KR100946879B1 - Connection for Steel Pile Head, Connection Structure and Method of Pile and Precast Concrete Pier Structure - Google Patents

Connection for Steel Pile Head, Connection Structure and Method of Pile and Precast Concrete Pier Structure Download PDF

Info

Publication number
KR100946879B1
KR100946879B1 KR1020090107526A KR20090107526A KR100946879B1 KR 100946879 B1 KR100946879 B1 KR 100946879B1 KR 1020090107526 A KR1020090107526 A KR 1020090107526A KR 20090107526 A KR20090107526 A KR 20090107526A KR 100946879 B1 KR100946879 B1 KR 100946879B1
Authority
KR
South Korea
Prior art keywords
assembly
support member
pile
concrete pier
steel pipe
Prior art date
Application number
KR1020090107526A
Other languages
Korean (ko)
Other versions
KR20090125233A (en
Inventor
장정환
심창수
이세호
Original Assignee
장정환
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 장정환 filed Critical 장정환
Priority to KR1020090107526A priority Critical patent/KR100946879B1/en
Publication of KR20090125233A publication Critical patent/KR20090125233A/en
Application granted granted Critical
Publication of KR100946879B1 publication Critical patent/KR100946879B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/28Stressing the soil or the foundation structure while forming foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Abstract

본 발명은 급속 시공이 요구되는 현장 상황에 맞추어 좁은 작업 공간에서도 짧은 기간 내에 설치될 수 있도록 콘크리트 교각 구조물을 프리캐스트 방식으로 사전 제작하고, 프리캐스트 콘크리트 교각 구조물이 현장으로 옮겨져 말뚝에 바로 조립되어 일체로 연결되도록 함으로써, 교통체증 유발방지 및 통행의 불편함을 최소화하고, 아울러 말뚝 두부가 보강되어 안정성이 한층 강화되도록 한 새로운 형태의 말뚝 두부 연결용 조립체, 이를 이용한 말뚝과 프리캐스트 콘크리트 교각 구조물의 연결구조 및 그 연결시공 방법에 관한 것이다. The present invention pre-fabricated concrete pier structure in a precast method to be installed in a narrow working space in a short period in accordance with the site situation that requires rapid construction, the precast concrete pier structure is moved to the site assembled directly on the pile To prevent traffic jams and to minimize traffic inconveniences, and to reinforce the pile head to further strengthen the stability of the pile head connection assembly, and the connection between the pile and the precast concrete pier structure using the same. It relates to a structure and a connection construction method thereof.

말뚝, 교각, 교량, 연결, 프리캐스트, 콘크리트, 구조물, 시공, 조립 Pile, Pier, Bridges, Connection, Precast, Concrete, Structures, Construction, Assembly

Description

강관 말뚝과 프리캐스트 콘크리트 교각 구조물의 연결용 조립체, 이를 이용한 강관 말뚝과 프리캐스트 콘크리트 교각 구조물의 연결구조 및 그 연결시공방법{Connection for Steel Pile Head, Connection Structure and Method of Pile and Precast Concrete Pier Structure}Assembly for connection of steel pipe pile and precast concrete pier structure, connection structure of steel pipe pile and precast concrete pier structure using the same and connection construction method

본 발명은 강관 말뚝과 프리캐스트 콘크리트 교각 구조물의 연결용 조립체, 이를 이용한 강관 말뚝과 프리캐스트 콘크리트 교각 구조물의 연결구조 및 그 연결시공방법에 관한 것으로서, 구체적으로는 급속 시공이 요구되는 현장 상황에 맞추어 좁은 작업 공간 내에서도 짧은 기간 내에 설치될 수 있도록 콘크리트 교각 구조물을 프리캐스트 방식으로 사전 제작하고, 그 콘크리트 교각 구조물이 현장으로 옮겨져 말뚝에 바로 조립 연결되도록 함으로써, 급속시공이 가능함은 물론, 말뚝 두부가 보강될 수 있도록 한 것이다.The present invention relates to an assembly for connecting a steel pipe pile and a precast concrete pier structure, a connection structure of a steel pipe pile and a precast concrete pier structure using the same, and a connection construction method thereof, specifically, to a site situation requiring rapid construction. Precast concrete piers can be prefabricated so that they can be installed within a short period of time even in a narrow work space, and the concrete piers can be transported to the site and assembled directly to the pile, enabling rapid construction and reinforcing the pile head. It would be possible.

일반적으로 교량 공사에 있어서, 콘크리트 구조물인 교각이 견고하게 설치될 수 있도록 통상 그 기초로서 지반에 말뚝이 시공된다. In general, in a bridge construction, piles are usually constructed on the ground as a foundation so that a pier, which is a concrete structure, can be firmly installed.

상기 말뚝은 여러 시공 타입이 있으나, 그 중 가장 많이 시공되는 타입으로는 현장 타설 말뚝, 매입 말뚝, 항타 말뚝이 있다.The pile has a number of construction types, but the most of the construction type is a cast-in-place pile, embedded pile, driving pile.

상기 현장 타설 말뚝은, 지반의 표면에서부터 굴착하여 깊이를 가지는 인입공을 형성하고, 그 인입공에 철근을 역어 만든 철근망을 삽입한 후 콘크리트로 채워 넣어 타설 하는 방식으로 시공된다.The site-pouring pile is excavated from the surface of the ground to form an inlet hole having a depth, the reinforcing bar made by reinforcing steel bars into the inlet hole is constructed by filling with concrete.

상기 매입 말뚝은, 지반의 표면에서부터 지지층까지 굴착하여 인입공을 형성하고, 그 인입공에 시멘트 밀크를 주입 후 강관을 삽입시켜 경타 하고, 콘크리트로 채워 넣어 타설 하는 방식으로 시공된다.The buried pile is excavated from the surface of the ground to the support layer to form a hole, and after the cement milk is injected into the hole, the steel pipe is inserted and struck, it is constructed by filling with concrete.

상기 항타 말뚝은, 지반의 표면에서부터 강관 혹은 또는 PHC말뚝을 항타 장비로 강타하여 지반의 지지층까지 도달하게 하는 방식으로 시공된다.The driving pile is constructed in such a way that the steel pipe or the PHC pile is hit by the driving equipment to reach the supporting layer of the ground from the surface of the ground.

그런데, 교량 공사에 있어서, 교각과 같은 콘크리트 구조물은 통상 지반에 설치되는 말뚝을 그 기초로 하여 그 상부에 현장 타설 방식으로 시공하고 있는 실정이다. 이러한 현장 타설은 거푸집을 설치하였다가 콘크리트 양생 후 해체함으로써 시공이 완료되는데, 이와 같이 거푸집을 이용하여 콘크리트 교각 구조물을 시공하려면 거푸집 설치 및 해체 등을 위한 각종 건설장비가 투입 및 사용되어야 하므로 작업공간과 작업부지를 많이 차지하게 되고, 또한 콘크리트의 양생을 위하여 절대적인 시간이 필요하므로 긴 시공기간과 함께 경제적으로도 효율적이지 못한 단점이 있다.By the way, in the bridge construction, concrete structures such as bridges are usually constructed on the basis of piles installed in the ground by the site casting method. The construction of the site is completed by installing the formwork and dismantling it after curing the concrete.In order to construct the concrete pier structure using the formwork, various construction equipment for formwork installation and dismantling must be put and used, It takes up a lot of work site, and also requires an absolute time for curing concrete has a disadvantage in that it is not economically efficient with a long construction period.

예컨대, 도심지 구간에서 고가도로, 경전철 등을 위한 교량이 시공될 경우, 지반에 설치되는 말뚝과 교각은 차량이 통행하는 도로에 설치되는 것이 일반적이므 로, 통상 통행 차량을 우회시키거나 차선 수를 대폭 줄여 작업공간과 작업부지 등을 확보함으로써, 교통체증 유발과 함께 심각한 교통문제가 불가피하고, 그에 따른 불편함과 시간적·경제적 손해를 끼친다는 점에서 단기간 내에 경제적인 시공이 절실히 요구되었다.For example, when bridges for overpasses, light rails, etc. are constructed in urban areas, the piles and piers installed on the ground are generally installed on roads through which vehicles pass, so it is common to bypass traffic vehicles or significantly reduce the number of lanes. By securing a working space and a working site, economical construction was urgently needed in that it caused inevitable traffic problems and serious traffic problems, resulting in inconvenience and time and economic damages.

본 발명은 상기와 같은 문제점을 해결하기 위해 개발된 것으로, 급속 시공이 요구되는 현장 상황에 맞추어 좁은 작업 공간 내에서도 단시간 내에 설치될 수 있도록 콘크리트 교각 구조물이 프리캐스트 방식으로 사전 제작된 후 현장으로 옮겨져 말뚝에 바로 조립될 수 있도록 하여 콘크리트 교각 구조물의 설치에 따른 급속 시공과 함께 공기를 단축하고, 아울러 말뚝 두부가 보강되어 경제적인 시공이 이루어질 수 있는 새로운 형태의 말뚝 두부 연결용 조립체, 이를 이용한 말뚝과 프리캐스트 콘크리트 교각 구조물의 연결구조 및 그 연결시공방법을 제공하는 것을 목적으로 한다.The present invention has been developed to solve the above problems, in order to be installed within a short working space in a narrow working space in accordance with the on-site situation that requires rapid construction, the concrete pier structure is pre-fabricated in the precast method and then moved to the site pile New construction of pile head connection assembly, which can be assembled economically by shortening the air with rapid construction according to the installation of concrete piers, and economically constructing the pile head. An object of the present invention is to provide a connection structure of a cast concrete pier structure and a connection construction method thereof.

