板231の差込孔234から抜けるのが防止される。なお図8(d)の符号236は差込材232の上面に設けた取っ手である。 The stopper 235 and the insertion rod 236 are provided to sandwich the fixing plate 231, thereby preventing the insert material 232 from coming out of the insertion hole 234 of the fixing plate 231. Note that the reference numeral 236 in FIG. 8(d) is a handle provided on the upper surface of the insert member 232.

本実施形態では、ディストリビュータ120とバケット130とを併用し、コンクリート9を複数系統で並行して打設する。 In this embodiment, the distributor 120 and the bucket 130 are used in combination to pour concrete 9 in multiple systems in parallel.

ディストリビュータ120による打設では、旋回部121により圧送配管122を回転させてその先端の吐出口を打設孔210の位置に移動させ、ホース124を吐出口に取り付ける。 In casting by the distributor 120, the rotating part 121 rotates the pressure feeding pipe 122 to move the discharge port at the tip thereof to the position of the casting hole 210, and the hose 124 is attached to the discharge port.

そして、打設孔210の蓋211を取り外し、ホース124を打設孔210に通して立坑2の外周部で垂下させ、コンクリートポンプ車から圧送配管122を介してコンクリート9を圧送し、立坑2の外周部にコンクリート9を打設する。 Then, the cover 211 of the pouring hole 210 is removed, the hose 124 is passed through the pouring hole 210 and suspended at the outer periphery of the shaft 2, and the concrete 9 is force-fed from the concrete pump vehicle via the pressure-feeding pipe 122, and the concrete 9 is pumped through the shaft 2. Concrete 9 is poured around the outer periphery.

これにより、外側帯鉄筋5、外側鉄骨6、内側帯鉄筋7、内側鉄骨8等の補強材の密集した立坑2の外周部に迅速かつ確実にコンクリート9が充填される。ホース124の下端はコンクリート9の天端の上昇に応じて引き上げる。 As a result, concrete 9 is quickly and reliably filled into the outer circumference of the shaft 2 where reinforcing materials such as the outer band reinforcing bars 5, the outer steel frames 6, the inner band reinforcing bars 7, and the inner steel frames 8 are densely packed. The lower end of the hose 124 is pulled up in accordance with the rise of the top end of the concrete 9.

一方、配筋の行われていない立坑2の中央部では、バケット130によるコンクリート9の打設が行われる。このように複数系統でコンクリート9を打設することにより、立坑2内でのコンクリート9の打設作業を合理化できる。 On the other hand, concrete 9 is placed using a bucket 130 in the center of the shaft 2 where reinforcement is not arranged. By placing the concrete 9 in multiple systems in this manner, the work of placing the concrete 9 within the shaft 2 can be streamlined.

図9に示すように、フロート足場140はコンクリート9の天端の上昇に伴って上昇し、常にコンクリート9の天端に配置される。コンクリート9は数段階に分けて打ち継ぎ、作業足場114はコンクリート9の打設作業の進行に応じて適切なタイミングで上昇させ、適切な高さのブラケット113に載置する。例えば図9に示す天端の位置までコンクリート9を打設する場合、その直上のブラケット113に作業足場114を事前に載置しておく。コンクリート9の締固め作業等は、これらの作業足場114やフロート足場140から行うことができる。 As shown in FIG. 9, the floating scaffold 140 rises as the top of the concrete 9 rises, and is always placed at the top of the concrete 9. The concrete 9 is poured in several stages, and the work scaffold 114 is raised at an appropriate timing as the concrete 9 pouring work progresses, and placed on the bracket 113 at an appropriate height. For example, when pouring concrete 9 to the top position shown in FIG. 9, a work scaffold 114 is placed in advance on a bracket 113 directly above the concrete 9. Compaction work of the concrete 9 and the like can be performed from these work scaffolds 114 and float scaffolds 140.

ディストリビュータ120による打設は、図10の矢印で示すように、圧送配管122を回転させて打設孔210の位置を変えながら順次実施する。バケット130による打設は上記打設孔210から離れた位置で行い、圧送配管122の回転に応じて打設位置を移動させる。これにより、バケット130の吊り込みとディストリビュータ120による打設が上下作業とならないようにする。 The casting by the distributor 120 is performed sequentially while rotating the pressure feed pipe 122 and changing the position of the casting hole 210, as shown by the arrow in FIG. Driving with the bucket 130 is performed at a position away from the driving hole 210, and the driving position is moved in accordance with the rotation of the pressure feed pipe 122. This prevents lifting of the bucket 130 and pouring by the distributor 120 from being vertical work.

