KR100937740B1 - A method of constructing precast concrete house under water using caisson - Google Patents

A method of constructing precast concrete house under water using caisson Download PDF

Info

Publication number
KR100937740B1
KR100937740B1 KR1020090094133A KR20090094133A KR100937740B1 KR 100937740 B1 KR100937740 B1 KR 100937740B1 KR 1020090094133 A KR1020090094133 A KR 1020090094133A KR 20090094133 A KR20090094133 A KR 20090094133A KR 100937740 B1 KR100937740 B1 KR 100937740B1
Authority
KR
South Korea
Prior art keywords
house
caisson
installing
underwater
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
KR1020090094133A
Other languages
Korean (ko)
Inventor
허남택
허용
Original Assignee
정석으뜸기술(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 정석으뜸기술(주) filed Critical 정석으뜸기술(주)
Application granted granted Critical
Publication of KR100937740B1 publication Critical patent/KR100937740B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/02Caissons able to be floated on water and to be lowered into water in situ
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/18Foundations formed by making use of caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/063Tunnels submerged into, or built in, open water

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Foundations (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

수중 피씨 하우스 케이슨 공법은 기초 파일을 설치하여 기초 파일 둘레에 가물막이를 설치하고, 가물막이 내부를 배수시켜 하부 브라켓을 설치하고, 하부 브라켓에 피씨 하우스를 안착시킨 후 상단에 스틸 케이슨을 설치하고, 스틸 케이슨 상단에 하중 재하부를 안착시키고 피씨 하우스 내부를 배수시켜 교량 기초물을 시공한다. 이와 같이 구성되는 수중 피씨 하우스 케이슨 공법에 의하면, 피씨 하우스의 상단에 설치되는 스틸 케이슨에 의해 피씨 하우스 내부 작업을 건식으로 실시하여 작업성이 향상되고 시공비를 줄일 수 있고, 스틸 케이슨 상부에 안착되는 하중 재하부에 의해 피씨 하우스가 부양하는 것을 방지할 수 있으므로 시공 편의성이 향상되는 이점이 있다.Underwater PC house caisson method installs a foundation pile around the foundation pile by installing the foundation pile, drains the interior of the barrier membrane to install the lower bracket, seats the PC house on the lower bracket, and then installs the steel caisson on the top, Place the bridge foundation on the top of the steel caisson and drain the interior of the PC house. According to the underwater PC house caisson method configured in this way, the steel caisson installed on the upper part of the PC house to dry the work inside the PC house to improve the workability and reduce the construction cost, the load that is seated on the upper steel caisson Since the PC house can be prevented from supporting by loading, there is an advantage in that construction convenience is improved.

Description

수중 피씨 하우스 케이슨 공법{A METHOD OF CONSTRUCTING PRECAST CONCRETE HOUSE UNDER WATER USING CAISSON}A METHOD OF CONSTRUCTING PRECAST CONCRETE HOUSE UNDER WATER USING CAISSON}

본 발명은 수중 피씨 하우스 케이슨 공법에 관한 것으로, 보다 상세하게는 수중에서 케이슨을 이용하여 피씨 하우스를 조립하는 공법에 관한 것이다.The present invention relates to an underwater PC house caisson method, and more particularly, to a method for assembling a PC house using caisson underwater.

일반적으로 교각은 철도, 차량, 보행자가 통행할 수 있는 교량 상판을 수상에서 일정한 높이로 위치시키기 위해 수중에 교각 기초가 시공된다. 교각기초는 주로 교각보다 큰 직경으로 제작되고 수중의 바닥면에 일정깊이로 매설되도록 시공되어 고정력이 부여된다.Generally, pier foundations are constructed underwater to position bridge decks that can be passed by railroads, vehicles, and pedestrians at a certain height in the water surface. Pier foundations are mainly manufactured with a larger diameter than the pier, and are constructed to be buried to a certain depth in the bottom of the water to impart a fixed force.

이러한 교각은 수상에서 공사를 하게 되므로 작업에 제약조건이 많고 수중공사가 시행되어야 하므로 고가의 공사비가 소요된다. 그리고, 최근에는 수중공사를 줄이기 위해 교각간의 길이를 길게 함으로써 하부 기초의 규모가 커져 공사비를 증가시키는 원인이 되고 있다.Since these bridges are constructed at the water level, there are many constraints on the work and underwater construction must be carried out, which requires expensive construction costs. In recent years, the length of the lower foundation is increased by increasing the length of the piers in order to reduce the underwater construction, causing the construction cost to increase.

일반적으로 교각기초를 형성하기 위한 공법 중 하나로 말뚝기초와 피씨하우 스(PC house)를 이용하는 방법이 있다. 피씨하우스란 육상에서 미리 제작된 프리캐스트 콘크리트 조립체를 해상으로 운반하여 조립함으로써 설치하는 구조물을 의미한다.In general, as a method for forming a bridge foundation, there is a method using a pile foundation and a PC house (PC house). The PC house refers to a structure installed by transporting and assembling the precast concrete assembly prefabricated on land.

말뚝기초에 피씨하우스를 조립하기 위해서는 용접을 이용하여 말뚝기초에 브라켓을 연결시키거나 분할된 피씨하우스 조립체를 서로 조립하는 공정이 필요하다. 말뚝기초에 브라켓을 연결시키기 위해서는 말뚝기초의 상단을 수면 밖으로 노출시킨 상태에서 용접을 실시하게 된다.In order to assemble the PC house on the pile foundation, it is necessary to connect the bracket to the pile foundation by welding or to assemble the divided PC house assemblies to each other. In order to connect the bracket to the pile foundation, welding is performed while the top of the pile foundation is exposed out of the water surface.

그러나, 조수간만 차에 의해 수심이 변화하는 지역이나 말뚝기초의 상단이 수면 밖으로 노출되지 않는 경우에는 말뚝기초에 브라켓을 연결시키는 작업이 매우 어렵거나 잠수사를 이용해야 하므로 공사비가 매우 커지는 문제점이 있다.However, in the case where the depth of the area or the top of the pile foundation is not exposed out of the water surface only by the tidal difference, the work of connecting the bracket to the pile foundation is very difficult or a diver needs to use a diver, so the construction cost is very large.

본 발명은 이와 같은 종래의 문제점을 해결하기 위한 것으로, 본 발명의 목적은 수심이 변화하는 지역이나 말뚝기초의 상단이 수면 밖으로 노출되지 않는 경우에도 케이슨을 이용하여 피씨하우스를 설치하도록 하는 것이다.The present invention is to solve such a conventional problem, it is an object of the present invention to install a PC house using a caisson even when the top of the area or the pile foundation is changed out of the water surface.

이와 같은 목적을 달성하기 위한 본 발명의 특징에 의하면, 본 발명의 수중 피씨 하우스 케이슨 공법은 하상 저면에 기초 파일을 근입하는 기초 파일 설치단계; 상기 기초 파일 둘레에 가물막이를 설치하고 내부의 물을 배수시키는 가물막이 설치단계; 상기 기초 파일에 하부 브라켓을 설치하고 상기 가물막이를 해체하는 하부 브라켓 설치단계; 상기 하부 브라켓에 피씨 하우스를 안착시키는 피씨 하우스 설치단계; 상기 피씨 하우스 상단에 스틸 케이슨을 설치하는 스틸 케이슨 설치단계; 상기 스틸 케이슨 상단에 하중 재하부를 설치하는 하중 재하부 설치단계; 상기 피씨 하우스 내부를 배수시키고 상부 브라켓을 설치하는 상부 브라켓 설치단계; 상기 하중 재하부를 해체하고, 상기 피씨 하우스에 교량 기초부를 시공하는 교량 기초부 시공단계;및 상기 스틸 케이슨을 해체하는 스틸 케이슨 해체단계를 포함하는 것이 바람직하다.According to a feature of the present invention for achieving the above object, the underwater PC house caisson method of the present invention is the foundation pile installation step of incorporating the foundation pile on the bottom of the bed; Installing a temporary curtain around the foundation pile and installing the temporary curtain to drain the water therein; A lower bracket installation step of installing a lower bracket on the foundation pile and dismantling the temporary barrier; A PC house installation step of seating the PC house on the lower bracket; Steel caisson installation step of installing a steel caisson on the top of the PC house; A load loading part installing step of installing a load loading part on an upper portion of the steel caisson; An upper bracket installation step of draining the inside of the PC house and installing an upper bracket; A bridge foundation construction step of dismantling the load bearing part and constructing a bridge foundation part in the PC house; and preferably, a steel caisson dismantling step of dismantling the steel caisson.

본 발명의 피씨 하우스 설치단계는 다수개로 분할된 피씨 하우스를 서로 연결하는 상기 피씨 하우스 연결단계를 포함하는 것이 바람직하다.The PC house installation step of the present invention preferably includes the PC house connection step of connecting the PC house divided into a plurality.

본 발명의 피씨 하우스 연결단계는 다수개의 피씨 하우스 내부에 구비되는 연결선을 프리텐션하여 분할된 피씨 하우스를 연결시키는 프리텐션 단계를 포함하는 것이 바람직하다.The PC house connection step of the present invention preferably includes a pretension step of connecting the divided PC houses by pretensioning connection lines provided in the plurality of PC houses.

본 발명의 피씨 하우스 연결단계는 분할된 상기 피씨 하우스의 연결지점에 구비된 연결부 사이에 지수재를 설치하고, 상기 연결지점에 콘크리트를 타설하는 것이 바람직하다.In the PC house connection step of the present invention, it is preferable to install the water repellent material between the connection parts provided at the connection points of the divided PC house, and to cast concrete at the connection points.

본 발명의 피씨 하우스 연결단계는 상기 피씨 하우스 내부에 지지대를 설치하는 지지대 설치단계를 포함하는 것이 바람직하다.PC house connection step of the present invention preferably includes a support installation step of installing a support in the PC house.

