KR101025892B1 - Concrete steel house - Google Patents

Concrete steel house Download PDF

Info

Publication number
KR101025892B1
KR101025892B1 KR1020100105469A KR20100105469A KR101025892B1 KR 101025892 B1 KR101025892 B1 KR 101025892B1 KR 1020100105469 A KR1020100105469 A KR 1020100105469A KR 20100105469 A KR20100105469 A KR 20100105469A KR 101025892 B1 KR101025892 B1 KR 101025892B1
Authority
KR
South Korea
Prior art keywords
precast panel
bracket
concrete
formwork
pile foundation
Prior art date
Application number
KR1020100105469A
Other languages
Korean (ko)
Inventor
강명석
Original Assignee
강명석
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 강명석 filed Critical 강명석
Priority to KR1020100105469A priority Critical patent/KR101025892B1/en
Application granted granted Critical
Publication of KR101025892B1 publication Critical patent/KR101025892B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/18Foundations formed by making use of caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes
    • E02D2200/1628Shapes rectangular
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Foundations (AREA)

Abstract

PURPOSE: A concrete steel house is provided to prevent the bulging of an assembly and secure structural stability by enhancing resistance against the lateral pressure of concrete. CONSTITUTION: A concrete steel house comprises precast panels(10), a combined cofferdam and form(20), and a variable bracket. The precast panels, in which distributing bars(14) are arranged, have through holes which pile bases pass through and are fastened to the pile bases with the variable bracket. The combined cofferdam and form is coupled to the side and bottom of the precast panels. The variable bracket comprises a top bracket which is formed in a U shape, a bottom bracket which is installed on the lower part of the pile bases and located underwater, top and bottom steel rods which are coupled to the top and bottom brackets with nuts, and support wires which are tensed with the nuts coupled to the top and bottom steel rods.

Description

콘크리트 스틸하우스{Concrete Steel House}Concrete Steel House

본 발명은 말뚝기초의 상부에 시공되는 푸팅을 용이하게 시공할 수 있으며, 누수를 방지하여 크랙현상을 억제할 수 있도록 한 콘크리트 스틸 하우스에 관한 것이다.
The present invention relates to a concrete steel house that can be easily installed in the footing to be installed on the top of the pile foundation, to prevent leakage by preventing leakage.

일반적으로 콘크리트 함거 블록은 암반층 지반에 말뚝기초를 고정시키고, 이의 상부에 푸팅(교각기초)을 시공하기 위하여 말뚝기초에 고정되는 가시설물이다.In general, the concrete containment block is a temporary fixture that is fixed to the pile foundation in order to fix the pile foundation on the rock foundation, and to put a footing (pier foundation) on the upper portion thereof.

이러한 콘크리트 함거 블록은 시공하고자 하는 푸팅의 크기와 동일하게 슬라브와 벽체를 일체로 제작된다.Such concrete impregnation block is integrally manufactured with the slab and the wall in the same size as the footing to be constructed.

이를 좀더 보충하면 지지층에 말뚝기초를 매설하고, 콘크리트 함거 블록을 고정시키기 위하여 말뚝기초의 상부에 받침대를 고정하며, 이에 미리 제작된 콘크리트 함거 블록을 안치시킨다. 이와 같이 콘크리트 함거 블록이 설치되면 내부에 콘크리트를 타설 양생시켜 푸팅을 시공하며, 이어서 상부구조물인 교각을 시공한다.To supplement this, the pile foundation is embedded in the supporting layer, and the pedestal is fixed to the upper portion of the pile foundation to fix the concrete containment block, and the prefabricated concrete containment block is placed therein. As such, when the concrete impregnation block is installed, the concrete is poured into the interior and the footing is constructed, followed by the construction of the piers, which are upper structures.

아울러 푸팅을 수중에 시공할 경우에는 외수의 유입을 방지하기 위하여 일정한 높이만큼 가물막이용 벽체를 제작하여 벽체 상부에 고정시킨 다음 말뚝기초에 안치시키거나, 콘크리트 함거 블록을 말뚝기초에 안치시킨 후 가물막이용 벽체를 고정시킨다.In addition, when installing footings in water, to prevent the inflow of external water, the wall for the temporary curtain wall is made to a certain height and fixed to the upper part of the wall, and then placed in the pile foundation or the concrete containment block in the pile foundation. Fix the wall for membrane.

이와 같은 콘크리트 함거 블록은 푸팅의 철근 배근과 콘크리트 타설을 위하여 외측에 거푸집을 설치함은 물론 비계, 동바리 등을 설치하여야 하는 불편함이 있고, 슬라브와 벽체가 일체로 이루어지므로 자중이 무거울 뿐만 아니라 대형 기중기 등을 사용하여 운반하므로 이에 소요되는 비용이 증가하게 되며, 벽체 상부에 가물막이용 벽체를 제작하여 설치하므로 이에 따른 비용의 증가는 물론 푸팅 시공 후 가물막이용 벽체를 철거하여야 하는 번거러움이 있다.Such concrete impregnation block has the inconvenience of installing a formwork on the outside for reinforcing reinforcement and concrete placing of footing, as well as installing scaffolding, clubs, etc. Since the crane is carried using a crane, etc., the cost required for this is increased, and since the wall is made and installed on the upper part of the wall, there is a need for removing the wall for the clam after the construction, as well as the increase in the cost.

또한, 콘크리트 함거 블록의 자중을 감소시키기 위하여 두께를 줄이면 이동 및 안치시 변형이나 균열, 파손이 발생하게 되며, 두께를 두껍게 하면 운반, 안치에 대형 기중기 등을 사용하므로 가시설물 설치에 많은 시간과 비용이 투입되는 단점이 있으며, 벽체 균열 및 변형으로 시공 후 콘크리트의 탈락 및 백태 발생으로 구조물 유지, 관리비용이 소요되는 문제점이 있다.
In addition, if the thickness is reduced in order to reduce the weight of the concrete containment block, deformation, cracking, and breakage may occur when moving and laying. If the thickness is thick, a large crane is used for transporting and laying, so it takes a lot of time and money to install the fixture. There is a disadvantage in that the input, there is a problem that the maintenance and management cost of the structure due to the falling off of the concrete and the occurrence of baektae after construction due to cracks and deformation of the wall.

이와 같은 문제점을 해결하기 위하여 본 출원인이 획득한 특허 제0744693호 콘크리트 스틸 하우스 및 이를 이용한 말뚝기초 푸팅시공방법이 있다.In order to solve such a problem, there is a patent No. 0744693 concrete steel house obtained by the present applicant and a pile foundation footing construction method using the same.

상기한 종래기술은 푸팅의 시공에 사용되는 프리캐스트 패널과 가물막이 겸용 거푸집으로 된 콘크리트 스틸 하우스를 조립식으로 제작하여 푸팅의 시공을 용이하게 함은 물론 가물막이 겸용 거푸집을 재사용 할 수 있는 이점이 있으나, 부력이 많이 발생되는 곳일 경우에는 프리캐스트 패널이 부상되어 구조적으로 안정적이지 못한 문제점이 있으며, 푸팅을 제작하기 위하여 가물막이 겸용 거푸집의 내부에 콘크리트를 타설할 때 상기 가물막이 겸용 거푸집은 콘크리트로부터 전가되는 측압에 대한 버팀강성이 미약하여 원활한 시공이 이루어질 수 없으며, 프리캐스트 패널을 지지하기 위한 받침대는 안정적인 지지력을 확보하기 위해 수중에서 견고하게 용접결합해야 하기 때문에 수중작업으로 인한 애로사항이 뒤따르는 한편, 프리캐스트 패널에 매설된 매설 너트의 공간을 통해 외수가 유입되어 푸팅에 크랙현상이 발생되고, 배력철근에 녹슴현상이 발생되는 문제점이 있다.
The prior art described above has the advantage of facilitating the construction of the footing as well as reusing the construction of the footing by prefabricating the concrete steel house made of the precast panel and the temporary film used in the construction of the footing as a prefabricated form. In the case where a lot of buoyancy is generated, the precast panel is injured and structurally unstable, and when the concrete is placed inside the double wall formwork to manufacture the footing, the double wall formwork is transferred from the concrete. Smooth construction is not possible due to the weak stiffness against the lateral pressure, and the support for the precast panel has to be welded firmly in the water to secure a stable supporting force. , Tying on precast panel Is oesu flows through the space of the embedded nut, and a crack occurs in the footing, there is a problem in that this phenomenon occurs in the booster nokseum reinforced.

본 발명은 상기한 종래기술의 문제점을 해결하기 위하여 안출된 것으로서, 푸팅의 시공에 사용되는 프리캐스트 패널과 가물막이 겸용 거푸집으로 된 콘크리트 스틸 하우스를 조립식으로 제작하여 푸팅의 시공을 용이하게 함은 물론 가물막이 겸용 거푸집을 재사용 가능하도록 하며, 푸팅을 제작하기 위해 가물막이 겸용 거푸집의 내부에 콘크리트를 타설할 때 콘크리트로부터 전가되는 측압에 대한 버팀강성이 증대되어 조립체의 배부름 현상을 방지하고 구조적으로 안정성을 확보할 수 있으며, 푸팅의 크랙현상 및 배력철근의 녹슴현상을 방지할 수 있도록 한 콘크리트 스틸 하우스를 제공하는데 그 목적이 있다.
The present invention has been made in order to solve the above problems of the prior art, by prefabricating the concrete steel house made of precast panel used in the construction of the footing and the temporary cladding formable to facilitate the construction of the footing as well The temporary cladding makes reusable formwork and increases the stiffness against the side pressure transferred from the concrete when the concrete is placed inside the dual formwork to prevent footing. The purpose of the present invention is to provide a concrete steel house to prevent cracking of footing and rust of reinforcing bars.