以上の作業により、図6(b)に示すようにコンクリート9が打設される。コンクリート9の打設後、固定部230を取り外して足場板200を撤去し、後の工程で転用する。一方、架台110はコンクリート9中に残置して埋殺しとする。なお図1および図6(b)~(d)では架台110の図示を省略している。 Through the above operations, concrete 9 is placed as shown in FIG. 6(b). After pouring the concrete 9, the fixing part 230 is removed and the scaffolding board 200 is removed to be used in a later process. On the other hand, the pedestal 110 is left in the concrete 9 and buried. Note that illustration of the pedestal 110 is omitted in FIG. 1 and FIGS. 6(b) to 6(d).

このように、本実施形態によれば、深礎基礎10を構築する際、外側鉄骨6や内側鉄骨8などの補強材が配置された立坑2の外周部において、外側鉄骨6や内側鉄骨8の上端部に足場板200を設置し、その打設孔210を用いてコンクリート9の圧送、打設を行う。これにより、立坑2の外周部で密に配筋されている場合にも迅速かつ確実にコンクリート9を充填でき、圧送配管122(旋回部121)の回転やホース124の取付など、コンクリート9の打設に係る様々な作業を足場板200上の作業員により容易に行うことができる。そのため、深礎基礎10の施工作業を効率化できる。 As described above, according to the present embodiment, when constructing the deep foundation 10, the outer steel frame 6 and the inner steel frame 8 are installed at the outer periphery of the shaft 2 where reinforcing members such as the outer steel frame 6 and the inner steel frame 8 are arranged. A scaffolding board 200 is installed at the upper end, and the concrete 9 is pumped and placed using its casting hole 210. This makes it possible to quickly and reliably fill the concrete 9 even when reinforcement is densely arranged around the outer periphery of the shaft 2. Various construction-related works can be easily performed by workers on the scaffolding board 200. Therefore, the construction work of the deep foundation 10 can be made more efficient.

また足場板200は、固定部230により外側鉄骨6や内側鉄骨8に固定し、位置ずれを防止することができる。また固定部230は、前記の固定板231と差込材232によるかんぬき状の構成とすることで、簡単な機構で足場板200を確実に固定することができる。 Furthermore, the scaffolding board 200 can be fixed to the outer steel frame 6 and the inner steel frame 8 by the fixing portion 230 to prevent positional displacement. In addition, the fixing portion 230 has a bar-shaped configuration including the fixing plate 231 and the insert member 232, so that the scaffold board 200 can be securely fixed with a simple mechanism.

また本実施形態では深礎基礎10の補強材として強度の高い形鋼(外側鉄骨6、内側鉄骨8)を用いることで、多量の鉄筋を配置する場合に比べて配筋作業を省力化することができる。 In addition, in this embodiment, by using high-strength shaped steel (outer steel frame 6, inner steel frame 8) as a reinforcing material for the deep foundation 10, it is possible to save labor in reinforcing work compared to when arranging a large number of reinforcing bars. I can do it.

しかしながら、本発明は以上の実施形態に限らない。例えば、深礎基礎10内の配筋は前記に限らず、外周部に補強材が配置されていればよい。例えば内側鉄骨8を省略すること等も可能であり、外側帯鉄筋5や内側帯鉄筋7の段数も変えることができる。また外側鉄骨6や内側鉄骨8として、ストライプH形鋼以外の形鋼を用いることも可能である。また立坑2の中央部において、バケット130以外の打設方法を適用することも可能である。 However, the present invention is not limited to the above embodiments. For example, the reinforcement arrangement within the deep foundation 10 is not limited to the above-mentioned example, and any reinforcing material may be provided on the outer periphery. For example, it is possible to omit the inner steel frame 8, and the number of stages of the outer band reinforcing bars 5 and the inner band reinforcing bars 7 can also be changed. Moreover, it is also possible to use steel sections other than striped H-section steel as the outer steel frame 6 and the inner steel frame 8. Further, in the center of the shaft 2, it is also possible to apply a driving method other than the bucket 130.