본 발명의 가물막이 설치단계는 상기 분할된 피씨 하우스의 면적에 대응되는 다수개의 기초 파일 둘레에 상기 가물막이를 설치하고, 상기 하부 브라켓이 설치되면 다시 새로운 다수개의 기초 파일 둘레에 상기 가물막이를 설치하는 것을 반복하는 것이 바람직하다.In the installation step of the temporary curtain of the present invention, the temporary curtain is installed around a plurality of foundation piles corresponding to the area of the divided PC house, and when the lower bracket is installed, the temporary curtain is installed around the new multiple foundation piles. It is preferable to repeat doing.

본 발명의 하부 브라켓 설치단계는 반복적으로 설치되는 상기 가물막이에 대응하여 상기 하부 브라켓을 설치하는 것이 바람직하다.In the lower bracket installation step of the present invention, it is preferable to install the lower bracket in response to the temporary barrier that is repeatedly installed.

본 발명의 스틸 케이슨 설치단계는 유압잭을 이용하여 연결봉을 인장시켜 상기 피씨 하우스와 상기 스틸 케이슨을 연결시키는 단계를 포함하는 것이 바람직하다.Steel caisson installation step of the present invention preferably comprises the step of connecting the PC house and the steel caisson by tensioning the connecting rod using a hydraulic jack.

본 발명의 가물막이 설치단계는 상기 가물막이가 안착될 하상 저면을 준설하여 안착홈을 형성하는 안착홈 형성단계를 포함하는 것이 바람직하다.The provision of the provisional barrier of the present invention preferably includes a stepping groove forming step of forming a recessing groove by dredging the bottom surface of the lower surface on which the temporary closure is to be seated.

본 발명의 수중 피씨 하우스 케이슨 공법의 제2 실시예는 하상 저면에 기초 파일을 근입하는 기초 파일 설치단계; 상기 기초 파일 둘레에 가물막이를 설치하고 내부의 물을 배수시키는 가물막이 설치단계; 상기 기초 파일에 하부 브라켓을 설치하고 상기 가물막이를 해체하는 하부 브라켓 설치단계; 상기 하부 브라켓에 분할된 스틸 케이슨이 연결된 분할된 피씨 하우스를 각각 안착시키는 피씨 하우스 설치단계; 상기 분할된 스틸 케이슨과 상기 분할된 피씨 하우스를 각각 연결시키는 조립단계; 상기 스틸 케이슨 상단에 하중 재하부를 설치하는 하중 재하부 설치단계; 상기 피씨 하우스 내부를 배수시키고 상부 브라켓을 설치하는 상부 브라켓 설치단계; 상기 하중 재하부를 해체하고, 상기 피씨 하우스에 교량 기초부를 시공하는 교량 기초부 시공단계;및 상기 스틸 케이슨을 해체하는 스틸 케이슨 해체단계를 포함하는 것이 바람직하다.A second embodiment of the underwater PC house caisson method of the present invention includes a foundation pile installation step of placing the foundation pile on the bottom of the bed; Installing a temporary curtain around the foundation pile and installing the temporary curtain to drain the water therein; A lower bracket installation step of installing a lower bracket on the foundation pile and dismantling the temporary barrier; PC house installation step of seating each of the divided PC house is connected to the steel caisson divided in the lower bracket; An assembling step of connecting the divided steel caisson and the divided PC house, respectively; A load loading part installing step of installing a load loading part on an upper portion of the steel caisson; An upper bracket installation step of draining the inside of the PC house and installing an upper bracket; A bridge foundation construction step of dismantling the load bearing part and constructing a bridge foundation part in the PC house; and preferably, a steel caisson dismantling step of dismantling the steel caisson.

본 발명의 조립단계는 다수개의 피씨 하우스 내부에 구비되는 연결선을 프리텐션하여 분할된 피씨 하우스를 연결시키고, 유압잭을 이용하여 연결봉을 인장시켜 분할된 스틸 케이슨을 연결시키는 것이 바람직하다.In the assembly step of the present invention, it is preferable to connect the divided PC houses by pretensioning the connection lines provided in the plurality of PC houses, and to connect the divided steel caissons by tensioning the connecting rods using a hydraulic jack.

본 발명의 조립단계는 상기 분할된 피씨 하우스의 접합면과 상기 분할된 스틸 케이슨의 접합면에 각각 지수재를 설치하는 것이 바람직하다.In the assembling step of the present invention, it is preferable to install the water receptacle on the joint surface of the divided PC house and the joint surface of the divided steel caisson, respectively.

본 발명의 조립단계는 상기 피씨 하우스 내부에 지지대를 설치하는 지지대 설치단계를 포함하는 것이 바람직하다.The assembling step of the present invention preferably includes a support installation step of installing a support in the PC house.

본 발명의 수중 피씨 하우스 케이슨 공법의 제3 실시예는 하상 저면에 기초 파일을 근입하는 기초 파일 설치단계; 상기 기초 파일 둘레에 하부용 가물막이를 설치하고 내부의 물을 배수시키는 하부용 가물막이 설치단계; 상기 기초 파일에 하 부 브라켓을 설치하고 상기 하부용 가물막이를 해체하는 하부 브라켓 설치단계; 상기 하부 브라켓에 피씨 하우스를 안착시키는 피씨 하우스 설치단계; 상기 피씨 하우스 내부의 기초 파일에 상부용 가물막이를 설치하고 내부의 물을 배수시키는 상부용 가물막이 설치단계; 상기 상부용 가물막이 내부의 기초 파일에 상부 브라켓을 설치하는 상부 브라켓 설치단계; 상기 상부용 가물막이를 해체하고, 상기 피씨 하우스 상단에 스틸 케이슨을 설치하는 스틸 케이슨 설치단계; 상기 피씨 하우스를 배수하여 교량 기초부를 시공하는 교량 기초부 시공단계;및 상기 스틸 케이슨을 해체하는 스틸 케이슨 해체단계를 포함하는 것이 바람직하다.A third embodiment of the underwater PC house caisson method of the present invention includes a foundation pile installation step of placing the foundation pile on the bottom of the bed; Installing a lower temporary curtain around the foundation pile and installing the lower temporary curtain for draining the water inside; A lower bracket installation step of installing a lower bracket on the foundation pile and dismantling the lower temporary closure; A PC house installation step of seating the PC house on the lower bracket; Installing the upper temporary curtain on the foundation pile inside the PC house and installing the upper temporary curtain to drain the water inside; An upper bracket installation step of installing an upper bracket on the foundation pile inside the upper temporary shield; A steel caisson installation step of dismantling the upper clamshell and installing a steel caisson on the top of the PC house; It is preferable to include a bridge foundation construction step of constructing the bridge foundation by draining the PC house; and steel caisson disassembly step of dismantling the steel caisson.

본 발명의 하부용 가물막이와 상기 상부용 가물막이에 지수재를 설치하는 단계를 포함하는 것이 바람직하다.It is preferable to include the step of installing the water repellent material in the lower temporary closure of the present invention and the upper temporary closure.

본 발명의 상부 브라켓 및 상기 하부 브라켓에는 브라켓 스토퍼를 설치하는 단계를 포함하는 것이 바람직하다.The upper bracket and the lower bracket of the present invention preferably includes a step of installing a bracket stopper.

본 발명의 상부 브라켓 및 상기 하부 브라켓이 상기 피씨 하우스와 접하는 지점에 지수재를 설치하는 단계를 포함하는 것이 바람직하다.It is preferable that the upper bracket and the lower bracket of the present invention preferably comprises the step of installing the water repellent material in contact with the PC house.

본 발명의 상부 브라켓과 상기 하부 브라켓과 상기 기초 파일이 연결되는 지점에는 연결 콘크리트를 타설하는 단계를 포함하는 것이 바람직하다.It is preferable to include the step of pouring the connection concrete at the point where the upper bracket and the lower bracket and the foundation pile of the present invention is connected.

본 발명의 하부 브라켓 설치단계는 상기 하부용 가물막이의 마감부에 연결 플레이트를 설치하고, 상기 연결 플레이트와 상기 기초 파일 사이에 지수재를 설치하여 일체로 고정시키고, 상기 기초 파일과 상기 하부용 가물막이가 접하는 부분에 가물막이 스토퍼를 설치하는 단계를 포함하는 것이 바람직하다.In the lower bracket installation step of the present invention, the connection plate is installed at the end of the lower clamper, and the watertight material is installed between the connection plate and the foundation pile to be fixed integrally, and the foundation pile and the provisional article for the lower portion. It is preferable to include the step of providing a temporary stopper at the portion where the membrane is in contact.

본 발명의 피씨 하우스 교량 구조물은 수중 피씨 하우스 케이슨 공법에 의해 시공되는 것이 바람직하다.The PC house bridge structure of the present invention is preferably constructed by the underwater PC house caisson method.

본 발명의 피씨 하우스 및 케이슨의 연결구조는 피씨 하우스의 상단에 스틸 케이슨을 설치하여 교량 구조물을 설치하는 상기 공법에 있어서, 상기 피씨 하우스와 상기 스틸 케이슨은 연결봉 및 연결너트에 의해 연결되고, 상기 분할된 피씨 하우스는 연결부에 의해 연결되고, 상기 피씨 하우스와 상기 교각기초는 상부 브라켓, 하부 브라켓 및 상기 상부 브라켓과 상기 하부 브라켓 사이에 타설되는 연결 콘크리트에 의해 연결되는 것이 바람직하다.In the construction method of the PC house and the caisson of the present invention in the method of installing a bridge structure by installing a steel caisson on the top of the PC house, the PC house and the steel caisson are connected by a connecting rod and a connection nut, the division It is preferable that the PC house is connected by a connection part, and the PC house and the bridge foundation are connected by an upper bracket, a lower bracket, and a connecting concrete that is poured between the upper bracket and the lower bracket.