본 발명에 따르면, 콘크리트 교각 구조물이 프리캐스트 방식으로 사전 제작된 후 현장에서 말뚝에 바로 조립 연결되어 설치됨으로써, 좁은 작업 공간에서도 급속시공이 가능하게 되고, 그에 따라 공기 단축은 물론, 경제적인 시공이 이루어 질 수 있는 효과를 기대할 수 있으며, 이러한 효과로 인해 교통체증 유발방지 및 통행의 불편함을 최소화할 수 있게 된다.According to the present invention, the concrete pier structure is pre-fabricated in the precast method, and then assembled and installed directly to the pile in the field, it is possible to rapid construction in a narrow working space, thereby reducing the air, as well as economical construction The effect that can be achieved can be expected, and due to this effect it is possible to prevent the traffic jam and minimize the inconvenience of traffic.

또한, 본 발명에서는 콘크리트 교각 구조물이 연결되는 말뚝 두부에 조립체가 간편하게 조립되어 구비됨으로써, 말뚝 두부에 대한 강도가 보강되고, 그와 함께 안전성이 확보될 수 있는 효과를 기대할 수 있다.In addition, in the present invention, since the assembly is easily assembled to the pile head to which the concrete pier structure is connected, the strength of the pile head may be reinforced, and safety with it may be expected.

또한, 본 발명에서는 차량 충돌에 대비하여 말뚝과 콘크리트 교각 구조물의 연결부위에 충격흡수부재가 설치됨으로써, 연결부위를 보호하고, 특히 차량 충돌로 인한 콘크리트 교각 구조물 및 두부의 손상이나 파손을 방지할 수 있으며, 이러한 충격흡수부재가 간편한 조립식 구조로 만들어 설치되므로 그 설치작업이 간편하고 취급이 용이한 효과도 기대할 수 있다.In addition, in the present invention, the shock absorbing member is installed at the connection portion between the pile and the concrete pier structure in preparation for a vehicle collision, thereby protecting the connection portion, and in particular, to prevent damage or damage to the concrete pier structure and the head caused by the vehicle collision. In addition, since the shock absorbing member is installed in a simple assembly structure, the installation work can be expected to be simple and easy to handle.

본 발명에서는 위와 같은 효과를 발휘하는 것으로서 다음과 같은 기술이 제공된다. In the present invention, as described above, the following technology is provided.

우선, 본 발명에서는 말뚝과 프리캐스트 콘크리트 교각 구조물을 연결하는 조립체로서, 중앙에는 인입공이 형성되어 있고, 상기 조립체의 상부에 배치되는 상부 지지부재; 상기 상부 지지부재로부터 간격을 두어 상기 조립체의 하부에 배치되는 하부 지지부재; 및 상기 상부 지지부재와 하부 지지부재가 서로 간격을 유지하는 상태로 고정되도록 상부 지지부재와 하부 지지부재를 관통하는 상태로 둘레를 따라 결합 고정되는 다수의 지지연결봉부재를 포함하여 구성되는 것을 특징으로 하 는 말뚝 두부 연결용 조립체가 제공된다. First, the present invention provides an assembly for connecting a pile and a precast concrete pier structure, the center is formed with a hole, the upper support member disposed on the assembly; A lower support member disposed below the assembly at a distance from the upper support member; And a plurality of support connecting rod members that are coupled and fixed along a circumference in a state of penetrating the upper support member and the lower support member such that the upper support member and the lower support member are fixed in a state where they are spaced from each other. An assembly for connecting the pile head is provided.

위와 같은 조립체에 있어서, 상기 상부 지지부재의 인입공과 마주하는 하부 지지부재의 중앙에 인입공이 형성되어 있고; 상기 인입공 간에 연결관이 연결될 수 있다. In the assembly as described above, the inlet hole is formed in the center of the lower support member facing the inlet hole of the upper support member; A connection pipe may be connected between the inlet holes.

또한, 본 발명에서 상기 조립체는, 상기 상부 지지부재의 인입공에 연결되어 하부방향으로 배치되는 연결관이 구비되며, 상기 연결관의 하단과 하부 지지부재 사이에 다수의 스페이서를 배치하여 측 방향으로 개구부가 형성되는 형태로 변형될 수 있다. In addition, in the present invention, the assembly is connected to the inlet hole of the upper support member is provided with a connecting pipe disposed in the lower direction, by placing a plurality of spacers between the lower end and the lower support member of the connecting pipe in the lateral direction It may be deformed into the shape in which the opening is formed.

더 나아가, 본 발명에 있어서, 상기한 조립체에서, 상기 하부 지지부재에는 철근망과 조립될 수 있도록 다수의 통공이 대응하는 위치에 형성될 수 있다. Furthermore, in the present invention, in the above assembly, a plurality of through holes may be formed in a corresponding position to be assembled with the reinforcing bar in the lower support member.

한편, 본 발명에서는 철근망을 포함하여 지반에 시공되는 현장 타설 말뚝과 프리캐스트로 제작된 콘크리트 교각 구조물의 연결구조로서, 상기 현장 타설 말뚝의 시공을 위하여 천공된 말뚝공에 철근망을 배치한 상태에서, 두부구간을 제외한 상태로 콘크리트가 타설되며; 상기 현장 타설 말뚝의 철근망이 하부 지지부재를 관통하여 상부 지지대에 지지되는 상태로 상기한 통공이 구비된 조립체가 두부구간에 배치되고; 상기 두부구간에서 상기 조립체의 상부 지지부재와, 상기 상부 지지부재로부터 돌출된 지지연결봉부재의 상단부가 노출되는 상태로 콘크리트가 타설되고;상기 프리캐스트 콘크리트 교각 구조물의 하단에 구비되는 연결부재가 상기 상부 지지부재의 상면에 고정 설치됨으로써, 상기 현장 타설 말뚝과 프리캐스트 콘크리트 교각 구조물이 상기 조립체에 의하여 일체로 연결되는 것을 특징으로 하는 말뚝 과 프리캐스트 콘크리트 교각 구조물의 연결구조가 제공된다. On the other hand, in the present invention is a connection structure between the site pour pile and precast concrete piers structure including the reinforcing bar, the rebar network is placed in the perforated pile for the construction of the site pour pile In, concrete is poured with the exception of the head section; An assembly having the above-described through hole is disposed in the head section in such a state that the reinforcing bar network of the site-pouring pile is supported by the upper support through the lower support member; Concrete is poured in a state in which the upper support member of the assembly and the upper end of the support connecting rod member protruding from the upper support member are exposed in the head section; the connection member provided at the lower end of the precast concrete pier structure is the upper portion By being fixedly installed on the upper surface of the support member, there is provided a connection structure of the pile and precast concrete pier structure, characterized in that the site-pouring pile and the precast concrete pier structure is integrally connected by the assembly.

본 발명에서 상기한 연결구조는 상기 두부구간을 포함한 상기 말뚝공에 콘크리트가 동시에 일괄 타설되도록 변형될 수 있다. In the present invention, the connection structure may be modified to simultaneously cast concrete in the pile hole including the head section.

더 나아가, 상기한 연결구조에서, 상기 연결부재와 조립체의 연결부위가 노출되지 않도록 고정구조물이 연결부재를 감싸는 상태로 고정 설치될 수도 있다. Furthermore, in the connection structure, the fixing structure may be fixedly installed in a state in which the connection structure surrounds the connection member so that the connection portion between the connection member and the assembly is not exposed.

한편, 상기한 연결구조는 지반에 시공되는 강관 말뚝과 프리캐스트로 제작된 콘크리트 교각 구조물의 연결구조에도 적용될 수 있는데, 이 경우, 지반에 설치된 상기 강관 말뚝의 상단이 상부 지지부재에 지지되도록 상기한 조립체가 강관 말뚝의 내부로 삽입되어 고정 설치되고; 상기 프리캐스트 콘크리트 교각 구조물의 하단에 구비되는 연결부재가 상기 상부 지지부재의 상면에 고정 설치됨으로써, 상기 강관 말뚝과 프리캐스트 콘크리트 교각 구조물이 상기 조립체에 의하여 일체로 연결되는 구성을 가진다. On the other hand, the above connection structure may be applied to the connection structure of the steel piling pile and precast concrete pier structure constructed on the ground, in this case, the upper end of the steel pipe pile installed on the ground is supported by the upper support member The assembly is inserted into the steel pipe pile and fixedly installed; The connection member provided at the lower end of the precast concrete pier structure is fixed to the upper surface of the upper support member, so that the steel pipe pile and the precast concrete pier structure is integrally connected by the assembly.

이와 같이 강관 말뚝에 적용되는 실시예에서, 상기 상부 지지부재에 구비된 연결관과 하부 지지부재의 사이에 형성되는 개구부를 통하여 상기 강관 말뚝의 내부가 콘크리트 타설될 수 있다. Thus, in the embodiment applied to the steel pipe pile, the interior of the steel pipe pile can be cast through the opening formed between the connection pipe and the lower support member provided in the upper support member.