また足場板200の形状、構成等も前記に限らず、打設孔210を有していればよい。また固定部230も前記した例の他、立坑2の外周部の補強材に足場板200を固定できるものであればよい。 Further, the shape, configuration, etc. of the scaffolding board 200 are not limited to those described above, as long as it has the casting hole 210. In addition to the above-mentioned example, the fixing part 230 may be any other member as long as it can fix the scaffold board 200 to the reinforcing material on the outer periphery of the shaft 2.

また本実施形態では、地下構造物として深礎基礎10を構築する例を説明したが、本実施形態の構築方法は、その他の地下構造物を構築する場合にも適用することができる。 Further, in this embodiment, an example of constructing the deep foundation 10 as an underground structure has been described, but the construction method of this embodiment can also be applied to the case of constructing other underground structures.

以上、添付図面を参照しながら、本発明に係る好適な実施形態について説明したが、本発明はかかる例に限定されない。当業者であれば、本願で開示した技術的思想の範疇内において、各種の変更例又は修正例に想到し得ることは明らかであり、それらについても当然に本発明の技術的範囲に属するものと了解される。 Although preferred embodiments of the present invention have been described above with reference to the accompanying drawings, the present invention is not limited to such examples. It is clear that those skilled in the art can come up with various changes or modifications within the scope of the technical idea disclosed in this application, and these naturally fall within the technical scope of the present invention. Understood.

1:地盤
2:立坑
3:設置台
4:底部コンクリート
5:外側帯鉄筋
6:外側鉄骨
7:内側帯鉄筋
8:内側鉄骨
9:コンクリート
10:深礎基礎
100:コンクリート打設システム
110:架台
120:ディストリビュータ
130:バケット
140:フロート足場
200:足場板
210:打設孔
220:貫通孔
230:固定部
231:固定板
232:差込材
1: Ground 2: Shaft 3: Installation platform 4: Bottom concrete 5: Outer band reinforcement 6: Outer steel frame 7: Inner band reinforcement 8: Inner steel frame 9: Concrete 10: Deep foundation 100: Concrete placement system 110: Frame 120 : Distributor 130: Bucket 140: Float scaffolding 200: Scaffolding board 210: Casting hole 220: Through hole 230: Fixed part 231: Fixed plate 232: Insert material

Claims (5)

地下構造物の構築方法であって、
地盤に形成した立坑内の外周部に補強材を配置する工程と、
前記立坑内にコンクリートを打設する工程と、
を有し、
コンクリートを打設する際、前記立坑内の外周部にコンクリートの打設を行うための打設孔を有する足場板を、前記補強材の上端部の高さに設け、圧送されたコンクリートを前記打設孔を介して前記立坑内の外周部で打設することを特徴とする地下構造物の構築方法。
A method for constructing an underground structure, the method comprising:
A step of placing reinforcing material around the outer periphery of a shaft formed in the ground;
a step of pouring concrete into the shaft;
has
When pouring concrete, a scaffold board having a pouring hole for pouring concrete on the outer periphery of the shaft is provided at the height of the upper end of the reinforcing material, and the pumped concrete is poured into the concrete. A method for constructing an underground structure, characterized in that the concrete is poured at the outer periphery of the shaft through a hole.
前記足場板は、前記足場板の貫通孔に配置された固定部により前記補強材に固定されることを特徴とする請求項1記載の地下構造物の構築方法。 2. The method of constructing an underground structure according to claim 1, wherein the scaffold board is fixed to the reinforcing material by a fixing part arranged in a through hole of the scaffold board. 前記固定部は、
前記貫通孔から上方に突出するように、前記補強材に取り付けられた固定板と、
前記固定板の差込孔に差し込まれ、両端が前記足場板上に載置される梁状の差込材と、
を有することを特徴とする請求項2に記載の地下構造物の構築方法。
The fixed part is
a fixing plate attached to the reinforcing material so as to protrude upward from the through hole;
a beam-shaped insertion material that is inserted into the insertion hole of the fixing plate and has both ends placed on the scaffolding board;
The method for constructing an underground structure according to claim 2, comprising:
前記補強材として、前記立坑内の外周部に鉛直方向の形鋼を配置することを特徴とする請求項1から請求項3のいずれかに記載の地下構造物の構築方法。 The method for constructing an underground structure according to any one of claims 1 to 3, characterized in that, as the reinforcing material, a vertically oriented steel section is arranged on the outer periphery of the shaft. 立坑内でのコンクリートの打設時に用いる足場構造であって、
立坑内の外周部に配置された補強材の上端部の高さに設けられ、前記立坑内の外周部にコンクリートの打設を行うための打設孔を有する足場板を具備することを特徴とする足場構造。
A scaffolding structure used when pouring concrete in a shaft,
The scaffolding board is provided at the height of the upper end of the reinforcing material arranged on the outer periphery of the shaft, and has a casting hole for pouring concrete on the outer periphery of the shaft. scaffolding structure.
JP2020185303A 2020-11-05 2020-11-05 Construction method of underground structure and scaffolding structure Active JP7431142B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020185303A JP7431142B2 (en) 2020-11-05 2020-11-05 Construction method of underground structure and scaffolding structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020185303A JP7431142B2 (en) 2020-11-05 2020-11-05 Construction method of underground structure and scaffolding structure