상기한 목적과제를 달성하기 위한 본 발명에 수단은 평판한 직사각형 형상으로 형성되며, 수중에 매설되는 말뚝기초가 관통되는 관통공이 간격을 두고 형성되어 길이 가변형 브라켓을 통해 말뚝기초에 설치되며, 내부에 배력 철근이 설치되는 프리캐스트 패널과; 일정한 높이를 갖도록 형성되면서 하단부가 수평하게 연장되어 상기 프리캐스트 패널의 측면과 하부에 결합되는 가물막이 겸용 거푸집;으로 이루어져 구성되는 콘크리트 스틸 하우스에 있어서, 상기 프리캐스트 패널의 측면과 저면에는 매설 너트가 더 구비되며, 상기 가물막이 겸용 거푸집에는 프리캐스트 패널의 매설 너트와 대응되는 위치에 통공이 더 형성되고, 상기 매설 너트에는 단부에 체결되는 너트를 통해 고정되는 볼트가 관통설치되며,
상기 가물막이 겸용 거푸집의 입구측에는 고정빔이 종,횡방향으로 더 설치되어 상기 가물 막이 겸용 거푸집의 내부에 콘크리트를 타설할 때 콘크리트로부터 전가되는 측압에 대한 버팀강성이 발생되도록 하고,
상기 길이 가변형 브라켓은, 상면과 하면 사이에 빈 공간이 형성된 "ㄷ"자 형상으로 형성되고, 상기 말뚝기초의 상부 측면에 결합되는 상부 브라켓과; 수평상의 평판 하측에 상기 평판과 직각으로 수직재가 고정되며, 상기 평판과 수직재 사이에 삼각 보강편이 고정되고, 수중에 위치되도록 상기 말뚝기초의 하부에 설치되며, 프리캐스트 패널이 거치되는 하부 브라켓과; 상기 상부 브라켓 및 하부 브라켓에 수직방향으로 이동가능하게 관통설치되며, 외주연에 나선이 형성되어 체결되는 너트를 통해 상기 상부 브라켓 및 하부 브라켓에 체결되는 상,하부 강봉과; 상기 상,하부 강봉의 사이에 결합되어 상,하방향으로 이동되는 상부 강봉에 의해 상기 하부 브라켓의 위치를 조정하고, 상기 상,하부 강봉에 체결되는 너트를 통해 인장력을 부여받는 지지용 와이어;로 이루어져 구성되는 것을 특징으로 한다.
Means in the present invention for achieving the above object is formed in a flat rectangular shape, the through hole through which the pile foundation embedded in the water is formed at intervals are installed on the pile foundation through a variable length bracket, therein A precast panel on which the reinforcing bars are installed; In the concrete steel house is formed to have a constant height and the lower end is horizontally extended to form a combined film coupled to the side and the bottom of the precast panel; the concrete steel house consisting of, the buried nuts on the side and bottom of the precast panel It is further provided, the through-hole double wall is formed in the position corresponding to the buried nut of the precast panel, the buried nut is installed through the bolt fixed through the nut fastened to the end,
A fixed beam is further installed in the longitudinal and lateral directions at the inlet side of the double-walled formwork so that the rigidity against the side pressure transferred from the concrete is generated when the temporary wall is poured into the double-walled formwork.
The variable length bracket may include an upper bracket formed in a “c” shape having an empty space formed between an upper surface and a lower surface thereof, and coupled to an upper side of the pile foundation; A lower bracket on which a vertical member is fixed at right angles to the flat plate below the horizontal plate, a triangular reinforcement piece is fixed between the flat plate and the vertical member, and is installed below the pile foundation so as to be located in water, and on which a precast panel is mounted; Upper and lower steel bars installed in the upper bracket and the lower bracket so as to be movable in a vertical direction, the upper and lower steel bars being fastened to the upper bracket and the lower bracket through a nut formed by a spiral formed on an outer circumference; A support wire that is coupled between the upper and lower steel bars to adjust the position of the lower bracket by an upper steel rod moved in the upper and lower directions, and receives a tensile force through a nut fastened to the upper and lower steel bars; Characterized in that consists of.

상기한 목적과제를 달성하기 위한 본 발명에 더한 다른 수단은 평판한 직사각형 형상으로 형성되며, 수중에 매설되는 말뚝기초가 관통되는 관통공이 간격을 두고 형성되어 길이 가변형 브라켓을 통해 말뚝기초에 설치되고, 내부에 배력 철근이 설치되는 프리캐스트 패널과; 일정한 높이를 갖도록 형성되며 상기 프리캐스트 패널의 측면에 결합되는 가물막이 겸용 거푸집;으로 이루어져 구성되는 콘크리트 스틸 하우스에 있어서, 상기 프리캐스트 패널의 측면에는 수직 지지용 홈이 더 형성되며, 상기 가물막이 겸용 거푸집에는 프리캐스트 패널의 수직 지지용 홈과 대응되는 위치에 통공이 더 형성되고, 상기 프리캐스트 패널의 수직 지지용 홈에는 가물막이 겸용 거푸집의 통공을 관통하며 단부에 체결되는 너트를 통해 고정되는 볼트가 관통설치되며, 상기 가물막이 겸용 거푸집의 입구측에는 고정빔이 종,횡방향으로 더 설치되고, 상기 가물막이 겸용 거푸집의 하부에는 상기 프리캐스트 패널의 하부를 지지하기 위한 타이바가 종,횡방향으로 체결인장되어 상기 가물 막이 겸용 거푸집의 내부에 콘크리트를 타설할 때 콘크리트로부터 전가되는 측압에 대한 버팀강성이 발생되도록 한 것을 특징으로 한다.
Another means in addition to the present invention for achieving the above object is formed in a flat rectangular shape, through-holes through which the pile foundation is buried in water is formed at intervals and installed in the pile foundation through a variable length bracket, A precast panel having a reinforcing bar installed therein; In the concrete steel house is formed to have a predetermined height and is coupled to the side of the precast panel combined formwork, in the concrete steel house consisting of, a vertical support groove is further formed on the side of the precast panel, the faux film The formwork further has a through hole formed at a position corresponding to the vertical support groove of the precast panel, and the bolt for fixing the nut through the through hole of the dual-purpose formwork is fixed to the end in the vertical support groove of the precast panel. Is installed in the through-hole, the fixed beam is further installed in the longitudinal, transverse direction at the inlet side of the dual-use double wall, the tie bar for supporting the lower part of the precast panel in the lower side of the dual-use double wall in the longitudinal, transverse direction Cone when the seal is placed and the concrete is placed inside the dual-use formwork Characterized in that a rigidity such that the stretching occurs for the lateral pressure which is passed on from the root.

상기한 목적과제를 달성하기 위한 본 발명에 더한 또 다른 수단은 평판한 직사각형 형상으로 형성되고, 수중에 매설되는 말뚝기초가 관통되는 관통공이 간격을 두고 형성되어 길이 가변형 브라켓을 통해 말뚝기초에 설치되며, 내부에 배력 철근이 설치되고, 상기 배력 철근의 일측에 단봉이 고정되며, 상기 단봉의 하부에 슈볼트가 결합되고, 상기 슈볼트의 일측으로는 빈 공간이 형성된 프리캐스트 패널과; 일정한 높이를 갖도록 형성되며 상기 프리캐스트 패널의 측면에 결합되는 가물막이 겸용 거푸집;으로 이루어져 구성되는 콘크리트 스틸 하우스에 있어서, 상기 가물막이 겸용 거푸집의 하부에는 프리캐스트 패널의 체결홈과 대응되는 위치에 통공이 더 형성되며, 상기 가물막이 겸용 거푸집의 배면에는 단면이 "ㄷ"자 형상으로 형성되는 형강이 상기 통공을 사이에 두고 형성되고, 상기 슈볼트의 외주연에는 상기 형강과 통공에 순차적으로 관통되는 타이볼트가 더 체결되어지되, 상기 가물막이 겸용 거푸집의 외면으로 노출되는 타이볼트에는 와셔를 밀착시킨 다음 너트를 체결하여 가압함으로써, 상기 가물 막이 겸용 거푸집의 내부에 콘크리트를 타설할 때 콘크리트로부터 전가되는 측압에 대한 버팀강성이 발생되도록 한 것을 특징으로 한다.
Another means in addition to the present invention for achieving the above object is formed in a flat rectangular shape, through-holes through which the pile foundation embedded in the water is formed at intervals are installed in the pile foundation through a variable length bracket A precast panel having a reinforcing reinforcement installed therein, a single rod being fixed to one side of the reinforcing reinforcing bar, a shoe bolt coupled to a lower portion of the single rod, and an empty space formed at one side of the shoe bolt; In the concrete steel house is formed to have a predetermined height and is coupled to the side of the precast panel combines the formwork, in the lower portion of the double-sided formwork combines the hole in the position corresponding to the fastening groove of the precast panel It is further formed, the back side of the double-sided formwork film is formed with a section steel formed in the shape of the cross-section "c" with the through-hole, the outer periphery of the shoe bolt is sequentially passed through the section steel and the through-hole The tie bolts are further fastened, but the tie bolts exposed to the outer surface of the dual-use formwork are brought into close contact with the washer and then pressurized by tightening nuts, so that the temporary coating is transferred from the concrete when the concrete is placed inside the dual-use formwork. Characterized in that the stiffness to the side pressure is generated.

