JPH1054037A - Coffering method and steel structural body therefor - Google Patents
Coffering method and steel structural body thereforInfo
- Publication number
- JPH1054037A JPH1054037A JP22746696A JP22746696A JPH1054037A JP H1054037 A JPH1054037 A JP H1054037A JP 22746696 A JP22746696 A JP 22746696A JP 22746696 A JP22746696 A JP 22746696A JP H1054037 A JPH1054037 A JP H1054037A
- Authority
- JP
- Japan
- Prior art keywords
- corrugated pipe
- corrugated
- outer corrugated
- stage
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】この発明は,既設の水中橋脚
等の水中脚の補強を行う既設水中脚補強工事等に適用し
て好適な締め切り工法,およびこの締め切り工法に用い
る鋼製構造体に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a deadline method suitable for reinforcing existing underwater legs such as existing underwater bridge piers and the like, and a steel structure used for the deadline method.
【0002】[0002]
【従来の技術】例えば水中に橋脚を構築する場合,その
構築作業を可能にするために,構築箇所を囲む適宜の範
囲に締め切り工を施し,その内部の水抜きを行う。この
種の締め切り工法には一般に,鋼矢板を打ち込む締め切
り工法が採用されている。この鋼矢板による締め切り工
法は施工性が良いが,例えば既設の水中の橋脚の補強工
事を行う場合には,既に橋桁が存在するので,鋼矢板を
打ち込むために必要な高さの上部空間を確保できず,鋼
矢板による締め切り工法が採用できない場合がある。ま
た,地盤が硬いため,あるいは市街地等で騒音問題のた
め,鋼矢板を打ち込む工法を採用できない場合もある。2. Description of the Related Art For example, in the case of constructing a pier underwater, in order to enable the construction work, an appropriate range surrounding a construction site is subjected to a deadline, and water is drained from the inside. Generally, this kind of deadline method employs a deadline method of driving a steel sheet pile. The deadline method using steel sheet piles has good workability. For example, when reinforcing existing underwater bridge piers, the bridge girder already exists, so secure the upper space necessary for driving steel sheet piles. In some cases, the deadline method using steel sheet piles cannot be adopted. In addition, the method of driving steel sheet piles cannot be adopted in some cases due to the hard ground or noise problems in urban areas.
【0003】このような場合に適用できる締め切り工法
として,図13に示すように,陸上で予め組み立てたラ
イナープレート製の内側筒体A,およびコルゲートパイ
プ製の外側筒体Bを基盤G上に設置し,設置した内側筒
体Aと外側筒体Bとの間に土砂等の中詰材Cを投入充填
し,次いで,外側筒体Bの基部B’外側の地盤G上にコ
ンクリート等を打設して根固めDを行う工法が提案され
ている(実公昭57−23553号参照)。なお,図に
おいて,Eは橋脚等の構造体である。As a deadline method applicable in such a case, as shown in FIG. 13, an inner cylinder A made of a liner plate and an outer cylinder B made of a corrugated pipe previously assembled on land are installed on a base G. Then, a filling material C such as earth and sand is charged and filled between the installed inner cylindrical body A and the outer cylindrical body B, and then concrete or the like is poured on the ground G outside the base B 'of the outer cylindrical body B. A method of performing the consolidation D has been proposed (see Japanese Utility Model Publication No. 57-23553). In the drawings, E is a structure such as a pier.
【0004】[0004]
【発明が解決しようとする課題】上記従来の工法は,鋼
矢板を使用しないので,鋼矢板を打ち込むのに必要な上
部空間の問題,硬い地盤の問題,騒音の問題等は生じな
い。しかし,二重の筒体A,Bを設置する必要があるこ
と,中詰め材Cを投入充填する必要があること等から,
施工の作業が著しく繁雑である。また,これは仮の締め
切り構造体であり,工事完了後にこの仮締め切り構造体
を撤去するが,打ち込み部分がない点で撤去が容易とい
っても,やはりこの仮締め切り構造体の撤去作業は繁雑
である。The above conventional method does not use steel sheet piles, so that there is no problem of an upper space necessary for driving the steel sheet piles, a problem of hard ground, a problem of noise, and the like. However, since it is necessary to install the double cylinders A and B, and it is necessary to charge and fill the filling material C,
Construction work is extremely complicated. In addition, this is a temporary deadline structure, and the temporary deadline structure will be removed after the construction is completed. However, even if it is easy to remove because there is no driving part, the removal work of this temporary deadline structure is also complicated. It is.
【0005】本発明は上記従来の欠点を解消するために
なされたもので,鋼矢板を用いない工法であって,しか
も施工性が良く,かつ工事完了後の撤去が容易な締め切
り工法,および締め切り工法用の鋼製構造体を提供する
ことを目的とする。SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned conventional drawbacks, and is a construction method which does not use steel sheet piles, has good workability, and is easy to remove after completion of construction, and a deadline method. An object of the present invention is to provide a steel structure for a construction method.