또한, 본 발명에서는 철근망을 포함하여 지반에 시공되는 현장 타설 말뚝과 프리캐스트로 제작된 콘크리트 교각 구조물의 연결시공방법으로서, 상기 현장 타설 말뚝의 시공을 위하여 천공된 말뚝공에 철근망을 배치한 상태에서, 두부구간을 제외한 상태로 콘크리트를 타설하는 단계; 상기 현장 타설 말뚝의 철근망이 하부 지지부재를 관통하여 상부 지지대에 지지되는 상태로 상기 조립체를 두부구간에 배치 하는 단계; 상기 두부구간에서 상기 조립체의 상부 지지부재와, 상기 상부 지지부재로부터 돌출된 지지연결봉부재의 상단부가 노출되는 상태로 콘크리트를 타설하는 단계; 및 상기 프리캐스트 콘크리트 교각 구조물의 하단에 구비되는 연결부재를 상기 상부 지지부재의 상면에 고정 설치하는 단계를 포함함으로써, 상기 현장 타설 말뚝과 프리캐스트 콘크리트 교각 구조물이 상기 조립체에 의하여 일체로 연결되는 것을 특징으로 하는 말뚝과 프리캐스트 콘크리트 교각 구조물의 연결시공방법이 제공된다. In addition, in the present invention as a method of connecting the construction of the cast-in-place concrete piles and pre-cast concrete piling structure, including the reinforcing bar network, the reinforcing pile is placed in the perforated pile for the construction of the site In the state, placing the concrete in a state excluding the head section; Disposing the assembly in the head section while the reinforcing bar network of the site-pouring pile is supported by the upper support through the lower support member; Placing concrete with the upper support member of the assembly and the upper end of the support connecting rod member protruding from the upper support member in the head section; And fixing and installing a connection member provided at a lower end of the precast concrete pier structure on an upper surface of the upper support member so that the site-pouring pile and the precast concrete pier structure are integrally connected by the assembly. There is provided a method of connecting a pile and a precast concrete pier structure.

본 발명에서 상기한 연결시공방법은 상기 두부구간을 포함한 상기 말뚝공에 콘크리트가 동시에 일괄 타설되도록 변형될 수 있다. In the present invention, the connection construction method may be modified to simultaneously cast concrete in the pile hole including the head section.

또한, 상기한 연결시공방법에서는, 상기 두부구간을 포함한 상기 말뚝공에 콘크리트를 타설하는 단계에 후속하여, 상기 연결부재와 상부 지지부재의 연결 부위에 매몰 시공을 위한 거푸집을 설치하고 고정구조물을 타설하는 단계를 더 포함할 수도 있다. In addition, in the above connection construction method, following the step of placing concrete in the pile hole including the head section, install the formwork for investment construction in the connection portion of the connection member and the upper support member and place the fixed structure It may further comprise the step of.

또한, 본 발명에서는, 지반에 시공되는 강관 말뚝과 프리캐스트로 제작된 콘크리트 교각 구조물의 연결시공방법으로서, 지반에 설치된 상기 강관 말뚝의 상단이 상부 지지부재에 지지되도록 상기 조립체가 강관 말뚝의 내부로 삽입되어 고정 설치하는 단계; 및 상기 프리캐스트 콘크리트 교각 구조물의 하단에 구비되는 연결부재를 상기 상부 지지부재의 상면에 고정 설치하는 단계를 포함하여, 상기 강관 말뚝과 프리캐스트 콘크리트 교각 구조물이 상기 조립체에 의하여 일체로 연결되는 것을 특징으로 하는 말뚝과 프리캐스트 콘크리트 교각 구조물의 연결시공방법이 제 공된다. In addition, in the present invention, as a method of connecting the steel piling pile and the concrete pier structure made of precast construction on the ground, the assembly is installed in the ground so that the upper end of the steel pipe pile is supported by the upper support member to the inside of the steel pipe pile Inserting and fixing the installation; And fixing and installing a connection member provided at a lower end of the precast concrete pier structure on an upper surface of the upper support member, wherein the steel pipe pile and the precast concrete pier structure are integrally connected by the assembly. The method of connecting piles and precast concrete piers is provided.

위와 같은 연결시공방법에서, 상기 연결부재를 상기 상부 지지부재의 상면에 고정 설치하는 단계에 후속하여, 상기 연결부재와 상부 지지부재의 연결 부위에 매몰 시공을 위한 거푸집을 설치하고 고정구조물을 타설하는 단계를 더 포함할 수도 있다. In the connection construction method as described above, following the step of fixedly installing the connection member on the upper surface of the upper support member, to install the formwork for investment construction in the connection portion of the connection member and the upper support member and cast the fixed structure It may further comprise a step.

다음에서는 본 발명의 실시예를 도시한 도면을 참조하여 본 발명의 구체적인 구성을 설명한다. Hereinafter, with reference to the drawings showing an embodiment of the present invention will be described a specific configuration of the present invention.

도 1에는 본 발명의 제 1실시예에 따른 말뚝 두부 보강 및 콘크리트 교각 구조물과의 연결을 위한 조립체(10)의 사시도가 도시되어 있다.1 shows a perspective view of an assembly 10 for pile head reinforcement and connection with a concrete pier structure according to a first embodiment of the present invention.

도면에 도시된 것처럼 본 발명에 따른 조립체(10)는, 상부에 상부 지지부재(12)가 배치되고, 하부에 하부 지지부재(14)가 배치되며, 그 둘레를 따라 상부 지지부재(12)와 하부 지지부재(14)를 관통하는 복수 개의 지지연결봉부재(16) 및 상기 지지연결봉부재(16)에 체결되어 결합되는 체결구(18,46)에 의하여, 상부 지지부재(12)와 하부 지지부재(14)가 간격을 유지한 상태로 견고하게 고정된다.As shown in the figure, the assembly 10 according to the present invention, the upper support member 12 is disposed on the upper portion, the lower support member 14 is disposed on the lower side, and the upper support member 12 along the circumference The upper support member 12 and the lower support member are formed by a plurality of support connecting rod members 16 penetrating the lower support member 14 and fasteners 18 and 46 fastened to and coupled to the support connecting rod member 16. (14) is firmly fixed in a state where the gap is maintained.

그러나 위와 같이 설명된 상기 체결구(18,46)의 사용으로 한정될 필요는 없으며, 상기 지지연결봉부재(16)와 상부 및 하부 지지부재(12,14)가 용접으로 고정되어도 무방하다. 또한, 상기 상부 지지부재(12)와 하부 지지부재(14)의 사이에는 지지연결봉부재(16)를 통합하여 하나로 묶는 띠철근(20)이 지지연결봉부재(16)의 길이방향을 따라 하나 이상 구비될 수 있는데, 이러한 띠철근(20)에 의해 지지연결봉부재(16)의 결속력과 지지력이 더욱 상승하게 된다.However, it is not necessary to be limited to the use of the fasteners 18 and 46 described above, and the support connecting rod member 16 and the upper and lower support members 12 and 14 may be fixed by welding. In addition, between the upper support member 12 and the lower support member 14 is provided with at least one band reinforcing bar 20 is integrated along the support connecting rod member 16 along the longitudinal direction of the support connecting rod member 16. It can be, by the band reinforcing bar 20 is to increase the binding force and the supporting force of the support connecting rod member 16.

상부 지지부재(12) 및 하부 지지부재(14)의 중앙에는 콘크리트 타설을 위한 관(트레미관)이 삽입되는 인입공(22,24)이 각각 형성되어 있고, 상부 및 하부 지지부재(12,14)의 인입공(22,24) 간에는 연결관(26)이 연결된다. 이때, 연결관(26)은 인입공(22,24)을 통해 시멘트 밀크 주입이나 혹은 콘크리트 타설시 도움을 제공하게 되며, 상부 지지부재(12)와 하부 지지부재(14)의 지지력 높여 조립체(10)의 견고성을 한층 강화시키는 기능을 발휘한다.At the centers of the upper support member 12 and the lower support member 14 are formed inlet holes 22 and 24 into which pipes (treme tubes) for concrete placing are inserted, respectively, and upper and lower support members 12 and 14, respectively. The connecting pipe 26 is connected between the inlet hole (22, 24) of. In this case, the connection pipe 26 is provided to assist in pouring cement milk or pouring concrete through the inlet hole (22, 24), to increase the support of the upper support member 12 and the lower support member 14 assembly 10 Exerts the function of further strengthening the).

한편, 상기 하부 지지부재(14)에는 테두리를 따라 통공(28)이 여러 개 형성되는데, 이때, 상기 통공(28)은 지지연결봉부재(16)가 관통하는 위치로부터 외곽에 형성되어 상기 조립체(10)와 철근망(30)을 조립시에 지지연결봉부재(16)로 인한 간섭이나 조립 상에 불편함을 피하는 것이 바람직하다.On the other hand, the lower support member 14 is formed with a plurality of through-holes 28 along the rim, wherein the through-holes 28 are formed on the outside from the position where the support connecting rod member 16 penetrates the assembly 10 ) And the reinforcing bar (30) when assembling it is desirable to avoid the inconvenience caused by interference or assembly due to the support connecting rod member (16).

그러나 위와 같이 설명된 상기 통공(28)의 위치는 지지연결봉부재(16)가 관통하는 위치로부터 외곽으로 한정될 필요는 없으며, 지지연결봉부재(16)가 관통하는 위치와 동일하거나 내곽에 설치되어도 무방하다.However, the position of the through hole 28 described above is not necessarily limited to the outside from the position where the support connecting rod member 16 penetrates, and may be installed at the same or inside the position where the support connecting rod member 16 penetrates. Do.