본 발명에 따른 콘크리트 스틸 하우스는 푸팅의 시공에 사용되는 프리캐스트 패널과 가물막이 겸용 거푸집으로 된 콘크리트 스틸 하우스를 조립식으로 제작하여 푸팅의 시공을 용이하게 함은 물론 가물막이 겸용 거푸집을 재사용 가능하도록 하며, 푸팅을 제작하기 위해 가물막이 겸용 거푸집의 내부에 콘크리트를 타설할 때 콘크리트로부터 전가되는 측압에 대한 버팀강성이 증대되어 조립체의 배부름 현상을 방지하고 구조적으로 안정성을 확보할 수 있으며, 푸팅의 크랙현상 및 배력철근의 녹슴현상을 방지할 수 있는 효과가 있다.
The concrete steel house according to the present invention prefabricated concrete steel house made of precast panel used in the construction of the footing and the composite film formable to facilitate the construction of the footing, as well as to enable reuse of the composite film formwork. When the concrete is placed inside the double wall formwork to make the footing, the stiffness against the side pressure transferred from the concrete is increased, thereby preventing the assembly of the assembly and ensuring structural stability, and the cracking of the footing. There is an effect that can prevent the phenomenon and rust phenomenon of reinforcement steel.

도 1은 본 발명의 제 1실시예에 따른 콘크리트 스틸 하우스의 단면도.
도 2는 본 발명의 제 1실시예 내지 제 3실시예에 따른 콘크리트 스틸 하우스에 길이 가변형 브라켓이 적용된 것을 도시한 측면도.
도 3은 본 발명의 제 1실시예 내지 제 3실시예에 따른 콘크리트 스틸 하우스에 부식 방지용 밴드 및 부력 방지대가 적용된 것을 도시한 측면도.
도 4는 본 발명의 제 2실시예에 따른 콘크리트 스틸 하우스의 단면도.
도 5는 본 발명의 제 2실시예에 따른 콘크리트 스틸 하우스의 평면도.
도 6은 본 발명의 제 3실시예에 따른 콘크리트 스틸 하우스의 단면도.
도 7은 본 발명의 제 1실시예 내지 제 3실시예에 따른 콘크리트 스틸 하우스를 통해 제작된 푸팅을 도시한 측면도.
1 is a cross-sectional view of a concrete steel house according to a first embodiment of the present invention.
Figure 2 is a side view showing that the variable length bracket is applied to the concrete steel house according to the first to third embodiments of the present invention.
Figure 3 is a side view showing that the anti-corrosion band and buoyancy guard is applied to the concrete steel house according to the first to third embodiments of the present invention.
4 is a cross-sectional view of a concrete steel house according to a second embodiment of the present invention.
5 is a plan view of a concrete steel house according to a second embodiment of the present invention.
6 is a cross-sectional view of a concrete steel house according to a third embodiment of the present invention.
7 is a side view showing a footing manufactured through the concrete steel house according to the first to third embodiments of the present invention.

이하 본 발명의 바람직한 실시 예를 첨부된 도면을 참조하여 함께 상세히 설명하면 더욱 명백해 질것이다.
Hereinafter, with reference to the accompanying drawings, preferred embodiments of the present invention will be more apparent.

<실시예 1>&Lt; Example 1 >

도 1은 본 발명의 제 1실시예에 따른 콘크리트 스틸 하우스의 단면도이고, 도 2는 본 발명의 제 1실시예 내지 제 3실시예에 따른 콘크리트 스틸 하우스에 길이 가변형 브라켓이 적용된 것을 도시한 측면도이며, 도 3은 본 발명의 제 1실시예 내지 제 3실시예에 따른 콘크리트 스틸 하우스에 부식 방지용 밴드 및 부력 방지대가 적용된 것을 도시한 측면도이다.
1 is a cross-sectional view of a concrete steel house according to a first embodiment of the present invention, Figure 2 is a side view showing that the variable length bracket is applied to the concrete steel house according to the first to third embodiments of the present invention; 3 is a side view showing that the anti-corrosion band and the buoyancy guard is applied to the concrete steel house according to the first to third embodiments of the present invention.

상기 도 1 내지 도 3에 도시된 바와 같이, 본 발명에 따른 콘크리트 스틸 하우스는 프리캐스트 패널(10)에 가물막이 겸용 거푸집(20)을 결합시킨 다음 상기 가물막이 겸용 거푸집(20)의 내부에 콘크리트를 타설/양생하여 형성된다.As shown in Figures 1 to 3, the concrete steel house according to the present invention is combined with the precast panel 10, the temporary film combine formwork 20, and then the concrete inside the temporary film 20 It is formed by pouring / curing.

상기 프리캐스트 패널(10)은 거푸집의 내부에 콘크리트를 타설/양생 한 다음 거푸집을 탈형함으로써 제작된다.The precast panel 10 is manufactured by pouring / curing concrete into the formwork and demolding the formwork.

이러한 프리캐스트 패널(10)은 평판한 직사각형 형상으로 형성되고, 수중에 매설되는 말뚝기초(1)가 관통되는 관통공(21)(11)이 간격을 두고 형성되며, 길이 가변형 브라켓(70)을 통해 상기 말뚝기초(1)에 안정적으로 설치된다.The precast panel 10 is formed in a flat rectangular shape, the through holes 21 and 11 through which the pile foundation 1 embedded in water are formed at intervals, and the variable length bracket 70 is formed. Through the pile foundation (1) is installed stably.

또한, 상기 프리캐스트 패널(10)의 측면과 저면에는 매설 너트(12)가 간격을 두고 형성되며, 바람직하게 상기 프리캐스트의 내부에는 일부분이 푸팅(110)과 결합됨으로 인해 프리캐스트 패널(10)과 푸팅(110) 간의 결합력이 증대될 수 있도록 배력 철근(14)이 더 매설된다.
In addition, the buried nut 12 is formed on the side and bottom of the precast panel 10 at intervals, and preferably, a part of the precast panel 10 is combined with the footing 110 in the precast panel 10. The backing rebar 14 is further buried so that the coupling force between the footing and the footing 110 can be increased.

상기에서 길이 가변형 브라켓(70)은 상면과 하면 사이에 빈 공간이 형성된 "ㄷ"자 형상으로 형성되고, 상기 말뚝기초(1)의 상부 측면에 결합되는 상부 브라켓(71)과, 수평상의 평판(72a) 하측에 상기 평판(72a)과 직각으로 수직재(72b)가 고정되며, 상기 평판(72a)과 수직재(72b) 사이에 삼각 보강편(72c)이 고정되고, 수중에 위치되도록 상기 말뚝기초(1)의 하부에 설치되며, 프리캐스트 패널(10)이 거치되는 하부 브라켓(72)과, 상기 상부 브라켓(71) 및 하부 브라켓(72)에 수직방향으로 이동가능하게 관통설치되며, 외주연에 나선이 형성되어 체결되는 너트를 통해 상기 상부 브라켓(71) 및 하부 브라켓(72)에 체결되는 상,하부 강봉(73b)과, 상기 상,하부 강봉(73b)의 사이에 결합되어 상,하방향으로 이동되는 상부 강봉(73a)에 의해 상기 하부 브라켓(72)의 위치를 조정하고, 상기 상,하부 강봉(73b)에 체결되는 너트를 통해 인장력을 부여받는 지지용 와이어(74)로 이루어져 구성된다.The variable length bracket 70 is formed in a "c" shape with an empty space formed between the upper surface and the lower surface, the upper bracket 71 is coupled to the upper side of the pile foundation (1), and a horizontal flat plate ( 72a) The vertical member 72b is fixed to the lower portion at right angles with the flat plate 72a, and the triangular reinforcement piece 72c is fixed between the flat plate 72a and the vertical material 72b, and the pile foundation is positioned in the water. It is installed in the lower part of 1), and is installed through the lower bracket 72, on which the precast panel 10 is mounted, so as to be movable in a vertical direction to the upper bracket 71 and the lower bracket 72, the outer periphery The upper and lower steel bars 73b fastened to the upper bracket 71 and the lower bracket 72 and the upper and lower steel bars 73b fastened to the upper bracket 71 and the lower bracket 72 through a nut to which the spiral is formed. Adjust the position of the lower bracket 72 by the upper steel bar (73a) moved to, and Phase, is constituted made up of a lower rod (73b), the support wire (74) is granted to a tensile force via a nut is fastened to.