【0006】[0006]
【課題を解決するための手段】上記課題を解決する本発
明の締め切り工法は,円弧状の複数のコルゲートシート
を水平の円周方向および垂直方向に接続して複数段から
なる外側コルゲートパイプを構成する工程と,前記外側
コルゲートパイプのコルゲートシートより曲率の小さな
円弧状の複数のコルゲートシートを,前記外側コルゲー
トパイプの少なくとも最下段部の内面に対向するように
円周方向にまたは円周方向および垂直方向に接続して1
段または前記外側コルゲートパイプより背の低い複数段
の内側コルゲートパイプを構成するとともに,この内側
コルゲートパイプと前記外側コルゲートパイプとを連結
部材により連結して,部分的二重筒構造体を構成する工
程と,前記部分的二重筒構造体を下降させ水底に設置す
る工程と,次いで,前記部分的二重筒構造体の外側コル
ゲートパイプと内側コルゲートパイプとの間に水中コン
クリートを打設する工程と,コンクリート硬化後,外側
コルゲートパイプ内の水抜きを行う工程とからなること
を特徴とする。In order to solve the above-mentioned problems, a closing method according to the present invention comprises connecting a plurality of arc-shaped corrugated sheets in a horizontal circumferential direction and a vertical direction to form an outer corrugated pipe comprising a plurality of stages. And forming a plurality of arcuate corrugated sheets having a smaller curvature than the corrugated sheet of the outer corrugated pipe in the circumferential direction or in the circumferential direction and vertically so as to face at least the inner surface of the lowermost step of the outer corrugated pipe. Connect in the direction 1
A step of forming a partially double cylindrical structure by forming a step or a plurality of steps of the inner corrugated pipe shorter than the outer corrugated pipe and connecting the inner corrugated pipe and the outer corrugated pipe by a connecting member; Lowering the partial double-cylinder structure and installing it on the bottom of the water; then, casting underwater concrete between the outer corrugated pipe and the inner corrugated pipe of the partial double-cylinder structure; And, after hardening the concrete, draining the water in the outer corrugated pipe.
【0007】請求項2は,請求項1の締め切り工法を既
設の水中脚の補強を行う既設水中脚補強工事に適用する
ものである。A second aspect of the present invention is to apply the deadline method of the first aspect to an existing underwater leg reinforcing work for reinforcing an existing underwater leg.
【0008】請求項3は,請求項1または2に記載の締
め切り工法に用いる鋼製構造体であって,円弧状の複数
のコルゲートシートを水平の円周方向および垂直方向に
接続して構成された複数段からなる外側コルゲートパイ
プと,前記外側コルゲートパイプのコルゲートシートよ
り曲率の小さな円弧状の複数のコルゲートシートを,前
記外側コルゲートパイプの少なくとも最下段部の内面に
対向するように円周方向にまたは円周方向および垂直方
向に接続して構成されるとともに,連結部材を介して前
記外側コルゲートパイプに連結された1段または前記外
側コルゲートパイプより背の低い複数段の内側コルゲー
トパイプとを備えたことを特徴とする。A third aspect of the present invention is a steel structure used in the closing method according to the first or second aspect, wherein a plurality of arcuate corrugated sheets are connected in a horizontal circumferential direction and a vertical direction. The outer corrugated pipe having a plurality of steps and a plurality of arcuate corrugated sheets having a smaller curvature than the corrugated sheet of the outer corrugated pipe are circumferentially arranged so as to face at least the inner surface of the lowermost step of the outer corrugated pipe. Or one or more inner corrugated pipes shorter than the outer corrugated pipe connected to the outer corrugated pipe via a connecting member and configured to be connected in the circumferential and vertical directions. It is characterized by the following.
【0009】[0009]
【発明の実施の形態】以下,本発明の実施の形態を図1
〜図12に示した実施例を参照して説明する。この実施
例は,既設の水中橋脚の補強を行う既設水中橋脚補強工
事に適用したものである。図1において,11は補強を
行おうとする橋脚,12は橋桁,13はその水中の基
礎,14は水面を示す。この橋脚11の補強は,例え
ば,この既設の橋脚11の周囲に,例えばその外周面と
の間に30mm程度の隙間をあけて例えば厚さ10mm
前後の鋼板を巻き立てるとともに,前記隙間にモルタル
または接着剤を充填し,また鋼板の外側の水中部分にコ
ンクリートを例えば500mm弱等の厚みで巻き立て
る,等によって行う。FIG. 1 is a block diagram showing an embodiment of the present invention.
This will be described with reference to the embodiment shown in FIGS. This embodiment is applied to an existing underwater pier reinforcement work for reinforcing an existing underwater pier. In FIG. 1, reference numeral 11 denotes a pier to be reinforced, 12 denotes a bridge girder, 13 denotes an underwater foundation, and 14 denotes a water surface. The pier 11 is reinforced, for example, with a thickness of about 10 mm around the existing pier 11 with a gap of about 30 mm between the pier 11 and the outer peripheral surface thereof.
The front and rear steel plates are rolled up, the gap is filled with mortar or an adhesive, and concrete is rolled up in a submerged portion outside the steel plate with a thickness of, for example, less than 500 mm.