본 발명의 피씨 하우스와 상기 스틸 케이슨은 상기 피씨 하우스의 측면에 구비된 연결너트에 의해 연결봉의 일단이 연결되고, 상기 스틸 하우스에 상기 연결봉이 연장되어 상기 연결봉을 인장시킴으로써 연결되는 것이 바람직하다.One end of the connecting rod is connected to the PC house and the steel caisson of the present invention by a connecting nut provided on the side of the PC house, and the connecting rod is extended to the steel house to be connected by tensioning the connecting rod.

본 발명의 분할된 피씨 하우스는 상기 피씨 하우스의 하면으로부터 하방으로 더 돌출된 연결부의 돌출부 사이에 지수재가 삽입되고, 상기 연결부의 상면에는 초속경 콘크리트가 타설되어 연결되는 것이 바람직하다.In the divided PC house of the present invention, a water stopper is inserted between the protrusions of the connection part which protrudes further downward from the bottom of the PC house, and the upper surface of the connection part is preferably superhard concrete poured.

본 발명의 피씨 하우스와 상기 스틸 케이슨 사이에는 지수재가 구비되는 것이 바람직하다.It is preferable that an index member is provided between the PC house and the steel caisson of the present invention.

이와 같은 본 발명에 의한 수중 피씨 하우스 케이슨 공법에 의하면, 수위변화가 심하거나 수중에 피씨 하우스가 설치되는 경우에도 피씨 하우스의 상단에 설 치되는 스틸 케이슨에 의해 피씨 하우스 내부 작업을 건식으로 실시할 수 있으므로 작업성이 향상되고 시공비를 줄일 수 있고, 스틸 케이슨 상부에 안착되는 하중 재하부에 의해 피씨 하우스가 부양하는 것을 방지할 수 있고, 하중 재하부가 없이 상부용 가물막이와 하부용 가물막이를 이용하여 상부 브라켓 및 하부 브라켓을 설치할 수 있으므로 시공편의성이 향상되는 이점이 있다.According to the underwater PC house caisson method according to the present invention, even when the water level change is severe or the PC house is installed in the water can be carried out dry work inside the PC house by the steel caisson installed on the top of the PC house. As a result, workability can be improved and construction cost can be reduced, and the PC house can be prevented from being floated by the load loading portion seated on the upper part of the steel caisson. Since the upper bracket and the lower bracket can be installed, there is an advantage that the construction convenience is improved.

이하에서는 본 발명에 의한 수중 피씨 하우스 케이슨 공법의 바람직한 실시예를 첨부된 도면을 참조하여 보다 상세하게 설명한다.Hereinafter, with reference to the accompanying drawings a preferred embodiment of the underwater PC house caisson method according to the present invention will be described in more detail.

도 1 내지 도 11에는 본 발명에 의한 수중 피씨 하우스 케이슨 공법의 제1 실시예에 의한 바람직한 실시예가 도시되어 있다. 1 to 11 show a preferred embodiment according to the first embodiment of the underwater PC house caisson process according to the present invention.

도 1에 도시된 바와 같이, 구조물의 기초를 형성하는 기초 파일(10)을 소정위치까지 근입시킨다. 상기 기초 파일(10)은 하상 바닥면에 설치되므로 암반층까지 근입되는 것이 바람직하다.As shown in FIG. 1, the foundation pile 10 forming the foundation of the structure is inserted to a predetermined position. Since the foundation pile 10 is installed on the bottom surface of the lower bed, it is preferable that the foundation pile 10 enters the rock bed.

상기 기초 파일(10)의 근입이 완료되면, 상기 기초 파일(10)이 3 ~ 4개 정도 설치된 주변 둘레에 가물막이(30)가 안착되기 위한 안착홈(21)을 형성한다. 상기 안착홈(21)은 수상에 위치한 준설크레인(23)을 이용하여 형성할 수 있다.When the entrance of the foundation pile 10 is completed, the mounting groove 21 for seating the temporary barrier 30 is formed around the periphery of the foundation pile 10 is installed. The seating groove 21 may be formed using a dredge crane 23 located in the water.

상기 안착홈(21)이 형성되면, 도 2에 도시된 바와 같이 3 ~ 4개 정도의 기초 파일(10) 둘레에 가물막이(30)를 설치한다. 상기 가물막이(30)는 상기 기초 파일(10) 상단에 연결되는 하부 브라켓(40)을 건식시공하기 위한 것으로서 일반적인 케이슨으로 구성될 수 있다.When the seating groove 21 is formed, as shown in FIG. 2, a temporary barrier 30 is installed around the foundation piles 10 of about 3 to 4. The temporary barrier 30 is for dry construction of the lower bracket 40 connected to the top of the foundation pile 10 may be composed of a general caisson.

상기 가물막이(30)의 설치가 완료되면 가물막이(30) 내부의 물을 배수시킨다. 상기 가물막이(30) 내부의 물이 모두 배수되면, 도 3에 도시된 바와 같이 상기 기초 파일(10) 상단에 하부 브라켓(40)을 연결시킨다. 상기 하부 브라켓(40)은 상단에 안착되는 피씨 하우스(50)를 지지하는 역할을 한다.When the installation of the temporary film 30 is completed, the water in the temporary film 30 is drained. When all of the water in the temporary film 30 is drained, the lower bracket 40 is connected to the top of the foundation pile 10 as shown in FIG. The lower bracket 40 serves to support the PC house 50 is mounted on the top.

상기 하부 브라켓(40)의 하면에 대응되는 기초 파일(10)의 외면에는 상기 하부 브라켓(40)이 하방으로 이동하지 않도록 하는 브라켓 스토퍼(41)(도 12 참조)가 구비될 수 있다.The outer surface of the base pile 10 corresponding to the lower surface of the lower bracket 40 may be provided with a bracket stopper 41 (see FIG. 12) to prevent the lower bracket 40 from moving downward.

상기 하부 브라켓(40)이 기초 파일(10) 상단에 연결되면, 상기 기초 파일(10)의 둘레에 설치된 가물막이(30)를 해체한 후, 아직 하부 브라켓(40)이 연결되지 않은 다른 기초 파일(10) 둘레에 가물막이(30)를 설치하고 상기 하부 브라켓(40)을 설치한다. 이와 같은 과정을 반복함으로써 모든 기초 파일(10) 상단에 하부 브라켓(40)을 설치할 수 있다.When the lower bracket 40 is connected to the top of the foundation pile 10, after dismantling the temporary barrier 30 installed around the foundation pile 10, another foundation pile not yet connected to the lower bracket 40. (10) Install the temporary shield 30 around the lower bracket 40 is installed. By repeating the above process, the lower bracket 40 can be installed on the top of all the foundation piles 10.

모든 기초 파일(10) 상단에 하부 브라켓(40)이 연결되면, 도 4에 도시된 바와 같이 프리캐스트 콘크리트 블럭으로 구성된 피씨 하우스(50)의 분할체를 상기 기초 파일(10) 상단의 하부 브라켓(40)에 안착시킨다. 상기 피씨 하우스(50)는 수십톤에 해당하는 중량을 가지므로 3개 내지 4개 정도로 분할되도록 형성되는 것이 바람직하다.When the lower bracket 40 is connected to the upper end of all the foundation piles 10, as shown in FIG. 4, the split bracket of the PC house 50 made of the precast concrete block is attached to the lower bracket (the upper portion of the foundation pile 10). Seat 40). Since the PC house 50 has a weight corresponding to several tens of tons, it is preferable that the PC house 50 is divided into three to four parts.

상기 피씨 하우스(50)의 측면 및 바닥판 내부에는 도 5에 도시된 바와 같이 분할된 피씨 하우스(50) 분할체를 서로 긴밀하게 밀착되도록 하는 연결선(51)이 구 비된다. 상기 연결선(51)은 PC 강선으로 구성되고, 피씨 하우스(50)의 측면 및 바닥판에 매설된 쉬스관용 PVC 파이프로 구성될 수 있는 연결관(53) 내부에 구비된다. Side lines of the PC house 50 and the inside of the bottom plate is provided with a connecting line 51 to closely contact the divided PC house 50 partitions as shown in FIG. The connecting line 51 is composed of a PC steel wire, is provided in the connecting pipe 53 which may be composed of PVC pipe for the sheath pipe embedded in the side and bottom plate of the PC house 50.

분할된 피씨 하우스(50) 분할체를 서로 연결한 뒤, 상기 연결선(51)의 양 단을 인장시켜 프리텐션을 가함으로써 분할된 피씨 하우스(50)를 기밀하게 연결시킬 수 있다. 그리고, 상기 피씨 하우스(50) 둘레의 측면판 상부에는 아래에서 설명할 스틸 케이슨(60)과 피씨 하우스(50)를 연결시키기 위한 연결봉 홈(55)이 형성된다. After the divided PC house 50 partitions are connected to each other, the divided PC house 50 may be hermetically connected by tensioning both ends of the connecting line 51 to apply pretension. In addition, a connecting rod groove 55 for connecting the steel caisson 60 and the PC house 50 to be described below is formed at an upper side of the side plate around the PC house 50.

상기 피씨 하우스(50)의 내부에는 다수개의 지지대(57)가 설치된다. 상기 지지대(57)는 상기 피씨 하우스(50) 내부를 배수한 후 주변에 가해지는 수압에 대해 지지력을 주기 위한 것이다.A plurality of supports 57 are installed in the PC house 50. The support 57 is to give a bearing force against the water pressure applied to the surrounding after draining the inside of the PC house 50.