이와 같이 구성되는 길이 가변형 브라켓(70)은 하부 브라켓(72)이 콘크리트 스틸 하우스를 구성하는 프리캐스트 패널(10)을 지지하고, 인장력이 부여된 지지용 와이어(74)가 상,하부 강봉(73b)을 매개로 하여 하부 브라켓(72)을 지탱하므로서 콘크리트 스틸 하우스가 부력에 의해 부상되는 것을 효율적으로 방지하여 구조적으로 안정성을 확보할 수 있도록 하며, 언급한 바와 같이 상기 지지용 와이어(74)가 하부 브라켓(72)을 지탱하는 구조이므로, 하부 브라켓(72)은 말뚝기초(1)에 간단히 태그용접으로 고정시켜도 하부 브라켓(72)의 고정력을 확보할 수 있어 시공시간 및 시공의 편리성도 부가적으로 제공할 수 있다.
The variable length bracket 70 configured as described above supports the precast panel 10 in which the lower bracket 72 constitutes the concrete steel house, and the supporting wire 74 given with tensile force is provided with upper and lower steel bars 73b. By supporting the lower bracket (72) through a) to effectively prevent the concrete steel house from being floated by buoyancy to ensure structural stability, as mentioned above the support wire 74 is lower Since the bracket 72 supports the structure, the lower bracket 72 can secure the fixing force of the lower bracket 72 even if it is simply fixed to the pile foundation 1 by tag welding. Can provide.

상기 가물막이 겸용 거푸집(20)은 일정한 높이를 갖도록 형성되면서 하단부가 수평하게 연장되어 그 단면이 대략 "ㄴ"자 형상으로 형성된다. 즉, 상기 가물막이 겸용 거푸집(20)의 수직면은 프리캐스트 패널(10)의 측면에 접촉고정되고, 수평면은 프리캐스트 패널(10)의 접촉고정된다.The temporary film double die 20 is formed to have a constant height while the lower end is extended horizontally is formed in a substantially "b" shaped cross-section. In other words, the vertical surface of the temporary mold double wall 20 is in contact with the side of the precast panel 10, the horizontal surface is fixed in contact with the precast panel (10).

상기한 가물막이 겸용 거푸집(20)에는 프리캐스트 패널(10)의 매설 너트(12)와 대응되는 위치에 통공(21)이 더 형성되어 프리캐스트 패널(10)과의 결합을 용이하게 한다.The temporary film 20 also has a through hole 21 formed at a position corresponding to the buried nut 12 of the precast panel 10 to facilitate coupling with the precast panel 10.

이를 좀 더 자세히 설명하면 상기 가물막이 겸용 거푸집(20)의 통공(21)과 프리캐스트 패널(10)의 매설 너트(12)에 볼트를 순차적으로 관통설치 한 다음 상기 가물막이 겸용 거푸집(20)의 외면으로 노출되는 볼트의 단부에 너트를 체결하여 상기 가물막이 겸용 거푸집(20)을 프리캐스트 패널(10)에 용이하면서 안정적으로 결합할 수 있다.In more detail, the bolts are sequentially installed in the through-holes 21 and the buried nuts 12 of the precast panel 10 in the temporary film combined formwork 20, and then Fastening the nut to the end of the bolt exposed to the outer surface can be easily and stably coupled to the precast panel 10 to combine the temporary film 20.

또한, 상기 통공(21)에는 볼트가 맞물리면서 따라 들어갈 수 있도록 나선을 형성하고, 상기 너트와 가물막이 겸용 거푸집(20)의 사이에는 가압력을 부여하는 와셔(51)를 더 개재하여 프리캐스트 패널(10)과 가물막이 겸용 거푸집(20) 간의 결합력을 극대화할 수 있다.
In addition, the through-holes 21 are formed with a spiral so that the bolt can be engaged with each other, and the precast panel 10 through a washer 51 for applying a pressing force between the nut and the double-sided formwork (20). ) And the temporary film can be combined to maximize the combined force (20).

상기 가물막이 겸용 거푸집(20)의 입구측에는 그 단면이 대략 "H"자 형상 또는 "I"자 형상으로 형성되는 고정빔(30)이 종,횡방향의 등간격으로 더 설치되어 프리캐스트 패널(10)과 가물막이 겸용 거푸집(20) 간의 결합상태를 휨,변형 없이 안정되게 지속적으로 유지시켜 준다.At the inlet side of the temporary double wall formwork 20, a fixed beam 30 whose cross section is formed in a substantially "H" shape or an "I" shape is further installed at equal intervals in the longitudinal and transverse directions to form a precast panel ( 10) and the temporary membrane keeps the bonding state between the combined formwork 20 without any bending or deformation.

그리고, 상기 가물막이 겸용 거푸집(20)의 내부에 콘크리트를 타설/양생 한 다음 프리캐스트 패널(10)에서 분리하게 되면 푸팅(110)이 제작된다.In addition, when the concrete film is poured / cured into the interior of the dual-use formwork 20 and separated from the precast panel 10, the footing 110 is manufactured.

이와 같이 조립된 조립체는 푸팅(110)을 제작하기 위해 내부에 콘크리트를 타설할 때 콘크리트로부터 전가되는 측압에 대한 버팀강성이 증대되어 조립체의 배부름 현상을 방지하고 구조적으로 안정성을 확보할 수 있도록 한다.
The assembly assembled as described above increases the stiffness against the side pressure transferred from the concrete when the concrete is placed therein to manufacture the footing 110, thereby preventing the assembly of the assembly and ensuring structural stability. .

이하, 본 발명에 따른 콘크리트 스틸 하우스를 이용한 말뚝기초(1) 푸팅(110) 시공방법을 구체적으로 설명한다.Hereinafter, the construction method of the pile foundation (1) footing 110 using a concrete steel house according to the present invention will be described in detail.

먼저, 말뚝기초(1)에 시공하고자 하는 푸팅(110)의 크기에 맞도록 프리캐스트 패널(10)을 준비한다. 그리고, 상기 프리캐스트 패널(10)에 가물막이 겸용 거푸집(20)을 결합하며, 상기 가물막이 겸용 거푸집(20)의 입구측에는 고정빔(30)을 종,횡방향의 등간격으로 더 설치하여 콘크리트 스틸 하우스를 제작한다.First, the precast panel 10 is prepared to fit the size of the footing 110 to be installed on the pile foundation (1). In addition, the precast panel 10 is coupled to the temporary film combined formwork 20, the inlet side of the combined film formwork 20, the fixed beam 30 is further installed at equal intervals in the longitudinal and transverse directions at the inlet side Build a steel house.

그리고, 상기 가물막이 겸용 거푸집(20)의 연결되는 부분에는 외수유입을 차단하기 위한 수밀재(미도시)를 개재하는 것이 바람직하다.In addition, it is preferable to interpose a watertight member (not shown) to block the inflow of external water to a part of the temporary film combined formwork 20 connected.

이후, 수중 구조물을 시공하고자 하는 위치로 이동하여 수중에 매설된 말뚝기초(1)에 길이가변형 브라켓을 고정시킨다.Thereafter, the variable length bracket is fixed to the pile foundation 1 embedded in the water by moving to the position where the underwater structure is to be constructed.

이후에, 상기 콘크리트 스틸 하우스에 인양 균형대(미도시)를 고정하고, 상기 인양 균형대에 와이어를 결속하며 작업선에 실린 기중기로 인양하여 작업 현장으로 이동한 다음 프리캐스트 패널(10)의 관통공(11)에 말뚝기초(1)가 관통되도록 하부 브라켓(72)에 콘크리트 스틸 하우스를 안착한다.Thereafter, the lifting balance (not shown) is fixed to the concrete steel house, the wire is tied to the lifting balance and lifted by a crane loaded on the work line and moved to the work site, and then the penetration of the precast panel 10. A concrete steel house is seated on the lower bracket 72 so that the pile foundation 1 penetrates the ball 11.

상기 프리캐스트 패널(10)의 관통공(11)은 말뚝기초(1) 및 길이 가변형 브라켓(70)을 모두 통과할 수 있는 직경으로 형성된다. 따라서, 말뚝기초(1)와 관통공(11) 사이에는 빈 공간이 형성되어 이 빈 공간 사이로 외수가 유입될 것이므로, 상기 프리캐스트 패널(10)의 관통공(11)과 말뚝기초(1)의 사이에는 콘크리트를 더 충진하여 외수 유입을 원천적으로 차단하는 것이 바람직하다.The through hole 11 of the precast panel 10 is formed to a diameter that can pass through both the pile foundation (1) and the variable-length bracket (70). Therefore, an empty space is formed between the pile foundation 1 and the through hole 11 so that the external water flows into the empty space, so that the through hole 11 and the pile foundation 1 of the precast panel 10 are formed. In between, it is preferable to block the inflow of the original water by further filling the concrete.

만약, 상기 프리캐스트 패널(10)이 설치되는 장소가 부력이 많이 발생되는 곳일 경우에는 상기 프리캐스트 패널(10)의 상부에는 측면이 프리캐스트 패널(10)의 상부로 돌출된 말뚝기초(1)에 고정되는 부력 방지대(100)를 더 설치하여 콘크리트 스틸 하우스의 부상을 방지할 수 있다.If the place where the precast panel 10 is installed is a place where a lot of buoyancy is generated, the pile foundation (1) protruding from the upper side of the precast panel 10 to the upper side of the precast panel 10. It is possible to prevent the injury of the concrete steel house by installing a buoyancy guard 100 is fixed to the more.