【0010】このような補強工事を行う場合,その作業
を行うために水抜きを行う締め切り工を施す必要がある
が,そのために,本発明の一実施例の締め切り工法が採
用される。図1はその始めの段階を示すもので,まず,
台船15を橋脚11に隣接して浮かべ,作業の足場とす
る。そして,この台船15上で,まず,円弧状の複数の
コルゲートシート17を水平の円周方向に接続して1段
のコルゲートパイプ18aを構成する。次いで,図2に
示すように,前記1段のコルゲートパイプ18aを図示
略の揚重機によりワイヤ16で吊り上げ,その下方で前
記と同様に,円弧状の複数のコルゲートシート17を水
平の円周方向に接続して1段のコルゲートパイプ18b
を構成する。次いで,始めのコルゲートパイプ18aを
下降させて,下のコルゲートパイプ18bの上縁部にラ
ップさせ,ボルトで上下のコルゲートパイプ18a,1
8bを接続する。なお,円弧状のコルゲートシート17
およびその接続要領は一般的なものであるが,その詳細
を図6に示す。図示のように,円弧状のコルゲートシー
ト17は,鋼板を波付けし,シート幅方向(図で上下方
向)の両端縁部および長手方向の両端縁部にそれぞれ取
り付け穴をあけ,所定の曲率で湾曲させたものであり,
コルゲートシート17どうしの接続は,シート幅方向ま
たは長手方向の端縁部を重ね合わせ,重ね部の取り付け
穴にボルト25を挿入しナットを螺合させ締め付けるこ
とにより行う。なお,図示は省略したが,コルゲートシ
ート17どうしの接続部等の必要箇所にはパッキンを介
在させて,止水を図る。また,コルゲートパイプ18a
等を吊り上げる揚重機の詳細は省略するが,橋桁12側
に揚重機構を取り付ける方法,揚重機を搭載した作業船
を利用する方法,岸壁に近い場合には陸上のクレーン車
を利用する方法,その他適宜の方法を採用することがで
きる。When performing such a reinforcement work, it is necessary to perform a deadline for draining water in order to perform the work. For this purpose, the deadline method according to one embodiment of the present invention is employed. Figure 1 shows the initial stage.
The barge 15 is floated adjacent to the pier 11 and used as a work platform. Then, on this barge 15, first, a plurality of arc-shaped corrugated sheets 17 are connected in a horizontal circumferential direction to form a single-stage corrugated pipe 18a. Next, as shown in FIG. 2, the one-stage corrugated pipe 18a is lifted by a wire 16 by a lifting machine (not shown), and a plurality of arc-shaped corrugated sheets 17 are placed below the corrugated pipes 17 in a horizontal circumferential direction. To the one-stage corrugated pipe 18b
Is configured. Next, the first corrugated pipe 18a is lowered, wrapped around the upper edge of the lower corrugated pipe 18b, and the upper and lower corrugated pipes 18a, 18 are bolted.
8b. The arcuate corrugated sheet 17
The connection procedure is general, and details thereof are shown in FIG. As shown in the figure, the arc-shaped corrugated sheet 17 is formed by corrugating a steel plate, making mounting holes at both ends in the sheet width direction (vertical direction in the drawing) and both ends in the longitudinal direction, and having a predetermined curvature. Which is curved,
The connection between the corrugated sheets 17 is performed by overlapping the edge portions in the sheet width direction or the longitudinal direction, inserting the bolt 25 into the mounting hole of the overlapping portion, screwing a nut, and tightening. Although not shown in the drawings, packing is interposed at necessary places such as connecting portions between the corrugated sheets 17 so as to stop water. Also, the corrugated pipe 18a
Although details of the hoist that lifts etc. are omitted, a method of attaching a hoisting mechanism to the bridge girder 12 side, a method of using a work boat equipped with a hoist, a method of using a land crane vehicle near the quay, Other appropriate methods can be adopted.
【0011】上記の作業を繰り返して,例えば,図3に
示すように1段のコルゲートパイプ18a,18b,1
8c,18d,18e,18fの6段から成る外側コル
ゲートパイプ18を構成する。なお,外側コルゲートパ
イプ18の補強のために,例えばI断面の鋼材を円筒状
の外側コルゲートパイプ18の内面に合わせて形成した
補強リングを外側コルゲートパイプ18の内面に上下方
向に適宜の間隔をあけて溶接固定するとよい。By repeating the above operation, for example, as shown in FIG. 3, one-stage corrugated pipes 18a, 18b, 1
An outer corrugated pipe 18 composed of six stages 8c, 18d, 18e and 18f is constructed. In order to reinforce the outer corrugated pipe 18, for example, a reinforcing ring formed by fitting a steel material having an I-section to the inner surface of the cylindrical outer corrugated pipe 18 is provided at appropriate intervals in the vertical direction on the inner surface of the outer corrugated pipe 18. Should be fixed by welding.
【0012】次いで,同じく図3に示すように.前記外
側コルゲートパイプ18のコルゲートシート17より曲
率の小さな円弧状の複数のコルゲートシート19を,前
記外側コルゲートパイプ18の最下段部18fの内面に
対向するように円周方向に接続して例えば1段の内側コ
ルゲートパイプ20を構成するとともに,この内側コル
ゲートパイプ20と前記外側コルゲートパイプ18の最
下段部18fとを連結部材21により連結して,部分的
二重筒構造体(鋼製構造体)22を構成する。この台船
15上で構成された部分的二重筒構造体22を図7に平
面図で示す。Next, as shown in FIG. A plurality of arcuate corrugated sheets 19 having a smaller curvature than the corrugated sheet 17 of the outer corrugated pipe 18 are connected in the circumferential direction so as to face the inner surface of the lowermost portion 18f of the outer corrugated pipe 18, for example, by one step. The inner corrugated pipe 20 is connected to the inner corrugated pipe 20 and the lowermost portion 18f of the outer corrugated pipe 18 by a connecting member 21 to form a partially double cylindrical structure (steel structure) 22. Is configured. FIG. 7 is a plan view showing the partial double-cylinder structure 22 formed on the barge 15.
【0013】前記連結部材21は,図8に示すように,
外側コルゲートパイプ18の最下段部18fの外面にボ
ルトで固定される垂直なアングル材21aと,最下段部
18fの下端位置で外側コルゲートパイプ18の内面か
ら中心方向に伸びて外側コルゲートパイプ18と内側コ
ルゲートパイプ20との間に渡され両者18,20にボ
ルトで固定される水平なアングル材21bと,両アング
ル材21a,21b間を連結する斜めのアングル材21
cとからなる。実施例では,図7に示すように例えば8
箇所においてこの連結部材21を設けている。[0013] As shown in FIG.