또한, 콘크리트(38,40)의 타설시 체결구(46)와 지지연결봉부재(16) 상단에 이물질이 달라붙지 않도록 사전에 보호부재(S)를 씌워 조립체(10)와 콘크리트 교각 구조물(32)의 연결이 원활하게 이루어질 수 있도록 하는 것이 바람직하다.In addition, the assembly 10 and the concrete pier structure 32 by covering the protection member (S) in advance so that foreign substances do not stick to the upper end of the fastener 46 and the support connecting rod member 16 when the concrete 38 and 40 is poured. It is desirable to ensure that the connection can be made smoothly.

위와 같이 구성된 조립체(10)는 콘크리트 교각 구조물(32)과 현장 타설 말뚝(34)에 조립되는데, 이러한 조립체(10)에 의하여 콘크리트 교각 구조물(32)과 현장 타설 말뚝(34)이 연결되는 연결구조에 대해서는 다음 단락에서 구체적으로 설명한다.The assembly 10 configured as described above is assembled to the concrete pier structure 32 and the site pour pile 34, the connection structure is connected to the concrete pier structure 32 and the site pour pile 34 by this assembly (10). This is explained in detail in the following paragraphs.

도 2a에는 본 발명에 따른 프리캐스트 콘크리트 교각 구조물(32)과 현장 타설 말뚝(34)이 제 1실시예에 따른 조립체(10)에 의하여 연결되는 상태를 보여주는 상세한 분해 사시도가 도시되어 있고, 도 2b에는 제 1실시예에 따른 조립체(10)가 현장 타설 말뚝(34)의 두부에 조립된 단면도가 도시되어 있으며, 도 2c에서는 도 2b의 A-A선을 따라 절개한 조립체(10)의 단면도가 도시되어 있다.Figure 2a shows a detailed exploded perspective view showing a state in which the precast concrete pier structure 32 and the site-pouring pile 34 according to the present invention is connected by the assembly 10 according to the first embodiment, Figure 2b FIG. 2 is a cross-sectional view of the assembly 10 according to the first embodiment assembled to the head of the site-pouring pile 34, and in FIG. 2C, a cross-sectional view of the assembly 10 cut along the line AA of FIG. 2B is shown. have.

도면에 도시된 것처럼, 프리캐스트 방식으로 사전 제작된 콘크리트 교각 구조물(32)이 견고하게 설치될 수 있도록 하기 위한 그 기초로서 지반에 현장 타설 말뚝(34)이 시공된다.As shown in the figure, a site-pouring pile 34 is constructed on the ground as a basis for allowing the concrete pier structure 32 prefabricated in a precast manner to be firmly installed.

상기 지반에 형성되는 현장 타설 말뚝(34)은, 앞서 설명되었듯이 지반의 표면에서부터 말뚝공(36)을 천공하고, 철근을 조립하여 제작한 철근망(30)을 상기 말뚝공(36)에 삽입한 후 콘크리트(38) 타설하는 방식으로 시공된다.The site-pouring pile 34 formed on the ground, as described above, drills the pile hole 36 from the surface of the ground, and inserts the reinforcing bar 30 manufactured by assembling the reinforcing bar into the pile hole 36. After the concrete 38 is constructed by pouring.

이때, 콘크리트(38)의 타설 수위는 조립체(10)가 철근망(30)의 상단에 조립될 수 있도록 두부구간(D)을 제외한 수위까지 타설된다.At this time, the pouring level of the concrete 38 is poured up to the level except for the head section (D) so that the assembly 10 can be assembled on the upper end of the rebar network (30).

상기와 같이 콘크리트(38)가 타설되면 현장 타설 말뚝(34)의 두부에 위와 같은 구조로 구성된 조립체(10)가 조립된다.When the concrete 38 is poured as described above, the assembly 10 having the above structure is assembled to the head of the site-pouring pile 34.

상기 조립체(10)를 조립할 때, 철근망(30)을 구성하는 철근이 하부 지지부재(14)의 통공(28)을 각각 통과하여 상부 지지부재(12)의 내면에 닿는 상태로 조립된다.When assembling the assembly 10, the reinforcing bars constituting the reinforcing bar 30 are assembled to pass through the through holes 28 of the lower supporting member 14 to reach the inner surface of the upper supporting member 12.

위와 같이 조립체(10)의 조립이 완료되면, 현장 타설 말뚝(34)의 두부구간(D)을 콘크리트(40)를 타설하여 조립체(10)가 말뚝(34) 두부에 견고하게 고정되 도록 매몰시킨다. 이때, 상부 지지부재(12)로부터 돌출된 지지연결봉부재(16)는 매몰되지 않도록 설치하게 된다.When the assembly of the assembly 10 is completed as described above, the head section (D) of the site-pouring pile (34) is poured into the concrete 40 to bury the assembly (10) to be firmly fixed to the head of the pile (34). . At this time, the support connecting rod member 16 protruding from the upper support member 12 is installed so as not to be buried.

그러나, 위와 같이 콘크리트(38,40)는 나누어 타설하지 않아도 무방하며, 말뚝공(36)에 철근망(30)을 삽입하여 고정 설치하고, 상기 조립체(10)를 철근망(30)의 상단에 조립하여 고정 설치 한 후, 두부구간(D)을 제외한 부분의 콘크리트(38)와 두부구간(D)의 콘크리트(40)를 일괄 타설할 수도 있다. However, as described above, the concrete 38 and 40 may be divided and poured, and the reinforcing rod 30 is inserted into and fixed to the pile hole 36, and the assembly 10 is placed on the upper end of the reinforcing mesh 30. After assembling and fixing and installing, the concrete 38 of the portion except for the head section D and the concrete 40 of the head section D may be poured in a batch.

도 3a에는 프리캐스트 콘크리트 교각 구조물(32)이 조립체(10)에 조립된 상태를 나타낸 단면도가 도시되어 있다.3A is a cross-sectional view showing a state in which the precast concrete pier structure 32 is assembled to the assembly 10.

도면에 도시된 바와 같이 조립체(10)가 현장 타설 말뚝(34)에 조립되고 두부구간(D)에 콘크리트(40)의 타설이 완료되면, 프리캐스트 방식으로 사전 제작된 콘크리트 교각 구조물(32)이 조립체(10)의 상부 지지부재(12)에 놓이는 상태로 조립된다.As shown in the figure, when the assembly 10 is assembled to the site-pouring pile 34 and the casting of the concrete 40 to the head section D is completed, the precast concrete pier structure 32 is pre-fabricated. Assembled with the upper support member 12 of the assembly (10).

이 과정에서 상부 지지부재(12)로부터 돌출된 지지연결봉부재(16)가 콘크리트 교각 구조물(32) 하단에 구비된 연결부재(42)의 결합부(44)를 통과하게 되며, 너트 등으로 이루어진 체결구(46)가 지지연결봉부재(16)에 체결되어 상기 조립체(10)와 콘크리트 교각 구조물(32)이 조립 연결된다. 이때, 상기 체결구(46)가 조임 체결될 수 있도록 지지연결봉부재(16)의 상단부분은 나사부가 형성되는 것이 바람직하다. In this process, the supporting connecting rod member 16 protruding from the upper supporting member 12 passes through the coupling part 44 of the connecting member 42 provided at the bottom of the concrete pier structure 32, and is made of a nut or the like. The sphere 46 is fastened to the support connecting rod member 16 to the assembly 10 and the concrete pier structure 32 is assembled. At this time, the upper end portion of the support connecting rod member 16 is preferably a screw portion is formed so that the fastener 46 is tightened.

도면에 도시된 실시예에서는 상기 지지연결봉부재(16)와 콘크리트 교각 구조물(32)의 연결부재(42)가 체결되어 연결되는 구성으로 설명하였다. 그러나 상기 콘크리트 교각 구조물(32)의 연결부재(42)와 조립체(10)간의 연결 고정이 반드시 이에 한정되지 아니하며, 연결 고정이 이루어질 있는 구조이라면 체결구성이 아닐지라도 무방하다. 그 예로써, 상기 콘크리트 교각 구조물(32)의 연결부재(42)와, 지지연결봉부재(16)가 서로 용접으로 고정될 수 있고, 또는 콘크리트 교각 구조물(32)의 연결부재(42)와 상부 지지부재(12)가 서로 용접될 수 있다.In the embodiment shown in the drawings has been described as a configuration in which the support connecting rod member 16 and the connecting member 42 of the concrete pier structure 32 is fastened and connected. However, the connection fixing between the connection member 42 and the assembly 10 of the concrete pier structure 32 is not necessarily limited thereto, and may be a fastening configuration if the connection fixing is made. For example, the connecting member 42 and the support connecting rod member 16 of the concrete pier structure 32 may be fixed to each other by welding, or the connecting member 42 and the upper support of the concrete pier structure 32 The members 12 can be welded to each other.

도 3b에는 콘크리트 교각 구조물(32)과 조립체(10)가 연결되는 부분에 고정구조물(48)이 설치되는 상태를 나타낸 단면도가 도시되어 있다. 3B is a cross-sectional view illustrating a state in which the fixed structure 48 is installed at a portion where the concrete pier structure 32 and the assembly 10 are connected.