그리고 상기 부력 방지대(100)와 기초 말뚝의 사이에는 부식방지용밴드(90)를 더 구비하여 푸팅의 내부로 외수가 유입되는 것을 차단하여 부식을 방지한다.
And between the buoyancy guard 100 and the foundation piles further provided with a corrosion preventing band 90 to prevent the inflow of external water into the footing to prevent corrosion.

이후에, 상기 콘크리트 스틸 하우스의 가물막이 겸용 거푸집(20) 상단에 작업자가 통행할 수 있도록 안전 작업대를 설치하고, 공지의 펌프를 이용하여 콘크리트 스틸 하우스 내부에 물을 외부로 배수시킨다.
Thereafter, a safety workbench is installed to allow a worker to pass on the upper part of the temporary film of the concrete steel house combined with the formwork 20, and the water is drained to the inside of the concrete steel house to the outside using a known pump.

이후, 도 7에 도시된 바와 같이, 콘크리트 펌프를 이용하여 콘크리트 스틸 하우스의 내부에 콘크리트를 타설 양생시키고, 계속해서 교각기초(120)가 시공되도록 거푸집을 설치한 다음 콘크리트를 타설 양생시켜 푸팅(110) 및 교각기초(120)를 시공한다.
Then, as shown in Figure 7, using a concrete pump to pour concrete into the interior of the concrete steel house, and then install the formwork so that the bridge foundation 120 is constructed, and then pour the concrete to put the footing (110) ) And pier foundation 120 is constructed.

이후에, 기중기를 이용하여 콘크리트 스틸 하우스에 체결된 볼트 및 너트를 해제하여 가물막이 겸용 거푸집(20) 및 고정빔(30)을 분리시키고, 길이가변형 브라켓을 분리시킨 다음 매설 너트(12)의 빈 공간에 수중 콘크리트(미도시) 또는 충진재(미도시)를 타설하여 메움으로서, 푸팅(110)의 외관을 복구한다.
Subsequently, the bolts and nuts fastened to the concrete steel house are lifted using a crane to separate the temporary film 20 and the fixed beam 30, and the length-variable bracket is separated, and then the hollow of the buried nut 12 is removed. By pouring underwater concrete (not shown) or filler (not shown) into the space, the exterior of the footing 110 is restored.

<실시예 2><Example 2>

도 4는 본 발명의 제 2실시예에 따른 콘크리트 스틸 하우스의 단면도이고, 도 5는 본 발명의 제 2실시예에 따른 콘크리트 스틸 하우스의 평면도이다.4 is a cross-sectional view of a concrete steel house according to a second embodiment of the present invention, Figure 5 is a plan view of a concrete steel house according to a second embodiment of the present invention.

상기 도 4 및 도 5에 도시된 콘크리트 스틸 하우스는 실시예 1의 도 1 내지 도 3에 도시된 콘크리트 스틸하우스와 그 구성에 있어서 많이 다르지는 않지만 몇가지 점에서 크게 차이가 있으므로 여기서는 도 4 및 도 5에 도시된 콘크리트 스틸 하우스의 구성요소를 간단히 언급하고 그 차이점에 대해서만 중점적으로 설명하도록 한다.
4 and 5 is not much different from the concrete steel house shown in FIGS. 1 to 3 of the first embodiment, but the configuration thereof is greatly different in several respects. The components of the concrete steel house shown in Figure 1 are briefly mentioned and only the differences will be explained.

상기 도 4 및 도 5에서 도시된 바와 같이, 본 발명에 따른 콘크리트 스틸 하우스는 프리캐스트 패널(10)에 가물막이 겸용 거푸집(20)을 결합시킨 다음 상기 가물막이 겸용 거푸집(20)의 내부에 콘크리트를 타설/양생하여 형성된다.
As shown in Figure 4 and 5, the concrete steel house according to the present invention is combined with the precast panel 10, the temporary film combine formwork (20) and then the interior of the temporary film combine formwork 20 It is formed by pouring / curing.

상기에서 프리캐스트 패널(10)의 측면에는 수직 지지용 홈(13)이 더 형성되며, 상기 가물막이 겸용 거푸집(20)에는 프리캐스트 패널(10)의 수직 지지용 홈(13)과 대응되는 위치에 통공(21)이 더 형성되어 프리캐스트 패널(10)의 수직 지지용 홈(13)과 가물막이 겸용 거푸집(20)의 결합을 용이하게 한다.The vertical support groove 13 is further formed on the side surface of the precast panel 10, and the position corresponding to the vertical support groove 13 of the precast panel 10 is provided in the temporary double wall 20. A through-hole 21 is further formed in the groove to facilitate coupling of the vertical support groove 13 of the precast panel 10 with the temporary film 20.

이를 좀 더 자세히 설명하면 상기 가물막이 겸용 거푸집(20)의 통공(21)과 프리캐스트 패널(10)의 수직 지지용 홈(13)에 볼트를 순차적으로 관통설치 한 다음 상기 가물막이 겸용 거푸집(20)의 외면으로 노출되는 볼트의 단부에 너트를 체결하여 상기 가물막이 겸용 거푸집(20)을 프리캐스트 패널(10)에 용이하면서 안정적으로 결합할 수 있다.To explain this in more detail, the bolts are sequentially installed in the through hole 21 and the vertical support groove 13 of the precast panel 10, and then the dual wall 20 Fastening the nut to the end of the bolt exposed to the outer surface of the) can be easily and stably coupled to the precast panel 10, the temporary film combines 20.

그리고,푸팅(110) 및 교각기초(120) 시공이 완료되면 가물막이 겸용 거푸집(20)을 분리시킨 다음 기밀유지용 부재(60)에 외주연에 점착제를 도포하여 수직 지지용 홈(13)에 삽입시켜 접착하므로서 외수유입을 차단하여 프리캐스트 패널(10)에 크랙이 발생되는 것을 방지하고 배력 철근(14)에 녹이 슬어 부식되는 것을 방지한다.
Then, when the construction of the footing 110 and the foundation of the bridge 120 is completed, the temporary film 20 is separated, and then the adhesive is applied to the outer periphery of the airtight member 60 to the vertical support groove 13. By inserting and bonding to block the inflow of external water to prevent the cracks generated in the precast panel 10 and to prevent rust and corrosion to the reinforcement reinforcement (14).

또한, 실시예 1과 동일하게 상기 가물막이 겸용 거푸집(20)의 통공(21)에는 나선을 더 형성하고 상기 너트와 가물막이 겸용 거푸집(20)의 사이에는 와셔(51)를 더 개재할 수 있으며, 상기 가물막이 겸용 거푸집(20)의 입구측에는 단면이 대략 "H"자 형상 또는 "I"자 형상으로 형성되는 고정빔(30)이 종,횡방향의 등간격으로 더 설치된다.
In addition, in the same manner as in Example 1, the through-hole 21 of the dual-use mold film 20 may be further formed with a spiral, and the washer 51 may be further interposed between the nut and the dual-use die 20. In addition, a fixed beam 30 having a cross-section having an approximately "H" shape or an "I" shape is further provided at the entrance side of the temporary film combine formwork 20 at equal intervals in the longitudinal and transverse directions.

그리고, 상기 가물막이 겸용 거푸집(20)의 하부에는 타이바(40)가 종,횡방향의 등간격으로 더 체결인장되어 상기 프리캐스트 패널(10)의 하부를 안정적으로 지지하면서 가물막이 겸용 거푸집(20) 간의 결합력을 확보하도록 한다.In addition, the tie bar 40 is further tightened and tensioned at equal intervals in the longitudinal and transverse directions at the lower portion of the dual-use double wall 20 to stably support the lower portion of the precast panel 10 while maintaining the dual double wall formwork ( 20) Ensure the bond between them.

이를 좀 더 보충하면 상기 타이바(40)를 마주보는 2개의 가물막이 겸용 거푸집(20)에 관통설치하고 가물막이 겸용 거푸집(20)의 외측으로 노출되는 타이바(40)의 양측에는 너트로 인장하여 타이바(40)의 인장상태를 유지할 수 있으며, 상기 타이바(40)의 장력 및 수평력을 통해 상기 프리캐스트 패널(10)을 안정적으로 지지하면서 가물막이 겸용 거푸집(20) 간의 결합력이 확보되도록 할 수 있는 것이다.Further supplementing this, the two bars of the tie bar 40 facing each other to install the penetrating through the 20, both sides of the tie bar 40 exposed to the outside of the double-sided formwork 20 is tensioned with a nut It is possible to maintain the tension state of the tie bar 40, so as to secure the coupling force between the temporary film and the formwork combine 20 while stably supporting the precast panel 10 through the tension and horizontal force of the tie bar 40. You can do it.

그리고, 상기 가물막이 겸용 거푸집(20)의 내측면에는 프리캐스트 패널(10)을 안정적으로 지지할 수 있는 받침 브라켓(130)이 더 설치될 수 있다.
In addition, a support bracket 130 that can stably support the precast panel 10 may be further installed on the inner surface of the temporary film combined formwork 20.