A vertical angle member 21a bolted to the outer surface of the lowermost portion 18f of the outer corrugated pipe 18, and the outer corrugated pipe 18 and the inner side extending from the inner surface of the outer corrugated pipe 18 toward the center at the lower end of the lowermost portion 18f. A horizontal angle member 21b which is passed between the corrugated pipe 20 and is fixed to both the bolts 18 and 20 by bolts, and an oblique angle member 21 which connects between the angle members 21a and 21b.
c. In the embodiment, for example, as shown in FIG.
This connecting member 21 is provided at a location.
【0014】次いで,図4に示すように,台船15を橋
脚11から遠ざけて,外側コルゲートパイプ18をかわ
せるようにした後,前記部分的二重筒構造体22を下降
させ,橋脚11の基礎13上に設置する。Next, as shown in FIG. 4, the barge 15 is moved away from the pier 11 so that the outer corrugated pipe 18 is bent, and then the partial double-cylinder structure 22 is lowered to form a foundation for the pier 11. 13.
【0015】基礎13上に設置した外側コルゲートパイ
プ18と内側コルゲートパイプ20との間には水中コン
クリートを打設するが,浮力により当該締め切り構造体
(水中コンクリートを打設した部分的二重筒構造体2
2)が移動しないための浮力対策として,図9に示すよ
うに,基礎13と後述する打設水中コンクリートとの間
の結合を図るためのアンカー(または差し筋)31を設
ける。また,円周方向に配した鉄筋32をアンカー31
に溶接して配筋する。Underwater concrete is cast between the outer corrugated pipe 18 and the inner corrugated pipe 20 installed on the foundation 13, but the deadline structure (partial double-cylinder structure in which the underwater concrete is cast) is applied by buoyancy. Body 2
As a countermeasure against buoyancy to prevent 2) from moving, as shown in FIG. 9, an anchor (or a reinforcing bar) 31 is provided for connecting the foundation 13 and a concrete to be poured underwater described later. In addition, the reinforcing steel 32 arranged in the circumferential direction is connected to the anchor 31.
Weld to and arrange reinforcement.
【0016】さらに,内側コルゲートパイプ20と外側
コルゲートパイプ18との間に打設した水中コンクリー
トが流出しないための水中コンクリート流出防止対策と
して,例えば図9に示すように,外側コルゲートパイプ
18および内側コルゲートパイプ20の下端に基礎13
の上面との隙間を塞ぐためのゴムベルト等のシール材3
3を取り付ける。この場合,シール材33はコルゲート
パイプ18,20に対してはボルトで,基礎13に対し
ては例えばドライビットを用いて取り付けるとよい。Further, as a countermeasure for preventing the underwater concrete from flowing out between the inner corrugated pipe 20 and the outer corrugated pipe 18 as shown in FIG. 9, for example, as shown in FIG. Foundation 13 at lower end of pipe 20
Sealing material 3 such as a rubber belt for closing the gap with the upper surface
3 is attached. In this case, the seal member 33 may be attached to the corrugated pipes 18 and 20 with bolts, and the base 13 may be attached with a dry bit, for example.
【0017】次いで,図5に示すように,外側コルゲー
トパイプ18と内側コルゲートパイプ20との間に水中
コンクリートを打設する。コンクリート養生の後,外側
コルゲートパイプ18内の水抜きを行うが,水中コンク
リート24により,外側コルゲートパイプ18の下端部
の止水が確実に図られる。以上により,前述した橋脚1
1の補強工事を行うことが可能となる。Next, as shown in FIG. 5, underwater concrete is poured between the outer corrugated pipe 18 and the inner corrugated pipe 20. After the concrete is cured, the inside of the outer corrugated pipe 18 is drained, but the underwater concrete 24 ensures that the lower end of the outer corrugated pipe 18 is stopped. As described above, the pier 1
It is possible to perform the first reinforcement work.
【0018】橋脚11の補強工事が完了した後は,外側
コルゲートパイプ18の最下段部18f以外の部分(図
示例ではコルゲートパイプ18a,18b,18c,1
8d,18eの部分)は,最下段部18fとの接続部の
ボルトを外せば容易に撤去することができる。したがっ
て,撤去したそれらは他の箇所での締め切り工法に再使
用でき,経済的である。なお,最下段部18fおよび内
側コルゲートパイプ20およびその間に打設されたコン
クリート24は,これを撤去することも可能ではある
が,撤去せずにそのまま残してよい。After the reinforcement work of the pier 11 is completed, the portion other than the lowermost portion 18f of the outer corrugated pipe 18 (corrugated pipes 18a, 18b, 18c, 1 in the illustrated example).
8d and 18e) can be easily removed by removing the bolt at the connection with the lowermost step 18f. Therefore, the removed ones can be reused in other construction deadlines and are economical. The lowermost portion 18f, the inner corrugated pipe 20, and the concrete 24 cast between them can be removed, but may be left without being removed.
【0019】本発明は図10に示すように,上面が傾斜
した基礎13’において施工する場合にも適用できる。
図示例では,水中コンクリート流出防止手段として,前
記と同様にゴムベルトによるシール材33を用いてい
る。As shown in FIG. 10, the present invention can be applied to a case where the work is carried out on a foundation 13 'having an inclined upper surface.
In the illustrated example, a sealing material 33 using a rubber belt is used as the means for preventing underwater concrete from flowing out, as described above.