도면에 도시된 바와 같이 프리캐스트 콘크리트 교각 구조물(32)과 조립체(10)의 연결이 완료되면, 콘크리트 교각 구조물(32)의 연결부재(42) 주변에 거푸집(50)을 설치하고, 콘크리트를 타설하여 고정구조물(48)이 설치되도록 한다. As shown in the drawing, when the connection of the precast concrete pier structure 32 and the assembly 10 is completed, the formwork 50 is installed around the connecting member 42 of the concrete pier structure 32, and the concrete is poured So that the fixing structure 48 is installed.

상기 고정구조물(48)이 설치되면, 조립체(10)와 연결부재(42)의 조립 부위가 매설되므로, 결합력과 내력이 증강되고, 아울러 지지연결봉부재(16), 체결구(46), 및 연결부재(42)의 부식도 방지할 수 있게 된다. 더 나아가 부식이 진행되더라도 고정구조물(48)이 견고하게 잡아주고 있어 안전성 확보에 전혀 지장이 없다. When the fixing structure 48 is installed, since the assembly portion of the assembly 10 and the connecting member 42 is embedded, the coupling force and the strength are enhanced, and the support connecting rod member 16, the fastener 46, and the connection Corrosion of the member 42 can also be prevented. Furthermore, even if corrosion proceeds, the fixed structure 48 is firmly held, so there is no problem in securing safety.

도 3c에는 본 발명에 따른 고정구조물(48)의 외부에 충격흡수부재(52)가 설치된 상태를 나타낸 단면도가 도시되어 있고, 도 4에는 본 발명에 따른 충격흡수부재(52)를 나타낸 사시도가 도시되어 있다.Figure 3c is a cross-sectional view showing a state in which the shock absorbing member 52 is installed on the outside of the fixed structure 48 according to the present invention, Figure 4 is a perspective view showing the shock absorbing member 52 according to the present invention It is.

도면에 도시된 바와 같이 고정구조물(48)이 설치되면, 차량 충돌에 대비하여 다음과 같은 충격흡수부재(52)가 상기 고정구조물(48)에 외면을 감싸도록 설치됨으로써, 차량 충돌로 인한 콘크리트 교각 구조물(32)의 연결부재(42)와 말뚝(34) 두 부의 파손을 방지하여 안정성이 더욱 높아지게 된다.As shown in the drawing, when the fixed structure 48 is installed, the following shock absorbing member 52 is installed to surround the outer surface to the fixed structure 48 in preparation for a vehicle collision, the concrete pier due to the vehicle collision The stability of the connection member 42 and the pile 34 of the structure 32 is prevented from being damaged further.

도면에 도시된 실시예에서 상기 충격흡수부재(52)는 두개의 부분으로 나뉘어져 있으며, 수평 연결체결구(54)에 의하여 양측에서 수평으로 연결 조립되는 조립식 구조로 만들어 설치하게 되므로 그 설치작업이 간편하고 취급이 용이하다.In the embodiment shown in the drawings, the shock absorbing member 52 is divided into two parts, and is installed in a prefabricated structure that is connected and assembled horizontally from both sides by a horizontal connection fastener 54, so the installation is easy. And easy to handle.

아울러 그 재질로서, 콘크리트, 합성수지, 충격흡수재 등 다양한 재질로 이루어지며, 나아가 충격을 흡수 완충할 수 있다면 그 왜 어떠한 재질의 사용도 무방하다. In addition, as the material, it is made of a variety of materials, such as concrete, synthetic resin, shock absorbing material, and furthermore, if the shock absorber can be buffered, why use any material.

도 5에는 본 발명의 제 2실시예에 따른 말뚝 두부 보강 및 콘크리트 교각 구조물과의 연결을 위한 조립체(10)의 사시도가 도시되어 있다.5 is a perspective view of an assembly 10 for pile head reinforcement and connection with a concrete pier structure according to a second embodiment of the present invention.

앞서 설명된 실시예 1의 조립체(10)는 현장 타설 말뚝(34)으로 시공되는 타입에서 철근망(30)과 조립될 수 있도록 하부 지지부재(14)에 통공(28)이 형성된 것이며, 실시예 2는 강관 말뚝(62)의 내부로 삽입되어 걸림 결합될 수 있도록 하는 구성을 가진다.The assembly 10 of the first embodiment described above is a through-hole 28 is formed in the lower support member 14 to be assembled with the reinforcing bar 30 in the type that is constructed as a site-pouring pile 34, embodiment 2 has a configuration that can be inserted into the interior of the steel pipe pile 62 to be engaged.

구체적으로, 도면에 도시된 것처럼 본 발명에 따른 조립체(10)는, 상부에 상부 지지부재(12)가 배치되고, 하부에 하부 지지부재(64)가 배치된다. 이러한 상부 지지부재(12)와 하부 지지부재(64)는 테두리를 따라 관통하는 복수 개의 지지연결봉부재(66)와, 이 지지연결봉부재(66)에 결합되는 체결구(18,46)로 인해 상부 지지부재(12)와 하부 지지부재(64)는 견고하게 고정된다.Specifically, as shown in the figure, the assembly 10 according to the present invention, the upper support member 12 is disposed at the top, the lower support member 64 is disposed at the bottom. The upper support member 12 and the lower support member 64 have an upper portion due to a plurality of support connecting rod members 66 penetrating along the rim, and fasteners 18 and 46 coupled to the support connecting rod members 66. The support member 12 and the lower support member 64 are firmly fixed.

또한, 상기 상부 지지부재(12)와 하부 지지부재(64)의 사이에는 지지연결봉부재(66)를 통합하여 하나로 묶는 띠철근(20)이 지지연결봉부재(66)의 길이방향을 따라 하나 이상 구비되어 앞서 설명된 바와 같이 지지연결봉부재(66)의 결속력과 지지력을 더욱 높이게 된다.In addition, between the upper support member 12 and the lower support member 64 is provided with at least one belt reinforcing bar 20 is integrated along the support connecting rod member 66 along the longitudinal direction of the support connecting rod member 66. As described above, the binding force and the supporting force of the support connecting rod member 66 are further increased.

또한, 상부 지지부재(12)의 중앙에는 콘크리트 주입을 위한 트레미관이 삽입되는 인입공(22)이 형성되어 있고, 아울러 상부 지지부재(12)의 인입공(22)에는 연결관(68)이 연결되어 하부 지지부재(64) 방향으로 배치된다. 이때, 상기 연결관(68)은 실시예 1의 연결관(26)과 달리 연결관(68)의 하단과 하부 지지부재(64) 사이에 스페이서(70)가 복수 개 배치되어 있다.In addition, the center of the upper support member 12 is formed with an inlet hole 22 through which a tremi tube for concrete injection is formed, and a connection tube 68 is provided in the inlet hole 22 of the upper support member 12. Connected to the lower support member 64. In this case, unlike the connection pipe 26 of the first embodiment of the connection pipe 68, a plurality of spacers 70 are disposed between the lower end of the connection pipe 68 and the lower support member 64.

위와 같은 상기 스페이서(70)에 의하여 연결관(68)과 하부 지지부재(64) 사이에는 개구부(72)가 형성되며, 이와 같이 형성되는 개구부(72)를 통해 강관 말뚝(62)의 내부로 시멘트 밀크 주입이나 콘크리트 타설에 따른 공급이 이루어질 수 있게 된다.An opening 72 is formed between the connection pipe 68 and the lower support member 64 by the spacer 70 as described above, and cement into the steel pipe pile 62 through the opening 72 formed as described above. Supply can be achieved by milk pouring or concrete pouring.

실시예의 2의 기타 구성은 앞서 설명한 실시예 1과 동일하므로, 동일한 부재번호를 사용하고 기타 설명은 생략한다.  Since the other components of Embodiment 2 are the same as those of Embodiment 1 described above, the same member numbers are used, and other descriptions are omitted.

위와 같이 구성된 조립체(10)는 콘크리트 교각 구조물(32)과 강관 말뚝(62)에 조립되며, 이러한 조립체(10)에 의하여 콘크리트 교각 구조물(32)과 강관 말뚝(62)이 일체로 연결되는 연결구조에 대해서는 다음 단락에서 구체적으로 설명하기로 한다.The assembly 10 configured as described above is assembled to the concrete pier structure 32 and the steel pipe pile 62, the connection structure that the concrete pier structure 32 and the steel pipe pile 62 is integrally connected by this assembly (10). This will be described in detail in the following paragraphs.

도 6a에는 본 발명에 따른 프리캐스트 콘크리트 교각 구조물(32)과 강관 말뚝(62)이 제 2실시예에 따른 조립체(10)에 의하여 연결되는 상태를 보여주는 상세한 분해 사시도가 도시되어 있고, 도 6b에는 제 2실시예에 따른 조립체(10)가 강관 말뚝(62) 두부에 조립된 단면도가 도시되어 있으며, 도 6c에서는 도 6b의 B-B선을 따라 절개한 조립체(10)의 단면도가 도시되어 있다.FIG. 6A shows a detailed exploded perspective view showing a state in which the precast concrete pier structure 32 and the steel pipe pile 62 according to the present invention are connected by the assembly 10 according to the second embodiment, and FIG. 6B. A cross-sectional view of the assembly 10 according to the second embodiment assembled to the head of the steel pipe pile 62 is shown. In FIG. 6C, a cross-sectional view of the assembly 10 cut along the line BB of FIG. 6B is shown.