이와 같이 조립된 조립체는 상기 실시예 1과 동일하게 푸팅(110)을 제작하기 위해 내부에 콘크리트를 타설할 때 콘크리트로부터 전가되는 측압에 대한 버팀강성이 증대되어 조립체의 배부름 현상을 방지하고 구조적으로 안정성을 확보할 수 있도록 한다.
The assembly assembled as described above has the same stiffness against the side pressure transferred from the concrete when the concrete is placed therein to produce the footing 110 as in Embodiment 1, thereby preventing the assembly of the assembly and structurally Ensure stability.

<실시예 3><Example 3>

도 6은 본 발명의 제 3실시예에 따른 콘크리트 스틸 하우스의 단면도이다.
6 is a cross-sectional view of a concrete steel house according to a third embodiment of the present invention.

상기 도 6에 도시된 콘크리트 스틸 하우스는 실시예 1 및 실시예 2의 도 1 내지 도 5에 도시된 콘크리트 스틸하우스와 그 구성에 있어서 많이 다르지는 않지만 몇가지 점에서 크게 차이가 있으므로 여기서는 도 6에 도시된 콘크리트 스틸 하우스의 구성요소를 간단히 언급하고 그 차이점에 대해서만 중점적으로 설명하도록 한다.
The concrete steel house shown in FIG. 6 is different from the concrete steel house shown in FIGS. 1 to 5 of Embodiments 1 and 2 but its configuration is greatly different in several respects, and thus is shown in FIG. 6. The components of the concrete concrete house are briefly mentioned and only the differences are explained.

상기 도 6에 도시된 바와 같이, 본 발명에 따른 콘크리트 스틸 하우스는 프리캐스트 패널(10)에 가물막이 겸용 거푸집(20)을 결합시킨 다음 상기 가물막이 겸용 거푸집(20)의 내부에 콘크리트를 타설/양생하여 형성된다.As shown in FIG. 6, the concrete steel house according to the present invention is coupled to the precast panel 10 by combining the temporary film 20 and then placing concrete inside the dual film 20. It is formed by curing.

상기 프리캐스트 패널(10)의 내부에는 배력 철근(14)이 설치되는데, 이 배력 철근(14)의 일부분은 상기 프리캐스트 패널(10)의 상부로 돌출되어 푸팅(110)과 결합됨으로 인해 프리캐스트 패널(10)과 푸팅(110) 간의 결합력이 증대되도록 한다.A backing reinforcement 14 is installed inside the precast panel 10. A part of the backing reinforcement 14 protrudes above the precast panel 10 and is coupled with the footing 110 to precast. The coupling force between the panel 10 and the footing 110 is increased.

또한, 상기 배력 철근(14)의 일측에는 단봉(15)이 용접 결합되며, 상기 단봉(15)의 하부에는 슈볼트(16)가 결합되며, 상기 프리캐스트 패널(10)의 내부 중 슈볼트(16)가 위치된 일측으로는 외부와 연통되는 빈 공간이 형성된다.
In addition, a single rod 15 is welded to one side of the reinforcing bar 14, the shoe bolt 16 is coupled to the lower portion of the single rod 15, the shoe bolt of the interior of the precast panel (10) On one side where 16) is located, an empty space communicating with the outside is formed.

상기 가물막이 겸용 거푸집(20)은 평판한 직사각형 형상으로 형성되며 하부에는 프리캐스트 패널(10)의 빈 공간과 대응되는 위치에 통공(21)이 더 형성되며, 배면에는 단면이 대략 "ㄷ"자 형상으로 형성되는 형강(22)이 상기 통공(21)을 사이에 두고 형성된다.The temporary film combiner 20 is formed in a flat rectangular shape and a lower portion of the through-hole 21 is formed at a position corresponding to the empty space of the precast panel 10, the cross-section on the back is approximately "c" Shaped steel 22 formed in a shape is formed with the through-hole 21 therebetween.

그리고, 상기 형강(22)의 사이와 통공(21)에 타이볼트(50)가 순차적으로 관통되어 슈볼트(16)의 외주연에 체결되고, 상기 가물막이 겸용 거푸집(20)의 외면으로 노출되는 타이볼트(50)의 외주연에는 와셔(51)를 밀착시킨 다음 너트를 체결하여 가압하게되면 상기 프리캐스트 패널(10)에 가물막이 겸용 거푸집(20)이 안정된 구조로 결합된다.
Then, the tie bolts 50 are sequentially penetrated between the shaped steels 22 and the through-holes 21 to be fastened to the outer circumference of the shoe bolts 16, and the temporary film is exposed to the outer surface of the dual-purpose formwork 20. When the washer 51 is closely attached to the outer circumference of the tie bolt 50, the nut 20 is coupled to the precast panel 10, and the double die 20 is coupled to the precast panel 10 in a stable structure.

이와 같이 조립된 조립체는 상기 실시예 1 및 실시예 2와 동일하게 푸팅(110)을 제작하기 위해 내부에 콘크리트를 타설할 때 콘크리트로부터 전가되는 측압에 대한 버팀강성이 증대되어 조립체의 배부름 현상을 방지하고 구조적으로 안정성을 확보할 수 있도록 한다.The assembly assembled as described above increases the stiffness against the side pressure transferred from the concrete when the concrete is placed therein to produce the footing 110 in the same manner as in the first embodiment and the second embodiment, thereby increasing the assembly phenomenon of the assembly. Prevent and structural stability.

10 : 프리캐스트 패널 11 : 관통공
12 : 매설 너트 13 : 수직 지지용 홈
14 : 배력 철근 15 : 단봉
16 : 슈볼트 17 : 체결홈
20 : 가물막이 겸용 거푸집 21 : 통공
22 : 형강 30 : 고정빔
40 : 타이바 50 : 타이볼트
51 : 와셔 60 : 기밀유지용 부재
70 : 길이 가변형 브라켓 71 : 상부 브라켓
72 : 하부 브라켓 72a : 평판
72b : 수직재 72c : 삼각 보강편
73a : 상부 강봉 73b : 하부 강봉
74 : 지지용 와이어 90 : 부식방지용 밴드
91 : 결합편 100 : 부력 방지대
110 : 푸팅 120: 교각기초
10 precast panel 11: through hole
12: buried nut 13: vertical support groove
14: reinforcement bar 15: single rod
16: Shubolt 17: Tightening groove
20: double-walled formwork 21: through-hole
22: section steel 30: fixed beam
40: tie bar 50: tie bolt
51: washer 60: member for confidentiality
70: variable length bracket 71: upper bracket
72: lower bracket 72a: flat plate
72b: vertical member 72c: triangular reinforcement
73a: upper steel bar 73b: lower steel bar
74: support wire 90: corrosion prevention band
91: engagement piece 100: buoyancy guard
110: footing 120: bridge foundation

Claims (6)