상기 피씨 하우스(50)의 분할체가 서로 연결되는 부분에는 요철형상의 연결부(59)가 형성되어 상기 연결부(59)가 서로 연결됨으로써 분할된 피씨 하우스(50)가 서로 연결될 수 있다.Concave-convex connecting portions 59 are formed at portions where the divided parts of the PC house 50 are connected to each other, so that the divided PC houses 50 may be connected to each other by connecting the connecting portions 59 to each other.

도 6에 도시된 바와 같이, 피씨 하우스(50)의 분할체가 연결되는 부분에는 하면에서 하방으로 돌출된 연결부(59)가 구비된다. 상기 연결부(59)에 의해 피씨 하우스(50)의 분할체가 연결되는 지점의 두께가 두껍게 형성됨으로써 분할체의 연결부 강성이 저하되는 것을 방지할 수 있다.As shown in FIG. 6, the connection portion 59 protruding downward from the lower surface is provided at a portion to which the division of the PC house 50 is connected. The thickness of the point where the split body of the PC house 50 is connected by the connecting part 59 may be increased to prevent the connection part rigidity of the split body from being lowered.

그리고, 상기 연결부(59)의 상부, 즉 피씨 하우스(50)의 분할체가 연결되는 부분은 소정 간격으로 이격되고, 피씨 하우스(50)의 분할체가 소정 간격으로 이격된 부분에는 철근이 배선되어 초속경 콘크리트(59c)가 타설된다.In addition, the upper portion of the connecting portion 59, that is, the portions where the divisions of the PC house 50 are connected are spaced at predetermined intervals, and reinforcing bars are wired to portions where the divisions of the PC house 50 are spaced at the predetermined intervals. Concrete 59c is poured.

그리고, 상기 연결부(59)에는 소정 형상의 돌출부(59t)가 형성된다. 그리고, 상기 돌출부(59t)가 상호 연결되는 지점에는 지수재(63)가 형성되어 상기 돌출부(59t)의 연결지점을 기밀하게 연결시킴으로써 수밀상태를 형성할 수 있다.The connecting portion 59 is provided with a protrusion 59t having a predetermined shape. In addition, the water discharge member 63 is formed at the point where the protrusions 59t are connected to each other to form a watertight state by hermetically connecting the connection points of the protrusions 59t.

상기 피씨 하우스(50)가 설치되면, 도 7에 도시된 바와 같이 상기 피씨 하우스(50)의 상면에 스틸 케이슨(60)을 연결한다. 상기 스틸 케이슨(60)의 측면은 수면 이상의 높이까지 연장되고 상기 스틸 케이슨(60) 내부의 물을 배수시킴으로써 건식작업을 실시할 수 있다.When the PC house 50 is installed, the steel caisson 60 is connected to the upper surface of the PC house 50 as shown in FIG. The side surface of the steel caisson 60 may extend to a height above the water surface and dry operation may be performed by draining the water inside the steel caisson 60.

상기 피씨 하우스(50)와 상기 스틸 케이슨(60)은 상기 피씨 하우스(50)의 측면에 형성된 연결봉 홈(55)에 연결되는 연결봉(61)에 의해 기밀하게 연결된다. The PC house 50 and the steel caisson 60 are hermetically connected by a connecting rod 61 connected to the connecting rod groove 55 formed on the side of the PC house 50.

도 10에는 상기 피씨 하우스(50)와 스틸 케이슨(60)의 연결구조가 상세하게 도시되어 있다. 도시된 바와 같이, 상기 피씨 하우스(50)의 측면 내부에는 연결관(53)이 구비되고, 상기 연결관(53) 내부에는 연결선(51)이 구비된다. 상기 연결선(51)을 인장시켜 프리텐션을 가함으로써 분할된 피씨 하우스(50)를 서로 기밀하게 연결시킬 수 있다.10 shows the connection structure of the PC house 50 and the steel caisson 60 in detail. As shown, the connection pipe 53 is provided inside the side of the PC house 50, the connection line 51 is provided inside the connection pipe 53. By tensioning the connecting line 51 and applying pretension, the divided PC houses 50 may be hermetically connected to each other.

그리고, 상기 피씨 하우스(50)의 측면 상단에 형성된 연결봉 홈(55)에는 연결봉(61)이 연결된다. 상기 연결봉(61)은 상기 피씨 하우스(50)의 상단에서부터 상기 스틸 케이슨(60)까지 연장된다. 상기 연결봉(61)의 일단에는 연결너트(65)가 구비되어 상기 연결봉(61)을 피씨 하우스(50)의 측면에 고정시킨다.In addition, the connecting rod 61 is connected to the connecting rod groove 55 formed at the upper side of the PC house 50. The connecting rod 61 extends from the top of the PC house 50 to the steel caisson 60. One end of the connecting rod 61 is provided with a connection nut 65 to fix the connecting rod 61 to the side of the PC house 50.

상기 연결봉(61)이 피씨 하우스(50)에 고정되면, 유압잭을 이용하여 상기 연결봉(61)을 인장시킴으로써 상기 피씨 하우스(50)와 스틸 케이슨(60)을 기밀하게 연결시킨다. 상기 피씨 하우스(50)와 상기 스틸 케이슨(60) 사이에는 지수재(63)가 구비되어 외부로부터 물이 유입되는 것을 방지할 수 있다.When the connecting rod 61 is fixed to the PC house 50, the PC house 50 and the steel caisson 60 are hermetically connected by tensioning the connecting rod 61 using a hydraulic jack. Between the PC house 50 and the steel caisson 60 is provided with an index member 63 to prevent water from flowing from the outside.

상기 피씨 하우스(50)와 상기 스틸 케이슨(60)이 연결되면, 상기 스틸 케이슨(60) 상면에 블럭과 같은 형태로 구성될 수 있는 하중 재하부(70)를 안착시킨다. 상기 스틸 케이슨(60)과 연결된 피씨 하우스(50)가 기초 파일(10)과 완전히 결합되지 않은 상태에서 상기 피씨 하우스(50) 내부의 물을 배수하면 부력에 의해 피씨 하우스(50)와 스틸 케이슨(60)이 부양할 수 있다. 따라서, 상기 하중 재하부(70)를 안착시킴으로써 부력에 의해 피씨 하우스(50) 및 스틸 케이슨(60)이 부양하는 것을 방지할 수 있다.When the PC house 50 and the steel caisson 60 are connected, the load loading portion 70, which may be configured as a block, is seated on the upper surface of the steel caisson 60. When the PC house 50 connected to the steel caisson 60 is drained out of the PC house 50 in a state in which it is not completely coupled to the foundation pile 10, the PC house 50 and the steel caisson ( 60) can support this. Therefore, it is possible to prevent the PC house 50 and the steel caisson 60 from lifting by buoyancy by seating the load bearing part 70.

상기 하중 재하부(70)가 안착되면, 상기 피씨 하우스(50) 및 스틸 케이슨(60) 내부의 물을 배수시킨다. 물이 모두 배수되어 건식 상태가 형성되면, 상기 피씨 하우스(50)와 기초 파일(10)에 상부 브라켓(80)을 연결시켜 상기 피씨 하우스(50)와 상기 기초 파일(10)을 완전히 결합시킬 수 있다. 상기 상부 브라켓(80)이 설치된 기초 파일(10)에도 브라켓 스토퍼(41)가 구비될 수 있다.When the load bearing portion 70 is seated, the water inside the PC house 50 and the steel caisson 60 is drained. When all of the water is drained to form a dry state, the PC house 50 and the foundation pile 10 may be connected to the upper bracket 80 to completely couple the PC house 50 and the foundation pile 10. have. A bracket stopper 41 may also be provided on the foundation pile 10 on which the upper bracket 80 is installed.

상기 상부 브라켓(80)이 상기 기초 파일(10)에 결합되면, 상기 하중 재하부(70)를 해체한다. 그리고, 상기 피씨 하우스(50) 내부에 철근 및 기초 콘크리트를 타설하여 교량 기초부(90)를 완성한다. When the upper bracket 80 is coupled to the foundation pile 10, the load bearing portion 70 is dismantled. Then, reinforcement and foundation concrete are poured into the PC house 50 to complete the bridge foundation 90.

상기 교량 기초부(90)가 설치된 단면 상태가 도 9에 도시되어 있다. 도시된 바와 같이, 상기 스틸 케이슨(60) 내부에도 외부 수압에 대응할 수 있는 지지대(57)가 설치된다.The cross-sectional state in which the bridge foundation 90 is installed is shown in FIG. As shown in the drawing, a support 57 is installed in the steel caisson 60 to cope with external hydraulic pressure.

상기 교량 기초부(90)가 완성되면, 상기 스틸 케이슨(60)을 해체함으로써 시공을 완료한다.When the bridge foundation 90 is completed, the construction is completed by disassembling the steel caisson 60.

본 발명에 의한 수중 피씨 하우스 케이슨 공법의 제2 실시예로서 피씨 하우스(50)와 스틸 케이슨(60)이 일체로 결합된 상태에서 수중에서 결합하는 방법에 대해 설명한다.As a second embodiment of the underwater PC house caisson method according to the present invention will be described a method of combining underwater in the state in which the PC house 50 and the steel caisson 60 are integrally coupled.

즉, 기초 파일(10) 설치 후 피씨 하우스(50)를 상기 기초 파일(10)의 하부 브라켓(40)에 안착시킬 때, 상기 피씨 하우스(50)의 상단에 분할된 스틸 케이슨(60)을 일체로 결합한 상태에서 상기 하부 브라켓(40)에 안착시킨다. 물론, 상기 스틸 케이슨(60)은 분할된 피씨 하우스(50)의 크기에 따라 분할된 상태로 구성되어야 한다. 상기 분할된 스틸 케이슨(60)은 상기 연결봉(61)을 이용하여 상호 연결될 수 있다.That is, when the PC house 50 is seated on the lower bracket 40 of the foundation file 10 after the foundation pile 10 is installed, the steel caisson 60 divided at the upper end of the PC house 50 is integrally formed. Seated on the lower bracket 40 in a coupled state. Of course, the steel caisson 60 should be configured in a divided state according to the size of the divided PC house 50. The divided steel caisson 60 may be interconnected by using the connecting rod 61.