도면에 도시된 것처럼, 프리캐스트 방식으로 사전 제작된 콘크리트 교각 구조물(32)이 견고하게 설치될 수 있도록 하기 위한 그 기초로서 앞서 설명된 바와 같이 지반에 매입 형식으로 강관 말뚝(62)을 시공하게 된다. 참고로 첨부된 도면에서는 매입 형식으로 시공되는 강관 말뚝(62)으로 도시되어 있으나, 이는 설명을 위한 하나의 예일 뿐이며 항타 형식의 강관 말뚝으로 시공되어도 무방하다. As shown in the drawings, the steel pipe pile 62 is constructed in the form of embedded in the ground as described above as a basis for allowing the concrete pier structure 32, which is pre-fabricated in the precast manner, to be firmly installed. . For reference, the accompanying drawings are shown as steel pipe piles 62 which are constructed in a buried form, but this is only one example for description and may be constructed as a steel pipe pile of a driving type.

위와 같은 시공으로 강관 말뚝(62)이 완료되면, 강관 말뚝(62) 두부에 조립체(10)가 조립되는데, 이 과정에서 상부 지지부재(12)를 제외한 조립체(10)의 하부 부분이 강관 말뚝(62)의 내부로 삽입되고, 강관 말뚝(62)이 상부 지지부재(12)의 내면에 닿는 상태로 조립된다.When the steel pipe pile 62 is completed by the above construction, the assembly 10 is assembled to the head of the steel pipe pile 62, and in this process, the lower portion of the assembly 10 except for the upper support member 12 is a steel pipe pile ( 62 is inserted into the inside, and the steel pipe pile 62 is assembled in contact with the inner surface of the upper support member 12.

위와 같이 조립체(10)의 조립이 완료되면, 조립체(10)의 인입공(22)을 통해 콘크리트 타설에 따른 공급이 이루어지게 되는데, 이때 콘크리트는 연결관(68)을 따라 흐르면서 개구부(72)를 통해 강관 말뚝(62)의 내부로 공급되어 타설된다. 참고로 첨부된 도면에서는 콘크리트가 강관의 내부 전체로 공급되어 있는 것이나, 구조 계산의 결과에 따라 하부 지지부재(64)까지 공급되어도 무방하다.When the assembly of the assembly 10 is completed as described above, the supply is made by placing the concrete through the inlet hole 22 of the assembly 10, wherein the concrete flows along the connecting pipe 68 and opens the opening 72. It is fed into the inside of the steel pipe pile 62 is poured. For reference, in the accompanying drawings, the concrete is supplied to the entire interior of the steel pipe, or may be supplied to the lower support member 64 according to the result of the structural calculation.

도 7a에서는 프리캐스트 콘크리트 교각 구조물(32)이 조립체(10)에 조립된 상태를 나타낸 단면도가 도시되어 있다.FIG. 7A shows a cross-sectional view of a precast concrete pier structure 32 assembled to the assembly 10.

도면에 도시된 바와 같이 조립체(10)가 강관 말뚝(62)에 조립이 완료되면, 프리캐스트 방식으로 사전 제작된 콘크리트 교각 구조물(32)이 조립체(10)의 상부 지지부재(12)에 놓이는 상태로 조립된다. As shown in the drawing, when the assembly 10 is completed to the steel pipe pile 62, the pre-fabricated concrete pier structure 32 is placed on the upper support member 12 of the assembly 10 Is assembled.

이 과정에서 상부 지지부재(12)로부터 돌출된 지지연결봉부재(66)가 콘크리트 교각 구조물(32) 하단에 구비된 연결부재(42)의 결합부(44)를 통과하여 결합되며, 너트인 체결구(46)가 조임 체결되는 것으로 조립체(10)와 콘크리트 교각 구조물(32)의 조립 연결이 완료된다.In this process, the supporting connecting rod member 66 protruding from the upper supporting member 12 is coupled through the coupling part 44 of the connecting member 42 provided at the bottom of the concrete pier structure 32, and the fastener which is a nut Tightening and fastening of 46 is completed assembling the assembly 10 and the concrete pier structure 32.

여기서도, 상기 체결구(46)가 조임 체결될 수 있도록 지지연결봉부재(66)의 상단부분에는 나사부가 형성되는 것이 바람직하다. Here, the upper end portion of the support connecting rod member 66 is preferably formed with a screw so that the fastener 46 can be tightened.

도면에 도시된 실시예에서는 상기 지지연결봉부재(66)가 콘크리트 교각 구조물(32)의 연결부재(42)와 체결되는 구성으로 설명하였으나, 앞서 설명된 바와 같이 용접에 의해 고정될 수 있으며, 콘크리트 교각 구조물(32)의 연결부재(42)와 조립체(10) 칸에 연결 고정이 이루어질 있는 구조라면 어떠한 연결구성도 무방할 것이다.In the embodiment shown in the drawing has been described as a configuration in which the support connecting rod member 66 and the connection member 42 of the concrete pier structure 32, but can be fixed by welding as described above, concrete pier Any connection configuration may be used as long as the connection is secured to the connection member 42 and the assembly 10 compartment of the structure 32.

도 7b에서는 본 발명에 따른 고정구조물(48)의 외부에 충격흡수부재(52)가 설치된 상태를 나타낸 단면도가 도시되어 있고, 도 7c에서는 본 발명에 따른 고정구조물(48)의 외부에 충격흡수부재(52)가 설치된 상태를 나타낸 단면도가 도시되어 있다. 7B is a cross-sectional view illustrating a state in which the shock absorbing member 52 is installed on the outside of the fixed structure 48 according to the present invention, and in FIG. 7C, the shock absorbing member is external to the fixed structure 48 according to the present invention. A cross-sectional view showing a state in which 52 is installed is shown.

도면에 도시된 바와 같이 프리캐스트 콘크리트 교각 구조물(32)의 연결부재(42)와 조립체(10)가 조립되면, 실시예 1에서 이미 설명되었듯이 콘크리트 교각 구조물(32)의 연결부재(42) 주변에 고정구조물(48)을 설치하고, 차량 충돌에 대비하여 충격흡수부재(52)가 상기 고정구조물(48)의 외면에 설치되도록 한다.As shown in the drawing, when the connecting member 42 and the assembly 10 of the precast concrete pier structure 32 are assembled, the surroundings of the connecting member 42 of the concrete pier structure 32 as already described in Embodiment 1 The fixed structure 48 is installed on the vehicle, and the shock absorbing member 52 is installed on the outer surface of the fixed structure 48 in preparation for a vehicle collision.

본 발명에 따르면, 프리캐스트 방식으로 제작된 콘크리트 교각 구조물(32)이 현장에서 말뚝(34,62)에 바로 조립되어 설치됨으로써, 시공이 신속하고 간편하여 교통체증 유발 방지 및 통행의 불편함이 최소화되고, 그와 함께 말뚝(34,62) 두부에 대한 보강을 통해 견고하고 강한 지지력은 물론, 안전성을 충분히 확보할 수 있게 된다.According to the present invention, the concrete pier structure 32 manufactured by the precast method is installed on the pile (34, 62) directly installed on the site, the construction is quick and easy to prevent traffic jams and minimize the inconvenience of traffic In addition, through the reinforcement to the head of the pile (34, 62), it is possible to secure a strong and strong bearing capacity, as well as safety enough.

위와 같이 설명된 본 발명에 따른 조립체(10)는, 말뚝(34,62)과 콘크리트 교각구조물(32)의 연결에 적합할 것이나, 그 사용 용도는 이에 한정되지 아니하며 다양한 연결구조에 사용될 수 있다.The assembly 10 according to the present invention described above will be suitable for the connection of the piles 34 and 62 and the concrete pier structure 32, but its use is not limited thereto and may be used in various connection structures.

또한, 위와 같이 설명된 본 발명에 따른 콘크리트 교각 구조물(32)은, 도 8에 도시된 바와 같이 원형 빔을 다수가 내장하거나 도 9에 도시된 바와 같이 H형 빔을 내장하여 프리캐스트 방식으로도 제작될 수 있다. In addition, the concrete pier structure 32 according to the present invention described above, a plurality of circular beams as shown in FIG. 8 or H-beams as shown in FIG. Can be made.

이상으로 본 발명의 바람직한 실시예에 대해 기술하였지만, 본 발명이 속하는 기술분야에 있어서 통상의 지식을 가진 사람이라면, 본 발명을 여러 가지로 변형 또는 변경하여 실시할 수 있음을 알 수 있을 것이다. 따라서 본 발명의 실시예들의 변경은 본 발명의 기술적 범위를 벗어날 수 없을 것이다.Although the preferred embodiments of the present invention have been described above, those skilled in the art will recognize that the present invention may be modified or modified in various ways. Therefore, changes of the embodiments of the present invention will not be able to escape the technical scope of the present invention.

도 1은 본 발명의 실시예 1에 따른 말뚝 두부 연결용 조립체를 나타낸 사시도이다.1 is a perspective view showing the assembly for connecting the pile head according to the first embodiment of the present invention.

도 2a는 실시예 1에 따른 조립체에 의하여 현장 타설 말뚝과 콘크리트 교각 구조물이 연결되는 상태를 보여주는 상세한 분해 사시도이다.Figure 2a is a detailed exploded perspective view showing a state in which the site-pouring pile and the concrete pier structure is connected by the assembly according to the first embodiment.

도 2b는 실시예 1에 따른 조립체가 현장 타설 말뚝에 조립되고, 타설된 상태를 나타낸 결합 단면도이다.Figure 2b is an assembled cross-sectional view showing a state in which the assembly according to the first embodiment is assembled to the site-pouring pile, and poured.