【0020】また,水中コンクリート流出防止対策とし
て,図11に示すように内側コルゲートパイプ18およ
び外側コルゲートパイプ20の下端部に土嚢34を配置
してもよい。基礎に傾斜がある場合は,特に外側コルゲ
ートパイプ18の下端の隙間が大きくなるので,土嚢3
4による間詰めが有効である。なお,図10のようにシ
ール材33を取り付けた上に土嚢34を配置すると,一
層有効である。As a countermeasure for preventing outflow of underwater concrete, sandbags 34 may be arranged at the lower ends of the inner corrugated pipe 18 and the outer corrugated pipe 20, as shown in FIG. If the foundation has an inclination, the gap at the lower end of the outer corrugated pipe 18 becomes particularly large, so that the sandbag 3
4 is effective. It is more effective to arrange the sandbag 34 on the sealing material 33 as shown in FIG.
【0021】また,上記の実施例では,内側コルゲート
パイプを1段だけ設けたが,状況により図12に示すよ
うに,コルゲートシートを円周方向および垂直方向に接
続して,複数段(図示例では2段)の内側コルゲートパ
イプ20’とする場合も考えられる。内側コルゲートパ
イプを高くしその高さまで水中コンクリートを打設する
と,外側コルゲートパイプの耐水圧強度が高くなるの
で,外側コルゲートパイプの直径や水深Hに応じて,必
要があれば,図示の内側コルゲートパイプ20’のよう
に高さhを高くする。すなわち,(H−h)が一定以上
にならないようにする。In the above embodiment, only one stage of the inner corrugated pipe is provided. However, as shown in FIG. 12, depending on the situation, the corrugated sheet is connected in the circumferential direction and the vertical direction to form a plurality of stages (in the illustrated example). In this case, a two-stage inner corrugated pipe 20 ′ may be used. If the inner corrugated pipe is raised and submerged concrete is poured to that height, the water pressure resistance of the outer corrugated pipe increases. Therefore, if necessary, depending on the diameter of the outer corrugated pipe and the water depth H, the inner corrugated pipe shown in the figure is used. The height h is increased as in 20 '. That is, (Hh) is prevented from exceeding a certain value.
【0022】なお,本発明は,既設の橋脚等がない場
合,すなわち新たに橋脚を構築する場合等のように,単
に水中に作業空間を作るための締め切り工法としても,
当然適用可能である。さらに,基礎が存在しない単なる
水底においても適用可能である。It should be noted that the present invention is also applicable to a deadline construction method for simply creating a work space underwater, such as when there is no existing pier or the like, that is, when a new pier is constructed.
Naturally applicable. In addition, it can be applied to a mere bottom without a foundation.
【0023】[0023]
【発明の効果】本発明の締め切り工法は,台船等の足場
上でコルゲートパイプを順次組み立てて,外側コルゲー
トパイプおよび内側コルゲートパイプおよび連結部材か
らなる部分的二重筒構造体を構成し,この部分的二重筒
構造体を水底(単なる水底あるいは水中脚の基礎上等)
に沈設し,外側コルゲートパイプと内側コルゲートパイ
プとの間に水中コンクリートを打設するものであるあか
ら,鋼矢板を打ち込む場合のような高い上部空間を必要
としない。したがって,既設の水中脚の補強工事等の場
合に好適である。また,岩盤が硬い場合,騒音の問題が
ある場合等にも好適である。According to the deadline method of the present invention, a corrugated pipe is sequentially assembled on a scaffold of a barge or the like to form a partial double cylindrical structure comprising an outer corrugated pipe, an inner corrugated pipe, and a connecting member. Partially double tubular structure on the bottom of the water
The underwater concrete is placed between the outer corrugated pipe and the inner corrugated pipe, so there is no need for the high head space required when driving steel sheet pile. Therefore, it is suitable for the case of reinforcing existing underwater legs. It is also suitable when the rock is hard or there is a problem of noise.
【0024】また,本発明工法によれば,外側コルゲー
トパイプおよび内側コルゲートパイプの組み立て,連結
部材による両者の一体連結,外側コルゲートパイプと内
側コルゲートパイプとの間への水中コンクリートの打設
等の作業はいずれも容易であり,施工性がきわめて良好
である。According to the method of the present invention, the outer corrugated pipe and the inner corrugated pipe are assembled, the two are integrally connected by a connecting member, and underwater concrete is poured between the outer corrugated pipe and the inner corrugated pipe. Are easy and the workability is very good.
【0025】また,本発明工法では,水中コンクリート
打設のために設けるコルゲートパイプ(すなわち内側コ
ルゲートパイプ)が締め切り構造の本体部分(すなわち
外側コルゲートパイプ)の内部にあるので,基礎が狭い
場合でも,この狭い基礎の上に容易に設置することがで
きる。また,水面より高い本体部分の内部で水中コンク
リートを打設するので,水中コンクリートの流出防止対
策は比較的容易である。Further, in the method of the present invention, since the corrugated pipe (that is, the inner corrugated pipe) provided for placing underwater concrete is inside the main body portion (that is, the outer corrugated pipe) of the deadline structure, even if the foundation is narrow, It can be easily installed on this narrow foundation. Also, since underwater concrete is poured inside the main body part higher than the water surface, it is relatively easy to prevent underwater concrete from flowing out.
【0026】また,本発明の締め切り工法においては,
外側コルゲートパイプはコンクリート打設部分を除け
ば,きわめて容易に撤去できる。したがって,コルゲー
トシートの大部分を再利用でき,経済的である。In the deadline method of the present invention,
The outer corrugated pipe can be removed very easily, except for the concrete placement. Therefore, most of the corrugated sheet can be reused and is economical.