상기 피씨 하우스(50)와 스틸 케이슨(60)이 일체로 하부 브라켓(40)에 안착되면, 분할된 피씨 하우스(50)와 스틸 케이슨(60)을 각각 연결시킨다. 그리고, 상기 스틸 케이슨(60) 상단에 하중 재하부(70)를 안착시킨 후, 피씨 하우스(50) 내부의 물을 배수시킴으로써 교량 기초부(90)를 시공할 수 있다.When the PC house 50 and the steel caisson 60 are integrally seated on the lower bracket 40, the PC house 50 and the steel caisson 60 are connected to each other. In addition, after the load loading portion 70 is seated on the upper portion of the steel caisson 60, the bridge foundation 90 may be constructed by draining the water inside the PC house 50.

본 발명에 의한 수중 피씨 하우스 케이슨 공법의 제3 실시예로서 하중재하부(70)를 사용하지 않고 상부 브라켓(80)과 하부 브라켓(40)을 설치하는 방법에 대해 설명한다.As a third embodiment of the underwater PC house caisson method according to the present invention, a method of installing the upper bracket 80 and the lower bracket 40 without using the load bearing portion 70 will be described.

본 발명에 의한 수중 피씨 하우스 케이슨 공법의 제3 실시예에 의해 설치되는 시공상태가 도 12 및 13에 도시되어 있다. 도 12는 본 발명에 의한 하부 브라 켓(40)이 기초 파일(10)에 연결되어 있는 상태를 나타낸다.12 and 13 show a construction state provided by the third embodiment of the underwater PC house caisson process according to the present invention. 12 shows a state in which the lower bracket 40 according to the present invention is connected to the foundation pile 10.

도시된 바와 같이, 기초 파일(10)에 하부 브라켓(40)을 설치하기 위하여, 각 기초 파일(10)마다 가물막이(30)를 설치한다. 상기 가물막이(30)는 하부 브라켓(40)을 설치하기 위한 하부용 가물막이(31)와, 상부 브라켓(80)을 설치하기 위한 상부용 가물막이(33)를 포함한다.As shown, in order to install the lower bracket 40 on the foundation pile 10, a temporary barrier 30 is provided for each foundation pile 10. As shown in FIG. The temporary curtain 30 includes a lower temporary curtain 31 for installing the lower bracket 40, and an upper temporary curtain 33 for installing the upper bracket 80.

상기 하부 브라켓(40)을 설치하기 위한 하부용 가물막이(31)가 도 12에 도시되어 있다. 도시된 바와 같이, 상기 하부용 가물막이(31)가 상기 기초 파일(10)과 밀접하게 연결되도록 상기 하부용 가물막이(31)의 하단부에는 하방으로 갈수록 폭이 좁아지도록 형성되는 마감부(35)가 구비된다.A lower temporary closure 31 for installing the lower bracket 40 is shown in FIG. 12. As shown in the drawing, the lower end portion 35 of the lower provisional seal 31 is formed so that the width thereof becomes narrower toward the lower portion 35 so that the lower provisional seal 31 is closely connected to the foundation pile 10. Is provided.

그리고, 상기 마감부(35)와 상기 기초 파일(10)이 연결되는 지점에는 연결 플레이트(37)가 구비되고, 상기 연결 플레이트(37)와 기초 파일(10)의 외면 사이에는 지수재(63)가 구비된다. 상기 연결 플레이트(37)는 상기 지수재(63)와 함께 상기 기초 파일(10)의 외면에 밀착됨으로써 상기 하부용 가물막이(31) 내부를 수밀상태로 유지할 수 있다.In addition, a connection plate 37 is provided at a point at which the finish part 35 and the foundation pile 10 are connected, and the index member 63 is disposed between the connection plate 37 and the outer surface of the foundation pile 10. Is provided. The connection plate 37 may be in close contact with the outer surface of the foundation pile 10 together with the index member 63 to maintain the interior of the temporary temporary sealer 31 in a watertight state.

또한, 상기 연결 플레이트(37)의 하면과 연결되는 상기 기초 파일(10)의 외면에는 상기 하부용 가물막이(31)가 하방으로 이동하지 않도록 하는 가물막이 스토퍼(39)가 구비된다.In addition, the outer surface of the foundation pile 10 connected to the lower surface of the connecting plate 37 is provided with a temporary film stopper 39 to prevent the lower temporary film 31 from moving downward.

상기 기초 파일(10)에 하부 브라켓(40)이 연결되면, 상기 하부용 가물막이(31)를 해체한 후, 아직 하부 브라켓(40)이 설치되지 않은 다른 기초 파일(10)에 하부용 가물막이(31)를 설치하여 하부 브라켓(40)을 설치한다. 이와 같은 과정을 반복하여 모든 기초 파일(10) 상단에 하부 브라켓(40)을 설치한다.When the lower bracket 40 is connected to the foundation pile 10, after disassembling the lower provisional seal 31, the lower provisional membrane is attached to another foundation pile 10 on which the lower bracket 40 is not yet installed. Install (31) to install the lower bracket (40). Repeat this process to install the lower bracket 40 on the top of all the foundation pile (10).

상기 하부 브라켓(40)이 설치되면, 상기 기초 파일(10) 상단에 피씨 하우스(50)의 분할체를 안착시킨 후, 분할된 피씨 하우스(50)를 서로 연결시킨다. 상기 피씨 하우스(50)를 연결할 때, 도 13에 도시된 바와 같이 상기 피씨 하우스(50)가 안착되는 상기 하부 브라켓(40)의 상면에는 지수재(63)를 설치한다.When the lower bracket 40 is installed, the partition of the PC house 50 is seated on the top of the foundation pile 10, and then the divided PC houses 50 are connected to each other. When the PC house 50 is connected, an index member 63 is installed on an upper surface of the lower bracket 40 on which the PC house 50 is seated, as shown in FIG. 13.

상기 피씨 하우스(50)가 연결되면, 도 13에 도시된 바와 같이 피씨 하우스(50) 내부에 상부용 가물막이(33)를 설치한다.When the PC house 50 is connected, as shown in FIG. 13, the upper temporary shield 33 is installed in the PC house 50.

도 13에 도시된 바와 같이, 상기 상부용 가물막이(33)와 피씨 하우스(50)가 접하는 지점에는 지수재(63)가 구비된다. 상기 상부용 가물막이(33)가 피씨 하우스(50) 내부에 설치되면, 상기 피씨 하우스(50) 내부를 배수하여 건식 상태를 형성한다.As shown in FIG. 13, an index member 63 is provided at a point where the upper temporary shield 33 and the PC house 50 come into contact with each other. When the upper temporary shield 33 is installed in the PC house 50, the inside of the PC house 50 is drained to form a dry state.

그리고, 상기 기초 파일(10)과 상기 피씨 하우스(50)가 접하는 지점에 상부 브라켓(80)을 설치한다. 상기 상부 브라켓(80)과 상기 피씨 하우스(50) 사이에도 지수재(63)가 설치될 수 있다. 이때, 상기 상부 브라켓(80)의 상면에 접하는 기초 파일(10)의 외면에는 상기 상부 브라켓(80)이 상방으로 이동하지 않도록 하는 브라켓 스토퍼(41)가 구비될 수 있다.In addition, the upper bracket 80 is installed at the point where the foundation pile 10 and the PC house 50 are in contact with each other. An index member 63 may be installed between the upper bracket 80 and the PC house 50. At this time, the outer surface of the foundation pile 10 in contact with the upper surface of the upper bracket 80 may be provided with a bracket stopper 41 to prevent the upper bracket 80 from moving upward.

상기 상부 브라켓(80)이 상기 기초 파일(10)에 설치되면, 상기 상부 브라켓(80)과 상기 기초 파일(10)과 상기 하부 브라켓(40)이 연결되는 지점에 연결 콘크리트(83)를 타설하여 연결부분을 일체화시킨다. When the upper bracket 80 is installed on the foundation pile 10, the connection concrete 83 is poured at a point where the upper bracket 80, the foundation pile 10, and the lower bracket 40 are connected to each other. Integrate the connection part.

상기 상부 브라켓(80)이 설치되면, 상기 상부용 가물막이(33)를 해체하고, 상기 피씨 하우스(50) 상면에 스틸 케이슨(60)을 연결시킨다. 그리고, 스틸 케이슨(60) 내부를 배수하여 건식 상태를 형성한 후, 교량 기초부(90)를 설치하고 스틸 케이슨(60)을 해체함으로써 시공을 완료한다.When the upper bracket 80 is installed, the upper clamshell 33 is dismantled and the steel caisson 60 is connected to the upper surface of the PC house 50. Then, after draining the inside of the steel caisson 60 to form a dry state, installation is completed by installing the bridge foundation 90 and dismantling the steel caisson 60.

이와 같이 상부용 가물막이(33)와 하부용 가물막이(31)를 사용하는 경우, 상기 스틸 케이슨(60)이 연결된 피씨 하우스(50)의 부양을 방지하기 위한 하중 재하부(70)를 설치하지 않아도 된다.When using the upper clamshell 33 and the lower clamshell 31 in this way, do not install the load loading portion 70 to prevent the support of the PC house 50 is connected to the steel caisson 60 You don't have to.

이와 같은 본 발명의 기본적인 기술적 사상의 범주에서, 당업계의 통상의 지식을 가진 자에게 있어서는 다른 많은 변형이 가능함은 물론이고, 본 발명의 권리범위는 후술하는 특허청구범위에 기초하여 해석해야 할 것이다.In the scope of the basic technical spirit of the present invention, many modifications are possible to those skilled in the art, and the scope of the present invention should be interpreted based on the claims below. .