도 2c는 도 2b에 도시된 A-A선을 따라 절개한 조립체의 단면도이다.FIG. 2C is a cross-sectional view of the assembly cut along the line A-A shown in FIG. 2B.

도 3a는 콘크리트 교각 구조물이 실시예 1에 따른 조립체에 조립된 상태를 나타낸 단면도이다.3A is a cross-sectional view showing a state in which the concrete pier structure is assembled to the assembly according to the first embodiment.

도 3b는 도 3a에 도시된 콘크리트 교각 구조물과 실시예 1에 따른 조립체의 연결부위에 고정구조물이 설치된 상태를 나타낸 단면도이다.Figure 3b is a cross-sectional view showing a state in which the fixed structure is installed on the connection portion of the assembly according to the concrete pier structure shown in FIG.

도 3c는 도 3b에 도시된 고정구조물에 충격흡수부재가 설치된 상태를 나타낸 단면도이다.3C is a cross-sectional view illustrating a state in which a shock absorbing member is installed in the fixed structure shown in FIG. 3B.

도 4는 도 3c에 도시된 충격흡수부재를 나타낸 사시도이다. Figure 4 is a perspective view of the shock absorbing member shown in Figure 3c.

도 5a는 본 발명의 실시예 2에 따른 말뚝 두부 연결용 조립체를 나타낸 사시도이다.Figure 5a is a perspective view showing the assembly for the connection of the head to the head according to the second embodiment of the present invention.

도 6a는 실시예 2에 따른 조립체에 의하여 강관 말뚝과 콘크리트 교각 구조물이 연결되는 상태를 보여주는 상세한 분해 사시도이다.Figure 6a is a detailed exploded perspective view showing a state in which the steel pipe pile and the concrete pier structure is connected by the assembly according to the second embodiment.

도 6b는 실시예 2에 따른 조립체가 강관 말뚝에 조립되고, 타설된 상태를 나 타낸 결합 단면도이다.6B is a cross-sectional view illustrating the assembled state of the assembly according to Example 2 in the steel pipe pile, and poured state.

도 6c는 도 6b에 도시된 B-B선을 따라 절개한 조립체의 단면도이다.6C is a cross-sectional view of the assembly cut along the line B-B shown in FIG. 6B.

도 7a는 콘크리트 교각 구조물이 실시예 2에 따른 조립체에 조립된 상태를 나타낸 단면도이다.7A is a cross-sectional view showing a state in which the concrete pier structure is assembled to the assembly according to the second embodiment.

도 7b는 도 7a에 도시된 콘크리트 교각 구조물과 실시예 2에 따른 조립체의 연결부위에 고정구조물이 설치된 상태를 나타낸 단면도이다.FIG. 7B is a cross-sectional view illustrating a state in which a fixing structure is installed at a connection portion of the assembly according to Embodiment 2 with the concrete pier structure shown in FIG. 7A.

도 7c는 도 7b에 도시된 고정구조물에 충격흡수부재가 설치된 상태를 나타낸 단면도이다.7C is a cross-sectional view illustrating a state in which a shock absorbing member is installed in the fixed structure shown in FIG. 7B.

도 8은 원형 빔을 내장한 프리캐스트 콘크리트 교각 구조물의 다른 예를 나타낸 사시도이다.8 is a perspective view showing another example of a precast concrete pier structure with a circular beam.

도 9는 H형 빔을 내장한 프리캐스트 콘크리트 교각 구조물의 다른 예를 나타낸 사시도이다.9 is a perspective view showing another example of a precast concrete pier structure containing an H-beam.

*도면의 주요부분에 대한 부호의 설명** Description of the symbols for the main parts of the drawings *

10 : 조립체 12 : 상부 지지부재10 assembly 12 upper support member

14,64 : 하부 지지부재 16,66 : 지지연결봉부재14,64: lower support member 16,66: support connecting rod member

18,46 : 체결구 20 : 띠철근18,46 fastener 20 strip reinforcing bar

22,24 : 인입공 26,68 : 연결관22,24: hole 26,68: connector

28 : 통공 30 : 철근망28: through-hole 30: rebar network

32 : 콘크리트 교각 구조물 34 : 현장 타설 말뚝32: concrete pier structure 34: cast-in-place pile

38,40 : 콘크리트 42 : 연결부재38,40 concrete 42 connection member

44 : 결합공 48 : 고정구조물44: coupling hole 48: fixed structure

50 : 거푸집 52 : 충격흡수부재50: formwork 52: shock absorbing member

54 : 수평연결체결구 62 : 강관 말뚝54: horizontal connection fastener 62: steel pipe pile

70 : 스페이서 72 : 개구부70: spacer 72: opening

Claims (5)

강관 말뚝(62)의 상단부에서 강관 말뚝(62)에 매립 설치되어, 말뚝과 프리캐스트 콘크리트 교각 구조물(32)을 연결하는 조립체(10)로서,As an assembly (10) buried in the steel pipe pile (62) at the upper end of the steel pipe pile (62), connecting the pile and the precast concrete pier structure (32), 복수개의 지지연결봉부재(66); A plurality of support connecting rod members 66; 중앙에는 콘크리트 타설을 위한 관이 삽입될 수 있는 인입공(22)이 형성되어 있고, 상기 조립체(10)의 상부에 배치되며, 상기 복수개의 지지연결봉부재(66)와 결합되어 상기 복수개의 지지연결봉부재(66)를 지지하는 상부 지지부재(12); Inlet hole 22 is formed in the center can be inserted into the pipe for placing concrete, disposed on the assembly 10, coupled to the plurality of support connecting rod member 66 and the plurality of support connecting rod An upper support member 12 for supporting the member 66; 상기 상부 지지부재(12)로부터 간격을 두어 상기 조립체(10)의 하부에 배치되며, 상기 복수개의 지지연결봉부재(66)와 결합되어 상기 복수개의 지지연결봉부재(66)를 지지하는 하부 지지부재(64);A lower support member disposed below the assembly 10 at intervals from the upper support member 12 and coupled to the plurality of support connecting rod members 66 to support the plurality of support connecting rod members 66; 64); 상기 상부 지지부재(12)의 인입공(22)에 연결되어 하부방향으로 배치되는 연결관(68); 및 A connection pipe 68 connected to the inlet hole 22 of the upper support member 12 and disposed in a lower direction; And 상기 연결관(68)의 하단과 하부 지지부재(64) 사이에 측 방향으로 개구부(72)가 형성되도록 배치된 다수의 스페이서(70)를 포함하여 구성되며; And a plurality of spacers (70) arranged to form openings (72) in the lateral direction between the lower end of the connecting pipe (68) and the lower support member (64); 상기 복수개의 지지연결봉부재(66)는, 상기 상부 지지부재(12)와 하부 지지부재(64)가 서로 간격을 유지하는 상태로 고정되도록 상부 지지부재(12)와 하부 지지부재(64)의 둘레를 관통하는 상태로 결합 고정되는 구조를 가지며; The plurality of support connecting rod members 66 may include a circumference of the upper support member 12 and the lower support member 64 such that the upper support member 12 and the lower support member 64 are fixed in a state where they are spaced from each other. It has a structure that is coupled and fixed in a state penetrating; 상기 복수개의 지지연결봉부재(66)는, 그 상단부가 콘크리트 교각 구조물(32)의 연결부재(42)와 결합될 수 있도록, 말뚝의 상단부에서 조립체(10)가 말뚝 에 매립 설치되었을 때, 상기 상부 지지부재(12)로부터 돌출되는 것을 특징으로 하는 강관 말뚝과 프리캐스트 콘크리트 교각 구조물의 연결용 조립체. The plurality of support connecting rod members 66, when the assembly 10 is embedded in the pile at the upper end of the pile so that the upper end thereof can be coupled to the connecting member 42 of the concrete pier structure 32, the upper Assembly for connecting the steel pipe pile and the precast concrete pier structure, characterized in that it protrudes from the support member (12). 지반에 시공되고 내부에 콘크리트가 타설되어 채워지는 강관 말뚝(62)과 프리캐스트로 제작된 콘크리트 교각 구조물(32)의 연결구조로서,As a connection structure between the steel pipe pile 62, which is constructed on the ground and filled with concrete, and the concrete pier structure 32 made of precast, 지반에 설치된 상기 강관 말뚝(62)의 상단이 상부 지지부재(12)에 지지되도록 청구항 제1항의 조립체(10)가 강관 말뚝(62)의 내부로 삽입되어 고정 설치되고;The assembly 10 of claim 1 is inserted into and fixed to the inside of the steel pipe pile 62 so that an upper end of the steel pipe pile 62 installed on the ground is supported by the upper support member 12; 상기 프리캐스트 콘크리트 교각 구조물(32)의 하단에 구비되는 연결부재(42)가 상기 상부 지지부재(12)의 상면에 놓이고; A connection member 42 provided at a lower end of the precast concrete pier structure 32 is placed on an upper surface of the upper support member 12; 상기 상부 지지부재(12)의 상면에 돌출되어 있는 상기 복수개의 지지연결봉부재(66)의 상단부가 콘크리트 교각 구조물(32)의 연결부재(42)와 결합되어, 상기 강관 말뚝(62)과 프리캐스트 콘크리트 교각 구조물(32)이 청구항 제1항의 조립체(10)에 의하여 일체로 연결되는 것을 특징으로 하는 강관 말뚝과 프리캐스트 콘크리트 교각 구조물의 연결구조.Upper ends of the plurality of supporting connecting rod members 66 protruding from the upper surface of the upper supporting member 12 are combined with the connecting members 42 of the concrete pier structure 32 to precast the steel pipe pile 62 and the precast member. Connection structure of a steel pipe pile and a precast concrete pier structure, characterized in that the concrete pier structure (32) is integrally connected by the assembly (10) of claim 1. 제2항에 있어서,The method of claim 2, 상기 강관 말뚝(62)의 내부에 채워지는 콘크리트는, 상기 상부 지지부재(12)에 구비된 연결관(68)과 하부 지지부재(64)의 사이에 형성되는 개구부(72)를 통하 여 타설되는 것을 특징으로 하는 강관 말뚝과 프리캐스트 콘크리트 교각 구조물의 연결구조. Concrete filled in the steel pipe pile 62 is poured through an opening 72 formed between the connection pipe 68 and the lower support member 64 provided in the upper support member 12. Connection structure between the steel pipe pile and the precast concrete pier structure. 지반에 시공되는 강관 말뚝(62)과 프리캐스트로 제작된 콘크리트 교각 구조물(32)의 연결시공방법으로서,As a method of connecting the steel pipe pile 62 to be constructed on the ground and the concrete pier structure 32 made of precast, 상부 지지부재(12)가 지반에 설치된 상기 강관 말뚝(62)의 상단에 지지되도록 청구항 제1항의 조립체(10)가 강관 말뚝(62)의 내부로 삽입되어 설치되는 단계; The assembly of claim 1 is inserted into the interior of the steel pipe pile 62 so that the upper support member 12 is supported on the upper end of the steel pipe pile 62 is installed on the ground; 청구항 제1항의 조립체(10)의 인입공을 통해 콘크리트가 타설되어 청구항 제1항의 조립체(10)가 콘크리트에 매립되는 단계; 및Pouring concrete through the inlet hole of the assembly (10) of claim 1 so that the assembly (10) of claim 1 is embedded in the concrete; And 상기 프리캐스트 콘크리트 교각 구조물(32)의 하단에 구비되는 연결부재(42)가, 상기 상부 지지부재(12)의 상면으로 돌출되어 있는 상기 복수개의 지지연결봉부재(66)의 상단부에 결합되어, 프리캐스트 콘크리트 교각 구조물(32)이 상기 상부 지지부재(12)의 상면에 고정 설치되는 단계를 포함하여, The connection member 42 provided at the lower end of the precast concrete pier structure 32 is coupled to the upper end of the plurality of support connecting rod member 66 protruding to the upper surface of the upper support member 12, Including the cast concrete pier structure 32 is fixed to the upper surface of the upper support member 12, 상기 강관 말뚝(62)과 프리캐스트 콘크리트 교각 구조물(32)이 청구항 제1항의 조립체(10)에 의하여 일체로 연결되는 것을 특징으로 하는 강관 말뚝과 프리캐스트 콘크리트 교각 구조물의 연결시공방법.The steel pipe pile and the precast concrete pier structure (32) is connected to the steel pipe pile and precast concrete pier structure, characterized in that integrally connected by the assembly (10) of claim 1. 제4항에 있어서,The method of claim 4, wherein 상기 연결부재(42)를 상기 상부 지지부재(12)의 상면에 고정 설치하는 단계에 후속하여, 상기 연결부재(42)와 상부 지지부재(12)의 연결 부위에 매몰 시공을 위한 거푸집(50)을 설치하고 고정구조물(48)을 타설하는 단계를 더 포함하는 것을 특징으로 하는 강관 말뚝과 프리캐스트 콘크리트 교각 구조물의 연결시공방법. Following the step of fixedly installing the connecting member 42 on the upper surface of the upper support member 12, the formwork 50 for embedding in the connection portion of the connecting member 42 and the upper support member 12 Installing and connecting the steel pipe piles and precast concrete pier structure characterized in that it further comprises the step of pouring the fixed structure (48).
KR1020090107526A 2009-11-09 2009-11-09 Connection for Steel Pile Head, Connection Structure and Method of Pile and Precast Concrete Pier Structure KR100946879B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090107526A KR100946879B1 (en) 2009-11-09 2009-11-09 Connection for Steel Pile Head, Connection Structure and Method of Pile and Precast Concrete Pier Structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090107526A KR100946879B1 (en) 2009-11-09 2009-11-09 Connection for Steel Pile Head, Connection Structure and Method of Pile and Precast Concrete Pier Structure