【図1】本発明の一実施例の締め切り工法を説明するも
ので,始めの段階を示す図である。FIG. 1 is a view for explaining a deadline method according to one embodiment of the present invention and is a diagram showing an initial stage.
【図2】上記一実施例の締め切り工法における図1に続
く段階を示す図である。FIG. 2 is a view showing a stage following the one in FIG. 1 in the deadline method of the embodiment.
【図3】上記一実施例の締め切り工法における図2に続
く段階を示す図である。FIG. 3 is a diagram showing a stage following FIG. 2 in the deadline method of the embodiment.
【図4】上記一実施例の締め切り工法における図3に続
く段階を示す図である。FIG. 4 is a view showing a stage following the one in FIG. 3 in the closing method according to the embodiment.
【図5】上記一実施例の締め切り工法における図4に続
く段階を示す図であり,締め切り構造物の設置が完了し
た状態の図である。FIG. 5 is a view showing a stage following the one in FIG. 4 in the deadline method of the embodiment, in which the installation of the deadline structure is completed.
【図6】上記締め切り工法におけるコルゲートパイプの
組み立て要領を説明する図である。FIG. 6 is a view for explaining a procedure for assembling a corrugated pipe in the deadline method.
【図7】図3のA−A断面図である。FIG. 7 is a sectional view taken along the line AA of FIG. 3;
【図8】図3等における連結部材の拡大図である。FIG. 8 is an enlarged view of a connecting member in FIG. 3 and the like.
【図9】上記実施例の締め切り工法における浮力防止対
策および水中コンクリート流出防止対策についての一例
の説明図である。FIG. 9 is an explanatory diagram of an example of a buoyancy prevention measure and an underwater concrete outflow prevention measure in the deadline method of the embodiment.
【図10】基礎の上面が傾斜している場合の実施例を示
す要部断面図である。FIG. 10 is a sectional view of a main part showing an embodiment in the case where the upper surface of the foundation is inclined.
【図11】水中コンクリート流出防止として土嚢を用い
た場合の実施例を示す要部断面図である。FIG. 11 is a sectional view of an essential part showing an embodiment in the case where sandbags are used for preventing outflow of underwater concrete.
【図12】複数段からなる内側コルゲートパイプを用い
た場合の実施例を示すもので,図5に相当する図であ
る。FIG. 12 is a view corresponding to FIG. 5, showing an embodiment in which an inner corrugated pipe having a plurality of stages is used.
【図13】従来の締め切り工法を説明する図である。FIG. 13 is a view for explaining a conventional closing method.
11 橋脚(水中脚) 12 橋桁 13 基礎 15 台船 16 ワイヤ 17,19 コルゲートシート 18 外側コルゲートパイプ 18a,18b,18c,18d,19e,18f 1
段のコルゲートパイプ 20 内側コルゲートパイプ 21 連結部材 22 部分的二重筒構造体(鋼製構造体) 24 水中コンクリート 31 アンカーまたは差し筋 32 補強鉄筋 33 シール材 34 土嚢Reference Signs List 11 bridge pier (underwater leg) 12 bridge girder 13 foundation 15 barge 16 wire 17, 19 corrugated sheet 18 outer corrugated pipe 18a, 18b, 18c, 18d, 19e, 18f 1
Step corrugated pipe 20 Inner corrugated pipe 21 Connecting member 22 Partial double tubular structure (steel structure) 24 Underwater concrete 31 Anchor or reinforcing bar 32 Reinforcing bar 33 Sealing material 34 Sandbag
Claims (3)
の円周方向および垂直方向に接続して複数段からなる外
側コルゲートパイプを構成する工程と,前記外側コルゲ
ートパイプのコルゲートシートより曲率の小さな円弧状
の複数のコルゲートシートを,前記外側コルゲートパイ
プの少なくとも最下段部の内面に対向するように円周方
向にまたは円周方向および垂直方向に接続して1段また
は前記外側コルゲートパイプより背の低い複数段の内側
コルゲートパイプを構成するとともに,この内側コルゲ
ートパイプと前記外側コルゲートパイプとを連結部材に
より連結して,部分的二重筒構造体を構成する工程と,
前記部分的二重筒構造体を下降させ水底に設置する工程
と,次いで,前記部分的二重筒構造体の外側コルゲート
パイプと内側コルゲートパイプとの間に水中コンクリー
トを打設する工程と,コンクリート硬化後,外側コルゲ
ートパイプ内の水抜きを行う工程とからなることを特徴
とする締め切り工法。1. A step of connecting a plurality of arc-shaped corrugated sheets in a horizontal circumferential direction and a vertical direction to form an outer corrugated pipe having a plurality of stages, and a circle having a smaller curvature than the corrugated sheet of the outer corrugated pipe. A plurality of arcuate corrugated sheets are connected circumferentially or circumferentially and vertically so as to face at least the inner surface of the lowermost portion of the outer corrugated pipe, so that the corrugated sheet is shorter than one corrugated pipe or the outer corrugated pipe. Forming a plurality of stages of inner corrugated pipes, and connecting the inner corrugated pipes and the outer corrugated pipes with connecting members to form a partially double tubular structure;
Lowering the partial double-cylinder structure and placing it on the bottom of the water; then, casting underwater concrete between the outer corrugated pipe and the inner corrugated pipe of the partial double-cylinder structure; A process of draining water inside the outer corrugated pipe after hardening.