평판한 직사각형 형상으로 형성되며, 수중에 매설되는 말뚝기초(1)가 관통되는 관통공(11)이 간격을 두고 형성되어 길이 가변형 브라켓(70)을 통해 말뚝기초(1)에 설치되며, 내부에 배력 철근(14)이 설치되는 프리캐스트 패널(10)과; 일정한 높이를 갖도록 형성되면서 하단부가 수평하게 연장되어 상기 프리캐스트 패널(10)의 측면과 하부에 결합되는 가물막이 겸용 거푸집(20);으로 이루어져 구성되는 콘크리트 스틸 하우스에 있어서,
상기 프리캐스트 패널(10)의 측면과 저면에는 매설 너트(12)가 더 구비되며,
상기 가물막이 겸용 거푸집(20)에는 프리캐스트 패널(10)의 매설 너트(12)와 대응되는 위치에 통공(21)이 더 형성되고,
상기 매설 너트(12)에는 단부에 체결되는 너트를 통해 고정되는 볼트가 관통설치되며,
상기 가물막이 겸용 거푸집(20)의 입구측에는 고정빔(30)이 종,횡방향으로 더 설치되어 상기 가물 막이 겸용 거푸집의 내부에 콘크리트를 타설할 때 콘크리트로부터 전가되는 측압에 대한 버팀강성이 발생되도록 하고,
상기 길이 가변형 브라켓(70)은,
상면과 하면 사이에 빈 공간이 형성된 "ㄷ"자 형상으로 형성되고, 상기 말뚝기초(1)의 상부 측면에 결합되는 상부 브라켓(71)과;
수평상의 평판(72a) 하측에 상기 평판(72a)과 직각으로 수직재(72b)가 고정되며, 상기 평판(72a)과 수직재(72b) 사이에 삼각 보강편(72c)이 고정되고, 수중에 위치되도록 상기 말뚝기초(1)의 하부에 설치되며, 프리캐스트 패널(10)이 거치되는 하부 브라켓(72)과;
상기 상부 브라켓(71) 및 하부 브라켓(72)에 수직방향으로 이동가능하게 관통설치되며, 외주연에 나선이 형성되어 체결되는 너트를 통해 상기 상부 브라켓(71) 및 하부 브라켓(72)에 체결되는 상,하부 강봉(73b)과;
상기 상,하부 강봉(73b)의 사이에 결합되어 상,하방향으로 이동되는 상부 강봉(73a)에 의해 상기 하부 브라켓(72)의 위치를 조정하고, 상기 상,하부 강봉(73b)에 체결되는 너트를 통해 인장력을 부여받는 지지용 와이어(74);로 이루어져 구성되는 것을 특징으로 하는 콘크리트 스틸 하우스.
Is formed in a flat rectangular shape, the through-hole 11 through which the pile foundation (1) embedded in the water is formed at intervals are installed in the pile foundation (1) through the variable-length bracket 70, the inside A precast panel 10 on which the reinforcing bars 14 are installed; In the concrete steel house formed of a constant height is formed so as to have a constant height and the horizontal film is combined with the side and the bottom of the precast panel 10 combined formwork;
A buried nut 12 is further provided on the side and bottom of the precast panel 10.
Through-holes 21 are further formed in the temporary film-forming formwork 20 at a position corresponding to the buried nut 12 of the precast panel 10,
The buried nut 12 is installed through the bolt fixed through the nut fastened to the end,
The fixed beam 30 is further installed in the longitudinal and lateral directions at the inlet side of the temporary film combined formwork 20 so that the rigidity against the side pressure transferred from the concrete is generated when the temporary film is placed in the interior of the combined formwork. and,
The variable length bracket 70,
An upper bracket 71 formed in a “c” shape having an empty space formed between an upper surface and a lower surface thereof, and coupled to an upper side of the pile foundation 1;
The vertical member 72b is fixed to the lower portion of the horizontal flat plate 72a at right angles to the flat plate 72a, and the triangular reinforcing pieces 72c are fixed between the flat plate 72a and the vertical material 72b, and positioned in the water. A lower bracket 72 installed below the pile foundation 1 and on which the precast panel 10 is mounted;
It is installed through the upper bracket 71 and the lower bracket 72 so as to be movable in a vertical direction, and is fastened to the upper bracket 71 and the lower bracket 72 through a nut formed by fastening a spiral on an outer circumference. Upper and lower steel bars 73b;
The position of the lower bracket 72 is adjusted by the upper steel bar 73a which is coupled between the upper and lower steel bars 73b and moves up and down, and is fastened to the upper and lower steel bars 73b. Concrete steel house, characterized in that consisting of; a support wire 74 is given a tensile force through the nut.
평판한 직사각형 형상으로 형성되며, 수중에 매설되는 말뚝기초(1)가 관통되는 관통공(11)이 간격을 두고 형성되어 길이 가변형 브라켓(70)을 통해 말뚝기초(1)에 설치되고, 내부에 배력 철근(14)이 설치되는 프리캐스트 패널(10)과; 일정한 높이를 갖도록 형성되며 상기 프리캐스트 패널(10)의 측면에 결합되는 가물막이 겸용 거푸집(20);으로 이루어져 구성되는 콘크리트 스틸 하우스에 있어서,
상기 프리캐스트 패널(10)의 측면에는 수직 지지용 홈(13)이 더 형성되며,
상기 가물막이 겸용 거푸집(20)에는 프리캐스트 패널(10)의 수직 지지용 홈(13)과 대응되는 위치에 통공(21)이 더 형성되고,
상기 프리캐스트 패널(10)의 수직 지지용 홈(13)에는 가물막이 겸용 거푸집(20)의 통공(21)을 관통하며 단부에 체결되는 너트를 통해 고정되는 볼트가 관통설치되며,
상기 가물막이 겸용 거푸집(20)의 입구측에는 고정빔(30)이 종,횡방향으로 더 설치되고,
상기 가물막이 겸용 거푸집(20)의 하부에는 상기 프리캐스트 패널(10)의 하부를 지지하기 위한 타이바(40)가 종,횡방향으로 체결인장되어 상기 가물 막이 겸용 거푸집의 내부에 콘크리트를 타설할 때 콘크리트로부터 전가되는 측압에 대한 버팀강성이 발생되도록 한 것을 특징으로 하는 콘크리트 스틸 하우스.
Is formed in a flat rectangular shape, the through-hole 11 through which the pile foundation (1) embedded in the water is formed at intervals and installed in the pile foundation (1) through the variable-length bracket (70), A precast panel 10 on which the reinforcing bars 14 are installed; In the concrete steel house is formed to have a predetermined height and is composed of a temporary film (20) combined formwork film coupled to the side of the precast panel 10,
The side of the precast panel 10 is further formed with a vertical support groove 13,
Through-holes 21 are further formed in the temporary film-forming formwork 20 at a position corresponding to the vertical support groove 13 of the precast panel 10,
In the vertical support groove 13 of the precast panel 10, a bolt through which the temporary film penetrates the through-hole 21 of the dual-purpose formwork 20 and fixed through a nut fastened to an end thereof is installed therethrough.
The fixed beam 30 is further installed in the longitudinal and lateral directions at the inlet side of the temporary film combine formwork 20,
The tie bar 40 for supporting the lower part of the precast panel 10 is tensioned in the longitudinal and lateral directions at the lower portion of the double wall formwork 20 to cast concrete in the interior of the double wall formwork. Concrete steel house, characterized in that when the stiffness to the side pressure that is transferred from the concrete is generated.
평판한 직사각형 형상으로 형성되고, 수중에 매설되는 말뚝기초(1)가 관통되는 관통공(11)이 간격을 두고 형성되어 길이 가변형 브라켓(70)을 통해 말뚝기초(1)에 설치되며, 내부에 배력 철근(14)이 설치되고, 상기 배력 철근(14)의 일측에 단봉(15)이 고정되며, 상기 단봉(15)의 하부에 슈볼트(16)가 결합되고, 상기 슈볼트(16)의 일측으로는 빈 공간이 형성된 프리캐스트 패널(10)과; 일정한 높이를 갖도록 형성되며 상기 프리캐스트 패널(10)의 측면에 결합되는 가물막이 겸용 거푸집(20);으로 이루어져 구성되는 콘크리트 스틸 하우스에 있어서,
상기 가물막이 겸용 거푸집(20)의 하부에는 프리캐스트 패널(10)의 체결홈(17)과 대응되는 위치에 통공(21)이 더 형성되며,
상기 가물막이 겸용 거푸집(20)의 배면에는 단면이 "ㄷ"자 형상으로 형성되는 형강(22)이 상기 통공(21)을 사이에 두고 형성되고,
상기 슈볼트(16)의 외주연에는 상기 형강(22)과 통공(21)에 순차적으로 관통되는 타이볼트(50)가 더 체결되어지되, 상기 가물막이 겸용 거푸집(20)의 외면으로 노출되는 타이볼트(50)에는 와셔(51)를 밀착시킨 다음 너트를 체결하여 가압함으로써,
상기 가물 막이 겸용 거푸집의 내부에 콘크리트를 타설할 때 콘크리트로부터 전가되는 측압에 대한 버팀강성이 발생되도록 한 것을 특징으로 하는 콘크리트 스틸 하우스.
It is formed in a flat rectangular shape, the through hole 11 through which the pile foundation 1 embedded in the water is formed at intervals, and is installed in the pile foundation 1 through the variable-length bracket 70. A backing bar 14 is installed, and a single bar 15 is fixed to one side of the backing bar 14, and a shoe bolt 16 is coupled to a lower part of the single bar 15, and the shoe bolt 16 A precast panel 10 having an empty space formed on one side thereof; In the concrete steel house is formed to have a predetermined height and is composed of a temporary film (20) combined formwork film coupled to the side of the precast panel 10,
The through-hole 21 is further formed at a lower portion of the temporary film combined formwork 20 corresponding to the fastening groove 17 of the precast panel 10,
On the back surface of the dual-purpose mold 20, the section steel 22 having a cross-section having a "C" shape is formed with the through-hole 21 interposed therebetween,
The outer bolt of the shoe bolt 16 is further coupled to the tie bolt 50, which is sequentially penetrated through the section steel 22 and the through-hole 21, the tie is exposed to the outer surface of the dual-purpose mold 20 By contacting the washer 51 to the bolt 50 and then tightening and pressing the nut,
The concrete steel house, characterized in that the brace stiffness to the side pressure transferred from the concrete is generated when the temporary film is placed in the interior of the dual-purpose formwork.
제 2항에 있어서,
상기 프리캐스트 패널(10)의 체결홈(17)에는 상기 프리캐스트 패널(10)의 내부에 점착제를 통해 접착되어 외수유입을 차단하기 위한 기밀유지용 부재(60)가 더 삽입되는 것을 특징으로 하는 콘크리트 스틸 하우스.
The method of claim 2,
The fastening groove 17 of the precast panel 10 is further adhered to the inside of the precast panel 10 by an adhesive, characterized in that the airtight member 60 for blocking the inflow of water is further inserted. Concrete steel house.
제 2항 또는 3항에 있어서,
상기 길이 가변형 브라켓(70)은,
상면과 하면 사이에 빈 공간이 형성된 "ㄷ"자 형상으로 형성되고, 상기 말뚝기초(1)의 상부 측면에 결합되는 상부 브라켓(71)과;
수평상의 평판(72a) 하측에 상기 평판(72a)과 직각으로 수직재(72b)가 고정되며, 상기 평판(72a)과 수직재(72b) 사이에 삼각 보강편(72c)이 고정되고, 수중에 위치되도록 상기 말뚝기초(1)의 하부에 설치되며, 프리캐스트 패널(10)이 거치되는 하부 브라켓(72)과;
상기 상부 브라켓(71) 및 하부 브라켓(72)에 수직방향으로 이동가능하게 관통설치되며, 외주연에 나선이 형성되어 체결되는 너트를 통해 상기 상부 브라켓(71) 및 하부 브라켓(72)에 체결되는 상,하부 강봉(73b)과;
상기 상,하부 강봉(73b)의 사이에 결합되어 상,하방향으로 이동되는 상부 강봉(73a)에 의해 상기 하부 브라켓(72)의 위치를 조정하고, 상기 상,하부 강봉(73b)에 체결되는 너트를 통해 인장력을 부여받는 지지용 와이어(74);로 이루어져 구성되는 것을 특징으로 하는 콘크리트 스틸 하우스.
The method of claim 2 or 3,
The variable length bracket 70,
An upper bracket 71 formed in a “c” shape having an empty space formed between an upper surface and a lower surface thereof, and coupled to an upper side of the pile foundation 1;
The vertical member 72b is fixed to the lower portion of the horizontal flat plate 72a at right angles to the flat plate 72a, and the triangular reinforcing pieces 72c are fixed between the flat plate 72a and the vertical material 72b, and positioned in the water. A lower bracket 72 installed below the pile foundation 1 and on which the precast panel 10 is mounted;
It is installed through the upper bracket 71 and the lower bracket 72 so as to be movable in a vertical direction, and is fastened to the upper bracket 71 and the lower bracket 72 through a nut formed by fastening a spiral on an outer circumference. Upper and lower steel bars 73b;
The position of the lower bracket 72 is adjusted by the upper steel bar 73a which is coupled between the upper and lower steel bars 73b and moves up and down, and is fastened to the upper and lower steel bars 73b. Concrete steel house, characterized in that consisting of; a support wire 74 is given a tensile force through the nut.
제 1항 내지 3항 중 어느 한 항에 있어서,
상기 프리캐스트 패널(10)의 상부에는 측면이 프리캐스트 패널(10)의 상부로 돌출된말뚝기초(1)에 고정되어 콘크리트 스틸 하우스의 부상을 방지하기 위한 부력 방지대(100)가 더 설치되고,
상기 부력 방지대(100)와 기초 말뚝의 사이에는 외수 유입을 차단하고, 배력 철근(14)의 부식을 방지하기 위해 설치되는 부식방지용 밴드(90)가 더 구비되는 것을 특징으로 하는 콘크리트 스틸 하우스.
The method according to any one of claims 1 to 3,
On the upper part of the precast panel 10, the side is fixed to the pile foundation (1) protruding to the upper portion of the precast panel 10 is further provided with a buoyancy guard 100 for preventing the injury of the concrete steel house ,
Concrete steel house, characterized in that provided between the buoyancy guard 100 and the foundation pile to block the inflow of external water, the anti-corrosion band 90 is installed to prevent corrosion of the reinforcement reinforcing bars (14).
KR1020100105469A 2010-10-27 2010-10-27 Concrete steel house KR101025892B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100105469A KR101025892B1 (en) 2010-10-27 2010-10-27 Concrete steel house