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR1020070107356A Division KR100950666B1 (en) 2007-10-24 2007-10-24 Connection for Pile Head, Connection Structure and Method of Pile and Precast Concrete Pier Structure

Publications (2)

Publication Number Publication Date
KR20090125233A KR20090125233A (en) 2009-12-04
KR100946879B1 true KR100946879B1 (en) 2010-03-09

Family

ID=41686802

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090107526A KR100946879B1 (en) 2009-11-09 2009-11-09 Connection for Steel Pile Head, Connection Structure and Method of Pile and Precast Concrete Pier Structure

Country Status (1)

Country Link
KR (1) KR100946879B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107152026A (en) * 2017-06-15 2017-09-12 中铁大桥局集团有限公司 The mud jacking pipe support and its distribution method of a kind of steel-pipe pile

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105002819A (en) * 2015-07-24 2015-10-28 华东交通大学 Gradient-structure composite bridge pier
CN108118611B (en) * 2018-01-23 2023-10-17 安徽省交通控股集团有限公司 Prefabricated mound, board cylindric shear force prop connection structure
CN108951402A (en) * 2018-06-29 2018-12-07 南京理工大学 Improve the device of Precast Concrete Segmental Bridges bridge pier energy dissipation capacity
KR101980079B1 (en) * 2018-12-06 2019-08-28 주식회사 강탄산업 Method for construction of soundproof wall foundation with tensile anchor
CN111155421A (en) * 2020-01-09 2020-05-15 三峡大学 Pier rolling stone impact prevention device and method for monitoring rolling stone impact
CN112112180A (en) * 2020-08-26 2020-12-22 绍兴文理学院 Connecting system of assembled combined pier and bearing platform and construction method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100507291B1 (en) 2001-05-24 2005-08-09 이윤주 Reinforced Method of Head in a Steel Pipe Pile
KR20060109404A (en) * 2006-09-30 2006-10-20 이호경 The apparatus for head reinforcement of phc pile
KR200432120Y1 (en) 2006-09-14 2006-11-29 김병조 A pile reinforcement cap

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100507291B1 (en) 2001-05-24 2005-08-09 이윤주 Reinforced Method of Head in a Steel Pipe Pile
KR200432120Y1 (en) 2006-09-14 2006-11-29 김병조 A pile reinforcement cap
KR20060109404A (en) * 2006-09-30 2006-10-20 이호경 The apparatus for head reinforcement of phc pile

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107152026A (en) * 2017-06-15 2017-09-12 中铁大桥局集团有限公司 The mud jacking pipe support and its distribution method of a kind of steel-pipe pile
CN107152026B (en) * 2017-06-15 2019-02-22 中铁大桥局集团有限公司 A kind of the mud jacking pipe support and its distribution method of steel-pipe pile

Also Published As

Publication number Publication date
KR20090125233A (en) 2009-12-04

Similar Documents

Publication Publication Date Title
KR100950666B1 (en) Connection for Pile Head, Connection Structure and Method of Pile and Precast Concrete Pier Structure
KR100946879B1 (en) Connection for Steel Pile Head, Connection Structure and Method of Pile and Precast Concrete Pier Structure
KR100643575B1 (en) Precast column structure and constructing method thereof
KR101897415B1 (en) Apparatus for forming a cip retaining wall construction method using thereof
JP4750562B2 (en) Connection structure between pile head and precast girder
KR100975124B1 (en) Connection method for lateral beam and column member of rahmen typed underground tunnel
KR101964678B1 (en) Combination structure of pile and copping and girder and method of construction
KR20110103000A (en) Precast bridge joint structure with composite hollow concrete filled tube and a construction method for the same
KR20100005830A (en) Development of a set bridge post connector using unit filled concrete with internally confined hollow and a method for construction
US20080019779A1 (en) Steel-Cased Concrete Piers
KR102227674B1 (en) Reinforcement unit for support point of steel girder and construction method thereof
JP4310444B1 (en) Width expansion material for road bridges
KR200381589Y1 (en) A pile head reinforcement structure of precastconcrete pile
KR101263370B1 (en) Precast end-block with girder connection member and bridge construction method using ths same
KR200383490Y1 (en) System for constructing composite reinforced concrete girders and beams using FRP
KR101167511B1 (en) Underpass using precast concrete pile and method for constructing the same
KR100650411B1 (en) Tunnel cover plate
KR100756517B1 (en) Hollow type composite pier
KR100619525B1 (en) Hollow type pier structure using corrugated steel pipe and construction method thereof
KR100679301B1 (en) A pile head reinforcement structure of precastconcrete pile
KR20110122485A (en) Cip use of underground motorways construction work method
JP5480744B2 (en) Foundation for structure and its construction method
JP5043879B2 (en) How to install width expansion materials for road bridges
KR20120122024A (en) Uniting Method of Temporary earth wall with basement exterior Wall using Couplers and Bolts.
JPH08312061A (en) Steel column member and leg part fixing structure thereof

Legal Events

Date Code Title Description
A107 Divisional application of patent
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130107

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20140102

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20150223

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20160517

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20170329

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20180320

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20190327

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20200226

Year of fee payment: 11