위에서 상세히 설명한 바와 같은 본 발명에 의한 수중 피씨 하우스 케이슨 공법에 의하면 다음과 같은 이점이 있다. Underwater PC house caisson method according to the present invention as described in detail above has the following advantages.

수위변화가 심하거나 수중에 피씨 하우스가 설치되는 경우에도 피씨 하우스의 상단에 설치되는 스틸 케이슨에 의해 피씨 하우스 내부 작업을 건식으로 실시할 수 있으므로 작업성이 향상되고 시공비를 줄일 수 있는 이점이 있다.Even if the water level is severe or the PC house is installed underwater, the steel caisson installed at the top of the PC house can be carried out dry work inside the PC house has the advantage of improved workability and construction costs.

그리고, 스틸 케이슨 상부에 안착되는 하중 재하부에 의해 피씨 하우스가 부양하는 것을 방지할 수 있고, 하중 재하부가 없이 상부용 가물막이와 하부용 가물막이를 이용하여 상부 브라켓 및 하부 브라켓을 설치할 수 있으므로 시공편의성이 향상되는 이점이 있다.In addition, the PC house can be prevented from supporting by the load loading portion seated on the upper part of the steel caisson, and the upper bracket and the lower bracket may be installed using the upper cladding block and the lower cladding block without the load loading part. There is an advantage that the convenience is improved.

도 1은 본 발명에 의한 수중 피씨 하우스 케이슨 공법의 기초 파일을 시공하는 단계를 보인 시공단면도.1 is a cross-sectional view showing a step of constructing the foundation pile of the underwater PC house caisson method according to the present invention.

도 2는 본 발명에 의한 수중 피씨 하우스 케이슨 공법의 가물막이를 시공하는 단계를 보인 시공단면도.Figure 2 is a construction cross-sectional view showing a step of constructing a cloak of the underwater PC house caisson method according to the present invention.

도 3은 본 발명에 의한 수중 피씨 하우스 케이슨 공법의 기초파일 상단에 하부브라켓을 연결하는 단계를 보인 시공단면도.Figure 3 is a cross-sectional view showing the step of connecting the lower bracket to the top of the foundation pile of the underwater PC house caisson method according to the present invention.

도 4는 본 발명에 의한 수중 피씨 하우스 케이슨 공법의 분할된 피씨 하우스를 연결하는 단계를 보인 시공단면도.Figure 4 is a cross-sectional view showing the step of connecting the divided PC house of the underwater PC house caisson method of the present invention.

도 5는 본 발명에 의한 수중 피씨 하우스 케이슨 공법의 피씨 하우스의 연결상태를 보인 평면도.Figure 5 is a plan view showing a connection state of the PC house of the underwater PC house caisson method according to the present invention.

도 6은 도 4의 P 부분을 확대한 시공단면도.6 is a cross-sectional view of an enlarged portion P of FIG.

도 7은 본 발명에 의한 수중 피씨 하우스 케이슨 공법의 스틸 케이슨과 하중재하부가 설치된 상태를 보인 시공단면도.7 is a construction sectional view showing a state in which the steel caisson and the load-bearing portion of the underwater PC house caisson method according to the present invention is installed.

도 8은 본 발명에 의한 수중 피씨 하우스 케이슨 공법의 교량 기초부를 시공하는 단계를 보인 시공단면도.8 is a cross-sectional view showing the step of constructing the bridge foundation of the underwater PC house caisson method according to the present invention.

도 9은 본 발명에 의한 수중 피씨 하우스 케이슨 공법의 교량 기초부를 시공하는 단계를 보인 시공단면도.9 is a construction sectional view showing the step of constructing the bridge foundation of the underwater PC house caisson method according to the present invention.

도 10는 도 8의 A 부분을 확대한 시공단면도.FIG. 10 is a cross-sectional view of an enlarged portion A of FIG. 8;

도 11은 본 발명에 의한 수중 피씨 하우스 케이슨 공법의 스틸 케이슨이 해 체된 교량 기초부의 시공상태를 보인 시공단면도.11 is a cross-sectional view showing the construction state of the bridge foundation is dismantled steel caisson of the underwater PC house caisson method according to the present invention.

도 12는 본 발명에 의한 수중 피씨 하우스 케이슨 공법의 제3 실시예에 따른 하부 브라켓의 연결상태를 보인 시공단면도.12 is a cross-sectional view showing a connection state of the lower bracket according to the third embodiment of the underwater PC house caisson method according to the present invention.

도 13은 본 발명에 의한 수중 피씨 하우스 케이슨 공법의 제3 실시예에 따른 상부 브라켓의 연결상태를 보인 시공단면도.Figure 13 is a cross-sectional view showing a connection state of the upper bracket according to the third embodiment of the underwater PC house caisson method of the present invention.

* 도면의 주요 부분에 대한 설명 *Description of the main parts of the drawing

10 : 기초 파일 30 : 가물막이10: foundation file 30: cloak

31 : 상부용 가물막이 33 : 하부용 가물막이31: upper temporary film 33: lower temporary film

35 : 마감부 37 : 연결 플레이트35: finish portion 37: connecting plate

39 : 가물막이 스토퍼 40 : 하부 브라켓39: stopper stopper 40: lower bracket

41 : 브라켓 스토퍼 50 : 피씨 하우스41: Bracket Stopper 50: PC House

51 : 연결관 59 : 연결부51: connector 59: connector

60 : 스틸 케이슨 61 : 연결봉 60: steel caisson 61: connecting rod

63 : 지수재 70 : 하중 재하부 63: index material 70: load bearing

80 : 상부 브라켓 83 : 연결 콘크리트80: upper bracket 83: connection concrete

Claims (24)