Publications (2)

Publication Number Publication Date
JP2022074888A JP2022074888A (en) 2022-05-18
JP7431142B2 true JP7431142B2 (en) 2024-02-14

Family

ID=81606189

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020185303A Active JP7431142B2 (en) 2020-11-05 2020-11-05 Construction method of underground structure and scaffolding structure

Country Status (1)

Country Link
JP (1) JP7431142B2 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100217824B1 (en) 1997-08-11 1999-09-01 이정국 Device for placing concrete to slip forms
JP2007063895A (en) 2005-09-01 2007-03-15 Shimizu Corp Construction method for side wall of underground tank
JP2009114649A (en) 2007-11-02 2009-05-28 Chugoku Electric Power Co Inc:The Caisson type pile foundation, and construction method and work scaffold therefor
JP2010174486A (en) 2009-01-28 2010-08-12 Ohbayashi Corp Method for constructing side wall of underground tank structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100217824B1 (en) 1997-08-11 1999-09-01 이정국 Device for placing concrete to slip forms
JP2007063895A (en) 2005-09-01 2007-03-15 Shimizu Corp Construction method for side wall of underground tank
JP2009114649A (en) 2007-11-02 2009-05-28 Chugoku Electric Power Co Inc:The Caisson type pile foundation, and construction method and work scaffold therefor
JP2010174486A (en) 2009-01-28 2010-08-12 Ohbayashi Corp Method for constructing side wall of underground tank structure

Also Published As

Publication number Publication date
JP2022074888A (en) 2022-05-18

Similar Documents

Publication Publication Date Title
CN102482892B (en) Telescopic tower assembly and method
CN101832049B (en) Concrete-structured conjoined cylindrical shell construction device and method therefor
JP6274688B1 (en) Temporary deadline construction method
JP6078196B1 (en) How to build steel columns
CN213951970U (en) Pier stud template
CN113502828B (en) Processing method for early warning of deep foundation pit
CN213804905U (en) Bailey beam suspension structure
JP7431142B2 (en) Construction method of underground structure and scaffolding structure
KR20160000702A (en) Fastening member used in concrete filled steel tube and its using concrete filled steel tube mounting structure and method and its includes build underground structure and method
CN112252197A (en) Pier column template and pier column construction method
JP7424959B2 (en) Construction method and concrete placement system for underground structures
CN105908752B (en) Formwork supporting and stripping system for pouring concrete on side wall and working process of formwork supporting and stripping system
JPH1054037A (en) Coffering method and steel structural body therefor
CN112227369B (en) Cover-excavation top-down construction permanent steel pipe stand column installation construction method
CN113338321B (en) Construction method of prestressed pier foundation
JP2020060000A (en) Skeleton construction method
JP7470009B2 (en) How to build an underground structure
JP2002021097A (en) Installation method for leg member of tower type structure and device used therefor
JP5437876B2 (en) Method of dismantling and removing support members in the construction process of RC RC ramen structure viaduct
JPH11200369A (en) Mortar caisson type pile construction method
JP2001241287A (en) Construction method of shaft, assembly method of structural body used for construction method, and assembly device used for assembly method
JP7470011B2 (en) Method for constructing underground structures and lifting equipment
JP7470010B2 (en) Method for constructing underground structure and lifting jig
KR20110123453A (en) A bridge post strengthen structure and construction methode there of
CN115419266B (en) Method for installing herringbone column template of large cooling tower

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230425

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20231222

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20240130

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20240201

R150 Certificate of patent or registration of utility model

Ref document number: 7431142

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150