強工事に適用される締め切り工法であって,円弧状の複
数のコルゲートシートを前記水中脚を囲むように円周方
向に接続して1段のコルゲートパイプを組み立て,この
1段のコルゲートパイプをほぼ1段高さ分上昇させると
ともに,これに続く下段のコルゲートパイプを同じよう
に組み立てかつ先のコルゲートパイプと接続する作業を
繰り返して,複数段からなる外側コルゲートパイプを構
成する工程と,前記外側コルゲートパイプのコルゲート
シートより曲率の小さな円弧状の複数のコルゲートシー
トを,前記外側コルゲートパイプの少なくとも最下段部
の内面に対向するように円周方向にまたは円周方向およ
び垂直方向に接続して1段または前記外側コルゲートパ
イプより背の低い複数段の内側コルゲートパイプを構成
するるとともに,この内側コルゲートパイプと前記外側
コルゲートパイプとを連結部材により連結して,部分的
二重筒構造体を構成する工程と,前記部分的二重筒構造
体を下降させ水中脚の基礎上に設置する工程と,次い
で,前記部分的二重筒構造体の外側コルゲートパイプと
内側コルゲートパイプとの間に水中コンクリートを打設
する工程と,コンクリート硬化後,外側コルゲートパイ
プ内の水抜きを行う工程とからなることを特徴とする締
め切り工法。2. A deadline method applied to an existing underwater leg reinforcing work for reinforcing an existing underwater leg, comprising connecting a plurality of arcuate corrugated sheets in a circumferential direction so as to surround the underwater leg. Assembling the one-stage corrugated pipe, raising the one-stage corrugated pipe by almost one stage height, and assembling the subsequent lower-stage corrugated pipe in the same manner and connecting it to the preceding corrugated pipe, A step of forming an outer corrugated pipe having a plurality of steps; and forming a plurality of arcuate corrugated sheets having a smaller curvature than the corrugated sheet of the outer corrugated pipe so as to face at least the inner surface of the lowermost step of the outer corrugated pipe. Circumferentially or circumferentially and vertically connected, one stage or multiple sections shorter than the outer corrugated pipe A step of forming an inner corrugated pipe of several stages and connecting the inner corrugated pipe and the outer corrugated pipe by a connecting member to form a partially double tubular structure; Lowering the body and placing it on the foundation of the underwater legs, then casting underwater concrete between the outer corrugated pipe and the inner corrugated pipe of the partial double tubular structure; A process of draining water in the outer corrugated pipe.
に用いる鋼製構造体であって,円弧状の複数のコルゲー
トシートを水平の円周方向および垂直方向に接続して構
成された複数段からなる外側コルゲートパイプと,前記
外側コルゲートパイプのコルゲートシートより曲率の小
さな円弧状の複数のコルゲートシートを,前記外側コル
ゲートパイプの少なくとも最下段部の内面に対向するよ
うに円周方向にまたは円周方向および垂直方向に接続し
て構成されるとともに,連結部材を介して前記外側コル
ゲートパイプに連結された1段または前記外側コルゲー
トパイプより背の低い複数段の内側コルゲートパイプと
を備えたことを特徴とする締め切り工法用の鋼製構造
体。3. A steel structure used in the closing method according to claim 1 or 2, wherein a plurality of arcuate corrugated sheets are connected in a horizontal circumferential direction and a vertical direction. And a plurality of arcuate corrugated sheets having a smaller curvature than the corrugated sheet of the outer corrugated pipe are circumferentially or circumferentially opposed to at least the inner surface of the lowermost portion of the outer corrugated pipe. And one or more inner corrugated pipes shorter than the outer corrugated pipe connected to the outer corrugated pipe via a connecting member. Steel structure for the deadline method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP22746696A JPH1054037A (en) | 1996-08-09 | 1996-08-09 | Coffering method and steel structural body therefor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP22746696A JPH1054037A (en) | 1996-08-09 | 1996-08-09 | Coffering method and steel structural body therefor |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH1054037A true JPH1054037A (en) | 1998-02-24 |
Family
ID=16861325
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP22746696A Withdrawn JPH1054037A (en) | 1996-08-09 | 1996-08-09 | Coffering method and steel structural body therefor |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH1054037A (en) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009068196A (en) * | 2007-09-11 | 2009-04-02 | Toyo Constr Co Ltd | Construction method for cofferdam wall using steel segment |
JP4625532B1 (en) * | 2009-08-26 | 2011-02-02 | 株式会社イスミック | Construction method of temporary closing structure around bridge pier and platform used for construction |
JP2011208389A (en) * | 2010-03-29 | 2011-10-20 | Nippon Steel & Sumikin Metal Products Co Ltd | Self-standing cofferdam structure and self-standing cofferdam method |
JP2012167473A (en) * | 2011-02-14 | 2012-09-06 | Oriental Shiraishi Corp | Reinforcement structure and reinforcement method of columnar structure |
CN104499494A (en) * | 2014-12-22 | 2015-04-08 | 江苏省交通科学研究院股份有限公司 | Double-wall corrugated steel cofferdam |
CN105625191A (en) * | 2016-02-02 | 2016-06-01 | 中交一公局第二工程有限公司 | Construction method of segment girder prestressed pipeline |
CN105951865A (en) * | 2016-05-26 | 2016-09-21 | 太原理工大学 | HDPE double-wall corrugated pipe foundation and construction process thereof |
JP2018138726A (en) * | 2017-02-24 | 2018-09-06 | Jfe建材株式会社 | Hollow segment, annular structure, and cut-off wall structure |
JP2020105895A (en) * | 2018-12-25 | 2020-07-09 | アザイ技術コンサルタント株式会社 | Construction method of cofferdam structure and float platform used in the same |
JP2020118015A (en) * | 2019-01-21 | 2020-08-06 | アザイ技術コンサルタント株式会社 | Cofferdam structure, construction method therefor, and waterproof cover used for construction method |
JP2021063399A (en) * | 2019-10-16 | 2021-04-22 | アザイ技術コンサルタント株式会社 | Float platform, and construction method of cofferdam structure using the same |