하상 저면에 기초 파일을 근입하는 기초 파일 설치단계;A basic file installation step of incorporating the foundation file on the bottom surface of the lower bed; 상기 기초 파일 둘레에 가물막이를 설치하고 내부의 물을 배수시키는 가물막이 설치단계;Installing a temporary curtain around the foundation pile and installing the temporary curtain to drain the water therein; 상기 기초 파일에 하부 브라켓을 설치하고 상기 가물막이를 해체하는 하부 브라켓 설치단계;A lower bracket installation step of installing a lower bracket on the foundation pile and dismantling the temporary barrier; 상기 하부 브라켓에 피씨 하우스를 안착시키는 피씨 하우스 설치단계;A PC house installation step of seating the PC house on the lower bracket; 상기 피씨 하우스 상단에 스틸 케이슨을 설치하는 스틸 케이슨 설치단계;Steel caisson installation step of installing a steel caisson on the top of the PC house; 상기 스틸 케이슨 상단에 하중 재하부를 설치하는 하중 재하부 설치단계;A load loading part installing step of installing a load loading part on an upper portion of the steel caisson; 상기 피씨 하우스 내부를 배수시키고 상부 브라켓을 설치하는 상부 브라켓 설치단계;An upper bracket installation step of draining the inside of the PC house and installing an upper bracket; 상기 하중 재하부를 해체하고, 상기 피씨 하우스에 교량 기초부를 시공하는 교량 기초부 시공단계;및A bridge foundation construction step of dismantling the load bearing part and constructing a bridge foundation in the PC house; and 상기 스틸 케이슨을 해체하는 스틸 케이슨 해체단계를 포함하는Comprising a steel caisson disassembly step of dismantling the steel caisson 수중 피씨 하우스 케이슨 공법.Underwater PC house caisson method. 제1항에 있어서,The method of claim 1, 상기 피씨 하우스 설치단계는The PC house installation step 다수개로 분할된 피씨 하우스를 서로 연결하는 상기 피씨 하우스 연결단계를 포함하는Comprising the PC house connection step of connecting the PC house divided into a plurality 수중 피씨 하우스 케이슨 공법.Underwater PC house caisson method. 제2항에 있어서,The method of claim 2, 상기 피씨 하우스 연결단계는The PC house connection step 다수개의 피씨 하우스 내부에 구비되는 연결선을 프리텐션하여 분할된 피씨 하우스를 연결시키는 프리텐션 단계를 포함하는A pretensioning step of connecting the divided PC houses by pretensioning connection lines provided in the plurality of PC houses; 수중 피씨 하우스 케이슨 공법.Underwater PC house caisson method. 제2항에 있어서,The method of claim 2, 상기 피씨 하우스 연결단계는The PC house connection step 분할된 상기 피씨 하우스의 연결지점에 구비된 연결부 사이에 지수재를 설치하고, 상기 연결지점에 콘크리트를 타설하는The installation of the water repellent material between the connection portion provided in the connection point of the divided PC house, and placing the concrete in the connection point 수중 피씨 하우스 케이슨 공법.Underwater PC house caisson method. 제2항에 있어서,The method of claim 2, 상기 피씨 하우스 연결단계는The PC house connection step 상기 피씨 하우스 내부에 지지대를 설치하는 지지대 설치단계를 포함하는Comprising a support installation step of installing a support in the PC house 수중 피씨 하우스 케이슨 공법.Underwater PC house caisson method. 제2항에 있어서,The method of claim 2, 상기 가물막이 설치단계는The faucet installation step 상기 분할된 피씨 하우스의 면적에 대응되는 다수개의 기초 파일 둘레에 상기 가물막이를 설치하고, 상기 하부 브라켓이 설치되면 다시 새로운 다수개의 기초 파일 둘레에 상기 가물막이를 설치하는 것을 반복하는Installing the clampers around a plurality of foundation piles corresponding to the area of the divided PC house, and if the lower bracket is installed, repeating installing the clampers around a plurality of new foundation piles again. 수중 피씨 하우스 케이슨 공법.Underwater PC house caisson method. 제6항에 있어서,The method of claim 6, 상기 하부 브라켓 설치단계는The lower bracket installation step 반복적으로 설치되는 상기 가물막이에 대응하여 상기 하부 브라켓을 설치하는To install the lower bracket in response to the temporary curtain is installed repeatedly 수중 피씨 하우스 케이슨 공법.Underwater PC house caisson method. 제1항에 있어서,The method of claim 1, 상기 스틸 케이슨 설치단계는The steel caisson installation step 유압잭을 이용하여 연결봉을 인장시켜 상기 피씨 하우스와 상기 스틸 케이슨을 연결시키는 단계를 포함하는Tensioning the connecting rod using a hydraulic jack to connect the PC house to the steel caisson; 수중 피씨 하우스 케이슨 공법.Underwater PC house caisson method. 제1항에 있어서,The method of claim 1, 상기 가물막이 설치단계는The faucet installation step 상기 가물막이가 안착될 하상 저면을 준설하여 안착홈을 형성하는 안착홈 형성단계를 포함하는And a seating groove forming step of forming a seating groove by dredging the bottom surface of the bottom on which the temporary barrier is to be seated. 수중 피씨 하우스 케이슨 공법.Underwater PC house caisson method. 하상 저면에 기초 파일을 근입하는 기초 파일 설치단계;A basic file installation step of incorporating the foundation file on the bottom surface of the lower bed; 상기 기초 파일 둘레에 가물막이를 설치하고 내부의 물을 배수시키는 가물막이 설치단계;Installing a temporary curtain around the foundation pile and installing the temporary curtain to drain the water therein; 상기 기초 파일에 하부 브라켓을 설치하고 상기 가물막이를 해체하는 하부 브라켓 설치단계;A lower bracket installation step of installing a lower bracket on the foundation pile and dismantling the temporary barrier; 상기 하부 브라켓에 분할된 스틸 케이슨이 연결된 분할된 피씨 하우스를 각 각 안착시키는 피씨 하우스 설치단계;PC house installation step of seating each of the divided PC house is connected to the steel caisson divided in the lower bracket; 상기 분할된 스틸 케이슨과 상기 분할된 피씨 하우스를 각각 연결시키는 조립단계An assembling step of connecting the divided steel caisson and the divided PC house, respectively 상기 스틸 케이슨 상단에 하중 재하부를 설치하는 하중 재하부 설치단계;A load loading part installing step of installing a load loading part on an upper portion of the steel caisson; 상기 피씨 하우스 내부를 배수시키고 상부 브라켓을 설치하는 상부 브라켓 설치단계;An upper bracket installation step of draining the inside of the PC house and installing an upper bracket; 상기 하중 재하부를 해체하고, 상기 피씨 하우스에 교량 기초부를 시공하는 교량 기초부 시공단계;및A bridge foundation construction step of dismantling the load bearing part and constructing a bridge foundation in the PC house; and 상기 스틸 케이슨을 해체하는 스틸 케이슨 해체단계를 포함하는Comprising a steel caisson disassembly step of dismantling the steel caisson 수중 피씨 하우스 케이슨 공법.Underwater PC house caisson method. 제10항에 있어서,The method of claim 10, 상기 조립단계는The assembly step 다수개의 피씨 하우스 내부에 구비되는 연결선을 프리텐션하여 분할된 피씨 하우스를 연결시키고,Pre-tension the connection lines provided in the plurality of PC houses to connect the divided PC house, 유압잭을 이용하여 연결봉을 인장시켜 분할된 스틸 케이슨을 연결시키는The hydraulic jack is used to tension the connecting rod to connect the divided steel caissons. 수중 피씨 하우스 케이슨 공법.Underwater PC house caisson method. 제10항에 있어서,The method of claim 10, 상기 조립단계는The assembly step 상기 분할된 피씨 하우스의 접합면과 상기 분할된 스틸 케이슨의 접합면에 각각 지수재를 설치하는To install an index member on the joint surface of the divided PC house and the joint surface of the divided steel caisson, respectively 수중 피씨 하우스 케이슨 공법.Underwater PC house caisson method. 제10항에 있어서,The method of claim 10, 상기 조립단계는The assembly step 상기 피씨 하우스 내부에 지지대를 설치하는 지지대 설치단계를 포함하는Comprising a support installation step of installing a support in the PC house 수중 피씨 하우스 케이슨 공법.Underwater PC house caisson method. 하상 저면에 기초 파일을 근입하는 기초 파일 설치단계;A basic file installation step of incorporating the foundation file on the bottom surface of the lower bed; 상기 기초 파일 둘레에 하부용 가물막이를 설치하고 내부의 물을 배수시키는 하부용 가물막이 설치단계;Installing a lower temporary curtain around the foundation pile and installing the lower temporary curtain for draining the water inside; 상기 기초 파일에 하부 브라켓을 설치하고 상기 하부용 가물막이를 해체하는 하부 브라켓 설치단계;A lower bracket installation step of installing a lower bracket on the foundation pile and dismantling the lower temporary closure; 상기 하부 브라켓에 피씨 하우스를 안착시키는 피씨 하우스 설치단계;A PC house installation step of seating the PC house on the lower bracket; 상기 피씨 하우스 내부의 기초 파일에 상부용 가물막이를 설치하고 내부의 물을 배수시키는 상부용 가물막이 설치단계;Installing the upper temporary curtain on the foundation pile inside the PC house and installing the upper temporary curtain to drain the water inside; 상기 상부용 가물막이 내부의 기초 파일에 상부 브라켓을 설치하는 상부 브라켓 설치단계;An upper bracket installation step of installing an upper bracket on the foundation pile inside the upper temporary shield; 상기 상부용 가물막이를 해체하고, 상기 피씨 하우스 상단에 스틸 케이슨을 설치하는 스틸 케이슨 설치단계;A steel caisson installation step of dismantling the upper clamshell and installing a steel caisson on the top of the PC house; 상기 피씨 하우스를 배수하여 교량 기초부를 시공하는 교량 기초부 시공단계;및Bridge foundation construction step of constructing the bridge foundation by draining the PC house; And 상기 스틸 케이슨을 해체하는 스틸 케이슨 해체단계를 포함하는Comprising a steel caisson disassembly step of dismantling the steel caisson 수중 피씨 하우스 케이슨 공법.Underwater PC house caisson method. 제14항에 있어서,The method of claim 14, 상기 하부용 가물막이와 상기 상부용 가물막이에 지수재를 설치하는 단계를 포함하는And installing a water repellent material on the lower temporary curtain and the upper temporary curtain. 수중 피씨 하우스 케이슨 공법.Underwater PC house caisson method. 제14항에 있어서,The method of claim 14, 상기 상부 브라켓 및 상기 하부 브라켓에는 브라켓 스토퍼를 설치하는 단계를 포함하는And installing a bracket stopper on the upper bracket and the lower bracket. 수중 피씨 하우스 케이슨 공법.Underwater PC house caisson method. 제16항에 있어서,The method of claim 16, 상기 상부 브라켓 및 상기 하부 브라켓이 상기 피씨 하우스와 접하는 지점에 지수재를 설치하는 단계를 포함하는And installing an index member at a point where the upper bracket and the lower bracket contact the PC house. 수중 피씨 하우스 케이슨 공법.Underwater PC house caisson method. 제14항에 있어서,The method of claim 14, 상기 상부 브라켓과 상기 하부 브라켓과 상기 기초 파일이 연결되는 지점에는 연결 콘크리트를 타설하는 단계를 포함하는At the point where the upper bracket and the lower bracket and the base pile is connected, the step of placing a connection concrete; 수중 피씨 하우스 케이슨 공법.Underwater PC house caisson method. 제14항에 있어서,The method of claim 14, 상기 하부 브라켓 설치단계는The lower bracket installation step 상기 하부용 가물막이의 마감부에 연결 플레이트를 설치하고,A connection plate is installed on the finishing part of the lower temporary closure; 상기 연결 플레이트와 상기 기초 파일 사이에 지수재를 설치하여 일체로 고정시키고,An index member is installed between the connecting plate and the foundation pile to be fixed integrally, 상기 기초 파일과 상기 하부용 가물막이가 접하는 부분에 가물막이 스토퍼를 설치하는 단계를 포함하는And installing a temporary stopper at a portion where the foundation pile and the lower temporary stopper come into contact with each other. 수중 피씨 하우스 케이슨 공법.Underwater PC house caisson method. 제1항 내지 제19항 중 어느 한 항에 의한 공법에 의해 시공되는 Constructed by the construction method according to any one of claims 1 to 19. 피씨 하우스 교량 구조물.PC House Bridge Structures. 피씨 하우스의 상단에 스틸 케이슨을 설치하여 교량 구조물을 설치하는 제1항 내지 제19항 중 어느 한 항에 의한 공법에 있어서,The method according to any one of claims 1 to 19, in which a steel caisson is installed on an upper end of the PC house to install a bridge structure, 상기 피씨 하우스와 상기 스틸 케이슨은 연결봉 및 연결너트에 의해 연결되고,The PC house and the steel caisson are connected by a connecting rod and a connecting nut, 상기 분할된 피씨 하우스는 연결부에 의해 연결되고,The divided PC house is connected by a connecting portion, 상기 피씨 하우스와 상기 교각기초는 상부 브라켓, 하부 브라켓 및 상기 상부 브라켓과 상기 하부 브라켓 사이에 타설되는 연결 콘크리트에 의해 연결되는The PC house and the bridge foundation are connected by an upper bracket, a lower bracket, and connecting concrete placed between the upper bracket and the lower bracket. 피씨 하우스 및 케이슨의 연결구조.Connection structure of PC house and caisson. 제21항에 있어서,The method of claim 21, 상기 피씨 하우스와 상기 스틸 케이슨은The PC house and the steel caisson 상기 피씨 하우스의 측면에 구비된 연결너트에 의해 연결봉의 일단이 연결되고, 상기 스틸 하우스에 상기 연결봉이 연장되어 상기 연결봉을 인장시킴으로써 연결되는One end of the connecting rod is connected by a connecting nut provided on the side of the PC house, and the connecting rod is extended to the steel house to be connected by tensioning the connecting rod. 피씨 하우스 및 케이슨의 연결구조.Connection structure of PC house and caisson. 제21항에 있어서,The method of claim 21, 상기 분할된 피씨 하우스는The divided PC house 상기 피씨 하우스의 하면으로부터 하방으로 더 돌출된 연결부의 돌출부 사이에 지수재가 삽입되고,The water repellent material is inserted between the protrusions of the connection part which protrudes further downward from the lower surface of the PC house, 상기 연결부의 상면에는 초속경 콘크리트가 타설되어 연결되는The upper surface of the connecting portion is cemented super hard concrete is connected 피씨 하우스 및 케이슨의 연결구조.Connection structure of PC house and caisson. 제21항에 있어서,The method of claim 21, 상기 피씨 하우스와 상기 스틸 케이슨 사이에는 지수재가 구비되는An index member is provided between the PC house and the steel caisson. 피씨 하우스 및 케이슨의 연결구조.Connection structure of PC house and caisson.
KR1020090094133A 2009-08-07 2009-10-01 A method of constructing precast concrete house under water using caisson Active KR100937740B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR1020090072870 2009-08-07
KR20090072870 2009-08-07