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100105469A KR101025892B1 (en) 2010-10-27 2010-10-27 Concrete steel house

Publications (1)

Publication Number Publication Date
KR101025892B1 true KR101025892B1 (en) 2011-03-30

Family

ID=43939572

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100105469A KR101025892B1 (en) 2010-10-27 2010-10-27 Concrete steel house

Country Status (1)

Country Link
KR (1) KR101025892B1 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101237986B1 (en) 2012-04-19 2013-02-27 건국대학교 산학협력단 Structure of offshore structure and construction method thereof
WO2014021625A1 (en) * 2012-08-01 2014-02-06 대한민국(농촌진흥청장) Greenhouse comprising concrete piles
KR101510453B1 (en) 2014-10-20 2015-04-08 주식회사 명훈이앤씨 Method for constructing steel house bridge footing using steel plate
CN105220699A (en) * 2015-09-21 2016-01-06 中铁建大桥工程局集团第一工程有限公司 Cofferdam construction method
CN106192767A (en) * 2016-08-31 2016-12-07 中交二航局第四工程有限公司 A kind of device that can improve bottom concrete bearing capacity and construction method
KR101898720B1 (en) * 2017-11-24 2018-09-13 공주대학교 산학협력단 Fixing block with expedite installation pile cap
CN109655601A (en) * 2019-01-15 2019-04-19 华东交通大学 Model test foundation pit enclosure structure deeply mixing cement-soil pile test device and test method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100744693B1 (en) * 2005-10-24 2007-08-01 (주) 선암기술연구소 Concrete-steel house and pile foundation footing construction method using thereof
KR20090037114A (en) * 2007-10-11 2009-04-15 현대건설주식회사 Cofferdam, its construction method using sheet file and wale and construction method for underwater structure using the cofferdam
KR100937740B1 (en) 2009-08-07 2010-01-20 정석으뜸기술(주) A method of constructing precast concrete house under water using caisson

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100744693B1 (en) * 2005-10-24 2007-08-01 (주) 선암기술연구소 Concrete-steel house and pile foundation footing construction method using thereof
KR20090037114A (en) * 2007-10-11 2009-04-15 현대건설주식회사 Cofferdam, its construction method using sheet file and wale and construction method for underwater structure using the cofferdam
KR100937740B1 (en) 2009-08-07 2010-01-20 정석으뜸기술(주) A method of constructing precast concrete house under water using caisson

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101237986B1 (en) 2012-04-19 2013-02-27 건국대학교 산학협력단 Structure of offshore structure and construction method thereof
WO2014021625A1 (en) * 2012-08-01 2014-02-06 대한민국(농촌진흥청장) Greenhouse comprising concrete piles
KR101510453B1 (en) 2014-10-20 2015-04-08 주식회사 명훈이앤씨 Method for constructing steel house bridge footing using steel plate
CN105220699A (en) * 2015-09-21 2016-01-06 中铁建大桥工程局集团第一工程有限公司 Cofferdam construction method
CN106192767A (en) * 2016-08-31 2016-12-07 中交二航局第四工程有限公司 A kind of device that can improve bottom concrete bearing capacity and construction method
CN106192767B (en) * 2016-08-31 2017-12-26 中交二航局第四工程有限公司 A kind of device and construction method that can improve bottom concrete bearing capacity
KR101898720B1 (en) * 2017-11-24 2018-09-13 공주대학교 산학협력단 Fixing block with expedite installation pile cap
CN109655601A (en) * 2019-01-15 2019-04-19 华东交通大学 Model test foundation pit enclosure structure deeply mixing cement-soil pile test device and test method

Similar Documents

Publication Publication Date Title
KR101025892B1 (en) Concrete steel house
KR100747661B1 (en) Mold-concrete composite Crossbeam and construction method using the same
AU2015409344B2 (en) Assembled type pier column member with steel-concrete composite structure
KR101381858B1 (en) Prefabricated column and beam with sheet concrete form
CN107030874A (en) Precast lattice beam for slope reinforcement and preparation method thereof and construction method
CN112982181B (en) Construction method for steel-concrete combined section of through-type steel box continuous arch bridge
KR100744693B1 (en) Concrete-steel house and pile foundation footing construction method using thereof
JP6427045B2 (en) Reinforcement structure and reinforcement method of existing concrete structure
KR101170922B1 (en) The rahmen bridge construction technique for which tendon and the connection support stand was used
KR100761785B1 (en) Mold-concrete composite crossbeam
CN113605771A (en) Prestress assembly type frame structure system
KR101086646B1 (en) Prestress concrete composite girder with prestress non-introducing portion provided at both ends, manufacturing method thereof, and built-up type slab bridge construction method using the same
KR101184719B1 (en) Method making rigid block with pile and slab/precast girder and method constructing the rahmen bridge thereof
KR100775359B1 (en) Concrete-mold assembly and construction method using the same
CN101550724A (en) Construction method of large-span post-tensioned prestressed longitudinal and transverse frame beams
KR101157607B1 (en) Prestressed steel composite girder with prestressed non-introducing portions provided at both ends of lower flange casing concrete, manufacturing method thereof, and Rahmen structure and construction method thereof
CN107586068B (en) Upright column concrete and construction method of concrete upright column
KR20060100814A (en) Synthetic construction wall of a waterway, a canal and a method of the construction
KR100860592B1 (en) Temporary system for vertical structure using precast concreat block
CN216129955U (en) Steel-concrete combined section structure of through-type steel box continuous arch bridge
KR200395627Y1 (en) Concrete composite Crossbeam
KR20130046490A (en) Pc column with joint of moment type
KR101211101B1 (en) A bridge post strengthen structure and construction methode there of
KR101215764B1 (en) A burial slab structure of an outer wall of an underground construction
CN110512776B (en) Construction method of assembled steel structure multi-cavity steel plate composite shear wall

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20140306

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20150306

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20160310

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20170323

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20180323

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20190311

Year of fee payment: 9