CN115419089A (en) * | 2022-09-01 | 2022-12-02 | 中铁七局集团武汉工程有限公司 | Shallow water bedrock geological bearing platform foundation pit construction method |
-
1996
- 1996-08-09 JP JP22746696A patent/JPH1054037A/en not_active Withdrawn
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009068196A (en) * | 2007-09-11 | 2009-04-02 | Toyo Constr Co Ltd | Construction method for cofferdam wall using steel segment |
JP4625532B1 (en) * | 2009-08-26 | 2011-02-02 | 株式会社イスミック | Construction method of temporary closing structure around bridge pier and platform used for construction |
JP2011069183A (en) * | 2009-08-26 | 2011-04-07 | Ismic:Kk | Construction method of cofferdam structure around bridge pier, and platform used for the construction |
JP2011208389A (en) * | 2010-03-29 | 2011-10-20 | Nippon Steel & Sumikin Metal Products Co Ltd | Self-standing cofferdam structure and self-standing cofferdam method |
JP2012167473A (en) * | 2011-02-14 | 2012-09-06 | Oriental Shiraishi Corp | Reinforcement structure and reinforcement method of columnar structure |
CN104499494B (en) * | 2014-12-22 | 2017-01-18 | 江苏省交通科学研究院股份有限公司 | Double-wall corrugated steel cofferdam |
CN104499494A (en) * | 2014-12-22 | 2015-04-08 | 江苏省交通科学研究院股份有限公司 | Double-wall corrugated steel cofferdam |
CN105625191A (en) * | 2016-02-02 | 2016-06-01 | 中交一公局第二工程有限公司 | Construction method of segment girder prestressed pipeline |
CN105951865A (en) * | 2016-05-26 | 2016-09-21 | 太原理工大学 | HDPE double-wall corrugated pipe foundation and construction process thereof |
CN105951865B (en) * | 2016-05-26 | 2017-12-01 | 大同市政建设集团有限公司 | HDPE double-wall corrugated pipes foundation and its construction technology |
JP2018138726A (en) * | 2017-02-24 | 2018-09-06 | Jfe建材株式会社 | Hollow segment, annular structure, and cut-off wall structure |
JP2020105895A (en) * | 2018-12-25 | 2020-07-09 | アザイ技術コンサルタント株式会社 | Construction method of cofferdam structure and float platform used in the same |
JP2020118015A (en) * | 2019-01-21 | 2020-08-06 | アザイ技術コンサルタント株式会社 | Cofferdam structure, construction method therefor, and waterproof cover used for construction method |
JP2021063399A (en) * | 2019-10-16 | 2021-04-22 | アザイ技術コンサルタント株式会社 | Float platform, and construction method of cofferdam structure using the same |
CN115419089A (en) * | 2022-09-01 | 2022-12-02 | 中铁七局集团武汉工程有限公司 | Shallow water bedrock geological bearing platform foundation pit construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111764379B (en) | Construction method and structure applied to reverse construction steel pipe pile | |
JP4793634B2 (en) | Temporary deadline construction method | |
JP5508917B2 (en) | Self-supporting temporary closing structure and self-supporting temporary closing method | |
CN114575356B (en) | Foundation pit supporting structure, supporting pile abnormal movement processing method and basement construction method | |
JPH1054037A (en) | Coffering method and steel structural body therefor | |
CN110863520A (en) | Construction structure and method for reinforcing pile foundation by using pushing steel sleeve | |
CN113529763A (en) | Method for constructing sea area shoal cushion cap by utilizing reinforced concrete combined steel cofferdam | |
JP2004183324A (en) | Repair structure and repair construction method for existing pile pier | |
KR20070037018A (en) | Concrete well construction method using weight reducing method and concrete well thereof | |
CN108425374B (en) | Integral construction method of steel suspension box cofferdam with tie beam dumbbell-shaped bearing platform under complex sea condition | |
CN113136853A (en) | Assembly type drilling platform and process for reservoir bare rock group pile foundation | |
CN105951865B (en) | HDPE double-wall corrugated pipes foundation and its construction technology | |
JP3888174B2 (en) | Temporary deadline construction method | |
KR20040039271A (en) | Shoe coffering method for new construction and repair, reinforcement of bridge open caisson foundation | |
JP3453664B2 (en) | Shaft construction method | |
CN214574092U (en) | Prefabricated assembly bottom sealing structure for bearing platform concrete in tidal water | |
JPH09158192A (en) | Coffering and steel structure for coffering | |
JP4384771B2 (en) | Artificial ground construction method | |
JPH11241314A (en) | Reinforcing construction method of underwater structure | |
JP2001348888A (en) | Method and device for constructing underwater foundation structure | |
CN215562723U (en) | Novel steel-concrete combined cofferdam for sea area shoal | |
JP7350797B2 (en) | How to lift bridge girders | |
CN221218871U (en) | Navigation mark precast concrete foundation | |
CN214245752U (en) | Prestressed reinforced cemented soil expanding head inclined throwing support | |
CN112030746B (en) | Method for dismantling water retaining steel cofferdam in advance in bridge construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A300 | Withdrawal of application because of no request for examination |
Free format text: JAPANESE INTERMEDIATE CODE: A300 Effective date: 20031104 |