Publications (1)

Publication Number Publication Date
KR100937740B1 true KR100937740B1 (en) 2010-01-20

Family

ID=41810027

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090094133A Active KR100937740B1 (en) 2009-08-07 2009-10-01 A method of constructing precast concrete house under water using caisson

Country Status (1)

Country Link
KR (1) KR100937740B1 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101025892B1 (en) 2010-10-27 2011-03-30 강명석 Concrete steel house
KR101117927B1 (en) * 2011-10-14 2012-02-24 현대건설주식회사 Offshore Structure Construction Method
KR101381276B1 (en) * 2012-08-03 2014-04-04 삼보이엔씨 주식회사 Construction method of split type pc house and split type pc house
KR20160060901A (en) * 2014-11-20 2016-05-31 삼성물산 주식회사 Construction and design method for pile-cap with precast system on water condition
KR20180065510A (en) * 2016-12-08 2018-06-18 오석환 Method of constructing base of bridge pier in water and structure thereof
KR102064969B1 (en) * 2017-10-30 2020-01-10 대림산업 주식회사 Water Proof Seal Structure between PC House and Pile, and Constructing Method thereof
KR102123558B1 (en) * 2019-12-16 2020-06-16 이진길 Tank allowing dry work for underwater framework for bridge construction and method of construction using that

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04174132A (en) * 1990-11-05 1992-06-22 Taisei Corp How to rigidly connect the box and support piles
KR100738488B1 (en) 2007-04-02 2007-07-12 정석으뜸기술(주) Bridge foundation caisson installation structure using precast concrete block
KR100766888B1 (en) 2006-04-15 2007-10-18 (주)스틸엔콘크리트 Prefabricated bridge and construction method using pier coping part by connecting pile column with pillar connecting member
KR100778252B1 (en) 2006-05-16 2007-11-22 (주)스틸엔콘크리트 Prefabricated slab bridge with H-girder installed on the connecting support member inserted on the lattice pile pillar and construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04174132A (en) * 1990-11-05 1992-06-22 Taisei Corp How to rigidly connect the box and support piles
KR100766888B1 (en) 2006-04-15 2007-10-18 (주)스틸엔콘크리트 Prefabricated bridge and construction method using pier coping part by connecting pile column with pillar connecting member
KR100778252B1 (en) 2006-05-16 2007-11-22 (주)스틸엔콘크리트 Prefabricated slab bridge with H-girder installed on the connecting support member inserted on the lattice pile pillar and construction method
KR100738488B1 (en) 2007-04-02 2007-07-12 정석으뜸기술(주) Bridge foundation caisson installation structure using precast concrete block

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101025892B1 (en) 2010-10-27 2011-03-30 강명석 Concrete steel house
KR101117927B1 (en) * 2011-10-14 2012-02-24 현대건설주식회사 Offshore Structure Construction Method
KR101381276B1 (en) * 2012-08-03 2014-04-04 삼보이엔씨 주식회사 Construction method of split type pc house and split type pc house
KR20160060901A (en) * 2014-11-20 2016-05-31 삼성물산 주식회사 Construction and design method for pile-cap with precast system on water condition
KR101684879B1 (en) * 2014-11-20 2016-12-12 삼성물산 주식회사 Construction and design method for pile-cap with precast system on water condition
KR20180065510A (en) * 2016-12-08 2018-06-18 오석환 Method of constructing base of bridge pier in water and structure thereof
KR101955579B1 (en) * 2016-12-08 2019-03-07 오석환 Method of constructing base of bridge pier in water and structure thereof
KR102064969B1 (en) * 2017-10-30 2020-01-10 대림산업 주식회사 Water Proof Seal Structure between PC House and Pile, and Constructing Method thereof
KR102123558B1 (en) * 2019-12-16 2020-06-16 이진길 Tank allowing dry work for underwater framework for bridge construction and method of construction using that

Similar Documents

Publication Publication Date Title
KR100937740B1 (en) A method of constructing precast concrete house under water using caisson
JP6010070B2 (en) Temporary closing method for existing underwater structures
JP4698491B2 (en) Temporary closing method and structure of underwater structure
KR102011321B1 (en) Construction method of foundation using rectangular pipe and its foundation
JP4528652B2 (en) Temporary closing method for underwater structures and temporary closing structure
KR100738488B1 (en) Bridge foundation caisson installation structure using precast concrete block
KR102162125B1 (en) Pile and Coping for Bridge Construction
CN100535264C (en) Steel boxed cofferdam and recovery method thereof
JP5189431B2 (en) Multi-span continuous concrete bridge
KR20070090733A (en) Watertight open caisson assembly and cast-in-place concrete foundation method using the same
KR100383409B1 (en) Construction Method of Direct Foundation for using Caisson
KR100704737B1 (en) Precast Submerged Pier Structure
KR101176937B1 (en) Underground reclamation type water storage tank having a assembling structure and its constructing method
KR20040039271A (en) Sugar barrier construction for new foundation of steel well and reinforcement of foundation.
KR100714179B1 (en) Construction method of well bucket by self-weight reduction method and the well bucket
JP6684459B1 (en) Reinforcement beam of structure, reinforcement method, and structure
KR100418268B1 (en) Well form bucket of division style for the base operation of pier and it's operation method
JP2001348888A (en) Method and device for constructing underwater foundation structure
JP5562715B2 (en) Underwater foundation construction method and outer shell structure
JP7616945B2 (en) Flat slab construction
JP2005139865A (en) Underwater temporary cutoff facility and its construction method
KR200404677Y1 (en) Concrete Well Construction Method Using Weight Reducing Method and Concrete Well Thereof
JP4475116B2 (en) Vertical shaft structure and its construction method
JP6960870B2 (en) How to build a pier
KR101381276B1 (en) Construction method of split type pc house and split type pc house

Legal Events

Date Code Title Description
A201 Request for examination
PA0109 Patent application

Patent event code: PA01091R01D

Comment text: Patent Application

Patent event date: 20091001

PA0201 Request for examination
A302 Request for accelerated examination
PA0302 Request for accelerated examination

Patent event date: 20091014

Patent event code: PA03022R01D

Comment text: Request for Accelerated Examination

Patent event date: 20091001

Patent event code: PA03021R01I

Comment text: Patent Application

E701 Decision to grant or registration of patent right
PE0701 Decision of registration

Patent event code: PE07011S01D

Comment text: Decision to Grant Registration

Patent event date: 20100106

GRNT Written decision to grant
PR0701 Registration of establishment

Comment text: Registration of Establishment

Patent event date: 20100112

Patent event code: PR07011E01D

PR1002 Payment of registration fee

Payment date: 20100113

End annual number: 3

Start annual number: 1

PG1601 Publication of registration
FPAY Annual fee payment

Payment date: 20130107

Year of fee payment: 4

PR1001 Payment of annual fee

Payment date: 20130107

Start annual number: 4

End annual number: 4

FPAY Annual fee payment

Payment date: 20131227

Year of fee payment: 5

PR1001 Payment of annual fee

Payment date: 20131227

Start annual number: 5

End annual number: 5

FPAY Annual fee payment

Payment date: 20150105

Year of fee payment: 6

PR1001 Payment of annual fee

Payment date: 20150105

Start annual number: 6

End annual number: 6

FPAY Annual fee payment

Payment date: 20160104

Year of fee payment: 7

PR1001 Payment of annual fee

Payment date: 20160104

Start annual number: 7

End annual number: 7

FPAY Annual fee payment

Payment date: 20170109

Year of fee payment: 8

PR1001 Payment of annual fee

Payment date: 20170109

Start annual number: 8

End annual number: 8

FPAY Annual fee payment

Payment date: 20180109

Year of fee payment: 9

PR1001 Payment of annual fee

Payment date: 20180109

Start annual number: 9

End annual number: 9

FPAY Annual fee payment

Payment date: 20190110

Year of fee payment: 10

PR1001 Payment of annual fee

Payment date: 20190110

Start annual number: 10

End annual number: 10

PR1001 Payment of annual fee

Payment date: 20211130

Start annual number: 13

End annual number: 13

PR1001 Payment of annual fee

Payment date: 20221110

Start annual number: 14

End annual number: 14

PR1001 Payment of annual fee

Payment date: 20241111

Start annual number: 16

End annual number: 16